COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1
COROT
COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 2
Main events from the last CW (Granada)
INSTRUMENT The Baffle
The problem (eigen frequencies) is understood, thanks to a very strong involvement of ESA, CNES and CSL technical teams.
New design of the feet Qualification is successful Flight Model is already manufactured & under integration
Integration & Test of the Instrument Flight Model has started in CNES-Toulouse
Optical verification under progress First « Image » made with the telescope
SATELLITE Mechanical & Thermal analyses have some delay because of late
inputs from the launcher Critical Design Review under progress Conflict of resources with the CALIPSO mission
COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 3
Main events from the last CW (Granada)
GROUND SEGMENT Control Segment nominal
Command & Control : under Integration test Flight Dynamics : under interface tests
Mission Segment some issues Very tight schedule Insufficient resources
SYSTEM & OPERATIONS RIS (System Interfaces Review)
Successful Main outcomes are
Conflicts of resources with the Calipso mission have to be closely managed
Exploitation Phase to be quickly assessed (tasks, responsibilities & resources
LAUNCHER contract has started with Arianespace & Starsem
COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 4
Main events from the last CW (Granada)
SYSTEM & OPERATIONS Reinforcement of the Network of Ground Stations Delay of the Brasilian Ground Station
Location Change from Natal to Alcantara No progress of interface definition for the last 6 months Discussions are slowly restarting
Search for alternatives Use of the MOST ground stations is under discussion Vienna ground station is the likely candidate
COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 5
Planning
COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 6
Milestones
System PDROct 2003
Satellite PDRJan 2004
Instrument CDRMay 2004
System Interfaces ReviewMarch 2005
Satellite CDRApril 2005
RPQT
Satellite Qualification Review
Flight Readiness Review
LAUNCH
Satellite I&T Readiness
COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 7
Next 6 months roadmap
Delivery of the Flight Instrument Delivery of the Flight Platform Preparation & Start of the satellite assembly Integration and test of the Ground Segment Preparation of the System Tests Preparation of operations Prepration of the launch campaign
Ship & Shoot approach (~30 days)
Ground Stations Secure the schedule the Alcantara ground station Perform the compatibility tests with the (MOST) ground station in
Vienna
COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 8
Start the thinking ofPost-Launch
Activities
Flight Acceptance At least 2 months Development Expertise is required
Technical assessment Trouble shooting
Exploitation A minimal Development Expertise is to be maintained Tasks and associated responsibilities are to be defined Resources needed (incl.preparation of exploitation
Manpower Money
Exploitation Cost sharing A dedicated Steering Committee has to be organized
COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 9
Budget (qualitative) Status
Instrument expenses are under control (development is over)
Satellite Overcosts are expected because of possible delays
System & Ground Segment Launcher: nominal expenses Control Centre : nominal expenses Mission Centre : serious funding issues
The budget for Exploitation is not defined yet
COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 10
Synthesis & Conclusion
Technical issues Normal work
Planning The launch of Calipso mission is on the (Corot) critical path
Budget To think of provision for shifts of planning Mission Center (CMC) funding to be increased
Exploitation to be prepared Organization Funding and budget
Conclusion Huge progress of the project, the dream is now reality The COROT team is at full-speed The count-down is still running The COROT satellite is still planned to be launched by the 2006