Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel...

27
Robin Bedilion Electric Power Research Institute Energy and Climate Change Research Seminar May 22, 2013 Cost and Performance of Generation Technologies

Transcript of Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel...

Page 1: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

Robin Bedilion

Electric Power Research Institute

Energy and Climate Change Research Seminar

May 22, 2013

Cost and Performance of Generation

Technologies

Page 2: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

2 © 2013 Electric Power Research Institute, Inc. All rights reserved.

Integrated Generation Technology Options

Report Overview

• Annual report published under EPRI’s Strategic Energy

Analysis work

• EPRI’s public cost and performance numbers

– Based on more detailed engineering and economic

evaluations conducted at EPRI

– Feeds into other EPRI analyses

• Overview of each technology

• Overview of trends in the electricity industry

EPRI report 1026656 available for download at www.epri.com

Page 3: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

3 © 2013 Electric Power Research Institute, Inc. All rights reserved.

Levelized Cost of Electricity Analysis –

Objectives

• Utilize EPRI capital cost data and methodologies to

calculate levelized costs of electricity (LCOEs) in constant

2011 $

– Incorporate key assumptions needed for calculations – capital cost,

fuel cost, fixed and variable O&M, fuel type and energy content,

capacity factor, cost of money

• Provide a generic basis for comparison of technologies for

baseload and renewable generation

• Evaluate sensitivities of LCOE to potential CO2 costs and

other parameters

Page 4: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

4 © 2013 Electric Power Research Institute, Inc. All rights reserved.

Levelized Cost of Electricity Analysis – Capital

Cost Estimate Basis

• Capital costs are reported as Total Capital Required

– Includes Total Plant Cost, Owner’s Costs, and Interest

During Construction

• Mercury*, SOx/H2S, NOx, and particulate matter removal

are included in PC and IGCC technologies; NOx removal is

included in NGCC technology

• All thermal plant cost and performance estimates assume

closed-cycle wet cooling tower

* New source Mercury and Air Toxics Standards (MATS) currently under review are not explicitly

addressed.

Page 5: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

5 © 2013 Electric Power Research Institute, Inc. All rights reserved.

Levelized Cost of Electricity Analysis – Capital

Cost Estimate Basis (cont.)

• Generic cost estimates excluding site-specific assumptions

• Cost estimate assumes mature technology

– Plant is assumed to operate as designed (no allowance

for field modifications)

– Extra costs for 1st-of-a-kind demonstration not included

• Cost ranges represent a range of potential plant

configurations and equipment types included in EPRI

studies and are not intended to indicate an uncertainty

range

Page 6: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

6 © 2013 Electric Power Research Institute, Inc. All rights reserved.

Levelized Cost of Electricity Analysis –

Assumptions

• All baseload technologies are assumed to have an 80% capacity factor, except for nuclear which has a 90% capacity factor.

• Non-dispatchable renewables assume a range of capacity factors based on a range of resource availability assumptions.

• No production or investment tax credits assumed for any technologies.

• No integration costs (e.g. costs associated with additional reserves, balancing, conventional generation cycling, etc.) included for non-dispatchable technologies.

Page 7: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

7 © 2013 Electric Power Research Institute, Inc. All rights reserved.

Near-Term: 2015

Page 8: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

8 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

Pulverized Coal (PC) – 2015

0.84 metric tons CO2/MWh

x $100/tonne = +$84/MWh

All-in Capital Costs: $2,400-2,875/kW

Fuel Costs: $2-3/MMBtu

All costs are in

constant Dec 2011$

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 9: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

9 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

Integrated Gasification Combined

Cycle (IGCC) – 2015

All-in Capital Costs: $3,375-3,750/kW

Fuel Costs: $2-3/MMBtu

0.85 metric tons CO2/MWh

x $100/tonne = +$85/MWh

All costs are in

constant Dec 2011$

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 10: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

10 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

Natural Gas Combined Cycle (NGCC) Fuel

Cost Sensitivity Comparison – 2015

All-in Capital Costs: $1,025-1,325/kW

Fuel Costs: $2-6/MMBtu

0.37 metric tons CO2/MWh

x $100/tonne = +$37/MWh

All costs are in

constant Dec 2011$

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 11: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

11 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

PC, IGCC, NGCC

Comparison – 2015

IGCC

PC

NGCC

All costs are in

constant Dec 2011$

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 12: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

12 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

Nuclear – 2015

All-in Capital Costs: $5,375-6,025/kW

Fuel Costs: $0.4-0.8/MMBtu

All costs are in

constant Dec 2011$

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 13: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

13 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

Biomass – 2015

*Biomass emissions can vary significantly based on fuel source and life-cycle emission assumptions.

Conventionally, the release of carbon from biogenic sources is assumed to be balanced by the uptake

of carbon when the feedstock is grown, resulting in zero net CO2 emissions over some period of time.

No investment or production tax credits are assumed.

CO2 emissions are assumed to be neutral*.

All-in Capital Costs: $4,150-5,250/kW

Fuel Costs: $2-6/MMBtu

All costs are in

constant Dec 2011$

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 14: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

14 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

Geothermal – 2015

All-in Capital Costs: $5,350-9,275/kW

No investment or production tax credits are assumed.

All costs are in

constant Dec 2011$

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 15: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

15 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

Wind – 2015

No investment or production tax credits are assumed.

All costs are in

constant Dec 2011$

Onshore Wind

All-in Capital Costs: $1,825-2,500/kW

Capacity Factor: 28-40%

Offshore Wind

All-in Capital Costs : $3,250-5,225/kW

Capacity Factor: 40-45%

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 16: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

16 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

Concentrating Solar Thermal

Power (CSP) – 2015

No investment or production tax credits are assumed.

All-in Capital Costs: $4,050-7,550/kW

Capacity Factor: 25-49%

All costs are in

constant Dec 2011$

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 17: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

17 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

Solar Photovoltaic (PV) – 2015

No investment or production tax credits are assumed.

All-in Capital Costs: $2,200-2,525/kW

Capacity Factor: 14-26%

All costs are in

constant Dec 2011$

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 18: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

18 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

PC

IGCC

NGCC

Nuclear

Biomass

Geothermal

Comparative Levelized Costs of Electricity of

Dispatchable Technologies – 2015

All costs are in

constant Dec 2011$

Average LCOE values based on estimated capital cost ranges.

No investment or production tax credits are assumed for any technology.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 19: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

19 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

Onshore Wind

Offshore Wind

CSP

Solar PV

Comparative Levelized Costs of Electricity of

Non-Dispatchable Technologies* – 2015

All costs are in

constant Dec 2011$

Average LCOE values based on estimated capital cost ranges.

No investment or production tax credits are assumed for any technology.

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

*For wind, solar PV, and CSP without storage, production is set by resource availability, not load demand.

LCOE values presented here do not include integration costs (e.g. costs associated with additional reserves,

balancing, conventional generation cycling, etc.). Care should be used when comparing LCOEs of these

technologies to dispatchable technologies.

Page 20: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

20 © 2013 Electric Power Research Institute, Inc. All rights reserved.

Longer-Term: 2025

Page 21: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

21 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

Coal, 2025 – Impact of CO2 Capture & Storage and

Technology Improvements on Levelized Cost of Electricity

No Technology

Improvement

Technology

Improvement

CCS = CO2 Capture & Storage. Capture costs included in capital costs;

transportation and sequestration assumed to be $10/metric ton.

IGCC + CCS

PC + CCS

All-in Capital Costs

PC + CCS: $3,950-5,050/kW

IGCC + CCS: $4,050-4,950/kW

Fuel Cost: $2-3/MMBtu

All costs are in

constant Dec 2011$

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 22: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

22 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

NGCC, 2025 – Impact of CO2 Capture & Storage on

Levelized Cost of Electricity

All-in Capital Costs

NGCC: $1,025-1,325/kW

NGCC + CCS: $2,050-2,525/kW

Fuel Cost: $4-8/MMBtu

NGCC+CCS

NGCC

All costs are in

constant Dec 2011$

CCS = CO2 Capture & Storage. Capture costs included in capital costs;

transportation and sequestration assumed to be $10/metric ton.

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 23: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

23 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

Solar Photovoltaic (PV) – 2025

No investment or production tax credits are assumed.

All-in Capital Costs: $1,650-1,850/kW

Capacity Factor: 15-27%

All costs are in

constant Dec 2011$

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 24: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

24 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

Comparative Levelized Costs of Electricity of

Dispatchable Technologies – 2025

All costs are in

constant Dec 2011$

Average LCOE values based on estimated capital cost ranges.

No investment or production tax credits are assumed for any technology.

PC + CCS

IGCC + CCS

NGCC + CCS

Nuclear

Biomass

Geothermal

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 25: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

25 © 2013 Electric Power Research Institute, Inc. All rights reserved.

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100

Le

ve

lize

d C

os

t o

f E

lec

tric

ity,

$/M

Wh

Cost of CO2, $/metric ton

Comparative Levelized Costs of Electricity of

Non-Dispatchable Technologies* – 2025

All costs are in

constant Dec 2011$

Average LCOE values based on estimated capital cost ranges.

No investment or production tax credits are assumed for any technology.

*For wind, solar PV, and CSP without storage, production is set by resource availability, not load demand.

LCOE values presented here do not include integration costs (e.g. costs associated with additional reserves,

balancing, conventional generation cycling, etc.). Care should be used when comparing LCOEs of these

technologies to dispatchable technologies.

Onshore Wind

Offshore Wind

CSP

Solar PV

LCOE is shown for high level comparison purposes. Actual plant investment decisions are affected by a number of other project specific considerations and caution should be used when comparing

technologies based on LCOE. See Appendix A of report 1026656 for more details.

Page 26: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

26 © 2013 Electric Power Research Institute, Inc. All rights reserved.

Closing Thoughts

• Several key uncertainties impact near-term and long-term

project decisions and research priorities:

– Stringency of future CO2 emissions reduction programs

– Future price of natural gas (high sensitivity and

variability)

– CO2 capture and storage technology development and

costs

– Renewable energy technology development

– Technology-driven escalations and reductions in plant

costs

• Demonstrates importance of developing and demonstrating

a portfolio of low cost generation technologies.

Page 27: Cost and Performance of Generation Technologies · All-in Capital Costs: $2,400-2,875/kW Fuel Costs: $2-3/MMBtu All costs are in constant Dec 2011$ LCOE is shown for high level comparison

27 © 2013 Electric Power Research Institute, Inc. All rights reserved.

Together…Shaping the Future of Electricity