Contract Strategy for Midland Bridge
description
Transcript of Contract Strategy for Midland Bridge
Contract Strategty for Midland Bridge
By
Nyasha GaziVandhana Lakshmanaperumalsamy
Cengiz MirapHamad Alhasan
Yuzhou ChenAlhassan Saaka
1.1 Primary Objectives
1. Client Objectives
Primary Objectives
QualityPublic
comfort
Safety
1.2 Secondary Objectives
1. Client Objectives
Secondary Objectives
Use oflocal labour
(non-specialist)
Client involvement
Environmental protection
2.1 Work Packages
2. Work packages
Work Packages
Construction of temporary steel structures
Demolition
Jacking
Stressing
2.2 Sequence of Works
2. Work packagesSite Visit
Design of jacks from contractor
Temporary Work
Widening of existing pilecap
Extending the piers
Jacking of deck
Temporary ramps
Install new tendons
Stressing of tendons & pier demolishing works to be
done simultaneously
Constructing new hearting to the 2 main piers
Jack down the deck – remove the jacks and
temporary ramps
Remove falsework
Test
3.1 Organisation roles
3. Contract strategies
3.2 Payment methods
3. Contract strategies
Specialist Contract
Target cost with Activity schedule
Non - specialist Contract
Target cost with Bill of Quantities
3.3 Tendering
3. Contract strategies
Specialist Contract
Tendering stage 1
Tendering stage 2
Single-stage tendering
Non - specialist Contract
4. Risk Assessment
High risks
Damage to deck
Failure of jacking system
Price changes of materials
Medium risksDisruption to
motorway traffic
Low risks
Failure of falsework
Contamination of river
Flood risks
Thank you!