COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT.

10
COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT

Transcript of COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT.

Page 1: COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT.

COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1

COROT

Page 2: COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT.

COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 2

Main events from the last CW (Granada)

INSTRUMENT The Baffle

The problem (eigen frequencies) is understood, thanks to a very strong involvement of ESA, CNES and CSL technical teams.

New design of the feet Qualification is successful Flight Model is already manufactured & under integration

Integration & Test of the Instrument Flight Model has started in CNES-Toulouse

Optical verification under progress First « Image » made with the telescope

SATELLITE Mechanical & Thermal analyses have some delay because of late

inputs from the launcher Critical Design Review under progress Conflict of resources with the CALIPSO mission

Page 3: COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT.

COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 3

Main events from the last CW (Granada)

GROUND SEGMENT Control Segment nominal

Command & Control : under Integration test Flight Dynamics : under interface tests

Mission Segment some issues Very tight schedule Insufficient resources

SYSTEM & OPERATIONS RIS (System Interfaces Review)

Successful Main outcomes are

Conflicts of resources with the Calipso mission have to be closely managed

Exploitation Phase to be quickly assessed (tasks, responsibilities & resources

LAUNCHER contract has started with Arianespace & Starsem

Page 4: COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT.

COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 4

Main events from the last CW (Granada)

SYSTEM & OPERATIONS Reinforcement of the Network of Ground Stations Delay of the Brasilian Ground Station

Location Change from Natal to Alcantara No progress of interface definition for the last 6 months Discussions are slowly restarting

Search for alternatives Use of the MOST ground stations is under discussion Vienna ground station is the likely candidate

Page 5: COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT.

COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 5

Planning

Page 6: COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT.

COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 6

Milestones

System PDROct 2003

Satellite PDRJan 2004

Instrument CDRMay 2004

System Interfaces ReviewMarch 2005

Satellite CDRApril 2005

RPQT

Satellite Qualification Review

Flight Readiness Review

LAUNCH

Satellite I&T Readiness

Page 7: COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT.

COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 7

Next 6 months roadmap

Delivery of the Flight Instrument Delivery of the Flight Platform Preparation & Start of the satellite assembly Integration and test of the Ground Segment Preparation of the System Tests Preparation of operations Prepration of the launch campaign

Ship & Shoot approach (~30 days)

Ground Stations Secure the schedule the Alcantara ground station Perform the compatibility tests with the (MOST) ground station in

Vienna

Page 8: COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT.

COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 8

Start the thinking ofPost-Launch

Activities

Flight Acceptance At least 2 months Development Expertise is required

Technical assessment Trouble shooting

Exploitation A minimal Development Expertise is to be maintained Tasks and associated responsibilities are to be defined Resources needed (incl.preparation of exploitation

Manpower Money

Exploitation Cost sharing A dedicated Steering Committee has to be organized

Page 9: COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT.

COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 9

Budget (qualitative) Status

Instrument expenses are under control (development is over)

Satellite Overcosts are expected because of possible delays

System & Ground Segment Launcher: nominal expenses Control Centre : nominal expenses Mission Centre : serious funding issues

The budget for Exploitation is not defined yet

Page 10: COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT.

COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 10

Synthesis & Conclusion

Technical issues Normal work

Planning The launch of Calipso mission is on the (Corot) critical path

Budget To think of provision for shifts of planning Mission Center (CMC) funding to be increased

Exploitation to be prepared Organization Funding and budget

Conclusion Huge progress of the project, the dream is now reality The COROT team is at full-speed The count-down is still running The COROT satellite is still planned to be launched by the 2006

summertime (NEXT YEAR)