Contractor Prequalification is it RIGHT for your Project? 2015 NC AWWA-WEA Annual Conference...
-
Upload
oswin-short -
Category
Documents
-
view
214 -
download
1
Transcript of Contractor Prequalification is it RIGHT for your Project? 2015 NC AWWA-WEA Annual Conference...
Contractor Prequalification is it RIGHT for your Project?
2015 NC AWWA-WEA Annual ConferenceRaleigh, North Carolina
Peter F. Schuler, PENovember 16, 2015
2
• Why Prequalify Contractors?• Prequalification Process / Metrics Evaluated• Case Studies• OWASA – Aeration / Odor Upgrades - $10 million
Contract• OWASA – Digester Rehabilitation - $2 million
Contract• Salisbury, MD – BNR/ENR Upgrades - $50 million
Contract
• Conclusions
Presentation Overview
3
Why Pre-Qualify Contractors?• Normal Procurement of Contractors• Contractor submits price and “Qualifications” on bid day• “Qualifications” – bonding Capacity, references, etc.• Low bid wins unless “Qualifications” are not acceptable• Owner then needs to either disqualify contractor
(possible lawsuit) or “grin and bear it”
• Prequalification of Contractors – 2 Step Bid Process• Contractors submit “Qualifications” first and Owner /
Engineer decide whether or not they are qualified• Only pre-qualified contractors can submit bids on bid
day• Low bid still wins – but you have a much better chance
of getting a qualified contractor• Process should not be used to limit the amount of
bidders – just to make sure they are qualified
4
• Request for Qualifications• Purchasing requirements – detailed description of
process• Detailed project description• Forms to fill out• Any State Forms – Minority / SB, AS&I, Wage Rates, etc.
• Contract Drawings (60%, 75%, 90%)• Contract Specifications
• Typically – Owner / Engineer must actively “market” contractors at this step• Normally – Include a “Pre-Bid” Meeting and Site Visit
Pre-Qualification Package - Includes
5
Prequalification Process / Metrics Evaluated
Non-Point Rating Items Criteria
Responsiveness to RFQMust answer all questions and provide all information to be
considered responsive
Debarment Status Cannot be debarred
Contractor’s License Must provide a copy of Contractor License for state project located in
Bonding Capacity / Signed StatementMust provide a signed statement
from Surety demonstrating sufficient bonding capacity
Past Safety PerformanceMust demonstrate safety perfomance
by providing EMR & DART Scores – past 3 years
Minimum Relevant Experience Varies by project as determined by Owner
Unsatisfactory Rating in Any Non-Point Rating Category – Disqualifies Contractor
6
Prequalification Process / Metrics EvaluatedPoint Rating Items (0-4 or 1-5
pts) Criteria
Past Project Performance (25%)Provide details on 3 or more projects of similar scope and
complexity
Personnel Qualifications / Experience (30%)
Essentially resumes of proposed Project Officer, PM,
Superintendent, etc. with a project organizational chart
References – Owners (15%) Schedule, Quality, Cooperation/Coordination
References – Engineers (5%) Overall Rating
Financial Data (5%) Compared against industry standards
Claims/Final Resolutions/Judgements (10%) 6 different categories evaluated
Failure to Complete – Applicant (5%) # of occurrences and explanations
Failure to Complete – Officer (5%) # of occurrences and explanations
Other Relevant Criteria (5% bonus) Varies by Project – Owner Decided
Must Achieve a Minimum of Average Score or Not Qualified
7
Case Study 1– OWASA Mason Farm WWTP
8
New Odor System – NSL Cells
New Turblex Blower
Aeration / Odor Improvements – Case Study #1• Complete Odor Control Upgrades• Nutrified Sludge Cells (NSL)• Aeration Basin Influent Channel• Aerated Cells
• Reduce Power Consumption and Improve Aeration Basin Performance• Replace Jet Aeration with Fine Bubble• Reduce Mixing Power Consumption• Improve Blower Efficiency
• Complete Project by December 2014 to Fulfill Promise to Town• Engineer’s Estimate = $9.5 million
9
• Minimum Experience to Be Demonstrated• 3 Water / WW Projects >$5
million in last 5 years • Experience with staged
construction• Experience with construction
of blowers, diffused aeration, odor control
• Complete project in 18 months
• 75% Contract Drawings / Specifications Provided
Pre-Qualification Requirements– Case Study 1
10
• 21 Contactors Submitted RFQs• 14 Contractors were “Qualified” • 7 Contractors were “Not-
Qualified”• 3 due to safety practices• 3 due to lack of relevant
experience• 1 due to claims and bad references
• Used a 1-5 scale for ratings• Qualified contractors all scored
better than 4.0• Only contractor “not qualified” due
to point rating scale scored 3.4
Pre-Qualification Results– Case Study 1
• New Invent Mixer
11
• Only 4 of 14 Qualified Contractors submitted bids• Low bidder made a math error and bid was thrown
out• Awarded to Haren Construction for $10 million or
$500k over engineer’s estimate• Lessons Learned - Why only 4 bids?• Too many pre-qualified firms – GCs don’t want more than 6
or at most 8 “competitors”(4 firms)• Bigger more attractive projects bidding at same time (4
firms)• Other more local projects to chase (2 firms)• Too much pre-negotiated equipment (1 firm)
• End Result – Project was completed ahead of time with less than 1.5% change orders – excellent project
Bid Day Results / Lessons Learned– Case Study 1
12
Case Study 2– OWASA Mason Farm WWTP
13
Digester 2 - Leaks
Dystor and Roof
Digester 1 and 2 Rehabilitation– Case Study #2• Scope of Work • Install new walls inside digesters 1 & 2• Install new gas membrane cover on
digester 1• Repair damaged concrete inside
control building• Install new roof on old digester control
building• Install new doors, stairway, heaters
and ventilation ductwork• Demolish heat exchangers and piping
that is no longer used• Repair inoperable valves and other
miscellaneous work
• Engineer’s Estimate = $1.9 million
14
• Minimum Experience to Be Demonstrated• 3 WWTP Projects >$5 million in
last 5 years • Experience with staged
construction• Experience with construction /
structural rehabilitation of digesters or other concrete tanks
• Complete project in 10 months
• Attempt to “weed-out” really small contractors • 60% Contract Drawings /
Specifications Provided
Pre-Qualification Requirements– Case Study 2
15
• 8 Contactors Submitted RFQs• 6 Contractors were
“Qualified” • 2 Contractors were “Not-
Qualified”• 1 due to safety practices• 1 due to lack of relevant
experience
• Used a 1-5 scale for ratings• Qualified contractors all scored
better than 4.0 except 1 • OWASA previously had good
experience with GC with <4 score
Pre-Qualification Results– Case Study 2
• Dystor Removed
16
• 5 of 6 Qualified Contractors submitted bids• Awarded to RTD Construction for $1.9 million
or $400 under engineer’s estimate• Lessons Learned - Why 5 of 6 bid?• Only one that declined to bid had recently won too
much work• All qualified contractors were small or mid-sized
firms• Relatively easy bid to put together • Owner made an effort to avoid competing bid dates
• Construction is just starting on this project – so too early to tell how it will go.
Bid Day Results / Lessons Learned– Case Study 2
17
Case Study 3– Salisbury BNR/ENR Upgrade
18
BNR / ENR Upgrade– Case Study #3• Scope of Work • Install new 4 Stage Bardenpho
Process• Install new Blower Building• Install 4th Secondary Clarifier and
rehab 3 existing Secondary Clarifiers• Replace Upflow Filters with Disc
Filters• Install new UV Disinfection Building• Improve Solids Processing System• Install new Class A Lime Stabilization
• Engineer’s Estimate = $52 million• MDE Reviewed Prequalification
Solicitation
19
• Minimum Experience to Be Demonstrated• 3 WWTP Projects >$40 million in
last 10 years • Experience with staged
construction• Experience with blowers and
activated sludge systems• Experience with UV, SCs, Disc
Filters• Experience with Lime Stabilization• Complete project in 30 months
• 90% Contract Drawings / Specifications Provided• Attempted to Prequalify General
and Electrical Contractors
Pre-Qualification Requirements– Case Study 3
20
• 9 General Contactors Submitted RFQs• 7 General Contractors were
“Qualified” • 2 General Contractors were
“Not-Qualified”• 1 due to safety practices• 1 due to lack of relevant
experience
• Electrical Contractors • Were uninterested in the process• Even GCs were unable to get
them to participate• Withdrew this RFQ solicitation
Pre-Qualification Results– Case Study 3
21
• 4 of 7 Qualified Contractors submitted bids• Awarded to Ulliman Schutte Construction for
approximately $50 million • Lessons Learned – • Qualify enough contractors to make sure you have
4 or 5 bids on bid day • A lot of effort was required to put this bid together• Bid date conflicted with DBIA conference• Prequalifying Electrical Contractors or other
subcontractors may be difficult
• Construction is just starting on this project – so too early to tell how it will go.
Bid Day Results / Lessons Learned– Case Study 3
22
• In all three case studies, Owner was able to pre-qualify GCs that met reasonable standards• Bid prices received were generally equal or
less than engineer’s estimate• Pre-qualification of the GCs, eliminated
surprises and Owners were generally pleased with results
Conclusions
2015 NC AWWA-WEA Annual Conference
Raleigh, North Carolina