Copy of GAWPL-civil Work Progress Up to 30-11-2015

15
WORKSHOP Covered Area 311 sq.m S. # DESCRPTION TOTAL NO % COMPLETE 1 Excavation - 100% 2 Foundation 18 100% 3 Plinth & Beam 100% 100% 4 Column 18 6 5 Roof Beam 100% 0% 6 Block Masonry - 0% 7 M E P Work - 0% 8 Finishing - 0% F F L + 0.75 ROOF LEVEL + 5.9 TOC

description

,mbjklbl

Transcript of Copy of GAWPL-civil Work Progress Up to 30-11-2015

Page 1: Copy of GAWPL-civil Work Progress Up to 30-11-2015

WORKSHOP

Covered Area 311 sq.m

S. # DESCRPTION TOTAL NO % COMPLETE REMAINING

1 Excavation - 100% 0%

2 Foundation 18 100% 0%

3 Plinth & Beam 100% 100% 100%

4 Column 18 6 12

5 Roof Beam 100% 0% 100%

6 Block Masonry - 0% 100%

7 M E P Work - 0% 100%

8 Finishing - 0% 100%

F F L + 0.75ROOF LEVEL + 5.9 TOC

Page 2: Copy of GAWPL-civil Work Progress Up to 30-11-2015

SUBSTATION

Covered Area 551.5 sq.m

S.No DESCRPTION TOTAL NO,s % COMPLETE REMAINING

1 Excavation - 100% 0%

2 Lean 100% 0%

3 Foundation 24 100% 0%

4 Plinth & Beam - 100% 0%

5 Column 24 24 0

6 Roof Beam 100% 60% 40%

7 Roof Slab 2 1 1

8 Parapet Wall 0 0% 100%

9 Block Masonry - 0% 100%

10 M E P Work - 0% 100%

11 Finishing - 0% 100%

F F L + 0.75ROOF LEVEL + 4.20 + 4.90

I16
tilalahmed:
Page 3: Copy of GAWPL-civil Work Progress Up to 30-11-2015

SWITCHYARD

S.No DESCRPTION % COMPLETE REMAINING

1 Excavation 100% 60% 40%

2 Foundation 82 82 0

3 Padistal 87 80 7

4

Transformer Foundation 2 40% 60%

Transformers Wall 4 10% 90%

Transformers Pad 2 0% 100%

5

Foundation Fire Wall 1 100% 0%

Fire Wall 100% 20% 80%

6

100 / m 0% 100%

Type 2 100 / m 0% 100%

7 Back Filling 100% 0% 100%

Padestal level +0.75

TOTAL Nos / m

Cable TrenchType 1

Page 4: Copy of GAWPL-civil Work Progress Up to 30-11-2015

WATCH TOWER PRECAST

S.No DESCRPTION TOTAL NO No. COMPLETE No. REMAINING

1 Foundation 12 12 0

2 Column 48 44 4

3 Mid slab 12 12 0

4 Roof slab 12 7 5

Mid slab level +6.050 FFLRoof slab level +9.400 TOC

Page 5: Copy of GAWPL-civil Work Progress Up to 30-11-2015

DORMITORY

Covered Area 225 sq.m

S.No DESCRPTION TOTAL NO,s % COMPLETE REMAINING

1 Excavation 100% 0%

2 Lean 100% 0%

3 Foundation 24 24 0

4 Plinth & Beam 100% 0% 100%

5 Column 30 0% 100%

6 Roof Beam done 0% 100%

7 Roof Slab done 0% 100%

8 Block Masonry - 0% 100%

9 M E P Work - 0% 100%

10 Finishing - 0% 100%

F F L + 0.75ROOF LEVEL + 3.75

Page 6: Copy of GAWPL-civil Work Progress Up to 30-11-2015

WTG,s Progress

S.No DESCRPTION TOTAL NO's NO. COMPLETE REMAINING

1 Excavation 20 20 02 Lean 20 20 03 Anchor cage 20 10 104 Steel 20 9 115 Formwork 20 9 116 Concrte 20 8 127 Backfiling 20 0 208 RMU & GSU shed columns 80 0 809 RMU & GSU Pad 20 0 20

Page 7: Copy of GAWPL-civil Work Progress Up to 30-11-2015

Progress Comparsion As Per Schedule

S.No Activities Description1 WTG'S WTG Foundation2

Watch TowersPre-Cast Structure

3 Erection4 Switchyard Equipment Foundations & Cable Trench

5 Substation Complete Building

6 Workshop Complete Building

7 Dormitory Complete Building

Page 8: Copy of GAWPL-civil Work Progress Up to 30-11-2015

Progress Comparsion As Per Schedule

As Per Site till date Baseline Start8 foundation Poured till 30th Nov Aug 10 '15

12 foundations /12midslabs /7 topslab casted0 erected Jul 1 '15

82 foundations completewith 80 pedistals concrete poured Aug 7 '15

Jul 17 '15

columns in progress Aug 27 '15

Sep 26 '15

Foundations in complete / cable gallery wall and roof poured/ plinthbeam 100% poured/24 columns ot of 24 casted

24 foundations poured out of 24/ plinth bem preparation In progress

Page 9: Copy of GAWPL-civil Work Progress Up to 30-11-2015

Progress Comparsion As Per Schedule

Baseline Finish As per Schedule till date StatusMar 25 '16 5th Foundations poured 0n 9 nov 15 On Schedule

All Should be casted till 17 Feb 2016 On ScheduleJan 2 '16 All Should be erected till 17 Feb 2016 On ScheduleFeb 3 '16 All should be casted till 3 Feb 2016 On Schedule

Jan 28 '16 Building should be complete till 28 jan 2016 On Schedule

Mar 24 '16 Building should be complete till 24 March 2016 On Schedule

Apr 3 '16 Building should be complete till 3 april 2016 On Schedule