Contracts, Construction and...

38
Contracts, Construction and Commissionings Wind Matters / 2008 Finance and Investment Workshop Toronto, Ontario – February 28, 2008 Uwe Roeper - ORTECH

Transcript of Contracts, Construction and...

Page 1: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Contracts, Construction and CommissioningsWind Matters / 2008

Finance and Investment WorkshopToronto, Ontario – February 28, 2008

Uwe Roeper - ORTECH

Page 2: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Contracts, Construction and Commissionings

• Wind sector success story• State of the market• Challenges

Page 3: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Wind Sector Success Story

• Sources:– CanWEA website– AWEA website– U.S. DOE

Page 4: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Wind Installed – 1,856 MW (Jan/08)

Source: http://www.canwea.ca/Map_of_Installations.cfm

Page 5: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Wind = 1% of Elec. Marketbut 1/3 of new supply built

Canada Power Consumption (TWh/yr)

5

577

Wind Other

Page 6: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Wind penetration elsewhere

Page 7: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Wind Picking Up

• 1,770 MW installed at end 2007• 2,600 MW contracted for 2008-2012• 3,000 MW in RFP / PPA tender stage

» Source, CanWEA

Page 8: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

More in the Wind

• Provincial policy goals:– ON 4,600 MW by 2020– QC 4,000 MW by 2016– AB 1,200+ MW– MB 1,000 MW by 2016– NB 400 MW by 2010– BC 325 MW by 2010– SK 300 MW by 2012– NS 300 MW by 2013– PEI 75 MW by 2013– NFL 51 MW by 2008

» Source: CanWEA

Page 9: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Wind Installed Capacity in Canada

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

Year

MW

137

Adapted from: www.canwea.ca and www.emerging-energy.com

198 236 322 444 684 1,4601,770

Estimated Wind Installed Capacity

Current Wind Installed Capacity

12,475

10,945

9,3707,870

6,6205,220

3,570

14,000

Page 10: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Investment in Wind

• $3 billion invested in wind in Canada• $1 billion/yr. in new wind farms• $70 million/yr. operations• Wind is quickly becoming an

important industry for investment, manufacturing, construction and service sector.

Page 11: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

New Manufacturing Investment News

• Siemens - new blade plant in Iowa• Suzlon - new nose cone plant in Minnesota• Vestas – new blade plant in Colorado• Acciona - new production plant in Iowa• Moventas – doubles gear production• REpower - new turbine plant• GE - doubling annual production

Source: http://www.reliableplant.com/article

Page 12: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Wind Sector Success Story

• Huge growth• Still in infancy• Lots of opportunity ahead ($30 billion

to be invested by 2020)

Page 13: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

State of the Market

• Key market drivers:– Green policy– Feasibility– Power sector deregulation

Page 14: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Excellent Green Policy Support

• Accelerated tax depreciation• $10/MW Federal production incentive• Provincial PPA purchases• Going forward, strong green policy

support is likely to continue (global trend)

Page 15: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Feasibility

• Wind became popular because technology made it almost competitive with traditional sources and it is green.

• Combination of cost competitiveness, scaleability, and green aspects put wind ahead of other green power sources.

Page 16: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Power Sector Deregulation

• Global move to deregulate power sector has increased opportunity for the private sector & wind.

Page 17: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Challenges

• Grid infrastructure is lacking• Power markets are complex• Green power premium hard to value• Energy output is variable• Capital costs are rising• Plant performance not perfect• Operating costs uncertain.

Page 18: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Challenges - Grid

• Canada’s transmission infrastructure is old and not built for distributed generation like wind.

• Deregulation has raised questions about who is responsible for investment in new transmission lines (could become a private sector opportunity).

• Best and cheapest wind resource is often further away and requires transmission line services.

• Canada’s grid systems run north-south, not east-west, making national strategy difficult.

• Jurisdiction for the grid rest with Provinces, resulting in a variety of different approaches.

Page 19: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Power Trade (GWh), 2005

Source: National Energy Board, Canada

Page 20: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

CANADIAN MARKET REGIONS(trading platforms)

http://www.pnrec.org/2001papers/Newcomb.pdf

Page 21: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Challenges – Power Markets

• 10 Provinces = 10 markets (complex)• Various states of deregulation• Various market structures (most are

PPA based because nothing else is in place to attract investors)

Page 22: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

AC4, 75

QC, 175

ON, 156

MB, 28

SK, 19

AB, 61

BC, 62 North, 1

Can. Power Markets (TWh)

Page 23: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Deregulation Status Varies

• Alberta – Wholesale and retail open access - Functional separation

• British Columbia – Wholesale open access - Functional separation

• Manitoba – Wholesale open access - Functional separation

• New Brunswick – Wholesale open access – Functional separation

• Newfoundland – Energy policies under review

• Nova Scotia – Wholesale open access in planning - Functional separation

• Ontario – Wholesale and limited retail open access – Functional separation

• Prince Edward Island – Distribution network only

• Québec – Wholesale open access - Functional separation - Wholesale competition for domestic

• Saskatchewan – Wholesale open access - Functional separation

Page 24: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Export (Example)

REC, 35

US$/MWh, 55

PTC, 0 Tax, 5

Merchant (Example)

$/MWh, 60

Subsidy, 10

Tax, 5

REC, 10

Wind Power Market Types

PPA Market (Example)

$/MWh, 80

Subsidy, 10Tax, 5

Page 25: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Challenges – Green Power Premium

• Canada carbon market and REC market is in its infancy

• No agreement among provinces• “green premium” is buried in PPA

price, ecoEnergy subsidy, tax breaks and REC (where available)

Page 26: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Figure 3 1990 to 2000 Domestic Energy Consumption, Net Energy Export and Emission Trends (source gov’t of Canada)

GHG & Energy in Canada of increasing political concern but no solution

Page 27: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Figure 4 Electricity Generation and Greenhouse Gas Emissions by Province, 2000 (source gov’t Canada)

Provinces differ in industry and policy

Page 28: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Green premium cont’d

• No national plan on the table, long way from consensus, provinces have too much at stake …………

• Premium price PPAs, subsidies and tax breaks are and will likely be the economic policy work around for some time to come.

Page 29: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Challenges – Variable Output

• Wind energy output varies daily, seasonally and from year-to-year. This causes issues for grid system operators who must be reliability focused.

• Initial reluctance by grid operators has been replaced by pro-active cooperation, but significant underlying technical issues still exist.

• Provinces with water power resources can deal with this more easily than others.

• Affects value of wind power.• Variability in output is the Achilles Heel of wind and is the

underlying technical reason for limited reliance on wind (20% of energy supply maximum?).

Page 30: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Challenges – Rising Capital Cost

• High costs increase risk to future growth in wind– Tight turbine supply– Raw materials prices rising– Booming labour market– Financing costs

• Supply needs to catch up to demand

Page 31: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Wind Install Cost

0

500

1,000

1,500

2,000

2,500

3,000

2004 2005 2006 2007 2008

Year

$ / k

W ($

CD

N)

Source: SEDAR

Page 32: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Historical & Projected Wind Energy Costs

0

5

10

15

20

25

30

1980 1985 1990 1995 2000 2005 2010

Year

cent

s U

S/kW

h

Not attainable

Adapted from: CanWEA 2004

Price Reduction Due to

Technology Innovation

Page 33: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Challenges – Plant Performance

• Economic inputs: capital cost, cost of capital, revenue assumption, operating cost assumption.

• Sensitivity: Capital cost and cost of capital are known at project finance stage, but even small changes in revenue or operating cost are significant.

• Canada’s track record in wind is mixed –performing close to but not at target.

Page 34: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Op. Performance Examples

Source: BMO Capital Markets, "Wind Storm", 2007

-5.1%34.0%28.9%Simple Avg.

-10.3%41.4%31.1%Mont Miller

-2.3%37.6%35.3%Pubnico Point

-8.5%39.3%30.8%Mount Copper

-8.7%25.9%17.2%Taylor

-3.8%30.7%26.9%Sinnott

-0.7%30.7%30.0%Cowley Ridge N

-1.1%32.3%31.2%Cowley Ridge

DifferenceExpectedActualWind Farm

Capacity Factor

Operating Performance

Page 35: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Challenges – Operating Costs

• Estimating operating costs over 20 years is challenging because wind equipment has not been around for long enough. Failure statistics and operating experience is limited.

• Cost estimates for the mechanical operation of wind farms range from $10,000 to $90,000 per WTG per year.

Page 36: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Cost of Warranty, Service Maintenance Contracts

• Examples of recent price quotes (note variability).

• Large WTGs typically have slightly higher $/WTG-yr but not the main factor.

$/WTG - O&M + Warranty (Yr. 3-5)

$20

$40

$60

$80

1 2 3 4 5 6 7 8 9

Thou

sand

s

Selected Price Quotations by OEMs

Page 37: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Illustration of Variable Annual Repair Costs

• While unscheduled minor maintenance is expected to remain fairly constant, major repair will occur in intervals and increase in cost with age – but scope of repair is difficult to estimate.

Annual Repair & Maintenance Expenditure (illustration)

$0

$10

$20

$30

$40

$50

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Thou

sand

s

Operating Year

$/W

TG-y

r

Page 38: Contracts, Construction and Commissioningsortech.ca/pdf/power/presentations/ContractsConstruction... · 2009. 4. 6. · • Siemens - new blade plant in Iowa ... AC4, 75 QC, 175 ON,

Conclusion

• Wind industry is booming.• Growth is expected to accelerate and

fundamentals are sound.• A long laundry list of growing pains and

challenges exists that the industry needs to work on to ensure success.

• Understanding the risks and opportunities is key to successful investing in wind.