CONTRACT NO. TE14-KLP09Q-0125: PROVISION OF … LINER DDR Report EIA.pdf · 2015-09-17 · a...
Transcript of CONTRACT NO. TE14-KLP09Q-0125: PROVISION OF … LINER DDR Report EIA.pdf · 2015-09-17 · a...
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
1
CONTRACT NO. TE14-KLP09Q-0125: PROVISION OF
PROFFESSIONAL SERVICES FOR THE DEVELOPMENT
OF A NEW LANDFILL SITE FOR TRANSNET
ENGINEERING AT KOEDOESPOORT CENTRE IN
PRETORIA
DETAILED DESIGN REPORT
LANDFILL LINER DESIGNS
SEPTEMBER 2015
Prepared for : Prepared by:
TRANSNET ENGINEERING DIVISION 160 Lynette Street Kilner Park Pretoria 0184 Tel: 012 391 1429
E-SQUARE ENGINEERING (PTY) LTD 95 First Road Farmall 1747 Kya Sands Tel: 011 875 9907 Fax: 011 875 9906
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
2
Document Control Sheet
PROJECT NAME:
PROVISION OF PROFESSIONAL SERVICES FOR THE DEVELOPMENT OF A NEW
LANDFILL SITE FOR TRANSNET ENGINEERING AT KOEDOESPOORT CENTRE
Project Team:
Project Leader: Hamilton Sithole
Project Manager: Hamilton Sithole
Architect Martin Chinyowa
Architectural Technologist Monametsi Ketlhaetse
Design Engineer: Structural Takudzwa Dodzo
Design Engineer: Civil Alpha Nhambure
Design Engineer: Landfill Andrew Maraura
Design Engineer: Electrical Innocent Matonhodze
Design Engineer: Mechanical Tsunyane Tsotetsi
EIA Professional Gabriel Ngorima
PREPARED CHECKED REVIEWED AUTHORISED
Name
Alpha Nhambure
Takudzwa Dodzo
Hamilton Sithole
Pr Eng 20120515
Hamilton Sithole
Pr Eng 20120515
Signature
Date
10/09/2015
10/09/2015
11/09/2015
11/09/2015
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
3
CHECKIST ON DEPARTMENT REQUIREMENTS
Item
Description Remarks
1.(a)
Design as per National Norms and Standards for
Disposal of Waste to Landfill, Regulation 636, dated 23
August 2013 (Clause 3 (1) and (2).
Yes
(b)
A Classification and Design Report to demonstrate
compliance with Regulation R636 to be submitted by
29 May 2015
Done
(c)
Report signed by the Registered Professional Civil
Engineer, with the name and surname and company,
readable + the ECSA Registration Number
Done
(d) Classification of the waste included Yes
(e)
Drawings signed by a Registered Professional Civil
Engineer, with the name and surname readable + the
Registration Number
Yes
(f) Site geology summarised
Yes
(g) Site geo-hydrology summarised
Yes
(h) All information on all the items in the attached
Regulation R636 section 3 (2) (a) to (i)
Yes
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
4
CONTENTS PAGE
Section Description Page
1.0 INTRODUCTION ................................................................................................................... 6
1.1 Background ........................................................................................................................ 6
1.2 Project Location .................................................................................................................. 6
1.3 Project Team ...................................................................................................................... 7
1.4 Aim of this Report ............................................................................................................... 8
2.0 SCOPE OF WORKS .............................................................................................................. 8
2.1 Waste Disposal ................................................................................................................... 8
2.2 Infrastructure ...................................................................................................................... 8
3.0 INFRASTRUCTURE .............................................................................................................. 9
3.1 Site Status .......................................................................................................................... 9
3.2 Design Aspects ................................................................................................................... 9
3.2.1 Architectural Designs.................................................................................................. 10
Structural .......................................................................................................................... 16
3.2.2 Designs ...................................................................................................................... 16
3.2.3 Civil Designs .............................................................................................................. 16
3.2.4 Electricals Designs ..................................................................................................... 17
3.2.5 Mechanical Designs ................................................................................................... 17
4.0 ENVIRONMENTAL IMPACT ASSESSMENT ....................................................................... 18
4.1 Environmental Impact Assessment ................................................................................... 18
4.1.1 Heritage Impact Assessment ...................................................................................... 18
4.1.2 Ecological Assessment ............................................................................................... 19
4.1.3 Geotechnical Investigation ......................................................................................... 20
4.1.4 Hydrogeological Investigation ..................................................................................... 22
4.1.5 Contaminated Assessment Report ............................................................................. 24
4.1.6 Traffic Impact Study ................................................................................................... 25
5.0 LANDFILL DESIGN ............................................................................................................. 26
5.1 Design Requirements ....................................................................................................... 26
5.2 Design of the Lining System ............................................................................................. 28
5.2.1 Landfill Sizing ............................................................................................................. 28
5.2.2 Detailed Liner Design For The TE Landfill .................................................................. 29
5.3 Landfill Daily Cover ........................................................................................................... 36
5.3.1 Selection for daily cover ............................................................................................. 36
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
5
5.4 Leachate Management ..................................................................................................... 37
5.4.1 Leachate & Contaminated Stormwater Dam ............................................................... 38
5.5 Landfill Operations ............................................................................................................ 39
5.6 Final Cover, Closure & Rehabilitation ............................................................................... 40
6.0 CONCLUSION ..................................................................................................................... 41
Table 1: Landfill Design Guides & Standards ................................................................................. 28
Figure 1: Site Development Plan ................................................................................................... 14
Figure 2: Site Birds Eye View (front of site) .................................................................................... 15
Figure 3: Site Birds Eye View (Back of site) ................................................................................... 15
Figure 4: Main Entrance Gate To Landfill site ................................................................................ 16
Figure 5: Typical Layer Design for Class A Landfill ........................................................................ 27
Figure 9: Typical Final Capping Layer ........................................................................................... 41
ANNEXURES
ANNEXURE 1 Calculations
ANNEXURE 2 Drawings
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
6
1.0 INTRODUCTION
1.1 Background
E- Square Engineering (EE) was appointed by Transnet Engineering (TE) to provide
Professional Services for the Development of a New Landfill Site at Koedoespoort Centre.
TE is an operating division of Transnet SOC Ltd and is the backbone of South Africa's railway
industry with nine product-focused businesses, approximately 120 depots, seven factories
and approximately 13,500 employees countrywide. TE operates from seven operating centres
scattered around the country namely, Koedoespoort, Kilner Park, Durban, Germiston,
Bloemfontein, Salt River and Uitenhage. TE is dedicated to in-service maintenance, repair,
upgrade, conversion and manufacture of freight wagons, mainline and suburban coaches,
diesel and electric locomotives as well as wheels, rotating machines, rolling stock equipment,
castings auxiliary equipment and services.
TE generates a lot of waste from its business that comprise of hazardous and non-hazardous
waste. The hazardous waste generated include chemicals, oils, batteries, lead, medical
waste, chemical sludge etc, Non-hazardous or general waste include food waste, metal,
plastic, rubber, paper, PPE, brake blocks etc. There is also remnants of hazardous waste
such as asbestos from previous Transnet operations in the 80-s. This waste needs to be
treated and managed efficiently and this is the reason for the need to develop the
Koedoespoort Landfill Site. This will service Koedoespoort operations, Germiston and
Bloemfontein regions.
The planning and construction of the facility will be financed by TE and the level of service
that can be provided is therefore determined by the amount that is available from the budget
and the minimum level of services guidelines prescribed by TE.
1.2 Project Location
The intended new landfill site will be developed on a site of approximately 13.7 hectares at
Koedoespoort Centre. The Koedoesspoort centre, erected on 100 hectares of land is the
biggest centre of Transnet Engineering situated in Koedoespoort, Pretoria, Gauteng, South
Africa under the City of Tshwane Metropolitan Municipality. It is located about 6.5km from
Pretoria Central.
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
7
The GPS coordinates for all corners of the facility are as follows:
25 42 55.18E 25 43 37.81E 25 43 35.74E 25 42 54.97E
28 17 30.40S 28 17 33.87S 28 16 56.74S 28 16 59.57S
1.3 Project Team
The following role players are involved in the implementation phase of the Project.
TABLE 1: Project Team
Designation Organisation Contact Person
Client Transnet Engineering DUMA MNQUMEVU
160 Lynette Street, Kilner Park
Pretoria
0184
Tel: (012) 391 1429
Fax: 086 773 1322
Landfill Design Engineers E-Square Engineering (Pty)
Ltd
HAMILTON SITHOLE
95 First Road, Farmall
Kya Sands
1747
Tel: (011) 875 9906
Fax: 011 875 9906
EIA Specialist Mawenje Consulting Africa
(Pty) Ltd
GABRIEL NGORIMA
P.O. Box 1453
Lone hill
1062
Tel: (012) 433 6472
Geohydrology Specialist USK Environmental &
Waste Engineering (Pty)
Ltd
DR STEVE K KALULE
P.O. Box 1018
Ruimsig
Rooderpoort 1739
Tel: (043) 748 5567/45
Fax: 043 748 1114
Geotechnical Specialist
USK Environmental &
Waste Engineering (Pty)
Ltd
DR STEVE K KALULE
P.O. Box 1018
Ruimsig
Rooderpoort 1739
Tel: (043) 748 5567/45
Fax: 043 748 1114
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
8
1.4 Aim of this Report
The report is a detailed design report for submission to Department of Water and Sanitation
(DWS) to obtain a Waste Use Licence.
The report presents the following:
Project Brief
Project Scope
Environmental Impact Assessment Process
Site Geohydrology
Site Geology
Liner Designs
2.0 SCOPE OF WORKS
The overall scope of works for the project is as follows:
2.1 Waste Disposal
Hazardous waste disposal Cell
Leachate dam for contaminated stormwater and landfill leachate dam.
Stormwater management system for clean and contaminated stormwater.
2.2 Infrastructure
For the operation of the landfill, the following facilities will be erected on site;
Recycling facility with an inspection and dispatching office
An administration building
An Operations building
An Access Control Facility with a Weigh bridge and Control room
A Security Office
A Wash bay for trucks connected to contaminated water drainage system
Peripheral gravel ring road within the site
Paved parking area
Monitoring boreholes minimum four (upstream & downstream & 2 others)
Three phase power supply
Perimeter fence
Laboratory
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
9
3.0 INFRASTRUCTURE
3.1 Site Status
The property covers approximately 13.7 hectares most of which are covered with bushy grass
and shrubs. The entire property could be classified into three major zones: i) a rubble
recycling area in the North; ii) concrete manufacturing plant in the Southeast and; iii) an open
undeveloped land. The first two shall be of significance when developing the site. The open
area, which consist of the bulk of the land, has been largely disturbed over several years by
previous activities related to grading, dozing and dumping of mixed waste including: stock
piles of concrete and other construction rubble, paint, tar, scrap metal, tyres, etc. There is
evidence of illegal dumping of material now mostly covered in over grown vegetation. There is
a drainage line that traverses through the site from the southwest towards the eastern portion
of the site. The eastern portion of the site is a low laying area and is characterized by marshy,
swampy and wetland like conditions. This marshy character could have been created by the
impounding of water from the surface water drainage over time, and/or as result of a natural
perched water table i.e. there is an accumulation of groundwater that is above the water table
in the unsaturated zone or marshland in the portion of the site. Ref Hydrogeological Report:
USK 2015.
The site is located around industrial, residential and commercial business areas. There are
gravel roads which are being utilized by the two companies operating there. The site slopes
from the South west to North east. The site is zoned as S.A.R (South African Railway
Services), therefore the site can be developed in any way the Transnet Engineering intends
to, as long as it is in line with T.E core business.
3.2 Design Aspects
Generally, the design criteria follow set guidelines and standards and take cognisance of the
following important aspects;
Use of locally manufactured materials
Unit cost to end-user
Long term maintenance requirements
The design philosophy is that buildings should be functional and provide for adequate natural
ventilation and lighting. Buildings shall be easily accessible by people with disabilities.
Sanitary facilities and water supply shall be provided, all connected to existing municipal
services. Adequate security measures will also be incorporated without compromising the
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
10
safety of people who shall use the facility. The design shall take cognisance of the durability
of the structure and the need to minimise maintenance costs. The design approach shall also
take into consideration the funding limits of the project and the envisaged implementation
modality for the project.
3.2.1 Architectural Designs
a) Design Approach
The Design Approach is based on a smooth operation of contaminated site remediation
and provision new landfill site in line with NEMA and acceptable solid waste management
design, construction and operation. The Approach was also driven by, national
hazardous and general solid waste requirements and municipal regulations that seek to
minimize the environmental impacts associated with landfills.
(i) Site Layout
The landfill and associated facilities are designed to
maximize the site layout
minimize potential environmental impacts
minimize health and safety risks for landfill site operations and the public
encourage recycling in accordance with the waste management hierarchy
make the most efficient use of resources on site
(ii) Access
Main Access to the site will be through Trans road on the South-Eastern part of
the site.
Secondary access will be through Lynette Street via Koedoespoort Operation
site. This access is a strategic access for use during the site contamination
remediation exercise. TE Kilner Park will also be using this access during the
landfill site operation to bring in the waste from TE Koedoespoort Site.
Solid palisade fencing will be provided to secure the site. Security gates will be
provided at the site entrances so that access to the site can be controlled during
office hours. The gate will be locked outside of normal working hours.
(iii) Gate House at Main entrance
It is the first line of active measures to control any incoming or outgoing movement to
the landfill site. This entrance will be used by vehicles coming from other TE sites
namely Germiston and Bloemfontein. The facility comprises of the guard house and
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
11
covered drive way around the guard house only. The guard house has a security
room, toilet, and kitchenette and security control room.
(iv) Administration & Operations Block
It is situated closer to the entrance and facing the bulk of the site. This building
houses the administration and management functions for the Reverse logistics and
Recycle Facilities. It also provides a support function, administration and operations,
with no internal link between these 2 functions in the building.
The Administration will accommodate 15-20 employees and its section in the
building will accommodate the following; covered entrance, reception, male and
female toilets, kitchen, eating area, boardroom, store room and 2 offices one of
which is for the landfill site manager.
The Operations, within the same building but in a different section, will accommodate
20 employees which includes for the landfill site field workers and it will have the
following accommodation; 2 offices, printing room, storeroom, kitchen with kitchen
yard, eating area, male and female change rooms.
(v) Weigh Bridge and Control Room
The weighbridge and control room has been strategically located to ensure that it will
cater for waste coming into the site through the secondary entrance. In order to
monitor and manage the volumes of waste and cover soils coming into the site, a 40
tonne weighbridge will be installed on site. Records of the waste material will be
submitted to the regional authority annually as per permit requirements. The
equipment used to record volumes of waste will be installed in the landfill Control
Room which will be operated by qualified personnel. The landfill Control Room will
be a double storey structure, with a platform used to inspect the waste before it is
taken to the respective areas.
(vi) Reverse logistics and Recycling Centre
This facility is located between all the facilities around the landfill site and close to the
administration and operations block. The activities in the administration and
operations block support the activities in the reverse logistics and recycling centre.
The reverse logistics and recycling centre are in one building accommodating both
operations, with a warehouse in the middle which will house all the day to day
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
12
operations of the facility. The warehouse has an open plan, with different floor
finishes and colours to demarcate different functions within the building, and a drive
through across the building for the trucks to load and offload materials to be recycled
and for separating the reverse logistics and recycling activities.
The warehouse building is designed with 4 roller shutter doors on either side or a
headroom of 8.5m in order to accommodate 2x 5 ton cranes. The warehouse
accommodates enclosed receiving office, enclosed dispatch office, receiving bay,
dispatch bay, sorting area bay, processing and storage bay for each function. On
both ends, the building has an attached single storey structure accommodating 20
employees per each operation, with the following accommodation schedule, male &
female change rooms, eating area, kitchen, storerooms and supervisor’s shared
offices.
Materials to be utilised for recycling and reverse logistic come from day to day
activities carried out at TE sites. The materials are wood, plastic and cardboard.
(vii) Laboratory
The laboratory is positioned close to the recycling facility and reverse logistics for
testing materials to be recycled. This facility will also be used for environmental lab
testing on landfill sites. Testing analysis includes; ground water, leachate, waste
water and solid waste testing. It is a building housing 3 components, dry laboratory,
wet laboratory and cold storage.
(viii) Wet waste area/Composite area
This facility is for cleaning/washing the skips & bins and it accommodates a hydro
wash areas and it is equipped with proper drainage to take the waste residue from
the skips and bins. This is a slab area having a foot print of 100 msq with bund-walls
and a light roof structure to lighten the storm water. It is positioned close to the
reverse logistics and recycling centre to wash the skips after offloading from the
recycling centre.
(ix) Wash Bay
The Washbay will be used for washing the trucks after they have dumped the waste
material either on the landfill site or reverse logistics and recycle facility. The
washbay will be a semi-automated facility which will allow for the spraying off of
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
13
waste residue and other contaminates from the vehicles with minimal human contact
before leaving the site. The Washbay will have concrete guard walls and covered
top. Water nozzles will be placed at both sides, bottom and top, to ensure maximum
reach and spray to the vehicle. 30000 litre tank (3 x 10 000litres) will be installed to
provide water for the washing process. A water collection chamber will be provided
where all wash water will be collected before being directed to the stormwater dam.
(x) Signage
Signage indicating the class of landfill, site rules, emergency contact details and any
other regulations will be erected. These will be done in line with the Client’s
specifications.
b) Proposed Design
The Architectural Design is presented as follows;
(i) Site Development Plan
(ii) 3D Presentations
Figure 1 below is the Site Development Plan (SDP). 3D Presentations of the site are
shown in Figures 2 to 4.
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
14
Figure 1: Site Development Plan
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
15
Figure 2: Site Birds Eye View (front of site)
Figure 3: Site Birds Eye View (Back of site)
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
16
Figure 4: Main Entrance Gate To Landfill site
3.2.2 Structural Designs
Structural designs were done for all the buildings discussed above.
3.2.3 Civil Designs
The following Civil designs were done;
Stormwater Water Management
Waste Water Design
Water Supply Design
Access and Internal Roads
Civil designs are guided by the following standards;
a) Design for Storm Water Drainage
The storm water design is advised by the rainfall and catchment to the proposed
developed site. As indicated in Section 3.2.1, the site has a North-Easterly slope. The
site has also been subject to drainage system that has been directed to the site. A
number of cut-off drains will be constructed on the site at strategic positions to ensure
that general storm water does not get access into and out of the general site. Storm
water cut-off drains will also be constructed around the landfill area to control storm water
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
17
captured on the waste body and also prevent ingress into the waste body of surface
water runoff.
The base of the landfill will be designed to slope at a minimum 3% gradient to facilitate
drainage of any contaminated storm water away from the waste body to a storm water
dam located on the NE side of the landfill.
A small berm of maximum 1m height with a crest width of 0.5m should be constructed
around the perimeter of the excavation of the landfill. The berm will act as containment
for the waste body that will rise above natural ground levels after the excavation has
been filled. The construction of additional berms will not be required, as long as normal
sanitary land filling practices are adhered to, including proper compaction of the waste,
and the correct amount of soil cover is applied during operation, preventing the
occurrence of litter and odours.
b) Water Supply
Potable water will be tapped from the existing municipal water line.
c) Wastewater / Sanitation Facilities
Waste Water will be discharged in the existing municipal sewer line.
d) Access Road Design
The main access to the site will be through Trans road on the South-East part of the site.
The existing road to the site is a Class 4 surfaced road. The road will be allowed to run
undisturbed. The access to the site will be tapped from this road.
The site will be serviced by Class 5 surfaced road as indicated on the Site Development
Plan. The road around the landfill site will be a Class 5 unsurfaced road.
3.2.4 Electricals Designs
Electrical designs will cater for Power Supply into the facility. The design philosophy is that
the building should be functional and be energy efficient. The building services and general
lighting designs will take into account energy saving installations and operations.
3.2.5 Mechanical Designs
The following mechanical systems will be in cooperated in the buildings;
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
18
Heat recovery, ventilation and air-conditioning system (HVAC)
Hot Water Generation
Fire Protection
Fire Detection
Smoke ventilation louvres at roof level.
4.0 ENVIRONMENTAL IMPACT ASSESSMENT
4.1 Environmental Impact Assessment
As per requirements from national landfill standards, an Environmental Impact Assessment
(EIA) study has been conducted to get a Waste Use Licence. Specialist studies were also
carried out to input into the EIA study and the Landfill Cell Design.
The various Specialist studies that were carried out are as follows:
a) Heritage Impact Assessment,
b) Ecological Assessment,
c) Geotechnical Investigations,
d) Hydro geological Investigations covering the following;
i. Geophysical Investigations,
ii. Borehole drilling, rehabilitation and groundwater monitoring
The Specialist studies as extracted from the respective reports carried out are outlined below;
4.1.1 Heritage Impact Assessment
Heritage Impact Assessment was intended to determine the presence of cultural heritage
sites and the impact of the proposed project on these resources within the area demarcated
for the proposed landfill site development.
4.1.1.1 Summary of Findings
The surveyed area has no identifiable heritage resources on the surface but sub-surface
chance finds are still possible.
4.1.1.2 Recommendations
If during the construction, operations or closure phases of this project, any person employed
by the developer, one of its subsidiaries, contractors and subcontractors, or service provider,
finds any artefact of cultural significance, work must cease at the site of the find and this
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
19
person must report this find to their immediate supervisor, and through their supervisor to the
senior on-site manager.
4.1.2 Ecological Assessment
The aim of the study was;
To undertake a study of the vegetation on site and provide species list
To identify red data floral species and important habitat that may occur within the
proposed site
To provide a desktop faunal survey of the site
To assess the impact of the proposed site on the ecological integrity of the area
To provide recommendation on ecological mitigation measures for the proposed
development
To provide an indication of the relative conservation importance and ecological function
of the study area in terms of flora and fauna
4.1.2.1 Findings
Marikana Thornveld (SVcb6) – this is the most widespread vegetation within the project area
and it is endangered vegetation.
4.1.2.2 Findings and Recommendations
It was found that the study area seems to have a general trend of low sensitivity and a
decrease sensitive feature to the north-eastern side, where historic farming and sand
mining and seem to have taken place with higher intensities.
The proposed landfill and associated developments must take special cognisance of the
drainage lines which poses a threat to the integrity of habitats and fresh water resources
if erosion processes continue or are worsened.
There were no protected animal and plant species identified on site, the site warrants a
careful approach to development through keeping the lay-out and construction footprint
to a minimum
There shall be rehabilitation provision for the weed infested previously cultivated potions
of the study site using erosion rehabilitation structures for the river banks and veld
restoration techniques
The majority of the site is suitable for development but the remaining unsuitable potions
should be afforded formal protection. Therefore a development with its associated
footprint and impacts can only be possible under strict environmental protection
guidelines to ensure prevention of further habitat loss for present flora and fauna as it
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
20
causes irreversible damage to biodiversity ecosystems within the Marikana Thornveld
vegetation type in the Savannah biome.
4.1.3 Geotechnical Investigation
The main objective of the study was to assess, evaluate and analyse the present soil material
properties of the site and provide recommendations based on the results.
4.1.3.1 Analysis Of Field And Laboratory Results
a) Site Geology
The site is underlain by shallow shale of the Silverton Formation on the South and the
diabase in the northern third of the site. Whilst the shale is relatively resistant to
weathering and thus the soil cover in the south is relatively thin, the diabase is resistant
too and forms quite a prominent ridge. The hard rock geology is covered by varying
thicknesses of an overburden that typically grades from mature residual soil through
completely decomposed and weathered rock to fresh bedrock. The evidence of the shale
and diabase was intersected in all test pits with the decomposed rock retaining the
original rock structure.
b) Site Hydrogeology
At the time of the investigation, there were no indications of presence of groundwater
within the top 4m from the surface as no water table was encountered in all boreholes
and trial pit locations. However, there was seepage of water from sides of two trial pits at
2.8 m and 3.2 m respectively. This was attributed to a possible localized patched water
table. As discussed previously, an open channel drainage line traverses eastwards
through the site to a marshy ground on the lowest areas of the property.
c) Description of the soils
The site is characterized by the residual soils comprising clayey sand or sandy clay with
pockets of silty clay. Due to the weathering of the shale and diabase, there are variations
to the soil profile across the site. Generally, the soil profile tends to be more deeply
weathered in the northern than in the southern portions.
d) Bedrock
According to borehole and trial pit logs, the depth to hard rock is concluded to be in
excess of about 4.0 and 2.5 m in the northern and southern portions respectively – with
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
21
soft rock being probably between depths of 2 m and 3 m. Tests were terminated between
these depths.
e) Compaction Characteristics
The maximum dry density (MDD) and optimum moisture content (OMC) values ranged
between 1569 kg/m3 and 1996 kg/m3, and 11.6 % and 23.1 % respectively. Usually soils
with MDD greater than 2000 kg/m3 and OMC less than 15% are easier to compact and
recommended for road construction. The MDD is also directly proportional to the strength
characteristics of a soil.
f) Excavation
The boreholes were auger drilled to depths of 1, 0 m to 3.6 m below the surface. The trial
pits were excavated with depths varying between 2.9 m and 4.0 m. The shale and
diabase rocks caused the drilling machine and TLB refusal at those respective depths.
On this evidence the use of a TLB could be utilized to excavate to a depth of about 1.4 m
to 4.0 m below the surface. (The observations regarding depth of excavation refer to
depths measured from existing natural ground level). Hard residual soils and rocks at
deeper depth may result in difficult excavation conditions. The use of a large excavator
(18-20 ton) would probably be required to allow deeper excavations in excess of 4.0 m
over most of the site.
g) Contamination Barrier and Cover
Although the highly weathered to completely weathered residual soil in majority of the
site can be regarded as suitable construction material, much of the clayey or fine material
found was highly variable with considerable portions of silt, sand, etc. that were non
plastic. Laboratory results confirmed it to be of low to medium plasticity. Therefore,
because of its quality and contamination in several places (refer to previous USK
Consulting reports of the site), it cannot form an effective seal between the surface and
the underlying rocks (and any associated aquifer). Neither can it be suitable as one of
the layers for the capping design.
4.1.3.2 Recommendations
Dumped substances into the area should be considered before and during the
construction.
The in-situ clayey or fine material cannot be used as one of the layers for the liner or
capping system due to its quality and contamination
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
22
Ground water expectations should always be considered especially during wetter months
Proposed landfill cell basin floor levels could be extended between 3.0 – 4.0 m below
ground. Sub-surface drainage shall be considered for the floor liner protection
The rock sequence of shale and diabase has undergone weathering thus it is likely not to
withstand pressure of more than 300 kPa
The in-situ clayey sands and sandy clay soils compacted to 98% Standard proctor
density are capable of forming the basin floor
The ground can sustain slopes of up to 450 without posing any slope instability issues
TLB will be required for 1.0 m to 4.0 m deep excavations unless diabase and shale rocks
are encountered. For deeper layers, a 20 ton excavator should be capable of excavating
with little difficulty.
4.1.4 Hydrogeological Investigation
The aim of the study was to;
Conduct a hydro census on site as well as the surrounding area – at least a 250 m
radius;
Conduct a geophysical survey on site by means of magnetic and resistivity methods;
Perform Electrical Conductivity profiling surveys on site;
Collect groundwater samples during the hydro census as well as after drilling of
monitoring boreholes;
Construct a preliminary, robust numerical groundwater model in order to simulate
possible plume extent and migration direction along the natural gradient at the proposed
site; and
To evaluate field generated data as well as information from literature in the public
domain and compile a report.
Assess and evaluate the hydrogeological aspects and requirements, and risk to
groundwater resources for the landfill.
Assess and evaluate the requirements for the landfill containment barrier system
(geomembrane lining) in accordance with the current legal framework and make key
recommendations in relation to the above site investigations.
Develop a suit of site-specific recommendations for consideration during the engineering
design of the proposed landfill site and associated infrastructure.
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
23
4.1.4.1 Findings
Ten private boreholes were identified in the residential area directly to the south of the
proposed site
Residential borehole depth information was sparse as most of the residents were not
present during the time when the borehole was drilled. The maximum recorded depth is
54 mbgl;
Recorded groundwater level information is sparse due to no access for measuring
equipment. Most boreholes were closed up to prevent theft and vandalism
Static groundwater levels could also not be measured due to reasons mentioned above
and some approximations were made. The deepest groundwater level recorded was
10.89 mbgl, which is the exception. All other groundwater levels measured were less
than 6 mbgl. If one compares this with drilling records of the four boreholes that was
drilled on site, most static water levels are above the main water strike zones, which is
indicative of a piezometric level and confined conditions
Two sumps were encountered that was collecting either groundwater seepage or storm
water runoff. If one compares the chemical characteristics of the samples obtained from
the two sumps, they are very similar to groundwater samples from the boreholes in the
residential area
4.1.4.2 Recommendations
The option of engineering a landfill site must be viewed as a mitigation measure to an
existing threat and risk to water resources.
The aquifer at the proposed site is classed as a minor aquifer and can be described as a
low to moderately yielding aquifer system of variable water quality.
Initial studies and existing geological maps suggest that there is a contact zone on the
site.
Geophysical surveys conducted at the site remained non-conclusive about the presence
of the contact zone.
Engineering designs must diligently consider and mitigate the risk imposed by the
probable presence of the contact zone
The aquifer is rated to have a Medium susceptibility.
Due to the clay presence on site, the landfill site poses a low – medium risk to
groundwater contamination risk.
The 4 new drilled monitoring boreholes should be maintained as part of a water quality
monitoring programme.
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
24
Monthly monitoring of water levels, rainfall figures and water quality is strongly
recommended and should strictly be adhered to. This data will form the basis from which
any changes in the groundwater regime are recognized.
A Groundwater Management Plan with relevant Groundwater Monitoring and Reporting
Protocol should be established and calibrated annually
4.1.5 Contaminated Assessment Report
The aim of the assessment was to evaluate the magnitude and severity of pollution of the five
identified sites at Koedoespoort centre.
The five sites are supposedly contaminated with asbestos which must be removed and
dumped in the landfill site under consideration. The landfill site proposed position is Site 5
which is this landfill under consideration.
4.1.5.1 Findings
Sites 1 – 4 are mainly contaminated with asbestos with low levels of heavy metals.
The contamination sources at the sites 1 – 4 can be classified as historical as there is no
on-going activity that is continuing to emit pollutants into the environmental space.
Site 5 was extremely littered with exposed observable asbestos sheets on the surface.
The direct probe drilling undertaken also exposed blue asbestos on sites 1, 4 and 5.
Besides asbestos, it was found that site 5 has been contaminated with the following
substances; Heavy Hydrocarbons (Tar), Coal waste, Oily Wastes and other mixed
wastes.
The contamination at site 5 has both a historical and current context to it, mainly because
the site continues to be used as an illegal dumping site.
The groundwater chemistry results from the samples drawn from the 4 new monitoring
wells at site 5 suggested that there is some level of impact on the groundwater from
contamination at the site.
Underground water was found to be endangered due to the on – going illegal dumping.
4.1.5.2 Recommendations
Given the above findings it is recommended that steps are taken to remediate all 5
impacted sites.
Given the type of contaminants and the wide spread nature contamination especially at
site 5, it is recommended that an onsite remedial option i.e. engineering the site to
contain the pollution be in form of a lined site be considered. The advantage that this
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
25
option offers is that contaminated soil from sites 1 – 4 can be disposed of at the ‘new
engineered and lined site 5, which eliminates risk of transporting contamination far off
site.
4.1.6 Traffic Impact Study
The aim of the study was to evaluate the impact of the development of the site on the
surrounding roads network from a traffic impact point of view
4.1.6.1 Findings
Taking cognizance of the small amount of trips that are expected to be generated by the
development, it is not expected that the additional traffic would have a significant impact
on the surrounding road network.
The addition of the expected trips to be generated is not seen as to contribute to any
significant changes to the current levels of service and congestion along the route.
It is not expected that any traffic from this development will move along the local road
network in the surrounding neighbourhoods affecting the residential region close to the
site. This region is primarily located south of the site (south of the existing railway lines
and Moreleta Street.
The site access will be provided along an existing access route and is not expected to
have an impact on access by the community. The current access route serves other
developments but the current traffic volumes generated by these developments are low
as shown on the applicable figures.
The access to the site is proposed off an existing access road that is well-defined and
constructed as paved route. It intersects with Dykor Street and curves at this intersection
is such that heavy vehicles can turn without difficulty to and from the access route
4.1.6.2 Recommendations
Limited mitigating measures are proposed for the development to ensure safe and
efficient traffic movements and the applicant is to be responsible for the costs associated
with these
It is further recommended that the application is to be supported from a traffic
engineering point of view.
That “Box marking” is provided within the intersections of the access road and Silwereike
Street to prevent blockage of the intersections by queuing vehicles from Moreleta Street
A properly constructed access road is to be provided from the existing access road from
Dykor Street to ensure safe vehicular movements to/from the main access road
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
26
5.0 LANDFILL DESIGN
5.1 Design Requirements
The type of waste to be dumped at the landfill comprise of hazardous and non-hazardous
waste. The hazardous waste generated include asbestos, chemicals, oils, batteries, lead,
medical waste, chemical sludge etc. Non-hazardous or general waste include food waste,
metal, plastic, rubber, paper, PPE, brake blocks etc.
Disposal for this kind of material is only allowed at a Class A landfill. This should be
designed in accordance with section 3(1) and (2) of the Norms and Standards.
In accordance with section 3(1) requirements, the typical layers are as indicated below.
Figure 8 below shows typical liner designs for Class A Landfill.
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
27
Figure 5: Typical Layer Design for Class A Landfill
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
28
The following standard layers have been designed for the landfill site;
a) Layer 1 (top) – Geotextile Filter
b) Layer 2 – 200mm Stone Leachate collection system
c) Layer 3– 100mm protection layer of silty sand or Geotextile protection layer
d) Layer 4 – Composite layer of 2mm HDPE Geomembrane and Geosynthetic Clay Liner
(GCL) or 2mm HDPE Geomembrane and 600mm Compacted Clay Liner (CCL)
e) Layer 5 – Geotextile Filter Layer followed by 150mm Leakage detection system of
granular material or geosynthetic equivalent
f) Layer 6 – 100mm protection layer of silty sand or Geotextile protection layer
g) Layer 7 – Composite layer of 1.5mm HDPE Geomembrane and Geosynthetic Clay Liner
(GCL) or 2mm HDPE Geomembrane and 200mm Compacted Clay Liner (CCL)
h) Layer 8 (bottom) –150mm base preparation layer
Landfill layers are designed in accordance with design guidelines below;
Table 1: Landfill Design Guides & Standards
GUIDELINE
REFERENCE
TITLE
Statute National Environmental Management Act (NEMA) (No. 107 of 1198) &
National Environmental Management Regulations
Statute National Environmental Management Waste Act (NEMWA) (No 59 of
2008)
Guide Minimum Requirements for Waste Disposal By landfill, DWA Second
Edition, 1998
Government
Gazette
Regulation 636 of the Government Gazzette 23 August 2013
5.2 Design of the Lining System
5.2.1 Landfill Sizing
The major purpose of the landfill is to remediate asbestos containing material from Sites 1-5
within the Transnet Koedoespoort area as discussed under the Alternatives Assessment
Report section. After disposing of all this material, waste from TE’s three sites namely
Germiston, Koedospoort and Bloemfontein will be disposed on the remaining space of the
landfill.
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
29
A summary of the Landfill sizing is indicated below. Refer to Annexure 1 for detailed
calculations
(a) The expected waste for disposal from the three sites is
2633.26 tonnes/year.
(b) The amount of Waste to be remediated = 290 110 m3
(c) Maximum cell excavation depth = 4 m
(d) Maximum Available Landfill Area on Site = 31 766 m2
(e) Maximum recommended Side slopes going up and down = 1:4
(f) Maximum height above ground = 15 m
(g) Calculated Maximum Excavated Volume = 106 670.00m3
(h) Calculated Maximum Airspace = 241 117.50 m3
(i) Maximum Total Volume Available on Site is ( (g) + (h)) = 347 787.50 m3
It is therefore concluded that the Landfill is adequate for waste
remediation
(j) Therefore Volume Available after remediation i.e ((i) – (j))
= 57 677.50 m3
(k) From (k) above, the calculated site life after remediation is 20 years (this
is assuming that TE is dumping 2633.26 tonnes per year. An increase in
this quantity results in a reduced landfill life and a decrease in the
quantities disposed will increase the Landfill Life.
In 20ys, the amount of waste that can be dumped on the landfill is
289 822.91 tonnes
5.2.2 Detailed Liner Design For The TE Landfill
The quantity of leachate produced is affected to some extent by decomposition
reactions and initial moisture content. However, it is largely governed by the
amount of external and initial moisture content. Thus, a key first step in controlling
leachate migration is to limit production by preventing, to the extent feasible, the
entry of external water into the waste layers. A second step is to collect any
leachate that is produced for subsequent treatment and disposal to limit the
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
30
amount of leachate that migrates into adjoining areas to a virtually immeasurable
volume. The integrity of the landfill structure and leachate control system should
be maintained.
Discussion on each layer is presented below;
5.2.2.1 Layer 1 – Geotextile Filter
Geotextiles are permeable fabrics which have the ability to separate, filter, reinforce, protect
and drain. Landfill designs consist of many layers to ensure that a durable system is created.
Mixing drainage materials with soils and liquids causes failures to the system. Using
geotextiles to separate these layers ensures long-term durability of the system; they
strengthen and stabilize by providing a permeable separation layer. Geotextiles are available
in different styles having various opening sizes which allows the designer to select the
appropriate filter opening size for specific soil conditions.
On this layer, the geotextile will serve the following purpose;
(i) Protection layer to prevent intrusion of soil and other waste into the layers underneath
(ii) Permeable filtration layer to separate liquid waste from solid waste.
General considerations for this layer are as follows;
(i) An A6 geotextile which provides the top end performance for available geotextiles. This
is a non-woven, continuous filament needle punched geotextile with the following
advantages;
High through flow and excellent filtration
High isotropic strength
High elongation
Superior chemical resistance
(ii) The selected filter has to last for the operational life of the landfill and the time it takes to
fill it, i. e. 20yrs (as per landfill site calculations).
(iii) The geo-textile should have 6 months life in the sun
5.2.2.2 Layer 2 – Leachate Collection System
Three different options have been considered on this layer as follows;
(i) Granular soils i.e 19mm stone and silty sand
(ii) Geosynthetics e.g geonets and geocomposites
(iii) Alternative materials such as recycled materials like tyres and glass cullet
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
31
The following considerations have been evaluated;
The material should be permeable enough to collect and transport leachate.
In case of soils and alternative materials, permeability tests are performed using standard
test methods
In case of geosynthetics, the equivalency in the hydraulic conductivity is considered.
The material should avoid accumulation of leachate head greater than 150mm
The material should be chemically compatible with the waste. For soils and alternative
materials, chemical compatibility is checked by immersing the test sample in a
representative leachate for two to three months and then a grain size analysis is
performed. If there is a difference in the grain size distribution between the original and
tested samples, it means its not compatible.
The material should not damage the liner. In the case of soil particles, sharp particles
have a potential of damaging the liner.
The material should be stable on slopes. The stability on slopes must be evaluated
The material should not get clogged easily. Clogging potential should be checked
In this design, a geosynthetic layer has been selected for the side slopes because of the
following;
Geosynthetics are already tested and have known properties. This gives us better quality
assurance (a requirement as per Regulation 636, Clause 3(2) (g)) as human error is
reduced during construction which would not be the case if using granular and alternative
materials.
Geosynthetics ensure a high degree of consistency within the layer
A geosynthetic collection layer eliminates the need for a protection layer.
Geomembranes in the liner system are only able to perform their function if they are
reliably protected against damage during installation and landfill operation. This makes
the use of geosynthetic suitable.
Geonets are a lot more stable on slopes than sand.
However, the base of the leachate collection will comprise of a 200mm stone leachate
collection layer for the following reasons
The stone layer will provide support for the leachate collection pipes
The extra depth i.e. 200mm + 100mm will reduce the leachate head that will extend into
the waste body
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
32
The drainage layer must contain drainage pipes of adequate size, spacing and strength to
ensure atmospheric pressure within the drainage application for the service life of the landfill.
To ensure that no leachate accumulates, the leachate should gravitate to leachate collector
pipes that drain to a leachate drainage network which lead to a leachate dam via a sump.
110mm diameter perforated HDPE pipes at 25m centres are recommended for the drainage.
The leachate should gravitate into 200mm diameter perforated HDPE pipes.
5.2.2.3 Layer 3 – Geotextile Protection Layer
On this layer, another geotextile is encooperated to protect the geomembrane underneath. It
has been found out that with a landfill liner at temperatures of 350C, the oxidant depletion time
for the geomembrane if it is in a composite liner with a geotextile protection layer is 40 years.
For the required life of 20years, this combination will be suitable.
The geotextile used should be minimum 1000g/m2 A10 bidim.
5.2.2.4 Layer 4 – Composite Liner
A composite liner is used for this layer consisting of a combination of either;
(i) Geomembrane (GM) and Compacted Clay Liner (CCL)
(ii) Geomembrane (GM) and Geosynthetic Clay Liner (GCL)
The following considerations have been evaluated;
Composite liners involving either a GM over a GCL or a GM over a CCL result in
leakages many orders of magnitude less than that expected for single liners. (Rowe,
2005). Thus using a composite liner in this design.
Geomembranes prevent contamination of soil and groundwater by leachate seepage.
This layer requires a material which is impermeable and heat resistant.
The required CCL, if used should have a high potential of expansion, with plasticity index
more than 20.
Factors determining the selection of GCL and CCL;
a) CCL Properties
Materials - Are obtained from native soils or blends of native soils and bentonites
Thickness - The layer thickness should be minimum 600mm
Permeability - should be less than or equal to 1 x 10-10 m/s
Constructability – slow speed and complicated
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
33
Manufacturing Quality Assurance & Manufacturing Quality Control - These are
naturally found materials or mineral layers generally requiring little inspection
Construction quality assurance & Construction Quality Control – complex procedures
requiring highly skilled and knowledgeable people.
Field desiccation Sensitivity – CCLs are nearly saturated; they can desiccate during
construction
Availability of materials – Varies widely from readily available to not available at all
Experience – CCLs have been used for many decades with great confidence as a
linear material.
b) GCL Properties
Materials – made of bentonites, adhesives, geotextiles and geomembranes
Thickness - The layer thickness should be 7 – 10mm @ minimum 3.8kg/m2 which is
equivalent to 600mm of compacted clay.
Permeability - should be less than or equal to (1 -5 )x 10-11 m/s
Constructability – rapid, simple installation
Manufacturing Quality Assurance & Manufacturing Quality Control - These are
naturally found materials or mineral layers generally requiring little inspection
Construction quality assurance & Construction Quality Control – factory
manufactured material requiring constant inspection
Field desiccation Sensitivity – GCLs cannot desiccate during construction unless
prematurely hydrated.
Availability of materials – Materials are available at different suppliers and readily
transported to any site
Experience – There is limited use due to newness and non-familiarity
The factors highlighted above indicate that a GCL would be more ideal for use than a
CCL. To add on, the type of clay on site has medium to low potential of expansion with PI
less than 20 thereby not suitable for use. All material will have to be imported. It has also
been found out that composite liners involving a GM over a GCL gives rise to
substantially less leakage than those involving a GM over a CCL. (Rowe, 2005).
Precautions must be taken when placng a GCL. The moiture content of the soil below
should be as close to the optimum moisture content as possible (OMC). The GCL should
be covered as quickly as possible after placement.
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
34
To add on, based on the fact that this is a Class A site which is a high risk, quality takes
priority over all other factors like cost etc. As such a GCL is the best option.
Selection for an HDPE
The selection for an HDPE is based on
Impermeability
This layer requires a material which is impermeable and heat resistant. This necessitates
the use of an HDPE geomembrane.
Service life
Service life is dependent on the polyethylene resin, the carbon black and the anti-oxidant
package. The anti-oxidants are depleted over time especially when immersed in water at
elevated temperatures. A 2mm HDPE will be utilised in this layer as recommended in the
regulations. A 2mm HDPE offers a long term time to anti-oxidant depletion.
Selection for a GCL
Three data sheets were obtained from AQUATAN. The Bentomat CL has been selected
because of its low conductivity which ensures a low passage for leachate. ASTM 5887 testing
is performed only on a periodic basis because the membrane is essentially impermeable.
5.2.2.5 Layer 5 – Leakage detection system (Underdrainge Monitoring System)
A geotextile filter is encooperated to filter any leachate from the liner, separate the liner and
the layer beneath (150mm leakage detection system) and to protect the liner. A6 bidim is
recommended. On the sides however, a geonet is used in place of 150mm stone, thus a
geotextile filter will not be required.
The leakage detection system follows. This system ensures that any leachate from the
system is collected in a sump. Samples for monitoring leachate will be taken from this sump
at regular basis during the operational phase of the landfill.
To ensure that no leachate accumulates, the leachate should gravitate to leachate collector
pipes that drain to a leachate drainage network which lead to a leachate dam via a sump. 100
by 100mm finger drain filled with 19mm stone wrapped in bidim at 25m centres are
recommended for the drainage.
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
35
5.2.2.6 Layer 6 – Geotextile Protection Layer
For Class A Landfills, extra precautions should be taken to ensure that no leachate escapes
into the ground water beneath. A geotextile protection layer, A10 bidim as described above is
installed.
5.2.2.7 Layer 7 – Composite Liner
Another composite liner as described in Layer 4 above is put on this layer. The differences
are
(i) the use of 1.5mm HDPE pipe in place of 2mmm pipe
(ii) use of a CCL in place of a GCL
(iii) thickness on the CCL which should be 200mm as opposed to the 600mm for Layer 4 in a
case whereby a CCL would have been used.
Lighter layers are used since this is serving only as a precautionary measure; we are not
expecting critical situations as in Layer 4.
5.2.2.8 Layer 8 (Bottom) 150mm Base Preparation Layer
The 150mm base preparation layer is a preparatory base for the cell. It is to be compacted to
95% MOD AASTHO and acts as a foundation for the liner. It should slope at a minimum 3%
gradient towards the lowest corner of the landfill cell.
5.2.2.9 Summary of Recommended Layers
Table 2: Summary Of Recommended Layers And Prospective Suppliers
Layer Material Specification Supplier
Contacts Quantity
required
1 Geotextile A6 Bidim or
similar
Kaytech 031 717 2300
2 (i) Geosynthetic
(slopes)
1. Flownet™ Kaytech 031 717 2300
2. Geonet GN
1250
Aquatan 011 974 5271
(ii)200mm
leachate
collection
layer(Base)
3. 19mm stone Commercial
Sources
4. 110mm
Perforated
Kaytech,
Geotextile
031 717 2300,
011 965 0205
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
36
HDPE Pipe Africa
3 Geotextile A10 Bidim Kaytech 031 717 2300
4
2mm HDPE
Geomembrane
Hi-DRILINE®
Textured
(HDPE)
Aquatan 011 974 5271
Geosynthetic
Clay Liner
X800
(4010g/m2)
Kaytech 031 717 2300
Bento 6 NFP
4000
(3670g/m2)
Geotextile
Africa
011 965 0205
5 (i) Geosynthetic
(slopes)
5. Flownet™ Kaytech 031 717 2300
6. Geonet GN
1250
Aquatan 011 974 5271
(ii)200mm
leachate
collection
layer(Base)
Geotextile A10
Bidim
Kaytech 031 717 2300
19mm stone Commercial
Sources
110mm
Perforated
HDPE Pipe
Kaytech,
Geotextile
Africa
031 717 2300,
011 965 0205
6 2mm HDPE
Geomembrane
Hi-DRILINE®
Textured
(HDPE)
Aquatan 011 974 5271
CCL 200mm Commercial
Sources
7 Base Preparation 150mm In situ
Material
5.3 Landfill Daily Cover
A landfill daily cover helps control and prevents disease, fire, odour, blowing litter and
scavenging in landfills. It is also expected to control dust, improve general site aesthetics and
act as a moisture barrier to limit excess precipitation from entering waste.
5.3.1 Selection for daily cover
The following considerations were made during the selection;
a) Soil
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
37
Soil is one of the cover materials that can be used.
It however consumes landfill space, 150mm thickness every day that could be used
for waste disposal. The size of each lift will vary depending on the quantity of waste
that is received each day. The use of cover material should be very carefully
managed so that no more than 15% of the total waste-fill in place comprises cover
material (i.e 150mm for every 1m of waste in place). If excessive cover material is
used, additional materials will have to be imported during the later operation of the
site.
Wet weather conditions can complicate the application of the cover.
Compactions must be proper to ensure the landfill reaches the design life
Plant will be required for compactions. The municipality may however run short of
plant or experience breakdowns thus affecting the landfill operation.
b) Geotextiles
is an ideal reusable daily cover material to provide overnight surface confinement
Ease of handling allows Geotextile to be quickly installed and removed on a daily
basis thus consuming no landfill space
It can be easily installed even in cold, wet weather. Its smooth surface makes it slide
easily over compacted refuse, and its tight fiber structure sheds excess precipitation.
Geotextile can be used over and over again.
For this design, an A10 Bidim geotextile is recommended for daily cover because of
reasons given above.
5.4 Leachate Management
Further to the considerations taken under the leachate collection layer, a sump will be
provided in the cell. This sump will have a 2.5mm thick HDPE liner over the 1.5mm HDPE
liner. An HDPE riser pipe will be inserted into the sump which will be perforated for the depth
of the sump. The HDPE pipe will be anchored to the side slope. A well sized submersible
pump will then be inserted into the HDPE pipe with an automatic level switch that will
automatically pump leachate once the sump is full to minimise start and stops in a timeous
manner.
The leachate collected from the landfill cell will be discharged in a leachate dam. This
leachate dam will also receive water from the stormwater dam. The mixture will be treated
and discharged into the municipal line.
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
38
5.4.1 Leachate & Contaminated Stormwater Dam
The dam will be constructed in a similar manner as the landfill cell. Below is a summary of the
layers.
Table 2: Summary Of Recommended Layers And Prospective Suppliers
Layer Material Specification Supplier
Contacts Quantity
required
1 Geotextile A6 Bidim or
similar
Kaytech 031 717 2300
2 (i) Geosynthetic
(slopes)
1. Flownet
™
Kaytech 031 717 2300
2. Geonet GN
1250
Aquatan 011 974 5271
(ii)200mm
leachate
collection
layer(Base)
3. 19mm stone Commercial
Sources
4. 110mm
Perforated
HDPE Pipe
Kaytech,
Geotextile
Africa
031 717 2300,
011 965 0205
3 Geotextile A10 Bidim Kaytech 031 717 2300
4
2mm HDPE
Geomembrane
Hi-DRILINE®
Textured
(HDPE)
Aquatan 011 974 5271
Geosynthetic
Clay Liner
X800
(4010g/m2)
Kaytech 031 717 2300
Bento 6 NFP
4000
(3670g/m2)
Geotextile
Africa
011 965 0205
5 (i) Geosynthetic
(slopes)
5. Flownet™ Kaytech 031 717 2300
6. Geonet GN
1250
Aquatan 011 974 5271
(ii)200mm
leachate
collection
layer(Base)
Geotextile A10
Bidim
Kaytech 031 717 2300
19mm stone Commercial
Sources
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
39
110mm
Perforated
HDPE Pipe
Kaytech,
Geotextile
Africa
031 717 2300,
011 965 0205
6 2mm HDPE
Geomembrane
Hi-DRILINE®
Textured
(HDPE)
Aquatan 011 974 5271
CCL 200mm Commercial
Sources
7 Base Preparation 150mm In situ
Material
5.5 Landfill Operations
It is recommended that landfill operations commence in the lower side of the cell and that the
waste is deposited in lifts of no more than 500mm in height and compacted, with the overall
waste body being covered by 150mm compacted cover material on a daily basis in
accordance with the specifications of the permit.
The Landfill slopes above ground level should not exceed 1:4 for stability purposes and for
equipment access.
It is further recommended as follows;
At the end of every working day, a geotextile fabric must be spread on top of the
compacted waste. A time personnel should be appointed for this task.
Monitoring of water quality from all drilled boreholes to be undertaken annually – TE to
appoint a service provider for this service if it does not have capacity
Monitoring of contaminated storm water from the site to be undertaken annually– TE to
appoint a service provider for this service if it does not have capacity
A waste management system including the use of a transfer station and recycling
systems to be implemented.
All the mitigation measures for the operational phase as per EMP report to be
implemented.
A professional landfill operator must be appointed. – TE to appoint a service provider for
this service if it does not have capacity. The operator must work in accordance with the
permit, approved Environmental management plan, the minimum DWA regulations and
the local municipality regulations.
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
40
Surveys should be undertaken annually to check the heights and slopes for compliance
with the permit.
5.6 Final Cover, Closure & Rehabilitation
Final cover is a requirement on all landfills as per Minimum Requirements. Cover is designed
for with the aim of achieving the following:
Separating the waste body from the environment for example wind and water erosion,
burrowing animals etc
Limit and control the amount of precipitation that infiltrate the waste body.
To promote stability of the waste body
Prevent ponding of water on the surface of the landfill and encourage vegetation growth.
When the capacity of the landfill is reached, the waste cells may be covered with a cap or
final cover. The landfill profile should comprise of gentle slopes and for this case a slope of
1:4 is recommended. A final 200mm thick top soil layer as shown below will be capable of
supporting vegetation in order to protect the landfill surface from wind and water erosion. The
topsoil should be grassed as soon as possible after formation to limit erosion.
The cover system consists of 150mm foundation and gas drainage layer, GCL, 200mm
compacted soil and 200mm top soil. The figure below illustrates the typical final cover layer
working in the following manner:
200mm thick top soil layer capable of supporting vegetation in order to protect the landfill
surface from wind and water erosion.
200mm thick layer of compacted soil of low permeability to limit and control the amount of
precipitation that enters the waste.
A Geosynthetic Clay Liner (GCL) to maximise runoff of precipitation while minimising
infiltration and preventing ponding of water on the landfill.
150mm thick foundation and gas drainage layer
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
41
Figure 6: Typical Final Capping Layer
Upon closure, the site can be used for recreational activities such as a soccer field or Public
Park and this can contribute to improved social conditions in the years to come
6.0 CONCLUSION
The report addressed all requirements from Regulation 636 3(1) and 3(2). Approval of design
report by DWA will enable movement to the construction phase.
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
42
ANNEXURES
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
43
ANNEXURE 1 Calculations
Contract No. TE14-KLP09Q-0125: Provision Of Professional Services For The Development Of A New Landfill Site For Transnet Engineering At Koedoespoort Centre
In Pretoria
44
ANNEXURE 2 Drawings