a mechanical model for the buckling of unilaterally constrained ...
Contract Termination and Excusable Delay. Definition: An action taken pursuant to a contract clause...
-
Upload
scarlett-garrett -
Category
Documents
-
view
213 -
download
1
Transcript of Contract Termination and Excusable Delay. Definition: An action taken pursuant to a contract clause...
Contract Termination and Excusable Delay
Contract Termination and Excusable Delay
• Definition: An action taken pursuant to a contract clause in which the contracting officer unilaterally ends all of part of the work.
• Types of terminations:– Termination for convenience- in the best interest of the
government– Termination for Cause/Default- Contractor has not
performed– Cancellation- There is no longer a need for the work
Contract Termination and Excusable Delay
• Termination for Cause/Default can be for:– Failure to perform– Failure to adhere to schedule– Failure to comply with specific terms and
conditions– Failure to comply with other terms and conditions
in contract– Repudiation- “just ain’t gonna do it”
Contract Termination and Excusable Delay
• Commercial Contract Termination:– UCC Section 2-309– Requires good faith of all parties• Notice given in reasonable time• Insures other party received unless:–Contract states that in breach or specific
cause no notice agreement will be provided– Termination by mutual consent– Bilateral Agreement required
Contract Termination and Excusable Delay
• Government Contract Termination– FAR 49- identifies government terminations except
commercial items subject to FAR 12– Basically 2 types:
• Convenience: – Contract no longer serves the best interest of the government due to
priorities, end of program, downsizing, other significant events not anticipated
• Default:– Contractor failed to perform one or more actions required in the
contract– General rule: No prior notice entitlement unless contract provision
requires it.
Contract Termination and Excusable Delay
• Notices if required:– Cure Notice: states that contractor will be subject to default
termination unless it corrects a specific contract noncompliance or makes necessary progress to meet the delivery schedule
– Show Cause Notice: asks for explanation of why the contractor should not be terminated for default and affords the contractor an opportunity to “show cause” as to why a termination for default should not be assessed.
– No Cost Termination: issued if the requirement no longer exists and the contractor is not liable to the government for damages the contracting officer may execute a “no-cost termination settlement” FAR 49.402-4
Contract Termination and Excusable Delay
• Government:– Excusable Delay :Protects the contractor from penalty for
• Acts of God or public enemy• Acts of the Government in either its sovereign or contractual capacity• Fire• Flood• Quarantine• Strikes• Epidemics• Unusual Severe Weather• Freight Embargos
• Commercial– Force Majeure (Superior Force) protects the contractor from
unexpected or uncontrollable event that upsets the plan.
Contract Termination and Excusable Delay
• Contract Cancellation– Usually occurs shortly after contract execution– Seller realizes they cannot perform– No cost to either party– Buyer can find other source