CONTROL COST – PROBLEM Name:_________

3
CONTROL COST – PROBLEM Name:_________ The Project is to color 4 rooms in a house, each room should take 1 day to color and is budgeted for $100/day. This 4 day project has a Start to Finish Relationship constraint (you have finish coloring the previous room to start working on the next). It’s the end of Day 3 today and the status of the project is as follows: Room 1 is completed and it cost $100, Room 2 is completed and cost $150, Room 3 is half way done (50%) and cost $70. Based on this scenario you have to apply Earned Value Management & Forecasting Techniques to find: 1. Planned value (PV) 2. Earned Value (EV) 3. Actual Cost (AC) 4. Budget at completing (BAC) 5. Schedule Variance (SV) 6. Schedule Performance Index (SPI) 7. Cost Variance (CV) 8. Cost Performance Index (CPI) 9. Estimate at Completing (EAC) 10. Estimate to Complete (ETC) 11. Variance at Complete (VAC)

description

CONTROL COST – PROBLEM Name:_________. - PowerPoint PPT Presentation

Transcript of CONTROL COST – PROBLEM Name:_________

Page 1: CONTROL COST – PROBLEM  Name:_________

CONTROL COST – PROBLEM Name:_________The Project is to color 4 rooms in a house, each room should take 1 day to color and is budgeted for $100/day. This 4 day project has a Start to Finish Relationship constraint (you have finish coloring the previous room to start working on the next). It’s the end of Day 3 today and the status of the project is as follows: Room 1 is completed and it cost $100, Room 2 is completed and cost $150, Room 3 is half way done (50%) and cost $70. Based on this scenario you have to apply Earned Value Management & Forecasting Techniques to find:

1. Planned value (PV)2. Earned Value (EV)3. Actual Cost (AC)4. Budget at completing (BAC)5. Schedule Variance (SV)6. Schedule Performance Index (SPI)7. Cost Variance (CV)8. Cost Performance Index (CPI)9. Estimate at Completing (EAC)10. Estimate to Complete (ETC)11. Variance at Complete (VAC)

Page 2: CONTROL COST – PROBLEM  Name:_________

Approach Process

Room / Day

Planned Value (PV)Budgeted Cost of WorkScheduled (BCWS) for 3 days

Earned Value (EV) Budgeted Cost of Work Performed (BCWP) in 3 Days

Actual Cost (AC)Actual Cost of Work Performed (ACWP) in 3 Days

Budget At Completing (BAC) Total amount of money budgeted for 4 rooms in 4 Days

Room 1-Day 1 @ 100% done ? ? ? ?

Room 2-Day 2@100% done ? ? ?

Room 3-Day 3 @ 50% done ? ? ?

TOTAL @ 3 Days ? ? ?

Please replace “?” with your answers

Page 3: CONTROL COST – PROBLEM  Name:_________

Acronym Formula Solution Interpretation

Schedule Variance (SV) SV=EV - PV

Schedule Performance Index (SPI)

SPI=EV / PV

Cost Variance (CV) CV=EV - AC

Cost Performance Index (CPI)

CPI=EV / AC

Estimate at Completion (EAC)

EAC=BAC/CPI

Estimate to Complete (ETC) ETC=EAC-AC

Variance at Complete (VAC) VAC=BAC-EAC

Solve the Problem