Cost Accounting (12)
-
Upload
nitin-rajotia -
Category
Documents
-
view
214 -
download
0
Transcript of Cost Accounting (12)
-
8/10/2019 Cost Accounting (12)
1/30
Chapter 5Activity-Based Costing
and
Activity-Based Management
-
8/10/2019 Cost Accounting (12)
2/30
Activity Based Costing System (ABC)
ABC systems follow a two-stage procedure to assign ovcosts to products.
Stage One: Identify significant activities and assign overhead costs to each ac
proportion to resources used.
Stage Two: Identify cost drivers appropriate to each activity and allocate ove
products.
Assigning Overhead to product costs is a difficult process.
Lets begin by identifying our major activities.
The first stage identifies significant activities in the production process and assigns overhead costs to
accordance with the cost of the organizations resources used by the activity. The overhead costs assi
comprise an activity cost pool.
Overhead assigned to activities are called activities cost pools.
After assigning overhead costs to activity cost pools in stage one, cost drivers appropriate for each co
stage two.Then the overhead costs are allocated from each activity cost pool to each product line in
amount of the cost driver consumed by the product line.
-
8/10/2019 Cost Accounting (12)
3/30
ABC uses a four-level cost structure to determine how far down t
cycle costs should be pushed:
Unit-level (output-level)
Batch-level
Product-sustaining-level
Facility-sustaining-level
Cost Hierarchies
-
8/10/2019 Cost Accounting (12)
4/30
Aerotech identified eight activity cost pools, which fall in
categories: unit level, batch level, product-sustaining lev
level.
The activity at the unit level must be applied to each uni
The activity at the batch level must be performed one tim
batch that goes into production.
The product-sustainingactivities are required to support
product line, but not needed for each unit or batch.
Facility-level activities are required in order for the entir
process to occur.
-
8/10/2019 Cost Accounting (12)
5/30
Overhead CostsTotal budgeted cost = $3,894,000
Activity
Cost
Pools
Machinery
cost pool$1,212,600
Setup
cost pool$3,000
Engineering
cost pool$700,000
Unit
Level
Batch
Level
Product-
Sustaining
Level
F
Activity
must be
done on
each unit
produced.
Activity
performed
on each
batch
produced.
Activities needed to support
an entire product lineActivity required
for the produc
process to oc
-
8/10/2019 Cost Accounting (12)
6/30
Machinery Cost PooTotal budgeted cost = $1,212
Maintenance
Depreciation
Computer Support
Lub
Ele
Cal
Activity
cost
pool
STAGE ONE
Various overhead
costs related
to machinery
Aerotech estimated the costs of maintenance, lubrication, depreciation, electricity, computer support
costs are added together. The sum is the machinery cost pool budgeted cost.
-
8/10/2019 Cost Accounting (12)
7/30
Calculate
the pool
rate
Budgeted Machinery Costs $1,212,600
Budgeted Machine Hours 43,000
$28.20/hour
Cost
Assignment
STAGE TWO
=
=
Mode I:
$28.20 per hr.
1 hr. per unit
$28.20 per unit
Mode II:
$28.20
1.25
$35.25
Mode III:
$28.20 per hr.
2 hr. per unit
$56.40 per unit
Aerotech selected machine hours for
the cost driver, since a product that
uses more machine hours should
bear a larger share of machine-
related costs.
The budgeted machinery costs are
divided by the budgeted number ofmachine hours to arrive at the
machinery cost pool rate.
Then, for each circuit board, the machinery cost pool rate is multiplied by the number of machin
Di t t d P d t C t
-
8/10/2019 Cost Accounting (12)
8/30
Can you identify a
is likely to face as a r
Mode I Mode II M
Tradition al cos tin g 209.00$ 302.00$ $
ABC cos tin g 183.44 261.81
Cos t dis tortion pe r u n it 25.56 40.19
Un its produ ce d 10,000 20,000 Total cos t dis tortion 255,600 803,800 (1
Traditional costing understates the cost of complex, low volume products
Distorted Product Costs
The cost per unit under ABC costing is deducted from the traditional costing unit cost.
This is cost distortion per unit.
The problem with cost distortion is more evident when the cost distortion per unit is multiplied by the n
produced.
The essence of the problem is that the traditional, volume-based costing system was over costing the hig
(Modes I and II) and under costing the complex, relatively low volume product line (Mode III).
The high-volume products basically subsidized the low volume line.
The activity-based costing system revealed this problem by more accurately assigning overhead costs to t
When the costs are understated, so is the selling price. See problem 1&2
-
8/10/2019 Cost Accounting (12)
9/30
ABC vs Simple Costing
ABC is generally perceived to produce superior cost
figures due to the use of multiple drivers across multi
levels
ABC is only as good as the drivers selected, and their act
relationship to costs. Poorly chosen drivers will produinaccurate costs, even with ABC
-
8/10/2019 Cost Accounting (12)
10/30
Conclusions
Each method is mathematically correct
Each method is acceptable
Each method yields a different cost figure, which will lea
to different Gross Margin calculations
Only Overhead is involved. Total Costs for the entire fir
remain the same they are just allocated to different coobjects within the firm
Selection of the appropriate method and drivers should b
based on experience, industry practices, as well as a cos
benefit analysis of each option under consideration
-
8/10/2019 Cost Accounting (12)
11/30
A Cautionary Tale
A number of critical decisions can be made using this
information;
Should one product be pushedover another?
Should one product be dropped?
Accounting for overhead costs is an imprecise science.Accordingly, best efforts should be put forward to arrive
at a cost that is fair and reasonable.
-
8/10/2019 Cost Accounting (12)
12/30
Rationale for Selecting a MoreRefined Costing System
Increase in product diversity
Increase in Indirect Costs
Advances in information technology
Competition in foreign markets
T ree gu e nes are presente or re n ng a cost ng system
-
8/10/2019 Cost Accounting (12)
13/30
Step 1: Identify the products that are the chosen cost objects.
Step 2: Identify the direct costs of the products.
Step 3: Select the activities and cost-allocation basesto use for
allocating indirect costs to the products.
Step 4: Identify the indirect costsassociated with each cost-allocation
base (activity).
Step 5: Compute the rate per unitof each cost-allocation base
(activity) used to allocate indirect costs to the products.
Step 6: Compute the indirect costs allocatedto the products.
Step 7: Compute the total costs of the productsby adding all direct andindirect costs assigned to the products.
T ree gu e nes are presente or re n ng a cost ng system.
Direct-cost tracing.Identify as many direct costs as is
economically feasible.
Indirect-cost pools.Expand the number of cost pools so that eapool is somewhat homogeneous. Each cost in the pool has a simil
cause-and-effect relationship with a single cost driver. Cost-allocation bases.The cost driver serves as the cost allocatbase for each homogeneous indirect-cost pool.
C D i A characteristic of an event o
-
8/10/2019 Cost Accounting (12)
14/30
Cost Drivers A characteristic of an event oin the incurrence of costs. In s
Degree of
Correlation
Cost of
Measurement
Behavioral
Effects
A cost driveris a characteristic of an
event or activity that results in the
incurrence of costs.
In activity-based costing systems, the
most significant cost drivers areidentified.
Then a database is created, which
shows how these cost drivers are
distributed across products.
Three factors are important in
selecting appropriate cost drivers.
The more activity cost pools
activity-based costing syste
the accuracy of the cost ass
more activity cost pools als
drivers, which results in gr
implementing and maintain
The first is the degree of
correlation. The concept of an
activity-based costing system is
to infer how each product line
consumes the activity by
observing how each product
line consumes the cost drive,
that is, how closely the two are
correlated.
The closer the correlation, the
more accurate the cost
assignments will be.
Designing any information
system entails cost-benefit
trade-offs.
Information systems have t
facilitate decisions but alsobehavior of decision make
This can be good or bad, de
behavioral effects.
In identifying cost drivers, a
consider the possible behav
Dysfunctional behavioral ef
COLLECTING ABC DATA
-
8/10/2019 Cost Accounting (12)
15/30
COLLECTING ABC DATAINTERVIEWS AND PAPER TRAILS - The information for ABC systems initiacomes from interviews with employees in the support departments and a revie
each departments records.
STORYBOARDING -A procedure used to develop a detailed process flow chwhich visually represents activities and the relationships among activities.
MULTIDISCIPLINARY ABC PROJECT TEAMSTo gather information fromfacets of an organizations operations, it is essential to involve personnel from a
of functional areas. A typical ABC project team includes ACCOUNTING, FINANC
PRODUCTION, OPERATIONS, ENGINEERS, MARKETINGetc.
A storyboarding session identifies the key activities involved in each department.
These activities are written on small cards and placed on a large board in the order they
accomplished.
After several storyboarding sessions, a completed storyboard emerges, recording key ac
information vital to the ABC project.
-
8/10/2019 Cost Accounting (12)
16/30
Activity-Based Management
The use of
ABC costing information
to help
management
make decisions
Using activity-based
costing (ABC)
information tosupport
organizational
strategy, improve
operations, and
manage costsis called
activity-basedmanagement or ABM.
-
8/10/2019 Cost Accounting (12)
17/30
Activity-Based Management
Activity-based costingestablishes relationshipbetween overhead costs and activities so that
we can better allocate overhead costs.
Activity-based managementfocuseson managing activities to reduce costs.
-
8/10/2019 Cost Accounting (12)
18/30
A method of management that used ABC as an integra
part in critical decision-making situations, including:
Pricing & product-mix decisions
Cost reduction & process improvement decisions
Design decisions
Planning & managing activities
Activity-Based Management
l d
-
8/10/2019 Cost Accounting (12)
19/30
Two-Dimensional ABC and Activity-
Based Management
Cost Objects
Activities
Resource costs
Cost Assignment View
The vertical element of
the model is the cost
assignment view of an
ABC system.
Cost assignment in an
ABC system uses a two-
stage cost allocation to
assignthe costs of
resources to the firms
cost objects.
Cost Object:A
product, serv
customer, act
or organizatio
unit to wh
costs are
assigned for
some
managementpurpose.
Two-Dimensional ABC and Activity-Based Management
-
8/10/2019 Cost Accounting (12)
20/30
Two Dimensional ABC and Activity Based Management
Activity
Triggers
Cost Objects
Activities
Root
Causes
Process ViewActivity Analysis
Resource costs
Cost Assignment View
Performa
Measur
Activity Evalua
The horizontal element of the model is the process view of an ABC system. The emph
now is on the activities themselves, the various processes by which work is accomplis
the organization. The left-hand side is the activity analysis. This is the identification a
description of the activities conducted in the enterprise.
Activity analysis also
identifies the root causesof
activities, the events that
trigger activities, and the
linkages among activities.
The right-hand sid
the evaluation of
activities throughperformance
measures.
It is these proce
of activity analy
and evaluation
comprise activi
based managem
-
8/10/2019 Cost Accounting (12)
21/30
Elimination of Non-Value-Added Cost
Nonvalue-added
activities
NecessaryUnnecessary
Activities
Reduce or
Eliminate
Continually Eval
and Improve
An important goal of activity-
based management is to
identify and eliminate non
value-added activities andcosts.
Non-value-added activ
operations that are eith
unnecessary and dispen
(2) necessary, but ineffi
and improvable.
Non-value-added costs, which
result from such activities, are
the costs of activities that can
be eliminated without
deterioration of product quality,
performance, or perceived
value.
U i ABM t Eli i t N V l
-
8/10/2019 Cost Accounting (12)
22/30
Using ABM to Eliminate Non-Value-
Added Activities and Costs
1. Identify Activities.
2. Identify Non-Value-Added Activities.
3. Understand Activity Linkages, Root Causes, andTriggers.
4. Establish Performance Measures.
5. Report Non-Value-Added Costs.
Specify
parts
Select
vendor
Receive
parts
Produce
goods
Inspect
finishedgoods
Re
depr
There are a few steps that provide a strategy for eliminanon value added costs in both manufacturing and servic
-
8/10/2019 Cost Accounting (12)
23/30
There are a few steps that provide a strategy for eliminanon value-added costs in both manufacturing and servicindustry firms.
Step one identifies all of the organizations significantactivities.
The resulting activity list should be broken down to the mfundamental level practical.
In step two, the non value-added activities are identified
Three criteria for determining whether an activity adds vare as follows:
Is the activity necessary? Is the activity efficiently performed? Is an activity sometimes value-added and sometimes non
value-added?
In identifying non value-added activities, it is critical to
understand the ways in which activities are linked togeth
The following chain of activities provides an example:
-
8/10/2019 Cost Accounting (12)
24/30
The rework of defective units is a non-value-added activity.
The rework is triggered by the identification of defective products duringinspection.
The root cause of the rework, however, could lie in any one of a number ofpreceding activities.
Perhaps the part specifications were in error. Or an unreliable vendor was se
Maybe the wrong parts were received. Or the production activity is to blam
A set of linked activities (such as that depicted above) is called a process.
Sometimes activity analysis is referred to as process value analysis (PVA).
By continually measuring the performance of all activities, and comparingperformance with benchmarks, managements attention may be directed tounnecessary or inefficient activities.
Non-value-added costs should be highlighted in activity center cost reports.
By identifying non-value-added activities, and reporting their costs, managecan strive toward the ongoing goals of process improvement and eliminationon-value-added costs.
Using ABM to Eliminate Non Value
-
8/10/2019 Cost Accounting (12)
25/30
Using ABM to Eliminate Non-Value-
Added Activities and Costs
Inspection time
Process time
Storage time
Move time Waiting time
One approach that cost-
management analysts find
helpful in identifying non-
value-added activities is tocategorize the ways in which
time is spent in a production
process.
In most manufacturing
operations, time is spent i
the five ways
See
pro
-
8/10/2019 Cost Accounting (12)
26/30
Significant overhead costs allocated using one or two co
pools
Most or all overhead is considered unit-level
Products that consume different amounts of resources
Products that a firm should successfully make and s
consistently show small profits Operations staff disagreeing with accounting ov
manufacturing and marketing costs
Signals that Suggest that ABCImplementation Could Help a Firm
-
8/10/2019 Cost Accounting (12)
27/30
Customer Profitability Analysis
Customer profitability analysis usesactivity-based costing to determine
the activities, costs, and profit associatedwith serving particular customers.
If managers hav
good understan
of which custom
are generating tgreatest profit, t
can make more-
informed decisio
about customer
service.
-
8/10/2019 Cost Accounting (12)
28/30
Customer Profitability Analysis
Orders
small
quantities.
Ord
freque
Often
changes
orders.
Required
special
packaging.
Deman
fast
servic
costly customer
Many factors can result in
some customers being more
profitable than others.
Customers that order in small
quantities, order frequently,
often change their orders,
require special packaging or
handling, demand faster
delivery, or need special parts
or engineering design generally
are less profitable than
customers who demand less in
terms of customized services.
Customer Profitability Analysis
-
8/10/2019 Cost Accounting (12)
29/30
Customer Profitability Analysis
Customer-Related Activities Cost Driver Base
Cost Dr
Rate
Order processing Purchase orders 1$
Sales contacts (phone calls, faxes, etc.) Contacts 1
Sales visits Visits 1,0
Shipment processing Shipments 2
Billing and collection Invoices 1Design/engineering change orders Design changes 4,0
Special packaging Units packaged
Special handling Units handled
A company may use these customer
related costs to help determine the
profitability of each customer.
Recall that ABC analysis relies on a cost hierarchy with cost levels, such as unit-
level, batch-level, product-line-level, customer-level, and facility- or general-
operations-level costs.
In this use of activity-based costing, the cost management team will focus on the
customer-related costs.
A company may then use these costs to determine the profitability of each
customer.
The first step is an activity based
costing analysis of certain
customer-related coststhat couldaffect a customers profitability.
-
8/10/2019 Cost Accounting (12)
30/30
Customer Profitability Analy
Customer Profitability
0.0%
25.0%
50.0%
75.0%
100.0%
125.0%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 1CumulativeOperat
ingIncomeasa%ofTotal
OperatingIncome
75% of actual operating income
50% of actual operating income
25% of actual operating income
A graphical
portrayal of the
complete
customer-
profitability
analysis is
called acustomer-
profitability
profile.
It is a common
and useful way
of presenting a
customer-profitability
analysis to
management.
See
problem