Corrigendum to the Tariff Order dated 04.03.2015 of the ... · 1.2 The Durgapur Projects Limited...
Transcript of Corrigendum to the Tariff Order dated 04.03.2015 of the ... · 1.2 The Durgapur Projects Limited...
West Bengal Electricity Regulatory Commission Corrigendum to the Tariff Order dated 04.03.2015 of the Commission including
the corrigendum dated 19.03.2015 in regard to the Tariff Application of the Durgapur Projects Limited (DPL) for the years
2014-2015 to 2016-2017 in Case No TP-55/13-14
Attention of the Commission has been drawn to a typographical error / apparent mistake
in the tariff order dated 04.03.2015 passed by the Commission including the
corrigendum dated 19.03.2015 in regard to the Tariff Application of the DPL for the years
2014-2015 to 2016-2017 in Case No: TP-55/13-14 .
The Commission is of the considered opinion that in the interest of all concerned such
typographical error / apparent mistake which do not have any effect on tariff
determination already made inadvertently in the said tariff order including the aforesaid
corrigendum, be corrected and necessary corrigendum be issued. The Commission
accordingly carries out such correction keeping in view the provisions of Section 94 of
the Electricity Act, 2003 and directs the Secretary to issue the following corrigendum :-
Correction of the typographical error / apparent mistake in the Tariff Order dated 04.03.2015 including corrigendum dated 19.03.2015 in respect of DPL.
************************************************************************************************
Page No Nomenclature Present Description Corrected Description
Power Factor (PF) Range in %
Power Factor (PF) Range
PF > 0.99% PF > 0.99 PF > 0.98% & PF < 0.99% PF > 0.98 & PF < 0.99 PF > 0.97% & PF < 0.98% PF > 0.97 & PF < 0.98 PF > 0.96% & PF < 0.97% PF > 0.96 & PF < 0.97 PF > 0.95% & PF < 0. 96% PF > 0.95 & PF < 0. 96 PF > 0.94% & PF < 0.95% PF > 0.94 & PF < 0.95 PF > 0.93% & PF < 0.94% PF > 0.93 & PF < 0.94 PF > 0.92% & PF < 0.93% PF > 0.92 & PF < 0.93 PF > 0.86% & PF < 0.92% PF > 0.86 & PF < 0.92 PF > 0.85% & PF < 0. 86% PF > 0.85 & PF < 0. 86 PF > 0.84% & PF < 0. 85% PF > 0.84 & PF < 0. 85 PF > 0.83% & PF < 0.84% PF > 0.83 & PF < 0.84 PF > 0.82% & PF < 0. 83% PF > 0.82 & PF < 0. 83 PF > 0.81% & PF < 0.82% PF > 0.81 & PF < 0.82 PF > 0.80% & PF < 0. 81% PF > 0.80 & PF < 0. 81
106
Some of the signs in first column with the column heading “Power Factor (PF) Range in %” of the Table “Power Factor Rebate & Surcharge on Energy Charge in Percentage” in the corrigendum.
PF < 0.80% PF < 0.80
Page No Nomenclature Present Description Corrected Description
126 From 6th line to 9th line in clause (i) under paragraph 8.5 of the tariff order.
Such calculation sheet shall also specifically mention the received fuel bill which has not been considered or partly considered in the said MVCA in pursuance to note (g) under sub- paragraph (e) of paragraph A of Schedule – 7B of the Tariff Regulations.
Such calculation sheet shall also specifically mention the received fuel bill and/or power purchase bill which has not been considered or partly considered in the said MVCA in pursuance to note (g) under sub- paragraph (e) of paragraph A of Schedule – 7B of the Tariff Regulations.
Sd/- (SUJIT DASGUPTA) MEMBER Dated: 25.05.2015
West Bengal Electricity Regulatory Commission Corrigendum to the Order dated 04.03.2015 of the Commission
in regard to the Tariff Application of the Durgapur Projects Limited (DPL), for the year 2014-2015 in Case No TP-55/13-14
Attention of the Commission has been drawn to a typographical error / apparent mistake
in the tariff order dated 04.03.2015 passed by the Commission in regard to the Tariff
Application of the DPL, for the year 2014-2015 in Case No: TP-55/13-14 .
The Commission is of the considered opinion that in the interest of all concerned such
typographical error / apparent mistake which do not have any effect on tariff
determination already made inadvertently in the said tariff order, be corrected and
necessary corrigendum be issued. The Commission accordingly carries out such
correction keeping in view the provisions of Section 94 of the Electricity Act, 2003 and
directs the Secretary to issue the following corrigendum :-
Correction of the typographical error / apparent mistake in the Tariff Order dated 04.03.2015 in respect of DPL.
************************************************************************************************
Page No Nomenclature Present Description Corrected Description
106
Some of the signs in first column with the column heading “Power Factor (PF) Range in %” of the Table “Power Factor Rebate & Surcharge on Energy Charge in Percentage” under sub-paragraph 7.3.7.1 are erroneously printed.
Power Factor (PF) Range in %
Power Factor (PF) Range in %
PF > 0.99 PF > 0.99%
PF > 0.98 & PF < 0.99 PF > 0.98% & PF < 0.99% PF > 0.97 & PF < 0.98 PF > 0.97% & PF < 0.98% PF > 0.96% & PF < 0.97% PF > 0.96% & PF < 0.97% PF > 0.95% & PF < 0. 96% PF > 0.95% & PF < 0. 96% PF > 0.94% & PF < 0.95% PF > 0.94% & PF < 0.95% PF > 0.93% & PF < 0.94% PF > 0.93% & PF < 0.94% PF > 0.92% & PF < 0.93% PF > 0.92% & PF < 0.93% PF > 0.86% & PF < 0.92% PF > 0.86% & PF < 0.92% PF > 0.85% & PF < 0. 86% PF > 0.85% & PF < 0. 86% PF > 0.84% & PF < 0. 85% PF > 0.84% & PF < 0. 85% PF > 0.83% & PF < 0.84% PF > 0.83% & PF < 0.84% PF > 0.82% & PF < 0. 83% PF > 0.82% & PF < 0. 83% PF > 0.81% & PF < 0.82% PF > 0.81% & PF < 0.82% PF > 0.80% & PF < 0. 81% PF > 0.80% & PF < 0. 81% PF < 0.80% PF < 0.80%
Sd/- (SUJIT DASGUPTA) MEMBER Dated: 19.03.2015
ORDER
OF THE
WEST BENGAL ELECTRICITY REGULATORY COMMISSION
FOR THE YEAR 2014 – 2015
IN
CASE NO: TP – 55 / 13 – 14
IN RE THE TARIFF APPLICATION OF
THE DURGAPUR PROJECTS LIMITED
FOR THE YEARS 2014-15, 2015-16 AND 2016-17
UNDER SECTION 64(3)(a) READ WITH SECTION
62(1) AND SECTION 62(3) OF THE
ELECTRICITY ACT, 2003
DATE: 04.03.2015
Tariff Order of DPL for the year 2014 – 2015
CHAPTER - 1 INTRODUCTION
West Bengal Electricity Regulatory Commission 2
1.1 The West Bengal Electricity Regulatory Commission (hereinafter referred to as
the “Commission”), a statutory body under the first proviso to section 82(1) of the
Electricity Act, 2003 (hereinafter referred to as the “Act”), has been authorized in
terms of the section 86 and section 62(1) of the Act to determine the tariff for a)
supply of electricity by a generating company to a distribution licensee, b)
transmission of electricity, c) wheeling of electricity and d) retail sale of electricity,
as the case may be, within the State of West Bengal.
1.2 The Durgapur Projects Limited (hereinafter referred to as DPL) was a sanction
holder under section 28 of the Indian Electricity Act, 1910 and has become a
deemed licensee in terms of the first proviso to section 14 of the Act with effect
from 10.06.2003 i.e. the date of coming into force of the Act, for distribution of
electricity in Durgapur area of West Bengal.
1.3 The Commission, in the past, passed tariff orders for DPL for fourteen years from
2000 – 2001 to 2013 – 2014 (both years inclusive) in ten orders, - three joint
orders covering the years (1) 2000 – 2001 and 2001 – 2002, (2) 2002 – 2003,
2003 – 2004 and 2004 – 2005 and (3) 2011-2012 and 2012-2013 and seven
single orders for the years 2005-2006, 2006-2007, 2007-08, 2008 – 2009, 2009
– 2010, 2010 – 2011 and 2013 – 2014. DPL felt aggrieved by the tariff order
dated 24.5.2004 determining its tariffs for the years 2000-2001 and 2001-2002
and filed a writ petition [W. P. No. 12108 (W) of 2004] and subsequent petition
bearing No. AST 1019 / 2004 in the Hon’ble High Court at Calcutta challenging
the order of the Commission dated 24.05.04. The matter lies pending before the
Hon’ble High Court at Calcutta for final disposal. DPL felt aggrieved by the order
of the Commission dated 9.6.2004 also and moved the Hon’ble High Court at
Calcutta in an appeal against the said tariff order [No. AST 1134 of 2004 and WP
No. 14128 (W) of 2004]. The Hon’ble High Court was pleased, by an order dated
15 July 2004, to stay the operation of one part of the tariff order of the
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 3
Commission dated 9.6.2004 involving a question of refund to the consumers of
DPL while the rest of the tariff order was not interfered with. This matter is still
sub-judice before the Hon’ble High Court at Calcutta.
1.4 West Bengal Electricity Regulatory Commission (Terms and Conditions of Tariff)
Regulations, 2011 has come into effect with effect from 29th April, 2011. The said
Tariff Regulations, 2011 was further amended by notifying the West Bengal
Electricity Regulatory Commission (Terms and Conditions of Tariff) (Amendment)
Regulations, 2012 in the extra ordinary edition of The Kolkata Gazette dated 27th
August, 2012 and was further amended by notification in The Kolkata Gazette
dated 30th
1.5 In terms of West Bengal Electricity Regulatory Commission (Terms and
Conditions of Tariff) Regulations, 2011, as amended from time to time
(hereinafter referred to as the ‘Tariff Regulations’), the tariff applications for the
fourth control period consisting of the years 2014 – 2015, 2015 – 2016 and 2016
– 2017 under the Multi Year Tariff (MYT) framework was required to be
submitted by DPL 120 days in advance of the effective date of the said control
period. The effective date of the fourth control period is 1
July, 2013..
st April, 2014. DPL
submitted an application on 25.11.2013 for extension of date for submission of
their MYT application for the forth control period upto 31.12.2013 on the plea that
the Amendment Regulations, 2013 contain many changes for generating station
and they had to study those amendments and to work out impact of such
changes which required some time. The Commission, after considering the
application of DPL and also the applications received from some distribution
licensees and the transmission licensee for extension of time of submission of
MYT application, decided to fix the last date of submission of MYT application for
the fourth control period on 31.12.2013 and accordingly issued an order dated
02.12.2013.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 4
1.6 DPL submitted their application for MYT for fourth control period on 30.12.2013
in an incomplete status. After a series of correspondence, DPL, however,
submitted the requisite forms / documents on 06.03.2014. The petition was
admitted by the Commission and numbered as TP-55/13-14.
1.7 After admission of the application DPL was directed to publish, the gist of the
application, as approved by the Commission, in the newspapers and also in their
website, as specified in the Tariff Regulations. The gist was, accordingly,
published simultaneously on 11.04.2014 in Economic Times, Ekdin, Bartaman
and Sanmarg. The publication invited the attention of all interested parties, stake
holders and the members of the public to the application for determination of tariff
of DPL for the fourth control period and requested for submission of objections,
comments etc., if any, on the tariff application to the Commission by 16.05.2014
at the latest. In order to invite more suggestions / objections from the stake
holders, interested parties and members of public, the Commission extended the
date of submission upto 25.05.2014. Opportunities were also afforded to all to
inspect the tariff application and take copies thereof.
1.8 The suggestions, objections and comments on the aforementioned application of
DPL for determination of tariff for the fourth control period were received only
from the following stake holders within the specified time limit and the same have
been recorded in a summarized form in Chapter 3 of the instant order.
a) M/s Shyam Ferro Alloys Limited.
b) M/s Bamunara Industries Welfare Association
1.9 The petitioner, DPL, while submitting its application for determination of tariff,
also sought for review of the norms specified by the Commission in the Tariff
Regulations. We may put it on record that the aforesaid Tariff Regulations were
finalized through previous publication. Having received suggestions, objections
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 5
and comments the Commission in exercise of its delegated legislative power duly
considered the matter in detail and framed such regulations and the regulations
were notified in the Kolkata Gazette. DPL should not have sought for review
which is practically seeking amendment to the tariff regulations. In tariff
determination proceedings once the regulations are framed by the Commission,
there is no scope to review or challenge such statutory norms in tariff
determination proceedings. Accordingly, the prayer for review seeking
modification to the statutory norms in the Tariff Regulations is not considered.
Thus, such issue will not be dealt in subsequent chapter further.
1.10 The Commission determines the tariff in accordance with the Electricity Act, 2003
and the Tariff Regulations framed thereunder and for this purpose, the
Commission has estimated the expenditure for 2013 – 2014 to arrive at the
estimated expenditure / cost under different heads for the years 2014 – 2015 to
2016 – 2017.
1.11 The estimation made for 2013 – 2014 by the Commission shall not be construed
by DPL as admission of at least such estimated amount in APR for 2013 – 2014.
On the other hand, if in APR any deduction is made then as a conclusion from
such decision one shall not expect that the impact of such deduction is to be
continued in fourth control period as this will tantamount to imposing a penalty of
infinite nature or double penalty for the same inefficiency.
Tariff Order of DPL for the year 2014 – 2015
CHAPTER - 2 THE CASE OF DPL
West Bengal Electricity Regulatory Commission 6
2.1 DPL has submitted the application containing its proposal for determination of
Annual Revenue Requirement (ARR) and tariff for the fourth control period,
covering the years 2014 – 2015 to 2016 – 2017, in accordance with the Tariff
Regulations. The tariff applicant has proposed the ARR and tariff for each year of
the fourth control period and has prayed for allowing the same. The licensee has
also prayed for other dispensations which are mentioned in subsequent
paragraphs.
2.2 DPL has stated that while proposing tariff for various categories of consumers,
they have followed the principles laid down in the Tariff Regulations, attempted to
reduce cross-subsidies and rationalize the tariff for various classes of consumers
and have also proposed gradual reduction of T&D losses.
2.3 According to DPL, the total cost of its power plant operations has increased
substantially during the current year and the same is expected to increase further
in the three years of the fourth control period. In submitting figures showing
revenue requirement and recoverable revenue from sale of power at existing
tariff, DPL has shown that there will be gap of Rs. 53144.70 lakh during 2014 –
2015, Rs. 64076.26 lakh during 2015 – 2016 and Rs. 75800.75 lakh during 2016
– 2017. DPL has, therefore, submitted that these gaps are needed to be covered
by increase in tariff and if the existing tariff is not increased for the fourth control
period, DPL’s financial position will be worsen impacting on its ability to serve its
consumers.
2.4 To justify the need for tariff increase, DPL has furnished figures under different
heads of actual expenditure of previous years from 2009 – 2010 to 2012 – 2013
and proposed expenditure for the ensuing years of the fourth control period i.e.
for 2014 – 2015, 2015 – 2016 and 2016 – 2017. Taking into consideration the
normative depreciation, normative return and non-tariff income, DPL has also
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 7
calculated and furnished the figures for ARR for each ensuing year of the fourth
control period and also the revenue recoverable through tariff during 2014 –
2015. Based on figures of sale of power DPL has proposed average tariff of
525.32 paise / kWh for 2014 – 2015, 538.83 paise / kWh for 2015 – 2016 and
566.99 paise / kWh for 2016 – 2017.
2.5 The Units III, IV & V (77 MW each) have been proposed for decommissioning
and no projection for generation has been made from these three units from
2014 – 2015 onwards. DPL has now two units in its power station with a total
capacity of 410 MW as against earlier four units with capacity of 641 MW. The
unit VI has a capacity of 110 MW and the 7th unit is having capacity of 300 MW.
DPL had taken up the construction of its 8th Unit for a capacity of 250 MW which
is projected to be commissioned on 01.07.2014 as per their submission. DPL,
however, submitted their application for prior approval of the Commission for
synchronization of unit VIII in terms of regulation 6.15.2 of the Tariff Regulations
only on 11.07.2014 order on which, have been passed by the Commission on
25.07.2014 giving go-ahead clearance for synchronization of the new 250 MW
unit no. VIII on or after 26.07.2014. DPL vide their letter no. MD/DPL/F-
148/2014/2400 dated 11.10.2014 have communicated that after successful
completion of trial run operation of 1 x 250 MW unit no. VIII, commercial
operation for the said unit has been declared from 00.00 hrs. of 01.10.2014.
Both the copies of the order dated 25.07.2014 and the letter dated 11.10.2014 of
DPL have been posted in the website of the Commission. Considering the fact,
the Commission decides to consider the COD as 01.10.2014 and all
components of generation, sales and cost have been determined accordingly.
DPL has proposed Plant Load Factor (PLF) for its old unit VI (110 MW) at 60%
in lieu of normative 64% for the year 2014 – 2015,2015-16 and 2016 – 2017 and
that for Unit VII and Unit VIII at 80% as per the norms specified in the Tariff
Regulations. Since, however, such high PLF could never be achieved in the past
from this old unit, DPL has submitted to review the fixation of PLF for Unit VI.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 8
Based on normative PLF, DPL has projected gross generation of power of the
order of 3995.76 MU during the year 2014 – 2015 and 4432.56 MU during each
of the two years 2015 – 2016 and 2016 – 2017.
2.6 The total sale of power of the licensee will be of the order of 3645.05 MU during
2014 – 2015, 4052.83 MU during 2015 – 2016 and 4052.83 MU during 2016 –
2017. The sales have been estimated based on the expected increase in
number of consumers and also increase in contract demand of the existing
consumers of DPL. DPL has shown the consumer category wise proposed
sales for each year of the fourth control period.
2.7 Though the generation of DPL is normally sufficient to meet the local demand
and allows it to sell the surplus power to WBSEDCL. In case of emergency or
whenever own generation of DPL is inadequate, power is sourced from
WBSEDCL to meet the local demand. DPL has proposed sale of power to
WBSEDCL and others of the order of 1177.860 MU during 2014 – 2015,
1112.420 MU during 2015 – 2016 and 1112.420 MU during 2016 – 2017. DPL
currently does not sell / purchase power to / from any other utility apart from
WBSEDCL.
2.8 The tariff applicant will purchase power from non-conventional sources of
energy as per the guidelines of the Commission depending on availability of the
same from M/s. Corporate Ispat and M/s Solitaire Industrial Infrastructure Pvt.
Ltd.
2.9 DPL has proposed to maintain its T & D losses at 5.20% for each of all the
three years under fourth control period despite increased technical losses due
to increase in system loading and extension of T & D net work. DPL has
undertaken several measures for reduction of T & D losses. Such measures
include augmentation and renovation of T&D system, replacement of single
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 9
phase and three phase electro mechanical meters by static meters, wide use of
plastic anti tamper & security seals, replacement of CTs of consumers, as
required, for recording energy accurately, surprise checking and regular raids to
curb theft of power etc.
2.10 The station heat rates as proposed by the licensee are as per norms specified
in the Tariff Regulations. As per norms, the heat rate of the old unit VI of DPL’s
power station is 3100 Kcal / kWh for all three years of the fourth control period
and the same for its new Units VII & VIII is 2345 Kcal / kWh for each year of the
fourth control period. Since, however, the average heat rate of the old unit VI is
around 3418 Kcal / kWh for various reasons like smaller size, vintage, non-
availability of H.P. heaters, presence of foreign materials in coal, boiler without
re-heater etc., DPL has submitted to allow the heat rate of 3418 Kcal / kWh for
unit VI.
2.11 DPL has proposed the average landed cost of coal considering the average
hike of 10% in coal price over the actual average coal price for 2012 – 2013.
2.12 The proposed transit and handling losses of coal are as per norm specified in
the Tariff Regulations. DPL, however, is of the opinion that it will not be able to
maintain such too low rate of transit and handling losses for various reasons
and since in reality the transit and handling losses are of the order 2% to 3%.
2.13 The proposed specific oil consumption rates are as specified for the units of
DPL in the Tariff Regulations.
2.14 The generating station of DPL had five existing units comprising 3X77 MW +
1x110 MW and a new unit of 1X300 MW. Another unit of 1X250 MW (Unit VIII)
was scheduled to be commissioned on 01.07.2014 as per submission of DPL.
DPL, however, have declared the COD of 1x250 MW unit no. VIII from 00.00
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 10
hrs of 01.10.2014 as already mentioned in paragraph 2.5 in this chapter and
the Commission considers the same for the purpose of tariff determination. DPL has proposed for decommissioning of Units III, IV & V (3X77 MW) with
effect from the beginning of the financial year of 2014 – 2015. It has submitted
that necessary process for decommissioning of the above three units has
already been taken up with the appropriate authority. DPL, therefore, is
presently operating with only two units i.e., units VI & VII (1X110 MW + 1X300
MW). Employees engaged in the concerned three units will be redeployed in
the above said existing two units and also in the forthcoming unit VIII. As per
Man / MW ratio of unit VIII, the number of employees comes to 300. In the
financial year 2014 – 2015, DPL projected fresh induction of 50% of
recommended employees against unit VIII and the rest 50% will be dealt
suitably with assessment of employees’ strength and agronomics thereon or for
further fresh induction after the decommissioning of the aforesaid units.
However, DPL projected employee cost against unit VIII as per existing
average salary for the ensuing years based on 150 employees.
2.15 Regarding expenses on Operation & Maintenance (O&M), DPL has stated that
they have proposed expenditure on this head of account as per norm specified
in the Tariff Regulations and proposed expenses for the years are as below:
• Rs. 11237.36 lakh for 2014 – 2015;
• Rs. 12578.47 lakh for 2015 – 2016;
• Rs. 13504.13 lakh for 2016 – 2017.
The reasons for such huge expenditure as stated by DPL are –
• frequent tube leakage for poor grade of coal,
• high up-keeping expenses for the old units,
• sixth unit was commissioned in the year 1985 and frequent outage invites
high maintenance expenses,
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 11
• the normative expenditure is for generation only and does not include
expenses for T & D wing,
• almost no inflation factor has been considered for fixing the norm. Current
inflation rate is around 9%.
In this regard, the Commission states that the contention of DPL that no
inflation is considered in fixing the norms is not correct. During norms
fixation, all the above aspects have been considered on the basis of
suggestions and objections of the stakeholders.
2.16 DPL has also prayed for allowing projected coal and ash handling charges and
water charges over and above the O&M expenses since these are not part of
the O&M expenditure in terms of the Tariff Regulations.
2.17 The licensee has doubtful debt of the order of Rs.89.07 crore of which certain
amount is almost not possible to be recovered since these dues are from sick
companies which are either referred to BIFR or closed or under liquidation. DPL
has, therefore, prayed to allow some more amounts in addition to normative
amount under this head of account.
2.18 DPL has proposed its other fixed costs for each ensuing year of the fourth
control period and adduced justifications for increase, wherever required.
2.19 DPL has stated that it has made every effort to meet the information
requirements as specified by the Commission. DPL has requested the
Commission to look at any omission or shortcoming sympathetically, in case
there is any gap in data submission. DPL agrees to make available all such
data as the Commission may require notwithstanding any waiver given by the
Commission, it has been stated.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 12
2.20 DPL has requested the Commission to (1) accept the Aggregate Revenue
Required and the Tariff Proposal for the fourth control period covering the years
2014 – 2015 to 2016 – 2017 and (2) pass orders as the Commission may deem
fit and proper keeping in view the facts and circumstances of the case.
Tariff Order of DPL for the year 2014 – 2015
CHAPTER - 3 Objections, Suggestions Etc.
West Bengal Electricity Regulatory Commission 13
3.1 Shyam Ferro Alloys Limited and Bamunara Industries Welfare Association
have submitted their objections, suggestions and comments on the MYT
application of DPL for the fourth control period within the scheduled date i.e.
25.05.2014. The main points of the objections, suggestions and comments
are summarized in subsequent paragraphs. The Commission’s observations
on some of the objections, suggestions and comments are also recorded in
this chapter.
3.2 Objections, suggestions and comments of Shyam Ferro Alloys Limited
3.2.1 Shyam Ferro Alloys Limited (SFAL) in their objections at first submits the
background of DPL and its consumers and the impact of proposed tariff if
implemented. They submit that from the figure indicated in the application
and other available documents, annual accounts etc., it appears that lower
utilization of generating units and other infrastructures, excessive cost on
fuel, O&M expenses and financial charges have resulted in increase in cost.
The Commission have noted the comments of SFAL and dealt with the same
while determining the cost under different heads in subsequent chapters.
3.2.1.1 SFAL says that power generated by DPL is supplied to its consumers in
Durgapur out of which about 90% constitute bulk industrial consumers. DPL
supplies power in an area covering a very small segment of say around 100
square kilo meters. Hence, from both consumer mix and distribution network
point of view, DPL enjoys substantial benefit compared to other distribution
licensees. Hence, the maximum ATC loss of 5.5% allowed to DPL by the
Hon’ble Commission is claimed by DPL for tariff. But the loss is incurred by
DPL mainly for about 10% of the power sold. If the said loss is properly
analyzed, it may be seen that the said loss for LT sector of consumer is either
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 14
substantially more or the said loss claimed to be actual may be inflated. This
is an area we believe reduction of tariff by a few paise exist.
This Commission has noted the point and dealt with in the subsequent
chapter for determination of energy balance as per the Tariff Regulations.
3.2.2 SFAL in their summarized objections have also stated, inter-alia, the following
item wise objections for consideration of the Commission:
3.2.2.1 Manpower allowed by Regulation and considered by DPL in MYT:
The Regulation provides the Man/MW ratio for DPL presuming combination
of different units in the following manner:
Unit No. Installed Capacity Man/MW Ratio 3, 4, 5 & 6 3x77+1x110 MW 3.5
3, 4, 5, 6 & 7 3x77+1x110+1x300 MW 2.42 3, 4, 5, 6, 7 & 8 3x77+1x110+1x300+1x250 MW 2.08
7 & 8 1X300+1X250 MW 1.20
DPL in its MYT application has indicated generation from Units 6, 7 & 8 only.
No generation from Unit 3, 4 & 5 has been considered. There is no Man/MW
ratio prescribed for Units 6, 7 & 8 only. Since the same for Units 3, 4, 5, 6, 7
& 8 have been stated as 2.08 men per MW and that for 3, 4, 5 & 6 is 3.5 men
per MW, the Man/MW ratio for Units 6, 7 & 8 only should in our opinion be
less than 1.5 men per MW. In that case the Man power for the power station
of DPL should be less than 990 persons.
The Commission has noted the above points but will follow the employee
cost determination by following Tariff Regulations and specifically paragraph
(xii) and (xv) of the note under Schedule – 9A of the Tariff Regulations.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 15
3.2.2.2 Escalation in Wages and Salary :
It has been a practice to claim ad-hoc escalation in expenditure on account of
salary. As we know, the Pay structure of DPL is similar to that of other state
owned power utilities. The pay scales are revised usually once in every 10
years. Since no such revision is due during the intervening period, the
escalation should remain limited to annual increment and increased DA. But
on the other hand there should be reduction in employees cost due to
reduction in work force on account of superannuation. Since, the average
gross remuneration of outgoing employees is substantially more than new
recruits, if any, the net impact should be nominal. But DPL has claimed a
very high rate of escalation for DA. While the increase in Basic Pay is from
Rs. 2607.18 lakh in 2013-14 to Rs. 2932.67 lakh in 2016-17, said increase in
case of DA is from Rs. 2392.79 lakh in 2013-14 to 3630.14 lakh in 2016-17
which in our opinion much more than the rate of inflation relevant index.
Similar escalation has been claimed for elements of employees cost also. No
consideration for reduced man power requirement with proposed mix of units
available for generation, as mentioned in previous Para, has been made.
Hence the amount claimed on this account may kindly be examined with
regard to escalation claimed.
The Commission has noted the above point.
3.2.2.3 Ash Handling Expenses :
DPL has its main generating units, whose generation has been projected in
MYT, are new and larger units. As we know, these units have adopted Dry
Ash disposal technology involving additional project cost associated with
O&M expenses and involvement of interest and depreciation. But, as it is
known to us DPL has a limited quantum of dry ash for disposal and as a
result expenditure incurred on this account appeared to be more than what it
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 16
should have been and thus the inefficiency or avoidable expenditure is
passed on to consumers.
The Commission has noted the above points;
3.2.2.4 Sub stations with under-utilized capacity :
DPL has expanded its distribution network investing a substantial amount
and as per petition it has borrowed money for the investment made for
construction of the sub-stations. Clause 2.3.9 of the MYT provides that there
are five 132/11 KV Grid sub-stations, 1 No. 132/33 KV sub-station and one
no. 33/11 KV sub-station. But the sale of power to local consumers does not
indicate that the investment is giving return out of increase in sale of power.
Hence, the consumers are compelled to bear the cost of idle investment.
The point raised is an issue related to the stage of investment approval for
which objections and suggestions had already been invited and investment
approval was accorded by the Commission.
3.2.2.5 Purchase of power from non-conventional sources :
In clause 2.3.7 of the MYT it has been stated that DPL has agreed to
purchase power from non-conventional sources at a high price. The weighted
average impact of such high rate for non-conventional power has an adverse
impact when the actual generation goes down. As the projected generation
and actual generation of DPL varies very widely almost every year, the
consumers may have to pay more which the Hon’ble Commission may kindly
see.
Purchase of power from non-conventional energy sources is done as per
obligation of National Tariff Policy and such purchase is as per procedure of
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 17
the concerned Regulations of the Commission. Considering larger aspects of
promotion of renewable energy, the objection cannot be considered.
3.2.2.6 Own consumption of Power :
The clause 2.3.7 of the MYT provides that own consumption of power shall
be 15 MU in a year. This is apart from the auxiliary consumption of power
and consumption of other Plant which the applicant has stated as Inter Plant
Transfer. The reasonability of the quantum of own consumption may kindly
be looked into.
The point has been noted. The own consumption as projected by DPL at
15.00 MU for each ensuing years are the consumption which are used for
administrative buildings, guest houses, hospitals, sub-stations and switch
yard lighting etc. Consumption at other plants of DPL are considered as
interplant transfer and treated as sale of energy at the rate specified in the
tariff structure and the cost is borne by the other business of DPL.
3.2.2.7 Reduction in O&M Cost for new Unit :
The 250 MW Unit No. 8, generation of which has been considered for part of
the year 2014-15 and thereafter, is a new Unit. The Unit should have
warranty period for replacement of damaged parts. The old Units 3, 4, 5 have
not been considered for projecting generation. Therefore, the expenditure on
account of Repair & Maintenance should be much less than previous years.
The Hon’ble Commission may kindly look into this aspect while determining
tariff based on the proposed MYT.
The norms set for O&M expenses for generating units specified under the
Tariff Regulations itself take care of the issue raised by the objector.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 18
3.2.2.8 Interest on working capital :
It appears from the Annual Accounts of DPL that it maintains a good amount
outstanding to its creditors. On the other hand its loan for working capital and
interest implications are increasing. It had often been heard that DPL had to
restrict supply of power due to low generation for want of coal. Hence, the
reasonability of the claim on this account may be examined please.
The point is noted. The apprehension of the objector has no merit as working
capital requirement is restricted through norms.
3.2.2.9 Water Consumption :
Water consumption expense is a major item of expenditure claimed by DPL.
There is substantial increase in rate of water which is a captive plant of DPL.
The quantum of consumption of water in future years should also reduce due
to commissioning of new plants with new technologies. We would accordingly
draw the attention of the Commission on this point so that the interests of the
Consumers are protected.
The point is noted.
3.2.3 Discrepancy in Tariff Rationalization:
3.2.3.1 SFAL has referred the provision of the section 61 and 62(3) of the Act on the
issue of Tariff Rationalization. SFAL have also submitted that the increase
solicited by DPL in their petition is ranging from about 10% to 19% in three
years inspite of elimination on un-economic old small size units and addition
of new efficient large size units having the benefits of low heat rate of the
units, less fuel consumption, low man-megawatt ratio, less R&M expenses in
initial year. SFAL have also compared the hike in average tariff in percentage
of the utilities under this Commission during last two years and pray to the
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 19
Commission to due diligently verify the need for tariff increase and to set the
industrial tariff as per provisions of the Act.
SFAL have also objected the proposed rate of demand charge comparing the
same with the rate approved in the tariff orders for 2012 – 2013 in some of
the other States.
SFAL have also proposed for introduction of load factor rebate in percentage
instead of absolute term in paise / kWh prevailing at present. They also
propose to consider for bringing a parity in the LF rebate with other utilities in
the State. SFAL have also proposed for introduction of timely payment rebate
for two folds effect, namely, make consumer interested in timely payment and
getting payment early by DPL which in turn reduce the impact of interest on
working capital.
SFAL have also suggested to look in to the tariff application of DPL in line
with the relevant Regulations with least possible differential effect on account
of arrear so that no consumer is required to pay large amount of arrears at a
subsequent date.
The Commission has noted all the above points raised by the objector. The
Commission will decide on all the issues as per provisions of the Act and
Regulations made thereunder while determining the cost under different
heads and tariff of DPL in subsequent chapters.
3.3 Objections of Bamunara Industries Welfare Association:
3.3.1 Bamunara Industries Welfare Association (BIWA), has stated, inter alia, the
following points for consideration of the Commission:
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 20
3.3.1.1 Fuel Cost :
The major objections in respect of proposed fuel cost are listed in the matrix
below:
• No documentary evidence in the form of fuel invoices for the said month
i.e., October 2013 have been enclosed with the MYT Petition, without
which, prudence check is not possible.
• The weighted average coal prices in 2013-14 (Rs. 2,478.08/Ton) are
exactly 10% higher than the coal prices in FY 2012-13 (Rs. 2,252.80/Ton).
• Similarly, in case of oil, the prices in 2013-14 (Rs. 56,511.99/KL) are
exactly 10% higher than the oil prices in FY 2012-13 (Rs. 51,374.54/KL)
• Presumably, the prices in FY 2013-14 have been simply projected to be
10% higher over previous year without any reference to actual fuel invoices
as purportedly by DPL.
• A strict prudence check is required by the Hon’ble Commission and the
copies of the fuel invoices for FY 2013-14 should be placed before the
Objector as well to reassure the Objector and general public at large of
fairness in determination of energy charges.
• As per the terms of the Tariff Regulations, no escalation in fuel prices has
to be considered while projecting the tariff for the ensuing years as the
variation in the fuel prices are to be covered through the mechanism of
Monthly Variable Cost Adjustment (MVCA).
• This was reaffirmed by the Hon’ble Commission in the Tariff Order for FY
2011-12 and 2012-13 dated 17.12.2012, wherein it has disallowed the hike
projected by the DPL in the fuel prices.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 21
The points are noted. The Tariff Regulations have never restricted in giving
escalation in price of fuel from year to year. In such case MVCA will be
computed accordingly. The Commission will consider the present notified
price of coal of CIL vide notification No. CIL:S&M:GM(S&M):Pricing:234
dated 27.05.2013 effective from 28.05.2013, while determining the fuel cost
in accordance with the provisions of the Tariff Regulations.
3.3.1.2 Relaxation in norms of Plant Load Factor (PLF), Station Heat Rate (SHR),
Secondary Fuel Oil consumption, Transit loss etc.
The Tariff Regulations prescribe the norms for all the operating parameters
viz., PLF, SHR, secondary fuel oil consumption and transit loss etc. for each
generating station. DPL have requested for relaxation in norms presumably
considering the age and rating of unit VI. The objector’s view is that there are
many generating stations in the country with similar age / rating which are
operating at much better efficiency. In this context they have given the
example of Badapur TPS, Tand TPS, Panipath TPS, GND TPS (Bhatinda),
Ukai TPS, Korba TPS, Sabarmali TPS, Kothaguden TPS, Talcher (old) TPS,
Jojober TPS. In their opinion operational norms prescribed in Tariff
Regulations for unit VI are significantly lower than the industry benchmark
and any further relaxation would be detrimental to the interest of the
consumer and would tantamount to rewarding the inefficiencies of DPL.
The Commission has noted the points stated by the objector and finds no
reason to consider the prayer of DPL as explained in paragraph 1.9 of this
order and considers the operating norms as specified in the Tariff
Regulations while determining the fuel cost in subsequent chapter, as the
Tariff Regulations are finalized after inviting suggestions and objections.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 22
3.3.1.3 Power Purchase :
DPL should have avoided the short term power purchase from WBSEDCL
which was done at around Rs. 5.06/kWh in FY 2012-13 when power was
available on the exchange at half the price at around Rs. 2.88/ kWh.
Considering the above, it is humbly prayed that exorbitant and unnecessary
short term power purchase should be disallowed. Further, it is understood,
that subsequent to commissioning of the unit VIII, DPL would not require any
short term purchases. In case there is any short term requirement, then DPL
should purchase cost effective power from exchanges rather than purchase
of costly power from WBSEDCL.
In the light of the above submissions, it is humbly prayed that the short term
power purchase be disallowed in the MYT order. In the unlikely case of short
term power purchase in the fourth control period, the same can be allowed
based on actuals through the FPPCA, MVCA and APR mechanisms.
The Commission agrees with the objector’s view. DPL shall procure short-
term requirement of power from the sources wherever it is cheaper.
3.3.1.4 Employee Cost:
Bamunara Industries Welfare Association objects the following in regard to
employee cost.
• The employee costs are allowable only up to the recommended Man/MW
ratio. Based on the objector’s assessment, the employee expenses of
1345 employees only are admissible.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 23
• The proportionate cost of centralized service department and central
workshop may be capped at 8.33% of the employee costs directly
attributable to generation function and 10% of the distribution function.
• Proposal for inclusion of employee expenses of new recruitments are not
admissible as DPL has already breached the recommended Man/MW
ratio.
• Notwithstanding the above, new recruitments (thereby replacing
superannuated employees) would optimize the employee costs rather
than increase it.
The Commission has already provided its view in the same context in
paragraph 3.2.2.1.
3.3.1.5 Operation and Maintenance Expenses:
DPL has claimed repair and maintenance expenses, other administrative and
general expenses, rent, rates and taxes and audit fees under the head
Operation and Maintenance (O&M) expenses. According to BIWA, DPL have
claimed Rs. 11237.04 lakh in financial year 2014 – 2015 which is an increase
of around 18.25% over the value submitted for financial year 2013 – 2014
and the increase claimed for financial year 2015 – 2016 and 2016 – 2017 is
around 11.94% and 7.36% respectively for which DPL have not assigned any
reason for such exorbitant expenditure. The objector’s view is that in the tariff
order for financial year 2011 – 2012 and 2012 – 2013 dated 17.12.2012, the
Commission had allowed a year-on-year increase of 5% during the third
control period and the operation and maintenance expenses during the fourth
control period be allowed by the Commission to DPL considering a year-on-
year increase of 5% over the financial year 2013 – 2014 level.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 24
The Commission has noted the suggestion of BIWA and give their views
while determining the (O&M) expenses in subsequent chapter.
3.3.1.6 Coal and Ash Handling Expenses:
The DPL has claimed Rs. 1,826.30 Lakh, Rs. 2,108.86 lakh and Rs. 2,214.31
lakh for FY 2014-15, 2015-16 and 2016-17 respectively towards coal and ash
handling expenses.
Such amounts are significantly higher than the amounts admitted in the APR
Order for FY 2011-12 dated 09.09.2013 and the amounts incurred by the
DPL in FY 2012-13 as per audited accounts.
In the earlier Tariff Orders, the Hon’ble Commission had approved coal and
ash handling expenses based on the amounts proposed by the DPL and
considering normative generation levels. But in the APR orders, such
expenses were significantly scaled downwards as actual generation was
significantly below the normative levels.
Approving higher amounts in a Tariff Order and subsequently scaling it
downwards in the APR, leads to artificial tariff hike and front loading of tariff.
It is humbly prayed that the coal and ash handling expenses be allowed
considering actual generation in historical years and not normative
generation as in the past, DPL has never been able to achieve normative
generation levels.
The Commission will decide the tariff on normative basis and in case DPL
fails to maintain norm then required recovery is done through APR which is
used to reduce the tariff of subsequent year. This cyclic process
automatically keeps the tariff under control and the question of inflation does
not arise.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 25
3.3.1.7 Water Charges:
The DPL has claimed Rs. 6,101.56 lakh in FY 2014-15 and Rs. 6,724.00 lakh
in FY 2015-16 and 2016-17 respectively towards water charges.
It is humbly prayed that the water charges be allowed considering actual
generation in historical years and not normative generation as in the past,
DPL has never been above to achieve normative generation levels.
The Commission will decide the tariff on normative basis and in case DPL
fails to maintain norm then required recovery is done through APR which is
used to reduce the tariff of subsequent year. This cyclic process
automatically keeps the tariff under control and the question of inflation does
not arise.
3.3.1.8 Interest on Borrowed Capital and Advance against Depreciation:
BIWA has stated in their submission that in the APR order for FY 2009-10
there was no loan balance attributable to PFC Loan No. 50403001. However,
the APR Order for 2010-11 depicted an opening balance of Rs. 3,544.37 lakh
attributable to PFC Loan No. 50403001. It is further stated that there were no
loan additions and no loan repayments in the said loan in the FY 2010-11 and
hence, the closing loan balance was depicted as Rs. 3,544.37 lakh.
Subsequently, the APR Order for 2011-12 depicted an opening balance of
Rs. 8,891.53 lakh. There is no explanation in the APR Order dated
09.09.2013 as to how the closing balance and the opening balance contained
a difference of Rs. 5,347.16 lakh, when there were no loan additions in FY
2011-12.
Further, in the APR Petition for FY 2012-13, nil (Zero) opening balance has
been provided on PFC Loan No. 50403001. However, in the APR Petition for
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 26
FY 2012-13, the DPL has claimed Rs. 1,553.63 lakh towards such loan, even
though there are no loan balances attributable to such loan.
Subsequently, in the MYT Petition, in the year 2014-15, there is an opening
balance of Rs. 12,499.41 lakh.
The Objector states that the capex-wise identification of the loan has not
been done by the DPL in the APR & MYT Petitions and pray that the
Commission may conduct a strict prudence check towards matching of loan
balances since the first tariff order for DPL and provide a detailed chart in the
MYT Order so that the Objector and consumers at large are reassured of
fairness in allowing amounts towards interest on borrowed capital.
The objector has illustrated the excessive claim towards interest on borrowed
capital which had been allowed in the past orders and the same have direct
implication on the allowable advance against depreciation. The objector prays
that the Commission may provide a detailed chart since inception i.e., first
tariff order of DPL indicating thereby the capex wise identification of the
loans, interest on borrowed capital, depreciation and advance against
depreciation computation.
The objections of Bamunara Industries Welfare Association in regard to
interest on borrowed capital are summarized below:
• Expenses towards interest on PFC loans be allowed after a strict
prudence check and after matching the loan balance w.r.t. past years.
• The Hon’ble Commission may provide a chart mapping the loans with
the capex schemes since the first tariff order for DPL and provide a
detailed chart in the MYT order so that the objector and consumers at
large are reassured of fairness in allowing amounts towards interest
on borrowed capital.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 27
• Disallow the interest on GoWB loan and CEA loan as they are
enjoying perpetual moratorium.
As pointed out by M/s Bamunara Industries Welfare Association, the
Commission has examined the loan balances of different years starting from
2009 – 2010 with reference to actual audited accounts of DPL. The opening
balance of PFC loan no. 50433001 of the year 2013-14 as submitted by DPL
in their MYT petition is found to be correct. The actual status is given in the
table below. For details, Form – C to Annexure – 1 submitted by DPL with the
MYT application may be referred to. The point raises is an issue related to
the stage of investment approval for which objections and suggestions had
already been invited and after considering the same, if any, investment
approval was accorded by the Commission.
PFC Loan No. 50403001
Year Opening balance
Fresh drawal Repayment
Closing balance
2008-09 0 4213.01 0 4213.01 2009-10 4213.01 2772.68 0 6985.69 2010-11 6985.69 1905.84 0 8891.53 2011-12 8891.53 4078.82 378.51 12591.84 2012-13 12591.84 1861.74 954.22 13499.36
3.3.1.9 Income Tax:
BIWA has submitted that the power business of DPL is not a separate
business entity for the assessment of income tax. Its tax liability would
depend on the overall taxable income of the company as a whole and the
Tariff Regulations provide only for reimbursement of income tax which is
actually paid and upon production of documentary evidence and thus no
amount towards income tax is allowable based on projection.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 28
The Commission has noted the points and dealt with in subsequent chapter
appropriately.
3.3.1.10 Demurrage:
BIWA has submitted that DPL has not advanced any reason for the need of
demurrage charges, nor has it submitted any document in support of the
claim. In terms of regulation 5.8.1(vi) of the Tariff Regulations, the demurrage
charge of a railway rake is an indicator of efficiency of rake unloading
capability of the generation station.
There was a specific direction issued to DPL by the Hon’ble Commission in
the APR order for FY 2011 – 2012, dated 09.09.2013, that from FY 2012 –
2013 onwards, the DPL should include the expenditure on account of
demurrage in fuel related costs in terms of regulation 5.8.1 (vi) of the Tariff
Regulations. Therefore, BIWAI feel that based on the Commission’s directive,
demurrage expenses are not permissible to be claimed separately and are to
be included as part of fuel related costs.
The Commission is of the opinion that demurrage charge is not a normal
business process and cannot be assessed in tariff determination stage. It is
applicable at the stage of FPPCA determination.
3.3.1.11 Development Fund:
The Objector submits that the DPL has neither mentioned the purpose of
such fund for a particular function nor have they segregated it function wise.
DPL has also not mentioned whether they will be able to comply with all the
provisions of the Regulations to maintain such fund. It is humbly prayed that
no amount under the head ‘development fund’ may be allowed in the MYT
order.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 29
The Commission has noted the points and dealt with in subsequent chapter
appropriately.
3.3.1.12 Income from other sources / Non Tariff Income:
BIWA submits that DPL has projected Rs. 816.84 lakh, Rs. 825.60 lakh and
Rs. 833.14 lakh during the year 2014 – 2015, 2015 – 2016 and 2016 – 2017
respectively towards non-tariff income. The year-on-year increase in non-tariff
income over the control period has been considered at a meager rate of 1%.
A close scrutiny of the audited accounts reveals that the actual incomes from
other sources / non-tariff income of DPL have been to the tune of Rs.
1037.47 lakh and Rs. 1768.46 lakh for FY 2011 – 2012 and 2012 – 2013
respectively.
It is thus seen that the non-tariff income have been projected on the lower
side in the MYT petition. Moreover, the year-on-year increase of mere 1%
considered by DPL is very unreasonable as the actual increase was 70% in
FY 2012 – 2013 over FY 2011 – 2012 levels.
BIWA pray that the Commission may approve non-tariff incomes based on
past trends and considering a year-on-year escalation of atleast 10% over the
control period.
The Commission agrees with the point and considers non-tariff income after
applying a growth rate on last audited value available on this head where the
growth rate is considered at 1% less rate of the average growth rate on this
head for last five years.
3.3.1.13 Income from Unscheduled Interchange (UI) of power:
DPL had earned an amount of Rs. 1941.41 lakh and Rs. 694.10 lakh from the
UI of power during FY 2011 – 2012 and 2012 – 2013 respectively. But in the
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 30
MYT petition, DPL have not projected any such income during the fourth
control period. BIWA prays that considering past trends and the energy
surplus position which DPL aims at to attain after commissioning of unit VIII,
the Commission considers an appropriate amount of UI earnings during the
fourth control period and allow it as a deduction from the ARR being
determined in terms of regulation 5.17.3.
The Commission is of the opinion that UI is not a normal business process
and cannot be assessed in tariff determination stage. UI occurs during real
time operation and thus it is applicable at the stage of FPPCA / APR
determination as per Tariff Regulations.
3.3.1.14 Violation of Regulations in computing Provisional Tariff of Unit No. VII:
It is stated that the project cost of unit VII could not be finalized in the APR
order dated 09.09.2013 by the Commission since DPL failed to fulfill certain
directives given by the Commission starting from the tariff orders for the FY
2007 – 2008 and thereafter. The same was recorded by the Commission in
paragraph 2.2.1 of the APR order dated 09.09.2013. The objector submits
that the in the said order, the Commission directed DPL to fulfill the
conditions laid down in the relevant Tariff Regulations in respect of
determination of final capital cost.
The objector submits that in the absence of furnishing of information /
documents’ relating to approval of final capital cost / investment approval, the
Commission, as per the provision of the relevant Tariff Regulations, has
power to grant a provisional tariff up to a maximum of 95% of the submitted
project cost prayed by DPL.
The objector also submits that pending the approval of the final project cost of
unit VII of DPL, the Commission, during determination of Aggregate Revenue
Requirements (ARR) for the years 2011 – 2012, 2012 – 2013 and 2013 –
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 31
2014 considered provisionally the project cost of unit VII, after deduction of
5% of the project cost, as indicated by the DPL in its tariff application. Hence,
the Commission, after deducting 5% of the provisional project cost amounting
to Rs. 6750.00 lakh allowed 95% of the project cost furnished by DPL.
The Commission has noted the points and in this context has given direction
in direction chapter. However, on the point of allowing excessive amount
towards advance against depreciation, it is to be noted that the amount
released is limited by the restriction as per the regulations but not more than
the amount to meet the repayment of the principal amount of loan.
3.3.1.15 Project cost of Unit VIII:
BIWA has stated that project capital cost of Rs. 6.80 crore/MW is enormously
high considering the unit VIII is a brown-field unit and taking into account the
market scenario when the project was envisaged and implemented. The
Hon’ble Commission and the consumers need to know the capital cost
envisaged, when the Detailed Project Report (DPR) was prepared and what
has been the variation in the actual costs vis-à-vis original cost. Any delay
which could have been avoided and is due to controllable reasons, should be
disallowed and its associated costs in terms of interest during construction
and over heads need to be disallowed.
The Commission has noted the points and dealt with the same in subsequent
chapter.
3.3.1.16 Units proposed to be decommissioned:
BIWA submits that since the units no. III, IV and V are proposed to be
decommissioned, hence any ARR (i.e., return on equity, depreciation, interest
on loan and operation and maintenance expenses) towards such units may
not be allowed in the fourth control period.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 32
The Commission has noted the points and dealt with the same in subsequent
chapter.
3.3.1.17 Consequential impact on interest on working capital:
BIWA submits that there is significant potential disallowance in the claims
made by DPL, which if approved by the Hon’ble Commission, would result in
reworking of the interest on working capital. In the light of the same, it is
stated that the working capital and interest thereon will have to be
recomputed as per the regulations 5.6.5.1 and 5.6.5.2 of the Tariff
Regulations.
The Commission will deal with the matter as per provisions of the Tariff
Regulations.
3.3.1.18 Revenue at current Tariff:
BIWA has submitted that the MYT application of DPL was filed on or around
28.12.2013. Around the same time, the Hon’ble Commission issued the tariff
order for the financial year 2013 – 2014 on 26.12.2013 in which the retail
tariffs were substantially increased. However, for the purpose of estimating
the revenue at current tariffs, DPL has considered the retail tariffs approved
by the Hon’ble Commission in the tariff order for the financial year 2012 –
2013 dated 17.12.2013 which on the current date is no longer applicable.
This resulted in under estimation of the revenue projections at current tariff
over the fourth control period. BIWA also states that the current tariff
proposals for the financial years 2014 – 2015, 2015 – 2016 and 2016 – 2017
made in the MYT petition have become infractuous as they are based on the
old applicable tariffs. BIWA urges the Hon’ble Commission to direct the DPL
to file fresh tariff proposal and allow the consumers to file comments on such
revised tariff proposal.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 33
The Commission will determine the tariffs of DPL for the ensuing years based
on the admissible ARR. The Commission will also view the current tariff as
per the tariff order for 2013 – 2014 while determining the tariff for the ensuing
years.
3.3.1.19 Demand Charges:
BIWA submits that DPL has not provided the details in respect of existing
connected load and the projected load growth in the fourth control period.
Further, in the revenue projections, DPL has shown nil (0) figures towards
same categories of consumers even though demand charges have been
prescribed.
DPL has proposed the demand charge for some categories for which no
revenue is projected. The Commission observes that this may be due to the
fact that there is no consumer under those categories of consumers. The
Commission is of the view that the tariff for those categories under which the
present consumer is nil is required to be determined so that the same may be
applied when any new consumer come under these categories.
3.3.1.20 Voltage wise cost of service and roadmap for reduction of cross subsidy:
BIWA submits that according to the Regulations of the State Commission, it
is bound to determine tariff in a manner such that it reflects the cost of supply
of electricity and also reduces cross subsidies within three years and is
consistent with the National Electricity Policy and Tariff Policy. Section 61(g)
of the Electricity Act, 2003 mandates that the State Commission while
determining the tariff, shall be guided by the objective that the tariff
progressively reflects the cost of supply of electricity and also the cross-
subsidies are reduced. However, the State Commission has not determined
the cost of supplying electricity to the industrial consumers at different voltage
levels and more particularly at higher voltage levels, which would involve
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 34
minimal technical losses and distribution expenses. The cross subsidy
surcharge according to Tariff Policy for open access consumer has to be the
difference between the applicable tariff and the cost of the distribution
licensee to supply electricity for the applicable class of consumers. Section
62(2) provides for the factors on which the tariffs of the various consumers
can be differentiated. Some of these factors like load factor, power factor,
voltage, total electricity consumption during any specified period or time or
geographical position also affects the cost of supply to the consumer. Due
weightage can be given in the tariffs to these factors to differentiate the tariffs.
However, BIWA infer the following conclusion after reading the provisions of
the Act, the Policy, Regulations and related judgements:
i) The cross subsidy for a consumer category is the difference between cost
to serve of that category of consumers and average tariff realization of
that category of consumers. While the cross-subsidies have to be
reduced progressively and gradually to avoid tariff shock to the
subsidized categories, the cross subsidies may not be eliminated.
ii) The tariff for different categories of consumer may progressively reflect
the cost of electricity to the consumer category but may not be a mirror
image of cost to supply to the respective consumer categories.
iii) The tariffs should be within + 20% of the average cost of supply by the
end of 2010 – 2011 to achieve the objective that the tariff progressively
reflects the cost of supply of electricity.
iv) The cross subsidies may gradually be reduced but should not be
increased for a category of subsidizing consumer.
v) The tariffs can be differentiated according to the consumer’s load factor,
power factor, voltage, total consumption of electricity during specified
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 35
period or the time or the geographical location, the nature of supply and
the purpose for which electricity is required.
In view of above, BIWA urged the Commission to approve the tariffs
considering the voltage wise cost of service and prescribe a roadmap for
reduction of cross subsidy.
The Commission has noted the points and will act according to Tariff
Regulations.
3.4 The Commission has taken note of the objections, suggestions and comments
offered. Some of the objections, suggestions and comments have been dealt
with in the paragraphs above. The objections, suggestions and comments which
have not been dealt with in earlier paragraphs and are directly concerned with
the instant petition, have been considered in the subsequent chapters of this
order in which various components of fixed costs have been analyzed and
discussed.
Tariff Order of DPL for the year 2014 – 2015
CHAPTER – 4
SALES, ENERGY BALANCE AND VARIABLE COST
West Bengal Electricity Regulatory Commission 36
4.1 While determining the Aggregate Revenue Requirement (in short ‘ARR’) for the
years 2014 – 2015, 2015 – 2016 and 2016 – 2017 under the fourth control period
for DPL, the following considerations have been made:
i) As per submission of DPL, the units III, IV and V of 77 MW each are not
in operation and to be decommissioned during 2013 – 2014 in stages and
their related generation, costs, etc. have been omitted from the tariff
determination process.
ii) As per submission of DPL, the date of commercial operation (COD) of
Unit VIII was scheduled on 1st
July, 2014. However, DPL could submit
their completed application for prior approval of the Commission for
synchronization as required under the Regulations for trial run operation
of the unit only on 11.07.2014 and necessary clearance from the
Commission was given on 25.07.2014 for trial run operation on or after
26.07.2014. DPL, however, communicated vide their letter no. MD/DPL/F-
148/2014/100 dated 09.10.2014 the COD of the unit VIII w.e.f.
01.10.2014. The Commission, thus, does not consider the date of COD of
unit VIII as 01.07.2014 as proposed by DPL, but considers to estimate
generation from the unit for a period of six months during the year 2014 –
2015 and all related elements of costs etc. have been considered
accordingly.
Therefore, the following chapters for determination of tariff are related to unit VI
(110 MW), Unit VII (300 MW) and Unit VIII (250 MW) of DPL.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 37
4.2 Projected Sales:
4.2.1 DPL is a multi-disciplinary company. Besides being in the business of power as a
distribution licensee, DPL is having a coke oven plant, a coal washery and a
water treatment plant. The energy requirements of coke oven plant, coal washery
and water treatment plant are met from the power business of DPL and are
treated as inter-plant transfer on cost recoverable basis. In addition to meet its
local demand, DPL will need to supply WBSEDCL at 11 KV and 33 KV at radial
mode. DPL shall supply the surplus energy, if any, to WBSEDCL at 132/ 220 KV
in 2014 – 2015, 2015 – 2016 and 2016 – 2017 as per the projections made by
them. DPL in their application has considered 50 MU as units utilized in own
premises including own consumption / other auxiliary consumption. The
Commission considers 15 MU as consumption in own premises and 35 MU as
inter plant transfer for all the three years viz., 2014 – 2015, 2015 – 2016 and
2016 – 2017. The sale of energy to the consumers in its licensed area, inter-plant
consumptions and sale to WBSEDCL at 11 KV / 33 KV / 132 KV / 220 KV in
radial mode and from Bus in different years of the fourth control period has been
shown as under as projected by DPL:
4.3 Sourcing of Energy for Distribution:
4.3.1 The entire energy requirement of DPL for distribution including inter-plant transfer
generally comes from its own generating units. Part of the ex-bus generation,
remaining surplus after meeting the demand of its licensed area and inter-plant
Figures in Million Units Sl. No. Category of Supply 2014 – 2015 2015 – 2016 2016 – 2017
1 Consumer 2432.190 2905.110 2923.410 2 Inter Plant Transfer 35.000 35.000 35.000 3 Consumption at own premises 15.000 15.000 15.000 4 Sale to WBSEDCL and other licensees 1177.860 1112.420 1112.425 5 Total (1 + 2 + 3) 3660.050 4067.530 4085.835
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 38
transfer, is to be sold to WBSEDCL. However, if own generation of DPL during a
period is found inadequate, energy is to be sourced from WBSEDCL or
elsewhere. The quantum of power purchase requirement for DPL from
WBSEDCL can be assessed after considering the projected generation of DPL
as well as the periodicity of such generation.
4.4 Gross Generation:
4.4.1 DPL has projected gross generation of 3995.760 MU, 4432.560 MU and
4432.560 MU during the years 2014 – 2015, 2015 – 2016 and 2016 – 2017
respectively in their MYT petition for the fourth control period considering
generation in full capacity of its units VI & VII and generation of unit VIII after its
COD (01.07.2014). No generation has been projected in respect of units III to V
which were stated to be decommissioned during 2013 – 2014. Gross energy
generation has been projected by DPL for the years 2014 – 2015, 2015 – 2016
and 2016 – 2017 considering the normative PLF of Unit VI to Unit VIII separately.
The Commission admits the projection of generation of DPL for energy balancing
for the years 2014 – 2015, 2015 – 2016 and 2016 – 2017 for Units VI & VII. For
unit VIII, proportionate generation for six months period, as stated in para 4.1
above, has been admitted by the Commission for 2014 - 2015. The Commission,
however, considers gross generation from unit VIII, as projected by DPL, on
normative PLF basis for the year 2015 – 2016 and 2016 – 2017.Accordingly, the
gross generations from these units of DPL for all the three years of the fourth
control period stand as follows:
Year Gross Generation (in MU) Unit VI Unit VII Unit VIII Total
2014 – 2015 578.160 2102.400 876.666 3557.226 2015 – 2016 578.160 2102.400 1752.000 4432.560 2016 – 2017 578.160 2102.400 1752.000 4432.560
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 39
4.5 Auxiliary Consumption:
4.5.1 DPL has claimed auxiliary consumption for the Units at 354.89 MU for 2014-15,
394.200 MU for 2015 – 2016 and 394.200 MU for 2016 – 2017. The Commission
has considered auxiliary consumption on the basis of the norms as specified in
the Tariff Regulations and accordingly the auxiliary consumption stands as per
the table below:
Auxiliary Consumption and Ex-Bus Generation (MU)
Year Unit Gross Generation
Rate of Aux. Consumption (%)
Aux. Consumption
Ex-bus Generation
2014 – 2015
VI 578.160 10.00 57.816 520.344 VII 2102.400 8.50 178.704 1923.696 VIII 876.666 9.00 78.900 797.766
Total Ex-bus Generation 3241.806
2015 – 2016
VI 578.160 10.00 57.816 520.344 VII 2102.400 8.50 178.704 1923.696 VIII 1752.000 9.00 157.680 1594.320
Total Ex-bus Generation 4038.360
2016 – 2017
VI 578.160 10.00 57.816 520.344 VII 2102.400 8.50 178.704 1923.696 VIII 1752.000 9.00 157.680 1594.320
Total Ex-bus Generation 4038.360
4.6 Distribution Loss:
4.6.1 DPL has projected distribution loss of 136.14 MU for 2014 – 2015, 162.248 MU
for 2015 – 2016 and 163.09 MU for 2016 – 2017. The Commission has allowed
distribution loss as per norms as specified in the Tariff Regulations against
projected sale of energy to the consumers and consumption at own premises.
The inter-plant transfer has not been considered as it does not involve
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 40
distribution network. Accordingly, the distribution loss as admitted by the
Commission is shown in the following table:
Distribution Loss
Year As Admitted by the Commission
Sale of Energy to Consumer and consumption at own premises in MU
Distribution Loss in % Distribution loss in MU
2014 – 2015 2447.190 5.20 134.234 2015 – 2016 2920.110 5.20 160.175 2016 – 2017 2938.410 5.20 161.179
4.7 Purchase of Power:
4.7.1 Normally, DPL will not need to purchase any power. But to meet the gap
between demand and available generation, DPL has to purchase some quantum
of power as and when required. Thus purchase of some quantum of power has
been considered.
4.7.2 As per energy balance in paragraph 4.8, the following amounts are admitted as
power purchase cost of DPL for the years 2014 – 2015, 2015 – 2016 and 2016 –
2017 considering the average rate of purchase by DPL from WBSEDCL as given
below:
Sl. No. Particulars 2014 – 2015 2015 – 2016 2016 – 2017
1 Quantum of Purchase (MU) 155.330 191.418 210.560 2 Average rate of Purchase (Paise/kWh) 563.00 619.00 681.00 3 Power Purchase Cost (Rs. in lakh) 8745.08 11848.77 14339.14
4.8 Energy Balance:
4.8.1 On the basis of the analysis done in the foregoing paragraphs, the Commission
admits the following Energy Balance for DPL for the years 2014 – 2015, 2015 –
2016 and 2016 – 2017.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 41
Figures in Million Units Sl. No. Particulars 2014 – 2015 2015 – 2016 2016 – 2017 Sources of Supply
1 Net Ex-Bus Generation 3241.806 4038.360 4038.360 2 Purchase 155.330 191.418 210.560 3 Total Supply (1 + 2) 3397.136 4229.778 4248.920 4 Sale to Consumers 2432.190 2905.110 2923.410 5 Inter-unit Transfer 35.000 35.000 35.000 6 Consumption at own premises 15.000 15.000 15.000 7 Distribution Loss (as per para 4.6) 134.234 160.175 161.179 8 Supply to WBSEDCL and others 780.712 1114.493 1114.331 9 Total ( 8= sum of 4 to 8 ) 3397.136 4229.778 4248.920
4.9 Fuel Cost:
4.9.1 An examination of the projected fuel cost claimed by DPL for the ensuing years
2014 – 2015, 2015 – 2016 and 2016 – 2017 of the fourth control period under
different heads for its power station has been taken up hereunder.
4.9.2 Fuel cost for the power station of DPL as per its projection comes as under:
Fuel Cost in Rupees in Lakh Power Station 2014 – 2015 2015 – 2016 2016 – 2017 DPL VI - VIII 84677.64 100785.72 110864.37
4.9.3 In the tariff application for the fourth control period, DPL has proposed fuel cost
separately for units VI to unit VIII on the basis of norms of plant load factor,
auxiliary consumption rate, oil consumption rate, station heat rate and transit and
handling losses of coal as specified in Schedule 9A of the Tariff Regulations.
4.9.4 The Commission, however, has adopted the procedure for calculation of the fuel
cost in accordance with regulation 5.8.1(ii) of the Tariff Regulations and
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 42
normative parameters applicable to DPL as specified in the Tariff Regulations
and allowed fuel cost to DPL as mentioned in subsequent paragraphs.
4.9.4.1 While determining the average price of coal and average price of oil for the years
2014 – 2015, 2015 – 2016 and 2016 – 2017 of the fourth control period, the
Commission has noted that DPL has projected cost of coal based on the
notification no. CIL:S&M:GM(F):Pricing 1965 dated 31 January, 2012 of Coal
India Limited for indigenous coal. Related charges are also factored in terms of
present fuel supply agreement. A number of statutory levies e.g., excise duty at
5.15% and clean energy cess i.e., Rs. 50/- per tonne have also been made
applicable.
4.9.4.2 The Commission, however, goes by the latest price notification No.
CIL:S&M:GM(F):Pricing:235 dated 27 May, 2013, CIL:S&M:GM(F):Pricing:2340
dated 13 November, 2013 and CIL:S&M:GM(F):Pricing:2784 dated 16
December, 2013 issued by Coal India Limited for determining the average price
of coal of 2014 – 2015, 2015 – 2016 and 2016 – 2017 of the fourth control
period. Related charges and the statutory levies are also considered as per the
latest price notifications.
4.9.4.3 The Commission considers the grade wise coal mix as projected by DPL for the
year 2014 – 2015. The Commission does not consider any hike in coal price for
the years 2015 – 2016 and 2016 – 2017. However, any major variation in coal
price in subsequent period will be adjusted through Monthly Variable Cost
Adjustment (MVCA) as per provision of the Tariff Regulations.
4.9.4.4 The average oil price has been considered at the actual price of oil for Rs.
51374.54 per KL during 2012 – 2013 as per audited annual accounts and
enhanced the same by 5% to arrive at the estimated price of Rs. 53943.27 per
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 43
KL for the year 2013 – 2014. The Commission observes that the oil prices
decreased to a great extent during the year 2014 – 2015. The Commission, thus,
does not consider any hike in the estimated price of 2013 – 2014 for the ensuing
years. Any difference in actual oil price during the ensuing years will be adjusted
through MVCA as per provision of the Tariff Regulations. The average coal and
oil price based on the proposal of DPL for grade mixing of coal from different
sources and the price of oil for the three ensuing years of the fourth control
period are shown below:
Average Coal Price in Rs./MT Average Oil Price in Rs./KL 2014 – 2015 2015 – 2016 2016 – 2017 2014 – 2015 2015 – 2016 2016 – 2017
2467.53 2467.53 2467.53 53943.27 53943.27 53943.27
Detailed computation of coal price for 2014 – 2015 has been given in Annexure –
4A to this chapter.
4.9.4.5 Heat value of oil for all the three years of the fourth control period has been
considered as per actual heat value of 2012 – 2013 which is 9200 Kcal/lit. Heat
value of coal has been considered as per the Tariff Regulations and the detailed
computations are shown in Annexure 4A to this chapter. However, it is to be
finalized during Fuel and Power Purchase Cost Adjustment (FPPCA) at the end
of the respective year.
4.9.4.6 On the basis of above average price of coal and average price of oil and as per
above heat value of fuel and normative parameters as specified in Schedule 9A
of the Tariff Regulations, the allowable fuel cost is shown by detailed
computation in the table at Annexure-4B to this chapter.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 44
4.9.4.7 The summarized statement of the admitted fuel cost for the power station of DPL
for the fourth control period as per admitted generation in paragraph 4.4.1 above
is given hereunder:
Power Station As admitted
Total fuel cost (Rs. in Lakh) 2014 – 2015 2015 – 2016 2016 – 2017
DPL Unit - VI 13757.51 13757.51 13757.51 DPL Unit - VII 36769.73 36769.73 36769.73 DPL Units - VIII 15841.30 31658.53 31658.53
Total 66368.54 82185.77 82185.77
4.9.4.8 The admitted cost of power purchase from WBSEDCL is Rs. 11260.00 lakh for
2014 – 2015. The admitted costs of power purchase of Rs. 12380.00 lakh for
2015 – 2016 and Rs. 13620.00 lakh for 2016 - 2017 are as per the rate projected
by WBSEDCL. Energy purchase rates from WBSEDCL are 563 paise / unit, 619
paise / unit and 681 paise / unit for 2014 – 2015, 2015 – 2016 and 2016 – 2017
respectively.
4.10 Energy charge for 2014 – 2015 of the power station of DPL now stands as
follows:
Year Fuel Cost (Rs. in Lakh)
Ex-bus Generation MU Energy Charge Paise/ kWh
2014 – 15 66368.54 3241.806 205
4.11 However, if the total generation in any year is less than the gross generation
shown in this order, the matter will be given due consideration by the
Commission in the APR and/or FPPCA for the concerned year. In case of any
major breakdown of any unit resulting in forced shut down of that unit over one
month, the targeted generation will be revised in APR and/or FPPCA after taking
normative PLF and other norms of different operational parameters as specified
in the Tariff Regulations for that unit into consideration.
Tariff Order of DPL for the year 2014 – 2015
ANNEXURE 4A
West Bengal Electricity Regulatory Commission 45
SOURCE / GRADE OF COAL QUANTITY (%) UNIT PRICE IN
RS / TONNEPRICE X QUANTITY
IN RSHEAT VALUE IN KCAL/KG
QUANTITY X HEAT VALUE
ECL - G3 0.009 5685.80 51.17 6200.00 55.80ECL - G4 0.035 5121.72 179.26 5600.00 196.00ECL - G5 0.049 4044.27 198.17 4940.00 242.06ECL - G6 0.028 2352.03 65.86 4940.00 138.32ECL - G7 0.016 2081.80 33.31 4200.00 67.20BCCL - G3 0.001 5685.80 5.69 6200.00 6.20BCCL - G4 0.001 5121.72 5.12 5600.00 5.60BCCL - G5 0.001 4044.27 4.04 4940.00 4.94BCCL - G7 0.027 2081.80 56.21 4200.00 113.40BCCL - G8 0.031 1879.19 58.25 3360.00 104.16BCCL - G9 0.028 1498.77 41.97 3360.00 94.08BECML - G6 0.270 2352.03 635.05 4940.00 1333.80MCL - G9 0.037 1610.26 59.58 3360.00 124.32MCL - G11 0.048 1210.90 58.12 2400.00 115.20MCL - G11 0.247 1210.90 299.09 2400.00 592.80MCL - G13 0.172 1075.79 185.04 1300.00 223.60TOTAL 1.000 1935.93 3417.48
1935.93531.6
2467.533417.48
TOTAL LANDED COST IN RS=
TOTAL PROJECTED COAL COST IN RS =
Projected Coal Price and Heat Value of DPL for the year 2014 - 2015
TOTAL PROJECTEDTRANSPORT COST IN RS =
AVERAGE UHV OF COAL =
Tariff Order of DPL for the year 2014 – 2015
ANNEXURE 4B FUEL COST DETERMINATION OF DPL
West Bengal Electricity Regulatory Commission 46
UNIT VI UNIT VII UNIT VII TOTAL UNIT VI UNIT VII UNIT VIII TOTAL UNIT VI UNIT VII UNIT VIII TOTAL1 Generation MU 578.160 2102.400 876.666 3557.226 578.160 2102.400 1752.000 4432.560 578.160 2102.400 1752.000 4432.560
2 Rate of Auxiliary Consumption % 10.00 8.50 9.00 10.00 8.50 9.00 10.00 8.50 9.00
3 Auxiliary consumption MU 57.82 178.70 78.90 315.42 57.82 178.70 157.68 394.20 57.82 178.70 157.68 394.204 Ex-bus generation MU 520.34 1923.70 797.77 3241.81 520.34 1923.70 1594.32 4038.36 520.34 1923.70 1594.32 4038.365 Station Heat rate KCAL/KWH 3100.00 2345.00 2425.00 3100.00 2345.00 2425.00 3100.00 2345.00 2425.006 Total heat required (1 x 5) M. Kcal 1792296.00 4930128.00 2125915.05 8848339.05 1792296.00 4930128.00 4248600.00 10971024.00 1792296.00 4930128.00 4248600.00 10971024.00
7 Specific Oil Consumption rate ml/kwh 2.75 1.00 1.00 2.75 1.00 1.00 2.75 1.00 1.00
8 Oil Consumed (1 x 7) KL 1589.940 2102.400 876.666 4569.006 1589.940 2102.400 1752.000 5444.340 1589.940 2102.400 1752.000 5444.3409 Average GCV of oil Kcal/lit 9200.00 9200.00 9200.00 9200.00 9200.00 9200.00 9200.00 9200.00 9200.00
10Heat generated from oil (8x9/1000) M Kcal 14627.45 19342.08 8065.33 42034.86 14627.45 19342.08 16118.40 50087.93 14627.45 19342.08 16118.40 50087.93
11Heat generated from coal (6-10) M Kcal 1777668.55 4910785.92 2117849.72 8806304.19 1777668.55 4910785.92 4232481.60 10920936.07 1777668.55 4910785.92 4232481.60 10920936.07
12 Heat value of Coal Kcal/Kg 3417.48 3417.48 3417.48 3417.48 3417.48 3417.48 3417.48 3417.48 3417.48
13 Coal required [(11/12)x1000] MT 520169.41 1436961.13 619710.93 2576841.47 520169.41 1436961.13 1238480.28 3195610.82 520169.41 1436961.13 1238480.28 3195610.82
14Coal required at 0.50%Transit loss MT 522783.33 1444182.04 622825.06 2589790.42 522783.33 1444182.04 1244703.80 3211669.17 522783.33 1444182.04 1244703.80 3211669.17
15 Average Price of Oil Rs/KL 53943.27 53943.27 53943.27 53943.27 53943.27 53943.27 53943.27 53943.27 53943.2716 Average Price of coal Rs/MT 2467.53 2467.53 2467.53 2467.53 2467.53 2467.53 2467.53 2467.53 2467.53
17 Cost of oil [(8x15)/100000] Rs(lakh) 857.67 1134.10 472.90 2464.67 857.67 1134.10 945.09 2936.86 857.67 1134.10 945.09 2936.86
18 Cost of Coal [(14x16)/100000] Rs. (lakh) 12899.84 35635.63 15368.40 63903.87 12899.84 35635.63 30713.44 79248.91 12899.84 35635.63 30713.44 79248.91
19 Total Cost of Fuel (17+18) Rs. (lakh) 13757.51 36769.73 15841.30 66368.54 13757.51 36769.73 31658.53 82185.77 13757.51 36769.73 31658.53 82185.77
As admitted 2016 - 2017
As admitted Sl No PARTICULARS UNIT2015 - 2016 2014 - 2015 As admitted
Tariff Order of DPL for the year 2014 – 2015
CHAPTER – 5 FIXED CHARGES
West Bengal Electricity Regulatory Commission 47
5.1 An examination of the projected fixed charges claimed by the DPL for the years
2014 – 2015, 2015 – 2016 and 2016 – 2017 of the fourth control period under
different heads for its power station and distribution system has been taken up in
this chapter.
5.2 Project Cost:
5.2.1 Project cost of Unit VII:
The project cost of Unit VII of DPL has not yet been finalized by the Commission.
In pursuance of the directives given by the Commission in the tariff order for
2007-08 and also through subsequent letters, DPL has submitted some
documents and clarifications and some information are yet to be submitted. On
the basis of those documents and clarifications furnished and to be furnished by
DPL, the Commission is examining the project cost of Unit VII of DPL. Pending
such examination, the Commission, during determination of Aggregate Revenue
Requirements (ARR) for the years 2014 – 2015, 2015 – 2016 and 2016 – 2017,
has considered the project cost of Unit VII, as indicated by DPL in its tariff
application, provisionally and taken the following decisions:
(i) The report as per regulation 2.8.1.4.13 of the Tariff Regulations has not
yet been submitted by DPL. In terms of the aforesaid regulation,
therefore, 5% of the provisional project cost amounting to Rs. 6750.00
lakh is being withheld for the time being.
(ii) There are other elements in the project cost of Unit VII, which will be
finalized by the Commission on submission of relevant data and for which
additional deduction from the provisional project cost of Unit VII could
have been made at this stage. The Commission, however, has not made
any deduction on these accounts at this stage and the same will be
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 48
considered during finalization of the project cost of Unit VII by the
Commission.
(iii) Withholding of 5% of the provisional project cost as per clause (i) above
and thereby reduction of the provisional project cost would have effect on
different fixed charge components viz. depreciation, interest, return on
equity and reserve for unforeseen exigencies. However, while
determining the ARR for DPL for 2014 – 2015, 2015 – 2016 and 2016 –
2017, though deduction has been made from the allocation under
depreciation head, no deduction has been made from the allocation under
advance against depreciation head; rather the allocation under this head
has been increased by the amount disallowed under depreciation head
for 2014 – 2015, 2015 – 2016 and 2016 – 2017, subject, however, to the
ceiling as specified in the Tariff Regulations, in order to facilitate loan
repayments as per schedule. Similarly, in order to facilitate interest
payment, no reduction in the allocation under interest head has been
effected. As reserve for unforeseen exigencies is primarily to protect the
interest of the consumers, no reduction in allocation under this head also
has been effected. These allowances under the heads advance against
depreciation, interest and reserve for unforeseen exigencies, however,
will not be detrimental to the interest of the consumers as the total
withheld amount under clause (ii) above and proportionate disallowance
in the head ‘return on equity’ due to reduction in the provisional project
cost as per clause (i) above will be sufficient to take care of the
allowances mentioned above. These allowances under the head
‘advance against depreciation, interest and reserve for unforeseen
exigencies’ shall not be construed as approval of the Commission to the
project cost applied for.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 49
(iv) The total withheld amounts as per clause (i) to clause (iii) above are
Rs. 313.88 lakh, Rs. 313.88 lakh and Rs. 313.88 lakh for the years 2014
– 2015, 2015 – 2016 and 2016 – 2017 respectively.
(v) As mentioned earlier, the project cost of Unit VII of DPL is under
consideration of the Commission. In case of any disallowance in the
project cost of Unit VII by the Commission, the withheld amounts as
mentioned in clause (iv) above shall be adjusted with the reduction in
project cost, if any, and corresponding impact on tariff shall accordingly
be adjusted in the APR / truing up exercise.
5.2.2 Project cost of Unit VIII:
COD of unit VIII was projected as 01.07.2014. DPL, accordingly, proposed all
costs relating to unit VIII. Considering present development, as stated in
paragraph 5.2.1 of this order, the Commission has decided to estimate the fixed
costs related to unit VIII considering COD on 01.10.2014. Project cost of unit VIII
has not yet been finalized. The Commission accorded second stage approval of
the investment proposal of DPL for unit VIII with an estimated project cost of Rs.
169968.00 lakh. Accordingly, for the reasons stated in paragraph 5.2(i) above,
5% of the estimated project cost of unit VIII, amounting to Rs. 8498.40 lakh, is
being kept withheld for the time being. Commission considers deductions of
different costs in respect of unit VIII, in line with the considerations given in
paragraph 5.2.1(iii) above in respect of unit VII. The total withheld amounts for
unit VIII, as per above are Rs. 74.98 lakh, Rs. 149.96 lakh and Rs. 149.96 lakh
for the years 2014 – 2015, 2015 – 2016 and 2016 – 2017 respectively.
5.3 Employees’ cost:
5.3.1. DPL has proposed its employees’ cost keeping Man / MW ratio as per norm
specified in the Tariff Regulations in respect of the regular employees excluding
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 50
that of centrally maintained expenses. In its application, DPL has highlighted the
revision of pay structure effective from 1st
5.3.2. In the table below, the proposal of DPL towards employee cost for 2014 – 2015,
2015 – 2016 and 2016 – 2017 of the fourth control period, submitted under forms
1.12, 1.15 and 1.17 of the tariff petition vis-à-vis actual expense during 2012 –
2013, is depicted. It is observed that DPL proposed a considerable increase in
employee cost and has requested the Commission for allowing the same.
April, 2007 based upon which its
employee cost was determined. The impact of half yearly increase in DA every
year (16%), annual increment (3%) on basic pay and other allowances @ 10%
every year as well as increase in field and night allowances have been
considered by DPL while estimating the future expenses. DPL has also
highlighted the increase in the amount of gratuity limit from Rs. 3.50 lakh to Rs.
10.00 lakh, sizeable increase in amount of employee cost towards statutory
liabilities under AS-15 at revised pay structure. The employee cost of service
department and central workshop allocated to it in pre-determined ratio has also
been considered by them. The employees engaged in operation of unit no. III to
V have been proposed to be suitably redeployed in other existing units including
unit VIII. They have considered only 50% of the Man / MW ratio of unit no. VIII
and rest 50% to be filled up through fresh induction or redeployment to be
assessed after completion of decommissioning of unit III, IV & V.
Rs. in Lakh
Particular Actual as per
audited accounts
2012 - 2013
As Proposed by DPL
Base year
2013 - 14
Increase over
previous year
2014-15 Increase
over previous
year 2015-16
Increase over
previous year
2016-17 Increase
over previous
year Employee cost of regular employees 7031.99 7711.02 9.66% 8432.05 9.35% 9027.64 7.06% 9954.22 10.26%
Share of employee cost of Service Dept. & Central Workshop
3401.48 3729.87 9.65% 4078.02 9.33% 4364.92 7.04% 4811.12 10.22%
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 51
Projections for Unit No. VIII 0.00 0.00 - 828.74 - 1216.16 46.75% 1340.98 10.26%
Share of employee cost of Service Dept. & Central Workshop
0.00 0.00 - 69.04 - 101.31 - 111.70 -
Total 10433.47 11440.89 9.66% 13407.85 17.19% 14710.03 9.71% 16218.02 10.25%
5.3.3. Against the above submissions of DPL, the Commission observed as below:
i) As per annual report and accounts for 2012 – 2013, the employee cost for
power plant including terminal benefits and Directors’ fees and expenses
and net of capitalization for 2012 – 2013 was Rs. 7040.71 lakh (Rs.
7031.99 lakh + Rs. 8.72 lakh). DPL has estimated the employee cost for
2013 – 2014 for power plant as Rs. 7711.02 lakh, which is 9.50% higher
than that of actual expense for 2012 – 2013. The Commission has viewed
that latest five DA (Dearness Allowance) increase in Central Government
during 01.07.2012 to 01.07.2014 is 7%, 8%, 10%, 10% and 7%.
Considering the impact of two instalments each at 10% of basic pay and
annual increment @ 3% on basic pay, the annual increase in employee
cost comes to 10.80% [{(3x8% + 6x18% + 3x28% + 12x3%) / 12} x 1/2} +
(3%x1/2x0.2)] [basic pay in the salary is 50% considering existing DA @
80% of basic pay and HRA @ 20% of basic pay in the salary] for the year
2013 – 2014 over the employee cost incurred during the year 2012 –
2013 and the estimated expenses come to Rs. 7801.11 lakh. Thus, the
Commission considers the estimated employee cost for power plant for
2013 – 2014 as Rs. 7711.02 lakh as projected by DPL. The last D.A.
increase announced by the Central Government w.e.f. 01.07.2014 is 7%.
Considering the impact of D.A. instalments @ 10% w.e.f. 01.01.2014 and
@ 7% w.e.f. 01.07.2014 and considering the half yearly D.A. increase @
7% in future and annual increment @ 3% on basic pay, annual increase
in employee cost for the year 2014 – 2015 comes at 9.07% [{(3x10% +
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 52
6x17% + 3x24% + 12x3%) / 12} x 1/2.27} + (3%x1/2.27x0.2)] (basic pay
in the salary is 1/2.27 considering the D.A. @ 107% of basic pay and
HRA @ 20% of basic pay in salary) over the estimated employee cost for
2013 – 2014. The Commission considers the increase in employee cost
for the year 2014 – 2015 over the estimated employee cost for 2013 –
2014 @ 9.07%. The estimated employee cost for power plant for the year
2014 – 2015, thus works out at Rs. 8410.41 lakh and the Commission
admits the same. The Commission also considers an annual increase in
employee cost @ 9.07% for the years 2015 – 2016 and 2016 – 2017 and
the amounts work out at Rs. 9173.23 lakh and Rs. 10005.25 lakh
respectively.
ii) However, no employee cost has been considered for unit VIII in 2014 –
2015, 2015 – 2016 and 2016 – 2017 separately as the employees of the
existing units III to V, which have already been decommissioned w.e.f.
01.04.2014 vide Order No. 103-PO/0/VI/5S-23/2009 dated 12.09.2014
issued by the Government of West Bengal, Department of Power & Non-
Conventional Energy Sources, will be deployed in unit VIII. If any
additional employment is required, DPL shall justify the same when they
claim for that in APR for the respective years. DPL may claim any
variation in employee cost in APR for the respective years as per
provisions of the Tariff Regulations.
iii) Allowable manpower of unit III, IV & V, already decommissioned,
considering normative Man / MW ratio as specified in the Tariff
Regulations, is 808 nos. The man power requirement for unit VII (250
MW) as per normative Man / MW ratio is 300 nos. (1.2x250) and
accordingly, the surplus manpower shall be deployed in unit VIII first and
the balance in other units VI, VII and distribution. The Commission
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 53
decides not to allow any separate employee cost for unit VIII as proposed
by DPL.
iv) In the submission DPL has stated that 50% of man / MW ratio of unit VIII
is considered for fresh induction and rest 50% for fresh induction or
redeployment after completion of decommissioning of units III to V. DPL
has not given any reason for such proposed fresh induction for unit VIII.
In this context, it is observed that the units III to V have already been
decommissioned as stated above. It is also seen that the surplus man
power as per man / MW ratio for unit III to V is much more than the
required man power for unit VIII. Thus, the Commission does not consider
the proposal of DPL for fresh induction for unit VIII. DPL shall give details
of the manpower employed / engaged in the units from the surplus
employees arising out of decommissioning of unit III to V in their APR
application for 2014 – 2015.
v) Thus, the employee cost as admitted by the Commission for the power
plant are as shown below:
Rupees in Lakh
Sl No Particular
As admitted by the Commission
2014-15 2015-16 2016-17
1 Unit – VI 4532.06 4943.11 5391.45
2 Unit - VII 1737.53 1895.12 2067.02
3 Unit - VIII 0.00 0.00 0.00
4 Sub total of Generation (4=1+2+3) 6269.59 6838.23 7458.47
5 Distribution 2140.82 2335.00 2546.78
6 Total (6=4+5) 8410.41 9173.23 10005.25
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 54
(iv) In addition to above, the share of the employee cost against centrally
maintained expenses has also been determined by the Commission and
has been shown separately on the basis of the proposal of DPL
furnished in Form 1.17(h). Centrally maintained expenses have been
segregated by the Commission between distribution and generation
head on the basis of ratio of the employee costs of generation and
distribution of regular employees as per the allocation submitted by DPL.
It is observed that 8.33% of the employee cost of power-stations is the
employee cost for centrally maintained expenses for DPL. In line with
that the Commission has admitted 8.33% of the employee cost of power
station of DPL for centrally maintained expenses for generation wing.
DPL’s distribution business being spread over a small area and major
part of its electricity consumers are bulk in nature in HT level, for DPL’s
distribution business a slightly higher rate of 10% of employee cost of
distribution wing has been admitted as centrally maintained expenses for
DPL’s distribution wing. Accordingly, the expenses for employee cost
against centrally maintained expenses as admitted by the Commission
are shown in the following table.
Rs. in lakh
Sl. No Particular As admitted by the Commission
2014-15 2015-16 2016-17 1 Units – VI 377.52 411.76 449.11 2 Units –VII 144.74 157.86 172.18 3 Unit - VIII 0.00 0.00 0.00 4 Sub total of Generation (3=1+2) 522.26 569.62 621.29 5 Distribution 214.08 233.50 254.68 6 Total (5=3+4) 736.34 803.12 875.97
5.3.4. If there be any variation in the admitted amount, DPL shall furnish relevant
information and supporting documents in this respect with the application for
APR for the concerned year and the same will be considered for adjustment in
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 55
APR to the extent it is found fit by the Commission. Along with the information
and documents as mentioned above, DPL shall, in the application for APR for the
concerned year, also furnish the information in the format given in Form 1.17(h)
of Annex – 1 to the Tariff Regulations indicating details in respect of both regular
and contracted employees.
The above information shall also show the expenditure of own employees and
employees on contract in regular establishment separately. Interest payment on
Contributory Provident Fund and General Provident Fund shall not be considered
as it is not permissible unless it is explicitly established that in spite of investment
of such fund in a prudent manner and management of fund efficiently, there is
shortfall in accrued interest to discharge the liability of statutory interest as laid
down in concerned laws. Henceforth, DPL shall show the production incentive
separately in its accounts under generation, distribution and centrally maintained
expenses heads.
5.3.5. In paragraph 4.34 of the tariff order dated 17.12.2012 for the year 2011 – 2012
and 2012 – 2013 in case no. TP-49/11-12 and in paragraph 2.3.7 of the order
dated 09.09.2013 in case no. APR-34/12-13 relating to APR for the year 2011 –
2012, DPL was directed to furnish relevant information and supporting
documents regarding basis of apportionment of centrally maintained expenses in
APR 2012 – 2013 application to establish their claim of apportionment. DPL, in
their application of APR for the year 2012 – 2013, did not furnish the information
and documents towards expenses in the centralized services particularly as
directed by the Commission in order to justify / establish their claim for
proportionate cost of centralized services under the head ‘employee cost’. DPL
have submitted in their brief of submission of APR application for the year 2012 –
2013 that they have not yet been able to physically segregate the centrally
maintained expenses from power plant business and the same was under
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 56
process pending apportionment of the centrally maintained expenses to the
power plant business under the head ‘employee cost’ in order to place a more
clear cut accountable system. DPL has submitted the break-up of the expenses
claimed for power plant and proportionate cost of centralized services as per
format 1.17(h) of Annexure – I. However, as required under the Form, the
number of employees engaged both in regular services and contractual services
for generating units have not been found available, in the absence of which it
could not be confirmed whether the same are as per the Man/MW ratio stipulated
in the Tariff Regulations. Nevertheless, DPL is yet to justify / establish the basis
of apportionment of cost of centralized services under the head ‘employee cost’
as claimed by them inspite of specific directions in this regard from time to time.
5.3.6. DPL is directed to submit break-up of the employees engaged both in regular
services and contractual services for their different generating units as per the
format 1.17(h) of the Tariff Regulations. DPL is also directed to submit the basis
of apportionment of employee cost of centralized services in order to justify their
claim under this head.
5.4 Coal and Ash Handling Expenses:
5.4.1 DPL has claimed Rs. 1826.30 lakh, Rs. 2108.86 lakh and Rs. 2214.31 lakh for
2014 – 2015, 2015 – 2016 and 2016 – 2017 respectively towards coal and ash
handling expenses. The proposal of DPL has been analyzed by the Commission
and found that said expenditure as projected are very high in comparison to the
actual expenditure of Rs. 893.72 lakh vis-à-vis actual generation of 1819.206 MU
during previous year i.e., 2012 - 2013 and the projected enhanced generation.
5.4.2 DPL has justified the increase in expenditure under the head mainly on the
following grounds:
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 57
i. Huge financial involvement for transportation of excavated ash in the
ensuing years with a view to comply with MOEF guidelines.
ii. High quantity of ash generation due to increased level of generation.
iii. Non-availability of sufficient high grade coal of ECL & MCL leaving to high
generation of ash.
iv. DPL has projected a gross generation level of 3995.76 MU, 4432.560 MU
and 4432.560 MU during the years 2014 – 2015, 2015 – 2016 and 2016 –
2017 respectively.
5.4.3 The Commission, after due consideration of the justification advocated by DPL
and in view of the fact that coal and ash handling expenses are uncontrollable in
nature and are directly related with high level of generation, admits the claim of
DPL as proposed by them in respect of Unit VI & VII. For unit VIII, proportionate
claim has been considered for 2014 – 2015 due to shifting of COD from July,
2014 to October, 2014. However, after submission of APR petitions at the end of
concerned years, the actual expenditure vis-à-vis actual generation will be
viewed separately by the Commission for adjustment of allowable expenses
under this head.
Coal and Ash Handling Expenses Rupees in Lakh Sl. No Particular As admitted by the Commission
2014-15 2015-16 2016-17 1 Unit - VI 393.45 413.12 433.78 2 Unit - VII 867.40 910.77 956.31 3 Unit - VIII 376.97 784.97 824.22 4 Total Generation ( 4 = 1 + 2 + 3 ) 1637.82 2108.86 2214.31
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 58
5.5 Water charges:
5.5.1. DPL meets processed water supply requirements for its generating station by
taking supply from its sister water plant unit. The inter-plant transfer rate for such
processed water during 2012 – 2013 was Rs. 6.50 per KL. The actual amount of
expenditure during 2012 – 2013 on this head was Rs. 1917.93 lakh.
5.5.2. DPL has projected expenditures of Rs. 6076.08 lakh, Rs. 6758.52 lakh and Rs.
6758.52 lakh for the years 2014 – 2015, 2015 – 2016 and 2016 – 2017
respectively towards water charges. They have submitted a detailed calculation
of water charges with respect to the projected generation during the ensuing
year. DPL has proposed a revision of rate of processed water to Rs. 15.00 per
KL from earlier rate of Rs. 6.50 per KL on the following grounds:
i) DVC from whom water supply is sourced by DPL, has increased the rate
of water supply to Rs. 28.41 per thousand gallon from earlier rate of Rs.
5.20 per thousand gallons with effect from 1st
ii) Actual rate of industrial water has gone upto Rs. 20.00 per KL and is
likely to be enhanced further.
October, 2012.
iii) Non-charging of water at market rate is becoming unviable by its sister
water plant unit.
iv) The last revision of inter-plant transfer rate of industrial water was made
by DPL from 1.10.2013 @ Rs. 15.00 KL.
5.5.3 DPL has, however, not submitted any copy of the Government order in respect of
interplant transfer rate of industrial water with effect from 1.10.2013. After going
through the facts stated by DPL as mentioned in the foregoing paragraphs and
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 59
also the fact that DPL has not submitted any Government order in support of the
claim of revision of interplant transfer rate of industrial water, the expenditure on
water charges being uncontrollable in nature, the Commission admits the
projected expenditures for the years under fourth control period considering rate
of inter-plant transfer @ Rs. 6.50 per KL for the projected generation level in
respect of Units VI & VII. For unit VIII, proportionate amount has been considered
based on COD from 01.10.2014. However, on submission of APR petitions along
with the copy of the Government order regarding interplant transfer rate for
industrial water, the actual expenditure vis-à-vis actual generation will be viewed
separately by the Commission for adjustment of allowable expenses under this
head. Admitted Water charges allocated to generation function of DPL, is given
hereunder:
Rupees in Lakh Water charges / Cess
Sl. No Particular
As admitted by the Commission 2014-15 2015-16 2016-17
1 Unit - VI 533.64 533.64 533.64 2 Unit - VII 1298.23 1298.23 1298.23 3 Unit - VIII 541.38 1081.86 1081.86 4 Total (6=4+5) 2373.25 2913.73 2913.73
5.5.4 It is also noticed by the Commission that DPL has not submitted any detailed
calculation of inter-plant transfer rate of Rs. 15.00 per KL of processed water
indicating both variable cost and fixed costs components of the rate so arrived.
The Commission, accordingly, directs that details of calculation of inter-plant
transfer rate of water at Rs. 15.00 per KL should be submitted by DPL along with
the APR petition of 2014 – 2015.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 60
5.6 Operation and Maintenance (O&M) Expenses, Rates & Taxes and Insurance:
5.6.1. O&M Expenses for Generation:
DPL has proposed decommissioning of unit III, IV and V in phases during 2013-
14. As far as O&M expenses of generation function is concerned, the
Commission goes in accordance with the norms specified in schedule 9A of the
Tariff Regulations for Units VI and VII and considering proportionate allowable
cost for Unit VIII for 2014 – 2015 based on COD in October, 2014. Accordingly,
the Commission admits the O & M expenses for generation function of DPL for
the years 2014 – 2015, 2015 – 2016 and 2016 – 2017, as given below:
Rupees in Lakh Operation and Maintenance Expenses for Generation Function
Unit 2014 – 2015 2015 – 2016 2016 – 2017
Unit VI (110 MW) 1824.90 1988.80 2168.10 Unit VII (300 MW) 2115.00 2241.00 2376.00 Unit VIII (250 MW) 651.25 1380.00 1462.50 Total O&M Expenses 4591.15 5609.80 6006.60
5.6.2. O&M Expenses for Distribution function, Rates & Taxes and Insurance:
The Commission has made prudent analysis of the charges claimed by DPL
under the following heads
(i) different sub-heads of O&M expenses for distribution function;
(ii) Rates and Taxes charges; and
(iii) Insurance charges.
While determining fixed charges on such heads for the fourth control period
(2014-15, 2015-16 & 2016-17) the following considerations have taken place.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 61
5.6.2.1 DPL has referred the current inflation rate of 9 %. Commission finds no merit in
considering the current inflation rate for estimate purpose when such estimate
will be applicable for thirty six months. The Commission instead of considering
the inflation rate of 9% in general for projection purpose decides to proceed in a
further rational manner by following a methodology that has been applied for all
distribution licensees subject to case specific differences in some cases to
protect the interest of the consumers as far as possible after meeting
requirement of reasonable tariff determination to provide end of justice to all of
the concerned stakeholders as deemed fit by the Commission. Moreover by the
time of processing the tariff application by Commission the inflationary trend
shows downward direction. The Commission decides to determine projected
inflation rate and the resultant escalation rate in view of such inflation rate as
detailed out in subsequent paragraphs.
Commission observed that Central Electricity Regulatory Commission based on
a hybrid index of WPI (Wholesale Price Index) & CPI (Consumer Price Index)
has observed an annual inflation trend of 8.35% while fixing the norms of O&M
expenses in Central Electricity Regulatory Commission (Terms and Conditions of
Tariff) Regulations, 2014 (hereinafter refer to as ‘CERC Tariff Regulations’) for
central sector utilities for the period 2014-2019. This inflation trend of 8.35 % is
computed based on five year average of WPI and CPI indices for FY 2008-09 to
FY 2012-13 considering 60% and 40% weightage on WPI and CPI respectively.
However, while fixing norms of O&M cost (which includes employee cost also)
the annual escalation rate on O&M expenses during the period 2014-2019 has
been considered as 3.32% for A.C. transmission system as per the statement of
reasons of the CERC Tariff Regulations for the said period. This 3.32% is the
110% of the actual Compounded Annual Growth Rate (CAGR) (3.02%) of O&M
expenses for A.C. transmission system during the period 2008-09 to 2012-13
computed on the basis of 70% weightage on actual O&M cost of per bay of sub-
station and 30% weightage on actual O&M cost of per CKM transmission line.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 62
Taking the above mentioned principle adopted by CERC as a guideline
Commission also decides to find out a reasonable annual escalation rate for DPL
for all sub-heads of O&M expenses for distribution function, rates & Taxes and
insurance with certain deviation based on certain reasons as explained below:
a) The control period is of three years and as more than 6 months of 2014 has
already passed thus the inflation trend between October, 2011 and
September 2014 has been computed where weightage has been given to
WPI & CPI at the ratio of 60:40 in line with the norms fixation methodology
under CERC Tariff Regulations. This is being done in order to capture the
realistic trend of 2014-15 as far as possible so that projection for fourth
control period can have better accuracy. Accordingly based on the WPI
numbers and CPI numbers as available in the website of Economic Advisor
of GOI for WPI and Labour Bureau of GOI for CPI the computed inflation
trend for the above 36 months are given in the following table 5.6.2.1-I.
Table- 5.6.2.1-I TREND OF INFLATION RATE FOR THE PERIOD OCTOBER 2011 TO SEPTEMBER 2014
Average inflation rate as per WPI from October 2011 to September 2014 6.62 Average inflation rate as per CPI from October 2011 to September 2014 9.15 Average inflation rate as per WPI + CPI (60:40) from October 2011 to September 2014 7.63 Note : For detail data at Annexure – 5A may be seen
b) Different sub heads under O&M expenses, rates and taxes and insurance are
effected by inflationary trend but at different degrees depending on the
characteristics of such head or sub-head. In this context two recognized
inflationary trends used in the country are WPI index and CPI index. Along
with this two types of inflationary rate for power sector another third type
inflationary rate used by the Commission is based on hybrid index (WPI+CPI)
as explained in paragraph (a) above. In table-2 in Annexure-5B the basis of
inflationary rate considered for such heads and sub-heads of expenditure are
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 63
given. In this context it is to be noted that all these heads of expenditure are
treated as heads under O&M function of CERC tariff regulations. Accordingly
the above inflation rate as given in the table above are used for applicability
in giving escalation in 2015-16 & 2016-17 with respect to the previous years’
admitted expenditure to find out the admitted expenditure of the referred
heads in those years. Thus the inflation rate considered for tariff computation
is as per the following table 5.6.2.1- II.
Table 5.6.2.1-II
INFLATION TRENDS Financial Years CPI WPI Combined WPI &
CPI (60 : 40) Remarks
2010-11 10.53 9.57 9.96 Actual 2011-12 8.42 8.96 8.74 Actual 2012-13 10.43 7.36 8.59 Actual 2013-14 9.72 5.98 7.47 Actual 2014-15 6.81 4.78 5.59 As per 6 months trend 2015-16 9.15 6.62 7.63 As per Table 5.6.2.1-I & as
explained above 2016-17 9.15 6.62 7.63 2011-12 to 2013-14 9.52 7.43 8.27 Averaged on annual basis 2010-11 to 2013-14 9.78 7.97 8.69
Note : For detail data at Annexure – 5A may be seen
In 2014-15 as the trend is downward than the value under Table 5.6.2.1-II
and the time already passed in 2014 – 2015 has covered fifty percent of the
period, such value has been considered with due insulation against
uncertainty wherever required through providing necessary certain additional
float.
c) For finding out the expenditure to be admitted by the Commission, the
estimated expenditures of 2013-14 submitted by DPL are scrutinized by the
Commission so that overestimated value can be rationalized to a reasonable
extent. This is being done as otherwise the existence of overestimated
expenditure for 2013-14 may result into unreasonably higher admitted
amount for fourth control period as because the computation for projection of
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 64
expenditure for 2014-15 to 2016-17 are done by applying the annual
escalation rate over the estimated figure of 2013-14. On the estimated value
as provided by DPL for 2013-14 Commission finds that against some
elements the estimation of expenditure seems to be on higher side as it has
been noticed that the estimated expenditure for some elements in 2013-14 as
made by DPL has a sharp increase which does not commensurate with the
previous trend even after considering the inflationary trend and impact of
business volume increase in a same way as has been considered for other
distribution licensee. The Commission cannot accept such over estimation.
In any year this deviation can occur for any item of expenditure but it cannot
be considered as a trend for future projection. The estimated expenditure of
elements which are identified to be overestimated by DPL for 2013-14 are on
the heads of repair & maintenance, audit fees, rates and taxes and
insurances. Thus for realistic projection for 2013 - 2014 the impact of
business volume increase has been given as 2% on items which are
sensitive to Consumer strength moderately. Such impact has been
considered as 1% where the expenditure of item is sensitive to distribution
line length. In such case Commission has done its own estimation based on
the Table-1 of Annexure–5B by applying its prudence which is explained
below item wise.
i) Commission estimates the expenditure for 2013-14 by analyzing the past
trend of expenditure on Repair & Maintenance Expenditure head during
the first two year of the third control period as is being shown in the
following table.
Particulars 2011-12 2012-13 R&M expenditure for distribution as proposed in tariff application (Rs Lakh) 1743.76 1859.01 Actual expenditure as per annual accounts/APR (Rs Lakh) 1091.29 1075.32
Actual expenditure w.r.t proposed amount in tariff application in % 62.58 57.84
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 65
From the above table it is seen that DPL’s projection in past is highly over
projected. In fact the average rate of actual expenditure during first two
years of third control period with respect to DPL’s own projection is
60.21%. Considering this rate the commission hence estimated the
expenditure for 2013-14 as Rs 1190.24 lakh.
ii) The estimated expenditure of Audit fees by DPL is slightly high in 2013-
14. Thus keeping the increasing trend from 2010-11 to 2012-13 and rate
of increase in the said period, the estimated expenditure for 2013-14 as
determined by Commission is Rs 0.68 Lakh.
iii) The estimated expenditure of rates & taxes for DPL is slightly high in
2013-14. Thus Commission estimates the expenditure of 2013-14 by
giving inflationary impact on actual value of 2012-13 along with additional
impact of 1% due to business volume increase as is being done for other
distribution licensee for the same period. Accordingly the estimated
expenditure by Commission on rates & taxes is Rs 4.455 lakh.
iv) The past trend of expenditure on insurance heads for DPL is highly
fluctuating and no significant trend can be established. Thus the average
expenditure of Rs 85.96 lakh for the period 2009-10 to 2012-13 is
considered by the Commission as estimated expenditure for 2013-14.
All the above estimated expenditure for 2013-14 by the Commission will be
used by the Commission only for the projection of expenditure during ensuing
years of fourth control period.
d) Where the past CAGR of expenditure of any above referred elements for any
period between 2010 – 2011 and 2013 – 2014 which has been considered as
basis for escalation rate for future projection for the fourth control period and
is lesser than the corresponding inflationary rate of the same period as
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 66
provided in table 5.6.2.1-II in such case in line with CERC’s principle 110%
(an additional 10% margin over actual growth rate) of such growth rate is
considered as the annual escalation rate for 2014-15 to 2016-17 for the
following reasons.
i) To ensure the interest of different stakeholders in a more better way from
the point of view of availability considerations of the network asset and
different services
ii) also to provide a comfort to DPL in carrying out O&M of the assets by
extending an additional insulation against uncertainty arising out of
increased expenditure for any unforeseen reason.
It is to be noted that for the said period the expenditure considered for 2013-
14 is estimated one by the Commission and for 2010-11, 2011-12 & 2012-13
actual expenditure has been taken. In general, the non zero least positive
value out of the three periods (2010-11 to 2013-14, 2011-12 to 2013-2014
and 2012-13 to 2013-2014) is considered for projection of estimated
expenditure of heads of any year under the fourth control period. The CAGR
for certain period is also considered where Commission finds that such
decision will provide more rationale and better accuracy in the projected
admitted cost.
e) Where the projected expenses by DPL is less than the estimated value of
2013-14 by the Commission and also actual value of 2012-13 in such case
no escalation is being allowed for fourth control period because DPL’s
projection is considered as admitted figure.
f) Where the past data shows irrational/asymmetric character in such case
Commission by applying due prudence take an appropriate escalation rate
which is discussed in relevant portions.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 67
g) Where annual escalation rate or CAGR of past period crosses the concerned
inflation rate of the said past period in such case escalation rate for projected
expenditure due to business volume increase is computed from past trend by
reducing it with the concerned inflation rate of the relevant past period and
that has been explained in the relevant portions. In such case the annual
escalation rate for 2014-15, 2015-16 and 2016-17 are as follows:
Annual Escalation Rate (%) for any ensuing year = A+ R × BGR+Ad_F
Where A = Inflation rate (%) based on CPI or WPI or hybrid
(WPI+CPI) index as applicable for the fixed charge
element.
R = Ratio of percentage annual increase in expenses in
the past period and percentage increase in
business volume parameter during the same
period.
BGR = Projected growth rate (%) for the ensuing year of
the business volume parameter to which the fixed
charge element under consideration is sensitive.
Ad_F = Additional float in % as decided by commission to
provide insulation against uncertainty in projected
inflation or business volume growth.
For such annual escalation rate calculation the annual increase (%) in
expenses as required for calculation of R is decided by the Commission by
taking the lowest positive CAGR value from among CAGR of 2013-14 (i.e.,
annual increase rate) or CAGR of 2011-12 to 2013-14 or CAGR of 2010-11 to
2013-14 subject to different aspects considering rationality or level of
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 68
asymmetric character of past data as has been explained in the relevant
portion. However, principally wherever R on computation found to be higher
than one then in such case R is considered not more than 1 as Commission
is of the opinion that rate of increase in expenses due to business volume
increase cannot surpass the rate of increase in business volume parameter
unless there is any specific reason which can be established by the licensee.
Similarly when R is found to be a value between 0.5 and 1 then also in
ensuing year annual escalation rate is further reduced by a small quantum
with an objective of gradual improvement in efficiency of the licensee in
expenditure control by utilizing different resources in a more effective
manner.
Where necessary while computing additional expenditure represented by
(R×BGR) of any element of fixed charge due to increase in business volume
that additional expenditure is modified in a reasonable and rational manner
after taking the impact of above mentioned sensitivity parameter on the
additional expenditure. Detail of such modification and any other specific
consideration are detailed out in relevant portion where each element of fixed
charge is dealt with. For controllable factor additional float of 0.5% is given to
cover any expenditure hike due to any unforeseen reasons.
h) Commission decides that for the ARR determination in the tariff order of
fourth control period the impact of increase in business volume on different
sub-heads/ heads will also be considered from the point of sensitivity of the
head/sub-heads to certain business volume parameter. For such purpose in
the business process of DPL there are two important business volume
parameters such as Distribution line length (DDL) in Circuit Kilometer (CKM)
and Consumer strength. Different elements of fixed charge elements are
sensitive to either of the above two parameters and where such element is
sensitive to consumer strength there is variation in the degree of such
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 69
sensitivity. After applying such degree of sensitivity the number of business
parameters considered in this tariff order are Distribution Line Length (DLL),
Consumer Strength in moderate degree(CSM), Consumer Strength in high
degree (CSH) and Consumer strength with lesser degree than CSM
(CSM-L). The Table 1 under Annexure 5B shows the concerned business
volume parameter sensitivity against different elements of the fixed charges.
i) DPL has projected consumer strength annually from where its annual growth
rate for 2014-15, 2015-16 and 2016-17 are 2.61%, 4.02% and 0.16%
respectively. However, for projection purpose escalation rate on consumer
strength has been considered for 2014-15, 2015-16 and 2016-17 as 2.61%,
4.02% and 4.02% respectively also as because the consumer strength
increase shown for 2016 – 2017 is very low. In absence of any projection in
distribution line length the projected annual escalation rate considered by
DPL for 2014-15, 2015-16 and 2016-17 are also considered as 2.61%, 4.02%
and 4.02% in line with the escalation rate of Consumer strength.
While projecting the above figure it has been considered that as the original
tariff application is submitted at the end of December, 2013 thus it can be
considered that the estimated data for 2013-14 will have high degree of
accuracy.
During truing up in Annual Performance Review (APR) of the above ensuing
years of 2014-15 to 2016-17 such projected distribution line length in CKM
and Consumer Strength in number as given above shall be considered as the
basis against which the expenditure has been admitted during concerned
tariff order and accordingly truing up will be taken up.
j) For computation of computed expenditure by the Commission on different
heads for 2014-15 to 2016-17 the base expenditure over which the above
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 70
escalation rates are applied has been considered on the estimated
expenditure of 2013-14 made by DPL and duly modified in some elements by
the Commission as explained in paragraph (g) above. This is being done as
the application of tariff is submitted at the end of December, 2013 and is likely
to have little inaccuracy with respect to actual expenditure or in other word
having better accuracy.
k) Based on the above principle the projected expenditure on above mentioned
different elements of fixed charges for 2014-15, 2015-16 and 2016-17 has
been computed and then compared with the claimed amount of DPL for the
said year and whichever is lowest is being admitted in this tariff-order.
5.6.2.2 O&M Expense determination for distribution function: Based on the laid
down principle in paragraph 5.6.2.1 above following different sub-heads of O&M
function are determined. In this context tables in Annexure – 5B may be referred
to for the past trend of expenditure.
a) Audit fees and Repair & Maintenance Expenditure : For these two
elements, the escalation rate that is considered for projection of expenditure
in 2014-15, 2015-16 and 2016-17 is on the basis of CAGR of the period
2011-12 to 2013-14 because other two periods under consideration has
either negative growth rate or higher growth rate. The past trend of
expenditure in third control period also shows very insignificant growth rate in
expenditure on these two heads. Accordingly the escalation rate thus
selected is the CAGR of 2011-12 to 2013-14 which is found to be lesser than
the average inflation rate for the above period. Then by using such escalation
rate in the methodology as mentioned in sub-paragraph (d), (j) and (k) of
Paragraph 5.6.2.1 the admitted amount found for ensuing years of 2014-15
to 2016-17 are given in Table 5.6.2.2-I.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 71
b) Other administrative and general expenditure: For this element of
expenditure the escalation rate considered is also CAGR of 2011-12 to 2013-
14 as such rate is found to be more logical in view of past data trend of actual
expenditure between 2010-11 to 2012-13 and also in view of inflationary
trend. Such escalation rate is however lower than the average inflation rate of
the above period. Thus by using such escalation rate in the methodology as
mentioned in sub-paragraph (d), (j) and (k) of Paragraph 5.6.2.1 the admitted
amount found for ensuing years of 2014-15 to 2016-17 are given in Table
5.6.2.2-I.
c) Thus the admitted expenditure for DPL under O&M expenses for distribution
function are as follows:
Table 5.6.2.2-I Sl
Particulars
As Claimed by DPL Ltd As Admitted by Commission
2014-15 2015-16 2016-17 2014-15 2015-16 2016-17
1. R & M Charges 1327.25 1440.61 1565.29 1213.00 1236.00 1259.00 2. Audit Fees 0.82 0.90 1.00 0.82 0.90 1.00 3. Other A&G expenses 662.35 728.81 801.70 637.00 674.00 713.00 4. A&G expenses (2+3) 663.17 729.71 802.70 637.82 674.90 714.00 5. O&M expenses (1+4) 1990.42 2170.32 2367.99 1850.82 1910.90 1973.00
Note : For detail calculation tables 1, 2 & 3 tables under Annexure-5B may be seen
5.6.2.3 Some Small Expenditure: Some of the small items viz., a) rates & taxes and b)
insurance are uncontrollable in nature till the third control period and thus they
are all dealt separately under paragraphs as below.
a) Rates & Taxes:
For this element the escalation rate considered is the annual growth rate of
2013-14 over 2012-13 as such value shows a reasonable annual escalation
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 72
rate than the extremely high value of other two periods which cannot be a
regular pattern. Thus by using such escalation rate for projection purpose of
this uncontrollable item for the period 2014-15 to 2016-17 the sub-paragraph
(g), (i) and (k) of Paragraph 5.6.2.1 has been applied. The admitted amounts
are given in Table below. The entire amount is allocated to the generation
function as proposed by DPL.
Sl
No. Expenditure
Head As Claimed by DPL As Admitted by
Commission 2014-15 2015-16 2016-17 2014-15 2015-16 2016-17
1. Rates & Taxes 6.18 6.80 7.48 5.00 5.00 5.00
Note : For detail calculation tables 1,2 & 3 under Annexure-5B may be seen
b) Insurance:
For this element of uncontrolled type of expenditure the trend of escalation
rate is CAGR of 2011-12 to 2013-14 as such rate is found to be only non zero
positive rate out of the growth rates of all three periods under consideration.
However such escalation rate is found to be lower than the average inflation
rate of the above period. Thus by using such escalation rate in the
methodology as mentioned in sub-paragraph (d), (i) and (k) of Paragraph
5.6.2.1 the admitted values found for the above referred heads for ensuing
years of 2014-15 to 2016-17 are given in Table below. The entire amount is
allocated to the generation function as proposed by DPL.
Sl No. Expenditure Head As Claimed by DPL As Admitted by Commission 2014-15 2015-16 2016-17 2014-15 2015-16 2016-17
1. Insurance 116.56 128.22 141.04 92.00 99.00 106.00 Note : For detail calculation tables 1,2 & 3 under Annexure-5B may be seen
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 73
5.6.2.4 It is to be noted that the estimated expenditure those are only determined by the
Commission for 2013-14 against any head or subheads as discussed above in
sub paragraph (i) to (iv) of paragraph 5.6.2.1(c) has been considered as base
year expenditure for those heads for tariff determination purpose only for fourth
control period. In case any of such estimated expenditure made by the
commission is found to be less than the audited actual expenditure for 2013-14
vis-à-vis business volume parameter increases then the consequential impact on
the projected expenditure against concerned heads/sub-heads for the period
2014-15 to 2016-17 will be passed through tariff in APR of concerned year
separately irrespective of whether such item is controllable factor or
uncontrollable factor. During truing up exercise in APR of the concerned year the
estimated expenditure of all the elements of different heads as mentioned in
paragraph 5.6.2.1(c) above for 2013-14 are to be considered as has been
incurred against the actual value of the business volume parameter (,i.e, DLL
and consumer strength) that has been achieved at the end of 2013-14. In case
the actual value of DLL or consumer strength in 2013-14 is found to be higher
than the estimated value that has been considered for 2013-14 in this tariff order
then impact of such enhanced amount will be added to the projected value of
DLL or Consumer strength for the period 2014-15 to 2016-17 of the tariff order to
find out the target business volume parameter against the projected expenditure
that has been admitted in the tariff order. On the basis of such revised targeted
business volume parameter the truing up exercise in APR will be done while
applying the regulation 2.6.10(v) of the Tariff Regulations.
5.6.2.5 The above expenditure be availed of on adherence to the conditions as
prescribed in regulation 5.23.1 of the Tariff Regulations.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 74
5.6.2.6 DPL is directed to submit the details of the process adopted for selection of the
Insurance Company and the items covered along with the APR application for
the respective years.
5.7 Demurrage:
5.7.1 DPL has projected Rs. 179.01 lakh, Rs. 196.91 lakh and Rs. 216.60 lakh as
probable demurrage charges payable during the years 2014 – 2015, 2015 –
2016 and 2016 – 2017 respectively. DPL has not advanced any reason for the
need of demurrage charges nor it has submitted any documents in support of the
claim.
5.7.2 During the year 2012 – 2013, the actual amount of expenditure was for Rs.
106.62 lakh. In terms of regulation 5.8.1(vi) of the Tariff Regulations, the
demurrage charge of railway rake is an indicator of efficiency of rake unloading
capability of the generating stations. For existing generating stations, allowance
for the demurrage will gradually be reduced to a target in a phased manner within
a stipulated period as per regulation 2.8.6 of the Tariff Regulations. It appears
that DPL has not put any endeavour for gradual reduction of demurrage charge,
instead the expenditure had gradually been increased over the years as evident
from the year 2012 – 2013 and projection for the years 2014 – 2015, 2015 –
2016 and 2016 – 2017.
5.7.3 The Commission could not admit the claim in its present form. However, such
need of demurrage charges cannot be ruled out totally in exigencies of
generation of power. During Annual Performance Review, DPL may approach
the Commission with actual expenditure incurred as per audited annual accounts
with detailed justification and a deliberation with planned gradual reduction of the
charge for consideration.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 75
5.8 Development Fund:
5.8.1 DPL, in their MYT petition for the fourth control period, has proposed for creation
of development fund in terms of regulation 5.19 of the Tariff Regulations. For
such creation, they have projected the need of Rs. 3921.02 lakh, Rs. 4271.50
lakh and Rs. 4327.57 lakh during the years 2014 – 2015, 2015 – 2016 and 2016
– 2017 respectively and prayed for providing the same as special allocation in
the gross revenue requirement for the respective years.
5.8.2 The Commission observes that DPL has neither mentioned the purpose of such
fund for a particular function nor they have segregated it function wise. DPL has
also not mentioned whether they will be able to comply with all the provisions of
the Regulations to maintain such fund. The Commission, therefore, decides not
to admit any amount under this head at present.
5.9 Depreciation:
5.9.1. DPL has submitted detailed computations in this regard and the Commission
agrees to such computations for depreciation. The Commission however, has
allowed depreciation considering 5% reduction of provisional project cost of Units
VII & VIII on the ground as mentioned in paragraphs 5.2.1 and 5.2.2 and the
amounts of depreciation admitted by the Commission stand as follows:
Rupees in Lakh Depreciation
Sl. No Particular As admitted by the Commission
2014-15 2015-16 2016-17 1 Unit - VI 62.33 62.33 62.33 2 Unit - VII 4792.43 4792.43 4792.43 3 Unit - VIII 4267.60 8527.44 8527.44 4 Sub total of Generation (4=1+2+3) 9122.36 13382.20 13382.20 5 Distribution 1089.67 1260.24 1260.24 6 Total (6=4+5) 10212.03 14642.44 14642.44
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 76
5.10 Advance against Depreciation:
5.10.1 The statements of capital borrowings and computations of chargeable interest
with reference to scheduled repayments show that DPL will require the following
amounts to make the total repayments in different years:
5.10.2 As a portion of the depreciation relating to units VII & VIII of the power plant has
been reduced, DPL will require additional amounts towards advance against
depreciation to keep up its loan repayment commitments considering DPL as a
whole (power business only). The amounts chargeable for depreciation in
different years under the control period, as shown in paragraph 5.9 will fall short
of the amounts required for repayments of loans. The net short fall for DPL as a
whole (power business only) will be as under:
Rupees in lakh
Year Amount of Loan Repayments Chargeable depreciation Shortfall
2014 – 2015 12666.60 10212.03 2454.07 2015 – 2016 17198.60 14642.44 2556.16 2016 – 2017 17198.60 14642.44 2556.16
5.10.3 To facilitate the scheduled loan repayments, the Commission considers to allow
the amounts of net shortfall as shown above as advance against depreciation in
terms of the Tariff Regulations. The allowable amounts of advance against
depreciation, therefore, are being allowed as per following allocation as shown
under:
Rupees in lakh 2014 – 2015 12666.60 2015 – 2016 17198.60 2016 – 2017 17198.60
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 77
Rupees in Lakh Advance against Depreciation
Sl. No Particular As admitted by the Commission
2014-15 2015-16 2016-17 1 Unit – VI 0.00 0.00 0.00 2 Unit - VII 2189.17 2018.60 2018.60 3 Unit – VIII 264.90 537.56 537.56 4 Sub total of Generation (4=1+2+3) 2454.07 2556.16 2556.16 5 Distribution 0.00 0.00 0.00 6 Total (6=4+5) 2454.07 2556.16 2556.16
5.11 Write off of Intangible Assets:
5.11.1 DPL has not projected any amount under the head intangible assets written off
during the years 2014 – 2015, 2015 – 2016 and 2016 – 2017. Hence no amount
is considered by the Commission.
5.12 Interest on Borrowed Capital:
5.12.1 DPL has provided detailed computations in regard to its claims towards interest
payable on capital borrowings from Central Electricity Authority (CEA), Power
Finance Corporation Ltd (PFCL) and Govt. of West Bengal. It has not claimed
interest on normative capital borrowings in terms of the Tariff Regulations.
5.12.2 DPL, in their submission, has highlighted the reason for providing the interest
liability for Rs. 3440.55 lakh of the loan from CEA for Rs. 1181.00 lakh upto
31.03.2013 which was obtained long back and yet to be repaid. This includes
penal interest also. In the APR order for 2011 – 2012 DPL was directed to submit
a detailed deliberation underlying the background of backlog interest for Rs.
3440.55 lakh above followed by a statement of interest actually paid so far year
wise, statement of interest payable, penal interest chargeable / paid year wise,
year wise provision in audited annual accounts, approach to CEA for making the
payment of the principal and interests and their response, highlighting the
reasons for failing to make timely payment of interest inspite of allowing the same
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 78
through APR orders issued by the Commission from time to time with fixing up of
accountability in this regard in a specific manner and then prefer the claim having
a valid support of the actions taken on the above points. The copies of all
correspondences made with CEA, the loan agreement underlying the terms and
conditions of payment and agenda notes with resolution of the Board of DPL may
be annexed to such submission. The amount of interest admitted by the
Commission in respective APR orders so far issued may also be mentioned.
Such submission was to be made in the APR application for the year 2012 –
2013 for examination by the Commission before finalizing its fate. DPL have not
complied with above direction of the Commission. Although, DPL stated to have
enclosed year wise statement of the backlog amount of interest, no such
enclosures were found in their petition of APR 2012 – 2013. Nevertheless, the
Commission is of the opinion that the consumers at large cannot be burdened
with the amount of interest including backlog interest for failure on the part of
DPL to repay the amount of loan in time thereby accruing huge amount of
interest liability. Thus, no interest on the loan from CEA as claimed by DPL for
the ensuing years under fourth control period is considered by the Commission. It
is directed that DPL should not come up with this interest burden on loan from
CEA in future.
5.12.3 The amounts of interest chargeable to Revenue Requirement are admitted and
allocated as suggested by DPL as under: Rupees in Lakh
Interest on borrowed capital Sl No Particular As Proposed by DPL As admitted by the Commission
2014-15 2015-16 2016-17 2014-15 2015-16 2016-17 1 Unit – VI 1017.35 1020.17 1023.00 838.94 838.94 838.94 2 Unit - VII 4961.46 4153.17 3366.09 4961.46 4153.17 3366.09 3 Unit – VIII 11530.49 15224.65 14572.38 8092.30 15773.04 14685.24
4 Sub total of Generation (4=1+2+3) 17509.30 20397.99 18961.47 13892.70 20765.15 18890.27
5 Distribution 1457.19 1338.75 1215.40 1457.19 1338.75 1215.40 6 Total (6=4+5) 18966.49 21736.74 20176.87 15349.89 22103.90 20105.67
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 79
5.12.4 The interest on capital borrowings, however, is not kept withheld for reduction in
provisional project cost of Unit VII & VIII for reasons mentioned in paragraph
5.2.1 (iii) and 5.2.2 of this order.
5.13 Other Finance Charges:
5.13.1 The amounts claimed by DPL towards other finance charges comprising
Guarantee Fees and Bank Charges are as under and the claims are found
reasonable and hence allowed.
Rupees in lakh Sl.No Particular As proposed by DPL and admitted by the Commission
2014-15 2015-16 2016-17 1 Unit – VI 135.69 131.10 125.59 2 Unit - VII 386.26 325.03 262.22 3 Unit – VIII 1325.46 1325.56 1325.67
4 Sub total of Generation (4=1+2+3) 1847.41 1781.69 1713.48
5 Distribution 56.39 40.40 24.54 6 Total (6=4+5) 1903.80 1822.09 1738.02
5.14 Bad Debts:
5.14.1 In terms of regulation 5.10.1 of the Tariff Regulations, the Commission may allow
amounts of bad debts as actually had been written off in the latest available
audited accounts subject to a ceiling of 0.5% of the annual gross sale value of
power at the end of the current year. DPL has projected Rs. 921.03 lakh, Rs.
1022.36 lakh and Rs. 1054.51 lakh for the year 2014 – 2015, 2015 – 2016 and
2016 – 2017 respectively towards bad debts.
5.14.2 As the amounts of bad debts have been projected only on prospective basis
without the same having been written off, the Commission is not inclined to admit
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 80
the claim as at present for obvious reason. However, after the amounts of bad
and doubtful debts have actually been written off from the book of accounts after
following usual procedure, the same may be considered by the Commission at
the time of Annual Performance Review of the respective years. The
Commission noticed that DPL has not written off any amount of bad debt during
2012 – 2013 and no amount on this account had been claimed in APR for 2012 –
2013.
5.15 Income Tax:
5.15.1 DPL has projected Rs. 3446.06 lakh, Rs. 3697.19 lakh and Rs. 3697.19 lakh for
the years 2014 – 2015, 2015 – 2016 and 2016 – 2017 respectively for income
tax. The power business of DPL is not a separate entity for the assessment of
income tax. Its tax liability will depend on the overall taxable income of the
company as a whole. Till the time the income tax is assessed and the part of the
tax payable is identified pertaining to power business, the Commission cannot
allow any provision in this regard. However, in case, such tax payable is
identified pertaining to power business of DPL, provision is made in the accounts
and audited, on submission of conclusive documentary evidences with the
application for APR in succeeding years, the same will be taken care of as per
relevant regulation of the Tariff Regulations.
5.16 Interest on Consumers’ Security Deposits:
5.16.1 DPL has claimed Rs. 58.71 lakh, Rs. 64.58 lakh and Rs. 71.03 lakh for the years
2014 – 2015, 2015 – 2016 and 2016 – 2017 respectively towards payment of
interest to the consumers on their security deposits. The projected amounts
under the head are allowed and allocated to distribution function.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 81
5.16.2 DPL is directed to furnish reconciliation of payment for interest on consumers’
security deposit in line with the provision laid down under regulation 4.2.6 of the
West Bengal Electricity Regulatory Commission (Miscellaneous Provisions)
Regulations, 2013 along with actual booking of interest on consumers’ security
deposit in the annual accounts duly certified by the statutory auditors in the
submission of petition for APR for 2014 – 2015. Non compliance of the above
directions in the APR application for 2014 – 2015 will be viewed by the
Commission seriously and no amount under this head will then be allowed in
APR for 2014 – 2015 and onwards.
5.17 Reserve for unforeseen exigencies:
5.17.1 DPL has claimed Rs. 868.45 lakh, Rs. 954.80 lakh and Rs. 954.80 lakh for the
years 2014 – 2015, 2015 – 2016 and 2016 – 2017 respectively towards
appropriation for the reserve for unforeseen exigencies in terms of regulation
5.11 of the Tariff Regulations.
5.17.2 In terms of the referred regulation, the Commission is thus allowing as per DPL
appropriations for creation of such reserves for the years under fourth control
period with the directives that investment of the amounts (including the arrears
for earlier years) must be done in accordance with the provisions of the Tariff
Regulations and the amounts of interest earnings thereon should not be taken as
income from non-tariff sources. For failure to comply with the provisions of the
referred regulation, double the amount allowed for the purpose will be deducted
from the amount of return on equity, allowed to DPL, during APR of any
succeeding years. Income from such investments of Reserve for Unforeseen
Exigencies shall be reinvested for the same purpose and shall be shown
separately in the application of APR or tariff, as the case may be, supported by
necessary audited data for any year. DPL is also directed to comply with the
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 82
directions given in para 3.16.6 to 3.16.8 of the APR order in case no. APR-40/13-
14 for the year 2012 – 2013 in all further submission of tariff petition. The
amounts allowed under this head are as under: Rupees in lakh Sl.No Particular As admitted by the Commission
2014-15 2015-16 2016-17 1 Unit – VI 133.61 133.61 133.61 2 Unit - VII 344.68 344.68 344.68 3 Unit – VIII 0.00 424.92 424.92
4 Sub total of Generation (4=1+2+3) 478.29 903.21 903.21
5 Distribution 51.59 51.59 51.59 6 Total (6=4+5) 529.88 954.80 954.80
5.17.3 Any amount of reserve for unforeseen exigencies however is not kept withheld
for reduction in the provisional project cost of Units VII & VIII for the reasons
mentioned at paragraph 5.2.1 (iii) and 5.2.2 of this order.
5.18 Return on Equity:
5.18.1 DPL has projected average equity base with reference to opening balance and
proposed addition during 2014 – 2015, 2015 – 2016 and 2016 – 2017 to the fixed
assets and considered return on equity @ 15.5% and 16.5% for generation and
distribution functions respectively for different years of the fourth control period
as shown below:
Rupees in lakh Return on Equity Base as Projected by DPL for generation function
Sl. No. Particular Average Equity Base as projected
by DPL Return on Equity Base as
projected by DPL 2014-15 2015-16 2016-17 2014-15 2015-16 2016-17
1 For Unit No. VI 29202.33 28829.40 28829.40 4526.36 4468.56 4468.56 2 For Unit No. VII 40500.00 40500.00 40500.00 6277.50 6277.50 6277.50 3 For Unit No. VIII 25495.50 33994.00 33994.00 3951.80 5269.07 5269.07 4 For distribution 15367.77 15367.77 15367.77 2535.68 2535.68 2535.68 5 Total 110565.60 118691.17 118691.17 17291.34 18550.81 18550.81
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 83
5.18.2 DPL has submitted that total equity received from Government of West Bengal till
2013 – 2014 against unit VIII is Rs. 19350.00 lakh. The Commission considers
the amount as the actual equity base at the beginning of the year 2014 – 2015.
5.18.3 Out of actual equity base of Rs. 89425.25 lakh for generating function at the
beginning of the year 2014 - 2015, Rs. 29575.25 lakh relates to equity base of
units III to VI, Rs. 40500.00 lakh to that of unit VII and Rs. 19350.00 lakh of unit
VIII, which is commissioned in October 2014. The units III, IV & V of DPL were
proposed for decommissioning and no generation from 2014 – 2015 onwards
has been projected by DPL. The value of equity for the remaining unit VI out of
Rs. 29575.25 lakh for the purpose of return, as stated in regulation 5.6.1.7 read
with regulation 5.6.1.5, shall be determined considering the value of equity of the
proposed inoperative units derived in terms of the formula laid down under
regulation 5.6.1.6(a) of the Tariff Regulations, as amended as under:
Where,
Eunit ═ Deemed Equity of inoperative unit under consideration.
Etot ═ Actual Equity against the concerned generating station.
Aunit ═ Age difference of the latest unit and the concerned inoperative unit.
IOunit ═ Installed capacity of the inoperative unit under consideration.
ICunitn ═ Installed capacity of the nth unit of the station.
Aunitn
E
═ Age difference of the latest unit and nth unit in completed year.
═ unit Etot X {IOunit X (0.9085)A
{ICunit}
unitn X (0.9085)Aunitn}
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 84
The units III, IV, V & VI were commissioned during the years 1964, 1964, 1966
and 1987 respectively. Deemed equity of the units proposed for
decommissioning is determined in the manner stated below:
Deemed equity for unit III (Eunit
Rs. 29575.25 lakh X {77X(0.9085)
) =
23
[77X(0.9085) }
+ 23 77X(0.9085) + 23 77X(0.9085) + 110X(0.9085)21 0
= Rs. 29575.25 lakh X 77 X 0.1100205 77 X .1100205 + 77 X .1100205 + 77 X 0.133298 + 110 X 1
= 250549.0528
8.4716 + 8.4716 + 10.2639 + 110
= 250549.0528 137.2071
= Rs. 1826.06 lakh
Deemed equity for unit IV (Eunit
(Rs. 29575.25 lakh – 1826.06 lakh) X {77X(0.9085)
) =
23
[77 X (0.9085) }
+ 23 77 X (0.9085) 21 + 110 X (0.9085)0
= Rs. 27749.19 lakh X 77 X 0.1100205 77 X 0.1100205 + 77 X 0.133298 + 110 X 1
= 235079.4414
128.7355
= Rs. 1826.06 lakh
Deemed equity for unit V (Eunit
(Rs. 29575.25 lakh – 1826.06 lakh – 1826.06) X {77X(0.9085)
) =
21
}
[77 X (0.9085) 21 + 110 X (0.9085)0
= Rs. 25923.13 lakh X 77 X 0.133298 77 X 0.133298 + 110
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 85
= 266073.6065 120.2639
= Rs. 2212.41 lakh
Therefore, the revised equity base of the remaining unit VI of DPL is arrived at
Rs. 23710.72 lakh (Rs. 29575.25 lakh - Rs. 1826.06 lakh - Rs. 1826.06 lakh - Rs.
2212.41 lakh).
5.18.4 The Commission now proceeds to determine the average equity base of DPL for
generating and distribution functions for the fourth control period. In terms of the
Tariff Regulations, returns on equity base are to be allowed @ 15.5% on
generating assets and 16.5% on distribution assets. Thus considering its
proportion of gross fixed assets of generation and distribution system at the
beginning and closing of the year, the equity base at its opening and closing of
the respective year has been arrived at. The detailed computation of the amounts
so arrived is shown in annexure 5C and 5D. Based on the computations shown
in annexure 5C and 5D, the average equity base for each year of 2014 – 2015,
2015 – 2016 and 2016 – 2017 for generating station and distribution system are
as below: Rupees in lakh
Admitted Average Equity Base Sl. No. Segment 2014 – 2015 2015 – 2016 2016 – 2017
1 Generation Unit – VI 23710.72 23710.72 23710.72 Unit - VII 40500.00 40500.00 40500.00 Unit - VIII 9675.00 19350.00 19350.00
Total 73885.72 83560.72 83560.72 2 Distribution system 15367.77 15367.77 15367.77 3 Overall 89253.49 98928.49 98928.49
5.18.5 It is to be clarified that equity base admitted for allowing returns as shown in the
referred annexure are computed for the prospective years and therefore, they
need adjustments subsequently on the basis of audited accounts. Such
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 86
adjustments will be carried out at the time of Annual Performance Review for the
concerned years.
5.18.6 The amounts of returns on equity allowable on above amounts of equity base
come as under after adjustments for Unit VII and Unit VIII in pursuance of
regulation 2.8.1.4.13 of the Tariff Regulations. Return against unit VIII for 2014 –
2015 is allowed to the extent of Rs. 1499.63 lakh because the unit was under
commercial operation for a period of 6 (six) months during the year.
Rupees in lakh Return on Equity as allowed in Tariff Order
2014-15 2015-16 2016-17 1 Generating Assets @
15.5% on average Equity base of generation segment
(a) For Units No. VI 3675.16 3675.16 3675.16 (b) For Unit No. VII Less: In pursuance of regulation 2.8.1.4.13 of the Tariff Regulations, as referred to in paragraph 5.2(i) of this order.
6277.50 (-) 313.88
6277.50 (-) 313.88
6277.50 (-) 313.88
Net Total for Unit No. VII 5963.62 5963.62 5963.62 c) For Unit No. VIII Less: In pursuance of regulation 2.8.1.4.13 of the Tariff Regulations, as referred to in paragraph 5.2(i) & 5.2(vi) of this order.
1499.63 (-) 74.98
2999.25 (-) 149.96
2999.25 (-) 149.96
Net Total for Unit No. VIII 1424.65 2849.29 2849.29 Total Generation 11063.43 12488.07 12488.07 2 Distribution assets @
16.5% on average equity base of distribution segment
Total Distribution 2535.68 2535.68 2535.68
Overall : 13599.11 15023.75 15023.75
5.18.7 The return on equity on account of the VIIth & VIIIth units of the generating
station will be withheld to the extent as mentioned in paragraph 5.2.1 and 5.2.2
for the reasons mentioned therein.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 87
5.19 Interest on Working Capital:
5.19.1 DPL has asked for interest on normative working capital as under:
Rupees in lakh 2014-15 2015-16 2016-17 2152.77 2469.49 2637.33
5.19.2 In terms of regulations 5.6.5.1 of the Tariff Regulations, as amended working
capital requirement shall be assessed on normative basis @ 18% on the base
amount derived by summation of annual fixed charges and fuel and power
purchase cost reduced by the elements of the ARR determined, viz., depreciation
etc. as at paragraph 5.18.4. However, the above assessment of requirement of
working capital would be 10% instead of 18% on the base amount since DPL has
already introduced Monthly Fuel Cost Adjustment or Monthly Variable Cost
Adjustment for all the years, i.e., 2014 – 2015, 2015 – 2016 and 2016 – 2017.
5.19.3 DPL is directed to utilize the consumers’ security deposit lying with them in
working capital requirement. If there is any shortfall between the working capital
requirement and consumers’ security deposit held and DPL is required to take
working capital loan that will be taken care of during APR for the concerned year
as per provision of the Tariff Regulations. As per audited accounts for 2012 –
2013, total amount of consumers’ security deposit held by DPL as on 31.03.2013
is Rs. 640.07 lakh. Interest paid to consumers against security deposit during
2012 – 2013 is Rs. 38.96 lakh. DPL has been allowed interest on consumer
security to the extent of Rs. 58.71 lakh, Rs. 64.58 lakh and Rs. 71.03 lakh for
2014 – 2015, 2015 – 2016 and 2016 – 2017 respectively as stated in paragraph
5.16.1 of the order. Thus, the normative requirement of working capital @ 10% of
the base amount is reduced by the security deposit held by DPL as on
31.03.2013 to arrive at the requirement of working capital. The interest on
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 88
working capital is considered @ 13.5% as claimed by DPL as the same is less
than the SBI PLR (14.45%) as on 01.04.2013.
5.19.4 As per their submission in Form 1.17(b), DPL has claimed the rate of interest @
13.50% per annum for all the years of the fourth control period. The interest on
working capital for generation function is worked out as under:
Sl. No. Particulars Amount in Rs. in lakh 2014-15 2015-16 2016-17
1 Annual Fixed charges now arrived excluding interest on working capital for generation function 54050.34 69718.94 68953.79
2 Fuel Cost as admitted 66368.54 82185.77 82185.77 3 Sub Total (1+2) 120418.88 151904.71 151139.56 Less:
4 Depreciation 9122.36 13382.20 13382.20 5 Advance against depreciation 2454.07 2556.16 2556.16 6 Deferred revenue expenditure 0.00 0.00 0.00 7 Return on Equity 11063.43 12488.07 12488.07 8 Bad and doubtful Debt 0.00 0.00 0.00 9 Reserve for Unforeseen Exigencies 478.29 903.21 903.21
10 Sub Total (4 to 9) 23118.15 29329.64 29329.64 11 Allowable Fixed Charges for working capital (3-10) 97300.73 122575.07 121809.92
12 Normative requirement of Working Capital (10% of 11) 9730.07 12257.51 12180.99
13 Security deposit held as on 31.03.2013 640.07 640.07 640.07
14 Requirement of working capital after utilizing the security deposit (12-13) 9090.00 11617.44 11540.92
15 Interest allowable @ 13.50% on 14 1227.15 1568.35 1558.02 16 Interest on working capital allowed 1227.15 1568.35 1558.02
5.19.5 The amounts of Rs. 1227.15 lakh, Rs. 1568.35 lakh and Rs. 1558.02 lakh for the
years 2014 – 2015, 2015 – 2016 and 2016 – 2017 respectively are allocated to
generation function only.
5.19.6 During APR of the concerned year, the interest on working capital as above will
be reviewed on the amount assessed on normative basis considering the actual
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 89
security deposit held during the year or the actual amount of interest paid,
whichever is less, in respect of both generation and distribution function as per
regulation 5.6.5.2 of the Tariff Regulations.
5.20 Income from other Sources:
5.20.1 DPL has projected incomes from non-tariff sources as under: Rupees in lakh Sl. No. Particulars 2014-15 2015-16 2016-17
1 Rental of meters etc. 91.37 92.27 93.19 2 Sale and Repairs of meters and apparatus etc. 0.31 0.31 0.31 3 Income from investment & bank balances 76.96 77.73 78.50 4 Surcharge on late payments 284.30 287.15 290.02 5 Income from consumers’ job 0.00 0.00 0.00 6 Sale of steam 222.03 224.05 226.50 7 others 141.77 143.19 144.62 8 Total 816.74 824.70 833.14
5.20.2 The proposal of income from non-tariff sources of DPL has been admitted by the
Commission for all the three years under fourth control period with allocation of
the income between generation and distribution on the basis of the nature of the
income. The incomes from rental of meters and other apparatus, sale and repair
of meters and other apparatus, surcharge for late payment, income from jobs at
consumers’ premises and other general receipt have been considered in the
distribution head. Income from sale of steam and income from investments have
been considered in the generation head of units VI and VII. Accordingly, the
allocated amounts as admitted by the Commission are as follows: Rupees in Lakh
Income from Other Sources Sl.No Particular As Proposed by DPL and Admitted by the Commission
2014-15 2015-16 2016-17 1 Unit – VI 187.98 189.76 191.75 2 Unit - VII 111.01 112.02 113.25 3 Unit – VIII 0.00 0.00 0.00
4 Sub total of Generation (4=1+2+3) 298.99 301.78 305.00
5 Distribution 517.75 522.92 528.14 6 Total (6=4+5) 816.74 824.70 833.14
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 90
5.20.3 As can be noted from the above break-ups, DPL earns a considerable amount by
sale of steam from the power plants to other agencies. DPL was directed in the
tariff order under third control period and also in the APR order for 2011 – 2012
and 2012 – 2013 to disclose the names of the agencies and rate at which such
supplies are being made. But nothing has been disclosed so far including the
tariff petition for fourth control period. The Commission has taken a serious note
of such non-compliance. DPL is once again directed to comply with the directions
in all future submission. However, the projected amounts of incomes from non-
tariff sources are being admitted.
5.21 Interest Credit:
5.21.1 In terms regulation 5.5.3 of the Tariff Regulations, where the actual amount of
loan repayment in any year falls short of the depreciation allowable during the
year, then interest credit of such excess depreciation charges at the rate of
weighted average cost of debt is admissible. DPL has projected Rs.19.03 lakh,
Rs. 18.24 lakh and Rs. 18.24 lakh as interest credit to be refunded in ARR during
2014 – 2015, 2015 – 2016 and 2016 – 2017 respectively as chargeable
depreciation for Unit VI is more than the amount of loan repayable for those
years. As may be seen in the preceding paragraphs 5.10.2 and 5.10.3 that the
Commission has admitted advance against depreciation to DPL due to accrued
shortfall in amount of depreciation in repayment of the loan for all the years under
fourth control period in terms of the Tariff Regulations and hence the interest
credit is not considered.
Tariff Order of DPL for the year 2014 – 2015
ANNEXURE – 5A
West Bengal Electricity Regulatory Commission 91
Monthly Rate of Inflation in CPI number for Industrial Worker Year Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb March Average
2010-11 13.33 13.91 13.73 11.25 9.88 9.82 9.7 8.33 9.47 9.3 8.82 8.82 10.53 2011-12 9.41 8.72 8.62 8.43 8.99 10.06 9.39 9.34 6.49 5.32 7.57 8.65 8.42 2012-13 10.22 10.16 10.05 9.84 10.31 9.14 9.6 9.55 11.17 11.62 12.06 11.44 10.43 2013-14 10.24 10.68 11.06 10.85 10.75 10.7 11.06 11.47 9.13 7.24 6.73 6.70 9.72 2014-15 7.08 7.02 6.49 7.23 6.75 6.3 6.81 Source : Website of Labour Bureau, GOI : Average Value is being Computed
WPI FROM OFFICE OF ECONOMIC ADVISOR , GOI
Year Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
2009-10 125.0 125.9 126.8 128.2 129.6 130.3 131.0 132.9 133.4 135.2 135.2 136.3
2010-11 138.6 139.1 139.8 141.0 141.1 142.0 142.9 143.8 146.0 148.0 148.1 149.5
2011-12 152.1 152.4 153.1 154.2 154.9 156.2 157.0 157.4 157.3 158.7 159.3 161.0
2012-13 163.5 163.9 164.7 165.8 167.3 168.8 168.5 168.8 168.8 170.3 170.9 170.1
2013-14 171.3 171.4 173.2 175.5 179.0 180.7 180.7 181.5 179.6 179.0 179.5 180.3
2014-15 180.8 182.0 183.0 184.6 185.7 185.0
Source : Website of Office of the Economic Advisor, GOI :
MONTHLY INFLATION RATE COMPUTED BASED ON WPI FROM OFFICE OF ECONOMIC ADVISOR , GOI
Year Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Average
2010-11 10.88 10.48 10.25 9.98 8.87 8.98 9.08 8.20 9.45 9.47 9.54 9.68 9.57 2011-12 9.74 9.56 9.51 9.36 9.78 10.00 9.87 9.46 7.74 7.23 7.56 7.69 8.96 2012-13 7.50 7.55 7.58 7.52 8.01 8.07 7.32 7.24 7.31 7.31 7.28 5.65 7.36 2013-14 4.77 4.58 5.16 5.85 6.99 7.05 7.24 7.52 6.40 5.11 5.03 6.00 5.98 2014-15 5.55 6.18 5.66 5.19 3.74 2.38 4.78
Tariff Order of DPL for the year 2014 – 2015
ANNEXURE – 5B
West Bengal Electricity Regulatory Commission 92
TABLE - I ANNUAL ACTUAL FIGURE OF DIFFERENT BUISNESS PARAMETERS OF DPL DISTRBUTION FUNCTION HAVING IMPACT ON TARIFF
Sl No Particulars Units
Inflat
ionar
y Ba
sis
Sens
itivity
Pa
rame
ter &
de
gree
of
sens
itivity
2009-10 2010-11 2011-12 2012-13 2013-14
(Estimated by DPL)
2013-14 (Estimated by
WBERC)
1 Total consumers on 31st March number 39836 41735 43634 47244 48479 48479 2 Repair & Maintenance Expenditure Rs Lakh WPI+CPI DLL 715.96 1697.21 1091.29 1075.32 1801.07 1190.00 3 Auditors Fees Rs Lakh WPI+CPI DLL 3.86 0.65 0.66 0.67 0.74 0.68 4 Others Administrative and General Expenses Rs Lakh WPI+CPI CSM 337.61 318.16 543.85 585.59 602.31 602.31 5 Total Administrative & General Expenses(3+4) Rs Lakh 341.47 318.81 544.51 586.26 603.05 602.99 6 Total O&M Function Expenses (2+5) Rs Lakh 1057.43 2016.02 1635.80 1661.58 2404.12 1792.99 7 Rates & Taxes Rs Lakh WPI+CPI DLL 0.47 0.38 2.93 4.10 4.51 4.45 8 Insurance Rs Lakh WPI+CPI DLL 81.37 96.29 75.86 90.33 99.36 85.96 9 Total Rs Lakh 1139.27 2112.69 1714.59 1756.01 2507.99 1883.40
Tariff Order of CESC Limited for the year 2014 – 2015
West Bengal Electricity Regulatory Commission
93
TABLE-2 PROJECTED ANNUAL ESCALATION RATE COMPUTATION OF DIFFERENT PARAMETERS DURING FOURTH CONTROL PERIOD (2014-15 TO 2016-17)
Sl No Particulars
Inflat
ionar
y Bas
is
Sens
itivity
Pa
rame
ter &
de
gree
of se
nsitiv
ity
CAGR (%) between
Aver
age
Inflat
ion
Rate
durin
g the
Co
ncer
ned p
eriod
$
Whe
ther I
nflati
on
rate
is ap
plica
ble
Addit
ional
Gro
wth
Rate
abov
e infl
ation
ra
te
Ratio
of E
xpen
ses
incre
ase a
nd
sens
itivity
pa
rame
ter in
creas
e Escalation rate (%) for
Rem
arks
2012
-13 t
o 20
13-1
4
2011
-12 t
o 20
13-1
4
2010
-11 t
o 20
13-1
4
2014
-15
2015
-16
2016
-17
1 Total consumers increase 2.61 5.41 5.12 2.61 4.02 4.02 2 Repair & Maintenance Expenditure WPI+CPI DLL 10.66 1.72 -12.7 8.27 No 1.89 1.89 1.89 3 Auditors Fees WPI+CPI DLL 1.52 1.51 1.52 8.27 No 1.66 1.66 1.66
4 Others Administrative and General Expenses WPI+CPI CSM 2.86 5.24 23.71 7.48 No 5.76 5.76 5.76
5 Total Administrative & General Expenses(3+4) 4.38 6.75 25.23 7.42 7.42 7.42
6 Total O&M Function Expenses (2+5) 15.04 8.47 12.53 9.31 9.31 9.31 7 Rates & Taxes WPI+CPI DLL 8.48 23.24 127.09 7.48 Yes 1.00 0.38 7.09 9.67 9.67 8 Insurance WPI+CPI DLL -4.84 6.45 -3.71 8.27 No 7.10 7.10 7.10
Tariff Order of CESC Limited for the year 2014 – 2015
West Bengal Electricity Regulatory Commission
94
ANNUAL ACTUAL FIGURE OF DIFFERENT BUISNESS PARAMETERS OF DPL DISTRBUTION FUNCTION HAVING IMPACT ON TARIFF
Sl No Particulars Units
Projected expenses
for 2014-15 by DPL
Computed expenses for
2014-15 by the Commission
Admitted expenses
for 2014-15
Projected expenses
for 2015-16 by DPL
Computed expenses for 2015-16 by
the Commission
Admitted expenses
for 2015-16
Projected expenses
for 2016-17 by DPL
Computed expenses for 2016-17 by
the Commission
Admitted expenses
for 2016-17
1 Total consumers on 31st March number 49744 49744 49744 51743 51743 51743 51826 53823 53823
2 Repair & Maintenance Expenditure Rs Lakh 1327.25 1213.00 1213.00 1440.61 1236.00 1236.00 1565.29 1259.00 1259.00
3 Auditors Fees Rs Lakh 0.82 1.00 0.82 0.90 1.00 0.90 1.00 1.00 1.00
4 Others Administrative and General Expenses Rs Lakh 662.35 637.00 637.00 728.81 674.00 674.00 801.70 713.00 713.00
5 Total Administrative & General Expenses(3+4) Rs Lakh 663.17 638.00 637.82 729.71 675.00 674.90 802.70 714.00 714.00
6 Total O&M Function Expenses (2+5) Rs Lakh 1990.42 1851.00 1850.82 2170.32 1911.00 1910.90 2367.99 1973.00 1973.00
7 Rates & Taxes Rs Lakh 6.18 5.00 5.00 6.80 5.00 5.00 7.48 5.00 5.00 8 Insurance Rs Lakh 116.56 92.00 92.00 128.22 99.00 99.00 141.04 106.00 106.00 9 Total Rs Lakh 2113.16 1948.00 1947.82 2305.34 2015.00 2014.90 2516.51 2084.00 2084.00
Tariff Order of DPL for the year 2014-15
ANNEXURE – 5C COMPUTATION OF AVERAGE EQUITY BASE
FOR GENERATION FUNCTION
West Bengal Electricity Regulatory Commission
95
Rs. in lakh
Unit III to VI Unit VII Unit VIII Total Unit VI Unit VII Unit VIII Total Unit VI Unit VII Unit VIII Total
2 Delition of equity for decommissioning of Units III, IV & V (as per paragraph 5.18.3) -5864.53 0.00 0.00 -5864.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3Admissible equity base at the beginning of the year (1+2) 23710.72 40500.00 0.00 64210.72 23710.72 40500.00 19350.00 83560.72 23710.72 40500.00 19350.00 83560.72
5Actual equity base at the end of the year (1+2+4) 23710.72 40500.00 19350.00 83560.72 23710.72 40500.00 19350.00 83560.72 23710.72 40500.00 19350.00 83560.72
7 Normative addition to equity base (30% of 5) 0.00 0.00 50990.40 50990.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9Admissible equity base considered at the closing of the year (3+8) 23710.72 40500.00 19350.00 83560.72 23710.72 40500.00 19350.00 83560.72 23710.72 40500.00 19350.00 83560.72
11 Allowable return @ 15.5% on 10 3675.16 6277.50 1499.63 11452.29 3675.16 6277.50 2999.25 12951.91 3675.16 6277.50 2999.25 12951.91
19350.00 83560.72
0.00 0.00 19350.00 19350.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
40500.00 19350.00 83560.72 23710.72 40500.0029575.25 40500.00 0.00 70075.25 23710.72
83560.72 83560.7223710.72 40500.009675.00 19350.00 19350.0023710.72 40500.00 73885.72 23710.72 40500.00
0.00 0.00 169968.00 0.00
0.000.00 0.00 19350.0019350.00
169968.00
0.00
0.00
0.00 0.00 0.00
0.00 0.000.000.00
0.000.00
0.00
0.00
0.00Net Addition to the original cost of fixed assets during the year
Addition to equity base considered for the year (lower of 4 and 7)
Average equity base for allowing returns (3+9)/2
Actual equity base at the beginning of the year1
4
6
8
10
Actual addition to equity base during the year
2014 - 2015 2015 - 2016 2016 - 2017 Sl. No. Particulars
Tariff Order of DPL for the year 2014 – 2015
ANNEXURE – 5D COMPUTATION OF AVERAGE EQUITY BASE
FOR DISTRIBUTION FUNCTION
West Bengal Electricity Regulatory Commission
96
Rs. in lakh
Sl. No. Particulars 2014 - 2015 2015 – 2016 2016 – 2017
1 Actual equity base at the beginning of the year. 15367.77 15367.77 15367.77
2 Admissible equity base at the beginning of the year 15367.77 15367.77 15367.77
3 Actual addition to / withdrawal of equity base during the year 0.00 0.00 0.00
4 Actual equity base at the end of the year (1+3) 15367.77 15367.77 15367.77
5 Net Addition to the original cost of fixed assets during the year as per Form 1.18 0.00 0.00 0.00
6 Normative addition to equity base (30% of 5) 0.00 0.00 0.00
7 Addition to equity base considered for the year (lower of 3 and 6) 0.00 0.00 0.00
8 Admissible equity base considered at the closing of the year (2+7) 15367.77 15367.77 15367.77
9 Average equity base for allowing returns (2+8)/2 15367.77 15367.77 15367.77
10 Allowable Return @ 16.5% 2535.68 2535.68 2535.68
Tariff Order of DPL for the year 2014 – 2015
CHAPTER – 6 SUMMARIZED STATEMENT OF
AGGREGATE REVENUE REQUIREMENT FOR THE YEARS 2014-15, 2015-16 & 2016-17
& REVENUE RECOVERABLE THROUGH TARIFF FOR THE YEAR 2014 – 2015
West Bengal Electricity Regulatory Commission 97
6.1 Based on the analyses and findings recorded in the foregoing chapters the
Commission is now drawing the statements of Aggregate Revenue
Requirements (ARR) separately for each of the three years of the third control
period covering the years 2014-15, 2015-16 and 2016-17. Such summarized
statements are given in Annexure 6A to 6C of this chapter.
6.2 In terms of the Tariff Regulations, it is also to ascertain the amount of revenue
recoverable through tariff for the year 2014-15 after carrying out adjustments of
the recoverable amount determined in Annual Performance Review (APR) for the
year 2012-13. The Commission in its APR order for 2012 – 2013 dated
21.05.2014 in Case No. APR-40/13-14 has determined the net amount of Rs.
14282.86 lakh recoverable by DPL from its consumers after taking into
consideration the adjustments in both variable costs and fixed costs. The
Commission now decides to adjust the net recoverable amount of 14282.86 lakh
determined in the APR for 2012 – 2013 with the ARR for 2014 – 2015 to
determine the revenue recoverable through tariff during 2014 – 2015. In addition
the income from sale of power by DPL to WBSEDCL has been considered after
taking into the selling rate at 380 paise / unit at 132 / 220 KV level and 395 paise
/ unit in the radial mode (33/11 KV) for all the three years of the fourth control
period. The adjustable amount of Rs. 14282.86 lakh for the year 2012 – 2013 are
being allocated to generation and distribution functions in proportion to ARR
determined for generation and distribution functions for the year 2014 – 2015.
Accordingly, the amount of revenue to be recovered through tariff for the year
2014 – 15 works out as under:
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 98
Rupees in Lakh REVENUE RECOVERABLE THROUGH TARIFF, CAPACITY CHARGES AND FIXED CHARGES
IN 2014-2015 Sl. No.
Particulars Generation Distribution Total
1 Aggregate Revenue Requirement for 2014-2015 121646.03 17682.28 139328.31
2 Adjustment for APR for 2012-2013 11811.37 2471.49 14282.86 3 Sub Total (1+2) 133457.40 20153.77 153611.17 4 Fuel Cost 66368.54 - - 5 Power Purchase Cost - 8745.08 - 6 Capacity Charges ( 6 = 3 - 4 ) 67088.86 - - 7 Fixed charges for Distribution (7 = 3 – 5) - 11408.69 -
6.3 The Commission has also worked out the average tariff for the consumers of
DPL for 2014-15 and the same is shown in the table below:
AVERAGE TARRIFF FOR CONSUMERS OF DPL in 2014 – 2015 Sl. No. Particulars Unit Total 1. Total revenue to be recovered through tariff Rs. Lakh 153611.17 2. Revenue from sale of power to WBSEDCL/other licensee Rs. Lakh 30474.45 3. Revenue Recoverable for supply of power to the consumers
(1-2) Rs. Lakh 123136.72
4. Energy sale to the consumers including inter-plant transfer MU 2467.19 5. Average tariff for the consumers (Sl.3 x 10 ÷ Sl. 4) Paisa/ kWh 499.10
6.4 The amount of revenue to be recovered through tariff, capacity charges and fixed
charges for the years 2015-16 and 2016-17 are also worked out as under:
Rupees in Lakh REVENUE RECOVERABLE THROUGH TARIFF, CAPACITY CHARGES AND FIXED CHARGES
IN 2015-2016 Sl. No. Particulars Generation Distribution Total
1 Aggregate Revenue Requirement for 2015-2016 153473.06 21096.49 174569.55
2 Fuel Cost 82185.77 - - 3 Power Purchase Cost - 11848.77 - 4 Capacity Charges (4 = 1 - 2 ) 71287.29 - - 5 Fixed charges for Distribution (5 = 1 – 4) - 9247.72 -
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 99
Rupees in Lakh REVENUE RECOVERABLE THROUGH TARIFF, CAPACITY CHARGES AND FIXED CHARGES
IN 2016-2017 Sl. No. Particulars Generation Distribution Total
1 Aggregate Revenue Requirement for 2015-2016 152697.58 23743.94 176441.52
2 Fuel Cost 82185.77 - - 3 Power Purchase Cost - 14339.14 - 4 Capacity Charges (4 = 1 - 2 ) 70511.81 - - 5 Fixed charges for Distribution (5 = 1 – 4) - 9404.80 -
Tariff Order of DPL for the year 2014 – 2015
ANNEXURE – 6A
West Bengal Electricity Regulatory Commission
100
2014 – 2015 2015 – 2016 2016 – 2017 ADMITTED ADMITTED ADMITTED
1 Fuel 66368.54 82185.77 82185.772 Employee Cost 6269.59 6838.23 7458.473 Centrally Maintained Exp 522.26 569.62 621.294 Coal and ash handling expenses 1637.82 2108.86 2214.315 Water Charges 2373.25 2913.73 2913.736 Operation & Maintenance expenses 4591.15 5609.80 6006.607 Rates & Taxes 5.00 5.00 5.008 Insurance 92.00 99.00 106.009 Depreciation 9122.36 13382.20 13382.20
10 Advance Against Depreciation 2454.07 2556.16 2556.1611 Write off of Intangible assets 0.00 0.00 0.0012 Interest on borrowed Capital 13892.70 20765.15 18890.2713 Interest on Working Capital 1227.15 1568.35 1558.0214 Other Finance Charges 1847.41 1781.69 1713.4815 Income tax 0.00 0.00 0.0016 Reserve for unforeseen exigencies 478.29 903.21 903.2117 ROE 11063.43 12488.07 12488.0718 Demurrage 0.00 0.00 0.0019 Development Fund 0.00 0.00 0.0020 Gross Revenue requirement ( 20 = sum 1 to 19) 121945.02 153774.84 153002.5821 Less Misc. other income 298.99 301.78 305.0022 Less: Interest Credit 0.00 0.00 0.0023 Net Total Revenue Required (23 = 20 – 21 - 22) 121646.03 153473.06 152697.58
GENERATION FIXED COST OF DPL (Rs. in lakh)Sl. No. PARTICULARS
Tariff Order of DPL for the year 2014 – 2015
ANNEXURE – 6B
West Bengal Electricity Regulatory Commission
101
2014 – 2015 2015 – 2016 2016 – 2017 ADMITTED ADMITTED ADMITTED
1 Power Purchase Cost 8745.08 11848.77 14339.142 Employee Cost 2140.82 2335.00 2546.783 Centrally Maintained Expenses 214.08 233.50 254.684 Water Charges 0.00 0.00 0.00
Operation & Maintenance Expenses(a) Other Administrative & General Expenses. 637.00 674.00 713.00(b) Legal & professional Charges 0.00 0.00 0.00(c) Audit Fees 0.82 0.90 1.00(d) Repair & Maintenance including Consumables 1213.00 1236.00 1259.00
Total 1850.82 1910.90 1973.006 Interest on borrowed capital 1457.19 1338.75 1215.407 Interest on working capital 0.00 0.00 0.008 Other Finance Charges 56.39 40.40 24.549 Interest on consumers' security deposit 58.71 64.58 71.03
10 Depreciation 1089.67 1260.24 1260.2411 Advance against Depreciation 0.00 0.00 0.0012 Write off of Intangible assets 0.00 0.00 0.0013 Bad debts written off 0.00 0.00 0.0014 Reserve for unforeseen exigencies 51.59 51.59 51.5915 ROE 2535.68 2535.68 2535.6816 Gross Revenue requirement 18200.03 21619.41 24272.0817 Less Misc. other income 517.75 522.92 528.1418 Net Total Revenue Required 17682.28 21096.49 23743.94
Sl. No. Particulars
5
FIXED COST OF DISTRIBUTION FUNCTION OF DPL (RS. IN LAKH)
Tariff Order of DPL for the year 2014 – 2015
ANNEXURE – 6C
West Bengal Electricity Regulatory Commission
102
2014 – 2015 2015 – 2016 2016 – 2017 ADMITTED ADMITTED ADMITTED
1 Fuel 66368.54 82185.77 82185.772 Power Purchase 8745.08 11848.77 14339.143 Employee Cost 8410.41 9173.23 10005.254 Centrally Maintained Exp 736.34 803.12 875.975 Coal and ash handling expenses 1637.82 2108.86 2214.316 Water Charges 2373.25 2913.73 2913.737 Operation & Maintenance expenses 6441.97 7520.70 7979.608 Rates & Taxes 5.00 5.00 5.009 Insurance 92.00 99.00 106.00
10 Depreciation 10212.03 14642.44 14642.4411 Advance Against Depreciation 2454.07 2556.16 2556.1612 Write off of Intangible assets 0.00 0.00 0.0013 Interest on borrowed Capital 15349.89 22103.90 20105.6714 Interest on Working Capital 1227.15 1568.35 1558.0215 Other Finance Charges 1903.80 1822.09 1738.0216 Bad Debts written off 0.00 0.00 0.0017 Income tax 0.00 0.00 0.0018 Interest on Consumers' Security Deposit 58.71 64.58 71.0319 Reserve for unforeseen exigencies 529.88 954.80 954.8020 ROE 13599.11 15023.75 15023.7521 Demurrage 0.00 0.00 0.0022 Development Fund 0.00 0.00 0.0023 Gross Revenue requirement ( 23 = sum 1 to 22) 140145.05 175394.25 177274.6624 Less Misc. other income 816.74 824.70 833.1425 Less: Interest Credit 0.00 0.00 0.0026 Net Total Revenue Required (26 = 23 – 24 - 25) 139328.31 174569.55 176441.52
Sl. No. PARTICULARS
TOTAL AGGREGATE REVENUE OF DPL (RS. IN LAKH)
Tariff Order of DPL for the year 2014 – 2015
CHAPTER - 7 TARIFF ORDER FOR 2014 – 2015
West Bengal Electricity Regulatory Commission 103
7.1 As mentioned in the previous chapter, the Commission, in accordance with the
Tariff Regulations, has determined for DPL the Aggregate Revenue Requirement
(ARR) for each year of the fourth control period, covering the years 2014-15 to
2016-17, and the revenue recoverable through tariff during 2014 – 2015 after all
the necessary adjustment as discussed in chapter 6. The tariff schedule
applicable to the consumers of DPL in 2014 – 2015 and the associated terms
and conditions given below are based on the category wise sale projected by
DPL for the year 2014 -2015. The Commission has observed that the projected
sales for 132 KV consumers during the year 2014 – 2015 are at a higher level
than that of previous year (about four times of actual sale to 132 KV consumers
during 2012 – 2013). On the other hand sale to consumers at 11 KV is projected
at a lower level than that of 2012 – 2013. These have caused reduction in
average rate at the existing tariff for 2013 – 2014. DPL has not given any reason
for such projection. The Commission has given necessary direction in this regard
in chapter – 8 of this order.
7.2 The tariff schedule as applicable to the consumers of DPL in the year 2014 –
2015 is given at Annexure - 7A1 for LV and MV consumers and at Annexure -
7A2 for HV and EHV consumers.
7.3 Details of different tariff schemes of different classes of consumers and various
associated terms and conditions are specified in various regulations and in
Annexure – C1 and Annexure – C2 of the Tariff Regulations. Other associated
conditions of the tariff for 2014 – 2015 shall be as follows.
7.3.1.1 In order to reduce the overall system T&D loss and to flatten the load curve by
improving the existing system load factor of DPL, the HT consumers shall receive
a voltage wise graded load factor rebate as per the following table:
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 104
LOAD FACTOR REBATE (Paise / KWH)
Range of Load Factor (LF) Supply Voltage 11 kV 33 kV 132 kV
Above 55% Up to 60% 1 2 3 Above 60% Up to 65% 2 3 4 Above 65% Up to 70% 3 4 5 Above 70% Up to 75% 10 11 12 Above 75% Up to 80% 12 13 14 Above 80% Up to 85% 14 15 16 Above 85% Up to 90% 16 17 18 Above 90% Up to 92% 18 19 20 Above 92% Up to 95% 22 24 25 Above 95% 25 27 28
7.3.1.2 The above load factor rebate shall be applicable on quantum of energy
consumed in a billing period (for example one 11 KV consumer at 85% load
factor shall be eligible for a rebate @ 14 paise / KWh on the total quantum of
energy consumed in a billing period).
7.3.1.3 Load factor surcharge shall continue at the prevailing rate for those categories of
consumers to whom these are applicable at present.
7.3.1.4 Load factor rebate and load factor surcharge shall be computed in accordance
with the formula and associated principles given in regulations 3.9.2, 3.9.3 and
3.9.4 of the Tariff Regulations and at the rates mentioned in paragraphs 7.3.1.1
and 7.3.1.3 above.
7.3.2.1 The fixed charge shall be applicable to different categories of consumers at the
rates as shown in Annexure 7A1 and Annexure 7A2 of this tariff order.
7.3.2.2 The demand charge shall be applicable to different categories of consumers as
per rates as shown in Annexure 7A1 and Annexure 7A2 of this order on the
basis of recorded demand as specified in regulation 4.3.3 of the Tariff
Regulations subject to the conditions as specified in the Tariff Regulations.
7.3.2.3 When a new consumer gets connected to the system, the computation of fixed
charge or demand charge for that month shall be made pro-rata for the number
of days of supply in that particular month.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 105
7.3.3 Subject to the conditions as specified in regulation 4.13 of the Tariff Regulations,
the minimum charge shall continue at the existing level for all consumers.
7.3.4 The applicable rate of temporary supply for a consumer during the year 2014 -
2015 shall be the same rate at which he is being charged prior to issue of this
order.
7.3.5 For all consumers, excluding consumers having pre-paid meters, rebate shall be
given @ 1% of the amount of the bill excluding meter rent, taxes, duties, levies
and arrears (not being the arrears due to revision of tariff) if the payment is made
within the due date.
7.3.6 In addition to the rebate under paragraphs 7.3.5 above, if the payment is made
within due date, then an additional rebate of 1% of the amount of the bill
excluding meter rent, taxes, duties, levies and arrears (not being arrears due to
revision of tariff) would be allowed to the consumers who would pay their energy
bills through e-payment facility (through web by using net banking, debit card,
credit card, electronic clearing scheme) as introduced by DPL. This rebate is
applicable after giving effect under paragraphs 7.3.5. A rebate of Rs. 5.00 will be
admissible prospectively if any consumer opts for e-bill following regulation
3.1.10 of West Bengal Electricity Regulatory Commission (Electricity Supply
Code) Regulations, 2013. These rebates are applicable after giving effect under
paragraphs 7.3.5.
7.3.7.1 The power factor rebate and surcharge shall continue for those categories of
consumers to whom these are applicable at present. The rate of rebate and
surcharge and methods of calculation of such rebate and surcharge for the year
2014 – 2015 are given below:
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 106
7.3.7.2 The above rebate and surcharge against different time periods shall be reflected
in the bill separately and shall be treated separately.
7.3.8 For short-term supply, emergency supply and supply for construction power no
rebate or surcharge will be applicable for power factor and load factor.
7.3.9 Delayed payment surcharge shall be applicable as per regulation 4.14 of the
Tariff Regulations.
7.3.10 All existing charges relating to meter rent, meter testing, meter replacement, fuse
call charges, disconnection and reconnection etc. shall continue.
Power Factor (PF) Range
Power Factor Rebate & Surcharge on Energy Charge in Percentage for the year 2014-15
For Consumers under TOD Tariff For Consumers under non-TOD
Tariff Normal Period
(6.00 AM to 5.00 PM)
Peak Period (5.00 PM to 11.00
PM)
Off-peak Period (11.00 PM to 6.00
AM) Rebate
in % Surcharge in %
Rebate in %
Surcharge in %
Rebate in %
Surcharge in %
Rebate in %
Surcharge in %
PF > 0.99 7.00 0.00 8.00 0.00 6.00 0.00 5.00 0.00 PF > 0.98 & PF < 0.99 6.00 0.00 7.00 0.00 5.00 0.00 4.00 0.00 PF > 0.97 & PF < 0.98 5.00 0.00 6.00 0.00 4.00 0.00 3.00 0.00 PF > 0.96 & PF < 0.97 4.00 0.00 5.00 0.00 3.00 0.00 2.50 0.00 PF > 0.95 & PF < 0.96 3.00 0.00 4.00 0.00 2.00 0.00 2.00 0.00 PF > 0.94 & PF < 0.95 2.25 0.00 3.00 0.00 1.50 0.00 1.50 0.00 PF > 0.93 & PF < 0.94 1.50 0.00 2.00 0.00 1.00 0.00 1.00 0.00 PF > 0.92 & PF < 0.93 0.75 0.00 1.00 0.00 0.50 0.00 0.50 0.00 PF > 0.86 & PF < 0.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 PF > 0.85 & PF < 0.86 0.00 1.00 0.00 1.25 0.00 0.75 0.00 0.75 PF > 0.84 & PF < 0.85 0.00 2.00 0.00 2.50 0.00 1.50 0.00 1.50 PF > 0.83 & PF < 0.84 0.00 2.50 0.00 3.25 0.00 1.75 0.00 1.75 PF > 0.82 & PF < 0.83 0.00 3.00 0.00 4.00 0.00 2.00 0.00 2.00 PF > 0.81 & PF < 0.82 0.00 4.00 0.00 5.00 0.00 3.00 0.00 2.50 PF > 0.80 & PF < 0.81 0.00 5.00 0.00 6.00 0.00 4.00 0.00 3.00 PF <0.80 0.00 6.00 0.00 7.00 0.00 5.00 0.00 3.50
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 107
7.3.11 A consumer opting for pre-paid meter shall not be required to make any security
deposit on the energy charge.
7.3.12 All statutory levies like Electricity Duty or any other taxes, duties etc. imposed by
the State Govt. / Central Govt. or any other competent authority shall be extra
and shall not be a part of the tariff as determined in this order.
7.3.13 All the rates and conditions of tariff for 2014-15 are effective from 1st
7.3.14 For 2014-15 the consumer and other licensee shall have to pay/shall be refunded
the difference of the following two:
April 2014
and onwards except where specific date is mentioned. The rate will continue till
further tariff order of the Commission.
i) tariff as declared under this order for 2014-15, and
ii) what they actually already paid for the concerned period as tariff and the
MVCA, if any, for the concerned month.
Adjustments, if any, for over recovery / under recovery for 2014-15 from the
energy recipients shall be made in 20 (twenty) equal monthly installments
through subsequent energy bills and such adjustment will start from the energy
bills raised on or after 1st
7.3.15 There will be no separate monthly variable cost adjustment (MVCA) or Adhoc
FPPCA for DPL on and from 01.04.2014 to till the date of issue of this order. The
MVCA or Adhoc FPPCA realized by DPL during the year 2014-15 shall be
March, 2015 in respect of L&MV consumers. The
adjustment in respect of High and Extra High voltage consumers shall be made
in 20 (twenty) instalments through subsequent energy bills and will start from the
month immediately after completion month of recovery of arrear amount as per
tariff order 2013 – 2014.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 108
adjusted in computation of any adjustments for over/under recovery from the
energy recipients as mentioned in paragraph 7.3.14 above.
7.3.16 In addition to the tariff determined under this tariff order, DPL would further be
entitled to additional sums towards enhanced cost of fuel and power purchase, if
any, after the date from which this tariff order takes effect. Thus DPL shall also
realize MVCA for any subsequent period after issuing of this order as per
provisions of the Tariff Regulations based on the tariff of this order. The fuel and
power purchase cost shall be subject to adjustment in accordance with the Tariff
Regulations through MVCA and/or FPPCA.
7.3.17 Optional TOD tariff scheme for LT Commercial, LT Industrial and LT Public
Water Works categories of consumers having minimum contract demand of 30
KVA, which was directed to be introduced in the tariff order for 2007-08, shall
continue and energy charge under such scheme shall be computed according to
regulation 4.12 of the Tariff Regulations, wherever applicable, if no tariff rates for
such consumers are mentioned in the tariff schedule.
7.3.18 For any pre-paid and TOD tariff scheme, other charges shall be the charges
applicable to consumers under respective category of non-TOD tariff.
7.3.20 An applicant for short term supply through pre-paid meter shall have to comply
with all necessary formalities for obtaining supply including payments in
accordance with the Regulations made by the Commission. The same will be
subject to the following conditions:
a) Provision of requisite meter security deposit to be kept with the licensee.
b) Provision of space for installing weather-proof, safe and secured terminal
services apparatus to protect sophisticated meter; and
c) Availability of prepaid-meter of appropriate capacity.
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 109
7.3.21 For a consumer with prepaid meter who has purchased voucher prior to the date
of issue of this order, the existing voucher will continue till such voucher is
exhausted.
7.3.22 To avail the rate for street lighting with LED [(Rate D (2)], the supply should be
metered and all the street lights under the same meter shall be illuminated with
LED. For mixed type of street lights under single meter the rate D(1) shall be
applicable.
7.3.23 The tariffs determined under this order for different categories of consumers are
the maximum ceilings for supply of electricity at any agreed price to the
consumers only for those areas of supply of DPL where multiple licensees exist.
However, if supply is effected to a consumer at a price lesser than the upper
ceiling, and as a result the licensee incurs loss, such loss shall not be allowed to
be passed on to any other consumers or any other distribution licensees of the
Commission.
7.3.24 Energy sale rate of DPL to WBSEDCL during the year 2014 – 2015 and onwards
shall be as per the rate approved in the tariff order of WBSEDCL for the year
2014-2015 in case no. TP – 61 / 13 – 14 for purchase of power by WBSEDCL
from DPL.
7.3.25 Any matter, which has not been explicitly mentioned in this order, shall be guided
by regulations 2.9.8 and 2.9.9 of the Tariff Regulations.
7.4 It is open to the State Government to grant any subsidy to any consumer or any
class of consumers in the tariff determined by the Commission for DPL. If at all
any such subsidy under the provisions of the Act is intimated to DPL and to the
Commission by the Government of West Bengal with clear indication of the
consumer or class of consumers to be subsidized and the amount of the subsidy
Tariff Order of DPL for the year 2014 – 2015
West Bengal Electricity Regulatory Commission 110
proposed to be given is paid in advance, the tariff of such consumer and / or the
class of consumers shall be deemed to have been reduced accordingly as has
been indicated by the State Government. However, such direction of the State
Government shall not be operative till the payment is made by the State
Government in accordance with the provisions of the Act and the Regulations
made thereunder and the tariff as fixed by the Commission shall remain
applicable. In accordance with the Tariff Regulations, the State Government is
required to communicate, within 15 days from the date of receipt of a tariff order,
whether it shall give any subsidy to any group of consumers etc.
7.5 DPL shall present to the Commission a gist of this order in accordance with
regulation 2.9.6 of the Tariff Regulations within three working days from the date
of receipt of this order for approval of the Commission and on receipt of the
approval shall publish the approved gist in terms of aforesaid regulation within
four working days from the date of receipt of the approval of the Commission.
Tariff Order of DPL for 2014-15
Annexure -7A1
West Bengal Electricity Regulatory Commission 111
Energy Charge P/kwh
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
Name of the Tariff Scheme
Energy Charge P/kWh
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
Consumer category
Name of the Tariff Scheme
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
1. Life Line
Consumer (Domestic)
250 5
First 25 345
Next 25 420
Next 50 435
Next 100 467
First 60 431 453
Next 40 472 498
Next 200 492
above 300 50506.00 hrs to 17.00
hrsAll units 313 All units 305
17.00 hrs to 23.00
hrs.All units 626 All units 610
23.00 hrs to 06.00
hrsAll units 172 All units 168
LOW AND MEDIUM VOLTAGE CONSUMERS
Optional tariff SchemeOptional Tariff Scheme - II
Type of Consumer
Monthly consumption in
KWH
Energy Charge P/kWh
Monthly consumption in
KWH
Applicable Tariff Scheme
Consumer category
Consumer category
NOT APPLICABLE
0 to 25
10 All Units 418
NOT APPLICABLE
10Rate
C(3R)pp/ C(3U)pp
Prepaid
Name of the Tariff Scheme
Optional Tariff Scheme – IMonthly consumption in
KWH
Normal
300 499
3. 20
Next 100 486
2. Rate
C(3R)/ C(3U)
Normal
Rate C(4-R) / C(4-U)
Normal
Rate C(5t)
Rate C(4-R)pp/C(4-U)pp
20Normal TOD 20
Commercial (Rural) or
Commercial (Urban)
Irrigation pumping for Agriculture
06.00 hrs to 17.00 hrs
17.00 hrs to 23.00 hrs.
23.00 hrs to 06.00 hrs
Sl No
Rate C(5)4.
NOT APPLICABLE
Domestic (Rural) or Domestic (Urban)
Above
Pre-Paid TOD
23.00 hrs to 06.00 hrs. 417
20
06.00 hrs to 17.00 hrs06.00 hrs to 17.00 hrs
Normal TOD 20
448
421
17.00 hrs to 23.00 hrs. 493
NOT APPLICABLE
17.00 hrs to 23.00 hrs.
Rate C(4-
R)ppt/C(4-U)ppt
Prepaid- TOD
23.00 hrs to 06.00 hrs.
Tariff Order of DPL for 2014-15
Annexure -7A1
West Bengal Electricity Regulatory Commission 112
Energy Charge P/kwh
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
Name of the Tariff Scheme
Energy Charge P/kWh
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
Consumer category
Name of the Tariff Scheme
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
LOW AND MEDIUM VOLTAGE CONSUMERS
Optional tariff SchemeOptional Tariff Scheme - II
Type of Consumer
Monthly consumption in
KWH
Energy Charge P/kWh
Monthly consumption in
KWH
Applicable Tariff Scheme
Consumer category
Consumer category
Name of the Tariff Scheme
Optional Tariff Scheme – IMonthly consumption in
KWHSl No
06.00 hrs to 17.00
hrsAll units 477
17.00 hrs to 23.00
hrs.All units 760
23.00 hrs to 06.00
hrsAll units 315
06.00 hrs to 17.00
hrsAll units 432
17.00 hrs to 23.00
hrs.All units 691
23.00 hrs to 06.00
hrsAll units 285
06.00 hrs to 17.00
hrsAll units 482
17.00 hrs to 23.00
hrs.All units 771
23.00 hrs to 06.00
hrsAll units 318
40
40 NOT APPLICABLE
Prepaid- TOD NOT APPLICABLE
20Short Term Irrigation Supply
Short Term supply for
Commercial Plantation
Rate C(5)-stis
Rate C(4)-stcp
5. Commercial Plantation
Rate C(4) cp
Prepaid- TOD
7.
6. Prepaid- TOD NOT APPLICABLE NOT APPLICABLE
NOT APPLICABLE
NOT APPLICABLE
Tariff Order of DPL for 2014-15
Annexure -7A1
West Bengal Electricity Regulatory Commission 113
Energy Charge P/kwh
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
Name of the Tariff Scheme
Energy Charge P/kWh
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
Consumer category
Name of the Tariff Scheme
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
LOW AND MEDIUM VOLTAGE CONSUMERS
Optional tariff SchemeOptional Tariff Scheme - II
Type of Consumer
Monthly consumption in
KWH
Energy Charge P/kWh
Monthly consumption in
KWH
Applicable Tariff Scheme
Consumer category
Consumer category
Name of the Tariff Scheme
Optional Tariff Scheme – IMonthly consumption in
KWHSl No
06.00 hrs to 17.00
hrsAll units 532
17.00 hrs to 23.00
hrs.All units 585
23.00 hrs to 06.00
hrsAll units 495
On all units
On all units
On all units
On all units
On all units
In Municipal Area/ Non-
Municipal Area
On all units
First 100 419 All units 434
Next 200 477 All units 477
Above 300 489 All units 40423.00 hrs to 06.00 hrs
06.00 hrs to 17.00 hrs
23.00 hrs to 06.00
hrs
491451Rate
C(2-U)
NOT APPLICABLE
Prepaid 24Rate C(2-U)pp On all UnitsOn all Units
Public utility /Specified Institution
Public Bodies
Rate C(sts)
Rate C(4 - ii)
40
Normal 12
Prepaid - TOD
24Normal
8. Short-term Supply
10.
Cottage Industry / Artisan /
Weavers / Small production
oriented establishment
9.
11. NOT APPLICABLE
462
Rate C(4 -ii) ppt
Prepaid - TOD
17.00 hrs to 23.00 hrs
Rate C (2-U) ppt
Prepaid TOD
NOT APPLICABLE
446
24
415
17.00 hrs to 20.00
hrs.
06.00 hrs. – 17.00 hrs. &
20.00 hrs - 23.00 hrs.
NOT APPLICABLE
12
Government School,
Government aided School
and Government sponsored
School
Rate C(GS) Normal On all Units 341 20370
326
Rate C(GSt)
Normal TOD
06.00 hrs. – 17.00 hrs. & 20.00 hrs - 23.00 hrs.
2017.00 hrs to 20.00 hrs.
23.00 hrs to 06.00 hrs
336
Tariff Order of DPL for 2014-15
Annexure -7A1
West Bengal Electricity Regulatory Commission 114
Energy Charge P/kwh
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
Name of the Tariff Scheme
Energy Charge P/kWh
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
Consumer category
Name of the Tariff Scheme
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
LOW AND MEDIUM VOLTAGE CONSUMERS
Optional tariff SchemeOptional Tariff Scheme - II
Type of Consumer
Monthly consumption in
KWH
Energy Charge P/kWh
Monthly consumption in
KWH
Applicable Tariff Scheme
Consumer category
Consumer category
Name of the Tariff Scheme
Optional Tariff Scheme – IMonthly consumption in
KWHSl No
First 100 428 All units 444
Next 200 443 All units 488
Above 300 490 All units 413
All Units 453
All Units 602
All Units 340
First 500 476 All Units 480
All Units 634
All Units 360
15. Street Lighting Rate D(1) 438 30
06.00 hrs to 17.00 hrs
17.00 hrs to 23.00 hrs
23.00 hrs to 06.00 hrs
06.00 hrs. – 17.00 hrs. & 20.00 hrs -
23.00 hrs.
NOT APPLICABLE
17.00 hrs to 20.00 hrs.
23.00 hrs to 06.00 hrs
Prepaid - TOD
30
06.00 hrs to 17.00 hrs
17.00 hrs to 23.00 hrs
23.00 hrs to 06.00 hrs
Rate C(4 -iii)ppt12
Rate B (II) Normal On all Units
Public Water Works &
Sewerage System
12.
13.
Poultry, Duckery, Horticulture,
Tissue culture, Floriculture,
Herbal – Medicinal – Bio-
diesel Plant Farming, Food
Processing Unit
Rate C(4 -iii) Normal
Rate C(1) Normal
30
NOT APPLICABLE
462 NOT APPLICABLE
12
Rate B (II)ppt 30
Prepaid - TOD
NOT APPLICABLE
Normal On all Units
14.
Industry (Rural) or Industry (Urban) Above 500 487
30 Rate C(1t)
Normal - TOD
NOT APPLICABLE
Tariff Order of DPL for 2014-15
Annexure -7A1
West Bengal Electricity Regulatory Commission 115
Energy Charge P/kwh
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
Name of the Tariff Scheme
Energy Charge P/kWh
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
Consumer category
Name of the Tariff Scheme
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
LOW AND MEDIUM VOLTAGE CONSUMERS
Optional tariff SchemeOptional Tariff Scheme - II
Type of Consumer
Monthly consumption in
KWH
Energy Charge P/kWh
Monthly consumption in
KWH
Applicable Tariff Scheme
Consumer category
Consumer category
Name of the Tariff Scheme
Optional Tariff Scheme – IMonthly consumption in
KWHSl No
16 Street Lighting (LED)
Rate D(3) 374 30
On all Units 487
On all Units 536
On all Units 453
06.00 hrs to 17.00
hrs
On all Units 614
17.00 hrs to 23.00
hrs
On all Units 810
23.00 hrs to 06.00
hrs
On all Units 461
06.00 hrs. – 17.00
hrs. & 20 .00 hrs to 23.00 hrs
On all Units 494
17.00 hrs to 20.00
hrs.
On all Units 627
23.00 hrs to 06.00
hrs
On all Units 420
NOT APPLICABLE
40 NOT APPLICABLE
30Rate D(5)t
NOT APPLICABLE
18.
Construction Power Supply19.
Rate D(6)
24
Prepaid- TOD
Prepaid-TOD
Emergency Supply
Rate D(7)
Rate D(5)
NOT APPLICABLE
30 17.00 hrs to 20.00 hrs
23.00 hrs to 06.00 hrs
Normal TOD
NOT APPLICABLE
06.00 hrs to 17.00 hrs & 20.00 hrs to
23.00 hrs
On all Units17.
Private Educational Institutions
and Hospitals
Normal 497
On all UnitsNormal
NOT APPLICABLE
NOT APPLICABLE
Tariff Order of DPL for 2014-15
Annexure -7A1
West Bengal Electricity Regulatory Commission 116
Energy Charge P/kwh
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
Name of the Tariff Scheme
Energy Charge P/kWh
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
Consumer category
Name of the Tariff Scheme
Fixed Charge/ Demand
Charge* in Rs/KVA/
mon
LOW AND MEDIUM VOLTAGE CONSUMERS
Optional tariff SchemeOptional Tariff Scheme - II
Type of Consumer
Monthly consumption in
KWH
Energy Charge P/kWh
Monthly consumption in
KWH
Applicable Tariff Scheme
Consumer category
Consumer category
Name of the Tariff Scheme
Optional Tariff Scheme – IMonthly consumption in
KWHSl No
On all Units 404
On all Units 444
On all Units 376
06.00 hrs. – 17.00
hrs. & 20 .00 hrs to 23.00 hrs
On all Units 465
17.00 hrs to 20.00
hrs.
On all Units 614
23.00 hrs to 06.00
hrs
On all Units 349
21.
20
30Rate D(8)
Rate D(2)
Prepaid - TOD
Common Services of Industrial
Estate
Normal
Bulk Supply at single point to Co-operative
Group Housing
Society for providing
power to its members or person for providing
power to its employees in a
single premises
20.
06.00 hrs to 17.00 hrs
All units 409
NOT APPLICABLE NOT APPLICABLE
NOT APPLICABLENormal - TOD 20
23.00 hrs to 06.00 hrs
Rate D(2t)
17.00 hrs to 23.00 hrs
Tariff Order of DPL for 2014-15
Annexure-7A2
West Bengal Electricity Regulatory Commission 117
Demand Charge
Demand Charge
(Rs./ KVA/ month)
(Rs./ KVA/ month)
Summer Monsoon Winter Summer Monsoon Winter
06.00 hrs-17.00 hrs
&20.00 hrs-23.00 hrs
17.00 hrs-20.00 hrs All Units 443 441 439
23.00 hrs-06.00 hrs All Units 375 373 371
06.00 hrs-17.00 hrs
&20.00 hrs-23.00 hrs
17.00 hrs-20.00 hrs All Units 438 436 433
23.00 hrs-06.00 hrs All Units 370 368 366
06.00 hrs-17.00 hrs All Units 490 488 486
17.00 hrs-23.00 hrs All Units 576 573 571
23.00 hrs- 06.00 hrs All Units 417 415 413
06.00 hrs-17.00 hrs
All Units 480 478 476
17.00 hrs-23.00 hrs
All Units 564 562 559
23.00 hrs- 06.00 hrs
All Units 408 406 405
Sl No
Type of Consumer
Applicable Tariff Scheme
1 Normal All Units 405Public Utility (11 KV)
Optional Tariff Scheme
Consumer category
Name of the Tariff
Scheme
Consumption per month in KWH
Energy Charge
P/kWh
Consumer category
Consumption per month in KWH
394
Rate F(2t)Rate F(2) 320398
320 Rate A(1t) TOD
320Normal - TOD
Energy Charge
401 399
320
Name of the Tariff
Scheme
Normal - TOD
All Units 398 396
3
4 Rate F(1a)
320Normal All Units 494 492 490
Normal -TOD
320
Rate A(1a)
Rate A(2)
Public Utility (33 KV)
401
396Normal All Units 4002
403
HIGH & EXTRA HIGH VOLTAGE CONSUMERS
Industries (11 KV)
Industries (33 KV)
P/kWh
Rate A(2t)
320
All Units 403
NOT APPLICABLE
Tariff Order of DPL for 2014-15
Annexure-7A2
West Bengal Electricity Regulatory Commission 118
Demand Charge
Demand Charge
(Rs./ KVA/ month)
(Rs./ KVA/ month)
Summer Monsoon Winter Summer Monsoon Winter
Sl No
Type of Consumer
Applicable Tariff Scheme
Optional Tariff Scheme
Consumer category
Name of the Tariff
Scheme
Consumption per month in KWH
Energy Charge
P/kWh
Consumer category
Consumption per month in KWH
Energy ChargeName of the Tariff
Scheme
HIGH & EXTRA HIGH VOLTAGE CONSUMERS
P/kWh
06.00 hrs-17.00 hrs
All Units 471 469 467
17.00 hrs-23.00 hrs
All Units 553 551 549
23.00 hrs- 06.00 hrs
All Units 400 399 397
06.00 hrs-17.00 hrs
All Units 444 442 440
17.00 hrs-23.00 hrs
All Units 799 796 792
23.00 hrs- 06.00 hrs
All Units 293 292 290
06.00 hrs-17.00 hrs
All Units 446 444 442
17.00 hrs-23.00 hrs
All Units 714 710 707
23.00 hrs- 06.00 hrs
All Units 294 293 292
06.00 hrs-17.00 hrs
All Units 466 464 462
17.00 hrs-23.00 hrs
All Units 746 742 739
23.00 hrs- 06.00 hrs
All Units 308 306 305
5
6Community Irrigation/ Irrigation
Normal - TOD
8 Rate S(stis)
Rate G(1a)
25Short Term Irrigation Supply
Normal - TOD
Commercial Plantation Rate S(cpt) Normal -
TOD
25Rate S(gt)
3207
Normal -TOD 320Industries
(132 KV) NOT APPLICABLE
NOT APPLICABLE
NOT APPLICABLE
NOT APPLICABLE
Tariff Order of DPL for 2014-15
Annexure-7A2
West Bengal Electricity Regulatory Commission 119
Demand Charge
Demand Charge
(Rs./ KVA/ month)
(Rs./ KVA/ month)
Summer Monsoon Winter Summer Monsoon Winter
Sl No
Type of Consumer
Applicable Tariff Scheme
Optional Tariff Scheme
Consumer category
Name of the Tariff
Scheme
Consumption per month in KWH
Energy Charge
P/kWh
Consumer category
Consumption per month in KWH
Energy ChargeName of the Tariff
Scheme
HIGH & EXTRA HIGH VOLTAGE CONSUMERS
P/kWh
06.00 hrs-17.00 hrs
All Units 451 449 447
17.00 hrs-23.00 hrs
All Units 722 718 715
23.00 hrs- 06.00 hrs
All Units 298 296 295
06.00 hrs-17.00 hrs All Units 499 494 489
17.00 hrs-23.00 hrs All Units 659 652 645
23.00 hrs- 06.00 hrs All Units 359 356 352
06.00 hrs-17.00 hrs All Units 490 485 480
17.00 hrs-23.00 hrs All Units 647 640 634
23.00 hrs- 06.00 hrs All Units 358 354 350
06.00 hrs-17.00 hrs All Units 460 455 450
17.00 hrs-23.00 hrs All Units 607 601 594
23.00 hrs- 06.00 hrs All Units 345 341 338
9
Short Term Supply for
Commercial Plantation
Normal - TOD 320
495Commercial (33 KV) Rate F(3)
495All UnitsNormal
475Commercial (132 KV)
NOT APPLICABLE
320
320
Normal - TOD
All Units
320505
12
Commercial (11 KV) Rate A(3) 500
Normal All Units
Normal - TOD
Normal - TOD
Rate G(3)
11 Normal
10
473 471
Rate A(3t)
Rate F(3t)
Rate G(3t)
493 491
320
320
Rate S(stcp)
320
Tariff Order of DPL for 2014-15
Annexure-7A2
West Bengal Electricity Regulatory Commission 120
Demand Charge
Demand Charge
(Rs./ KVA/ month)
(Rs./ KVA/ month)
Summer Monsoon Winter Summer Monsoon Winter
Sl No
Type of Consumer
Applicable Tariff Scheme
Optional Tariff Scheme
Consumer category
Name of the Tariff
Scheme
Consumption per month in KWH
Energy Charge
P/kWh
Consumer category
Consumption per month in KWH
Energy ChargeName of the Tariff
Scheme
HIGH & EXTRA HIGH VOLTAGE CONSUMERS
P/kWh
06.00 hrs-17.00 hrs All Units 459 457 455
17.00 hrs-23.00 hrs All Units 505 503 501
23.00 hrs- 06.00 hrs All Units 427 425 42306.00 hrs-17.00 hrs
&20.00 hrs-23.00 hrs17.00 hrs-20.00 hrs All Units 565 558 552
23.00 hrs-06.00 hrs All Units 312 309 305
06.00 hrs-17.00 hrs &
&20.00 hrs-23.00 hrs
17.00 hrs-20.00 hrs
All Units 562 553 557
23.00 hrs-06.00 hrs
All Units 320 314 317
422
14 Rate E (pw)
Public Water Works &
Sewerage (11 KV)
Public Water Works &
Sewerage (33 KV)
All Units 465 463 461
446
All Units
450Rate S(c ) Normal All Units
Normal All Units
Normal - TOD
13 Domestic Rate S(d) Normal
320
Normal - TOD 25Rate
S(dt)
Rate E(pwt)
25
15 Rate F(pw)
428
426 419
439 Normal - TOD320437 435
44816
Sports Complex &
Auditorium run by Govt./ local
bodies for cultural affairs
320
NOT APPLICABLE
418423
NOT APPLICABLE
All Units
34
Tariff Order of DPL for 2014-15
Annexure-7A2
West Bengal Electricity Regulatory Commission 121
Demand Charge
Demand Charge
(Rs./ KVA/ month)
(Rs./ KVA/ month)
Summer Monsoon Winter Summer Monsoon Winter
Sl No
Type of Consumer
Applicable Tariff Scheme
Optional Tariff Scheme
Consumer category
Name of the Tariff
Scheme
Consumption per month in KWH
Energy Charge
P/kWh
Consumer category
Consumption per month in KWH
Energy ChargeName of the Tariff
Scheme
HIGH & EXTRA HIGH VOLTAGE CONSUMERS
P/kWh
06.00 hrs-17.00 hrs All Units 441 438 43517.00 hrs-23.00 hrs All Units 582 578 574
23.00 hrs- 06.00 hrs All Units 322 320 318
06.00 hrs-17.00 hrs
All Units 510 500 490
17.00 hrs-23.00 hrs
All Units 714 700 686
23.00 hrs- 06.00 hrs
All Units 383 375 368
06.00 hrs-17.00 hrs & 20.00 hrs.- 23.00 hrs
All Units 432 422 412
17.00 hrs-20.00 hrs
All Units 570 557 544
23.00 hrs-06.00 hrs
All Units 315 308 301
06.00 hrs-17.00 hrs
All Units 440 437 434
17.00 hrs-23.00 hrs
All Units 484 481 477
23.00 hrs- 06.00 hrs All Units 409 406 404
447
25
320
438
320
441All Units 444
451 Rate A(4-pit)
Normal - TOD
Rate S(cot)
NOT APPLICABLE
NOT APPLICABLE
449All Units
Construction Power Supply Rate S(con)19
17
Normal-TOD
NormalCold storage or
Dairy with Chilling Plant
(11 KV)
Rate A(4-pi)
Normal-TOD
20
Bulk Supply at single point to Co-operative Group
Housing Society for providing power to
its members or person for providing
power to its employees in a single premises
NormalRate S(co)
18 Emergency Supply Rate S (ES)
25
320
Normal - TOD
320
Tariff Order of DPL for 2014-15
Annexure-7A2
West Bengal Electricity Regulatory Commission 122
Demand Charge
Demand Charge
(Rs./ KVA/ month)
(Rs./ KVA/ month)
Summer Monsoon Winter Summer Monsoon Winter
Sl No
Type of Consumer
Applicable Tariff Scheme
Optional Tariff Scheme
Consumer category
Name of the Tariff
Scheme
Consumption per month in KWH
Energy Charge
P/kWh
Consumer category
Consumption per month in KWH
Energy ChargeName of the Tariff
Scheme
HIGH & EXTRA HIGH VOLTAGE CONSUMERS
P/kWh
443 433 423
585 572 558
332 325 317
22 Traction (25 KV) Rate T (a) Normal 480 470 460 320
23 Traction (132 KV) Rate T (b) Normal 475 465 455 320
06.00 hrs-17.00 hrs
All Units 490 488 486
17.00 hrs-23.00 hrs
All Units 539 537 535
23.00 hrs- 06.00 hrs
All Units 456 454 452
06.00 hrs-17.00 hrs All Units 462 457 452
17.00 hrs-23.00 hrs All Units 508 503 497
23.00 hrs- 06.00 hrs All Units 430 425 420
26 Inter Plant Transfer Rate IPT Normal 499.10 499.10 499.10 0
320
06.00 hrs-17.00 hrs & 20.00 hrs.- 23.00
hrs
24 Short-term Supply
Normal - TOD
17.00 hrs-20.00 hrs
All Units
All Units
Rate S(st)
23.00 hrs-06.00 hrs
21Common
Services of Industrial
Estate
Rate – E (ict) Normal - TOD
NOT APPLICABLE
NOT APPLICABLE
NOT APPLICABLE
320
Rate E (eit) Normal - TOD 320320
NOT APPLICABLE
25Private
Educational Institutions
Rate E (ei) Normal
All Units NOT APPLICABLE
480 475 470All Units
Tariff Order of DPL for the year 2014 – 2015
CHAPTER - 8 DIRECTION
West Bengal Electricity Regulatory Commission 123
8.1 The Commission has given some direction in different paragraphs in Chapter-4
and Chapter-5 of this order while determining the fuel cost and fixed cost of DPL.
DPL shall comply with those directions. DPL shall also comply with the following
directions:
8.2 In view of the fact that DPL failed to submit their tariff application complete in all
respect for the fourth Control period within the target date of 30th November,
2013 as per provisions of the Tariff Regulations, for the said period no carrying
cost has been and will be provided for the enhanced part of the tariff during
2014-15.
8.3 The Commission has decided that in future any delay in submission of tariff
application by any distribution licensee for any control period beyond the 4th
Further, it is also required to be noted that any delay with or without the approval
of the Commission in submission of either of the applications of APR or FPPCA
of any year (Y) within the target date as specified in the Tariff Regulations of the
following year may result into non-inclusion of the impact of APR and/or FPPCA
order in the concerned tariff order of the year Y+2. In such case, the impact will
be considered in any future year beyond (Y+2) year as applicable without any
allowance for carrying cost, if otherwise applicable. Thus, in filing of
control period or any year as applicable, will result in not providing any increase
in tariff for equal number of days and thus the under recovery due to such
measure will not be allowed to be passed through any tariff mechanism or during
truing up in Annual Performance Review (APR) or Fuel & Power Purchase Cost
Adjustment (FPPCA). Moreover, henceforth any delay in submission in APR or
FPPCA application shall not be considered as ground for delay by the licensee
for submission of tariff application.
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 124
application(s) / petition(s), the licensee is required to maintain the relevant time
schedule(s) as specified in the Tariff Regulations.
It may be further noted that the arrear amount that is to be recovered in a single
or number of installments as will be determined by the Commission for any
financial year due to issuance of delayed tariff order as consequence to delayed
submission of tariff application by the licensee will not be provided with any
carrying cost. Further such matter will be dealt as per direction already issued by
the Commission vide its order in Case no. SM-10/14-15 dated 18.07.2014.
The Commission also observed that during truing up in the APR order of the
distribution licensees and in the Fuel Cost Adjustment (FCA) of the generating
company, a considerable amount is further recoverable by the licensees and the
generating company even after realization of MVCA or MFCA during the year. It
appears that the distribution licensees and the generating company have failed to
understand the true spirit of introduction of the MVCA and MFCA and they are
not considering the eligible cost in computation of their MVCA or MFCA as per
the formula specified in the Tariff Regulations properly. The Commission in terms
of regulation 5.8.12 of the Tariff Regulations directs DPL to compute their MVCA
taking into consideration the related cost in its true sense keeping in their mind
the true spirit of introduction of such monthly adjustment failing which the
Commission will think not to allow such adjustment in full in future or not to pass
the amount as found recoverable on account of FPPCA during truing up in APR
for DPL.
8.4 DPL shall note that as already MVCA has been introduced, the amount that be
claimed in FPPCA at the end of any year is not expected to be higher than the
summated value of following factors:
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 125
i) impact due to rounding off as per note (f) under the sub- paragraph (d) of
paragraph (A) of Schedule - 7B of the Tariff Regulations against the
applicable MVCA for the month of February and March of that year;
ii) impact due to non-recovery of any additional fuel cost of March of any year
over and above what is recovered on the basis of MVCA as calculated from
data of February due to the fact that MVCA calculated on the basis of
data of March becomes applicable for next financial year only,
iii) impact due to application of disallowance of cost as per FPPCA formula at
FPPCA determination stage.
Thus, in such case if recoverable amount under FPPCA of any year is found to
be higher than the above referred summated value then such excess amount
will be dealt as per direction already issued by the Commission vide its order in
case no. SM-10/14-15 dated 18.07.2014. In this context it is to be noted that
such excess amount represent the amount that would have been collected
through MVCA and thus “not raising of such bill” resulted into distorted merit
order dispatch in the system. In fact by virtue of this type of practice there is high
possibility of vitiating the environment of merit order dispatch in the whole supply
chain in West Bengal power sector and thereby affecting the economic load
dispatch in the systems. As a result ultimate sufferer will be the retail consumers
of West Bengal. In view of the above discussions no carrying cost will be
allowed by the Commission in case of creation of such excess amount as
regulatory asset through FPPCA. Whenever such excess amount is released in
number of installments then also it will not be entitled to any carrying cost.
However, this direction shall not be construed as an approval of such delayed
claim of excess fuel cost through FPPCA instead of MVCA and such matter will
be dealt as per direction already issued by the Commission vide its order in case
no. SM-10/14-15 dated 18.07.2014.
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 126
8.5 While declaring MVCA for any month henceforth DPL shall follow the following
directions:
i) Irrespective of change in MVCA in any month from the previous month, the
detail calculation sheet of MVCA prepared for the purpose of determination
of MVCA for that month as per regulation 5.8.9 of the Tariff regulations shall
be submitted to the Commission within seven days of notification of the
MVCA or in case of no notification within thirty days after the end of the
month under consideration for MVCA. Such calculation sheet shall also
specifically mention the received fuel bill which has not been considered or
partly considered in the said MVCA in pursuance to note (g) under sub-
paragraph (e) of paragraph A of Schedule – 7B of the Tariff Regulations.
DPL shall also upload such calculation sheet in their web-site for each
month and shall maintain till three months after the date of publication of
APR order of the concerned year.
ii) In continuation of earlier order vide case no. WBERC/A-35/2 dated 19-02-
2014 Commission again reiterated that DPL will publish the notification of
change of MVCA in terms of 4th
8.6 While submitting the Fuel and Power Purchase Cost Adjustment (FPPCA)
application for any year DPL shall give a list of fuel bill or power purchase bill
which has not been claimed under MVCA calculation along with the provisions of
the Tariff Regulations under which such claim has not been done. A further
reconciliation statement shall be given to establish that DPL has followed the
direction of paragraph 8.4 and. 8.5 above effectively. In case of non submission
of the above documents/ information the application of APR will not be admitted.
paragraph of regulation 5.8.9 of Tariff
Regulations in such daily newspapers which are widely circulated in West
Bengal .Any deviation in this regard will be seriously viewed.
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 127
8.7 While computing the renewable and cogeneration purchase obligations, the
energy generated from Solar roof-top photovoltaic power plants shall be
considered by any distribution licensee both on consumption side and as input
energy from renewable sources towards fulfillment of renewable and
cogeneration purchase obligations in terms of the Electricity Act, 2003 and the
relevant Regulations. The licensee is required to furnish suitable details in this
respect.
8.8 DPL shall submit a report within 01.10.2015 on the following issues:
i) Implementation problem in removing minimum 30 KVA load criterion on
eligibility for TOD conversion.
ii) Possibility of shifting of load of drinking water pumping station, drainage
station and other utility services to non-peak hours through TOD and other
Demand Side Management strategy.
8.9 In the notes of Financial statement of Annual Accounts of 2014-15 and onward or
through Auditor’s Certificate, the following information is to be provided by DPL in
a manner as described below:
i) All the expenditure or cost element considered under tariff applications are
to be provided separately for distribution function and generation function
for the regulatory requirement.
ii) The penalty, fine and compensation under Electricity Act 2003 shall also be
shown separately for distribution function and generation function.
iii) Any fine, penalty or compensation in any other statute other than Electricity
Act 2003 shall be mentioned separately for distribution function and
generation function along with the reference of the statute.
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 128
iv) The figure of AT & C loss for the years concerned in line with the
computation methodology as specified in Form 1.8 of the Tariff Regulations
is to be provided. Beside that AT&C loss calculated with arrear recovery
done for the period prior to the year for which the account is prepared shall
also be shown separately.
In case of non submission of the above documents/ information the application of
APR will not be admitted.
8.10 While submitting APR application of any ensuing year DPL shall submit the
certificate from the statutory auditor of the annual accounts of the said year for
the following parameters.
i) Based on fixed asset register the parameters to be submitted are
a) The distribution line length and transmission line (if any which is
essential part of distribution system as per section 2(72) of Electricity
Act 2003) length in CKM for each level of Voltage related to the assets
of DPL. For the asset which is not owned by the DPL but maintained
by DPL shall be shown separately.
b) Similarly the number of transformers and total installed capacity of
transformers in MVA or KVA for each category of transformers for
distribution system are to be provided.
ii) For the year concerned under the APR the actual number of Consumer, the
consumption level in MU and total connected load in KVA for each category
of consumers on whom the tariff rate has been issued in the tariff order of
the year corresponding to the APR under consideration.
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 129
iii) List of expenditure arises on account of penalty, fine and compensation due
to non-compliance of any statute or statutory order along with the reasons
for each such type of penalty, fine and compensation.
iv) Copies of the audited accounts of all the terminal benefit funds for the year
for which APR is under consideration in a complete shape and not by any
selective pages.
v) A statement showing monthly deposition in different terminal benefit funds
for the year for which APR is under consideration in persuasion to the
direction given in paragraph 8.13. A detail breakup showing total
expenditure and employee strength against each level of all categories of
employees including the whole time directors of the board. If any director
or employee discharge any function of other companies also then the
allocation of cost among the companies shall be shown separately and
distinctly against each level below.
vi) In pursuance to regulation 5.8.1(vi) of Tariff Regulations the licensee/
generating Company shall submit the total demurrage hour and related
demurrage charges paid against total no. of rakes for each generating
station for the year concerned along with the APR/ FPPCA application of
every ensuing year which shall be certified by the auditors.
vii) Henceforth with the application of APR, DPL shall also enclose their
compliance report on Renewable Purchase Obligation power in pursuance
to clause 8 of the West Bengal Electricity Regulatory Commission
(Cogeneration and Generation of Electricity from Renewable Sources of
Energy) Regulations, 2013 or any of its subsequent amendment or
replacement in future.
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 130
In case of non-submission of the above documents, the application of APR will
not be admitted.
8.11 In case of expenditure at a level higher than the admitted amount under any
uncontrollable factor in this tariff order on account of fixed charges, while
submitting APR application of any ensuing year DPL has to justify in detail with
supporting documents and evidence on the basis of which the Commission will
take its decision during truing up exercise and it may be noted that without
sufficient justification the excess expenditure may not be admitted in the APR
fully or partly. Similarly for controllable factors, where applicable as per the Tariff
Regulations, for the same reasons supporting documents and evidence is to be
submitted to justify their claim. While truing up any uncontrollable factor on
account of fixed charges, the actual business volume parameter (Distribution line
length or consumer strength) and actual inflation rate to which such
uncontrollable item is sensitive will be considered in the same manner and
principle as determined under the tariff order subject to the limitation as per the
Tariff Regulations. However, where applicable as per this tariff order the ratio of
expenses increase in % on any item and the sensitivity parameter increase will
remain the same as that of this tariff order.
8.12 While submitting application for APR of 2014-15 and onwards by any licensee, if
such application shows any net claim for that year after considering the
concerned FPPCA, then in such case the licensee shall suggest in specific terms
the ensuing year(s) in which they intend to recover such claim and by what
amount. Licensee shall also show the consequential impact of such recovery in
the expected average cost of supply in those ensuing years after considering the
total revenue recoverable through the tariff. The total revenue recoverable
through the tariff means the summated amount of the Net Aggregate Revenue
Requirement plus all other amount on account of any release of regulatory asset,
FPPCA and APR for any year which is being already decided by the Commission
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 131
in earlier orders. They shall also mention the carrying cost if necessary where it
is applicable in terms of the Tariff Regulations and different orders and direction
in this respect. Above mentioned consequential impact on tariff of ensuing years
shall also be provided in the gist of the APR application.
In case of non submission of the above information the application of APR will
not be admitted.
8.13 In order to ensure that in future actuarial valuation of terminal benefit fund can be
kept in control in a better way by avoiding carrying cost of such liability in future
following is to be adhered.
i) DPL shall ensure that henceforth the amount that is statutorily required to
be deposited in a month in different fund on account of terminal benefit, as
a part of employee cost admitted in the tariff order, is to be deposited in
different terminal benefit funds every month as a first charge item.
ii) On the head of terminal benefit fund, if there is shortage in the deposit
amount in the terminal benefit fund admitted in employee cost through this
order, the balance amount of contribution to terminal benefit fund is
required to be deposited as first charge item over and above what had
already been deposited for the year 2014-15, from the effective date of
recovery of the recoverable amount against this order from the very first
day. So, it is directed that the balance amount of contribution as discussed
above to terminal benefit fund for the year 2014-15, i.e., the difference
between the amount of contribution to terminal benefit funds as allowed in
this order as a part of employee cost and that has already been deposited
in the fund for the year 2014-15, is to be deposited in the respective
different terminal benefit funds. Such balance amount is to be deposited in
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 132
different terminal benefit funds in 12 monthly equal installments from the
date on which the recovery through tariff against this order will start.
iii) While submitting application for APR of 2014 – 2015 , 2015-16 and 2016-
17, DPL shall show through audited accounts of different terminal benefit
funds that the contribution to the different terminal benefit funds during the
concerned year as a part of employee cost is deposited in the terminal
benefit funds.
In case of non-deposition of amount admitted for terminal benefit fund as
provided in (a) to (c) above in the respective fund as directed above, Commission
may withhold or deduct same amount equivalent to amount of non-deposition.
8.14 DPL shall purchase short term power from WBSEDCL if it is found to be
comparable with the short-term market or less. If it is day ahead basis
procurement then such comparable rate will be that of exchange if WBSEDCL
agreed so. Otherwise procurement shall be done from exchange if it is available
in the exchange. In case of weak-ahead purchase corresponding market
segment of exchange shall be the benchmark for comparability. For procurement
above seven days tender shall be done. However, if through a long term PPA the
short term requirement is met from WBSEDCL based on a principle that will
ensure comparable price with market then such can be done subject to the
condition that such PPA is being approved by the Commission.
8.15 DPL shall submit the project cost in respect of unit VII within 30.06.2015. It is to
be noted that the deductable amount for last few years are cumulatively piling up
and in future on compliance of the Commission’s direction on project cost in
pursuance to regulation 2.8.1.4.12 of Tariff Regulations, Commission will come
out with a approved project completion cost on the basis of which the admissible
amount payable for the past years since 2008-09 will be released in at least
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 133
equal number of years and no carrying cost will be provided for that purpose as
DPL is delaying in submission of the finalized project completion cost.
The COD of unit VIII of DPL has been declared as 01.10.2014. In terms of
regulation 2.8.1.4.10 of the Tariff Regulations the performance guarantee test is
to be completed within four months from the date of synchronization and on
completion of performance guarantee test for the unit, detailed results along with
the related documents of such tests are to be submitted along with the next tariff
application or next APR application whichever is earlier. DPL is directed to
conduct the performance guarantee tests, if not yet done, immediately and
submit the details of the performance guarantee tests as per provisions of the
regulations 2.8.1.4.10 of the Tariff Regulations along with their APR application
for 2014 – 2015 failing which 15% of the permitted return will be withheld as per
provisions of the Tariff Regulations.
8.16 All the distribution licensees and generating companies shall follow regulation
5.6.5.1 of the Tariff Regulations in its true spirit. According to regulation 5.6.5.1 of
the Tariff Regulations the interest on working capital requirement of a generating
company or a licensee shall be assessed on normative basis @ 18% on a base
amount derived by summation of annual fixed charges, fuel cost and power
purchase cost reduced by certain elements of the ARR. It has also been
mentioned there that where Monthly Fuel Cost Adjustment (MFCA) or Monthly
Variable Cost Adjustment (MVCA) exists, in that case for interest on working
capital requirement the above normative basis shall be 10% instead of 18% on
the said base amount. In this context it may be noted by all stakeholders that any
distribution licensee or generating company on which collection of MFCA and
MVCA, as the case may be, is applicable as per Tariff Regulations, shall not be
entitled to claim interest on the above referred normative basis of 18% even on
the plea of not claiming MFCA or MVCA throughout any financial year.
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 134
8.17 Every day by 11.30 a.m. DPL shall upload its initial drawal schedule as per the
format under Annexure – IV and also initial injection schedule (i.e., schedule of
Actual Declared Capacity and Notional Declared Capacity) in accordance with
the prevailing State Grid Code framed by WBERC for the next day in their
website. If necessary, for proper representation of the schedule in the website
the format can be altered with approval of the Commission. This schedule shall
be kept in the website till the next two months after the date of the order of the
APR or FPPCA whichever is later in relation to the year concerned to the day
under discussion. The website design shall be such so that the schedule of any
date can be easily fetched. This facility is to be made operational from 1st of April,
2015. DPL is also directed to upload such schedule of every day from 1st April,
2014 to 31st March 2015 within 1st
8.18 The Commission is statutorily duty bound to promote generation of electricity
from following sources of energy:
June 2015. This direction has been issued for
sake of transparency and to protect the interest of all the stakeholders in large.
i) Co-generation of electricity from renewable sources.
ii) Co-generation of electricity from fossil fuel sources.
iii) Co-generation of electricity from hybrid sources of fossil fuel /
conventional sources and renewable sources.
iv) Electricity generation from renewable sources.
In order to promote above mentioned type of generation of electricity by applying
regulations 8.3 and 8.4 of the Tariff Regulations and regulations 19.1 and 19.2 of
the West Bengal Electricity Regulatory Commission (Cogeneration and
Generation of Electricity from Renewable Sources of Energy) Regulations, 2013,
the Commission decides that from the APR of the ensuing year 2016 – 2017 a
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 135
deduction of 5% from Return on Equity will be done if DPL fails to comply with
the Renewable Purchase Obligation as per West Bengal Electricity Regulatory
Commission (Cogeneration and Generation of Electricity from Renewable
Sources of Energy) Regulations, 2013 or any of its subsequent amendment. In
this context, the Commission also directs that henceforth DPL shall advertise on
important national media inviting the interested parties of supplying renewable
and cogeneration electricity on every fourth months for next two years instead of
one time in a year in pursuance to the regulation 3.5 of the said Regulations
8.19 Henceforth, any application for Power Purchase Agreement (PPA), except for
short term PPA meaning PPA for a period not exceeding one year, submitted by
any licensee to the Commission for approval of the PPA shall go through the
process of inviting suggestions and objections from all stakeholders through at
least three well circulated newspaper publication for consideration of the
Commission of all such suggestions and objections as a process of the approval
procedure and subsequent to such approval only, the PPA can be executed by
the licensee and the seller of the power. For this purpose, while submitting the
said PPA the licensee shall also give a draft gist for newspaper publication for
approval of the Commission. On getting approval of the Commission such gist
shall be published in the newspapers within 5 working days. Such gist shall also
be posted in the website along with the application and PPA from the date of gist
publication to at least the last date of submission of suggestions and objections
as will be mentioned in the gist. The gist shall cover the name of seller of the
power, type of specific source (such as coal, gas, hydro, solar, etc.), major
important parameters that are required under the Tariff Regulations for such
purchase and the important points of the purpose of such procurement. The
application submitted shall have the above points of the gist along with detailed
justification of such proposed procurement along with all the information and
parameters that are required under the Tariff Regulations or Regulations of the
Tariff Order of DPL for the year 2011 – 2012 and 2012 – 2013
West Bengal Electricity Regulatory Commission 136
Commission related to renewable and cogeneration sources of energy. The
application shall also clearly spell that how the interest of the consumer as well
as of the licensee has been safeguarded in the PPA. The application without
such gist and the points as mentioned shall not be admitted. This process is
done in order to meet the end of justice after keeping consistency with the
Electricity Act, 2003.
Sd/- SUJIT DASGUPTA
MEMBER
DATE: 04.03.2015