Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building...

74
Samantha deVries Advisor: Dr. Thomas Boothby Department of Architectural Engineering The Pennsylvania State University Structural Option Spring 2015 11141 Georgia Ave Wheaton, Maryland

Transcript of Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building...

Page 1: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Samantha deVries

Advisor: Dr. Thomas Boothby

Department of Architectural Engineering

The Pennsylvania State University

Structural Option

Spring 2015

11141 Georgia Ave

Wheaton, Maryland

Page 2: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Owner

General Contractor and CM

Architect

Structural Engineer

Building Overview

• 158 Feet

• 14 Stories

• 180,000 Gross Square Feet

• $44 Million

• Constructed Feb. 2013 – Aug. 2014

• Apartment Building

Project Team

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Image Source: The George Apartments online

Page 3: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Site Information

• Wheaton, MD

• North of D.C.

• Close to Metro Station

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Image Source: Google Maps Image Source: Architectural Documents

Page 4: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Existing Structural System

• 1960’s Concrete Office Building

• Renovation

• Concrete Layout

• Steel Addition Layout

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Image Source: Whiting Turner Progress Photos

Page 5: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Existing Structural System

• 1960’s Concrete Office Building

• Renovation

• Concrete Layout

• Steel Addition Layout

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Image Source: Structural Building Documents

Page 6: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Existing Structural System

• 1960’s Concrete Office Building

• Renovation

• Concrete Layout

• Steel Addition Layout

Image Source: Structural Building Documents

Page 7: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Existing Structural System

• 1960’s Concrete Office Building

• Renovation

• Concrete Layout

• Steel Addition Layout

Image Source: Structural Building Documents

Page 8: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Problem Statement

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Redesign the Addition

• Building Reuse and Renovation

• Lightweight Addition

• Sustainable Alternative

Image Source: Whiting Turner Progress Photos

Page 9: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Melbourne, Australia

• 10-story apartment building

• Forte at Victoria Harbour

Intro to Tall Timber

• Current Tall Wood Buildings

• Cross Laminated Timber

• Benefits and Challenges of tall wood

Image Source: Herald Sun Online

Page 10: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Berlin, Germany

• 7-story apartment building

• E3 Project

Image Source: Green Building Online

Intro to Tall Timber

• Current Tall Wood Buildings

• Cross Laminated Timber

• Benefits and Challenges of tall wood

Page 11: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Future Potential Tall Buildings

• 14-stories under construction in Norway

• 18-stories proposed in Canada

• 34-stories proposed in Sweden

Image Source: Rendering from the Nordic Page

Intro to Tall Timber

• Current Tall Wood Buildings

• Cross Laminated Timber

• Benefits and Challenges of tall wood

Page 12: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Cross Laminated Timber

• Engineered Wood Panel Product

• Layers glued perpendicular (dimensional stability)

• At least 3 plies between 5/8” and 2” thick

• Max manufactured size 10’ x 40’

Image Source: archi-expo.com

Intro to Tall Timber

• Current Tall Wood Buildings

• Cross Laminated Timber

• Benefits and Challenges of tall wood

Page 13: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Cross Laminated Timber

• Engineered Wood Panel Product

• Layers glued perpendicular (dimensional stability)

• At least 3 plies between 5/8” and 2” thick

• Max manufactured size 10’ x 40’

Image Source: woodwindowstoday.blogspot.com

Intro to Tall Timber

• Current Tall Wood Buildings

• Cross Laminated Timber

• Benefits and Challenges of tall wood

Page 14: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Challenges of Using Wood in Tall Buildings

• Combustion during fire

• Connection details (steel loses strength in fire)

• Doesn’t meet code for buildings over 4-6 stories

• Historical fires in wood buildings

• Not used widely in US, therefore knowledge is limited

• Several topics require further research

Intro to Tall Timber

• Current Tall Wood Buildings

• Cross Laminated Timber

• Benefits and Challenges of tall wood

Page 15: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Challenges of Using Wood in Tall Buildings

• Combustion during fire

• Connection details (steel loses strength in fire)

• Doesn’t meet code for buildings over 4-6 stories

• Historical fires in wood buildings

• Not used widely in US, therefore knowledge is limited

• Several topics require further research

Benefits of Using Wood in Tall Buildings

• Renewable construction material (sustainable)

• Versatile material

• Lightweight

• Fast construction time

• Aesthetically pleasing if left exposed

• Heavy Timber burns slowly

Intro to Tall Timber

• Current Tall Wood Buildings

• Cross Laminated Timber

• Benefits and Challenges of tall wood

Page 16: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Proposed Solution

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Proposed Structural System

• CLT Panels Span between Glulam Girders

• Glulam Girders span to Glulam Columns

• Concrete Shear Walls

Image Source: Sourceable Industry New & Analysis

Page 17: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Gravity Redesign

• CLT Floor Panel Design

• Glulam Girder Design

• Glulam Column Design

• Design Summary

• Comparison to Existing System

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Flexure

CM = 1.0

CT = 1.0

Ci = 1.0

CD = 0.9 for Dead Load

CD = 1.0 for Live Load

CD = 1.6 for Fire Performance

Page 18: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Gravity Redesign

• CLT Floor Panel Design

• Glulam Girder Design

• Glulam Column Design

• Design Summary

• Comparison to Existing System

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Flexure Deflections

Live Load Deflection Limit:

l/360

Dead and Live Deflection Limit”

l/240CM = 1.0

CT = 1.0

Ci = 1.0

CD = 0.9 for Dead Load

CD = 1.0 for Live Load

CD = 1.6 for Fire Performance

Page 19: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Gravity Redesign

• CLT Floor Panel Design

• Glulam Girder Design

• Glulam Column Design

• Design Summary

• Comparison to Existing System

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Flexure Deflections Fire Performance (using encapsulation method)

CM = 1.0

CT = 1.0

Ci = 1.0

CD = 0.9 for Dead Load

CD = 1.0 for Live Load

CD = 1.6 for Fire Performance

Live Load Deflection Limit:

l/360

Dead and Live Deflection Limit”

l/240

Page 20: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Gravity Redesign

• CLT Floor Panel Design

• Glulam Girder Design

• Glulam Column Design

• Design Summary

• Comparison to Existing System

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Glulam Girder Design Process Same as CLT Except:

• More sides of material lost in fire performance design

• Volume factor, Cv used in design

• Assumed to be fully braced by floor

Page 21: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Gravity Redesign

• CLT Floor Panel Design

• Glulam Girder Design

• Glulam Column Design

• Design Summary

• Comparison to Existing System

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Glulam Girder Design Process Same as CLT Except:

• More sides of material lost in fire performance design

• Volume factor, Cv used in design

• Assumed to be fully braced by floor

Page 22: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Gravity Redesign

• CLT Floor Panel Design

• Glulam Girder Design

• Glulam Column Design

• Design Summary

• Comparison to Existing System

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Compressive Strength Fire Performance

• 4 sides now exposed to fire

Page 23: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Gravity Redesign

• CLT Floor Panel Design

• Glulam Girder Design

• Glulam Column Design

• Design Summary

• Comparison to Existing System

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Design Summary

• 12th Level

• 7-ply panel on 12th level

• 18” deep girder

• All other levels

• 5-ply panel

• Typical girder 15” deep

• Typical Column 12” x 10 1/2” at base

Page 24: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Gravity Redesign

• CLT Floor Panel Design

• Glulam Girder Design

• Glulam Column Design

• Design Summary

• Comparison to Existing System

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Page 25: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Gravity Redesign

• CLT Floor Panel Design

• Glulam Girder Design

• Glulam Column Design

• Design Summary

• Comparison to Existing System

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Page 26: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Gravity Redesign

• CLT Floor Panel Design

• Glulam Girder Design

• Glulam Column Design

• Design Summary

• Comparison to Existing System

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Page 27: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Lateral Redesign

• Lateral Introduction

• Lateral System Behavior

• Shear Wall Design

• Lateral Design Summary

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Page 28: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Lateral Redesign

• Lateral Introduction

• Lateral System Behavior

• Shear Wall Design

• Lateral Design Summary

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

• Rigid Diaphragm

• Semi-Rigid

• Flexible

Page 29: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Lateral Redesign

• Lateral Introduction

• Lateral System Behavior

• Shear Wall Design

• Lateral Design Summary

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

In-Plane Deflections

Page 30: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Lateral Redesign

• Lateral Introduction

• Lateral System Behavior

• Shear Wall Design

• Lateral Design Summary

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

In-Plane Deflections

• From ETABS Model

• Compare to L/360

Page 31: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Lateral Redesign

• Lateral Introduction

• Lateral System Behavior

• Shear Wall Design

• Lateral Design Summary

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

In-Plane Deflections

• From ETABS Model

• Compare to L/360

Page 32: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Lateral Redesign

• Lateral Introduction

• Lateral System Behavior

• Shear Wall Design

• Lateral Design Summary

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Drift Check (L/400)

• Deflection of Lateral Elements Only

Page 33: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Lateral Redesign

• Lateral Introduction

• Lateral System Behavior

• Shear Wall Design

• Lateral Design Summary

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Drift Check (L/400)

• Deflection of Lateral Elements Only

• Drift due to both Diaphragm and Lateral Elements

• 1.0D + 0.5L + 0.7W for total building drift

Page 34: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Lateral Redesign

• Lateral Introduction

• Lateral System Behavior

• Shear Wall Design

• Lateral Design Summary

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Drift Check (L/400)

• Deflection of Lateral Elements Only

• Drift due to both Diaphragm and Lateral Elements

• 1.0D + 0.5L + 0.7W for total building drift

• 3/8” interstory drift for non-structural elements

Page 35: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Lateral Redesign

• Lateral Introduction

• Lateral System Behavior

• Shear Wall Design

• Lateral Design Summary

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Drift Check (L/400)

• Deflection of Lateral Elements Only

• Drift due to both Diaphragm and Lateral Elements

• 1.0D + 0.5L + 0.7W for total building drift

• 3/8” interstory drift for non-structural elements

Page 36: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Lateral Redesign

• Lateral Introduction

• Lateral System Behavior

• Shear Wall Design

• Lateral Design Summary

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Overturning Moment

• Has been an issue in taller wood buildings due to low mass

• Typically design for uplift

• Original concrete portion very heavy

• OTM not an issue for this building

Page 37: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Lateral Redesign

• Lateral Introduction

• Lateral System Behavior

• Shear Wall Design

• Lateral Design Summary

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Hand Spot Check of Shear Wall Design

• Checked at critical section

• Enough concrete for shear

• Minimum reinforcing provided in field of wall

• Design controlled by flexure

• Reinforcing required at endsImage Source: Structural Building Documents

Page 38: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Lateral Redesign

• Lateral Introduction

• Lateral System Behavior

• Shear Wall Design

• Lateral Design Summary

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Wall Design

• 8” concrete wall w/ 2 curtains rebar

• #4’s at 18” o.c. Vertical

• #4’s at 10” o.c. Horizontal

• Typ. #6’s in the Corners and Ends

Page 39: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Construction Management

• Introduction

• Schedule Analysis

• Cost Analysis

• System Comparison

Breadth Topics:

• Mechanical

• No concealed spaces, mechanical is exposed

• Chose new mechanical system

• Construction Management

• Schedule Analysis

• Cost Analysis

Page 40: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Construction Management

• Introduction

• Schedule Analysis

• Cost Analysis

• System Comparison

CM Scope

• Structure in Addition

• Partitions

• Shear walls for full building

• Sound insulation

Page 41: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Construction Management

• Introduction

• Schedule Analysis

• Cost Analysis

• System Comparison

Schedule Assumptions

• Pre-fabricated panels

• CLT not found in RS Means

• Construction similar to precast concrete

• Steel Addition Concrete topping needs to cure

Estimated Schedule Time:

• Steel: 9 months

• Wood: 4 months

Page 42: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Construction Management

• Introduction

• Schedule Analysis

• Cost Analysis

• System Comparison

Cost Assumptions

• CLT product from Structurlam product info

• All other cost information from RS Means

• 5% estimate added to labor (not many CLT buildings in US)

• No addition for waste included due to prefabrication

• Lower General Conditions Costs in Wood

Estimated Cost:

• Steel: $2.17 Million

• Wood: $2.76 Million

Page 43: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Construction Management

• Introduction

• Schedule Analysis

• Cost Analysis

• System Comparison

Schedule Estimate

• Wood Addition: 9 months

• Existing Steel Addition: 4 months

• 5 months shorter for wood addition

• Approx. 19 months to 14 months

Cost Estimate

• Wood Addition: $2.76 Million ($25 per SF)

• Existing Steel Addition: $2.17 Million ($19 per SF)

• 30% increase for wood addition

• $44 million total cost to $44.59 million (1.5% increase)

Page 44: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Conclusions

• Summary

• Acknowledgements

Proposed Goals

• Redesign Addition Gravity System in Wood

• Design appropriate shear wall system for gravity design

• Investigate feasibility of wood in design for fire performance

• Investigate cost and schedule feasibility

Page 45: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Conclusions

• Summary

• Acknowledgements

Proposed Goals

• Redesign Addition Gravity System in Wood

• Design appropriate shear wall system for gravity design

• Investigate feasibility of wood in design for fire performance

• Investigate cost and schedule feasibility

• Gravity system met goals for redesign

Page 46: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Conclusions

• Summary

• Acknowledgements

Proposed Goals

• Redesign Addition Gravity System in Wood

• Design appropriate shear wall system for gravity design

• Investigate feasibility of wood in design for fire performance

• Investigate cost and schedule feasibility

• Gravity system met goals for redesign

• Lateral design met strength and deflection requirements

Page 47: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Conclusions

• Summary

• Acknowledgements

Proposed Goals

• Redesign Addition Gravity System in Wood

• Design appropriate shear wall system for gravity design

• Investigate feasibility of wood in design for fire performance

• Investigate cost and schedule feasibility

• Gravity system met goals for redesign

• Lateral design met strength and deflection requirements

• Deflection and vibration controlled over fire performance

Page 48: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Conclusions

• Summary

• Acknowledgements

Proposed Goals

• Redesign Addition Gravity System in Wood

• Design appropriate shear wall system for gravity design

• Investigate feasibility of wood in design for fire performance

• Investigate cost and schedule feasibility

• Gravity system met goals for redesign

• Lateral design met strength and deflection requirements

• Deflection and vibration controlled over fire performance

• Wood redesign 30% more expensive, but can be built in less

than half the schedule

Page 49: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Thank you to the following people:

• The engineers at Rathgeber/Goss Associates

• My parents

• The AE faculty and my advisor Dr. Thomas Boothby

• My classmates and friends

Conclusions

• Summary

• Acknowledgements

Page 50: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Thank You

Page 51: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Appendix Contents

Gravity System

• Sound and Vibrations

• Typical Opening

• Floor Tables

• Beam Tables

• Column Tables

• Design Values

Lateral System

• Drift

• In-Place Deflections

• Shear Wall Reinforcement

• Overturning Moment

• Hand Spot Check

CM Breadth

• CLT Cost Table

• Quantity Tables

• Cost Tables

• Schedule Tables

• Schedule

Mech Breadth

• Plans

• Sample Apartment

• Hand Calculations

Page 52: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Appendix

• Sound and Vibrations

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Sound Performance

• Topping required for sound insulation

• Additional weight and height included in design

Vibration Performance

• Single spans isolated apartments from each other

• Vibrations not as important for residential

• Thicker panel required for 12th level, assembly occupation

Image Source: CLT Handbook

Image Source: CLT Handbook

Page 53: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Appendix

• Typical Opening

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Page 54: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Floor Tables

Page 55: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Girder Tables

Page 56: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Girder Tables

Page 57: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Girder Tables

Image Source: CLT Handbook

Page 58: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Column Tables

Page 59: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Column Tables

Page 60: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Design Values

Image Source: CLT HandbookImage Source: CLT HandbookImage Source: Eng. Wood Assoc.

Page 61: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Appendix

• Wind Drift Check

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Page 62: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• In-Plane Deflection

Page 63: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Shear Wall Reinforcement

Modeling Assumptions Using ETABS:

• All bases pinned

• Only lateral system and loads modeled

• 4000 psi NW concrete

• Concrete cracking modifier of 0.7 for walls

• CLT floor modeled as orthotropic

• Only addition modeled

• Actual elevations above ground level used

• Automatic ASCE 7-05 wind loads used and verified

Page 64: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Overturning Moment

Page 65: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Shear Wall Hand Check at Critical Section

Page 66: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Shear Wall Hand Check at Critical Section

Page 67: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• CM Cost Analysis

Page 68: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• CM Cost Analysis

Page 69: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• CM Cost Analysis

Page 70: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• CM Schedule Analysis

Page 71: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• CM Schedule Analysis

Page 72: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Mechanical Plans

Page 73: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Mechanical Sample Apartment

Page 74: Coppin State University...Owner General Contractor and CM Architect Structural Engineer Building Overview • 158 Feet • 14 Stories • 180,000 Gross Square Feet • $44 Million

Building Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion AppendixBuilding Introduction Problem Statement Tall Timber Introduction Proposed Solution Gravity Redesign Lateral Redesign Construction Management Conclusion Appendix

Appendix

• Mechanical Calcs