Copyright © 2011 Railinc Corp. All Rights Reserved.
2012 Industry Projects
and the
RPSWC Process
1
Copyright © 2011 Railinc Corp. All Rights Reserved.
Agenda
• 2012 Industry Projects– Car Hire Data Exchange Edits– 2012 Industry Studies
• Railinc Project Support Working Committee (RPSWC) – What is it?– How does it work?
• Questions?
2
2012 INDUSTRY PROJECTS
3
Copyright © 2011 Railinc Corp. All Rights Reserved.
2012 Industry Projects• 7 projects were identified in April as potential
2012 projects in Asset Utilization & Compensation– Car Hire Data Exchange Edits– Car Accounting Self Service Enhancements– Car Hire Liability File Expansion– Deprescription Electronic Marketplace– Elimination of Reclaims for Empty Cars under Revenue
Billing (Rule 4)– Locomotive HPH and Fuel Equalization Data Exchange– Rejected Cars Visibility
4
Copyright © 2011 Railinc Corp. All Rights Reserved.
2012 Industry Projects• Railinc developed associated business cases
(identified costs and benefits) for 4 projects– Car Hire Data Exchange Edits– Car Accounting Self Service (CASS) Enhancements– Car Hire Liability File (CHLF) Expansion– Deprescription Electronic Marketplace
• The 4 projects progressed to the business case stage were selected in June by the Railinc Project Support Working Committee (RPSWC) based on:– High level themes– Qualitative benefits
5
Copyright © 2011 Railinc Corp. All Rights Reserved.
2012 Industry Projects• 1 project was approved in
August for 2012 development:
Car Hire Data Exchange (CHDX) Edits
– Relatively small project– Envisioning – late 1Q12– Development/
implementation – 2Q12 (as currently envisioned)
6
Why?
Quality Data “In”
Quality Data “Out”
Reduced Claims
Fewer Exception Handlings
Improved industry efficiency and
lower costs
Copyright © 2011 Railinc Corp. All Rights Reserved.
Car Hire Data Exchange Edits• Builds on development work from the 2011 CHDX
Platform Upgrade Project– Alex Pritchett will speak on Thursday at 2pm about this
effort
• Two primary themes under development:– Identification of specific CHDX elements (“critical edits”)
which would cause a file to be rejected• Further identification of soft edits for informational purposes
– Web-based resubmission for specific fields for companies that don’t want to resubmit entire file
7
Copyright © 2011 Railinc Corp. All Rights Reserved.
Car Hire Data Exchange Edits• The Information & Data Quality Task Force will
make recommendations for the critical edits to the Equipment Assets Committee
• They will also solicit feedback from submitters on the CHDX timetable to ensure that rejected files can be corrected and resubmitted in time.
8
Copyright © 2011 Railinc Corp. All Rights Reserved.
Car Hire Data Exchange Edits
Edits to Consider• Mark Look-up
• Detail/Summary Code
• Account Type Code
• Transaction Set Purpose Code
The edit creation process might span several years and that the industry could identify new edits over time for inclusion as “rejectable.”
9
Copyright © 2011 Railinc Corp. All Rights Reserved.
2012 Industry Studies• 2 studies were discussed as 2012 initiatives:
– Mileage Comparison• Compare Railinc Accumulated Mileage Process and resulting
files with CHDX Mileage records
– Deprescription Business Process• Identify scope of work involved in supporting Bid & Offer
process to understand development needs for enhanced Railinc solution
10
RAILINC PROJECT SUPPORT WORKING COMMITTEE
(RPSWC)
11
Copyright © 2011 Railinc Corp. All Rights Reserved.
Railinc Project Support Working Committee (RPSWC)
• Mission:
Maximize Business Process Understanding and the Communication Link between the Industry Business
Stakeholders and Railinc
• Established in 2010
• Includes senior executives from Class 1 railroads and AMTRAK
12
Copyright © 2011 Railinc Corp. All Rights Reserved.
Railinc Project Support Working Committee (RPSWC)
• Three primary roles:
1. Act as Ultimate Sponsors for Industry Initiatives, Interfacing with SOMC and Home Road Decision Makers
2. Prioritize Railinc’s Industry (AAR) Product Investment and Ensure that Industry Needs are Supported
3. Commit to Home Road Finance and Resource Support for Approved Projects
13
Copyright © 2011 Railinc Corp. All Rights Reserved.
Railinc Project Support Working Committee (RPSWC)
• Great industry work is identified and supported, as measured by a positive ROI and qualitative benefits :
• Safety and environmental mandates
• Cost reductions
• Operational efficiencies
• Customer service criteria
14
Copyright © 2011 Railinc Corp. All Rights Reserved.
EAC Meeting
EAC Meeting
RPSWC Project Selection Timeline
JuneJanuary
• Establish 2012 plan and schedule
April
• Preliminary Pipeline Review
• Selection and prioritization of 2013 project opportunities
August
• Final selection of 2013 Project Opportunities
15
October
• Budgeting Review
Identify potential 2013 projects at relevant industry committees and Railinc
Define 2013 project opportunities
Evaluate qualitative benefits and initial quantitative benefits (theme level only)
Further develop 2013 business case
Identify project costs and industry benefits
Define 2013 project estimates; secure formal commitment from RPSWC representatives
Planning for 2014 projects
EAC Meeting
TODAY
Planning for 2013 projects
QUESTIONS?