Cooling Path Case Study Whitepaper

download Cooling Path Case Study Whitepaper

of 18

Transcript of Cooling Path Case Study Whitepaper

  • 8/8/2019 Cooling Path Case Study Whitepaper

    1/18

    A WHITE PAPER FROM

    FUTURE FACILITIES INCORPORATED

    Cooling Path Management for the Mission

    Critical Facility (MCF): A Case Study

    A simulation-based methodology to maximize equipmentresilience and cooling energy efficiency

    Akhil Docca and Sherman Ikemoto

    2/28/2008

    Executive summary

    The proliferation of modern, high-powered IT equipment is creating a new set of coolingchallenges in the data center that can reduce equipment resilience well before the coolingcapacity of the room is reached. This is forcing owner/operators to take a conservativeapproach by overcooling the data center paying more excessively to operate the coolingsystems. This paper is a case study for cooling path management; a simulation basedmethodology to maximize IT equipment resilience and cooling energy efficiency.

  • 8/8/2019 Cooling Path Case Study Whitepaper

    2/18

    2 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    A Case Study for Cooling Path ManagementThe Cooling PathCooling path management is a simulation-based methodology for data center cooling system

    management. The methodology is based on the Virtual Facility approach to data center

    modeling which takes all of the major elements of the data center into full account, including theinfrastructure, cooling components, cabinets and IT equipment. The cooling path is defined as

    the route taken by the cooling air from the ACU supplies, to the inlets of each individual unit of

    IT equipment and back to the ACU returns. Cooling paths are intricate and complex as they

    exist in the data center but are intuitive as a management methodology and straightforward to

    control within the Virtual Facility model to achieve operational objectives for the cooling system.

    Cooling path management is the process of stepping through the full route taken by the cooling

    air and systematically minimizing or eliminating cooling breakdowns and inefficiencies with the

    ultimate goal of meeting the air intake requirement for each unit of IT equipment. Strict

    adherence to the methodology eliminates the need to know in advance where to look for

    problems and enables design options to be addressed holistically over the full scale of the roomfrom the equipment inlets and exhausts to the room itself.

    The cooling path can be split into three primary segments that simplify the methodology as

    shown in Figure 1.

    Figure 1: The Cooling Path is the route taken by the cooling air from the ACU supply to the

    perforated tiles, to the equipment inlets and back to the ACU return

    Each segment has its own specific objectives for improvement and associated set of change

    options for achieving the objectives. This makes the methodology easy to use, repeatable and

    applicable to all combinations of IT equipment, cabinets and rooms. The objectives and

    associated change options are shown in Table 1.

  • 8/8/2019 Cooling Path Case Study Whitepaper

    3/18

    3 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    Segment Description Design Objective Problem areas Design Options1 ACU supply to

    perforated tile Meet flow rate andtemperaturespecification for

    each perforated tile

    Low pressures

    zones due to low

    airflow or flow

    vortices

    ACU selection andplacement

    Blockage relocation

    Tile placement Baffles/diffusers

    2 Perforated tileto equipment

    inlets Meet flow rate andtemperaturespecification foreach piece ofequipment

    Bypass flow from

    perforated tiles to

    ACUs Blanking ACU controls Equipment redistribution Hot/cold aisle Ducting Hot/cold aisle

    containment

    3 Equipmentexhausts to

    ACU returnRecirculation from

    equipment

    exhausts to inlets

    Table 1: The Cooling Path is divided into three segments to simplify the methodologyThe cooling paths are influenced by the room configuration, the IT equipment and how they are

    arranged relative to each other. Any changes to the facility including ACU settings, cabinet

    arrangement and equipment placement will change fundamentally the cooling paths. Cooling

    path management, therefore, is appropriate to initial design of the room and to configuration

    management throughout the data center life span in order to manage cooling problems or

    inefficiencies that creep in over time.

    More information on cooling path management and the Virtual Facility can be found on the

    Future Facilities website (www.futurefacilities.com).

    Case Study DescriptionCooling path management with the Virtual Facility is best illustrated with a case study. Figure 2

    shows a small but representative Virtual Facility that was built in the 6SigmaRoom design

    software. The main objective of the methodology is to minimize cooling problems and maximize

    cooling system efficiency by managing the cooling path for each unit of IT equipment in

    accordance with design objectives. The process should be re-applied for every major change to

    the room configuration or IT equipment.

    http://www.futurefacilities.com/http://www.futurefacilities.com/http://www.futurefacilities.com/http://www.futurefacilities.com/
  • 8/8/2019 Cooling Path Case Study Whitepaper

    4/18

    4 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    Figure 2: Isometric view of the data center case study

    The case study room is designed to the following specifications:

    1000 sq.ft

    23 cabinets, 3.75 kW/cabinet

    90 kW total load, 90 W/sq.ft

    4 ACUs , 120 kW total cooling capacity, n+1

    Three IT equipment configurations were studied to illustrate how cooling path management is

    performed as part of the inventory management process. The configurations selected for studyare:

    Initial design or pre-commissioning

    Loaded to 30% of cooling capacity

    Loaded to 80% of cooling capacity

    Now, lets take a detailed look at each section of the facility starting from the raised floor.

    Raised Floor:The raised floor stands 2 feet off the ground and is non-rectangular to accommodate an

    entrance ramp. The ACUs reside within the room and the chilled water supply plumbing lieunder the raised floor alongside the data and power cables. These must be included the Virtual

    Facility model as they have a significant impact on Segment #1 of the cooling path.

    ACU 01PDU 01

    PDU 02

    PDU 03

    ACU 02

    ACU 03

    ACU 04

    Perforated tiles

    Raised Floor

    Cutout

  • 8/8/2019 Cooling Path Case Study Whitepaper

    5/18

    5 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    Figure 3: Under floor obstructions

    Air Conditioner Unit (ACU):There are 4 ACUs in the room capable of providing 30 kW of cooling and 4,200 CFM of air at

    maximum return air temperature of the 20 C. The set point for each is 22 oC. The ACU control

    system is important to model properly in the Virtual Facility to simulate the actual behavior of the

    ACU in the data center. The ACU libraries and generic models that are available within

    6SigmaRoom model the controls properly and can accurately predict the potential cooling and

    efficiency problems that can occur at any point along the cooling path.

    Figure 4: ACUs are rated at 30 kW of cooling at a maximum return air temperature of 20

    Cable Trays

    Chilled WaterPipes

    Power Cables

  • 8/8/2019 Cooling Path Case Study Whitepaper

    6/18

    6 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    Cabinets:There are a total of 23 Cabinets in the room. 20 of these have been specified to house servers

    and storage equipment (2000 mm height x 600 mm width x 900 mm depth) and the remaining

    three have been specified to house networking equipment (2000 mm height x 800 mm width x

    900 mm depth). All the cabinets are on casters and are 50 mm (2) above the raised floor. The

    cable penetrations at the rear of the cabinets have cold-locks and have a sealing efficiency of80%. The cabinet libraries available within 6SigmaRoom contain all of the detail necessary to

    predict with a high level of accuracy potential cooling and efficiency problems that can occur

    along cooling path Segments #2 and #3.

    Figure 5: Cabinet & Equipment View

    Cooling Path Design at Three Stages of LifeInitial design or pre-commissioning:The initial design of the data center is done often without specific knowledge of the equipment

    that will eventually populate the cabinets. At this stage, the focus of cooling path design is

    limited to Segment #1 as design of Segments #2 and #3 have little meaning given the lack of

    information about the IT equipment that will eventual be deployed. Here, simple 3.75 kW of

    load evenly distributed over the vertical height of each cabinet is used to approximate the fully

    loaded condition. In reality, this is far from the worst case thermal loading condition, but has

    become the standard configuration for cooling design at the pre-commissioning stage.

    Segment #1 is the path from the ACU supplies to the perforated tiles. The design goal is to

    supply a minimum of 450 CFM of cooling air to each perforated tile; an amount, in theory,

    sufficient to hold the 3.75kW cabinets to a temperature rise of 15 C. The ACUs, tiles and

    under-floor obstructions (chilled water pipes, data cables & power cables) can be configured in

    the room to achieve the design goal.

    Cabinet Exterior Shell

    Cabinet Interior Shell (Mounting Rails,

    Equipment & Empty U Slots

  • 8/8/2019 Cooling Path Case Study Whitepaper

    7/18

    7 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    The Virtual Facility reveals a breakdown in Segment #1 of the cooling path in the form of low

    flow by 100 CFM at tile O8 as shown in Figure 6.

    Figure 6: Airflow rate coded by color at each perforated tile

    The under-floor airflow and pressure distribution reveals the root of the problem as shown in

    Figure 7.

    Figure 7: Velocity vector plot of airflow under the raised floor. Note the indicated airflow vortex.

    Airflow vortex Low pressure zone

    Flow from tile O8 is

    below specification

    by 100 cfm

  • 8/8/2019 Cooling Path Case Study Whitepaper

    8/18

    8 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    The vortex creates a low pressure zone that reduces the airflow at the corresponding perforated

    tile (O8) to 450 CFM. This vortex has to be minimized or eliminated to bring Segment #1 to

    specification. Referring to Table 1, under floor problems can be addressed by four methods.

    We start by examining the location of ACU 04 which is supplying the air that is swirling under tile

    O8. After testing a few different locations, the Virtual Facility revealed that a 2 foot shift to the

    left of ACU 04 (Figure 8) reduces the vortex enough to meet the airflow specification.

    Figure 8: ACU 04 was shifted by 2 feet to the left to reduce the vortex generated on the

    downstream side of the floor cutout.

    This design change resulted in a 30% increase in flow rate at tile O8 from 450 to 586 CFM

    above the required 550 CFM specification as shown in Figure 9.

    Figure 9: Reducing the under-floor vortex increases the flow to the corresponding perforated tile

    Tile flow rate at 450 CFM originally Tile flow rate at 600 CFM after the design change

    2 shiftACU 04

  • 8/8/2019 Cooling Path Case Study Whitepaper

    9/18

    9 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    More optimization can be done, but given that specifications are met, cooling path design for the

    pre-commissioning stage is complete. Without knowledge of the equipment, Segments #2 (tile

    to equipment inlet) and #3 (equipment exhaust to ACU) of the cooling path are undefined which

    makes cooling path design for these segments ineffectual.

    In addition to the tile flow rate specification, a hot aisle/ cold aisle arrangement is specified to

    further ensure the resilience of equipment that will eventually populate the room. As we will see

    later in the case study, room-side thermal design guidelines like the hot aisle/cold aisle can be

    defeated easily by high power IT equipment.

    Loaded to 30% of cooling capacityThe case study continues at the stage when the first wave of equipment is deployed and cooling

    path Segments #2 (from the tiles to the equipment inlets) and #3 (from the equipment exhausts

    to the ACUs) come into play for the first time. The room is loaded to 30% of its cooling capacity

    as shown in Figure 10.

    Figure 10: Data center loaded to 30% of cooling capacity

    The Virtual Facility reveals a cooling path problem for a networking unit as shown in Figure 11.

    Figure 11: The color plot shows an over temperature problem within the networking cabinet

    Overheated

    networking unit

    4 networking units

    in two cabinets

    36 storage units in 3

    cabinets

    27 computing units in 7

    cabinets

  • 8/8/2019 Cooling Path Case Study Whitepaper

    10/18

    10 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    We know from the design of Segment #1 that sufficient air is being supplied to the tile in front of

    the cabinet, therefore the problem must exist in cooling path Segments #2 or #3 for this piece of

    equipment. Lets start with Segment #2 where bypass air is the problem to be examined.

    6SigmaRoom can calculate a useful metric called ACU Supply Effectiveness Indexto quantify

    the amount of air that bypasses the equipment and returns directly to the ACUs.

    ACU Supply Effectiveness: the overall percentage of cooling air supplied by the ACUs that

    enters the equipment intake vents (as opposed to returns directly to ACU)

    In the current configuration, only 24% of the cooling air supplied enters the equipment. This

    value can be confirmed graphically by the airflow patterns in front of the networking cabinets as

    shown in Figure 12.

    Figure 12: 76% of the cooling air supplied by the perforated tiles bypasses completely theequipment inlets and returns directly to the ACUs

    A secondary effect of the bypass is poor operating efficiency for ACUs 01 and 02 as shown in

    Figure 13 on the right. The air returns at a relatively cool temperature of 20 C which reduces

    the cooling effect of ACUs 01 and 02 according to the cooling profile shown in Figure 4. As a

    result, ACUs 01 and 02 supply the networking equipment with air that is warmer than desired as

    shown in Figure 13 on the left.

    The amount of bypass air is

    significant in the current

    configuration

  • 8/8/2019 Cooling Path Case Study Whitepaper

    11/18

    11 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    Figure 13: Non-uniform supply temperature is shown on the left that is dictated primarily by ACU

    operating efficiency that is show on the right

    Both the effectiveness index and the non-uniform supply temperature strongly indicate that

    reducing bypass will improve the cooling problem for the networking unit. At the very least, a

    significant amount of cooling energy could be saved.

    Referring to Table 1, bypass reduction for Segment #2 can be accomplished in this case by four

    methods:

    Shutting down ACU 01 and 02 (this option has the added benefit of reducing cooling

    costs) and making the remaining 3 ACUs to operate at a higher efficiency

    Reducing the supply flow rate from the ACUs by 50% (assuming variable speed drives

    are in use)

    Shutting off floor grilles in front of cabinets without any equipment to force the air to

    reach the cabinets with equipment in them

    Redistributing the networking equipment equally in 4 cabinets instead of two

    The options were implemented one at a time to assess the impact individually. Eventually all

    the four options had to be implemented to achieve the best possible result on the resilience of

    the networking equipment without incurring a lot of cost. The resulting overheat plot in Figure

    14 shows that all the networking units that were originally operating above the specifiedtemperature limit are now below the limit.

    ACU 02

    ACU 01

    ACU 03

    ACU 04Warm air being supplied

    by ACUs 01 and 02

  • 8/8/2019 Cooling Path Case Study Whitepaper

    12/18

    12 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    Figure 14: The over temperature condition has been eliminated as a result of reducing bypass

    air associated with the networking equipment

    This result is somewhat counterintuitive in that the over temperature condition was eliminated by

    cutting the cooling supply in half. Figure 15 illustrates why this happened.

    Figure15: Segment #2 cooling path before and after shutting off ACUs 01 and 02.With all the changes made, less cooling air is being supplied, but the supply temperature is

    lower by 5 C. Also, the ACU supply effectiveness has increased from 24% to 47%, which is a

    marked improvement over the original facility layout. These combine to solve the temperatureproblem and reduce the cooling system operating cost by 50%.

    Cooling path design summary at 30% loading:

    IT equipment cooling problems can occur in a partially loaded data center

    Bypass is high before proposed changes Bypass is reduced after implementing the changes

  • 8/8/2019 Cooling Path Case Study Whitepaper

    13/18

    13 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    IT equipment cooling problems are most often associated with cooling path Segments

    #2 and #3 as Segment #1 is typically within specification when the room is

    commissioned

    In this case, the problem was too much bypass air in Segment #2.

    The problem was fixed by shutting down two ACUs, closing the floor grilles in front of

    empty cabinets and distributing the networking equipment evenly in networking row ofcabinets.

    Loaded to 80% of cooling capacityOur case study continues with the introduction of new equipment that loads the room to 80% of

    its cooling capacity as shown in Figure 16. 80 units have been added and the room power

    dissipation has increased from 40 kW to 77 kW. All four ACUs are now operational to

    accomodate the increased equipment load; damper settings have been removed from the

    perforated floor tiles to faciliate maximum airflow to all cabinets.

    Figure 16: 58 servers, 84 storage units and 8 networking units are added to the room.

    8 networking units

    in 4 cabinets

    84 storage units in 7

    cabinets

    58 computing units in

    13 cabinets

  • 8/8/2019 Cooling Path Case Study Whitepaper

    14/18

    14 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    Thermal problems are expected to reappear with the change, and they do as shown in Figure

    17.

    Figure 17: New over temperature problems within one computing and networking cabinet

    The equipment within cabinets C5 and N6 are receiving cooling air that is above their specified

    maximum. A look inside the Cabinets C5 and N6 (Figure 18) shows the specific units that areoverheating.

    Figure 18: Equipment overheat plot C5 and N6 cabinets

    A walk through of the cooling path in the Virtual Facility shows that Segments #1 and #2 are fine

    for both the blade server and networking switch. However, the Virtual Facility reveals that

    Segment #3 problems exist for both units as a significant amount of hot air is being re-circulated

    from the exhausts to the inlets as shown in Figures 19 and 20. At this stage, the concept ofeffectivness indices will be used again as a metric to improve the design. This time, the

    efficiency index will be associated with the equipment inlets.

    Equipment Supply Effectivness - the percentage of cooling air entering a specific piece of

    equipment that comes directly from an ACU supply (as opposed to the exhaust of a neighboring

    piece of equipment)

    IBM Blade

    Center 1

    Rackable C3106

    C5 Cabinet N6 Cabinet

    Cisco 6509

    networking

    switches

    Cabinet C5Cabinet N6

  • 8/8/2019 Cooling Path Case Study Whitepaper

    15/18

    15 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    In the current configuration, only 51% of the air enters the IBM Blade Center 1 comes from the

    ACU supply as shown in Figure 20.

    Figure 20: Hot air from the server across the hot aisle and from its own exhaust is re-ingested

    Specifically, the IBM Blade Center 1 ingests warm exhaust air from two locations a) from its own

    exhaust and b) from the HP DL360 G5 server that sits across the hot aisle. In this case, the hot

    aisle/cold aisle arrangement was defeated by the equipment it was implemented to protect.

    The remaining cabinets in row C house HP DL 360 G4 servers that have a different fan

    characteristic from the G5 servers and blow air into the hot aisle at a lower velocity. Without the

    additional hot air from across the aisle, the IBM Blade Center servers in the remaining cabinets

    (C4, C7, C8, C9 & C10) do not overheat.

    For the Cisco unit, 52% of its cooling air comes directly from an ACU as shown in Figure 21.

    Figure 21: Hot air from the exhaust re-circulates into the intake of the Cisco 6509

  • 8/8/2019 Cooling Path Case Study Whitepaper

    16/18

    16 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    Specifically, the Cisco 6509 power supply at the bottom of the unit is ingesting air that is

    exhausted from the line cards that sit above in the same chassis.

    The re-circulating exhaust air must be reduced to improve the Segment #3 cooling paths for the

    overheating IBM Blade Center 1 and Cisco 6509 units. Referring to Table 1, a simple and cost-

    effective way of reducing re-circulation is to install blanking panels in the empty slots of the

    cabinet. For the IBM unit, most of the exhaust air is prevented from flowing to the front of the

    cabinet where it can be entrained into the inlets as shown in Figure 22.

    Figure 22: Blanking solves the cooling problem for the IBM Blade Center 1 by preventing

    enough exhaust air from re-circulating to the intake

    However, more must be done to solve the cooling problem for the Cisco unit. Here, internal

    cabinet baffling is installed within the cabinet to segregate the intake and exhaust air as shownin Figure 23.

    Figure 23: Internal baffling solves the cooling problem for the Cisco 6509 by segregating the

    intake and exhaust air between the PSU and the Line Cards

  • 8/8/2019 Cooling Path Case Study Whitepaper

    17/18

    17 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    The resulting overheat plot in Figure 24 shows that all the equipment in the data center is

    operating under maximum allowable inlet temperature for the room at 80% cooling load. In

    other words, the full cooling path for each unit of equipment has been designed and

    implemented properly.

    Figure 24: The cooling problems have been fixed for the room at 80% of cooling capacity

    It is important to emphasize once again that each individual unit of equipment in the Virtual

    Facility is modeled explicitly to attain sufficient modeling resolution for full cooling path design.

    Equipments from different vendors have unique power dissipation and air flow characteristics

    such as intake and exhaust size and location and fan flow rates. Capturing these details is

    critical to defining fully cooling path Segments #2 and #3 in the Virtual Facility. Lacking thesedetails would have prevented in this case the insight necessary to solve the cooling problems,

    maximize equipment resilience and improve cooling system efficiency.

    Summary Points High power dissipation and power cooling fans within the IT equipment are driving the

    need for a new simulation-based methodology called cooling path design

    Room-side design guidelines such as specified tile flow rates and hot aisle/cold aisles do

    not ensure resilience for modern IT equipment

    Cooling path design is the systematic improvement of the entire cooling path for every

    unit of equipment in the data center

    Cooling path design must be performed for every change in inventory or room

    configuration as these have a fundamental impact on the cooling path definition for the

    affected equipment

    The Virtual Facility, with its ability to model and track changes to the inventory explicitly,

    provides an effective platform for cooling path design

    In this case study, the follow objectives were achieved:

  • 8/8/2019 Cooling Path Case Study Whitepaper

    18/18

    18 Future Facilities Incorporated. All rights reserved. No part of this publication may be used reproduced or photocopied, transmitted, or stored in a retrievalsystem of any nature, without the permission of the copyright owner. www.futurefacilities.com | A White Paper from FUTURE FACILITIES INCORPORATED

    Stage Problem area Design achievementPre-commissioning Swirling flow under perforatedtile leading to low flow Met the tile flow ratespecification for the room30% loaded to

    capacity Overheating equipment Wasted cooling capacity

    Solved cooling problem for

    networking equipment

    Reduced cooling cost by 50%

    80% loaded to

    capacity Overheating equipment Solved complex coolingproblem for networking andblade server

    References1. ASHRAE. (2005) Datacom Equipment Power Trends and Cooling Applications. Atlanta:

    ASHRAE

    2. ASHRAE. (2006) Design Consideration for Datacom Equipment Centers. Atlanta: ASHRAE

    3. Garday, D and Costello, D. (2006) Air-Cooled High-Performance Data Centers: Case

    Studies and Best Methods.http://www.intel.com/it/pdf/air-cooled-data-centers.pdf

    4. Malone, C. and Belady, C. (2006) Data Center Power Projections to 2014. iTHERM 2006,

    San Diego, CA

    5. Malone, C. and Belady, C. (2006) Metrics to Characterize Data Center IT Equipment Energy

    Use. Proceedings of 2006 Digital Power Forum, Richardson, TX

    6. Patel, C.D., Sharma, R, Bash, C.E., Beitelmal, A. (2002) Thermal Considerations in Cooling

    Large Scale High Compute Density Data Centers, (2002) Inter Society Conference on

    Thermal Phenomena, pg 767-776

    7. Patterson, M., Costello, D., and Grimm, P. (2007) Data Center TCO, A Comparison of High-

    Density and Low-Density Spaces, Hillsboro, Thermes 2007, Santa Fe, NM

    8. VanGilder, J.W. and Schmidt, R.R. (2005) Airflow Uniformity through perforated tiles in a

    raised-floor Data Center. ASME Interpack 05, San Francisco, CA

    AuthorsAkhil Docca is the Engineering Services Manager at Future Facilities Inc.

    Sherman Ikemoto is the General Manager of Future Facilities Inc.

    http://www.intel.com/it/pdf/air-cooled-data-centers.pdfhttp://www.intel.com/it/pdf/air-cooled-data-centers.pdfhttp://www.intel.com/it/pdf/air-cooled-data-centers.pdfhttp://www.intel.com/it/pdf/air-cooled-data-centers.pdf