Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.
-
Upload
jayson-palmer -
Category
Documents
-
view
219 -
download
0
Transcript of Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.
![Page 1: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/1.jpg)
Contracting Practices and Learning to Contract
ESNIE 2004
Nicholas ArgyresBoston University
![Page 2: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/2.jpg)
What kinds of things do we know about the economics of contract structure from empirical studies?
![Page 3: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/3.jpg)
Contract duration
Joskow (1985, 1987): Greater relationship-specific investments associated with longer contracts in coal.
Masten/Crocker (1985, 1988): Performance incentives facilitate longer-term contracting in natural gas.
Pirrong (1993): Longer contracts used to avoid temporal, contractual specificities in ocean shipping.
![Page 4: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/4.jpg)
Payment Terms, Incompleteness
Leffler and Rucker (1991): Payment terms reflect measurement costs in timber harvesting.
Crocker and Reynolds (1993): Greater incompleteness chosen to manage technological uncertainty, longer time horizons.
![Page 5: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/5.jpg)
Equity, Control rights
Pisano (1989), Oxley (1997): Equity alliances more common when R&D is exchanged.
Lerner and Merges (1998): Allocation of intellectual property rights reflects bargaining power as much as marginal contributions in biotechnology.
![Page 6: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/6.jpg)
Assertion
We know much less about how contract structures evolve over time, either: Between two partners Across an industry
Are “optimal” contract structures discovered quickly?
![Page 7: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/7.jpg)
Determinants of Contract Evolution
Well understood: Changes in nature of contractual
hazards Regulatory changes (e.g., natural gas)
Less well understood Shifts in bargaining power (e.g.,
Lerner/Merges) Learning to contract
![Page 8: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/8.jpg)
Why few studies of learning to contract?
Equilibrium theories Cross-sectional studies on old
industries with stable contract structures: Coal Natural gas Petroleum coke Timber harvesting Lobstering
![Page 9: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/9.jpg)
The Evolution of a Contractual Relationship Seller: Small U.S. software developer Buyer: large Japanese
computer/electronics firm Series of short term contracts over 9
years 100% customized software
![Page 10: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/10.jpg)
Four Types of Changes in Contract Changes
Enhancing communication Clarifying responsibilities &
expectations Contingency planning Format changes
![Page 11: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/11.jpg)
Enhancing Communication
Changes to the contract must be in writing (SOW #3) Conflicting requests from HW personnel.
Changes to the contract must be reported in a timely manner (#6) Response to delays caused by #3 change.
Problem reporting process added (#8) #3 change didn’t eliminate conflicting
requests Single point of contact at Softstar (#9)
![Page 12: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/12.jpg)
Clarifying Responsibilities and Expectations
Softstar receives full hardware spec’s (#6) HW had tried to push spec development onto
Sofstar Addition of Softstar deliverables section (#7)
Ensures HW release notes, info about source codes, etc.
Project schedule to be negotiated immediately after contract is signed (#7) To address conflicts over deadlines.
Project schedule to be negotiated into contract (#8) Attention deficit after contract signed.
![Page 13: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/13.jpg)
Clarifying Responsibilities and Expectations (cont’d)
Delivery schedule for hardware platforms from HW Inc. added (#8)
Quality assurance/test procedure added (#9)
Features to be included in each release are added (#10) Conflict: HW wants more content in alpha, beta,
versions, Softstar wants more staggering. Equipment and materials required section
of the contract gets much more detailed (#10)
![Page 14: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/14.jpg)
Planning for Contingencies
Addition of risks/concerns section to the contract (#5) HW complains about delays; Softstar cites
technical problems Clause added: hardware problems,
requested changes lead to re-negotiation of the contract and schedule (#8) Conflicts over definition of “minor” change
request Engineering change process added (#9)
Provides guidelines for price, schedule updating
![Page 15: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/15.jpg)
Planning for Contingencies (cont’d)
Section dealing with how to adjust to changes in industry standards added (#10)
![Page 16: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/16.jpg)
Modifying the Format
System architecture section added (#3)
Revision history section added (#5) Table of contents added (#6) System architecture section
expands to include much more product detail (#6)
![Page 17: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/17.jpg)
Learning to Contract Problems encountered previous
projects/contract were incorporated into future contracts.
Contingencies had to be experienced before they were addressed in contracts – few anticipated. Even after contingencies experienced, several
remedies initially failed, and revision required At no point was effort made to
systematically identify/contract against future possible disturbances.
![Page 18: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/18.jpg)
Nature of Learning
Learning tended to be slow, incremental, backward looking. Problemistic search (Cyert & March)
No evidence of learning from contracts with other parties, or from industry associations, etc.
![Page 19: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/19.jpg)
Governance and Communication
Learning was largely in directions consistent with TCE: Many new contract terms aim to help
prevent/resolve disputes stemming fromself-interestedness, if not outright opportunism
Communication effects of contracts also important.
![Page 20: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/20.jpg)
Figure 1Project Size and SOW (Contract) Length
0
5
10
15
20
25
30
35
40
45
1 2 3 4 5 6 7 8 9 10 11
$0
$50,000
$100,000
$150,000
$200,000
$250,000
$300,000
SOW Pages - TechnicalContent
SOW Pages - AdminProcesses
Total SOW Pages
Estimated Project Cost
Softstar and HW Inc. Relationship
![Page 21: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/21.jpg)
Alternative Explanations
Did detailed contracts reflect efforts to increase safeguards as asset specificity increased? Association between project cost and no. of
administrative pages only begins at SOW #7 Also: can’t ignore interview data
Increased contract length also not due to technical communication requirements only: Administrative pages grew faster than technical
pages
![Page 22: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/22.jpg)
Alternative Explanations (cont’d)
Did parties trust each other less over time and thus require longer contracts? Opposite of suggestion by Gulati 1995, Doz
1996 No evidence of diminishing trust:
Softstar employees, including the project manager in charge of the relationship, report an increase in trust over time
Because documentation in contracts helped avoid “unrealistic expectations”
![Page 23: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/23.jpg)
Contracts as Knowledge Repositories
Contracts can play key role in codifying knowledge about how to collaborate: Such codification may assist in development
of collaborative capability (e.g., Zollo & Winter 2002; Kale Dyer & Singh 2002)
“Contracting routines” can support the kinds of knowledge-sharing routines in alliances emphasized by Dyer & Singh 1998.
![Page 24: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/24.jpg)
Beyond the Flexible Framework
Lewelyn, Macneil emphasized contracts as “flexible frameworks” for adaptation “iron rules” vs. “yielding rules”
When contracts serve as knowledge repositories, rules themselves are added or transformed over time.
![Page 25: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/25.jpg)
Key conditions for repository role Contracts most likely to play
knowledge repository role when: Technical change is rapid Tight compatibility requirements
between buyer/supplier technologies Lawyers are in background
![Page 26: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/26.jpg)
Effects of contracts on trust Some argue for negative effect
(e.g., Macauley 1963; Larson 1992; Uzzi 1997) Especially as relationship continues
(Ring & Van de Ven 1994; Gulati 1995) Others argue for positive effect
(e.g., Sitkin 1995; Lorenz 1999; Poppo & Zenger 2002)
Empirical evidence evidence exists to support both sides.
E.g., negative effect: Malhotra & Murnighan (2002) E.g., positive effect: Poppo & Zenger 2002
![Page 27: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/27.jpg)
Implications for trust debate
In our case, effect was positive. Trust enhanced by:
Better understanding of roles and responsibilities in contracts
“Learning together” atmosphere that developed in contracting process
![Page 28: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/28.jpg)
Implications for TCE In high tech industries, contracting
behavior may not be as forward-looking as theory assumes – contracts slowly evolve toward efficient structure.
Contract design capabilities could vary across firms and become a source of competitive advantage.
Such capabilities could act as a “shift parameter” in TCE calculus: Strong capability -> outsource transactions at
lower threshold level of asset specificity.
![Page 29: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/29.jpg)
2nd Paper We identify several dimensions
along which learning to contract occurs: Dispute Resolution Assigning Roles and Responsibilities Communication Allocating Decision/Control Rights Contingency Planning
![Page 30: Contracting Practices and Learning to Contract ESNIE 2004 Nicholas Argyres Boston University.](https://reader033.fdocuments.us/reader033/viewer/2022051216/5697c0231a28abf838cd436a/html5/thumbnails/30.jpg)
2nd paper (cont’d)
Claim: Learning to contract involves achieving better trade-offs, along each dimension, between: Level of contract detail Use of template vs. Customized contract
Claim: Contract design capabilities inhere primarily in lawyers or managers/engineers depending on key dimension.