Core Network Planning Cell, 614, Bharat Sanchar Bhavan ... · PDF filePresentation to...

37
Page 1 of 37 [email protected] No: 66-07/CNP / MNGT / 09 /51 Dt: 21/12/2009 Sub : Presentation by CNP Cell to Management Committee of BSNL board on Analysis of NIB-II MPLS network along with Recommendation for MNGT 1. A presentation was given by Core Network Planning (CNP) cell indicating the broad points observed while carrying out the analysis of the NIB-II MPLS with respect to traffic generating trends of different access networks such as broadband, IP TAX, Wi- Max, GSM, Enterprise etc which are riding on NIB-II MPLS network. 2. The analysis has provided critical insight into the traffic generating capacity of these access networks. The presentation also included the connectivity requirement of different access networks for the next three years along with broad recommendation related to planning of the different access network. 3. The analysis also indicated about the multiplicity of IP / MPLS network being deployed with project planned by each business vertical. To optimize CAPEX and OPEX, Optimization and sharing have to be an integral part of planning. 4. All the recommendations, as spelt out in the presentation, were approved by the Management Committee of BSNL Board in its 34 th Meeting held on 9 th December 2009. 5. The copy of the presentation is enclosed herewith for information of all field units. Encl: As above (71 slides) (SANJEEV VERMA) Dy, General Manager (Core Network Planning – IV) Copy To: [1] All CGM (Telecom Circles / Metro Districs / Projects / Regions / BBNW / QA / Inspection Circle / Training Centres) for information please – (Through Intranet) [2] PGMs /GMs of BSNL Corporate Office – (Through Intranet) Core Network Planning Cell, 614, Bharat Sanchar Bhavan, Janpath New Delhi: 110001 [email protected]

Transcript of Core Network Planning Cell, 614, Bharat Sanchar Bhavan ... · PDF filePresentation to...

Page 1 of 37

[email protected]

No: 66-07/CNP / MNGT / 09 /51 Dt: 21/12/2009

Sub: Presentation by CNP Cell to Management Committee of BSNL board on Analysis of

NIB-II MPLS network along with Recommendation for MNGT

1. A presentation was given by Core Network Planning (CNP) cell indicating the broad

points observed while carrying out the analysis of the NIB-II MPLS with respect to

traffic generating trends of different access networks such as broadband, IP TAX, Wi-

Max, GSM, Enterprise etc which are riding on NIB-II MPLS network.

2. The analysis has provided critical insight into the traffic generating capacity of these

access networks. The presentation also included the connectivity requirement of

different access networks for the next three years along with broad recommendation

related to planning of the different access network.

3. The analysis also indicated about the multiplicity of IP / MPLS network being

deployed with project planned by each business vertical. To optimize CAPEX and

OPEX, Optimization and sharing have to be an integral part of planning.

4. All the recommendations, as spelt out in the presentation, were approved by the

Management Committee of BSNL Board in its 34th

Meeting held on 9th

December

2009.

5. The copy of the presentation is enclosed herewith for information of all field units.

Encl: As above (71 slides)

(SANJEEV VERMA) Dy, General Manager (Core Network Planning – IV)

Copy To:

[1] All CGM (Telecom Circles / Metro Districs / Projects / Regions / BBNW / QA /

Inspection Circle / Training Centres) for information please – (Through Intranet)

[2] PGMs /GMs of BSNL Corporate Office – (Through Intranet)

Core Network Planning Cell,

614, Bharat Sanchar Bhavan, Janpath

New Delhi: 110001

[email protected]

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 2 of 37

Annexure – I

Analysis of Analysis of Analysis of Analysis of

NIB NIB NIB NIB –––– II MPLS Network II MPLS Network II MPLS Network II MPLS Network

24 November 2009 Core Network Planning 1

Approach FollowedApproach FollowedApproach FollowedApproach Followed• Identify who are the users?

• What are their Requirements?

Bottom – Up Approach

• Internal:

• Different Access Networks such as broadband, GSM, Wi-Max, IP TAX, Class V NGN, FTTX (GPON / GEPON),SSTP

• External:

• Enterprise users: For provisioning of VPN circuits, Internet Leased Line

Target Users

• For Internal user: Discussion done with respective GM Network planning.

• For External user: Discussion done with GM (Business Strategy) – E at Corporate Office / Field.

One-to-One Discussion

• The current expansion is not a green field deployment

• A realistic picture on traffic as on day is available for different type of traffic

• A balanced approach (mix of realistic and visionary) is followed.

Optimize CAPEX and

OPEX

24 November 2009 Core Network Planning 2

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 3 of 37

Project

NIB - II

GSM – Phase V

GSM – Phase VI

CDR Project

Tx NMS (Planned)

No of Routers

150

Around 300

Around 300 (Exp)

Around 500

Around 500

Remarks

MPLS enabled

MPLS enabled

MPLS Enabled

IP Enabled

IP Enabled

1. NIB- II – The smallest in number is catering to maximum load.

2. There is a need for having a centralized approach to optimize CAPEX and OPEX.

3. Every project tends to plan its own IP network – Not a judicious approach

4. GSM Phase VI deployment can leverage on GSM Phase V and NIB-II MPLS network

5. Huge network deployed as part of CDR .

!!! BSNL has multiple Data Networks !!! BSNL has multiple Data Networks !!! BSNL has multiple Data Networks !!! BSNL has multiple Data Networks –––– Need for Centralized approach !!!Need for Centralized approach !!!Need for Centralized approach !!!Need for Centralized approach !!!

24 November 2009 Core Network Planning 3

Important facts about NIB Important facts about NIB Important facts about NIB Important facts about NIB –––– II MPLSII MPLSII MPLSII MPLS

• MPLS acting as an unified IP transport layer for voice, video and data.

• Predominantly for facilitating inter-City flow of trafficUnified Transport

• The general philosophy followed for Connectivity of different access network has been dictated purely from the interface requirement – in the absence of any relevant traffic details.

• It should, henceforth be, dictated purely from traffic.

Review of

integration

philosophy

•MPLS network complements the metro area aggregation

network – Very important.

•Different access network shall aggregate the traffic using aggregation network and only aggregated interface shall connect with the MPLS.

Hierarchical

connectivity

• The interface utilization of existing edge connectivity is only 15-20%

• Realistic assessment of traffic for expansion of existing and deployment of future access networks

Actual traffic far less

than that

anticipated

24 November 2009 Core Network Planning 4

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 4 of 37

AgendaAgendaAgendaAgenda• Review of Integration Philosophy

• Hierarchical Connectivity

• Internal Users: Analysis of Traffic from Different Access Network

– Broadband (DSL) + Class V NGN + FTTx

– IP TAX

– Wi-MAX

– GSM

– Other Access Networks

• External Users: Enterprise User

• Summary of Expansion

• Future Line of Action (Through MNGT)

24 November 2009 Core Network Planning 5

Review of Integration Review of Integration Review of Integration Review of Integration

Philosophy of MPLS NetworkPhilosophy of MPLS NetworkPhilosophy of MPLS NetworkPhilosophy of MPLS Network

24 November 2009 Core Network Planning 6

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 5 of 37

Broad Components of MPLS NetworkBroad Components of MPLS NetworkBroad Components of MPLS NetworkBroad Components of MPLS Network

• Akin to Local ExchangeAkin to Local ExchangeAkin to Local ExchangeAkin to Local Exchange

• Subscriber termination point

• Different Access network such as broadband, GSM, wi-Max etc gets terminated here.

• Connectivity on Gigabit Ethernet (GE) interface – based on the traffic generating capacity of different network

PE

Router

• Akin to Level 1 TAXAkin to Level 1 TAXAkin to Level 1 TAXAkin to Level 1 TAX

• Carries out transit function.

• High Speed transfer of packet from one city to Other City

• National Highway

P

Router

24 November 2009 Core Network Planning 7

Let’s reLet’s reLet’s reLet’s re----fresh L2 TAX Connectivityfresh L2 TAX Connectivityfresh L2 TAX Connectivityfresh L2 TAX Connectivity

• Why the Small X-ges are

first aggregated at Tandem

and not connected directly

to Level – II TAX?

– This ensures optimal

utilization of aggregated

interface.

– Individual X-ge are not

capable of generating traffic

equivalent to one E1

(minimum connectivity)

– Tandem acts as an

aggregation Layer. Tandem

Complements TAX in

ensuring optimal

connectivity

Level II TAXTandem

E-10 B OCB

RLU RLU RSURSU RSURLU

X-A X-B X-C

X-D

X-E X-F X-G

This is an aggregated

interface

If Small X-ges are connected

directly to TAX, the TAX

Capacity requirement increases

Along with dramatic fall in

Its utilization

24 November 2009 Core Network Planning 8

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 6 of 37

MPLS Edge Connectivity is Similar to L2 TAX ConnectivityMPLS Edge Connectivity is Similar to L2 TAX ConnectivityMPLS Edge Connectivity is Similar to L2 TAX ConnectivityMPLS Edge Connectivity is Similar to L2 TAX Connectivity

MPLS PE

MGW – IP

TAX

DSLAM LMG BTS - WiMAX

This is an aggregated

interface

Metro

Aggregation

Network

FTTX

Multiplay

Project

Class V

NGN

Wi-MAX

(Rural and

Urban)

GPON / GEPON

Project

RPR / Ethernet based aggregation

Network deployed in Multiplay

Level II TAXTandem

E-10 B OCB

RLU RLU RSURSU RSURLU

X-A X-B X-C

X-D

X-E X-F X-G

This is an aggregated

interface

24 November 2009 Core Network Planning 9

MPLS Edge Connectivity is Similar to L2 TAX ConnectivityMPLS Edge Connectivity is Similar to L2 TAX ConnectivityMPLS Edge Connectivity is Similar to L2 TAX ConnectivityMPLS Edge Connectivity is Similar to L2 TAX Connectivity

What done for Level 2 TAX?

• Minimum Connectivity is

E1.

• Small X-ges, which are not

capable of generating

traffic equivalent to one E1

are aggregated using

Tandem.

• This ensures optimal

utilization of E1 interface

• Tandem Complements TAX

in ensuring optimal

connectivity

What shall be done for Edge Connectivity?

• Minimum Connectivity is Gigabit Ethernet (GE)

• Small access network, which are not capable of generating traffic equivalent to one GE are aggregated using Metro Area Aggregation Network.

• This ensures optimal utilization of GE interface – it is costly

• Metro Area aggregation network complements MPLS network in ensuring optimal connectivity

24 November 2009 Core Network Planning 10

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 7 of 37

Hierarchical Hierarchical Hierarchical Hierarchical

ConnectivityConnectivityConnectivityConnectivity

24 November 2009 Core Network Planning 11

Core IP/MPLS Network

Hierarchical ConnectivityHierarchical ConnectivityHierarchical ConnectivityHierarchical Connectivity

IP NetworkGateway

IP NetworkGatewayCity A

City B

Metro Area AggregationMetro Area AggregationMetro Area AggregationMetro Area Aggregation

NetworkNetworkNetworkNetwork

Metro Area AggregationMetro Area AggregationMetro Area AggregationMetro Area Aggregation

NetworkNetworkNetworkNetwork

MPLS PE

Router

MPLS PE

Router

DSLAM LMGGPON /

GEPONMGW BSC / RNC

Edge Connectivity: This interface to

be dimensioned purely from

Traffic anticipated from

Set of customers

Set of Customers

NOC

• AAA• LDAP

• Billing• Provisioning

Examples of IP Network Gateway:

•BNG

•ASN

•SGSN , GGSN

24 November 2009 Core Network Planning 12

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 8 of 37

Analysis of Traffic From Analysis of Traffic From Analysis of Traffic From Analysis of Traffic From

Different Access Different Access Different Access Different Access

NetworksNetworksNetworksNetworks

24 November 2009 Core Network Planning 13

BroadbandBroadbandBroadbandBroadband

24 November 2009 Core Network Planning 14

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 9 of 37

Current Status (as on 31/10/2009)Current Status (as on 31/10/2009)Current Status (as on 31/10/2009)Current Status (as on 31/10/2009)

• DSL Capacity = 8.5 Mn

• Broadband Connections =4.52 Mn

• Disabled Customers = 1 Mn

• Active Customers = 3.52 Mn

• Loading w.r.t Active customers = 41%

• Concurrent connections = 0.61Mn

• No of BNGs = 175 (128*)

• Utilization of BNGs :• Session handling capacity 8926/48000 = 18.6 %

• Link Utilization = 12%

• International bandwidth (utilization 70%) = 45 Gbps

• Average BW per prov customer = 7 kbps

• Average BW per concurrent customer = 60 kbps

*: Commissioned

24 November 2009 Core Network Planning 15

Broadband Customer FunnelBroadband Customer FunnelBroadband Customer FunnelBroadband Customer Funnel

Provisioned Customers (100)

Active Customers (78)

Concurrent (12)

BW =

0.72 Mbps

78%78%78%78%

12%12%12%12%

60 Kbps60 Kbps60 Kbps60 Kbps

Per concurrentPer concurrentPer concurrentPer concurrentcustomercustomercustomercustomer

22% are disabled

24 November 2009 Core Network Planning 16

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 10 of 37

Targetted Customer Growth (11Targetted Customer Growth (11Targetted Customer Growth (11Targetted Customer Growth (11thththth Five Year Plan)Five Year Plan)Five Year Plan)Five Year Plan)

Parameter Status as on

31/03/09

MOU for 09-

10

Target for

10-11

Target for

11-12

Cumulative

Total

Wireline 293.46 -8.5 -27 -25 214.46

WLL 54.33 +15 +15 92.84

Mobile 467.11 120 200 220 1007.11

NGN 0

Total 814.91 101.5 188 210 1314.41

Broadband

(Fixed)

35.57 15 25 30 105.57

Broadband

(Wireless)

- - 10 20 30

TAX Circuits

(Kc)

8528 1200 2100 1700* 13,528

OF Cable

(Rkm)

5,95,392 28,500 30,000 30,000 6,83,892

All figures in Lakhs unless specified

14 Mn broadband customers by 201214 Mn broadband customers by 201214 Mn broadband customers by 201214 Mn broadband customers by 2012

24 November 2009 Core Network Planning 17

Major Drivers for Increased TrafficMajor Drivers for Increased TrafficMajor Drivers for Increased TrafficMajor Drivers for Increased Traffic

• Focus on Content which has higher simultaneous usage during peak hour

Increase in

Concurrency

• Focus on On-demand content

• Broadcast content (Multicast) doesn’t generate much traffic

Bandwidth intensive

Service

• With GPON / GEPON + VDSL2+ , other than HSI , VoIP and VPN we don’t have any other service

Required for

leveraging FTTX

• Will increase volumes and hence total traffic

• What about average customer traffic ?

Pre-Paid broadband

Service:

• Will leverage on the DSL infrastructure

• But focus has to beyond VoIP – Multi-media applications

Class V NGN

• Incremental TAX traffic will expected to flow through this.

• However the same will not be significant as current average loading of TAX is around 67%.

IP TAX Traffic

24 November 2009 Core Network Planning 18

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 11 of 37

Scenario AnalysisScenario AnalysisScenario AnalysisScenario Analysis

BB Cust

(Today)

BB Cust

(Planned)

Increase

in fold

Avg usage

(Today)

Avg Usage

(Planned)

Increase

in usage

Gross

Increase

in Traffic

4.5 Mn 14 Mn 3.1 7 kbps 7 kbps 1 3

4.5 Mn 14 Mn 3.1 7 kbps 14 Kbps 2 6

4.5 Mn 14 Mn 3.1 7 kbps 21 Kbps 3 9

4.5 Mn 14 Mn 3.1 7 kbps 28 Kbps 4 12

4.5 Mn 14 Mn 3.1 7 kbps 35 kbps 5 15

4.5 Mn 14 Mn 3.1 7 kbps 50 kbps 7 21

1. The average usage of around 21 kbps per customer is taken for planning purpose

2. This will require 9 times increase in traffic with 3 times increase in customer

base in the next three years – A challenging proposition?

24 November 2009 Core Network Planning 19

Parameters for dimensioningParameters for dimensioningParameters for dimensioningParameters for dimensioningBNG :

• Concurrency rate (Present 13.5%) = 40 %

• Average BW per customer = 21 kbps

• Calculation:

– Customers 1 BNG can handle = 1.25 L

– Maxm traffic in 1 BNG = 2.62 Gbps

– 14 Mn customers require = 112 BNGs

– 25% over provision = 140 BNGs

– BNGs already planned upto Ph – II = 175

Further Expansion of BNG not required in Phase Further Expansion of BNG not required in Phase Further Expansion of BNG not required in Phase Further Expansion of BNG not required in Phase ---- IIIIIIIIIIII

24 November 2009 Core Network Planning 20

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 12 of 37

Broad Dimensioning CriteriaBroad Dimensioning CriteriaBroad Dimensioning CriteriaBroad Dimensioning Criteria

Parameter

Customer base

Concurrency

Avg BW per cust

Edge Connectivity

No of BNGs

Link Utilization (2GE)

Current

4.5 Mn

13.5%

7 kbps

2 GE

128

12%**

Planned

14 Mn (Mar ‘12)

40%

21 kbps

3 GE*

175

???

Note:

*: Planned initially in A type cities. Progressively for B type cities

**: This will fall further to 6-8% with the commissioning of balance 47 BNGs (as part of Phase

II)

24 November 2009 Core Network Planning 21

Executive Summary Executive Summary Executive Summary Executive Summary ---- IIII• The DSL port loading is around 41%.

• With current rate of growth (1.5 lakhs pm), the network will be loaded 90% in another 27 months (more than 2 years)

• The current BNG is sufficient to handle more than 14 Mn broadband customers

Current Loading is

Low

• Each BNG is presently connected on 2 GE interface to MPLS PE

• The average Traffic loading of this link is around 12%

• No new connectivity of BNG is required with MPLS PE Router for the next three – four yrs.

• Provision is made for additional 1 GE connectivity in top 20 cities for further increase in traffic.

Existing Edge

Connectivity

sufficient for the

next 2 - 3 yrs

• The low traffic in broadband is predominantly

due to slow off take of IP TV service.

• Focussed Strategy on IP TV including On demand

content. The services to be strengthened in the

existing 98 cities before venturing into new

cities.

• Optimizing Broadcast content to ensure seamless

experience to user.

Focussed Strategy

on IP TV Service:

24 November 2009 Core Network Planning 22

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 13 of 37

Executive Summary Executive Summary Executive Summary Executive Summary ---- IIIIIIII

• Enterprise segment can leverage on that for Ethernet connectivity to customer.

RPR Aggregation

Network in top

98 cities:

• Around 3 Mn ports planned.

• The planned expansion to take care of above points.

• Alignment of the expansion as per the NGN framework approved by the Management Committee.

Phase III

Expansion

• Expansion has to be done in the IGW locations.

• Core connectivity to be augmented to nx10Gbps in the top 10-15 cities.

International

Bandwidth

• Project 3 LDAP Capacity: To be in sync with the access capacity available as part of DSL, FTTX and Wi-MAX.

• (Project 3 – CDR Project) issue to be sorted out.Other Points

24 November 2009 Core Network Planning 23

IP TAXIP TAXIP TAXIP TAX

24 November 2009 Core Network Planning 24

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 14 of 37

Current StatusCurrent StatusCurrent StatusCurrent Status

• Total TAX Circuits = 8.5 Mn

• Average Loading = 67%

• Loading of Level I TAX = 90%

• Existing (As on 31/10/2009):

– TDM PSTN = 28.327 Mn

– GSM = 53.994 Mn

– CDMA = 5.4 Mn

– IP NGN = 0

Total telephone customers as on 31/10/2009 = 87.75 Mn

24 November 2009 Core Network Planning 25

Macro Level Dimensioning of IP TAXMacro Level Dimensioning of IP TAXMacro Level Dimensioning of IP TAXMacro Level Dimensioning of IP TAX

• Total Connections (expected) * =150 Mn (131 Mn)

• Contention ratio (1:10)

• No of active circuits = 15 Mn (13 Mn)

• Local Calls around 25%

• So no of active circuits in TAX = 11.25 Mn (9.75 Mn)

• Existing Capacity = 8.5 Mn

• Additional Capacity required = 2.75 Mn (1.25 Mn)

Note:*: By March ‘’121. The above calculation assumes that all the connections are on TDM infrastructure &

thus banks on TAX circuits.

2. The scenario has changed with the introduction of IP in GSM Ph V.3. Thus the requirement of IP TAX will come down further considering GSM –

GSM calls are 70% of the total GSM calls.

24 November 2009 Core Network Planning 26

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 15 of 37

IP TAX Deployment Plan IP TAX Deployment Plan IP TAX Deployment Plan IP TAX Deployment Plan –––– Phase IPhase IPhase IPhase I

• Total Cities = 265– Cities with 4 KC (0.5 Gbps) = 79

– Cities with 8 KC (1 Gbps) = 67

– Remaining Cities =119

Note:

– A Total of 3 Mn circuits planned to be deployed in the first phase. 2.2 Mn to M/s ZTE and 0.9 Mn to M/s ITI – M/s Huawei

– The above loading is at the maximum utilization with no compression. However, as the compression is implemented the bandwidth requirement is expected to be reduced by 40%.

24 November 2009 Core Network Planning 27

Traffic Flow and TrendsTraffic Flow and TrendsTraffic Flow and TrendsTraffic Flow and Trends

• The intra-Circle traffic shall be catered by the

existing TAX capacity – we are not replacing

but augmenting TAX network??

• Also this traffic will come down as TDM PSTN

is migrated to NGN.

• Because of GSM expansion and Landline

surrender / migration to NGN, the traffic will

further come down.

In the current scenario, the utilization of IP TAX In the current scenario, the utilization of IP TAX In the current scenario, the utilization of IP TAX In the current scenario, the utilization of IP TAX

will be significant only in top 20 citieswill be significant only in top 20 citieswill be significant only in top 20 citieswill be significant only in top 20 cities

24 November 2009 Core Network Planning 28

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 16 of 37

IP TAX IP TAX IP TAX IP TAX –––– Traffic Flow ScenarioTraffic Flow ScenarioTraffic Flow ScenarioTraffic Flow Scenario

TDM TAX (L1 + LII)/

TandemIP TAX

LE LE LE LE

Other TDM

networks – GSM

(Upto Phase IV)

CDMA

Existing TDM Local Switch

Phase V GSM

and onwards

This link will carry incremental inter

Circle traffic and traffic where

One end is TDM PSTN and other

End is IP NGN, GSM (Phase V onwards)

Pure TDM to

TDM traffic

Can be carried

Through existing

TAX network except

L1, where Loading

Is 90%.

NGN

(DSL, FTTX, LMG

etc)

24 November 2009 Core Network Planning 29

Core IP/MPLS Network

MGW

MGW

IP TAX Connectivity in A Cities (L1 TAX)IP TAX Connectivity in A Cities (L1 TAX)IP TAX Connectivity in A Cities (L1 TAX)IP TAX Connectivity in A Cities (L1 TAX)

MGW

MGW

MGWMGW

MGW

GEGE

L1 TAX /

Tandem

L1 TAX /

Tandem

E1s

Soft

Switch

Soft

SwitchEthernet

Switch

24 November 2009 Core Network Planning 30

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 17 of 37

RPR Aggregation

Layer

MPLSLayer

BNG

RPR Tier 1 Switch

10 GRPR

PE RouterGE

GE

GE

MGW

MPLS Nation wide Core

IP TAX Connectivity in B CitiesIP TAX Connectivity in B CitiesIP TAX Connectivity in B CitiesIP TAX Connectivity in B Cities

RPR Tier 2 Switch

DSLAM

GE

L2 T

AX

E1s

24 November 2009 Core Network Planning 31

SDH RING

GE

OC city OC city

X-ge A

X-ge C

ADSL terminalsADSL

terminals

X-ge B

X-ge D

GE

Tier 1 LAN

Switch

BB

BNG GigE

Corerouter

FE

OC Switch

RPR

To nearest A/B cities

where RPR Tier 1 Switch is there

IP TAX Connectivity in ‘OC’ CitiesIP TAX Connectivity in ‘OC’ CitiesIP TAX Connectivity in ‘OC’ CitiesIP TAX Connectivity in ‘OC’ Cities

MGW

GE

L2 T

AX

E1s

MGW

24 November 2009 Core Network Planning 32

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 18 of 37

Executive Summary of IP TAXExecutive Summary of IP TAXExecutive Summary of IP TAXExecutive Summary of IP TAX• IP TAX planning was done more than three years back (Aug ‘06).

• During this period, lot of changes have happened particularly in the landline + GSM

• In the current scenario, loading of 3 Mn is not expected on immediate basis except may be in top 15-20 cities.

Utilization in the

Current Scenario will be

low

• The direct connectivity will be done only in top 15-20 cities.

• In other cities, it will leverage on the existing broadband connectivity.

So, Connectivity will be

on shared basis

• As we migrate towards Class V NGN, loading of IP TAX will also come down.

• This will also come down as landline gets surrendered in favour of GSM.

• Can we explore the alternate usage of IP TAX infrastructure

Loading will further

come down…

•Maintenance issues can be solved through replacement of TDM TAX Circuits – What is the Policy on that?

•The Media Gateway used for GSM Phase VI expansion???

•Whole sale service to other TDM operators

How to increase loading

of IP TAX?

• The order of Phase – II may have to be re-looked into from the actual loading of 3 Mn Circuits planned in Phase I

Phase II

24 November 2009 Core Network Planning 33

WiWiWiWi----MAXMAXMAXMAX

24 November 2009 Core Network Planning 34

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 19 of 37

Wi-MAX

Urban

Procurement

Kerala –

ICommPunjab –Huawei

Franchisee

Soma (Guj,

MH AP)

EOI other Circles

A type (1000 BTS): 6 Circles

B Type (700 BTS): 6 Circles

C Type (500 BTS): 4 Circles

Rural (Procurement)

Phase I (1000

BTSs)

HCL Info (592 BTS)

– N + E

Gemini (408) –

S+W

Phase II (6863

BTSs)

L1: - Gemini (Juniper) L2: ZTE

L3: ICOMM

L4: Vipula -Alvarion

WiWiWiWi----Max Project Roll Out PlanMax Project Roll Out PlanMax Project Roll Out PlanMax Project Roll Out Plan

24 November 2009 Core Network Planning 35

Key Concern Areas in the WiKey Concern Areas in the WiKey Concern Areas in the WiKey Concern Areas in the Wi----Max deploymentMax deploymentMax deploymentMax deployment

• Majority of the procurement based deployment is happening in Rural areas.

• Infrastructure will be established but what about Rural specific contents.

Predominantly

Rural

deployment

• Franchisee based except in Kerala and Punjab

• Only 2500 customers in three states (GUJ, MH and AP)

• Three cities: Ahemdabad, Panjim and Vizag

Urban Roll out

is slow

• A 10 city pilot deployment on 802.1d technology was done

• What is the status of the pilot? How many customers?

Status of Pilot

deployment

All this demand a progressive way of establishing Core connectivity. All this demand a progressive way of establishing Core connectivity. All this demand a progressive way of establishing Core connectivity. All this demand a progressive way of establishing Core connectivity.

2222----2 .5 Mn Wi2 .5 Mn Wi2 .5 Mn Wi2 .5 Mn Wi----Max user Is taken from the Core sideMax user Is taken from the Core sideMax user Is taken from the Core sideMax user Is taken from the Core side

24 November 2009 Core Network Planning 36

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 20 of 37

Initial Macro Level Planning of WiInitial Macro Level Planning of WiInitial Macro Level Planning of WiInitial Macro Level Planning of Wi----Max NetworkMax NetworkMax NetworkMax Network

• 1 ASN = 100 BTS.

– 1 BTS (Capacity in No of customers) = 100

• No of ASNs across the Network = 100

• BW between ASN and MPLS = 1 Gbps

• Total Pipe = 100 Gbps

• Current Avg utilization = 7 kbps

• No of Users it can take = 14 Mn

Current Status:

– User Base = 2500

– BW = 10 Mbps

The MPLS connectivity is significantly high24 November 2009 Core Network Planning 37

Executive Summary of WiExecutive Summary of WiExecutive Summary of WiExecutive Summary of Wi----MaxMaxMaxMax

• The current plan of 100 ASNs provides 100 Gbpspipe towards MPLS . This will be a huge pipe with severe under loading.

• So, we need to follow a progressive approach

Current connectivity is not in sync with

the traffic.

• Either from the traffic perspective or from inter-operability

• The current 18 ASNs can cater from the traffic perspective for around 2 Mn Wi-Max user

• Thus the current plan of 100 ASNs has to be re-looked into.

• In case, few more ASNs are required from inter-op perspective (for new OEMs not part of initial 18), the number to be worked out purely from the traffic.

• These ASNs be deployed near the international Gateway Location (Mumbai, Chennai, Bangalore, Noidaor Kolkatta) and aggregated with the existing ASNs

Why you require more ASNs?

• Instead of deploying back-end infrastructure (ASN: 100 Nos) at one go, deploy as you grow.

• The current 18 ASNs can take care of 2 Mn users.Progressive Approach

24 November 2009 Core Network Planning 38

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 21 of 37

GSM Network TrafficGSM Network TrafficGSM Network TrafficGSM Network Traffic

24 November 2009 Core Network Planning 39

Salient Points of GSM NetworkSalient Points of GSM NetworkSalient Points of GSM NetworkSalient Points of GSM Network• Upto Phase IV, a total of 36 Mn capacity deployed, TDM based

• The connectivity is extended using TDM TAX circuits

• In Phase VI, under Service equivalency, migration to IP based network is planned progressively.

Upto Phase IV, infrastructure is TDM

based

• In Phase V, the IP connectivity was introduced at the level of Core equipments such as Media Gateway (MGW)

• A separate MPLS infrastructure deployed / planned in each Zone

• This will carry intra-Circle voice and intra-Circle signallingtraffic

IP Connectivity introduced at the Core Equipment

Level in Ph V

• BTS / Node B – BSC / RNC is on E1s.

• BSC / RNC – Media Gateway is on E1s

• BSC / RNC – SGSN is on Ethernet over SDH (Point to Point)

TDM / EoS used at the Access Network Level

• The inter-Circle voice traffic will ride on NIB-II MPLS along

with inter-Circle signaling traffic for connectivity to SSTP.

• The connectivity between NIB-II and GSM MPLS network is done at Gateway location per Circle.

• 8 in NZ, 5 in EZ, 9 in SZ and 8 in WZ.

Inter-Circle Call riding on NIB-II MPLS

• The Data connectivity at GGSN – One per Zone

• Kolkatta, Chandigarh, Pune and Chennai

Data is handed at One per Zone

24 November 2009 Core Network Planning 40

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 22 of 37

Circle Wise GSM Connections (As on 31/10/09)Circle Wise GSM Connections (As on 31/10/09)Circle Wise GSM Connections (As on 31/10/09)Circle Wise GSM Connections (As on 31/10/09)

Circle* GSM Conn Circle GSM Conn

A & N 0.09 Mn MP 1.86 Mn

AP 3.86 Mn Maharashtra 3.87 Mn

Assam 0.96 Mn NE-I + II 0.766 Mn

Bihar 2.07 Mn Orissa 1.845 Mn

Chattisgarh 0.83 Mn Punjab 3.232 Mn

Gujarat 2.64 Mn Rajasthan 3.247 Mn

Haryana 2.17 Mn TN 3.763 Mn

HP 1.07 Mn Uttaranchal 0.868 Mn

J&K 0.89 Mn UP - East 6.544 Mn

Jharkhand 0.844 Mn UP-West 1.853 Mn

Karnataka 2.866 Mn West Bengal 1.914 Mn

Kerala 3.11 Mn Kolkatta 1.653 Mn

Chennai 1.15 Mn

Total Connections: = 53.994 MnCapacity planned / deployed upto Ph V = 69.74 Mn (36 Mn TDM based)Capacity Planned in Phase VI = 93 Mn

IP Capacity:

• 9 Mn for South Zone

• 9 Mn for West Zone

• 13.5 Mn for N + E Zone

Note:*: Source: CP&M Monthly DEL report

24 November 2009 Core Network Planning 41

GSM Traffic DistributionGSM Traffic DistributionGSM Traffic DistributionGSM Traffic Distribution

MSC (100)

Intra-MSC Inter-MSC

MSC in Same Circle

GMGW of the Circle

GMGW of Other Circle

LI TAX of PSTN (10+20)

To Other operator

Legacy MSC (upto Ph – IV)

NIB - II MPLS N/w

This traffic will get

Migrated to MPLS N/w

as the Legacy MSC is

Replaced With

(MGW + MSC – S)

As part of service

equivalencyGS

M M

PLS

N/w

TDM

24 November 2009 Core Network Planning 42

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 23 of 37

Traffic Calculation (Voice) Traffic Calculation (Voice) Traffic Calculation (Voice) Traffic Calculation (Voice) –––– For Ph V and onwardsFor Ph V and onwardsFor Ph V and onwardsFor Ph V and onwards

Assumptions: (From Ph VI Tender)

• Average traffic per customer = 50 mErl

– Incoming = 25 mErl

– Outgoing = 25 mErl

• GSM – GSM = 70%

• GSM – PSTN = 10%

• PSTN – GSM = 20%

Traffic Calculation:1. Traffic from 1 Mn customers = 50,000 Erlg

2. Traffic in IP (@ 70% utilization)

a) 50000X50/(1000000*.7) = 3.5 Gbps simplex

= 1.75 Gbps duplex

3. Traffic distributed among GSM , NIB and TDM

4. Peak expected traffic in NIB Core around = 0.8 Gbps full duplex

24 November 2009 Core Network Planning 43

Zone Circle Nov ‘ 08 Apr ‘ 09 Circle Nov ‘ 08 Apr ‘09

South

AP 0.68 0.92 TN 0.73 1.25

Kerala 1.51 2.76 CHTD 0.81 1.26

Karnataka 1.08 1.58

North

HR 0.88 0.58 UP E 6.31 11.7

PB+HP+JK 21.71 23.24 UPW

+UAL

6.29 10.32

Rajasthan 4.9 2.82

East

AS+NEI+NEII 4.53 3.99 WB+AN 6.04 -

BR + JKND 2.11 2.66 CLTD 2.76 2.03

OR 2.22 6.29

West

MH 3.22 6.16 GJ 3.17 3.4

MP + CHG 3.8 3.14

Avg Throughput(GGSN Avg Throughput(GGSN Avg Throughput(GGSN Avg Throughput(GGSN ---- SGSN) in MbpsSGSN) in MbpsSGSN) in MbpsSGSN) in Mbps

As can be seen, Data Traffic is hardly anything at this instantAs can be seen, Data Traffic is hardly anything at this instantAs can be seen, Data Traffic is hardly anything at this instantAs can be seen, Data Traffic is hardly anything at this instant.The Loading of existing SGSN is low (The Loading of existing SGSN is low (The Loading of existing SGSN is low (The Loading of existing SGSN is low (Capacity = 100 MbpsCapacity = 100 MbpsCapacity = 100 MbpsCapacity = 100 Mbps))))

24 November 2009 Core Network Planning 44

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 24 of 37

Wireless Growth (In 09Wireless Growth (In 09Wireless Growth (In 09Wireless Growth (In 09----10)*10)*10)*10)*

0

2

4

6

8

10

12

14

16

April '09 May ' 09 June '09 July '09 Aug '09 Sept '09

Countrywide Addition

BSNL Share

1. Total of 79.92 Mn added in the last 6 months.

2. BSNL Share = 6.543 Mn, As %age = 8.1%3. Average additions of 1.1 Mn per month in the Last 6 months

4. In 08- 09, BSNL share was 7%, 9.1 Mn out of 129.2 Mn (All lines )

*: Source: TRAI Report

24 November 2009 Core Network Planning 45

GSM GSM GSM GSM ---- NIBNIBNIBNIB----II MPLS ConnectivityII MPLS ConnectivityII MPLS ConnectivityII MPLS Connectivity

Project Zone Vendor IP Capacity NIB-II MPLS Remarks

Phase V South M/s Huawei 9 Mn 9 + 9 Gbps

Phase V West M/s Alcatel 9 Mn 8 + 8 Gbps

Phase V North M/s

Ericsson

8 Mn 8+8 Gbps 1+1 GE at

Chandigarh.

Other 7

places at 2*

STM-1

Phase V East M/s

Ericsson

5.5 Mn 6+6 Gbps 2+1 GE at

Kol. Other 4

places at 2 *

STM-1

Note: - A 31 Gbps Pipe built up between GSM Network and NIB-II Network•The above connectivity can cater to 35 Mn customers on GSM IP platform under fully loaded condition.

•Provision is made for additional 35 Mn customers on GSM IP platform.

(either expansion or under service equivalency).

•Further expansion in selected cities depending upon actual traffic.

24 November 2009 Core Network Planning 46

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 25 of 37

Executive Summary of the Recommendation Executive Summary of the Recommendation Executive Summary of the Recommendation Executive Summary of the Recommendation ---- IIII

• No need for separate MPLS infrastructure as part of Phase VI.

• Leverage on MPLS infrastructure as part of Phase V and NIB-II MPLS.

Optimize MPLS Deployment

• Presently the voice is on TDM and Data is on EoS.

• The current packet connectivity on SDH shall be migrated to Packet based network progressively.

• The same can be implemented using existing Metro Area Aggregation Network, as and when the same is planned.

IP Connectivity of Access Network (BTS / Node B – BSC

/ RNC – MSC / SGSN)

• The current GPRS / EDGE traffic is insignificant.

• The same is expected to increase with launch of 3G

• Focussed approach on 3G – Top few cities .

Data Traffic is negligible

• For connectivity to PSTN for new network, leverage on IP TAX.

• Explore Usage of Media Gateway deployed as part of IP TAX.

Leverage on IP –TAX infrastructure

Leverage on Existing Infrastructure (GSM + IP TAX) for future expansionLeverage on Existing Infrastructure (GSM + IP TAX) for future expansionLeverage on Existing Infrastructure (GSM + IP TAX) for future expansionLeverage on Existing Infrastructure (GSM + IP TAX) for future expansion

24 November 2009 Core Network Planning 47

Executive Summary of the Recommendation Executive Summary of the Recommendation Executive Summary of the Recommendation Executive Summary of the Recommendation ---- IIIIIIII

• GSM MPLS Network of M/s Ericsson

• Connectivity with NIB-II MPLS at Chandigarh, Ambala, Jammu, Lucknow, Noida, Shimla, Jaipur and Jullundhur.

North Zone

• GSM MPLS Network of M/s Ericsson

• Connectivity with NIB-II MPLS at Kolkatta, Patna, Shillong, Guwahati and Sambalpur

East Zone

• GSM MPLS Network of M/s Alcatel – M/s CISCO

• Connectivity with NIB-II MPLS at Pune, Nagpur, Ahemdabad, Surat, Bhopal, Indore, Raipur and Durg(Parented to Raipur)

West Zone

• GSM MPLS Network of M/s Huawei

• Connectivity with NIB-II MPLS at Hyderabad, Vijayawada, BGL, Mysore, Chennai, Coimbatore, Ernakulem, Madurai and TVM

South Zone

The initial connectivity will be on 1+1 GE interface to be augmented The initial connectivity will be on 1+1 GE interface to be augmented The initial connectivity will be on 1+1 GE interface to be augmented The initial connectivity will be on 1+1 GE interface to be augmented

to 2+1 GE depending on the trafficto 2+1 GE depending on the trafficto 2+1 GE depending on the trafficto 2+1 GE depending on the traffic.

24 November 2009 Core Network Planning 48

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 26 of 37

Other NetworksOther NetworksOther NetworksOther Networks

24 November 2009 Core Network Planning 49

Connectivity to Other Access NetworksConnectivity to Other Access NetworksConnectivity to Other Access NetworksConnectivity to Other Access Networks• Around 500 Routers are deployed covering all SSA.

• Expected Peak loading around 30%. We can spare some Routers through consolidation.

• These Routers are planned to be connected on STM-1 on dual mode basis

• Project delayed. Still in PoC Stage.

• Focus on early commissioning of the same.

CDR Project

• SSTP Switches deployed in 24 cities

• The present connectivity is on Fast Ethernet Interface

• The same is planned to be connected on Gigabit Ethernet interface – the peak traffic presently is only 20 Mbps.

SSTP

• Connectivity with Ku-band Router at Bangalore

• The physical connectivity is through n*64 / E1 / FE

• One link per VPN customer is used between PE Router and Ku-band Router

Ku band VSAT

• One per Zone

• Connectivity on 1+1 GE interfaceCDMA PDSN

• Routers / Switches at SSA connected on E1s

• Regional NMS connected on STM-1Tax NMS

24 November 2009 Core Network Planning 50

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 27 of 37

Enterprise UsersEnterprise UsersEnterprise UsersEnterprise Users

24 November 2009 Core Network Planning 51

Current StatusCurrent StatusCurrent StatusCurrent Status• Distribution of MPLS VPN Circuits

• 44% are 64 kbps 25% are 128 kbps

• 10% are 256 kbps 8% are 512 kbps

• 8.5 % are > 1 Mbps

1.7 lakh Leased lines and 19,475 VPN Circuits

• 40% increase in revenue with 30% decrease in tariif

• Revenue of Rs 960 Cr in 08-09 for LL / VPN.

• The revised fig for 09-10 is Rs 1650 Cr. Revenue in the first six months is Rs 620 Cr.

Huge Growth in Leased Line

• This indicates majority of the circuit is 64 kbps and 128 kbps

Avg Revenue per Ckt is Rs 90,000 pm

• 19,255 circuits provisioned from Jan ‘06 to Dec ‘’08

• 5,651 circuits provisioned from Jan ‘09 to Aug ‘’09

• Average monthly additions around 700 ckts pm

VPN Growth in the Last three Years – 700 ckts

pm

• 25 Cities are there where Loading is > 35%

• 58 Cities are there where Loading is < 20%

• Average Loading is 24% .

VPN Loading in the top 25 cities are significant

24 November 2009 Core Network Planning 52

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 28 of 37

VPN Site Wise Loading VPN Site Wise Loading VPN Site Wise Loading VPN Site Wise Loading –––– Top 25 CitiesTop 25 CitiesTop 25 CitiesTop 25 CitiesSite Name %age Loading Site Name %age Loading

Ahemdabad - 1 71.88 Bhubaneshwar 43.00

Bangalore - 1 71.33 Surat 42.04

Ernakulem - 1 68.97 Bangalore - 2 40.85

Hyderabad - 1 62.35 Hyderabad - 2 39.44

Mumbai - 1 61.08 Patna 39.18

Pune – 1 60.92 Jabalpur 37.91

Kolkatta - 1 59.57 Rajkot 37.55

Chennai - 1 59.46 Jaipur 37.14

Hubli 54.95 Ambala 36.81

Chennai - 2 54.04 Delhi - 1 36.36

Ahemdabad - 2 53.28 Gurgaon 35.92

Dehradun 49.45 Trichy 35.71

Mumbai - 2 49.30 Madurai 35.51

Ernakulem – 2 46.94 Mangalore 35.02

Chennai - 3 45.37 Noida 34.62

Coimbatore 43.68 Indore 33.47

24 November 2009 Core Network Planning 53

Site Wise Loading Site Wise Loading Site Wise Loading Site Wise Loading –––– Bottom 26 CitiesBottom 26 CitiesBottom 26 CitiesBottom 26 Cities

Site Name %age Loading Site Name %age Loading

Gwalior 11.43 Dhanbad 7.66

Patiala 11.43 Kharagpur 7.66

Ananthapur 11.11 Solapur 7.66

Alwar 11.11 Raichur 6.51

Trichur 10.99 Sagar 6.51

Nellore 10.73 Eluru 6.12

Amritsar 10.61 Sambalpur 5.36

Durgapur 10.44 Anand 4.6

Shillong 10.2 Mumbai – 3 3.98

Karvar 9.2 Dhule 3.83

Moradabad 9.2 Nanded 3.83

Jammu 8.98 Bangalore - 3 3.41

Jhansi 8.43 Ferozepur 3.3

Jamshedpur 8.24 Ahemdabad - 3 -

Palghat 8.24 Hyderabad - 3 -

24 November 2009 Core Network Planning 54

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 29 of 37

Growth in the data market expected to be driven by MPLSVPN and High Speed Data & Internet (HSDI)

1,689

3,9541,373

2,5873,618

5,782

99

127

0

2,000

4,000

6,000

8,000

10,000

12,000

6,807

CY 2008

12,422

CY 2013

LegacyPacket

LeasedLine

Hi SpeedData andInternet

MPLSVPN

Rs. Cr.

Source: Frost & Sullivan, IDC, Gartner, Ovum, Analyst Reports, BCG analysis

CAGRCAGRShare of

BSNL

Share of BSNL TrendsTrends

~13%

~44%

2%

10%

14%

19%

• Will continue to be used by

select verticals (e.g. BFSI) for running core apps till

such time switching costs

remain high

• ISDN & VSAT used for

data connectivity backup

• DSL primary source of

internet connectivity for

small & SOHO

• Gaining popularity for transport of distributed

data owing to lower TCO

• Expected to take share

from legacy packet as

customers upgrade their

data networks

13%

~95%-5%

• Preferred for high

bandwidth P2P links

Mainstay for international

data connectivity

Enterprise data market break up by product (2008-13)

24 November 2009 Core Network Planning 55

BSNL is currently a strong player in the data marketOwing to dominant share in the NPLC and HSDI markets

BSNL is the joint #3 player in the enterprise data services market

No presence in IPLC today

Negligible presence in MPLS VPN

HSDI dominance due to high fixed line penetration

Predominant share in NPLC

22%

19%

17%

9%

100%

5%

5%

6%

0 20 40 60 80 100

Tulip

Sify

HCL

Others

Total

Share in enterprise data market1 (%)

TCL

Reliance

Bharti

17%BSNL

1. This denotes the share in the entire enterprise data services market – corporate + SMBNote: Market shares for FY 2006-07Source: Frost & Sullivan, Analyst Reports, BCG analysis

24%

24%

100%

5%

12%

0 50 100

36%BSNL

Reliance

Bharti

TCL

MTNL

Total

28%

100%

64%

0 50 100

TCL

Reliance

8%Bharti

Total

26%

100%

6%

11%

14%

0 50 100

44%BSNL

Bharti

Reliance

TCL

Others

Total 100%

4%

2%

5%

6%

12%

21%

22%

28%

0 50 100

Tulip

Sify

Reliance

Bharti

HCL

TCL

BSNL

Others

Total

24 November 2009 Core Network Planning 56

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 30 of 37

Key points For the Enterprise Segment for VPNKey points For the Enterprise Segment for VPNKey points For the Enterprise Segment for VPNKey points For the Enterprise Segment for VPN

• More and More customers will demand Ethernet as the preferred interface

• MPLS VPN will be preferred over LL because of lower TCO. Customer need to be educated and convinced on the same.

Future trend towards Ethernet

and VPN

• Presently most of the Circuits are 64 kbps and 128 kbps

• They require lot of intermediate elements such as MUX, MLLN equipment etc – Mtce issues

• Migrating to 2 Mbps will make implementation and maintenance smoother

Focus more on 2Mbps and above

for VPN

• This results in very long last mile

• This even go upto 25-30 Km

• Multiple POPs in Delhi and Mumbai

• End-to-End infrastructure: Local lead, Tx back-haul + Router

No MAN in Delhi and Mumbai

• In Other cities, MAN has been built up as part of Multiplay project.

• Leverage on the same for provisioning of Ethernet connectivity

Leverage on the MAN in Other Cities

24 November 2009 Core Network Planning 57

CPE

V

M

U

X

CPE

D

X

C

V

M

U

X

D

X

C

V

M

U

X

V

M

U

X

CPE

V

M

U

X

CPED

X

C

V

M

U

X

D

X

C

V

M

U

X

V

M

U

X

V

M

U

X

City A City B

City A City B

VIRTUAL

POP

PHYSICAL

POP

OtherCities

OtherCities

MPLS MPLS MPLS MPLS –––– MLLN: Complement Each OtherMLLN: Complement Each OtherMLLN: Complement Each OtherMLLN: Complement Each Other

24 November 2009 Core Network Planning 58

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 31 of 37

Virtual POP Vs Physical POPVirtual POP Vs Physical POPVirtual POP Vs Physical POPVirtual POP Vs Physical POP

Parameter

Local Lead

MLLN Cost

Back-haul Cost

Router Cost

Link performance

Commissioning time

OPEX

Virtual POP

Extended to nearest City

(B) - Longer

From City A to City B on

MLLN - higher

Zero

Zero

Same

Similiar

Lesser

Physical POP

Confined to City A itself -

Shorter

MLLN confined to City A

only - Lesser

Minimum 2 STM-1s

Around 26 lacs

Improved due to

redundancy

Similiar

Higher – due to

deployment of Router

Note:

1. In both the models, the issue predominantly comes in the last mile. In case of Virtual POP, every VMUX is already connected with nearest DXC on E1 and practically there is no such maintenance issue once the link is commissioned.

2. The average loading of MLLN Network is 38% spanning 1800 SDCAs

24 November 2009 Core Network Planning 59

Additional POPs where LL is Around 1000 CircuitsAdditional POPs where LL is Around 1000 CircuitsAdditional POPs where LL is Around 1000 CircuitsAdditional POPs where LL is Around 1000 Circuits

Circles POP Present Addtl POP Circles POP Present Addtl POP

AP 8 1 (Guntur) NE – I 1 0

Assam 4 0 NE – II 0 0

Bihar 4 0 Orissa 3 0

Jharkhand 3 0 Punjab 7 0

Gujrat 5 0 Rajasthan 5 0

Haryana 3 1 (Karnal) Tamilnadu 7 -

HP 1 0 UP-East 6 0

J&K 2 0 Up-West 6 0

Karnataka 7 0 Uttaranchal 2 0

Kerala 5 0 West Bengal 3 0

MP 5 0 Chennai TD 4 0

Chattisgarh 2 0 Kolkatta TD 4 0

Maharashtra 9 0

Only two Cities are there where Additional POP may be required. Further Only two Cities are there where Additional POP may be required. Further Only two Cities are there where Additional POP may be required. Further Only two Cities are there where Additional POP may be required. Further ---- Delhi Delhi Delhi Delhi

And Mumbai will require multiple POPs (4 each) for geographical diversityAnd Mumbai will require multiple POPs (4 each) for geographical diversityAnd Mumbai will require multiple POPs (4 each) for geographical diversityAnd Mumbai will require multiple POPs (4 each) for geographical diversity

24 November 2009 Core Network Planning 60

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 32 of 37

Additional POPs where LL is Around 400 Additional POPs where LL is Around 400 Additional POPs where LL is Around 400 Additional POPs where LL is Around 400 ---- 500 Circuits500 Circuits500 Circuits500 Circuits

Circles POP Present Addtl POP Circles POP Present Addtl POP

AP 8 2 (Kurnool, NL) NE – I 1 0

Assam 4 0 NE – II 0 0

Bihar 4 0 Orissa 3 0

Jharkhand 3 0 Punjab 7 2 (Bathinda,

Pathankot)

Gujrat 5 0 Rajasthan 5 2 (Bikaner,

Srigangangr)

Haryana 3 2 (Hissar, Rohtak) Tamilnadu 7 -

HP 1 0 UP-East 6 0

J&K 2 0 Up-West 6 1 (Bareilly – 713)

Karnataka 7 2 (Shimoga, Tumkur) Uttaranchal 2 1 (Nainital)

Kerala 5 5 West Bengal 3 1 (Asansol)

MP 5 0 Chennai TD 4 0

Chattisgarh 2 0 Kolkatta TD 4 0

Maharashtra 9 0

Around 20 POPs additionally.. This makes the total no of Routers to 30.Around 20 POPs additionally.. This makes the total no of Routers to 30.Around 20 POPs additionally.. This makes the total no of Routers to 30.Around 20 POPs additionally.. This makes the total no of Routers to 30.

24 November 2009 Core Network Planning 61

Executive Recommendation for Enterprise UserExecutive Recommendation for Enterprise UserExecutive Recommendation for Enterprise UserExecutive Recommendation for Enterprise User

• Expansion may have to be done in the existing 15-20 cities only. This can be done through re-arrangement of cards from smaller cities.

Expansion in Top 20-25 Cities

• 10 POPs will be required predominantly at Mumbai and Delhi

• 20 addtl POPs for Cities where LL is > 500 circuits for offering improved SLA to customer.

10 + 20 New POPs

• MLLN spans 1800 SDCAs with plan to cover remaining 800.

• All MLLN Nodes are Virtual Nodes.

Leverage on MLLN infrastructure

• MAN has to be built up in Delhi and Mumbai

• Technologies such as RPR / FTTX / Carrier Ethernet can be explored.

Deploy MAN in Delhi and Mumbai

• In top 98 cities, leverage on the MAN deployed as part of Multiplay.

• Phase III expansion to provision for Ethernet interface for enterprise user

Leverage on existing MAN in Other 98 Cities

• DSL also can be positioned for providing VPN service in smaller cities and also for providing lower bandwidth.

• Each DSLAM acts as MPLS POP, more than 2000 cities

DSL for Lower bandwidth

24 November 2009 Core Network Planning 62

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 33 of 37

Summary of ExpansionSummary of ExpansionSummary of ExpansionSummary of Expansion

24 November 2009 Core Network Planning 63

Details of Interface RequirementDetails of Interface RequirementDetails of Interface RequirementDetails of Interface Requirement–––– A type Cities A type Cities A type Cities A type Cities

Project POI Existing

Interface

per POI

A1 – DLI,

MUM

A1 - 3 A2 - 3 A3 - 6 A4 – 10

Broadband 166 at 106

locations

2 0 10*1 6*1 4*1 2*1

GSM 29

locations

0 0 4 PN -4,

Other - 2

2 RP, NGP,

CBT, VYD,

MYS,

CHD,GWH,

– 2, Other

0

IP TAX 20

locations*

2GE at CHN

and DLI

2 2 2 2 , IND=0 RP,NGP,GW

H,CBT = 2

Wi-Max 22

locations

0 0 2 2 2 RNC, GWH,

CHD = 2,

Other = 0

SSTP 24

locations

2*FE 2 2 2, PN=0 2, IND= 0 NGP,GWH,

CBT = 2

CDR 104 loc 0 8*STM-1 8*STM-1 8*STM-1 8*STM-1

All interfaces in GE unless specified

24 November 2009 Core Network Planning 64

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 34 of 37

Details of Interface Requirement Details of Interface Requirement Details of Interface Requirement Details of Interface Requirement –––– B type CitiesB type CitiesB type CitiesB type Cities

Project POI Existing Interface

per POIB1 B2

Broadband 166 at 106

locations

2 0 0

GSM 29 locations 0 SU,TVM,MYS,

MD,BP ,JAM,

NDA,= 2, Other 0

AMB, SMB,SML,

IP TAX 19 locations* 0 BP,Agra,Rajkot =2 Ambala, Cuttack =

2

Wi-Max 0 NDA, BP, TVM,

LDH, AMR = 2,

Other =0

Calicut, Trichur = 2,

Other = 0

SSTP 24 locations 2 * FE BP,Agra,Rajkot ,

JAM,Shillong =2

AMB, SHM, CUT,

Dimapur = 2

CDR 104 locations 0 4*STM-1 4*STM-1

All interface in GE unless specified

24 November 2009 Core Network Planning 65

Summary of Other RequirementsSummary of Other RequirementsSummary of Other RequirementsSummary of Other Requirements

• Expansion in Top 15 – 20 cities through re-arrangement of cards.

• 10 + 20 new POPs

• Deployment of Metro Area Aggregation Network in Mumbai and Delhi to reduce last mile.

• Leveraging on existing RPR Metro Area Aggregation Network in top 98 cities

For Enterprise

User

• Required in Mumbai, Chennai and Bangalore.

• One high end Router already there.

• One more set of IGW – IGW PE Router per City may be required – Total 6 Routers.

International Gateway

router

• New Core Routers to be deployed in top 15-20 Cities with 10GE connectivity and nx10Ge with Bangalore, Mumbai and Chennai. Total routers = 30-40.

• Existing Core Routers to continue the way as it is.

Core Connectivity

24 November 2009 Core Network Planning 66

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 35 of 37

Line of ActionLine of ActionLine of ActionLine of Action

24 November 2009 Core Network Planning 67

Executive Summary of the RecommendationExecutive Summary of the RecommendationExecutive Summary of the RecommendationExecutive Summary of the Recommendation

• The interface requirement can be taken care by existing spare GE interface / Spare Slots.

• 6 Routers required for IGW to be deployed in Mumbai, Chennai and Bangalore

For Internal User

• Expansion in Top 15 – 20 cities through rearrangement of Cards.

• 10 + 20 new POPs

For Enterprise User

• New Core Routers to be deployed in 15-20 Cities with 10GE connectivity and nx10Ge with Bangalore, Mumbai and Chennai

• Existing Core Routers to continue the way as it is

Core Connectivity

• Unification of Data Network.

• No separate deployment of MPLS network in GSM Phase VI

• Any expansion shall inevitably look into the loading of existing deployment.

•Optimization & Sharing to be an integral part of Planning

Other Points

24 November 2009 Core Network Planning 68

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 36 of 37

Proposal for MNGTProposal for MNGTProposal for MNGTProposal for MNGT

• There have been major changes in the Quantity / SOR.

• So, cancel the existing tender.

Cancellation

of Existing

Tender

• The current requirement has come down drastically in the wake of low traffic from different access network.

• Reassess the traffic trend after one year (Dec ‘ 2010)

Reassess the

Requirement

after One Year

• Core Routers: 40 high end. Through tender

• Edge Routers: Few routers / interfaces in the existing router can be purchased on existing vendor / RQ / leverage on CDR infrastructure.

• Limit the number of OEMs to circumvent inter-op issue.

Minor

Expansion

24 November 2009 Core Network Planning 69

Action ItemAction ItemAction ItemAction Item

BSNL

Business Strategy: How do we sustain this Model

Optimization and Sharing

•BSNL has always been aggressive in

pricing (Low Cost)

•With continuous fall in Tariffs , Operating

Margin are severely impacted.

• To maintain Profitability, sustained effort in

reducing Network cost is one of the key

elements

•Optimization & Sharing to be an integral

part of any planning across business

verticals.

•Optimize CAPEX and OPEX through

sharing of Network & effective inventory

Management. Build as you grow.

•Focus on BSNL Network instead of

individual project or business vertical

specific network .

•End-to-end visibility while planning

•Periodic assessment of utilization of

network

•Nodal Cell: CNP cell for any IP / MPLS

Network incl expansion on existing IP /

MPLS network.

Step towards Integrated, Complementary and Value enhancement modeStep towards Integrated, Complementary and Value enhancement modeStep towards Integrated, Complementary and Value enhancement modeStep towards Integrated, Complementary and Value enhancement mode

What needs to be done?

24 November 2009 Core Network Planning 70

Presentation to Management Committee Analysis of NIB-II MPLS Network

Core Network Planning Page 37 of 37

THANK YOUTHANK YOUTHANK YOUTHANK YOU

For Any Clarification, Pls Contact:

SANJEEV VERMADGM (CNP – IV)

Mob: [email protected]

24 November 2009 Core Network Planning 71

************************************************************************