ANNEX “D” CONTRACT IMPLEMENTATION GUIDELINES FOR THE PROCUREMENT OF GOODS, SUPPLIES AND MATERIALS 1. Amendment to Order 2. Suspension of Work 3. Liquidated Damages 4. Advance Payment 5. Other Rules and Guidelines BACK

Transcript of CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the...

Page 1: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ANNEX“D”CONTRACTIMPLEMENTATIONGUIDELINESFORTHEPROCUREMENTOFGOODS,SUPPLIESANDMATERIALS

1.AmendmenttoOrder2.SuspensionofWork3.LiquidatedDamages4.AdvancePayment5.OtherRulesandGuidelines

BACK

Page 2: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ANNEX"E"CONTRACTIMPLEMENTATIONGUIDELINESFORTHEPROCUREMENTOFINFRASTRUCTUREPROJECTS

1.VARIATIONORDERS-CHANGEORDER/EXTRAWORKORDER2.ADDITIONAL/EXTRAWORKCOSTING3.CONDITIONSUNDERWHICHCONTRACTOR4.ADVANCEPAYMENT5.PROGRESSPAYMENT6.RETENTIONMONEY7.CONTRACTCOMPLETION8.LIQUIDATEDDAMAGES9.SUSPENSIONOFWORK10.EXTENSIONOFCONTRACTTIME11.ACCREDITATIONOFTESTINGLABORATORIES12.EVALUATIONOFCONTRACTORSPERFORMANCE13.OTHERRULESANDGUIDELINES

BACK

Page 3: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ANNEXFCONTRACTIMPLEMENTATIONGUIDELINESFORTHEPROCUREMENTOFCONSULTINGSERVICES

1.AdvancePaymentforMobilizationTheGovernment,asitconsidersfairandreasonable,mayallowadvancepaymenttotheConsultantintheamountwhichshallnotexceedfifteenpercent(15%)ofthecontractamounttocoverthecostofmobilization,subjecttothepostingofanirrevocablestandbyletterofcreditissuedbyanentityacceptabletotheagencyandofanamountequaltotheadvancepayment.TheadvancepaymentshallberepaidbytheConsultantbydeductingfromhisprogresspaymentssuchsumasagreeduponduringthecontractnegotiationsuntilfullyliquidatedwithinthedurationofthecontract.

2.CostofConsultingServicesAllConsultancycontractsshallbefixedpricecontracts.Anyextensionofcontracttimeshallnotinvolveanyadditionalcost.

3.OtherRulesandGuidelines

TherulesandregulationsfortheotheraspectsofcontractimplementationshallbeincludedinthemanualstobeissuedbytheGPPB.

BACK

Page 4: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ANNEX“G”GUIDELINESFORTHEPROCUREMENTANDIMPLEMENTATIONOFCONTRACTSFORDESIGNANDBUILDINFRASTRUCTUREPROJECTS

1.SCOPEANDAPPLICATION2.PURPOSE3.GUIDINGPRINCIPLES4.DEFINITIONOFTERMS5.CONDITIONSFORTHEUSEOFTHEDESIGNANDBUILDSCHEME6.CREATIONOFDESIGNandBUILDCOMMITTEE7.PRELIMINARYDESIGNANDCONSTRUCTIONSTUDIES8.DETAILEDENGINEERINGREQUIREMENTS9.ELIGIBILITYREQUIREMENTS10.SUBMISSIONANDRECEIPTOFBIDS11.BIDEVALUATION12.POST-QUALIFICATIONandAWARDOFTHECONTRACT13.CONTRACTIMPLEMENTATION14.AMENDMENTSANDFORMS

BACK

Page 5: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ANNEXHTHRESHOLDSFORSHOPPINGANDSMALLVALUEPROCUREMENT

1.Shopping[Section52.1.(a)].Whenthereisanunforeseencontingencyrequiringimmediatepurchase,theamountshallnotexceedthefollowing:a)ForNGAs,GOCCs,GFIs,andSUCs,OneHundredThousandPesos(P100,000).b)ForLGUs,inaccordancewiththefollowingschedule:DOFClassificationofLGUsMaximumAmount(inPhilippinePeso)ProvinceCityMunicipality1stClass100,000100,00050,0002ndClass100,000100,00050,0003rdClass100,00080,00050,0004thClass80,00060,00050,0005thClass60,00050,00050,0006thClass50,00050,00050,000Inthecaseofbarangays,FiftyThousandPesos(P50,000).

2.Shopping[Section52.1.(b)]andSmallValueProcurement[Section53.9].Procurementshallnotexceedthefollowing:a)ForNGAs,GOCCs,GFIs,andSUCs,FiveHundredThousandPesos(P500,000).b)ForLGUs,inaccordancewiththefollowingschedule:DOFClassificationofLGUsMaximumAmount(inPhilippinePeso)ProvinceCityMunicipality1stClass500,000500,000100,0002ndClass500,000500,000100,0003rdClass500,000400,000100,0004thClass400,000300,00050,0005thClass300,000200,00050,0006thClass200,000100,00050,000Inthecaseofbarangays,FiftyThousandPesos(P50,000).

3.ForForeign-fundedProcurement,thethresholdsshallbedeterminedineachcase,takingintoaccountthenatureofthegoods,works,orassignment,byagreementbetweentheGOPandtheforeigngovernment/foreignorinternationalfinancinginstitution.

BACK

Page 6: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

a)Procurementforgoods,infrastructureprojects,andconsultingservicesfundedfromForeignGrantscoveredbyR.A.8182,asamendedbyR.A.8555,entitled"AnActExcludingOfficialDevelopmentAssistance(ODA)fromtheForeignDebtLimitinordertoFacilitatetheAbsorptionandOptimizetheUtilizationofODAResources,AmendingforthePurposeParagraph1,Section2ofRepublicActNo.4860,AsAmended",unlesstheGOPandtheforeigngrantor/foreignorinternationalfinancinginstitutionagreeotherwise;

BACK

Page 7: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

b)AcquisitionofrealpropertywhichshallbegovernedbyR.A.8974,entitled"AnActtoFacilitatetheAcquisitionofRight-of-WaySiteorLocationforNationalGovernmentInfrastructureProjectsandforOtherPurposes,"andotherapplicablelaws;and

BACK

Page 8: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

c)Public-PrivatesectorinfrastructureordevelopmentprojectsandotherprocurementcoveredbyR.A.6957,asamendedbyR.A.7718,entitled"AnActAuthorizingtheFinancing,Construction,OperationandMaintenanceofInfrastructureProjectsbythePrivateSector,andforOtherPurposes,"asamended:Provided,however,ThatfortheportionsfinancedbytheGOP,regardlessofsourceoffunds,whetherlocalorforeign,theprovisionsofthisIRRshallapply.(1a)

BACK

Page 9: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

a)Act.ReferstoR.A.9184,entitled"AnActProvidingfortheModernization,StandardizationandRegulationoftheProcurementActivitiesoftheGovernmentandforotherPurposes,"otherwiseknownastheGovernmentProcurementReformAct.

Section5.DefinitionofTerms

Page 10: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

b)ApprovedBudgetfortheContract.ReferstothebudgetforthecontractdulyapprovedbytheHeadoftheProcuringEntity,asprovidedforintheGeneralAppropriationsAct(GAA),continuing,andautomaticappropriations,inthecaseofnationalgovernmentagencies(NGAs);thecorporatebudgetforthecontractapprovedbythegoverningboard,pursuanttoExecutiveOrderNo.518,seriesof1979(E.O.518),inthecaseofGOCCsandGFIs,andR.A.8292inthecaseofSUCs;thebudgetapprovedbytheSanggunianinthecaseofLGUs;andtheestimatedcontractcostinthecaseofForeign-fundedProcurement.Forpurposesof,andthroughoutthisIRR,theterms"ABC","ApprovedBudgetfortheContract",and"ApprovedBudget"shallhavethesamemeaningandshallbeusedinterchangeably.ForForeign-fundedProcurement,theestimatedcontractcostfortheprojectreferstothecostestimatepreparedbytheprocuringentityandapprovedbytheforeigngovernment/foreignorinternationalfinancinginstitutionasspecifiedintheTreatyorInternationalorExecutiveAgreement.(a)

Section5.DefinitionofTerms

Page 11: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

c)BAC.ReferstotheBidsandAwardsCommitteeestablishedinaccordancewithRuleVofthisIRR.

Section5.DefinitionofTerms

Page 12: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

d)Bid.ReferstoasignedofferorproposaltoundertakeacontractsubmittedbyabidderinresponsetoandinconsonancewiththerequirementsoftheBiddingDocuments.Forpurposesof,andthroughoutthisIRR,theterm"Bid"shallbeequivalenttoandbeusedinterchangeablywith"Proposal"and"Tender".

Section5.DefinitionofTerms

Page 13: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

e)Bidder.Referstoaneligiblecontractor,manufacturer,supplier,distributorand/orconsultantcompetingfortheawardofacontractinanyprocurementbytheGOP.Acontractor,manufacturer,supplier,distributororconsultantissaidtobeeligibleifitmeetsalltheeligibilityrequirementsissuedbytheprocuringentity.

Section5.DefinitionofTerms

Page 14: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

f)BiddingDocuments.Refertothedocumentsissuedbytheprocuringentityasthebasisforbids,furnishingallinformationnecessaryforaprospectivebiddertoprepareabidfortheinfrastructureprojects,goodsand/orconsultingservicesrequiredbytheprocuringentity.

Section5.DefinitionofTerms

Page 15: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

g)Common-UseSupplies.Refertothosegoods,materialsandequipmentthatareusedintheday-to-dayoperationsofProcuringEntitiesintheperformanceoftheirfunctions.ForthepurposeofthisIRR,common-usesuppliesshallbethoseincludedintheElectronicCatalogueofthePhilGEPS.(a)

Section5.DefinitionofTerms

Page 16: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

h)CompetitiveBidding.Referstoamethodofprocurementwhichisopentoparticipationbyanyinterestedpartyandwhichconsistsofthefollowingprocesses:advertisement,pre-bidconference,eligibilityscreeningofprospectivebidders,receiptandopeningofbids,evaluationofbids,post-qualification,andawardofcontract.Forpurposesof,andthroughoutthisIRR,theterms"CompetitiveBidding"and"PublicBidding"shallhavethesamemeaningandshallbeusedinterchangeably.

Section5.DefinitionofTerms

Page 17: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)ConsultingServices.RefertoservicesforinfrastructureprojectsandothertypesofprojectsoractivitiesoftheGOPrequiringadequateexternaltechnicalandprofessionalexpertisethatarebeyondthecapabilityand/orcapacityoftheGOPtoundertakesuchas,butnotlimitedto:(i)advisoryandreviewservices;(ii)preinvestmentorfeasibilitystudies;(iii)design;(iv)constructionsupervision;(v)managementandrelatedservices;and(vi)othertechnicalservicesorspecialstudies.GeneralprinciplesonconsultingservicesareprovidedforinAnnex"B"ofthisIRR.(a)

Section5.DefinitionofTerms

Page 18: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

j)DomesticBidder.Referstoanypersonorentityofferingunmanufacturedarticles,materialsorsuppliesofthegrowthorproductionofthePhilippines,ormanufacturedarticles,materials,orsuppliesmanufacturedortobemanufacturedinthePhilippinessubstantiallyfromarticles,materials,orsuppliesofthegrowth,production,ormanufacture,asthecasemaybe,ofthePhilippines.(n)

Section5.DefinitionofTerms

Page 19: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

k)DomesticEntity.ReferstoanindividualorasoleproprietorwhoisacitizenofthePhilippinesorapartnership,corporation,cooperative,orassociationdulyorganizedunderthelawsofthePhilippinesandofwhichatleastseventyfivepercent(75%)oftheinterestoroutstandingcapitalstockbelongstocitizensofthePhilippines,habituallyestablishedinbusinessandhabituallyengagedinthemanufactureorsaleofthemerchandisecoveredbyhisbid,andthebusinesshasbeeninexistenceforatleastfive(5)consecutiveyearspriortotheadvertisementand/orpostingoftheInvitationtoBid.(n)

Section5.DefinitionofTerms

Page 20: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

l)ExecutiveAgreements.RefertoInternationalAgreementsexceptthattheydonotrequirelegislativeratification.(n)

Section5.DefinitionofTerms

Page 21: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

m)ExpendableSupplies.Refertoarticleswhicharenormallyconsumedinusewithinone(1)yearorconvertedintheprocessofmanufactureorconstruction,orthosehavingalifeexpectancyofmorethanone(1)yearbutwhichshallhavedecreasedsubstantiallyinvalueafterbeingputtouseforonlyone(1)year(e.g.,medicines,stationery,fuel,andspareparts).(n)

Section5.DefinitionofTerms

Page 22: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

n)ForeignBid.Referstoanyofferofarticles,materialsorsuppliesnotmanufacturedornottobemanufacturedinthePhilippines,substantiallyfromarticles,materials,orsuppliesofthegrowth,production,ormanufacture,asthecasemaybe,ofthePhilippines.(n)

Section5.DefinitionofTerms

Page 23: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

o)Foreign-fundedProcurement.Referstotheacquisitionofgoods,consultingservices,andthecontractingforinfrastructureprojectsbytheGOPwhicharewhollyorpartlyfundedbyForeignLoansorGrantspursuanttoaTreatyorInternationalorExecutiveAgreement.Forpurposesof,andthroughoutthisIRR,theterm"foreignfundedprocurement"shallhavethesamemeaningasandshallbeusedinterchangeablywith"foreign-fundedprojects"or"foreign-assistedprojects".(n)

Section5.DefinitionofTerms

Page 24: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

p)ForeignGrants.Refertograntswithnorepaymentobligationsandareprovidedinmonetaryform,goods,works,andconsultancyservices,amongothers.(n)

Section5.DefinitionofTerms

Page 25: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

q)ForeignLoans.Refertoloans,credits,andindebtednesswithprivateforeignbanksorwithforeigngovernments,agencies,orinstrumentalitiesofsuchforeigngovernments,foreignfinancialinstitutions,orotherinternationalorganizationswithwhom,orbelongingtocountrieswithwhich,thePhilippineshasdiplomaticrelations,asmaybenecessaryanduponsuchtermsandconditionsasmaybeagreedupon,toenabletheGOPtofinance,eitherdirectlyorthroughanygovernmentoffice,agencyorinstrumentalityoranygovernment-ownedandcontrolledcorporation,industrial,agriculturalorothereconomicdevelopmentpurposesorprojectsauthorizedbylaw.(n)

Section5.DefinitionofTerms

Page 26: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

r)Goods.Refertoallitems,supplies,materialsandgeneralsupportservices,exceptconsultingservicesandinfrastructureprojects,whichmaybeneededinthetransactionofpublicbusinessesorinthepursuitofanygovernmentundertaking,projectoractivity,whetherinthenatureofequipment,furniture,stationery,materialsforconstruction,orpersonalpropertyofanykind,includingnon-personalorcontractualservices,suchas,therepairandmaintenanceofequipmentandfurniture,aswellastrucking,hauling,janitorial,security,andrelatedoranalogousservices,aswellasprocurementofmaterialsandsuppliesprovidedbytheprocuringentityforsuchservices.Theterm"related"or"analogousservices"shallinclude,butnotbelimitedto,leaseorpurchaseofofficespace,mediaadvertisements,healthmaintenanceservices,andotherservicesessentialtotheoperationoftheprocuringentity.

Section5.DefinitionofTerms

Page 27: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

s)GPPB.ReferstotheGovernmentProcurementPolicyBoardcreatedinaccordancewithRuleXXofthisIRR.

Section5.DefinitionofTerms

Page 28: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

t)HeadoftheProcuringEntity.Refersto:

theheadoftheagencythegoverningboardthelocalchiefexecutive

Section5.DefinitionofTerms

Page 29: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

u)InfrastructureProjects.Includetheconstruction,improvement,rehabilitation,demolition,repair,restorationormaintenanceofroadsandbridges,railways,airports,seaports,communicationfacilities,civilworkscomponentsofinformationtechnologyprojects,irrigation,floodcontrolanddrainage,watersupply,sanitation,sewerageandsolidwastemanagementsystems,shoreprotection,energy/powerandelectrificationfacilities,nationalbuildings,schoolbuildings,hospitalbuildings,andotherrelatedconstructionprojectsofthegovernment.Forpurposesof,andthroughoutthisIRR,theterm"InfrastructureProjects"shallhavethesamemeaningas,andshallbeusedinterchangeablywith,"civilworks"or"works".

Section5.DefinitionofTerms

Page 30: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

v)InternationalAgreement.Referstoacontractorunderstanding,regardlessofnomenclature,enteredintobetweentheGOPandanothergovernmentorforeignorinternationalfinancinginstitutioninwrittenformandgovernedbyinternationallaw,whetherembodiedinasingleinstrumentorintwo(2)ormorerelatedinstruments.(n)

Section5.DefinitionofTerms

Page 31: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

w)Non-expendableSupplies.Refertoarticleswhicharenotconsumedinuseandordinarilyretaintheiroriginalidentityduringtheperiodofuse,whoseserviceablelifeismorethanone(1)yearandwhichaddtotheassetsoftheGOP(e.g.,furniture,fixtures,transportandotherequipment).(n)

Section5.DefinitionofTerms

Page 32: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

x)PhilGEPS.ReferstothePhilippineGovernmentElectronicProcurementSystemasprovidedinSection8ofthisIRR.Forpurposesof,andthroughoutthisIRR,theterm"PhilGEPS"shallhavethesamemeaningas,andshallbeusedinterchangeablywith,"G-EPS"referredtointheAct.(a)

Section5.DefinitionofTerms

Page 33: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

y)PhilippineNational.ReferstoanindividualorasoleproprietorwhoisacitizenofthePhilippinesorapartnership,corporation,cooperative,orassociationorganizedunderthelawsofthePhilippinesofwhichatleastsixtypercent(60%)ofthecapitalorinterestisownedbycitizensofthePhilippines.(n)

Section5.DefinitionofTerms

Page 34: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

z)Portal.Referstoawebsitethatintegratesawidevarietyofcontentsforthepurposeofattractingandaggregatingmultipleuserstogetherinacentralvirtualspace.

Section5.DefinitionofTerms

Page 35: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

aa)Procurement.Referstotheacquisitionofgoods,consultingservices,andthecontractingforinfrastructureprojectsbytheprocuringentity.Incaseofprojectsinvolvingmixedprocurements,thenatureoftheprocurement,i.e.,goods,infrastructureprojects,orconsultingservices,shallbedeterminedbasedontheprimarypurposeofthecontract.Procurementshallalsoincludetheleaseofgoodsandrealestate.Withrespecttorealproperty,itsprocurementshallbegovernedbytheprovisionsofR.A.8974andotherapplicablelaws,rulesandregulations.

Section5.DefinitionofTerms

Page 36: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

bb)ProcuringEntity.Referstoanybranch,constitutionalcommissionoroffice,agency,department,bureau,office,orinstrumentalityoftheGOP(NGA),includingGOCC,GFI,SUCandLGUprocuringgoods,consultingservicesandinfrastructureprojects.

Section5.DefinitionofTerms

Page 37: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

cc)Treaties.RefertointernationalagreementsenteredintobytheGOPwhichrequirelegislativeratificationafterexecutiveconcurrence.(n)

Section5.DefinitionofTerms

Page 38: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

dd)UniversalorCommercialBanks.RefertouniversalorcommercialbanksdulyauthorizedunderR.A.8791,otherwiseknownas"TheGeneralBankingActof2000".(n)

Section5.DefinitionofTerms

Page 39: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

7.3.1.Atthestartofeverybudgetperiod,theprocuringentityshallprepareitsproposedbudgetforthesucceedingcalendaryear,takingintoconsiderationthebudgetframeworkforthatyearinordertoreflectitsprioritiesandobjectivesforthebudgetperiod.(n)

BACK

Page 40: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

7.3.2.Theend-userunitsoftheprocuringentityshallpreparetheirrespectiveProjectProcurementManagementPlan(PPMP)fortheirdifferentprograms,activities,andprojects(PAPs).ThePPMPshallinclude:a)informationonwhetherPAPswillbecontractedout,implementedbyadministrationinaccordancewiththeguidelinesissuedbytheGPPB,orconsigned;

b)thetypeandobjectiveofcontracttobeemployed;

c)theextent/sizeofcontractscopes/packages;

d)theprocurementmethodstobeadopted,andindicatingiftheprocurementtasksaretobeoutsourcedasprovidedinSection53.6ofthisIRR;

e)thetimescheduleforeachprocurementactivityandforthecontractimplementation;and

f)theestimatedbudgetforthegeneralcomponentsofthecontract.

ForpurposesofthisSection,consignmentreferstoanarrangementwherethefollowingrequisitesarepresent:(a)deliveryofgoodsbytheirowner(consignor),withoutsale,toagovernmentagency(consignee);(b)consigneemusttrytosellthegoodsandremitthepriceofthesoldgoodstotheconsignor;(c)consigneeacceptswithoutanyliabilityexceptforfailuretoreasonablyprotectthemfromdamage;(d)nodisbursementofgovernmentfundsisinvolved;and(e)attermsnotdisadvantageoustotheGOP.(n)

BACK

Page 41: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

7.3.3.ThePPMPshallthenbesubmittedtotheprocuringentity'sBudgetOffice.Theprocuringentity'sBudgetOfficeshallevaluateeachend-user'ssubmittedPPMPand,ifwarranted,includeitintheprocuringentity'sbudgetproposalforapprovalbytheHeadoftheProcuringEntity.(n)

BACK

Page 42: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

7.3.4.AfterthebudgetproposalhasbeenapprovedbytheHeadoftheProcuringEntityand/orotheroversightbodies,theprocuringentity'sbudgetofficeshallfurnishacopyoftheprocuringentity'sbudgetproposalaswellasthecorrespondingPPMPstotheBACSecretariatforitsreviewandconsolidationintotheproposedAPP.TheproposedAPPshallbeconsistentwiththeprocuringentity'sbudgetproposal.(n)

BACK

Page 43: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

7.3.5.AssoonastheGAA,corporatebudget,orappropriationordinance,asthecasemaybe,becomesfinal,theend-userunitsshallreviseandadjustthePPMPtoreflectthebudgetaryallocationfortheirrespectivePAPs.TherevisedPPMPsshallbesubmittedtotheBAC,throughitsSecretariat,forthefinalizationofthemodesofprocurementundertheproposedAPP.TheAPPshallthenbeapprovedinaccordancewithSection7.2ofthisIRR.(n)

BACK

Page 44: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.1.1.Topromotetransparencyandefficiency,informationandcommunicationstechnologyshallbeutilizedintheconductofprocurementprocedures.Accordingly,thereshallbeasingleportalthatshallserveastheprimarysourceofinformationonallgovernmentprocurement.ThePhilGEPSshallserveastheprimaryanddefinitivesourceofinformationongovernmentprocurement.Forthispurpose,theElectronicProcurementSystem(EPS)establishedinaccordancewithExecutiveOrderNo.322,seriesof2000,andExecutiveOrderNo.40,seriesof2001(E.O.40),shallcontinuetobemanagedbythePS-DBMunderthesupervisionoftheGPPB,asthePhilGEPS,inaccordancewiththisIRR.

8.1.ThePhilGEPS

Page 45: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.1.2.Totakeadvantageofthesignificantbuilt-inefficienciesofthePhilGEPSandthevolumediscountsinherentinbulkpurchasing,allProcuringEntitiesshallutilizethePhilGEPSfortheprocurementofCommon-UseSuppliesinaccordancewiththerulesandprocedurestobeestablishedbytheGPPB.Withregardtotheprocurementofnon-commonuseitems,infrastructureprojects,andconsultingservices,agenciesmayhireserviceprovidersthroughcompetitivebiddingtoundertaketheirelectronicprocurement:Provided,however,Thattheseserviceprovidersmeetthefollowingminimumrequirements:a)Complywiththeprovisionsb)LinkedtothePhilGEPSc)Allowparallelmanualsubmissiond)EnsurethattheBACe)Itssystemmustbevirus-resilientf)Mustprovidefortheuseofelectronicsignaturesg)Musthavesufficientredundanth)Musthaveprovisionsforlinkagei)Electronicpaymentfacilities

8.1.ThePhilGEPS

Page 46: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.1.3.TheGPPBshalldetermineandcertifycompliancewiththeaboverequirements.However,theGPPBmaydelegatethistasktotechnicallycapableagencies/offices/unitsoftheGovernment.

8.1.ThePhilGEPS

Page 47: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.2.1.TheElectronicBulletinBoard

a)ThePhilGEPSshallhaveacentralizedelectronicbulletinboardforpostingprocurementopportunities,notices,awardsandreasonsforaward.AllProcuringEntitiesarerequiredtopostallprocurementopportunities,resultsofbiddingandrelatedinformationinthePhilGEPSbulletinboard.

b)ProcuringEntitiesshallposttheInvitationtoBidforgoodsandinfrastructureprojectsortheRequestforExpressionofInterestforconsultingservices,intheelectronicbulletinboardinaccordancewithSection21ofthisIRR.

8.2.FeaturesofthePhilGEPS

Page 48: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.2.2.RegistryofManufacturers,Suppliers,Distributors,ContractorsandConsultants

a)ThePhilGEPSshallhaveacentralizedelectronicdatabaseb)Registrationshallentailthesubmissionoftherequirementsc)Manufacturers,suppliers,distributors,contractorsandconsultantsd)ThePhilGEPSshalldenyregistratione)Amanufacturer,supplier,distributor,contractororconsultantapplyingforregistrationf)Registeredmanufacturers,suppliers,distributors,contractorsandconsultantsg)RegistrationwiththePhilGEPS

8.2.FeaturesofthePhilGEPS

Page 49: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.2.3.TheElectronicCatalogue

a)ThePhilGEPSshallhaveacentralizedelectroniccatalogueb)ProcuringEntitiesshallprocurecommon-usegoodsc)ProcuringEntitieswithoutinternetaccessd)TheElectronicCatalogue

8.2.FeaturesofthePhilGEPS

Page 50: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.2.4.AdditionalFeaturesThePhilGEPSshallalsofeatureaVirtualStore,ElectronicPayment,ElectronicBidSubmission,andsuchotherfeaturesasmaybedevelopedinthefuture.

8.2.4.1.VirtualStore8.2.4.2.ElectronicPayment8.2.4.3.ElectronicBidSubmission

8.2.FeaturesofthePhilGEPS

Page 51: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.3.1.AllProcuringEntitiesaremandatedtofullyusethePhilGEPSinaccordancewiththepolicies,rules,regulations,andproceduresadoptedbytheGPPBandembodiedinthisIRR.Inthisconnection,allProcuringEntitiesshallregisterwiththePhilGEPSandshallundertakemeasurestoensuretheiraccesstoanon-linenetworktofacilitatetheopen,speedyandefficienton-linetransmission,conveyanceanduseofelectronicdatamessagesorelectronicdocuments.ThePS-DBMshallassistProcuringEntitiestoensuretheiron-lineconnectivityandhelpintrainingtheirpersonnelresponsiblefortheoperationofthePhilGEPSfromtheirterminals.

8.3.UseofthePhilGEPS

Page 52: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.3.2.TherulesandregulationsgoverningthemanualmethodofprocurementshallapplywhenevertherulesinthisSectionaresilent.Further,theGPPBisauthorizedtoapprovechangesintheprocurementprocesstoadapttoimprovementsinmoderntechnology,providedthatsuchmodificationsareconsistentwiththeprovisionsofSection3oftheActandthisIRR.

8.3.UseofthePhilGEPS

Page 53: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.4.1.Pre-bidconferencesshallbeconductedinaccordancewithSection22ofthisIRR:Provided,however,Thattherequirementforface-to-facebiddingconferencemaybereplacedoncevideoconferencing,webcasting,orsimilartechnologybecomesthenorminbusinesstransactionsinthecountry.ProcuringEntitieswithvideoconferencingcapabilitiesthathavemanufacturers,suppliers,distributors,contractorsand/orconsultantsthatalsohavevideoconferencingcapabilitiesmayconducttheirpre-biddingconferenceselectronically.

8.4.Pre-bidConferencesandNoticesunderthePhilGEPS

Page 54: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.4.2.RequestsforclarificationfrombiddersmaybesentelectronicallytotheBAC.Tobebindingonbidders,clarificationsandamendmentstotheInvitationtoBid/RequestforExpressionofInterestandtotheBiddingDocumentsshallbeintheformofSupplemental/BidBulletinswhichshallbepostedinthePhilGEPSbulletinboard.

8.4.Pre-bidConferencesandNoticesunderthePhilGEPS

Page 55: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.4.3.TheSupplemental/BidBulletinsmentionedintheimmediatelyprecedingSubsectionaswellasallothernoticestobemadebytheBACtothebiddersorprospectivebiddersshallbepostedinthePhilGEPSbulletinboardandsentelectronicallytothee-mailaddressindicatedinthebidders'registration.

8.4.Pre-bidConferencesandNoticesunderthePhilGEPS

Page 56: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.5.1.ToensurethewidestdisseminationoftheInvitationtoBid/RequestforExpressionofInterest,manufacturers,suppliers,distributors,contractorsand/orconsultantsshallregisterwiththePhilGEPS.AllProcuringEntitiesalreadymaintaininganelectronicregistryupontheeffectivityofthisIRRshallintegratethesamewiththatofthePhilGEPS.Amanufacturer,supplier,distributor,contractororconsultantdulyregisteredwiththePhilGEPSmayparticipateinaprocurementundertakenbyanyprocuringentity,providedthatthesaidmanufacturer,supplier,distributor,contractororconsultantmaintainsitsregistrationcurrentandupdatedinaccordancewiththeprovisionsofthisIRR,anditsregistrationisproperandrelevanttotheparticulartypeofprocurement.(a),(23a)

8.5.Registration,EligibilityRequirementsandSubmissionofBidsunderthePhilGEPS

Page 57: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.5.2.EligibilityrequirementsmaybesentelectronicallytoaprocuringentitythroughthePhilGEPS:Provided,however,ThattheprospectivebidderconcernedshallsubmitacertificationtotheBACatleastseven(7)calendardaysbeforethedeadlineforthesubmissionandopeningofthetechnicalandfinancialenvelopesthatthedocumentssubmittedareauthenticcopiesoftheoriginal,complete,andallstatementsandinformationprovidedthereinaretrueandcorrect:Provided,further,ThatthePhilGEPSshallallowmanualsubmissionofeligibilityrequirements.ThePhilGEPSshallgenerateandsendanacknowledgementofanyeligibilityrequirementreceivedbyit.(a)

8.5.Registration,EligibilityRequirementsandSubmissionofBidsunderthePhilGEPS

Page 58: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.5.3.RegisteredbiddersdeterminedtobeeligiblemaysubmittheirbidsatanytimebeforetheclosingdatespecifiedintheBiddingDocuments.ThePhilGEPSshallbarallincomingbidsaftersuchdate.

8.5.Registration,EligibilityRequirementsandSubmissionofBidsunderthePhilGEPS

Page 59: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.5.4.ThePhilGEPSshallhaveafeaturethatallowstheelectronicsubmissionofeligibilityrequirementsandbids.

8.5.Registration,EligibilityRequirementsandSubmissionofBidsunderthePhilGEPS

Page 60: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.5.5.Uponreceiptofabid,thePhilGEPSshallgenerateandsendamessagetothebidderacknowledgingsuchreceipt.

8.5.Registration,EligibilityRequirementsandSubmissionofBidsunderthePhilGEPS

Page 61: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.6.1.TheBACshallhavethesoleauthoritytoopenthebids.

8.6.OpeningofBidsunderthePhilGEPS

Page 62: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.6.2.Onlythefinancialproposalsofbidderswhosetechnicalproposalsmeettheminimumtechnicalrequirementsshallbeopenedordecrypted.

8.6.OpeningofBidsunderthePhilGEPS

Page 63: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.6.3.Anupdateofallprocurementcontracts,regardlessofwhetherprocurementisdoneelectronicallyormanually,shallbepostedonthePhilGEPSbulletinboard.Theupdateshallinclude,butshallnotbelimitedto,thestatusofprocurementcontracts,includingthenamesofcontractawardeesandtheamountofthecontract.

8.6.OpeningofBidsunderthePhilGEPS

Page 64: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.6.4.WithoutprejudicetocriminalprosecutionundertheapplicableprovisionsoftheActandthisIRR,R.A.8792,R.A.3019,otherwiseknownasthe"Anti-GraftandCorruptPracticesAct,"andotherapplicablepenallaws,publicofficialsandemployeeswhocommitanyofthefollowingactsshallbedeemedtohavecommittedgravemisconductandshallbesanctionedand/orpenalizedinaccordancewiththeapplicableCivilServicerulesandregulations:a)Openingordecryption,bywhatevermeans,ofbidssubmittedthroughthePhilGEPSaheadoftheappointedtimefortheopeningordecryptionofsuchbids;b)CausingtheunauthorizeddisclosureofanyinformationordocumentsubmittedthroughthePhilGEPS;c)HackingintoorcrackingthePhilGEPS,oraidinganotherpersontohackintoorcrackthesame;ord)Anyotheractthatbreachesorviolatesthesecurity,integrity,andconfidentialityofthePhilGEPS.

8.6.OpeningofBidsunderthePhilGEPS

Page 65: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.6.5.Whenanyoftheforegoingactsisdonebytheadministrator(s)oremployee(s)ofaserviceproviderhiredbyaprocuringentity,orincollusionwith,orbyaprivatepartywhoisaparticipantinthebiddingprocess,saidadministrator(s),employee(s)orprivatepartyshallbeimposedthecorrespondingsanctionsand/orpenaltiesunderthisIRR.

8.6.OpeningofBidsunderthePhilGEPS

Page 66: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

a)Security-ThePhilGEPSshallbeprotectedfromunauthorizedaccessorinterferencethroughtheincorporationofsecurityfeaturessuchas,butnotlimitedto,firewalls.Periodictestsshallbeconductedtoensurethatthesystemcannotbebreached.

Section9.Security,IntegrityandConfidentiality

Page 67: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

b)Integrity-ThePhilGEPSshallensurethatnoperson,includingthesystemadministratorsandchairpersonandmembersoftheBAC,shallbeabletoalterthecontentsofbidssubmittedthroughthesystemorreadthesameaheadofthestipulatedtimeforthedecryptionoropeningofbids.Forthispurpose,bidssubmittedthroughthePhilGEPSshallbesealedthroughelectronickeys.TheauthenticityofmessagesanddocumentssubmittedthroughthePhilGEPSshallalsobeensuredbytheuseofelectronicsignatures.

Section9.Security,IntegrityandConfidentiality

Page 68: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

c)Confidentiality-ThePhilGEPSshallensuretheprivacyofpartiestransactingwithit.Forthispurpose,noelectronicmessageordocumentsentthroughthesystemshallbedivulgedtothirdpartiesunlesssuchelectronicmessageordocumentwassentafterthesenderwasinformedthatthesamewillbemadepubliclyavailable.ThePhilGEPSshallprotecttheintellectualpropertyrightsoverdocuments,includingtechnicaldesigns,submittedinresponsetoInvitationstoBid.

Section9.Security,IntegrityandConfidentiality

Page 69: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

d)AuditTrail-ThePhilGEPSshallincludeafeaturethatprovidesforanaudittrailforonlinetransactions,andallowstheCommissiononAudit(COA)toverifythesecurityandintegrityofthesystematanytime.

Section9.Security,IntegrityandConfidentiality

Page 70: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

e)PerformanceTracking-Theperformanceofmanufacturers,suppliers,distributors,contractorsandconsultantsshallbetrackedtomonitorcompliancewithdeliveryschedulesandotherperformanceindicators.Similarly,theperformanceofProcuringEntitiesshallbetrackedtomonitorthesettlementoftheirobligationstomanufacturers,suppliers,distributors,contractorsandconsultants.

Section9.Security,IntegrityandConfidentiality

Page 71: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

11.1.1.EachprocuringentityshallestablishinitsheadofficeasingleBACtoundertakethefunctionsspecifiedinSection12ofthisIRRinordertofacilitateprofessionalizationandharmonizationofproceduresandstandards.Inlinewiththestandardizationofprocurementproceduresandthethrusttowardsstrengtheningtheprocurementfunctiontoincreaseoperationalefficiencyandeffectiveness,HeadsofProcuringEntitiesshallaimtoconsolidateorunifyallprocurementactivitiesoftheorganization,whetherlocally-fundedorforeign-assisted,andwhetherpertainingtogoods,infrastructureprojects,orconsultingservices.(a)

11.1.BACStructure

Page 72: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

11.1.2.However,toexpeditetheprocurementprocessforpracticalintentsandpurposes,theHeadoftheProcuringEntitymaycreateseparateBACswherethenumberandcomplexityoftheitemstobeprocuredshallsowarrant.TheBACsmaybeorganizedeitheraccordingto:(a)geographicallocationofPMOorend-userunitsoftheprocuringentity;or(b)natureofprocurement.SimilarcommitteesfordecentralizedandlowerlevelofficesmayalsobeformedwhendeemednecessarybytheHeadoftheProcuringEntity.(a)

11.1.BACStructure

Page 73: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

11.2.1.TheHeadoftheProcuringEntityshalldesignateatleastfive(5)butnotmorethanseven(7)memberstotheBACofunquestionableintegrityandprocurementproficiency.(a)

11.2.BACComposition

Page 74: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

11.2.2.TheBACforNGAs,departments,bureaus,offices,orinstrumentalitiesoftheGOP,includingthejudicialandlegislativebranches,constitutionalcommissions,SUCs,GOCCs,andGFIsshallbecomposedofthefollowing:RegularMembers:a)Chairman,whoisatleastathirdrankingpermanentofficialoftheprocuringentity;

b)Anofficer,whoisatleastafifthrankingpermanentofficial,withknowledge,experienceand/orexpertiseinprocurementwho,totheextentpossible,representsthelegaloradministrativeareaoftheprocuringentity,providedthatinthecaseofbureaus,regionalofficesandsubregional/districtoffices,BACmembersshallbeatleastathirdrankingpermanentpersonnel;

c)Anofficer,whoisatleastafifthrankingpermanentofficial,withknowledge,experienceand/orexpertiseinprocurementwho,totheextentpossible,representsthefinanceareaoftheprocuringentity,providedthatinthecaseofbureaus,regionalofficesandsub-regional/districtoffices,BACmembersshallbeatleastathirdrankingpermanentpersonnel;ProvisionalMembers:

d)Anofficerwhohastechnicalexpertiserelevanttotheprocurementathand,and,totheextentpossible,hasknowledge,experienceand/orexpertiseinprocurement;and

e)Arepresentativefromtheenduserunitwhohasknowledgeofprocurementlawsandprocedures.TheChairmanandtheVice-ChairmanshallalsobedesignatedbytheHeadoftheprocuringentity.Moreover,theVice-ChairmanshallbearegularmemberoftheBAC.ForpurposesofthisIRR,theterm"permanent"shallrefertoaplantillapositionwithintheprocuringentityconcerned.(a)

11.2.BACComposition

Page 75: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

11.2.3.TheBACforLocalGovernmentUnitsshallbecomposedofthefollowing:a)OnerepresentativeeachfromtheregularofficesundertheOfficeoftheLocalChiefExecutivesuchas,butnotlimitedto,thefollowing:OfficeoftheAdministrator,BudgetOffice,LegalOffice,EngineeringOffice,GeneralServicesOffices;and

b)Arepresentativefromtheenduserunit.ThemembersshallelectamongthemselveswhoshallactastheChairmanandVice-Chairman.TheChairmanoftheBACshallbeatleastathirdrankingpermanentofficialoftheprocuringentity.ThemembersoftheBACshallbepersonneloccupyingplantillapositionsoftheprocuringentityconcerned.(a)

11.2.BACComposition

Page 76: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

11.2.4.TheHeadoftheProcuringEntitymaydesignatealternatememberstotheBAC,whoshallhavethesamequalificationsastheirprincipalsassetintheActandthisIRR.ThealternatemembersshallattendmeetingsoftheBACandreceivethecorrespondinghonoraria,whenevertheirprincipalsareabsent.Thealternatemembersshallhavethesametermastheirprincipals.Theaccountabilityoftheprincipalandthealternatemembershallbelimitedtotheirrespectiveactsanddecisions.(n)

11.2.BACComposition

Page 77: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

11.2.5.InnocaseshalltheHeadoftheProcuringEntityand/ortheapprovingauthoritybetheChairmanoramemberoftheBAC.

11.2.BACComposition

Page 78: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

11.2.6.Unlesssoonerremovedforacause,themembersoftheBACshallhaveafixedtermofone(1)yearreckonedfromthedateofappointment,renewableatthediscretionoftheHeadoftheProcuringEntity.Uponexpirationofthetermsofthecurrentmembers,theyshallcontinuetoexercisetheirfunctionsuntilnewBACmembersaredesignated.Incaseofresignation,retirement,separation,transfer,re-assignment,removal,ordeath,thereplacementshallserveonlyfortheunexpiredterm:Provided,however,Thatincaseofleaveorsuspension,thereplacementshallserveonlyforthedurationoftheleaveorsuspension.Forjustifiablecauses,amembershallbesuspendedorremovedbytheHeadoftheProcuringEntity.(a)

11.2.BACComposition

Page 79: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)Forinfrastructureprojects,nationalassociationsofconstructorsdulyrecognizedbytheConstructionIndustryAuthorityofthePhilippines(CIAP),suchas,butnotlimitedtothefollowing:(1)PhilippineConstructorsAssociation,Inc.;(2)NationalConstructorsAssociationofthePhilippines,Inc.;and(3)PhilippineInstituteofCivilEngineers(PICE).

13.1.Toenhancethetransparencyoftheprocess

Page 80: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ii)Forgoods,aspecificrelevantchamber-memberofthePhilippineChamberofCommerceandIndustry.

13.1.Toenhancethetransparencyoftheprocess

Page 81: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iii)Forconsultingservices,aproject-relatedprofessionalorganizationaccreditedordulyrecognizedbytheProfessionalRegulationCommissionortheSupremeCourt,suchas,butnotlimitedto:(1)PICE;(2)PhilippineInstituteofCertifiedPublicAccountants(PICPA);and(3)ConfederationofFilipinoConsultingOrganizations;and

13.1.Toenhancethetransparencyoftheprocess

Page 82: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)availabilityofappropriationsandprogrammedbudgetforcontract;

20.1.Priortotheadvertisement

Page 83: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ii)completenessoftheBiddingDocumentsandtheiradherencetorelevantgeneralprocurementguidelines;

20.1.Priortotheadvertisement

Page 84: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iii)completionofthedetailedengineeringaccordingtotheprescribedstandardsinthecaseofinfrastructureprojects;and

20.1.Priortotheadvertisement

Page 85: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iv)confirmationoftheavailabilityofROWandtheownershipofaffectedproperties.

20.1.Priortotheadvertisement

Page 86: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)Goods,thenameofthecontracttobebidandabriefdescriptionofthegoodstobeprocured;

21.1.ContentsoftheInvitationtoBid/Request

Page 87: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ii)Infrastructureprojects,thenameandlocationofthecontracttobebid,theprojectbackgroundandotherrelevantinformationregardingtheproposedcontractworks,includingabriefdescriptionofthetype,size,majoritems,andotherimportantorrelevantfeaturesoftheworks;and

21.1.ContentsoftheInvitationtoBid/Request

Page 88: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iii)Consultingservices,thenameofthecontracttobebid,ageneraldescriptionoftheprojectandotherimportantorrelevantinformation;

21.1.ContentsoftheInvitationtoBid/Request

Page 89: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

21.2.1.ExceptasotherwiseprovidedinSections21.2.2and54.2ofthisIRRandfortheprocurementofcommon-usegoodsandsupplies,theInvitationtoBid/RequestforExpressionofInterestshallbe:a)Advertisedatleastonceinone(1)newspaperofgeneralnationwidecirculationwhichhasbeenregularlypublishedforatleasttwo(2)yearsbeforethedateofissueoftheadvertisement;b)PostedcontinuouslyinthePhilGEPSwebsite,thewebsiteoftheprocuringentityconcerned,ifavailable,andthewebsiteprescribedbytheforeigngovernment/foreignorinternationalfinancinginstitution,ifapplicable,forseven(7)calendardaysstartingondateofadvertisement;andc)Postedatanyconspicuousplacereservedforthispurposeinthepremisesoftheprocuringentityconcernedforseven(7)calendardays,ifapplicable,ascertifiedbytheheadoftheBACSecretariatoftheprocuringentityconcerned.(a)

21.2.AdvertisingandPostingoftheInvitation

Page 90: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

21.2.2.AdvertisementoftheInvitationtoBid/RequestforExpressionofInterestinanewspaperofgeneralnationwidecirculationprovidedinSection21.2.1(a)shallnotberequiredforcontractstobebidwithanapprovedbudgetofTwoMillionPesos(P2,000,000.00)andbelowfortheprocurementofgoods,FiveMillionPesos(P5,000,000.00)andbelowfortheprocurementofinfrastructureprojects,andOneMillionPesos(P1,000,000.00)andbeloworthosewhosedurationisfour(4)monthsorlessfortheprocurementofconsultingservices.(a)

21.2.AdvertisingandPostingoftheInvitation

Page 91: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

22.5.1.Requestsforclarification(s)onanypartoftheBiddingDocumentsorforaninterpretationmustbeinwritingandsubmittedtotheBACoftheprocuringentityconcernedatleastten(10)calendardaysbeforethedeadlinesetforthesubmissionandreceiptofbids.TheBACshallrespondtothesaidrequestbyissuingaSupplemental/BidBulletin,dulysignedbytheBACchairman,tobemadeavailabletoallthosewhohaveproperlysecuredtheBiddingDocuments,atleastseven(7)calendardaysbeforethedeadlineforthesubmissionandreceiptofbids.(a)

22.5.Supplemental/BidBulletins

Page 92: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

22.5.2.Supplemental/BidBulletinsmaybeissuedupontheprocuringentity'sinitiativeforpurposesofclarifyingormodifyinganyprovisionoftheBiddingDocumentsatleastseven(7)calendardaysbeforethedeadlineforthesubmissionandreceiptofbids.AnymodificationtotheBiddingDocumentsshallbeidentifiedasanamendment.(a)

22.5.Supplemental/BidBulletins

Page 93: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

22.5.3.AnySupplemental/BidBulletinissuedbytheBACshallalsobepostedonthePhilGEPSorthewebsiteoftheprocuringentityconcerned,ifavailable.ItshallbetheresponsibilityofallthosewhohaveproperlysecuredtheBiddingDocumentstoinquireandsecureSupplemental/BidBulletinsthatmaybeissuedbytheBAC.However,bidderswhohavesubmittedbidsbeforetheissuanceoftheSupplemental/BidBulletinmustbeinformedandallowedtomodifyorwithdrawtheirbidsinaccordancewithSection26.1ofthisIRR.(a)

22.5.Supplemental/BidBulletins

Page 94: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)RegistrationcertificatefromSEC,DepartmentofTradeandIndustry(DTI)forsoleproprietorship,orCDAforcooperatives,oranyproofofsuchregistrationasstatedintheBiddingDocuments.

23.1.Forpurposesofdeterminingtheeligibility

Page 95: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ii)Mayor'spermitissuedbythecityormunicipalitywheretheprincipalplaceofbusinessoftheprospectivebidderislocated.TechnicalDocuments

23.1.Forpurposesofdeterminingtheeligibility

Page 96: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iii)Statementoftheprospectivebidderofallitsongoingandcompletedgovernmentandprivatecontracts,includingcontractsawardedbutnotyetstarted,ifany,whethersimilarornotsimilarinnatureandcomplexitytothecontracttobebid,withintherelevantperiodasprovidedintheBiddingDocuments.ThestatementshallincludeallinformationrequiredinthePBDsprescribedbytheGPPB.

23.1.Forpurposesofdeterminingtheeligibility

Page 97: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iv)Inthecaseofprocurementofinfrastructureprojects,avalidPhilippineContractorsAccreditationBoard(PCAB)licenseandregistrationforthetypeandcostofthecontracttobebid.FinancialDocuments

23.1.Forpurposesofdeterminingtheeligibility

Page 98: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

v)Theprospectivebidder sauditedfinancialstatements,showing,amongothers,theprospectivebidder stotalandcurrentassetsandliabilities,stampedreceivedbytheBIRoritsdulyaccreditedandauthorizedinstitutions,fortheprecedingcalendaryearwhichshouldnotbeearlierthantwo(2)yearsfromthedateofbidsubmission.

23.1.Forpurposesofdeterminingtheeligibility

Page 99: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

vi)Theprospectivebidder scomputationforitsNetFinancialContractingCapacity(NFCC)oracommitmentfromaUniversalorCommercialBanktoextendacreditlineinfavoroftheprospectivebidderifawardedthecontracttobebid(CLC).

23.1.Forpurposesofdeterminingtheeligibility

Page 100: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.4.1.TheregistrysystemshallcontaintheforegoingClassAdocumentswhichshouldbemaintainedcurrentandupdatedbythebidderconcernedatleastonceayearormorefrequentlywhenneeded.(a)

23.4.Tofacilitatedeterminationofeligibility

Page 101: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.4.2.AbidderwhomaintainsacurrentandupdatedfileofhisClassADocumentsshallbeissuedacertificationbytheBACtothateffect,whichcertificationmaybesubmittedtotheprocuringentityconcernedinlieuoftheforegoingClassAdocuments.(a)

23.4.Tofacilitatedeterminationofeligibility

Page 102: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.4.3.IftheprocuringentitymaintainsaregistrysystemusingthePhilGEPSoritsownelectronicsystem,aprospectivebidder,whetherornotdulyregisteredineithersystem,shallsubmitawrittenletterofintentand/oritsapplicationforeligibilityandlatestClassAdocuments,totheBAConorbeforethedeadlinespecifiedintheBiddingDocuments.Anyapplicationforeligibilityorupdatessubmittedafterthedeadlineforthesubmissionoftheletterofintentshallnotbeconsideredforthebiddingathand.(a)

23.4.Tofacilitatedeterminationofeligibility

Page 103: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.5.1.Fortheprocurementofgoods:

23.5.1.1.Thefollowingshallbeeligible23.5.1.2.Foreignbiddersmaybeeligible23.5.1.3.Theprospectivebidder23.5.1.4.Iftheprospectivebiddersubmitsacomputation

23.5.EligibilityCriteria

Page 104: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.5.2.Fortheprocurementofinfrastructureprojects:

23.5.2.1.Thefollowingpersons/entities23.5.2.2.Foreignbidders23.5.2.3.InaccordancewithR.A.456623.5.2.4.TheConstructorsPerformanceEvaluationSummary(CPES)23.5.2.5.Theprospectivebidder23.5.2.6.Iftheprospectivebiddersubmitsacomputation

23.5.EligibilityCriteria

Page 105: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)RegistrationcertificatefromSEC,DepartmentofTradeandIndustry(DTI)forsoleproprietorship,orCDAforcooperatives,oranyproofofsuchregistrationasstatedintheBiddingDocuments;

24.1.Thefollowingdocumentsshallbesubmitted

Page 106: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ii)Mayor spermitissuedbythecityormunicipalitywheretheprincipalplaceofbusinessoftheprospectivebidderislocated;TechnicalDocuments

24.1.Thefollowingdocumentsshallbesubmitted

Page 107: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iii)Statementoftheprospectivebidderofallitsongoingandcompletedgovernmentandprivatecontracts,includingcontractsawardedbutnotyetstarted,ifany,whethersimilarornotsimilarinnatureandcomplexitytothecontracttobebid,withintherelevantperiodasprovidedintheBiddingDocuments.ThestatementshallincludeallinformationrequiredinthePBDsprescribedbytheGPPB.

24.1.Thefollowingdocumentsshallbesubmitted

Page 108: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iv)Statementoftheconsultantspecifyingitsnationalityandconfirmingthatthosewhowillactuallyperformtheserviceareregisteredprofessionalsauthorizedbytheappropriateregulatorybodytopracticethoseprofessionsandalliedprofessions.FinancialDocument

24.1.Thefollowingdocumentsshallbesubmitted

Page 109: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

v)Theconsultantsauditedfinancialstatements,showing,amongothers,theconsultantstotalandcurrentassetsandliabilities,stampedreceivedbytheBIRoritsdulyaccreditedandauthorizedinstitutions,fortheprecedingcalendaryearwhichshouldnotbeearlierthantwo(2)yearsfromthedateofbidsubmission.

24.1.Thefollowingdocumentsshallbesubmitted

Page 110: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

24.3.1.Thefollowingpersons/entitiesshallbeallowedtoparticipateinthebiddingforconsultingservices:a)DulylicensedFilipinocitizens/soleproprietorships;

b)PartnershipsdulyorganizedunderthelawsofthePhilippinesandofwhichatleastsixtypercent(60%)oftheinterestbelongstocitizensofthePhilippines;

c)CorporationsdulyorganizedunderthelawsofthePhilippinesandofwhichatleastsixtypercent(60%)oftheoutstandingcapitalstockbelongstocitizensofthePhilippines;

d)CooperativesdulyorganizedunderthelawsofthePhilippines,andofwhichatleastsixtypercent(60%)belongstocitizensofthePhilippines;or

e)Persons/entitiesformingthemselvesintoajointventure,i.e.,agroupoftwo(2)ormorepersons/entitiesthatintendtobejointlyandseverallyresponsibleorliableforaparticularcontract:Provided,however,ThatFilipinoownershiporinterestthereofshallbeatleastsixtypercent(60%).Forthispurpose,FilipinoownershiporinterestshallbebasedonthecontributionsofeachofthemembersofthejointventureasspecifiedintheirJVA.(n)

24.3.EligibilityCriteria

Page 111: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

24.3.2.Whenthetypesandfieldsofconsultingservicesinwhichtheforegoingpersons/entitieswishtoengageinvolvethepracticeofprofessionsregulatedbylaw,thosewhowillactuallyperformtheservicesshallbeFilipinocitizensandregisteredprofessionalsauthorizedbytheappropriateregulatorybodytopracticethoseprofessionsandalliedprofessions.(a)

24.3.EligibilityCriteria

Page 112: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

24.3.3.InordertomanifesttrustandconfidenceinandpromotethedevelopmentofFilipinoconsultancy,foreignconsultantsmaybehiredintheeventFilipinoconsultantsdonothavethesufficientexpertiseandcapabilitytorendertheservicesrequiredundertheproject,asdeterminedbytheHeadoftheProcuringEntity.Foreignconsultantsmaybeeligibletoparticipateintheprocurementofconsultingservices,subjecttothefollowingqualifications:a)mustberegisteredwiththeSECand/oranyagencyauthorizedbythelawsofthePhilippines;and

b)whenthetypesandfieldsofconsultingservicesinwhichtheforeignconsultantwishestoengageinvolvethepracticeofregulatedprofessions,theforeignconsultantmustbeauthorizedbytheappropriateGOPprofessionalregulatorybodytoengageinthepracticeofthoseprofessionsandalliedprofessions:Provided,however,Thatthelimitsofsuchauthorityshallbestrictlyobserved.(a)

24.3.EligibilityCriteria

Page 113: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

24.4.1.TheeligibilityenvelopesofprospectivebiddersforprocurementofconsultingservicesshallbesubmittedonorbeforethedeadlinespecifiedintheRequestforExpressionofInterest,andshallbeopenedbeforethedatesofthepre-bidconferenceandbidopeningtodetermineeligibilityofprospectivebidders,whoshallthenbeallowedtoacquireorpurchasetherelevantBiddingDocumentsfromtheprocuringentity.AprospectivebiddermaybeallowedtosubmithiseligibilityrequirementselectronicallyinaccordancewithSection8.5ofthisIRR.(a)

24.4.EligibilityCheckofProspectiveBidders

Page 114: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

24.4.2.SubjecttotheshortlistingofconsultantsasprovidedinthisIRR,thedeterminationofeligibilityofconsultantsshallbebasedontheevaluationoftheeligibilitydocumentsprescribedaboveinaccordancewiththeproceduresprovidedinSections30.1and30.3ofthisIRR.

24.4.EligibilityCheckofProspectiveBidders

Page 115: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

24.4.3.Tofacilitatedeterminationofeligibility,theBACofaprocuringentitymaymaintainaregistrysystemusingthePhilGEPSoritsownmanualorelectronicsystemthatallowssubmissionand/orrecording/entryofeligibilityrequirementssimultaneouslywithregistration.(a)24.4.3.1.Theregistrysystem24.4.3.2.Abidderwhomaintainsacurrentandupdatedfile24.4.3.3.Iftheprocuringentitymaintainsaregistrysystem

24.4.EligibilityCheckofProspectiveBidders

Page 116: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

24.5.1.Withrespecttoaparticularcontractforconsultingservicestobebid,theconcernedprocuringentityshallonlyconsiderforshortlistingthoseconsultantswhosecontracts,asidentifiedintheeligibilitydocumentssubmittedforregistration,aresimilarinnatureandcomplexitytothecontracttobebid,basedontheRequestforExpressionofInterest.

24.5.ShortListingofProspectiveBidders

Page 117: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

24.5.2.TheBACshalldrawuptheshortlistofconsultantsfromthosewhohavebeendeterminedaseligible,andwhohavesubmittedtheirLOI,bothinaccordancewiththeprovisionsofthisIRR.Thenumberofshortlistedconsultants,whichshallbedeterminedinthepre-procurementconference,shallconsistofthree(3)toseven(7)consultants,withfive(5)asthepreferablenumber.Shouldlessthantherequirednumberapplyforeligibilityandshortlisting,passtheeligibilitycheck,and/orpasstheminimumscorerequiredintheshortlisting,theBACshallconsiderthesame.

24.5.ShortListingofProspectiveBidders

Page 118: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

24.5.3.TheBACshallspecifyintheRequestforExpressionofInterestthesetofcriteriaandratingsystemforshortlistingofconsultantstobeusedfortheparticularcontracttobebid,whichshallconsiderthefollowing,amongothers:a)Applicableexperienceoftheconsultantandmembersincaseofjointventures,consideringboththeoverallexperiencesofthefirmor,inthecaseofnewfirms,theindividualexperiencesoftheprincipalandkeystaff,includingthetimeswhenemployedbyotherconsultants;b)Qualificationofpersonnelwhomaybeassignedtothejobvis-ŕ-visextentandcomplexityoftheundertaking;andc)Currentworkloadrelativetocapacity.(a)

24.5.ShortListingofProspectiveBidders

Page 119: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

24.5.4.TheBACshallrecommendtheshortlistofconsultantstotheHeadoftheProcuringEntityforconsiderationandapproval.Theentireprocessofeligibilitycheckandshortlistingshallnotexceedtwenty(20)calendardays.

24.5.ShortListingofProspectiveBidders

Page 120: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)EligibilityrequirementsunderSection23.1ofthisIRR;

25.2.Thefirstenvelope

Page 121: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ii)Thebidsecurityintheprescribedform,amountandvalidityperiod;

25.2.Thefirstenvelope

Page 122: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iii)Technicalspecifications,whichmayincludeproduction/deliveryschedule,manpowerrequirements,and/orafter-salesservice/parts,ifapplicable;and

25.2.Thefirstenvelope

Page 123: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iv)SwornstatementbytheprospectivebidderoritsdulyauthorizedrepresentativeintheformprescribedbytheGPPBastothefollowing:(1)ItisnotblacklistedorbarredfrombiddingbytheGOPoranyofitsagencies,offices,corporations,orLGUs,includingforeigngovernment/foreignorinternationalfinancinginstitutionwhoseblacklistingruleshavebeenrecognizedbytheGPPB;

(2)Eachofthedocumentssubmittedinsatisfactionofthebiddingrequirementsisanauthenticcopyoftheoriginal,complete,andallstatementsandinformationprovidedthereinaretrueandcorrect;

(3)ItisauthorizingtheHeadoftheProcuringEntityorhisdulyauthorizedrepresentative/stoverifyallthedocumentssubmitted;

(4)Thesignatoryisthedulyauthorizedrepresentativeoftheprospectivebidder,andgrantedfullpowerandauthoritytodo,executeandperformanyandallactsnecessaryand/ortorepresenttheprospectivebidderinthebidding,withthedulynotarizedSecretarysCertificateattestingtosuchfact,iftheprospectivebidderisacorporation,partnership,cooperative,orjointventure;

(5)ItcomplieswiththedisclosureprovisionunderSection47oftheActinrelationtootherprovisionsofR.A.3019;

(6)ItcomplieswiththeresponsibilitiesofaprospectiveoreligiblebidderprovidedinthePBDs;and

(7)Itcomplieswithexistinglaborlawsandstandards,inthecaseofprocurementofservices.(a)

25.2.Thefirstenvelope

Page 124: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)EligibilityrequirementsunderSection23.3ofthisIRR;

25.2.Thefirstenvelope

Page 125: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ii)Bidsecurityintheprescribedform,amountandvalidityperiod;

25.2.Thefirstenvelope

Page 126: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iii)ProjectRequirements,whichshallincludethefollowing:(1)Organizationalchartforthecontracttobebid;

(2)Listofcontractor spersonnel(viz,ProjectManager,ProjectEngineers,MaterialsEngineers,andForemen),tobeassignedtothecontracttobebid,withtheircompletequalificationandexperiencedata;

(3)Listofcontractor sequipmentunits,whichareowned,leased,and/orunderpurchaseagreements,supportedbycertificationofavailabilityofequipmentfromtheequipmentlessor/vendorforthedurationoftheproject;and

25.2.Thefirstenvelope

Page 127: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iv)SwornstatementbytheprospectivebidderoritsdulyauthorizedrepresentativeintheformprescribedbytheGPPBastothefollowing:(1)ItisnotblacklistedorbarredfrombiddingbytheGOPoranyofitsagencies,offices,corporations,orLGUs,includingforeigngovernment/foreignorinternationalfinancinginstitutionwhoseblacklistingruleshavebeenrecognizedbytheGPPB;

(2)Eachofthedocumentssubmittedinsatisfactionofthebiddingrequirementsisanauthenticcopyoftheoriginal,complete,andallstatementsandinformationprovidedthereinaretrueandcorrect;

(3)ItisauthorizingtheHeadoftheProcuringEntityorhisdulyauthorizedrepresentative/stoverifyallthedocumentssubmitted;

(4)Thesignatoryisthedulyauthorizedrepresentativeoftheprospectivebidder,andgrantedfullpowerandauthoritytodo,executeandperformanyandallactsnecessaryand/ortorepresenttheprospectivebidderinthebidding,withthedulynotarizedSecretarysCertificateattestingtosuchfact,iftheprospectivebidderisacorporation,partnershiporjointventure;

(5)ItcomplieswiththedisclosureprovisionunderSection47oftheActinrelationtootherprovisionsofR.A.3019;

(6)ItcomplieswiththeresponsibilitiesofaprospectiveoreligiblebidderprovidedinthePBDs;and

(7)Itcomplieswithexistinglaborlawsandstandards.(a)

25.2.Thefirstenvelope

Page 128: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)Thebidsecurityintheprescribedform,amountandvalidityperiod;

25.2.Thefirstenvelope

Page 129: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ii)Organizationalchartforthecontracttobebid;

25.2.Thefirstenvelope

Page 130: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iii)Listofcompletedandon-goingprojects;

25.2.Thefirstenvelope

Page 131: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iv)Approach,workplan,andschedule:Provided,however,Thatforarchitecturaldesign,submissionofarchitecturalplansanddesignsshallnotberequiredduringtheconsultantsselectionprocess;

25.2.Thefirstenvelope

Page 132: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

v)Listofkeypersonneltobeassignedtothecontracttobebid,withtheircompletequalificationandexperiencedata;and

25.2.Thefirstenvelope

Page 133: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

vi)SwornstatementbytheprospectivebidderoritsdulyauthorizedrepresentativeintheformprescribedbytheGPPBastothefollowing:(1)ItisnotblacklistedorbarredfrombiddingbytheGOPoranyofitsagencies,offices,corporations,orLGUs,foreigngovernment/foreignorinternationalfinancinginstitutionwhoseblacklistingruleshavebeenrecognizedbytheGPPB;

(2)Eachofthedocumentssubmittedinsatisfactionofthebiddingrequirementsisanauthenticcopyoftheoriginal,complete,andallstatementsandinformationprovidedthereinaretrueandcorrect;

(3)ItisauthorizingtheHeadoftheProcuringEntityorhisdulyauthorizedrepresentative/stoverifyallthedocumentssubmitted;

(4)Thesignatoryisthedulyauthorizedanddesignatedrepresentativeoftheprospectivebidder,andgrantedfullpowerandauthoritytodo,executeandperformanyandallactsnecessaryand/ortorepresenttheprospectivebidderinthebidding,withthedulynotarizedSecretarysCertificateattestingtosuchfact,iftheprospectivebidderisacorporation,partnershiporjointventure;

(5)ItcomplieswiththedisclosureprovisionunderSection47oftheActinrelationtootherprovisionsofR.A.3019;

(6)ItcomplieswiththeresponsibilitiesofaprospectiveoreligiblebidderprovidedinthePBDs;and

(7)Itcomplieswithexistinglaborlawsandstandards.(a)

25.2.Thefirstenvelope

Page 134: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

32.2.1.TheBACshallimmediatelyconductadetailedevaluationofallbidsusingnondiscretionarycriteriainconsideringthefollowing:a)Completenessofthebid.UnlesstheInstructionstoBiddersspecificallyallowpartialbids,bidsnotaddressingorprovidingalloftherequireditemsintheBiddingDocumentsincluding,whereapplicable,billofquantities,shallbeconsiderednon-responsiveand,thus,automaticallydisqualified.Inthisregard,wherearequireditemisprovided,butnopriceisindicated,thesameshallbeconsideredasnon-responsive,butspecifyinga0(zero)forthesaiditemwouldmeanthatitisbeingofferedforfreetotheGovernment;andb)Arithmeticalcorrections.Considercomputationalerrors,omissions,andotherbidmodifications,ifallowedintheBiddingDocuments,toenablepropercomparisonofalleligiblebids.Anyadjustmentshallbecalculatedinmonetarytermstodeterminethecalculatedprices.(a)

32.2.Fortheprocurementofgoods

Page 135: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

32.2.2.TheBACshallevaluateallbidsonanequalfootingtoensurefairandcompetitivebidcomparison.Forthispurpose,allbiddersshallberequiredtoincludethecostofalltaxes,suchas,butnotlimitedto,valueaddedtax(VAT),incometax,localtaxes,andotherfiscalleviesanddutieswhichshallbeitemizedinthebidformandreflectedinthedetailedestimates.Suchbids,includingsaidtaxes,shallbethebasisforbidevaluationandcomparison.(a)

32.2.Fortheprocurementofgoods

Page 136: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

32.2.3.Incaseofdiscrepanciesbetween:(a)bidpricesinfiguresandinwords,thelattershallprevail;(b)totalpriceperitemandunitpricefortheitemasextendedormultipliedbythequantityofthatitem,thelattershallprevail;(c)statedtotalpriceandtheactualsumofpricesofcomponentitems,thelattershallprevail;(d)unitcostinthedetailedestimateandunitcostinthebillofquantities,thelattershallprevail.

32.2.Fortheprocurementofgoods

Page 137: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

32.2.4.Bidsshallthenberankedintheascendingorderoftheirtotalcalculatedbidprices,asevaluatedandcorrectedforcomputationalerrors,andotherbidmodifications,toidentifytheLowestCalculatedBid.Totalcalculatedbidprices,asevaluatedandcorrectedforcomputationalerrors,andotherbidmodifications,whichexceedtheABCshallbedisqualified.(a)

32.2.Fortheprocurementofgoods

Page 138: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

33.2.1.TheBACshallconductadetailedevaluationofbidsusingeitherofthefollowingevaluationproceduresasspecifiedintheBiddingDocuments:a)Quality-BasedEvaluationProcedure

i)Atwo-stageprocedureii)Afterreceiptofbidsiii)TheHeadoftheProcuringEntityiv)AfterapprovalbytheHeadv)Negotiations

b)Quality-CostBasedEvaluationProcedure

i)Thetechnicalproposalii)Thefinancialandtechnicalproposalsiii)TheHeadoftheProcuringEntityiv)AfterapprovalbytheHeadoftheProcuringEntity

33.2.Thepurposeofbidevaluation

Page 139: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

33.2.2.ThetechnicalproposalsofconsultantsshallbeevaluatedbasedonthefollowingcriteriaandusingthecorrespondingnumericalweightsindicatedintheBiddingDocuments:a)Qualityofpersonneltobeassignedtotheprojectwhichcoverssuitabilityofkeystafftoperformthedutiesoftheparticularassignmentsandgeneralqualificationsandcompetenceincludingeducationandtrainingofthekeystaff;

b)Experienceandcapabilityoftheconsultantwhichincluderecordsofpreviousengagementandqualityofperformanceinsimilarandinotherprojects;relationshipwithpreviousandcurrentclients;and,overallworkcommitments,geographicaldistributionofcurrent/impendingprojectsandattentiontobegivenbytheconsultant.Theexperienceoftheconsultanttotheprojectshallconsiderboththeoverallexperiencesofthefirmandtheindividualexperiencesoftheprincipalandkeystaffincludingthetimeswhenemployedbyotherconsultants;and

c)Planofapproachandmethodologywithemphasisontheclarity,feasibility,innovativenessandcomprehensivenessoftheplanapproach,andthequalityofinterpretationofprojectproblems,risks,andsuggestedsolutions.Forcomplexoruniqueundertakings,suchasthoseinvolvingnewconcepts/technologyorfinancialadvisoryservices,participatingshortlistedconsultantsmayberequired,attheoptionoftheagencyconcerned,tomakeanoralpresentationtobepresentedbyeachconsultant,oritsnominatedProjectManagerorhead,incaseoffirms,withinfifteen(15)calendardaysafterthedeadlineforsubmissionoftechnicalproposals.

33.2.Thepurposeofbidevaluation

Page 140: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

33.2.3.Inordertoeliminatebiasinevaluatingthetechnicalproposals,itisrecommendedthatthehighestandlowestscoresforeachconsultantforeachcriterionshallnotbeconsideredindeterminingtheaveragescoresoftheconsultants,exceptwhentheevaluationisconductedinacollegialmanner.(a)

33.2.Thepurposeofbidevaluation

Page 141: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

33.2.4.Allparticipatingshortlistedconsultantsshallbefurnishedtheresults(rankingandtotalscoresonly)oftheevaluationaftertheapprovalbytheHeadoftheProcuringEntityoftheranking.SaidresultsshallalsobepostedinthePhilGEPSandthewebsiteoftheprocuringentity,wheneveravailable,foraperiodofnotlessthanseven(7)calendardays.(a)

33.2.Thepurposeofbidevaluation

Page 142: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

33.2.5.Negotiationsshallcoverthefollowing:a)DiscussionandclarificationoftheTORandScopeofServices;

b)Discussionandfinalizationofthemethodologyandworkprogramproposedbytheconsultant;

c)Considerationofappropriatenessofqualificationsandpertinentcompensation,numberofman-monthsandthepersonneltobeassignedtothejob,takingnoteofover-qualifiedpersonnel,tobecommensuratewiththecompensationofpersonnelwiththeappropriatequalifications,numberofman-monthsandscheduleofactivities(manningschedule);

d)Discussionontheservices,facilitiesanddata,ifany,tobeprovidedbyprocuringentityconcerned;

e)Discussiononthefinancialproposalsubmittedbytheconsultant;and

f)Provisionsofthecontract.Exceptformeritoriousreasons,negotiationswithanyoneconsultantshallbecompletedwithinten(10)calendardays.(a)

33.2.Thepurposeofbidevaluation

Page 143: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

33.2.6.Totalcalculatedbidprices,asevaluatedandcorrectedforminorarithmeticalcorrections,suchascomputationalerrors,whichexceedtheABCshallnotbeconsidered.(a)

33.2.Thepurposeofbidevaluation

Page 144: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)Verificationandvalidationofthebidder sstatedcompetenceandexperience,andthecompetenceandexperienceofthebidder skeypersonneltobeassignedtotheproject,fortheprocurementofinfrastructureprojectsandconsultingservices;

34.3.Thepost-qualificationshallverify,validate,andascertainallstatements

Page 145: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ii)Verificationofavailabilityandcommitment,and/orinspectionandtestingfortherequiredcapacitiesandoperatingconditions,ofequipmentunitstobeowned/leased/underpurchasebythebidderforuseinthecontractunderbidding,aswellascheckingtheperformanceofthebidderinitsongoinggovernmentandprivatecontracts(ifanyoftheseon-goingcontractsshowsareportednegativeslippageofatleastfifteenpercent(15%),orsubstandardqualityofworkaspercontractplansandspecifications,orunsatisfactoryperformanceofthecontractor sobligationsaspercontracttermsandconditions,atthetimeofinspection,andiftheBACverifiesanyofthesedeficienciestobeduetothecontractor sfaultornegligence,theagencyshalldisqualifythecontractorfromtheaward),fortheprocurementofinfrastructureprojects;

34.3.Thepost-qualificationshallverify,validate,andascertainallstatements

Page 146: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iii)Verificationand/orinspectionandtestingofthegoods/product,after-salesand/ormaintenancecapabilities,inapplicablecases,fortheprocurementofgoods;and

34.3.Thepost-qualificationshallverify,validate,andascertainallstatements

Page 147: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iv)Ascertainmentofthesufficiencyofthebidsecurityastotype,amount,formandwording,andvalidityperiod.

34.3.Thepost-qualificationshallverify,validate,andascertainallstatements

Page 148: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

37.1.1.TheBACshallrecommendtotheHeadoftheProcuringEntitytheawardofcontracttothebidderwiththeLowestCalculatedResponsiveBid/HighestRatedResponsiveBidortheSingleCalculated/RatedResponsiveBidafterthepost-qualificationprocesshasbeencompleted.Tofacilitatetheapprovaloftheaward,theBACshallsubmitthefollowingsupportingdocumentstotheHeadoftheProcuringEntity:a)ResolutionoftheBACrecommendingaward;

b)AbstractofBids;

c)Dulyapprovedprogramofworkordeliveryschedule,andCostEstimates;

d)Documentissuedbyappropriateentityauthorizingtheprocuringentitytoincurobligationsforaspecifiedamount;ande)Otherpertinentdocumentsrequiredbyexistinglaws,rules,and/ortheprocuringentityconcerned.(a)

37.1.ContractAward

Page 149: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

37.1.2.Withinaperiodnotexceedingseven(7)calendardaysfromthedateofreceiptoftherecommendationoftheBAC,theHeadoftheProcuringEntityshallapproveordisapprovethesaidrecommendation.However,forinfrastructureprojectswithanABCofFiftyMillionPesos(P50,000,000)andbelow,theHeadoftheProcuringEntityshallapproveordisapprovethesaidrecommendationwithinfour(4)calendardays.InthecaseofGOCCsandGFIs,theperiodprovidedhereinshallbefifteen(15)calendardays.Withinthesameperiodprovidedherein,theBACshallnotifyalllosingbiddersofitsdecision.

37.1.ContractAward

Page 150: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

37.1.3.Incaseofapproval,theHeadoftheProcuringEntityshallimmediatelyissuetheNoticeofAwardtothebidderwiththeLowestCalculatedResponsiveBid/HighestRatedResponsiveBid.IntheeventtheHeadoftheProcuringEntityshalldisapprovesuchrecommendation,suchdisapprovalshallbebasedonlyonvalid,reasonable,andjustifiablegroundstobeexpressedinwriting,copyfurnishedtheBAC.(n)

37.1.ContractAward

Page 151: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

37.1.4.NotwithstandingtheissuanceoftheNoticeofAward,awardofcontractshallbesubjecttothefollowingconditions:a)Submissionofthefollowingdocumentswithintheprescribedperiod:

i)ValidJVA,ifapplicableii)Inthecaseofinfrastructureprojects

b)PostingofperformancesecurityinaccordancewithSection39ofthisIRR;

c)SigningofthecontractasprovidedinSection37.2ofthisIRR;and

d)Approvalbyhigherauthority,ifrequired,asprovidedinSection37.3ofthisIRR.(n)

37.1.ContractAward

Page 152: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

37.1.5.ContractawardshallbemadewithinthebidvalidityperiodprovidedinSection28ofthisIRR.(a)

37.1.ContractAward

Page 153: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

37.1.6.TheBAC,throughtheSecretariat,shallpost,withinthree(3)calendardaysfromitsissuance,theNoticeofAwardinthePhilGEPS,thewebsiteoftheprocuringentity,ifany,andanyconspicuousplaceinthepremisesoftheprocuringentity.(n)

37.1.ContractAward

Page 154: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

37.2.1.ThewinningbiddershallposttherequiredPerformanceSecurityandenterintocontractwiththeprocuringentitywithinten(10)calendardaysfromreceiptbythewinningbidderoftheNoticeofAward.(a)

37.2.ContractSigning

Page 155: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

37.2.2.Theprocuringentityshallenterintocontractwiththewinningbidderwithinthesameten(10)dayperiodprovidedthatallthedocumentaryrequirementsarecompliedwith.(a)

37.2.ContractSigning

Page 156: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

37.2.3.Thefollowingdocumentsshallformpartofthecontract:a)ContractAgreement;

b)BiddingDocuments;

c)Winningbidder sbid,includingtheEligibilityrequirements,TechnicalandFinancialProposals,andallotherdocuments/statementssubmitted;d)PerformanceSecurity;e)CreditlineinaccordancewiththeprovisionsofthisIRR,ifapplicable;f)NoticeofAwardofContract;andg)Othercontractdocumentsthatmayberequiredbyexistinglawsand/ortheprocuringentityconcernedintheBiddingDocuments,suchastheconstructionscheduleandS-curve,manpowerschedule,constructionmethods,equipmentutilizationschedule,constructionsafetyandhealthprogramapprovedbytheDepartmentofLaborandEmployment,andPERT/CPMforinfrastructureprojects.(a)

37.2.ContractSigning

Page 157: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

37.4.1.TheprocuringentityshallissuetheNoticetoProceedtogetherwithacopyoftheapprovedcontracttothesuccessfulbidderwithinthree(3)calendardaysfromthedateofapprovalofthecontractbytheappropriategovernmentapprovingauthority.However,forinfrastructureprojectswithanABCofFiftyMillionPesos(P50,000,000)andbelow,themaximumperiodistwo(2)calendardays.ThecontracteffectivitydateshallbeprovidedintheNoticetoProceedbytheprocuringentity,whichdateshallnotbelaterthanseven(7)calendardaysfromitsissuance.(a)

37.4.NoticetoProceed

Page 158: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

37.4.2.Theprocuringentity,throughtheBACSecretariat,shallpostacopyoftheNoticetoProceedandtheapprovedcontractinthePhilGEPSorthewebsiteoftheprocuringentity,ifany,withinfifteen(15)calendardaysfromtheissuanceoftheNoticetoProceed.(n)

37.4.NoticetoProceed

Page 159: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

43.1.1.ConsistentwiththeGOPsobligationsunderinternationaltreatiesoragreements,goodsmaybeobtainedfromdomesticorforeignsources:Provided,however,Thattheprocurementthereofshallbeopenonlytoeligiblesuppliers,manufacturersanddistributors:Provided,further,That,intheinterestofavailability,efficiencyandtimelydeliveryofgoods,theprocuringentitymaygivepreferencetothepurchaseofdomestically-producedandmanufacturedgoods,suppliesandmaterialsthatmeetthespecifiedordesiredquality,inaccordancewiththeprovisionsofCommonwealthActNo.138.(a)

43.1.ScopeandApplication

Page 160: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

43.1.2.Theprocuringentityshallgivepreferencetomaterialsandsuppliesproduced,madeandmanufacturedinthePhilippinesandtoDomesticEntities,subjecttotheconditionshereinbelowspecified.TheawardshallbemadetothelowestDomesticBidderorlowestDomesticEntity,providedhisbidisnotmorethanfifteenpercent(15%)inexcessofthelowestForeignBid.(n)

43.1.ScopeandApplication

Page 161: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

43.1.3.ADomesticEntitycanonlyclaimpreferenceifitsecuresfromtheDTIacertificationthatithasallthequalificationsrequiredunderthisIRR,incaseofsoleproprietorships,SEC,incaseofpartnershipsandcorporations,orCDA,incaseofcooperatives.(n)

43.1.ScopeandApplication

Page 162: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

43.1.4.ADomesticBiddercanonlyclaimpreferenceifitsecuresfromtheDTIacertificationthatthearticlesformingpartofitsbidaresubstantiallycomposedofarticles,materials,orsuppliesgrown,produced,ormanufacturedinthePhilippines.(n)

43.1.ScopeandApplication

Page 163: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

43.2.1.Thepreferenceshallbeappliedwhen(a)thelowestForeignBidislowerthanthelowestbidofferedbyaDomesticBidder,or(b)thelowestbidofferedbyanon-PhilippinenationalislowerthanthelowestbidofferedbyaDomesticEntity.TheprocuringentityshallensurethatbothbidsareresponsivetotheminimumrequirementsasspecifiedintheBiddingDocuments.(n)

43.2.ProceduresandGuidelines

Page 164: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

43.2.2.Forevaluationpurposes,thelowestForeignBidorthebidofferedbyanon-Philippinenationalshallbeincreasedbyfifteenpercent(15%).(n)

43.2.ProceduresandGuidelines

Page 165: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

43.2.3.Intheeventthat(a)thelowestbidofferedbyaDomesticBidderdoesnotexceedthelowestForeignBidasincreased,or(b)thelowestbidofferedbyaDomesticEntitydoesnotexceedthelowestbidofferedbyanon-Philippinenationalasincreased,thentheprocuringentityshallawardthecontracttotheDomesticBidder/EntityattheamountofthelowestForeignBidorbidofferedbyanon-Philippinenational,asthecasemaybe.(n)

43.2.ProceduresandGuidelines

Page 166: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

43.2.4.IftheDomesticEntity/BidderrefusestoaccepttheawardofcontractattheamountoftheForeignBidorbidofferedbyanon-Philippinenationalwithintwo(2)calendardaysfromreceiptofwrittenadvicefromtheBAC,theprocuringentityshallawardtothebidderofferingtheForeignBidorthenon-Philippinenational,asthecasemaybe,subjecttopost-qualificationandsubmissionofallthedocumentaryrequirementsunderthisIRR.(n)

43.2.ProceduresandGuidelines

Page 167: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

53.1.1.Afterconductofthemandatoryreviewoftheterms,conditions,specifications,andcostestimates,asprescribedinSection35ofthisIRR,theBACshallreviseandagreeontheminimumtechnicalspecifications,andifnecessary,adjusttheABC,subjecttotherequiredapprovals.However,theABCcannotbeincreasedbymorethantwentypercent(20%)oftheABCforthelastfailedbidding.(n)

53.1.TwoFailedBiddings

Page 168: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

53.1.2.TheBACshallinviteandengageinnegotiationswithasufficientnumberofsuppliers,contractorsorconsultantstoensureeffectivecompetition.(a)53.1.2.1.Inthecaseofinfrastructureprojects53.1.2.2.AllProcuringEntities

53.1.TwoFailedBiddings

Page 169: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

53.1.3.Anyrequirements,guidelines,documents,clarifications,orotherinformationrelativetothenegotiationsthatarecommunicatedbytheprocuringentitytoasupplier,contractor,orconsultantshallbecommunicatedonanequalbasistoallothersuppliers,contractors,orconsultantsengaginginnegotiationswiththeprocuringentityrelativetotheprocurement.(n)

53.1.TwoFailedBiddings

Page 170: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

53.1.4.Followingcompletionofthenegotiations,theprocuringentityshallrequestallsuppliers,contractors,orconsultantsremainingintheproceedingstosubmit,onaspecifieddate,abestandfinalofferwithrespecttoallaspectsoftheirproposals.(n)

53.1.TwoFailedBiddings

Page 171: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

53.1.5.TheprocuringentityshallselectthesuccessfulofferonthebasisofsuchbestandfinalofferswhichshouldmeettheprocuringentitysminimumtechnicalrequirementsandshouldnotexceedtheABC.(n)

53.1.TwoFailedBiddings

Page 172: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

53.1.6.Inallstagesofthenegotiations,observersshallbeinvited.(n)

53.1.TwoFailedBiddings

Page 173: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

53.3.1.Thecontractmaybenegotiatedstartingwiththesecondlowestcalculated/highestratedbidderfortheprojectunderconsiderationatthebidder soriginalbidprice.(a)

53.3.Take-OverofContracts

Page 174: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

53.3.2.Ifnegotiationfails,thennegotiationshallbedonewiththethirdlowestcalculated/highestratedbidderathisoriginalprice.Ifthenegotiationfailsagain,ashortlistofatleastthree(3)eligiblecontractorsshallbeinvitedtosubmittheirbids,andnegotiationshallbemadestartingwiththelowestcalculated/highestratedbidder.(a)

53.3.Take-OverofContracts

Page 175: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

53.3.3.AuthoritytonegotiatecontractsforprojectsundertheseexceptionalcasesshallbesubjecttopriorapprovalbytheHeadsoftheProcuringEntitiesconcerned,withintheirrespectivelimitsofapprovingauthority.(a)

53.3.Take-OverofContracts

Page 176: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

53.9.1.Theprocuringentityshalldrawupalistofatleastthree(3)suppliers,contractors,orconsultantsofknownqualificationswhichwillbeinvitedtosubmitproposals,inthecaseofgoodsandinfrastructureprojects,orcurriculumvitae,inthecaseofconsultingservices.(a)

53.9.SmallValueProcurement

Page 177: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

53.9.2.ThethresholdsprescribedinAnnexHofthisIRRshallbesubjecttotheperiodicreviewbytheGPPB.Forthispurpose,theGPPBshallbeauthorizedtoincreaseordecreasethesaidamountinordertoreflectthechangesineconomicconditionsandforotherjustifiablereasons.(n)

53.9.SmallValueProcurement

Page 178: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

62.2.1.Fromthetimeprojectconstructioncommenceduptofinalacceptance,thecontractorshallassumefullresponsibilityforthefollowing:a)anydamageordestructionoftheworksexceptthoseoccasionedbyforcemajeure;and

b)safety,protection,security,andconvenienceofhispersonnel,thirdparties,andthepublicatlarge,aswellastheworks,equipment,installationandtheliketobeaffectedbyhisconstructionwork;(a)

62.2.Fortheprocurementofinfrastructureprojects

Page 179: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

62.2.2.One(1)yearfromprojectcompletionuptofinalacceptanceorthedefectsliabilityperiod.62.2.2.1.Thecontractorshallundertaketherepairworks,athisownexpense,ofanydamagetotheinfrastructureonaccountoftheuseofmaterialsofinferiorquality,withinninety(90)daysfromthetimetheHeadoftheProcuringEntityhasissuedanordertoundertakerepair.Incaseoffailureorrefusaltocomplywiththismandate,theprocuringentityshallundertakesuchrepairworksandshallbeentitledtofullreimbursementofexpensesincurredthereinupondemand.

62.2.2.2.ThedefectsliabilityperiodshallbecoveredbythePerformanceSecurityofthecontractorrequiredinSection39.1ofthisIRR,whichshallguaranteethatthecontractorperformshisresponsibilitiesstatedintheimmediatelyprecedingSection.IfthecontractorfailstocomplywithitsobligationsunderSection62.2.2.1ofthisIRR,theprocuringentityshallforfeititsperformancesecurity,subjectitsproperty(ies)toattachmentorgarnishmentproceedings,andperpetuallydisqualifyitfromparticipatinginanypublicbidding.AllpayablesoftheGOPinhisfavorshallbeoffsettorecoverthecosts.(a)

62.2.Fortheprocurementofinfrastructureprojects

Page 180: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

62.2.3.FromfinalacceptanceoftheprojectuptotheperiodprescribedinSection62.2.3.2.62.2.3.1.Thefollowingshallbeheldresponsible62.2.3.2.ThewarrantyagainstStructuralDefects62.2.3.3.Toguaranteethatthecontractor62.2.3.4.Thewarrantysecurity

62.2.Fortheprocurementofinfrastructureprojects

Page 181: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

62.2.4.IncaseofStructuralDefects/FailureoccurringduringtheapplicablewarrantyperiodprovidedinSection62.2.3.2hereof,theprocuringentityshallundertakethenecessaryrestorationorreconstructionworksandshallbeentitledtofullreimbursementbythepartiesfoundtobeliableforexpensesincurredthereinupondemand,withoutprejudicetothefilingofappropriateadministrative,civil,and/orcriminalchargesagainsttheresponsiblepersonsaswellastheforfeitureofwarrantysecuritiespostedinfavoroftheprocuringentity.(a)

62.2.Fortheprocurementofinfrastructureprojects

Page 182: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

1.Detailedengineeringshallproceedonlyonthebasisofthefeasibilityorpreliminaryengineeringstudymadewhichestablishesthetechnicalviabilityoftheprojectandconformancetolanduseandzoningguidelinesprescribedbyexistinglaws.Thefindingscontainedinthefeasibilitystudy,ifundertakenfortheproject,shallbeexamined.If,inthecourseofthisexercise,itisfoundthatchangeswouldbedesirableinthedesignstandardsofprincipalfeatures,asproposed,specificrecommendationsforsuchchangesshallbesupportedbydetailedjustifications,includingtheireffectsonthecost,and(ifnecessary)theeconomicjustification.

BACK

Page 183: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

2.Ascheduleofdetailedengineeringactivitiesshallincludethefollowing:a)Surveyb)SiteInvestigationc)SoilsandFoundationInvestigationd)ConstructionMaterialsInvestigatione)PreparationofDesignPlansf)PreparationofTechnicalSpecificationsg)PreparationofQuantityandCostEstimatesh)PreparationofProgramofWorki)PreparationofProposedConstructionSchedule(andestimatedCashFlowforprojectswithScheduleoverSix(6)Months)j)PreparationofSiteorRight-of-WayPlansincludingScheduleofAcquisitionk)PreparationofUtilityRelocationPlanl)PreparationandSubmissionofDesignReportm)EnvironmentalImpactStatementforcriticalprojectasdefinedbytheDepartmentofEnvironmentandNaturalResources(DENR)n)PreparationofminimumrequirementsforaConstructionSafetyandHealthProgramfortheprojectbeingconsideredo)PreparationofBid/TenderDocuments

BACK

Page 184: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

3.Workunderdetailedengineeringshallinclude,butnotnecessarilybelimitedto,thefollowing:a)DesignStandardsb)FieldSurveysAndInvestigationsc)ContractPlansd)Quantitiese)SpecialProvisionsf)UnitPricesg)ApprovedBudgetfortheContracth)BiddingDocumentsi)ProgramofWorkj)ContractTimeorDurationk)WarrantyPeriodl)ValueEngineeringm)SiteorRight-of-WayAcquisitionPlansandResettlementActionPlans

BACK

Page 185: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

4.Asarequirementfortheprocurementofinfrastructureworks,theconcernedconsultants/governmentofficialswhopreparedandapprovedthedetailedengineeringshallissueacertificationthatthedetailedengineeringsurveysanddesignshavebeenconductedaccordingtotheprescribedagencystandardsandspecificationsinconformancewiththeprovisionsofthisAnnex,andthatthedetailedengineeringoutputsareadequatefortheprocurementathand.Theapprovalbytheauthorizedgovernmentofficialsofdetailedengineeringsurveysanddesignsundertakenbyconsultantsneitherdiminishestheresponsibilityofthelatterforthetechnicalintegrityofthesurveysanddesignsnortransferanypartofthatresponsibilitytotheapprovingofficials.

BACK

Page 186: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

5.Theaboverulesshallapplytotheimplementationofinfrastructureprojectsundernormalorordinaryconditions.However,underemergencyorextraordinarycasesinvolvingmajorcalamitiesanddisastersasdeclaredbythePresidentwheretimeisoftheessencetosavelivesandpropertiesandrestoredamagedinfrastructures,detailedengineeringworksshallbeconductedinaccordancewiththeguidelinesandprocedures,asprescribedbytheheadoftheappropriateinfrastructureagencyandapprovedbytheInfrastructureCommitteeoftheNationalEconomicandDevelopmentAuthorityBoard,toenablequickresponsetosaidcases,whilemaintainingthesafetyandintegrityofthestructure.

BACK

Page 187: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

1.Definition

Anaturalorjuridicalperson,qualifiedbyappropriateeducation,trainingandrelevantexperiencetorenderanyorallofthetypesandfieldsofconsultingservicesasdefinedinthisIRR,shallbeconsideredasaConsultant,subjecttotherequirementsprovidedinthisIRRforeligibilitycheckandpost-qualification.

BACK

Page 188: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

2.TheNeedforConsultants

Theservicesofconsultantsmaybeengagedbyanyprocuringentityforgovernmentprojectsorrelatedactivitiesofsuchmagnitudeand/orscopeaswouldrequirealevelofexpertiseorattentionbeyondtheoptimumin-housecapabilityoftheprocuringentityconcernedandconsistentwiththeGovernmentspolicynottocompetewiththeprivatesector.

BACK

Page 189: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

3.IndependenceofConsultants

Toensuretheconsultantsprofessionalindependence,integrity,andobjectivity,consultants,aswellaskeystaffworkingfortheconsultingentity,whomaybedirectlyorindirectlyassociatedwithnon-consultingfirmsthatmayhaveaninterestinorbiastowardstheprojectconcerned,shallbeselectedonlyiftheyagreetolimittheirroletothatofconsultantsandwilldisqualifythemselvesandtheiraffiliatesforbiddingforproductsandservicesofthesamegovernmentproject.

BACK

Page 190: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

4.HiringofConsultants

4.1.Consultantsshallbehiredonthebasisoftheirprovenexpertise,experienceandcapability.Undercertainconditionsprovidedherein,costmaybeincludedasafactorintheselectionofconsultants.

4.2.InordertomanifesttrustandconfidenceinandpromotethedevelopmentofFilipinoconsultancy,FilipinoconsultantsshallbehiredwhenevertheservicesrequiredfortheprojectarewithintheexpertiseandcapabilityofFilipinoconsultants:Provided,however,ThatintheeventFilipinoconsultantsdonothavethesufficientexpertiseandcapabilitytorendertheservicesrequiredundertheproject,asdeterminedbytheHeadoftheProcuringEntity,foreignconsultantsmaybehired.

4.3.Inthehiringofforeignconsultants,allpertinentlawsandregulationsofthePhilippinesshallbefollowed.

4.4.Technologyandknowledgetransfertotheprocuringentityshallberequiredintheprovisionofconsultingservices,whereapplicable.

BACK

Page 191: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

5.OrganizationofConsultants

5.1.TheumbrellaorganizationofconsultantsrecognizedbytheGovernmentshallbecomposedofthevariousorganizationsofconsultantsthatmaybeengagedbytheGovernmentunderthisIRRandshallaccredititsmembersonthetypesofservicesandfieldsofprofessionswherethemembersaretechnicallyandfinanciallyqualifiedtooffertheirservices.TheumbrellaorganizationshallprepareandcertifyalistoffieldsandexpertiseinsuchfieldsavailablewiththenamesoftheaccreditedlocalconsultantswhichshallbeupdatedannuallyorasoftenasnecessaryanddisseminatesuchlisttoconcernedagenciesoftheGovernment.Itshalllikewiseregulateitsmembersforthedevelopmentoftheindustry.TheGovernmentmayconsultanddealwiththisumbrellaorganizationonmattersrelatingtotheindustry.TheGPPBshallbetheappropriategovernmentbodythatshallrecognizetheconsultantsumbrellaorganization.

5.2.TheumbrellaorganizationmaysubmititsfilesofaccreditedconsultantstotheBACoftheprocuringentityinaccordancewiththeformprescribedbytheBACwhichcanserveasregistrationoftheconsultantsunderthenextsucceedingSubsection:Provided,however,ThateachsuchaccreditedconsultantshallcomplywiththeeligibilityrequirementsprovidedinthisIRR.Suchqualificationstatements,togetherwiththelistofaccreditedconsultantspreparedinaccordancewiththeimmediatelyprecedingsection,shallguidetheBACindeterminingthefieldswhereFilipinoconsultantsarealreadyqualifiedandcapableandwhereforeignconsultantsmaynotberequired.

BACK

Page 192: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

6.TypesofConsultingServicesTheservicestobeprovidedbyconsultantscanbedividedintosix(6)broadcategories,namely:(a)advisoryandreviewservices;(b)pre-investmentorfeasibilitystudies;(c)design;(d)constructionsupervision;(e)managementandrelatedservices;and(f)othertechnicalservicesorspecialstudies.

6.1.AdvisoryandReviewServices6.2.Pre-InvestmentorFeasibilityStudies6.3.Design6.4.ConstructionSupervision6.5.ManagementandRelatedServices6.6.OtherTechnicalServicesorSpecialStudies

BACK

Page 193: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

LATESTALLOWABLETIME

StageActivitiesDeadlineGoodsInfrastructureProjectsConsultingServicesForABC50MandbelowForABCabove50M

1Advertisement/PostingofInvitationtoBid/RequestforExpressionofInterest7cd7cd7cd7cd2EligibilityCheck(andShortListing,incaseofConsultingServices)RefertoStage5RefertoStage5RefertoStage520cd3IssuanceandavailabilityofBiddingDocumentsFrom1stdayofStage1untilStage54Pre-bidConference12cdbeforeStage51cd1cd1cd1cdRequestforclarification10cdbeforeStage5Supplemental/BidBulletin7cdbeforeStage55SubmissionandreceiptofBids45cdfromlastdayofStage1forGoods.50/65cdfromlastdayofStage1forInfrastructureProjects.75cdfromlastdayofStage1forConsultingServices.1cd(includesopeningofbidsandeligibilitycheck)1cd(includesopeningofbidsandeligibilitycheck)1cd(includesopeningofbidsandeligibilitycheck)1cd(includesopeningofbids)Submissionofadditionalrequirements3cdafterStage56BidEvaluation7cd5cd7cd21cd+2cdforapprovalofranking7Notificationfornegotiationn/an/an/a3cd8Negotiationn/an/an/a10cd9Post-qualification30cd30cd30cd30cd10Approvalofresolution/IssuanceofNoticeofAward7cd4cd7cd7cd11Contractpreparationandsigning10cd10cd10cd10cd12Approvalofcontract15cd5cd15cd15cdbyhigherauthority13IssuanceofNoticetoProceed3cd2cd3cd3cdTotalTime124cd113cd144cd170cd

BACK

Page 194: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

EARLIESTPOSSIBLETIME

StageActivitiesDeadlineGoodsInfrastructureProjectsConsultingServices

1Advertisement/PostingofInvitationtoBid/RequestforExpressionofInterest7cd7cd7cd2EligibilityCheck(andShortListing,incaseofConsultingServices)RefertoStage5RefertoStage53cd(1cdforeligibility,1cdforshortlisting,and1cdfornotice)3IssuanceandavailabilityofBiddingDocumentsFrom1stdayofStage1untilStage54Pre-bidConference12cdbeforeStage51cd1cd1cdRequestforclarification10cdbeforeStage5Supplemental/BidBulletin7cdbeforeStage55SubmissionandreceiptofBids1cd(includesopeningofbidsandeligibilitycheck)1cd(includesopeningofbidsandeligibilitycheck)1cd(includesopeningofbids)Submissionofadditionalrequirements3cdafterStage56BidEvaluation1cd1cd1cd+1cdforapprovalofranking7Notificationfornegotiationn/an/a1cd8Negotiationn/an/a1cd9Post-qualification1cd1cd1cd10Approvalofresolution/IssuanceofNoticeofAward2cd(1cdforBACresolutionand1cdforNOA2cd(1cdforBACresolutionand1cdforNOA2cd(1cdforBACresolutionand1cdforNOA11Contractpreparationandsigning2cd(1cdforcontractpreparationand1cdforcontractsigning2cd(1cdforcontractpreparationand1cdforcontractsigning2cd(1cdforcontractpreparationand1cdforcontractsigning12Approvalofcontract1cd1cd1cdbyhigherauthority13IssuanceofNoticetoProceed1cd1cd1cdTotalTime28cd28cd34cd

BACK

Page 195: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

1.AmendmenttoOrder

1.1.Subjecttotheconditions1.2.Anamendmenttoordermaybeissuedonlyinemergencycases1.3.Anamendmenttoordermayalsobeissuedbytheconcernedprocuringentity1.4.Undernocircumstances

BACK

Page 196: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

2.SuspensionofWork

2.1.Theprocuringentitymaysuspendtheworkwhollyorpartlybywrittenorderforacertainperiodoftime,asitdeemsnecessaryduetoforcemajeureoranyfortuitouseventsasdefinedinthecontract.Thesupplierorconsultantshalltakeallreasonablestepstominimizethecostsallocabletotheworkcoveredbysuchorderduringworkstoppage.

2.2.Beforethesuspensionorderexpires,theprocuringentityconcernedshalleitherliftsuchorderorterminatetheworkcoveredbythesame.Ifthesuspensionorderislifted,oriftheperiodoftheorderexpires,thesupplierorconsultantshallhavetherighttoresumework.Appropriateadjustmentsshallbemadeinthedeliveryorcontractschedule,orcontractprice,orboth,andthecontractshallbemodifiedaccordingly.

BACK

Page 197: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

3.LiquidatedDamages

3.1.Whenthesupplierfailstosatisfactorilydelivergoodsunderthecontractwithinthespecifieddeliveryschedule,inclusiveofdulygrantedtimeextensions,ifany,thesuppliershallbeliablefordamagesforthedelayandshallpaytheprocuringentityliquidateddamages,notbywayofpenalty,anamountequaltoone-tenth(1/10)ofonepercent(1%)ofthecostofthedelayedgoodsscheduledfordeliveryforeverydayofdelayuntilsuchgoodsarefinallydeliveredandacceptedbytheprocuringentityconcerned.

3.2.Theprocuringentityneednotprovethatithasincurredactualdamagestobeentitledtoliquidateddamages.Suchamountshallbedeductedfromanymoneydueorwhichmaybecomeduetothesupplier,orcollectedfromanysecuritiesorwarrantiespostedbythesupplier,whicheverisconvenienttotheprocuringentityconcerned.Innocaseshallthetotalsumofliquidateddamagesexceedtenpercent(10%)ofthetotalcontractprice,inwhicheventtheprocuringentityconcernedshallautomaticallyrescindthecontractandimposeappropriatesanctionsoverandabovetheliquidateddamagestobepaid.

BACK

Page 198: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

4.AdvancePayment

4.1.InaccordancewithPresidentialDecree14454.2.Allprogresspayments4.3.Asingleadvancepayment4.4.Advancepayment4.5.Forgoodssupplied

BACK

Page 199: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

5.OtherRulesandGuidelines

TherulesandregulationsfortheotheraspectsofcontractimplementationshallbeincludedinthemanualstobeissuedbytheGPPB,suchas,butnotlimitedto,thefollowing:a)IncidentalServices;b)SpareParts;c)DelaysintheSupplier sPerformance;d)Purchaser sResponsibilities;e)Prices;f)Payment;g)TaxesandDuties;h)Subcontracts;i)Standards;j)Packing;k)Insurance;l)Transportation;m)InspectionsandTests;n)PatentRights;o)LimitationsofLiability;p)TerminationforDefault;q)TerminationforInsolvency;r)TerminationforConvenience;ands)Assignment.

BACK

Page 200: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

1.VARIATIONORDERS-CHANGEORDER/EXTRAWORKORDER

1.1.VariationOrders1.2.AChangeOrder1.3.AnExtraWorkOrder1.4.AnycumulativepositiveVariationOrder1.5.InclaimingforanyVariationOrder

BACK

Page 201: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

2.ADDITIONAL/EXTRAWORKCOSTING

2.1.ForVariationOrders,thecontractorshallbepaidforadditionalworkitemswhoseunitpricesshallbederivedbasedonthefollowing:a)Foradditional/extraworksdulycoveredbyChangeOrdersinvolvingworkitemswhichareexactlythesameorsimilartothoseintheoriginalcontract,theapplicableunitpricesofworkitemsoriginalcontractshallbeused.b)Foradditional/extraworksdulycoveredbyExtraWorkOrdersinvolvingnewworkitemsthatarenotintheoriginalcontract,theunitpricesofthenewworkitemsshallbebasedonthedirectunitcostsusedintheoriginalcontract(e.g.,unitcostofcement,rebars,formlumber,laborrate,equipmentrental,etc.).Allnewcomponentsofthenewworkitemshallbefixedprices,providedthesameisacceptabletoboththeGovernmentandthecontractor,andprovidedfurtherthatthedirectunitcostsofnewcomponentsshallbebasedonthecontractor'sestimateasvalidatedbytheprocuringentityconcernedviadocumentedcanvassinaccordancewithexistingrulesandregulations.Thedirectcostofthenewworkitemshallthenbecombinedwiththemark-upfactor(i.e.,taxesandprofit)usedbythecontractorinhisbidtodeterminetheunitpriceofthenewworkitem.

2.2.Requestforpaymentbythecontractorforanyextraworkshallbeaccompaniedbyastatement,withtheapprovedsupportingforms,givingadetailedaccountingandrecordofamountforwhichheclaimspayment.Saidrequestforpaymentshallbeincludedwiththecontractor'sstatementforprogresspayment.

BACK

Page 202: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

3.CONDITIONSUNDERWHICHCONTRACTORISTOSTARTWORKUNDERVARIATIONORDERSANDRECEIVEPAYMENTS

3.1.UndernocircumstancesshallacontractorproceedtocommenceworkunderanyChangeOrderorExtraWorkOrderunlessithasbeenapprovedbytheHeadoftheProcuringEntityorhisdulyauthorizedrepresentative.Exceptionstotheprecedingrulearethefollowing:

a)TheHeadoftheProcuringEntityb)ForaChangeOrderorExtraWorkOrder

BACK

Page 203: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

4.ADVANCEPAYMENT

4.1.Theprocuringentityshall,uponawrittenrequestofthecontractorwhichshallbesubmittedasacontractdocument,makeanadvancepaymenttothecontractorinanamountnotexceedingfifteenpercent(15%)ofthetotalcontractprice,tobemadeinlumpsumor,atthemost,twoinstallmentsaccordingtoaschedulespecifiedintheInstructionstoBiddersandotherrelevantTenderDocuments.

4.2.Theadvancepaymentshallbemadeonlyuponthesubmissiontoandacceptancebytheprocuringentityofanirrevocablestandbyletterofcreditofequivalentvaluefromacommercialbank,abankguaranteeorasuretybondcallableupondemand,issuedbyasuretyorinsurancecompanydulylicensedbytheInsuranceCommissionandconfirmedbytheprocuringentity.

4.3.Theadvancepaymentshallberepaidbythecontractorbydeductingfifteenpercent(15%)fromhisperiodicprogresspaymentsapercentageequaltothepercentageofthetotalcontractpriceusedfortheadvancepayment.

4.4.ThecontractormayreducehisstandbyletterofcreditorguaranteeinstrumentbytheamountsrefundedbytheMonthlyCertificatesintheadvancepayment.

BACK

Page 204: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

5.PROGRESSPAYMENT

5.1.Onceamonth,thecontractormaysubmitastatementofworkaccomplished(SWA)orprogressbillingandcorrespondingrequestforprogresspaymentforworkaccomplished.TheSWAshouldshowtheamountswhichthecontractorconsidersitselftobeentitledtouptotheendofthemonth,tocover(a)thecumulativevalueoftheworksitexecutedtodate,basedontheitemsintheBillofQuantities,and(b)adjustmentsmadeforapprovedvariationordersexecuted.

5.2.Theprocuringentitysrepresentative/projectengineershallcheckthecontractor smonthlySWAandcertifytheamounttobepaidtothecontractorasprogresspayment.ExceptasotherwisestipulatedintheInstructiontoBidders,materialsandequipmentdeliveredonthesitebutnotcompletelyputinplaceshallnotbeincludedforpayment.

5.3.Theprocuringentityshalldeductthefollowingfromthecertifiedgrossamountstobepaidtothecontractorasprogresspayment:

a)Cumulativevalueoftheworkpreviouslycertifiedandpaidfor.b)Portionoftheadvancepaymenttoberecoupedforthemonth.c)Retentionmoneyinaccordancewiththeconditionofcontract.d)Amounttocoverthirdpartyliabilities.e)Amounttocoveruncorrecteddiscovereddefectsintheworks.

BACK

Page 205: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

6.RETENTIONMONEY

6.1.Progresspaymentsaresubjecttoretentionoftenpercent(10%)referredtoasthe"retentionmoney."Suchretentionshallbebasedonthetotalamountduetothecontractorpriortoanydeductionandshallberetainedfromeveryprogresspaymentuntilfiftypercent(50%)ofthevalueofworks,asdeterminedbytheprocuringentity,arecompleted.If,afterfiftypercent(50%)completion,theworkissatisfactorilydoneandonschedule,noadditionalretentionshallbemade;otherwise,thetenpercent(10%)retentionshallbeimposed.

6.2.Thetotal"retentionmoney"shallbedueforreleaseuponfinalacceptanceoftheworks.Thecontractormay,however,requestthesubstitutionoftheretentionmoneyforeachprogressbillingwithirrevocablestandbylettersofcreditoffromacommercialbank,bankguaranteesorsuretybondscallableondemand,ofamountsequivalenttotheretentionmoneysubstitutedforandacceptabletoGovernment,providedthattheprojectisonscheduleandissatisfactorilyundertaken.Otherwise,thetenpercent(10%)retentionshallbemade.Saidirrevocablestandbylettersofcredit,bankguaranteesand/orsuretybonds,tobepostedinfavoroftheGovernmentshallbevalidforadurationtobedeterminedbytheconcernedimplementingoffice/agencyorprocuringentityandwillanswerforthepurposeforwhichthetenpercent(10%)retentionisintended,i.e.,tocoveruncorrecteddiscovereddefectsandthirdpartyliabilities.

BACK

Page 206: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

7.CONTRACTCOMPLETION

Oncetheprojectreachesanaccomplishmentofninetyfive(95%)ofthetotalcontractamount,theprocuringentitymaycreateaninspectorateteamtomakepreliminaryinspectionandsubmitapunch-listtothecontractorinpreparationforthefinalturnoveroftheproject.Saidpunch-listwillcontain,amongothers,theremainingworks,workdeficienciesfornecessarycorrections,andthespecificduration/timetofullycompletetheprojectconsideringtheapprovedremainingcontracttime.This,however,shallnotprecludetheprocuringentity'sclaimforliquidateddamages.

BACK

Page 207: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.LIQUIDATEDDAMAGES

8.1.Wherethecontractorrefusesorfails8.2.Aprojectoraportionthereofmaybedeemed8.3.Tobeentitledtosuchliquidateddamages8.4.Incasethatthedelayinthecompletionofthework8.5.Innocasehowever,shallthetotalsumofliquidateddamages8.6.Forterminatedcontracts

BACK

Page 208: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

9.SUSPENSIONOFWORK

9.1.Theprocuringentity9.2.Thecontractor9.3.Incaseoftotalsuspension

BACK

Page 209: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

10.EXTENSIONOFCONTRACTTIME

10.1.Shouldtheamountofadditionalwork10.2.Noextensionofcontracttimeshallbegrantedthecontractor10.3.Extensionofcontracttimemaybegrantedonlywhentheaffectedactivities10.4.Noextensionofcontracttimeshallbegrantedwhenthereasongiventosupport10.5.Extensionofcontracttimeshallbegrantedforrainy/unworkabledays

BACK

Page 210: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

11.ACCREDITATIONOFTESTINGLABORATORIES

11.1.Tohelpensurethequalityofmaterialsbeingusedininfrastructureprojects,theBureauofResearchandStandards(BRS)oftheDPWH,DepartmentofScienceandTechnology(DOST),orDepartmentofTradeandIndustry(DTI)shallaccredit,inaccordancewithindustryguidelines,thetestinglaboratorieswhoseservicesareengagedortobeengagedininfrastructureprojects.Allgovernmentinfrastructureprojectownersmustacceptresultsofmaterialtest(s)comingonlyfromDOST/BRSaccreditedlaboratories.

BACK

Page 211: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

12.EVALUATIONOFCONTRACTORSPERFORMANCE

12.1.SubjectandScopeAllProcuringEntities12.2.EvaluationGuidelines12.3.ImplementationMechanism12.4.SubmissionandDissemination12.5.UtilizationofEvaluationResults

BACK

Page 212: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

13.OTHERRULESANDGUIDELINESTherulesandregulationsfortheotheraspectsofcontractimplementationshallbeincludedinthemanualstobeissuedbytheGPPB,suchas,butnotlimitedto,thefollowing:a)Sub-contracting;b)InterferencewithTrafficandAdjoiningProperties;c)ClearanceofProjectSiteofObstruction;d)InspectionandTesting;e)Daywork;f)MeasurementofWorks;andg)OtherImplementationAspects.

BACK

Page 213: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

1.SCOPEANDAPPLICATION

TheseguidelinesshallgoverntheprocurementandimplementationofcontractsfordesignandbuildinfrastructureprojectsandshallsupplementapplicableprovisionsofRepublicActNo.9184(RA9184)anditsRevisedImplementingRulesandRegulations(IRR)inparticularSection17.6andAnnexE.

BACK

Page 214: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

2.PURPOSE

Theseguidelinesareformulatedtodeterminetheconditionsfortheuseofthedesignandbuildschemeforinfrastructureprojectsandtheproceduresfortheimplementationthereof.

BACK

Page 215: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

3.GUIDINGPRINCIPLESTheprocuringentity,priortoresortingtothedesignandbuildscheme,shouldconsiderthefollowingadvantagesanddisadvantagesofsaidscheme:

3.1.Advantages3.2.Disadvantages

BACK

Page 216: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

4.DEFINITIONOFTERMS

a.ApprovedBudgetfortheContract(ABC)b.BiddingDocumentsforDesignandBuildSchemec.ConceptualDesignd.DesignandBuildProjectse.PerformanceSpecificationsandParametersf.PreliminaryInvestigationsg.PreliminarySurveyandMappingh.ProjectDescriptioni.UtilityLocations

BACK

Page 217: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

5.CONDITIONSFORTHEUSEOFTHEDESIGNANDBUILDSCHEME

5.1.TheDesignandBuildscheme5.2.Alldesignandbuildprojects

BACK

Page 218: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

6.CREATIONOFDESIGNandBUILDCOMMITTEE

TheprocuringentitymaycreateaDesignandBuildCommittee(DBC)composedofhighlytechnicalpersonnelexperiencedinthefieldofarchitecture,engineeringandconstructionintheparticulartypeofprojecttobebid.TheDBCshallassisttheprojectmanagementoffice(PMO)inthepreparationoftheconceptualdesignandperformancespecificationsandparameters,reviewofdetailedengineeringdesignandsupervisionoftheproject.Itshall,likewise,assisttheBidsandAwardsCommittee(BAC)andtheTechnicalWorkingGroup(TWG)intheevaluationoftechnicalproposalsinaccordancewiththecriteriasetintheBiddingDocuments.

BACK

Page 219: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

7.PRELIMINARYDESIGNANDCONSTRUCTIONSTUDIES

NobiddingandawardofdesignandbuildcontractsshallbemadeunlesstherequiredpreliminarydesignandconstructionstudieshavebeensufficientlycarriedoutanddulyapprovedbytheHeadoftheProcuringEntitythatshallinclude,amongothers,thefollowing:

i.ProjectDescriptionii.ConceptualDesigniii.PerformanceSpecificationsandParametersiv.PreliminarySurveyandMappingv.PreliminaryInvestigationsvi.UtilityLocationsvii.ApprovedBudgetfortheContractviii.ProposedDesignandConstructionScheduleix.MinimumrequirementsforaConstructionSafetyandHealthProgramfortheprojectbeingconsideredx.Tender/BiddingDocuments,includingInstructionstoBiddersandConditionsofContract

Theabovedataareforreferenceonly.Theprocuringentitydoesnotguaranteethatthesedataarefullycorrect,uptodate,andapplicabletotheprojectathand.Thecontractorisresponsiblefortheaccuracyandapplicabilityofalldata,includingtheabove,thatitwilluseinitsdesignandbuildproposalandservices.Theacquisitionofright-of-wayandtheconductofeminentdomainproceedingsshallstillbetheresponsibilityoftheprocuringentity,whichshallincludeapreliminarybudgetforthispurpose.

BACK

Page 220: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.DETAILEDENGINEERINGREQUIREMENTS

8.1.Uponawardofthedesignandbuildcontract,thewinningbiddershallberesponsibleforthepreparationandsubmissionofallnecessarydetailedengineeringinvestigations,surveysanddesignsinaccordancewiththeprovisionsofAnnexAofthisIRR(withtheexceptionoftheBiddingDocumentsandtheABC).

8.2.Theprocuringentityshallensurethatallthenecessaryscheduleswithregardtothesubmission,confirmationandapprovalofthedetailedengineeringdesignandthedetailsoftheconstructionmethodsandproceduresshallbeincludedinthecontractdocuments.

8.3.Theprocuringentityshallreview,orderrectification,andapproveordisapproveforimplementationonly-thesubmittedplanswithintheseschedules.Allinstructionsforrectificationshallbeinwritingstatingthereasonsforsuchrectification.Thedesignandbuildcontractorshallbesolelyresponsiblefortheintegrityofthedetailedengineeringdesignandtheperformanceofthestructureirrespectiveoftheapproval/confirmationbytheprocuringentity.

BACK

Page 221: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

9.ELIGIBILITYREQUIREMENTS

9.1.TheeligibilityrequirementsforDesignandBuildinfrastructureprojectsshallcomplywiththeapplicableprovisionsofSections23-24ofIRR.

9.2.Amodifiedsetofrequirementsintegratingeligibilitydocumentsandcriteriaforinfrastructureprojectsandconsultingservicesshallbeadopted,asfollows:

i.ClassADocumentsii.EligibilityCriteria

BACK

Page 222: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

10.SUBMISSIONANDRECEIPTOFBIDS

10.1.Inthesubmissionofbids,thefirstenvelope10.2.Thesecondenvelope

BACK

Page 223: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

11.BIDEVALUATION

Forthedetailedevaluationofthedesignandbuildproposalsatwo-stepprocedureshallbeadoptedbytheBAC,whichmaybeundertakenwiththeassistanceoftheDBC.

11.1.First-StepProcedure11.2.Second-StepProcedure

BACK

Page 224: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

12.POST-QUALIFICATIONandAWARDOFTHECONTRACT

12.1.TheLCBshallbesubjecttopost-qualificationinaccordancewithSection34,RuleXofthisIRRtodetermineitsresponsivenesstotheeligibilityandbidrequirements.Ifafterpost-qualificationtheLowestCalculatedBidisdeterminedtobepost-qualifieditshallbeconsideredtheLowestCalculatedandResponsiveBid(LCRB)andthecontractshallbeawardedtothebidder.Incaseofpost-disqualificationoftheLCB,theprocedureunderSection34shallalsobefollowed.

12.2.TheHeadoftheProcuringEntityshallapproveordisapprovetherecommendationsoftheBACwithinaperiodnotexceedingseven(7)calendardaysfromthedeterminationanddeclarationbytheBACoftheLCRB.

12.3.TheHeadoftheProcuringEntityconcernedshallawardthecontracttothesaidbidderpursuanttotheprovisionsofSection37,RuleXIofthisIRR.

BACK

Page 225: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

13.CONTRACTIMPLEMENTATION

13.1.Noworksshallcommence13.2.Thecontractorshallberesponsible13.3.TheContractorshallsubmitadetailedprogram13.4.Anyerrors,omissions,inconsistencies,inadequacies13.5.Asarule,changesindesignandconstructionrequirements13.6.Thecontractdocuments13.7.Thecontractorshallbeentitled13.8.Theprocuringentityshalldefinethequalitycontrol13.9.Thecontractorshallprovideallnecessaryequipment13.10.Alldesignandbuildprojects13.11.Thecontractorshallbeheldliablefordesign

BACK

Page 226: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

14.AMENDMENTSANDFORMS

Intheimplementationoftheseguidelines,theGPPBmayissueadditionalguidelinesorintroducemodificationstheretothroughtheamendmentofitsspecificprovisionsastheneedarises,aswellas,formulate,approveanddisseminatestandardBiddingDocuments,formsandevaluationdocuments,whenevernecessary.

BACK

Page 227: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

(i)theheadoftheagencyorbody,orhisdulyauthorizedofficial,forNGAsandtheconstitutionalcommissionsoroffices,andbranchesofgovernment;

t)HeadoftheProcuringEntity

Page 228: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

(ii)thegoverningboardoritsdulyauthorizedofficial,forGOCCs,GFIsandSUCs;or

t)HeadoftheProcuringEntity

Page 229: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

(iii)thelocalchiefexecutive,forLGUs:Provided,however,Thatinanagency,department,orofficewheretheprocurementisdecentralized,theheadofeachdecentralizedunitshallbeconsideredastheHeadoftheProcuringEntity,subjecttothelimitationsandauthoritydelegatedbytheheadoftheagency,department,oroffice.

HeadoftheProcuringEntity

Page 230: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

a)ComplywiththeprovisionsoftheActandthisIRR,andR.A.8792,otherwiseknownasthe"ElectronicCommerceAct;"

8.1.2Totakeadvantageofthesignificantbuilt-inefficienciesofthePhilGEPS

Page 231: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

b)LinkedtothePhilGEPS,particularlywithregardtothepostingofallbidopportunitiesandawards;

8.1.2Totakeadvantageofthesignificantbuilt-inefficienciesofthePhilGEPS

Page 232: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

c)Allowparallelmanualsubmissionofbidstotheprocuringentity;

8.1.2Totakeadvantageofthesignificantbuilt-inefficienciesofthePhilGEPS

Page 233: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

d)EnsurethattheBACshallhavecompletecontrolofthebiddingprocess,andthattheBAC'ssoleauthoritytoopenbidsisstrictlyobserved;

8.1.2Totakeadvantageofthesignificantbuilt-inefficienciesofthePhilGEPS

Page 234: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

e)Itssystemmustbevirus-resilientandmustprovidesufficientsecuritywhichisatleastequivalenttothatemployedbythePhilGEPS,suchas,butnotlimitedto,firewallandencryptiondevices;

8.1.2Totakeadvantageofthesignificantbuilt-inefficienciesofthePhilGEPS

Page 235: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

f)Mustprovidefortheuseofelectronicsignaturesandothercurrentelectronicauthenticationdevices;

8.1.2Totakeadvantageofthesignificantbuilt-inefficienciesofthePhilGEPS

Page 236: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

g)Musthavesufficientredundantback-upfacilities;

8.1.2Totakeadvantageofthesignificantbuilt-inefficienciesofthePhilGEPS

Page 237: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

h)Musthaveprovisionsforlinkagetotheprocuringentity'sFinancialManagementInformationSystem(FMIS),LogisticsManagementSystems,andotherinternalinformationsystemsthatmayinteractwiththeprocurementprocess;and

8.1.2Totakeadvantageofthesignificantbuilt-inefficienciesofthePhilGEPS

Page 238: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)Electronicpaymentfacilities,ifused,shallcomplywithalllaws,rulesandregulationsissuedbytheGovernment.

8.1.2Totakeadvantageofthesignificantbuilt-inefficienciesofthePhilGEPS

Page 239: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

a)ThePhilGEPSshallhaveacentralizedelectronicdatabaseofallmanufacturers,suppliers,distributors,contractorsandconsultantsregisteredunderthesystem.

8.2.2.RegistryofManufacturers,Suppliers,Distributors,ContractorsandConsultants

Page 240: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

b)RegistrationshallentailthesubmissionoftherequirementsspecifiedbythePS-DBM.Submissionoftheserequirementsmaybedoneon-lineatthePhilGEPSwebsiteorphysicallyatthePhilGEPSoffice.Registrationshallbeeffectiveforoneyearandmayberenewed,providedthatthemanufacturer,supplier,distributor,contractororconsultantconcernedmaintainsitsregistrationcurrentandupdatedatleastonceayear,ormorefrequentlywhenneeded.

8.2.2.RegistryofManufacturers,Suppliers,Distributors,ContractorsandConsultants

Page 241: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

c)Manufacturers,suppliers,distributors,contractorsandconsultantsapplyingforregistrationmustalsoindicatetheiraccountnumberwithabankdulylicensedbytheBangkoSentralngPilipinas(BSP)tofacilitatepaymentaswellasthepostingofbidandperformancesecurity,whenapplicable.Anyinformationsubmittedinconnectionwiththissubsectionshallbekeptconfidential.(a)

8.2.2.RegistryofManufacturers,Suppliers,Distributors,ContractorsandConsultants

Page 242: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

d)ThePhilGEPSshalldenyregistrationtoorexcludefromtheregistryanypartythatisfoundtohavewillfullymisrepresentedanyoftheinformationprovidedintheapplicationforregistrationorwhoisinthe"blacklist"oftheGovernmentoranyofitsProcuringEntitiesinaccordancewithSection69.4ofthisIRR,includingforeigngovernment/foreignorinternationalfinancinginstitutionwhoseblacklistingruleshavebeenrecognizedbytheGPPB.

8.2.2.RegistryofManufacturers,Suppliers,Distributors,ContractorsandConsultants

Page 243: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

e)Amanufacturer,supplier,distributor,contractororconsultantapplyingforregistrationshallberequiredtoprovideane-mailaddresstowhichallcommunicationsfromtheBACandtheprocuringentityshallbesent.Thee-mailaddressprovidedshallbeconsideredassuchapplicant'sinformationsystemforpurposesofreckoningthedateofsendingorreceiptofelectronicmessagesordocuments.

8.2.2.RegistryofManufacturers,Suppliers,Distributors,ContractorsandConsultants

Page 244: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

f)Registeredmanufacturers,suppliers,distributors,contractorsandconsultantsshallsecureadigitalcertificatefromthegovernment-accreditedcertificationauthoritytobeabletoparticipateintheprocurementactivitiesofthePhilGEPS.(a)

8.2.2.RegistryofManufacturers,Suppliers,Distributors,ContractorsandConsultants

Page 245: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

g)RegistrationwiththePhilGEPSisnotanaccreditationandthusnottantamounttoafindingofeligibility,norisitaguarantythatamanufacturer,supplier,distributor,contractororconsultantmayparticipateinapublicbiddingwithoutfirstbeingdeterminedtobeeligibleforthatparticularpublicbidding.

8.2.2.RegistryofManufacturers,Suppliers,Distributors,ContractorsandConsultants

Page 246: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

a)ThePhilGEPSshallhaveacentralizedelectroniccatalogueofcommonandnon-commonusegoods,supplies,materialsandequipment.

8.2.3.TheElectronicCatalogue

Page 247: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

b)ProcuringEntitiesshallprocurecommon-usegoods,supplies,materialsandequipmentfromtheElectronicCatalogueinthePhilGEPS.TobeabletousethePhilGEPS,ProcuringEntitiesshallberequiredtoregisteranddesignatetheofficialsorpersonnelauthorizedtotransactwithandoperatethePhilGEPSfromsuchProcuringEntities'terminals.

8.2.3.TheElectronicCatalogue

Page 248: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

c)ProcuringEntitieswithoutinternetaccessmayavailofthePhilGEPSPublicAccessTerminalswhichshallbeinstalledatDBM-designatedlocationsintheprovincesandinMetroManila:Provided,however,ThattheyshallcomplywithSection8.3ofthisIRR.

8.2.3.TheElectronicCatalogue

Page 249: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

d)TheElectronicCataloguemayalsofeaturenon-commonuseitemsthatmaybeprocureddirectlyandwithoutpublicbiddingbyProcuringEntitiesfromsuppliersthroughthePhilGEPSVirtualStore:Provided,however,ThatforanitemtobecarriedintheElectronicCatalogueforthispurpose,thesupplierthereofmusthavebeendeterminedastheLowestCalculatedResponsiveBidderinapreviousbiddingconductedbyPS-DBMorbyaprocuringentityforPS-DBM:Provided,further,ThatsuchitemwillbefeaturedintheElectronicCatalogueforamaximumperiodofsix(6)monthsunlessanothersupplieroffersapricelowerbyatleastfivepercent(5%)andsuchsupplierisdeterminedbythePS-DBMorbytheprocuringentitythatconductedthepreviousbiddingforPS-DBMtomeettheeligibilityandbiddingrequirementsfortheitem,inwhichcasetheitemfromthelattersupplierwillbethatfeaturedintheElectronicCataloguefortheremainderofthesix(6)-monthperiod.(a)

8.2.3.TheElectronicCatalogue

Page 250: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.2.4.1.VirtualStoreThePhilGEPSmayhaveafeaturethatwillenabletheorderingofcommon-useandnon-commonuseitemsonlinecalledavirtualstore.Thevirtualstoreshallbeopenonlytoregisteredprocuringentitiesandmaynotbeaccessedbysuppliers.

8.2.4.AdditionalFeatures

Page 251: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.2.4.2.ElectronicPaymentThePhilGEPSmaysupporte-paymentfunctionstopayforgoodspurchasedthroughtheVirtualStoretomanagethegenerationofpurchaseordersandthepaymentofbidsprocessedthroughthesystem.(a)ThefocusofthisfeatureistofacilitatetheelectronictransferoffundsfromPS-DBMtoandfromprocuringentitiesandsuppliers,andfromprocuringentitiestosuppliers,forbidsmanageddirectlybytheprocuringentity.Thesystemshall:a)Generatepurchaseordersfromabidnotice,awardnoticeorcontract;

b)Supportapprovalprocessforpurchaseordersbeforeanypaymentorfundtransferisprocessed;

c)Haveaprocesstosubmitrequestforpaymentupondeliveryofgoodsand/orservicesandthecompletionoftheapprovalprocess;and

d)Havetheabilitytointerfacewiththedesignatedbankoftheprocuringentityandsupplierstosupporttheelectronictransferoffunds.

8.2.4.AdditionalFeatures

Page 252: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.2.4.3.ElectronicBidSubmissionThePhilGEPSmaysupporttheimplementationofe-Bidsubmissionprocesses,whichincludescreationofelectronicbidforms,creationofbidbox,deliveryofbidsubmissions,notificationtosupplierofreceiptofbids,bidreceivingandelectronicbidevaluation.Thisfacilityshallcoveralltypesofprocurementforgoods,infrastructureprojectsandconsultingservices.

8.2.4.AdditionalFeatures

Page 253: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.5.1.1.Thefollowingshallbeeligibletoparticipateinthebiddingforthesupplyofgoods:a)DulylicensedFilipinocitizens/soleproprietorships;

b)PartnershipsdulyorganizedunderthelawsofthePhilippinesandofwhichatleastsixtypercent(60%)oftheinterestbelongstocitizensofthePhilippines;

c)CorporationsdulyorganizedunderthelawsofthePhilippines,andofwhichatleastsixtypercent(60%)oftheoutstandingcapitalstockbelongstocitizensofthePhilippines;

d)CooperativesdulyorganizedunderthelawsofthePhilippines,andofwhichatleastsixtypercent(60%)belongstocitizensofthePhilippines;or

e)Persons/entitiesformingthemselvesintoajointventure,i.e.,agroupoftwo(2)ormorepersons/entitiesthatintendtobejointlyandseverallyresponsibleorliableforaparticularcontract:Provided,however,ThatFilipinoownershiporinterestofthejointventureconcernedshallbeatleastsixtypercent(60%).Forthispurpose,FilipinoownershiporinterestshallbebasedonthecontributionsofeachofthemembersofthejointventureasspecifiedintheirJVA.(a)

23.5.1.Fortheprocurementofgoods:

Page 254: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.5.1.2.Foreignbiddersmaybeeligibletoparticipateunderanyofthefollowingcircumstances:a)WhenprovidedforunderanyTreatyorInternationalorExecutiveAgreementasprovidedinSection4oftheActandthisIRR;

b)Whentheforeignsupplierisacitizen,corporationorassociationofacountry,includedinAnnex"I"tobeissuedbytheGPPB,thelawsorregulationsofwhichgrantreciprocalrightsorprivilegestocitizens,corporationsorassociationsofthePhilippines;

c)Whenthegoodssoughttobeprocuredarenotavailablefromlocalsuppliers;ord)Whenthereisaneedtopreventsituationsthatdefeatcompetitionorrestraintrade.TheGPPBshallpromulgatethenecessaryguidelinesforthisprovision.(a)

23.5.1.Fortheprocurementofgoods:

Page 255: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.5.1.3.Theprospectivebiddermusthavecompleted,withintheperiodspecifiedintheInvitationtoBid,asinglecontractthatissimilartothecontracttobebid,andwhosevalue,adjustedtocurrentpricesusingtheNationalStatisticsOffice(NSO)consumerpriceindices,mustbeatleastfiftypercent(50%)oftheABC.However,inthecaseofExpendableSupplies,saidsinglecontractmustbeatleasttwentyfivepercent(25%)oftheABC.If,attheoutsetandafterconductingmarketresearch,theprocuringentitycanalreadydeterminethatimposingthesamewilllikelyresultto:(a)failureofbidding,or(b)monopolythatwilldefeatthepurposeofpublicbidding,theprocuringentity,inlieuoftheabove,mayrequirethefollowing:i)Theprospectivebiddershouldhavecompletedatleasttwo(2)similarcontractsandtheaggregatecontractamountsshouldbeequivalenttoatleastthepercentageoftheABCasrequiredabove;and

ii)ThelargestofthesesimilarcontractsmustbeequivalenttoatleasthalfofthepercentageoftheABCasrequiredabove.Forthispurpose,thesimilarcontractsmentionedunder(i)and(ii)abovemusthavebeencompletedwithintheperiodspecifiedintheInvitationtoBid.TheprocuringentitymayclarifyintheBiddingDocumentsthedefinitionordescriptionofwhatitconsiderstobeasimilarproject.(a)

23.5.1.Fortheprocurementofgoods:

Page 256: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.5.1.4.IftheprospectivebiddersubmitsacomputationofitsNFCC,theNFCCmustbeatleastequaltotheABCtobebid,calculatedasfollows:NFCC=[(Currentassetsminuscurrentliabilities)(K)]minusthevalueofalloutstandingoruncompletedportionsoftheprojectsunderongoingcontracts,includingawardedcontractsyettobestartedcoincidingwiththecontracttobebid.Where:K=10foracontractdurationofoneyearorless,15foracontractdurationofmorethanoneyearuptotwoyears,and20foracontractdurationofmorethantwoyears.IftheprospectivebiddersubmitsaCLC,theCLCmustbeatleastequaltotenpercent(10%)oftheABCtobebid.IftheCLCisissuedbyaforeignUniversalorCommercialBank,itshallbeconfirmedorauthenticatedbyaUniversalorCommercialBank.ForbiddingsconductedbyLGUs,theprospectivebiddermayalsosubmitCLCfromotherbankscertifiedbytheBSPasauthorizedtoissuesuchfinancialinstrument.(a)

23.5.1.Fortheprocurementofgoods:

Page 257: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.5.2.1.Thefollowingpersons/entitiesshallbeallowedtoparticipateinthebiddingforinfrastructureprojects:a)DulylicensedFilipinocitizens/soleproprietorships;

b)PartnershipsdulyorganizedunderthelawsofthePhilippinesandofwhichatleastseventy-fivepercent(75%)oftheinterestbelongstocitizensofthePhilippines;

c)CorporationsdulyorganizedunderthelawsofthePhilippines,andofwhichatleastseventy-fivepercent(75%)oftheoutstandingcapitalstockbelongstocitizensofthePhilippines;

d)CooperativesdulyorganizedunderthelawsofthePhilippines,andofwhichatleastseventypercent(75%)belongstocitizensofthePhilippines;or

e)Persons/entitiesformingthemselvesintoajointventure,i.e.,agroupoftwo(2)ormorepersons/entitiesthatintendtobejointlyandseverallyresponsibleorliableforaparticularcontract:Provided,however,That,inaccordancewithLetterofInstructionsNo.630(LOI630),Filipinoownershiporinterestofthejointventureconcernedshallbeatleastseventy-fivepercent(75%):Provided,further,ThatjointventuresinwhichFilipinoownershiporinterestislessthanseventy-fivepercent(75%)maybeeligiblewherethestructurestobebuiltrequiretheapplicationoftechniquesand/ortechnologieswhicharenotadequatelypossessedbyaperson/entitymeetingtheseventy-fivepercent(75%)Filipinoownershiprequirement:Provided,finally,Thatinthelattercase,Filipinoownershiporinterestshallnotbelessthantwenty-fivepercent(25%).Forthispurpose,FilipinoownershiporinterestshallbebasedonthecontributionsofeachofthemembersofthejointventureasspecifiedintheirJVA.(a)

23.5.2.Fortheprocurementofinfrastructureprojects:

Page 258: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.5.2.2.ForeignbiddersmaybeeligibletoparticipateintheprocurementofinfrastructureprojectswhenprovidedforunderanyTreatyorInternationalorExecutiveAgreementasprovidedinSection4oftheActandthisIRR.(n)

23.5.2.Fortheprocurementofinfrastructureprojects:

Page 259: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.5.2.3.InaccordancewithR.A.4566,entitledAnActCreatingthePhilippineLicensingBoardforContractors,PrescribingitsPowers,DutiesandFunctions,ProvidingFundsTherefor,andforOtherPurposes,thepersons/entitiesenumeratedinSection23.5.1.1ofthisIRRmayparticipateinpublicbiddingifhehasbeenissuedalicensebythePCABtoengageoractasacontractor.(a)

23.5.2.Fortheprocurementofinfrastructureprojects:

Page 260: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.5.2.4.TheConstructorsPerformanceEvaluationSummary(CPES)ratingand/orcertificateofcompletionandowner sacceptanceofthecontractmustbesatisfactory.

23.5.2.Fortheprocurementofinfrastructureprojects:

Page 261: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.5.2.5.Theprospectivebiddermusthaveanexperienceofhavingcompleted,withinaperiodoften(10)yearsfromthedateofsubmissionandreceiptofbids,atleastone(1)contractthatissimilartothecontracttobebid,andwhosevalue,adjustedtocurrentpricesusingtheNSOconsumerpriceindices,mustbeatleastfiftypercent(50%)oftheABCtobebid:Provided,however,ThatcontractorsunderSmallAandSmallBcategorieswithoutsimilarexperienceonthecontracttobebidmaybeallowedtobidifthecostofsuchcontractisnotmorethanfiftypercent(50%)oftheAllowableRangeofContractCost(ARCC)oftheirregistrationbasedontheguidelinesasprescribedbythePCAB.ForForeign-fundedProcurement,theGOPandtheforeigngovernment/foreignorinternationalfinancinginstitutionmayagreeonanothertrackrecordrequirement.Moreover,acontractshallbeconsideredsimilar tothecontracttobebidifithasthesamemajorcategoriesofwork.(a)

23.5.2.Fortheprocurementofinfrastructureprojects:

Page 262: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

23.5.2.6.IftheprospectivebiddersubmitsacomputationofitsNFCC,theNFCCmustbeatleastequaltotheABCtobebid,calculatedasfollows:NFCC=[(Currentassetsminuscurrentliabilities)(K)]minusthevalueofalloutstandingoruncompletedportionsoftheprojectsunderongoingcontracts,includingawardedcontractsyettobestartedcoincidingwiththecontracttobebid.Where:K=10foracontractdurationofoneyearorless,15foracontractdurationofmorethanoneyearuptotwoyears,and20foracontractdurationofmorethantwoyears.IftheprospectivebiddersubmitsaCLC,theCLCmustbeatleastequaltotenpercent(10%)oftheABCtobebid.IftheCLCisissuedbyaforeignUniversalorCommercialBank,itshallbeconfirmedorauthenticatedbyaUniversalorCommercialBank.ForbiddingsconductedbyLGUs,theprospectivebiddermayalsosubmitCLCfromotherbankscertifiedbytheBSPasauthorizedtoissuesuchfinancialinstrument.(a)

23.5.2.Fortheprocurementofinfrastructureprojects:

Page 263: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

24.4.3.1.TheregistrysystemshallcontaintheforegoingClassAdocumentswhichshouldbemaintainedcurrentandupdatedbythebidderconcernedatleastonceayearormorefrequentlywhenneeded.(a)

24.4.3.Tofacilitatedeterminationofeligibility

Page 264: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

24.4.3.2.AbidderwhomaintainsacurrentandupdatedfileofhisClassADocumentsshallbeissuedacertificationbytheBACtothateffect,whichcertificationmaybesubmittedtotheprocuringentityconcernedinlieuoftheforegoingClassAdocuments.(a)

24.4.3.Tofacilitatedeterminationofeligibility

Page 265: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

24.4.3.3.IftheprocuringentitymaintainsaregistrysystemusingthePhilGEPSoritsownelectronicsystem,aprospectivebidder,whetherornotdulyregisteredineithersystem,shallsubmitawrittenletterofintentand/oritsapplicationforeligibilityandlatestClassAdocuments,totheBAConorbeforethedeadlinespecifiedintheBiddingDocumentswhichshallinnocasebelaterthanthedateforthesubmissionandreceiptofbids.Anyapplicationforeligibilityorupdatessubmittedafterthedeadlineforthesubmissionoftheletterofintentshallnotbeconsideredforthebiddingathand.(a)

24.4.3.Tofacilitatedeterminationofeligibility

Page 266: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)Atwo-stageprocedureshallbeadoptedwherebyeachconsultantshallberequiredtosubmithistechnicalandfinancialproposalssimultaneouslyinseparatesealedenvelopes.

33.2.1.TheBACshallconductadetailedevaluation

Page 267: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ii)Afterreceiptofbids,thetechnicalproposalsshallfirstbeopenedandevaluated,inaccordancewithSection33.2.2ofthisIRR.TheBACshallranktheconsultantsindescendingorderbasedonthenumericalratingsoftheirtechnicalproposalsandidentifytheHighestRatedBid:Provided,however,thattheHighestRatedBidshallpasstheminimumscoreindicatedintheBiddingDocuments.

33.2.1.TheBACshallconductadetailedevaluation

Page 268: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iii)TheHeadoftheProcuringEntityshallapproveordisapprovetherecommendationsoftheBACwithintwo(2)calendardaysafterreceiptoftheresultsoftheevaluationfromtheBAC.

33.2.1.TheBACshallconductadetailedevaluation

Page 269: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iv)AfterapprovalbytheHeadoftheProcuringEntityoftheHighestRatedBid,itsfinancialproposalshallthenbeopened.TheBACshall,withinthree(3)calendardays,notifyandinvitetheconsultantwiththeHighestRatedBidfortheopeningoffinancialproposalforthepurposeofconductingnegotiationswiththesaidconsultant.Intheletterofnotification,theBACshallinformtheconsultantoftheissuesinthetechnicalproposaltheBACmaywishtoclarifyduringnegotiations.

33.2.1.TheBACshallconductadetailedevaluation

Page 270: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

v)NegotiationsshallbeinaccordancewithSection33.2.5ofthisIRR,providedthattheamountindicatedinthefinancialenvelopeshallbemadeasthebasisfornegotiationsandthetotalcontractamountshallnotexceedtheamountindicatedintheenvelopeandtheapprovedbudgetforthecontractasstatedintheBiddingDocuments.(a)

33.2.1.TheBACshallconductadetailedevaluation

Page 271: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)Thetechnicalproposaltogetherwiththefinancialproposalshallbeconsideredintheevaluationofconsultants.ThetechnicalproposalsshallbeevaluatedfirstusingthecriteriainSection33.2.2ofthisIRR.Thefinancialproposalsoftheconsultantswhomeettheminimumtechnicalscoreshallthenbeopened.

33.2.1.TheBACshallconductadetailedevaluation

Page 272: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ii)Thefinancialandtechnicalproposalsshallbegivencorrespondingweightswiththefinancialproposalgivenaminimumweightoffifteenpercent(15%)uptoamaximumoffortypercent(40%).Theweightofthetechnicalcriteriashallbeadjustedaccordinglysuchthattheirtotalweightinpercenttogetherwiththeweightgiventothefinancialproposalshalladdtoonehundredpercent(100%).TheexactweightsshallbeapprovedbytheHeadoftheProcuringEntityupontherecommendationoftheBACandindicatedintheBiddingDocuments.TheBACshallranktheconsultantsindescendingorderbasedonthecombinednumericalratingsoftheirtechnicalandfinancialproposalsandidentifytheHighestRatedBid.

33.2.1.TheBACshallconductadetailedevaluation

Page 273: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iii)TheHeadoftheProcuringEntityshallapproveordisapprovetherecommendationsoftheBACwithintwo(2)calendardaysafterreceiptoftheresultsoftheevaluationfromtheBAC.

33.2.1.TheBACshallconductadetailedevaluation

Page 274: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

iv)AfterapprovalbytheHeadoftheProcuringEntityoftheHighestRatedBid,theBACshall,withinthree(3)calendardays,notifyandinvitetheconsultantwiththeHighestRatedBidfornegotiationinaccordancewithSection33.2.5ofthisIRR,exceptforitem(e)thereof.(a)

33.2.1.TheBACshallconductadetailedevaluation

Page 275: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)ValidJVA,ifapplicable,withinten(10)calendardaysfromreceiptbythebidderofthenoticefromtheBACthatthebidderhastheLowestCalculatedResponsiveBidorHighestRatedResponsiveBid,asthecasemaybe;or

37.1.4.NotwithstandingtheissuanceoftheNoticeofAward

Page 276: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ii)Inthecaseofinfrastructureprojects,validPCABlicenseandregistrationforthetypeandcostofthecontracttobebidforforeignbidders,withinthirty(30)calendardaysfromreceiptbythebidderofthenoticefromtheBACthatthebidderhastheLowestCalculatedResponsiveBid,whentheTreatyorInternationalorExecutiveAgreementexpresslyallowssubmissionofthePCABlicenseandregistrationforthetypeandcostofthecontracttobeasapreconditiontotheNoticeofAward;

37.1.4.NotwithstandingtheissuanceoftheNoticeofAward

Page 277: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

53.1.2.1.Inthecaseofinfrastructureprojects,bonafidecontractorslicensedwiththeCIAPwhoseeligibilitydocumentsareonfilewiththeprocuringentityconcernedortheDepartmentofPublicWorksandHighways(DPWH)ContractorsRegistry,asthecasemaybe,andwhohavebeenclassifiedunderthetypeofcontract/projectwherethesubjectcontractfallsareeligibletobeinvitedfornegotiation.Othercontractorsnotpreviouslydeemedeligiblemayalsoapplyforeligibility.

53.1.2.TheBACshallinviteandengageinnegotiations

Page 278: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

53.1.2.2.AllProcuringEntitiesshallmaintainaregistryofsuppliers,contractors,andconsultantsasbasisfordrawinguptheshortlistand/orselectingthesuppliers,contractors,andconsultantsfornegotiations.

53.1.2.TheBACshallinviteandengageinnegotiations

Page 279: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

62.2.3.1.ThefollowingshallbeheldresponsibleforStructuralDefects,i.e.,majorfaults/flaws/deficienciesinoneormorekeystructuralelementsoftheprojectwhichmayleadtostructuralfailureofthecompletedelementsorstructure,orStructuralFailures,i.e.,whereoneormorekeystructuralelementsinaninfrastructurefacilityfailsorcollapses,therebyrenderingthefacilityorpartthereofincapableofwithstandingthedesignloads,and/orendangeringthesafetyoftheusersorthegeneralpublic:a)ContractorWhereStructuralDefects/Failuresariseduetofaultsattributabletoimproperconstruction,useofinferiorquality/substandardmaterials,andanyviolationofthecontractplansandspecifications,thecontractorshallbeheldliable;

b)ConsultantsWhereStructuralDefects/Failuresariseduetofaultyand/orinadequatedesignandspecificationsaswellasconstructionsupervision,thentheconsultantwhopreparedthedesignorundertookconstructionsupervisionfortheprojectshallbeheldliable;

c)ProcuringEntitysRepresentatives/ProjectManager/ConstructionManagersandSupervisorsTheprojectowner srepresentative(s),projectmanager,constructionmanager,andsupervisor(s)shallbeheldliableincaseswheretheStructuralDefects/Failuresareduetohis/theirwillfulinterventioninalteringthedesignsandotherspecifications;negligenceoromissioninnotapprovingoractingonproposedchangestonoteddefectsordeficienciesinthedesignand/orspecifications;andtheuseofsubstandardconstructionmaterialsintheproject;

d)ThirdParties-ThirdPartiesshallbeheldliableincaseswhereStructuralDefects/Failuresarecausedbyworkundertakenbythemsuchasleakingpipes,diggingsorexcavations,undergroundcablesandelectricalwires,undergroundtunnel,miningshaftandthelike,inwhichcasetheapplicablewarrantytosuchstructureshouldbeleviedtothirdpartiesfortheirconstructionorrestorationworks.

e)Users-IncaseswhereStructuralDefects/Failuresareduetoabuse/misusebytheenduseroftheconstructedfacilityand/ornoncompliancebyauserwiththetechnicaldesignlimitsand/orintendedpurposeofthesame,thentheuserconcernedshallbeheldliable.(a)

62.2.3.Fromfinalacceptanceoftheproject

Page 280: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

62.2.3.2.ThewarrantyagainstStructuralDefectsandFailuresshallcoverthefollowingperiodsfromfinalacceptance,exceptthoseoccasionedbyforcemajeure:a)PermanentStructures:Fifteen(15)yearsBuildingsoftypes4and5asclassifiedundertheNationalBuildingCodeofthePhilippinesandotherstructuresmadeofsteel,iron,orconcretewhichcomplywithrelevantstructuralcodes(e.g.,DPWHStandardSpecifications),suchas,butnotlimitedto,steel/concretebridges,flyovers,aircraftmovementareas,ports,dams,tunnels,filtrationandtreatmentplants,seweragesystems,powerplants,transmissionandcommunicationtowers,railwaysystem,andothersimilarpermanentstructures;

b)Semi-PermanentStructures:Five(5)yearsBuildingsoftypes1,2,and3asclassifiedundertheNationalBuildingCodeofthePhilippines,concrete/asphaltroads,concreterivercontrol,drainage,irrigationlinedcanals,riverlanding,deepwells,rockcauseway,pedestrianoverpass,andothersimilarsemi計ermanentstructures;and

c)OtherStructures:Two(2)yearsBaileyandwoodenbridges,shallowwells,springdevelopments,andothersimilarstructures.(a)

62.2.3.Fromfinalacceptanceoftheproject

Page 281: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

62.2.3.3.ToguaranteethatthecontractorshallperformhisresponsibilitiesasprescribedinSection62.2.3.1(a)ofthisIRR,itshallberequiredtopostawarrantysecurityinaccordancewiththefollowingschedule:FormofWarrantySecurityAmountofWarrantySecurity(EqualtoPercentageoftheTotalContractPrice)a)CashorLetterofCreditissuedFivepercent(5%)byaUniversalorCommercialBank:Provided,however,thattheLCshallbeconfirmedorauthenticatedbyaUniversalorCommercialBank,ifissuedbyaforeignbank.

b)BankguaranteeconfirmedbyaUniversalorCommercialBank.Tenpercent(10%)

c)SuretybondcallableupondemandissuedbyGSISorasuretyorinsurancecompanydulycertifiedbytheInsuranceCommissionasauthorizedtoissuesuchsecurity.Thirtypercent(30%)ForbiddingsconductedbyLGUs,thecontractormayalsosubmitwarrantysecuritiesintheformofbankguaranteeorletterofcreditfromotherbankscertifiedbytheBSPasauthorizedtoissuesuchfinancialinstrument.(a)

62.2.3.Fromfinalacceptanceoftheproject

Page 282: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

62.2.3.4.ThewarrantysecurityshallbedenominatedinPhilippinePesos,remaineffectiveforone(1)yearfromthedateofissuanceoftheCertificateofFinalAcceptancebytheprocuringentity,andreturnedonlyafterthelapseofthesaidone(1)yearperiod.(a)

62.2.3.Fromfinalacceptanceoftheproject

Page 283: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

a)DesignStandardsDesignstandardsshallbeinaccordancewithappropriatestandardsandaccepteddetailedengineeringpracticeadoptedbytheagencyconcerned.Designstandardsforstructuresshalltakeintoaccount,amongotherthings,theseismicityoftheareatodeterminetheoptimumsafetyofstructuresandtominimizepossibleearthquakedamage.

BACK

Page 284: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

b)FieldSurveysAndInvestigationsNecessaryfieldsurveysandinvestigationswhichmayincludeaerial,hydrographic,topographic,hydrologic,sub-surface,monumentingandothersurveysshallbecarriedoutinaccordancewiththedesignguidelines,criteriaandstandardsadoptedbytheagencyconcerned.Allsurveyandinvestigationworksshallbepreparedinamannersatisfactorytocarryoutaccuratedesignandproductionofplansthatwillpermitquantityestimatestobemadewithinplusorminustenpercent(10%)ofthefinalquantitiesofthecompletedstructure.

BACK

Page 285: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

c)ContractPlansThefollowingplansshallbepreparedforeachconstructioncontractinaccordancewithguidelinesandstandardsadoptedbytheprocuringentityconcerned,incorporatingatleastthefollowing:i)Sitedevelopmentplanii)Plansandprofilesheetiii)Typicalsectionsanddetailsiv)Drainagedetailswhereapplicablev)Structuralplansatappropriatescalesindicatingalldetailsnecessaryinorderthatthecompletestructurecanbesetoutandconstructedvi)Otherdetailswhichmayberequiredbytheheadoftheagency

BACK

Page 286: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

d)QuantitiesAllconstructionquantitiesshallbecomputedtoareasonableaccuracyofnotmorethanplusorminustenpercent(10%)ofthefinalquantitiesoftheas-builtstructure.

BACK

Page 287: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

e)SpecialProvisionsSpecificationsshallbepreparedforspecifictermsofworkormethodsofconstruction,measurementandpaymentundereachcontract,whicharenotcoveredbyStandardConstructionandMaterialSpecificationsadoptedbytheprocuringentityconcerned.

BACK

Page 288: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

f)UnitPricesTheseshallbepreparedforeachcontractusingcostsbasedonreasonableapprovedcurrentpricesasprojectedovertheproposedconstructionperiod,dividedintolocalandforeignexchangecosts,asthecasemaybe.

BACK

Page 289: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

g)ApprovedBudgetfortheContracttheABCtobebidshallbepreparedbyofficial(s)dulydesignatedbytheHeadoftheProcuringEntityconcernedorbyhisdulyauthorizedofficial.ItshallbeapprovedbytheHeadoftheProcuringEntityorhisdulydesignatedofficial.Sincethecontractsarefixedpricecontracts,theABCtobebidshallprovidefortheprojectedmovementsofconstructioncostsovertheconstructionperiodconsideringtheprojectedinflationandforeignexchangeratesasissuedbytheDevelopmentBudgetCoordinationCommittee(DBCC).Itshallalsoshowthelocalandforeigncurrencyrequirements,asthecasemaybe.TheABCtobebidshallspecifyforeachmajorworkitem,suchasearthwork,roadwork,andmassiveconcreting,thecomponentsforequipmentrentals,fuel,labor,materialsandoverhead,includingthecostoftheapprovedconstructionsafetyandhealthprogramandwarrantypremium.

BACK

Page 290: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

h)BiddingDocumentsTheseshallbepreparedasprovidedforintheIRR.

BACK

Page 291: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i)ProgramofWorkBeforeprosecutinganyproject,thenecessaryprogramofworkshallbepreparedandsubmittedforapproval.Innocaseshallconstructionfundsberemittedtofieldofficesorconstructionworkonaprojectbestartedbeforetheprogramofworkisapproved,inaccordancewithexistinglaws.Noprogramofworkforanyprojectshallbeapprovedwithoutdetailedengineering.Theprogramofworkshallinclude,amongotherthings,estimatesofthework,items,quantitiesandcostsandaPERT/CPMnetworkoftheprojectactivities.Theprogramofworkshallcoveratleastausableportionoftheprojectandnoconstructionshallbestartedforportionsoftheprojectthatarelessthanusable,exceptprojectsrequiringstageconstruction,inwhichcasecontinuityofconstructionuptothecompletionofausableportionmustbeassured.

BACK

Page 292: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

j)ContractTimeorDurationInthepreparationoftheBiddingDocuments,theagencyshallmakeanestimateoftheactualnumberofworkingdaysrequiredtocompletetheprojectthroughPERT/CPManalysisoftheprojectactivitiesandcorrectedforholidaysandweekends.Likewise,theagencyshallmakeanestimateofthenumberofrainy/unworkabledaysconsideredunfavorablefortheprosecutionoftheworksatthesite,basedontherecordsofthePhilippineAtmospheric,GeophysicalandAstronomicalServicesAdministration(PAGASA),andincorporatethesameinthecorrectedactualnumberofworkingdaysdeterminedabove,whichshallbemadethebasisofthetotalcontracttime.Theestimatednumberofrainy/unworkabledaysconsideredunfavorablefortheprosecutionoftheworksatthesiteshallbemadeknownbeforethedateofbiddingthroughtheInstructionstoBiddersforthepurposeofguidingthecontractorinpreparinghisbidandasreferencetoboththeGOPandwinningcontractorstakingactionontherequestsfortimeextensions.Withouttheestimatednumberofrainy/unworkabledaysestablishedbeforethebiddingdateandmadeknowntoallparticipatingbidders,thecontracttimeispresumedtohaveexcludedtheunfavorableconditions.

BACK

Page 293: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

k)WarrantyPeriodLikewise,theBiddingDocumentsshallspecifythetypeofprojectandthecorrespondingwarrantyperiodrequiredbytheprocuringentity.

BACK

Page 294: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

l)ValueEngineeringFormajorprojectsasspecifiedbytheagency,valueengineeringshallbeconductedaccordingtoacceptedstandardsandpractices.Valueengineeringshallanalyzealternativeschemesofachievingtheprojectsobjectivesinordertodeleteorreducenon-essentialfeaturesandlessenthelifecyclecostsoftheprojectswithoutsacrificingthequalityandintegrityofthestructure,whilemaintainingitsessentialfunction,performance,andsafety.

BACK

Page 295: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

m)SiteorRight-of-WayAcquisitionPlansandResettlementActionPlansTheseshallbepreparedbasedonparcellarysurveysandsocio-economicsurveysofhouseholdsaffectedbytheproject.

BACK

Page 296: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

6.1.AdvisoryandReviewServices.Theseservicesincludeadviceonparticularprojectsorproblems.Thesewillincludeadviceonandreviewof,amongothers,planning,designandotherprofessionalservices,aswellasmanagement,production,inspection,testingandqualitycontrol.Theyalsoincludesuchservicesasappearancesbeforecommissions,boardsorotherjudicialbodiestogiveevidenceorotherwisesubmitprofessionalopinions.

BACK

Page 297: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

6.2.Pre-InvestmentorFeasibilityStudies.Thesearethestudieswhichnormallyprecededecisionstogo(ornottogo)forwardwithspecificprojects.Thesestudiesmayhaveastheirobjectives:

a)Toestablishinvestmentprioritiesandsectorpolicies-Studiesforthisobjectiveinclude,amongothers,basicresourceinventories,suchas,riverbasinsurveys,transportsectorsurveys,andstudiesofalternativedevelopmentpatternsandofsectorsonaregionalornationwidescale.

b)Todeterminethebasicfeaturesandthefeasibilityofindividualprojects-Studiesforthisobjectiveinclude,amongothers,thefunctionaldesign,projectsiteselection,architecturalandspaceprogrammingandphysicallayoutofspecificprojects,preliminarydesignandcostestimates,andtheeconomic,financialandenvironmentalimpactanalysesrequiredforprojectevaluation.

c)Todefineandproposechangesingovernmentalpolicies,operationsandinstitutionsnecessaryforthesuccessfulimplementationorfunctioningofinvestmentprojects-Studiesforthisobjectiveinclude,amongothers,analysisofprojectrelatedorganizations,administrativeproblems,planningmachinery,regulatoryandmarketingpolicies,accounting,andmanagementsystems,manpowerresourcesandtrainingrequirements.

BACK

Page 298: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

6.3.Design.Thistypeofservicesnormallyconsistsofthree(3)phases:

a)Pre-DesignPhaseestablishesthegeneralsizeandscopeoftheprojectanditslocationonthesite.Theservicesincludebutarenotlimitedtoreconnaissance,topographicalandotherengineeringandlandsurveys,soilsinvestigations,preparationofpreliminaryarchitectural/engineeringdesigns,layouts,outlinespecifications,preliminarycostestimatesandspecificrecommendationspriortoactualdesign;

b)BasicDesignPhaseincludesthepreparationofdetailedplans,designs,workingdrawings,specifications,detailedcostestimatesandtenderdocumentsrequiredforinvitationsofbidsforconstructionworksandequipment;and

c)SupportServicesDuringConstructionincludesassistanceandadviceinsecuringbids,tabulationandanalysisofbidresults,andmakingrecommendationsontheawardofconstructioncontracts,andinpreparingformalcontractdocuments;preparationofsupplementarydrawingsrequiredtosuitactualfieldconditions;checkingdetailedconstructionandas-builtdrawings,shopanderectiondrawingssubmittedbycontractors;makingperiodicvisitstocheckonthegeneralprogressofworkandqualityofmaterialsandworkmanship;observingperformancetestsandstart-upandmakingreportthereon;andmakingafinalinspectionandreportingofcompletedproject.

BACK

Page 299: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

6.4.ConstructionSupervision.Theseincludethefollowing:

a)Inspectionandexpeditingofthework;b)Verificationandcheckingofquantitiesandqualitiesofworkaccomplishedbythecontractorasagainsttheapprovedplans,specifications,andprogramsofwork;c)Issuanceofinstructionforcorrectionsofdefectsonthework;d)Verificationandrecommendationforapprovalofstatementsofworkaccomplishedandcertificateofprojectcompletedbythecontractor;e)Reviewandrecommendationforapprovalofprogressandfinalbillingsofthecontractor;andb)Provisionofrecordoras-builtdrawingsofthecompletedprojects.Theabovedonotmeandirection,superintendence,ormanagementofconstruction.

BACK

Page 300: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

6.5.ManagementandRelatedServices.Thesemayincludethefollowing:

a)Sectorpolicyandregionaldevelopmentstudies;b)Planning,feasibility,market,economic,financial,technical,operationsandsociologicalstudies;c)Projectmanagement,includingprocurementadvisoryservices,impactmonitoring,andpost-evaluationservices;d)Productionmanagement,inventorycontrol,andproductivityimprovement;e)Marketingmanagementandsystems;f)Informationandcommunicationstechnologyservices,includingbutnotlimitedto,informationsystemsdesignanddevelopment,andnetworkdesignandinstallation;g)Institutionalstrengthening,organizationdevelopment,manpowerrequirements,trainingandtechnologytransfer;h)Generalmanagementconsultancy;andi)Otherrelatedservices.

BACK

Page 301: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

6.6.OtherTechnicalServicesorSpecialStudies.TheTechnicalServicesmayincludethefollowing:a)Institutionbuilding,includingorganizationandmanagementstudies,andbusinessprocessre-engineeringanddevelopment;b)Designandexecutionoftrainingprogramsatdifferentlevels;c)Provisionofstafftocarryoutcertainfunctionsandtotraintheirreplacements;andd)Tasksrelatingtoeconomicandfinancialstudiessuchasthoseoftariffstructures.TheSpecialStudiesmayincludethefollowingandotherstudiesnotcoveredunderanyoftheservicesandstudiesdescribedabove:

a)Soilsinvestigation;

b)Studies,testsandprocessdeterminationperformedtoestablishdesigncriteriaforwaterfacilities;

c)Detailedmill,shop,and/orlaboratoryinspectionofmaterialsandequipment;

d)Landsurveys,establishmentofboundariesandmonuments,andrelatedofficecomputationsanddrafting;e)Parcellarysurveys;f)Engineeringsurveys(fordesignandconstruction)andphotogrammetry;

g)Assistanceinlitigationarisingfromthedevelopmentorconstructionofprojectsandinhearingsbeforevariousapprovingandregulatoryagencies;

h)Investigationinvolvingdetailedconsiderationoftheoperation,maintenance,andoverheadexpenses;andthepreparationofrateschedules;earningandexpensestatements,feasibilitystudies,appraisals,evaluations,andmaterialauditsorinventoriesrequiredforcertificationofforceaccountconstructionperformedbytheagencies;

i)Preparationofenvironmentalstatementsandassistancetotheagenciesinpublichearings;j)Preparationofoperatinginstructionsandmanualsforfacilitiesandtrainingofpersonnelandassistanceininitialoperationoffacilities;

k)Designstomeetuniqueand/orabovenormalrequirementsbroughtaboutbysevereearthquakes,tornadoes,orblasts,orsatisfyuniqueorabnormaltolerances,safetyrequirements,etc.;

l)Siteandphysicalplanning;

m)Environmentalandotheraspectsofplanning;

n)Housing;

o)Interiordesign;

p)Studiesonpreservationandrestorationofhistorical,cultural,andartworks;

q)Landscaping;

r)Constructionmanagement;and

s)Defensesystemsdesign,includingself-reliancedefenseprogram.Technologyandknowledgetransfershouldbeconsideredanimportantobjectiveintheprovisionofconsultingservices.

Page 302: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

BACK

Page 303: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

1.1.Subjecttotheconditionssetforthbelow,amendmentstoordermaybeissuedatanytimebytheprocuringentityconcerned.Ifanysuchorderincreasesordecreasesthecostof,orthetimerequiredforexecutinganypartoftheworkundertheoriginalcontract,anequitableadjustmentincontractpriceand/ordeliveryscheduleshallbemutuallyagreeduponbetweenthepartiesconcerned,andthecontractmodifiedinwriting.

BACK

Page 304: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

1.2.Anamendmenttoordermaybeissuedonlyinemergencycasesorduringfortuitouseventsrequiringnecessaryadjustmentswithinthegeneralscopeofthecontractinanyoneormoreofthefollowingisrequiredinordertofullymeettherequirementsoftheproject:a)drawings,designorspecifications,ifthegoodstobefurnishedaretobespecificallymanufacturedfortheGovernmentinaccordancetherewith;b)methodofshipmentorpacking;orc)placeofdelivery.

BACK

Page 305: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

1.3.Anamendmenttoordermayalsobeissuedbytheconcernedprocuringentitywherethereareadditionalitemsneededandnecessaryfortheprotectionofthegoods,whichwerenotincludedintheoriginalcontract.Paymentsfortheseadditionalitemsshallbebasedontheunitpricesintheoriginalcontractforitemsofgoodssimilartothoseintheoriginalcontract.Ifthecontractdoesnotcontainanyrateapplicabletotheadditionalitems,thensuitablepricesshallmutuallybeagreeduponbetweentheparties.Requestforpaymentbythesupplierforanyadditionalitemsshallbeaccompaniedbyastatementwiththeapprovedsupportingforms,givingadetailedaccountingandrecordofamountforwhichitclaimspayment.Thecontracttimeshalllikewisebeextendediftheacquisitionofsuchadditionalitemssowarrants.

BACK

Page 306: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

1.4.UndernocircumstancesshallasupplierproceedtocommenceworkunderanyamendmenttoorderunlessthesamehasbeenapprovedbytheHeadoftheProcuringEntityconcernedorhisdulyauthorizedrepresentative.Asanexceptiontotherule,theRegionalDirector/Headconcernedmayauthorizetheimmediatestartofworkunderanyamendmenttoorderintheeventofemergenciestoavoiddetrimenttopublicservice,ordamagetolifeand/orpropertyorwhentimeisoftheessence:Provided,however,ThatthesameisvalidonlyonitemsuptothepointwherethecumulativeincreaseinthecontractcostwhichhasnotyetbeendulyfullyapprovedbytheHeadoftheProcuringEntityconcernedorhisdulyauthorizedrepresentativedoesnotexceedfivepercent(5%)oftheoriginalcontractcost:Provided,further,ThatthecorrespondingamendmenttoordershallimmediatelybepreparedandsubmittedforapprovaltotheHeadoftheProcuringEntityconcernedorhisdulyauthorizedrepresentative.Foranamendmenttoorderinvolvingacumulativeamountexceedingfivepercent(5%)oftheoriginalcontactprice,noworkthereonshallbecommencedunlessthesamehasbeenapprovedbytheHeadofProcuringEntityconcernedorhisdulyauthorizedrepresentative:Provided,That,thesaidcumulativeamountdoesnotexceedtenpercent(10%)oftheoriginalcontractprice.

BACK

Page 307: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

4.1.InaccordancewithPresidentialDecree1445,advancepaymentshallbemadeonlyafterpriorapprovalofthePresident,andshallnotexceedfifteenpercent(15%)ofthecontractamount,unlessotherwisedirectedbythePresident;Provided,however,thatforcasesmentionedunder4.3,4.4,and4.5oftheseguidelines,nopriorapprovalbythePresidentshallbenecessary.

BACK

Page 308: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

4.2.Allprogresspaymentsshallfirstbechargedagainsttheadvancepaymentuntilthelatterhasbeenfullyexhausted,unlessotherwiseapprovedbythePresident.

BACK

Page 309: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

4.3.Asingleadvancepaymentnottoexceedfiftypercent(50%)ofthecontractamountshallbeallowedforcontractsenteredintobyaprocuringentityforthefollowingserviceswhererequirementofdownpaymentisastandardindustrypractice:a)Hotelandrestaurantservices;b)Useofconference/seminarandexhibitareas;andc)Leaseofofficespace.

BACK

Page 310: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

4.4.Advancepaymentnottoexceedfifteenpercent(15%)ofthecontractamount,unlessotherwisedirectedbythePresident,shallalsobeallowedforprocurementofgoodsrequiredtoaddresscontingenciesarisingfromnaturalorman-madecalamitiesinareaswhereaStateofCalamityhasbeendeclaredbyappropriateauthorities.

BACK

Page 311: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

4.5.Forgoodssuppliedfromabroadtenpercent(10%)oftheContractPriceshallbepaidwithin60daysfromsigningofthecontractanduponsubmissionofaclaimandabankguaranteeissuedbyalicensedbankfortheequivalentamountvaliduntilthegoodsaredeliveredandintheformprovidedintheBiddingDocuments.

BACK

Page 312: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

1.1.VariationOrdersmaybeissuedbytheprocuringentitytocoveranyincrease/decreaseinquantities,includingtheintroductionofnewworkitemsthatarenotincludedintheoriginalcontractorreclassificationofworkitemsthatareeitherduetochangeofplans,designoralignmenttosuitactualfieldconditionsresultingindisparitybetweenthepreconstructionplansusedforpurposesofbiddingandthe"asstakedplans"orconstructiondrawingspreparedafterajointsurveybythecontractorandtheGovernmentafterawardofthecontract,providedthatthecumulativeamountofthepositiveoradditiveVariationOrderdoesnotexceedtenpercent(10%)oftheoriginalcontractprice.Theaddition/deletionofworksunderVariationOrdersshouldbewithinthegeneralscopeoftheprojectasbidandawarded.ThescopeofworksshallnotbereducedsoastoaccommodateapositiveVariationOrder.AVariationOrdermayeitherbeintheformofeitherachangeorderorextraworkorder.

BACK

Page 313: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

1.2.AChangeOrdermaybeissuedbytheimplementingofficialtocoveranyincrease/decreaseinquantitiesoforiginalworkitemsinthecontract.

BACK

Page 314: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

1.3.AnExtraWorkOrdermaybeissuedbytheimplementingofficialtocovertheintroductionofnewworknecessaryforthecompletion,improvementorprotectionoftheprojectwhichwasnotincludedasitemsofworkintheoriginalcontract,suchas,wheretherearesubsurfaceorlatentphysicalconditionsatthesitedifferingmateriallyfromthoseindicatedinthecontract,orwheretherearedulyunknownphysicalconditionsatthesiteofanunusualnaturedifferingmateriallyfromthoseordinarilyencounteredandgenerallyrecognizedasinherentintheworkorcharacterprovidedforinthecontract.

BACK

Page 315: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

1.4.AnycumulativepositiveVariationOrderbeyondtenpercent(10%)oftheoriginalcontractpriceshallbesubjectofanothercontracttobebidoutiftheworksareseparablefromtheoriginalcontract.Inexceptionalcaseswhereitisurgentlynecessarytocompletetheoriginalscopeofwork,theHeadoftheProcuringEntitymayauthorizeapositivevariationorderthatwillmakethecumulativevalueofthepositiveVariationOrdersgobeyondtenpercent(10%)butnotmorethantwentypercent(20%)oftheoriginalcontractprice,subjecttotheguidelinestobedeterminedbytheGPPB:Provided,however,Thatappropriatesanctionsshallbeimposedonthedesigner,consultantorofficialresponsiblefortheoriginaldetailedengineeringdesignwhichfailedtoconsidertheVariationOrderbeyondtenpercent(10%).

BACK

Page 316: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

1.5.InclaimingforanyVariationOrder,thecontractorshall,withinseven(7)calendardaysaftersuchworkhasbeencommencedorafterthecircumstancesleadingtosuchcondition(s)leadingtotheextracost,andwithintwenty-eight(28)calendardaysdeliverawrittencommunicationgivingfullanddetailedparticularsofanyextracostinorderthatitmaybeinvestigatedatthattime.Failuretoprovideeitherofsuchnoticesinthetimestipulatedshallconstituteawaiverbythecontractorforanyclaim.ThepreparationandsubmissionofVariationOrdersareasfollows:a)Iftheprocuringentitysrepresentativeb)TheHeadoftheProcuringEntityorhisdulyauthorizedrepresentative,uponreceiptoftheproposedChangeOrderc)TheHeadoftheProcuringEntityorhisdulyauthorizedrepresentative,afterbeingsatisfiedthatsuchChangeOrderd)If,afterreviewoftheplans,quantitiesandestimatedunitcoste)ThetimeframefortheprocessingofVariationOrders

BACK

Page 317: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

a)TheHeadoftheProcuringEntityorhisdulyauthorizedrepresentativemay,subjecttotheavailabilityoffunds,authorizetheimmediatestartofworkunderanyChangeorExtraWorkOrderunderanyorallofthefollowingconditions:

i)Intheeventofanemergencywheretheprosecutionoftheworkisurgenttoavoiddetrimenttopublicservice,ordamagetolifeand/orproperty;and/orii)Whentimeisoftheessence;Provided,however,Thatsuchapprovalisvalidonworkdoneuptothepointwherethecumulativeincreaseinvalueofworkontheprojectwhichhasnotyetbeendulyfullyapproveddoesnotexceedfivepercent(5%)oftheadjustedoriginalcontractpricewhicheverisless;Provided,further,Thatimmediatelyafterthestartofwork,thecorrespondingChangeOrderorExtraWorkOrdershallbepreparedandsubmittedforapprovalinaccordancewiththeaboveruleshereinset.PaymentsforworkssatisfactorilyaccomplishedonanyChangeOrderorExtraWorkOrdermaybemadeonlyafterapprovalofthesamebytheHeadoftheProcuringEntityorhisdulyauthorizedrepresentative.

BACK

Page 318: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

b)ForaChangeOrderorExtraWorkOrderinvolvingacumulativeamountexceedingfivepercent(5%)oftheoriginalcontractprice,noworkthereonmaybecommencedunlesssaidChangeOrderorExtraWorkOrderhasbeenapprovedbytheHeadoftheProcuringEntityorhisdulyauthorizedrepresentative.

BACK

Page 319: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.1.Wherethecontractorrefusesorfailstosatisfactorilycompletetheworkwithinthespecifiedcontracttime,plusanytimeextensiondulygrantedandisherebyindefaultunderthecontract,thecontractorshallpaytheprocuringentityforliquidateddamages,andnotbywayofpenalty,anamount,asprovidedintheconditionsofcontract,equaltoatleastonetenth(1/10)ofone(1)percentofthecostoftheunperformedportionoftheworksforeverydayofdelay.

BACK

Page 320: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.2.Aprojectoraportionthereofmaybedeemedusablewhenitstartstoprovidethedesiredbenefitsascertifiedbythetargetedend-usersandtheconcernedprocuringentity.

BACK

Page 321: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.3.Tobeentitledtosuchliquidateddamages,theprocuringentitydoesnothavetoprovethatithasincurredactualdamages.Suchamountshallbedeductedfromanymoneydueorwhichmaybecomeduethecontractorunderthecontractand/orcollectsuchliquidateddamagesfromtheretentionmoneyorothersecuritiespostedbythecontractorwhicheverisconvenienttotheprocuringentity.

BACK

Page 322: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.4.Incasethatthedelayinthecompletionoftheworkexceedsatimedurationequivalenttotenpercent(10%)ofthespecifiedcontracttimeplusanytimeextensiondulygrantedtothecontractor,theprocuringentityconcernedmayrescindthecontract,forfeitthecontractor'sperformancesecurityandtakeovertheprosecutionoftheprojectorawardthesametoaqualifiedcontractorthroughnegotiatedcontract.

BACK

Page 323: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.5.Innocasehowever,shallthetotalsumofliquidateddamagesexceedtenpercent(10%)ofthetotalcontractprice,inwhicheventthecontractshallautomaticallybetakenoverbytheprocuringentityconcernedorawardthesametoaqualifiedcontractorthroughnegotiationandtheerringcontractor'sperformancesecurityshallbeforfeited.Theamountoftheforfeitedperformancesecurityshallbeasidefromtheamountoftheliquidateddamagesthatthecontractorshallpaythegovernmentundertheprovisionsofthisclauseandimposeotherappropriatesanctions.

BACK

Page 324: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

8.6.Forterminatedcontractswherenegotiationshallbeundertaken,theproceduresprescribedintheIRRshallbeadopted.

BACK

Page 325: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

9.1.Theprocuringentityshallhavetheauthoritytosuspendtheworkwhollyorpartlybywrittenorderforsuchperiodasmaybedeemednecessary,duetoforcemajeureoranyfortuitouseventsorforfailureonthepartofthecontractortocorrectbadconditionswhichareunsafeforworkersorforthegeneralpublic,tocarryoutvalidordersgivenbytheprocuringentityortoperformanyprovisionsofthecontract,orduetoadjustmentofplanstosuitfieldconditionsasfoundnecessaryduringconstruction.Thecontractorshallimmediatelycomplywithsuchordertosuspendtheworkwhollyorpartly.

BACK

Page 326: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

9.2.Thecontractororitsdulyauthorizedrepresentativeshallhavetherighttosuspendworkoperationonanyorallprojects/activitiesalongthecriticalpathofactivitiesafterfifteen(15)calendardaysfromdateofreceiptofwrittennoticefromthecontractortothedistrictengineer/regionaldirector/consultantorequivalentofficial,asthecasemaybe,duetothefollowing:1.Thereexistright-of-wayproblemswhichprohibitthecontractorfromperformingworkinaccordancewiththeapprovedconstructionschedule.

2.Requisiteconstructionplanswhichmustbeowner-furnishedarenotissuedtothecontractorprecludinganyworkcalledforbysuchplans.

3.Peaceandorderconditionsmakeitextremelydangerous,ifnotpossible,towork.However,thisconditionmustbecertifiedinwritingbythePhilippineNationalPolice(PNP)stationwhichhasresponsibilityovertheaffectedareaandconfirmedbytheDepartmentofInteriorandLocalGovernment(DILG)RegionalDirector.

4.Thereisfailureonthepartoftheprocuringentitytodelivergovernment-furnishedmaterialsandequipmentasstipulatedinthecontract.

5.Delayinthepaymentofcontractor'sclaimforprogressbillingbeyondforty-five(45)calendardaysfromthetimethecontractor'sclaimhasbeencertifiedtobytheprocuringentitysauthorizedrepresentativethatthedocumentsarecompleteunlesstherearejustifiablereasonsthereofwhichshallbecommunicatedinwritingtothecontractor.

BACK

Page 327: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

9.3.Incaseoftotalsuspension,orsuspensionofactivitiesalongthecriticalpath,whichisnotduetoanyfaultofthecontractor,theelapsedtimebetweentheeffectiveorderofsuspendingoperationandtheordertoresumeworkshallbeallowedthecontractorbyadjustingthecontracttimeaccordingly.

BACK

Page 328: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

10.1.Shouldtheamountofadditionalworkofanykindorotherspecialcircumstancesofanykindwhatsoeveroccursuchastofairlyentitlethecontractortoanextensionofcontracttime,theprocuringentityshalldeterminetheamountofsuchextension;providedthattheprocuringentityisnotboundtotakeintoaccountanyclaimforanextensionoftimeunlessthecontractorhas,priortotheexpirationofthecontracttimeandwithinthirty(30)calendardaysaftersuchworkhasbeencommencedorafterthecircumstancesleadingtosuchclaimhavearisen,deliveredtotheprocuringentitynoticesinorderthatitcouldhaveinvestigatedthematthattime.Failuretoprovidesuchnoticeshallconstituteawaiverbythecontractorofanyclaim.Uponreceiptoffullanddetailedparticulars,theprocuringentityshallexaminethefactsandextentofthedelayandshallextendthecontracttimecompletingthecontractworkwhen,intheprocuringentity'sopinion,thefindingsoffactsjustifyanextension.

BACK

Page 329: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

10.2.Noextensionofcontracttimeshallbegrantedthecontractordueto(a)ordinaryunfavorableweatherconditionsand(b)inexcusablefailureornegligenceofcontractortoprovidetherequiredequipment,suppliesormaterials.

BACK

Page 330: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

10.3.ExtensionofcontracttimemaybegrantedonlywhentheaffectedactivitiesfallwithinthecriticalpathofthePERT/CPMnetwork.

BACK

Page 331: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

10.4.Noextensionofcontracttimeshallbegrantedwhenthereasongiventosupporttherequestforextensionwasalreadyconsideredinthedeterminationoftheoriginalcontracttimeduringtheconductofdetailedengineeringandinthepreparationofthecontractdocumentsasagreeduponbythepartiesbeforecontractperfection.

BACK

Page 332: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

10.5.Extensionofcontracttimeshallbegrantedforrainy/unworkabledaysconsideredunfavorablefortheprosecutionoftheworksatthesite,basedontheactualconditionsobtainedatthesite,inexcessofthenumberofrainy/unworkabledayspre-determinedbythegovernmentinrelationtotheoriginalcontracttimeduringtheconductofdetailedengineeringandinthepreparationofthecontractdocumentsasagreeduponbythepartiesbeforecontractperfection,and/orforequivalentperiodofdelayduetomajorcalamitiessuchasexceptionallydestructivetyphoons,floodsandearthquakes,andepidemics,andforcausessuchasnon-deliveryontimeofmaterials,workingdrawings,orwritteninformationtobefurnishedbytheprocuringentity,non-acquisitionofpermittoenterprivatepropertieswithintheright-of-wayresultingincompleteparalyzationofconstructionactivities,andothermeritoriouscausesasdeterminedbytheGovernment'sauthorizedEngineerandapprovedbytheprocuringentity.Shortageofconstructionmaterials,generallaborstrikes,andpeaceandorderproblemsthatdisruptconstructionoperationsthroughnofaultofthecontractormaybeconsideredasadditionalgroundsforextensionofcontracttimeprovidedtheyarepubliclyfeltandcertifiedbyappropriategovernmentagenciessuchasDTI,DOLE,DILG,andDND,amongothers.Thewrittenconsentofbondsmenmustbeattachedtoanyrequestofthecontractorforextensionofcontracttimeandsubmittedtotheprocuringentityforconsiderationandthevalidityoftheperformancesecurityshallbecorrespondinglyextended.

BACK

Page 333: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

12.1.SubjectandScopeAllProcuringEntitiesimplementinggovernmentinfrastructureprojectsaremandatedtoevaluatetheperformanceoftheircontractorsusingtheNEDA-ApprovedConstructorsPerformanceEvaluationSystem(CPES)Guidelinesforthetypeofprojectbeingimplemented.Theseguidelinescoverallinfrastructureprojectsawardedbythegovernmentregardlessofcontractamountandfundingsource.CPESevaluationshallbedoneduringconstructionanduponcompletionofeachgovernmentproject.ToensurecontinuousimplementationofCPES,allProcuringEntitiesconcernedarerequiredtoincludeintheirProjectsEngineeringandAdministrativeOverheadCostthebudgetfortheimplementationofCPESpursuanttoNEDABoardResolutionNo.18(s.2002).

BACK

Page 334: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

12.2.EvaluationGuidelinesForprojecttypeswhichdonothavespecificCPESGuidelines,theProcuringEntitiesconcernedmayformulateandadopttheirownimplementingGuidelinesspecifictotheirneedsprovidedtheNEDA-INFRACOMposesnoobjectionstotheiradoption,andprovidedfurtherthatsaidGuidelinesaremadeknowntoallprospectivebidders.

BACK

Page 335: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

12.3.ImplementationMechanismforCPESAllProcuringEntitiesimplementinginfrastructureprojectsarerequiredtoestablishCPESImplementingUnits(IUs)intheirrespectiveoffices/agencies/corporations.TheCPESImplementingUnitsshallberesponsiblefortheimplementationoftheCPESImplementingguidelines,includingbutnotlimitedto,thesupervisionofConstructorsPerformanceEvaluators(CPEs)tobeaccreditedbytheConstructionIndustryAuthorityofthePhilippines(CIAP).TheprocuringentitysCPESIUshallberesponsibleforthefollowing:a)pre-screeningofapplicationsofCPEs,b)fundingforCPEsaccreditationtrainingandseminars;andc)yearlyevaluationofCPEs.

BACK

Page 336: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

12.4.SubmissionandDisseminationofEvaluationResultsAllProcuringEntitiesimplementingCPESshallsubmittheresultsoftheirperformanceevaluationtotheCIAPonamonthlybasisorasoftenasnecessary.TheprocuringentitysCPES-IUshalllikewisedevelopandmaintainadatabankanddisseminatetheCPESreportstotheconcernedunits/departmentswithintheprocuringentityandtootherinterestedusers.

BACK

Page 337: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

12.5.UtilizationofEvaluationResultsTheCIAPshallconsolidatealloftheCPESevaluationresultsreceivedandshalldisseminatethesametoallProcuringEntitiesconcerned.TheCPESratingandotherinformationshallbeusedbytheconcernedgovernmentagenciesforthefollowingpurposes:(a)prequalification/eligibilityscreeningofconstructors;(b)awardingofcontracts;(c)projectmonitoringandcontrol;(d)issuanceofCertificateofCompletion;(e)policyformulation/review;(f)industryplanning;(g)grantingofIncentives/Awards,and,inadoptingmeasuretofurtherimproveperformanceofcontractorsintheprosecutionofgovernmentprojects.

BACK

Page 338: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

3.1.Advantages:a)Sincebothdesignandconstructionareinthehandsofthecontractor,thereisasinglepointofresponsibilityforquality,cost,andscheduleadherence,includingtherisksrelatedtodesign.Thisprecludesbuck-passingandfinger-pointingbetweenthedesignerandthebuilder.

b)Becausedesignandconstructionperiodscanoverlap,thetotaldesignandconstructiontime,aswellasthefinalprojectcost,willbesignificantlyreduced.

c)Theprocuringentityisassuredofqualityconsideringthatthelargerresponsibilityimplicitinthedesign-buildschemeservesasmotivationforhighqualityofthefacilitytobeprovided.Oncetherequirementsoftheprocuringentityaredefinedinperformanceterms,thedesigner-builderisresponsibleforproducingtheresultsaccordingly.Thedesigner-builderwarrantstotheprocuringentitythatthedesigndocumentsarecompleteandfreefromerror.

d)Theprocuringentitydoesnotneedtospendmuchtimeandmoneyinseeingtoitthattheworkisdonebythecontractorexactlyasindicatedbythedesigndocumentspreparedbythedesigner,andincoordinatingandarbitratingbetweenseparatedesignandconstructioncontracts.

BACK

Page 339: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

3.2.Disadvantages:a)ProcuringEntitiesshould,however,takeintoaccountthatinutilizingthedesignandbuildschemeforaparticularproject,contractorsaregiventoomuchdiscretionindeterminingtheprojectcostandthereisdifficultyinpredictingitsfinalcostuntiltheactualcommencementofconstruction.This,however,canbeaddressedbyprescribingthatthebid/contractpriceshouldnotexceedtheApprovedBudgetforContract(ABC)oftheprocuringentityandthatthecontractpriceisafixedlumpsumamount.

b)Consideringthattheextentoftheintegrationofdesignandconstructionoftheprojectisexceptionallydependentonthecontractor,theremaybecaseswhentheend-resultmaynotbeexactlyinaccordancewithwhattheprocuringentityhasrequired.Thesecasescanbeavoidediftheprocuringadequatelydefinestheoutputorperformancespecificationsandparameters.

BACK

Page 340: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

a.ApprovedBudgetfortheContract(ABC).Thisshallbealumpsumamountthatshallcoverthecostofdesignandconstructionworks(attheoptionoftheprocuringentity)basedontheconceptualdesignandperformancespecificationsandinaccordancewithapplicableprovisionsofthelaworagencyguidelines.TheABCshallbecalculatedbasedoneithertheapproximatequantitiesofworkoftheconceptualdesign,fromstandardizeddesignsorfromcostrecordsofpreviousprojectsofsimilarkind.

BACK

Page 341: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

b.BiddingDocumentsforDesignandBuildScheme.TheseshallbasicallybesimilartotheBiddingDocumentsforinfrastructureprojectsandshallalsoincludetheperformancespecificationsandparameterstobefollowedbythedesignandbuildcontractorsandthemethodforallocationofrisksforthedesignandbuildcontract,amongothers.

BACK

Page 342: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

c.ConceptualDesign.Thisshalldescribethegeneralideaoftheprocuringentitywithregardtothecompletedfacilityandshallidentifythescopeorphysicalcomponentsandstructures,specificoutputsandrequirementsofthestructuresandproposedmethodsofconstruction,wherenecessary.

BACK

Page 343: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

d.DesignandBuildProjects.Thisreferstoinfrastructureprojectswheretheprocuringentityawardsasinglecontractforthearchitectural/engineeringdesignandconstructiontoasinglefirm,partnership,corporation,jointventureorconsortium.

BACK

Page 344: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

e.PerformanceSpecificationsandParameters.Theprocuringentityshalldefinetherequiredperformancespecificationsandcriteriaanditsmeansofmeasurementbasedontheoperatingoutputsandinaccordancewithappropriatedesignandconstructionstandards,legalandtechnicalobligationsandanyotherrelevantgovernmentcommitmentsasrequiredbyexistinglawsandregulations.Itshallnotbedrawnuptofavoraparticularsolution,designandconstructionmethod.

BACK

Page 345: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

f.PreliminaryInvestigations.Theseshallinclude,amongothers,informationonsoil,geotechnical,hydrologic,hydraulic,seismic,traffic,andenvironmentalconditionsthatshallbeusedtodefineprojectdesigncriteria,tosetthebasisforanychangedconditionsandestablishpreliminaryprojectcostestimates.

BACK

Page 346: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

g.PreliminarySurveyandMapping.Theseshalldetermineboundariesandprovidestationingalongcontrollinestoestablishfeatureanddesigncriterialocation,andidentifyexistingandfutureright-of-waylimitsandconstructioneasementsassociatedwiththeprocuringentitysconceptualdesign.

BACK

Page 347: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

h.ProjectDescription.Thisshalldefinetheobjectives,purpose,limitationsorconstraints,aswellastheallocationofrisksbetweentheprocuringentityandthewinningbidder.

BACK

Page 348: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i.UtilityLocations.Theprocuringentityshallprovideinformationonexistingutilitiesinandaroundtheprojectsarea.

BACK

Page 349: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

5.1.TheDesignandBuildschemeshallbeappliedunderanyofthefollowingcases:a.Forflagship,priorityandfasttrackprojectsthatneedtobecompletedonatightcompletionschedule,asincludedintheMediumTermPublicInvestmentProgram(MTPIP)fornationalprojectsandintheRegionalDevelopmentInvestmentPlan(RDIP)forregionalandprovincialprojects;b.Forinfrastructureprojectsrequiringadvancedengineeringorconstructiontechnologiesorwhoseintellectualpropertyrightsbelongtoprivatecompanies;c.Forinfrastructureprojectswheredesign,equipment,plantandconstructioncanbeprovidedexclusivelybyacompanyorwheremanufacturer sknow-howisimportantintheconstructionofsuchfacility;ord.Forsmallprojectswheretherearepreviouslyapproveddrawingsorstandardizeddesignsandaninnovationindesignandconstructionmethodsunderthedesignandbuildschemewillresultinlowercostsandhigherqualityprojects.Examplesoftheseareschoolbuildings,ruralhealthunits,amongothers.

BACK

Page 350: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

5.2.AlldesignandbuildprojectsshallbeincludedintheAnnualProcurementPlan(APP)oftheprocuringentityconcernedandshallbesubjecttopriorapprovalbytheHeadoftheProcuringEntityorhis/herdulyauthorizedrepresentative.

BACK

Page 351: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

i.ClassADocuments(Legal,TechnicalandFinancialDocuments)andClassBDocumentsTheprospectivebiddershallsubmitalltherequiredClassAandClassBdocumentsforinfrastructureprojectsandthefollowing:a)relevantstatementsofallon-going,completed,awardedbutnotyetstarteddesign/designandbuildrelatedcontracts,curriculumvitaeofkeystaff,partnersorprincipalofficers;and

b)validlicensesissuedbytheProfessionalRegulatoryCommission(PRC)fordesignprofessionalsinaccordancewiththeprovisionsunderSection24.7.1(TechnicalDocuments)ofthisIRR.

BACK

Page 352: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

ii.EligibilityCriteriaa)Theeligibilityofdesignandbuildcontractorsshallbebasedonthelegal,technicalandfinancialrequirementsabovementioned.Inthetechnicalrequirements,thedesignandbuildcontractor(assoloorinjointventure/consortia)shouldbeabletocomplywiththeexperiencerequirementundertheIRRofR.A.9184,whereoneoftheparties(inajointventure/consortia)shouldhaveatleastonesimilarproject,bothindesignandconstruction,withatleast50%ofthecostoftheABC.

b)Ifthebidderhasnoexperienceindesignandbuildprojectsonitsownitmayenterintosubcontracting,partnerships,orjointventurewithdesignorengineeringfirmsforthedesignportionofthecontract.

c)TherelevantprovisionsunderSection23.11.2.1oftheIRRofR.A.9184oneligibilityrequirementsshallbeobserved,withthefollowingexceptions:

Jointventures/consortiaamongFilipinocontractorsandconsultantsoramongFilipinocontractorsandforeignconsultantsshallbeallowedsubjecttopertinentlawsandtherelevantprovisionsoftheIRRofR.A.9184.Thejointventure/consortiashallbejointlyandseverallyresponsiblefortheobligationsandthecivilliabilitiesarisingfromthedesignandbuildcontract:Provided,however,ThatFilipinoownershiporinterestthereofshallbeatleastseventyfivepercent(75%):Providedfurther,Thatjointventures/consortiainwhichFilipinoownershiporinterestislessthanseventy-fivepercent(75%)maybeeligiblewherethestructurestobebuiltrequiretheapplicationoftechniquesand/ortechnologieswhicharenotadequatelypossessedbyFilipinosandthatFilipinoownershiporinterestshallnotbelessthantwenty-fivepercent(25%):Provided,finally,thatwhenthedesignservicesinwhichthejointventurewishestoengageinvolvethepracticeofprofessionsregulatedbylaw,allthosewhowillactuallyperformtheservicesshallbeFilipinocitizensandregisteredprofessionalsauthorizedbytheappropriateregulatorybodytopracticethoseprofessionsandalliedprofessionsandwhereforeigndesignersarerequired,theforeigndesignermustbeauthorizedbytheappropriatePhilippineGovernmentprofessionalregulatorybodytoengageinthepracticeofthoseprofessionsandalliedprofessions.

BACK

Page 353: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

10.1.Inthesubmissionofbids,thefirstenvelope(TechnicalProposal)shallcontainalltherequireddocumentsforinfrastructureprojectsunderSection25.3(b)oftheIRRofR.A9184andthefollowingadditionaldocuments:

i.PreliminaryConceptualDesignPlansinaccordancewiththedegreeofdetailsspecifiedbytheprocuringentity;ii.Designandconstructionmethods;iii.Listofdesignandconstructionpersonnel,tobeassignedtothecontracttobebid,withtheircompletequalificationandexperiencedata;andiv.Valueengineeringanalysisofdesignandconstructionmethod.

BACK

Page 354: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

10.2.Thesecondenvelope(FinancialProposal)shallcontainalltherequireddocumentsforinfrastructureprojectsunderSection25.3(b)oftheIRRofR.A9184andthefollowingadditionaldocuments:

i.Lumpsumbidprices,whichshallincludethedetailedengineeringcost,intheprescribedBidForm;ii.Detailedestimatesincludingasummarysheetindicatingtheunitpricesofconstructionmaterials,laborratesandequipmentrentalsusedincomingupwiththebid;andiii.Cashflowbythequarterandpaymentsschedule.

BACK

Page 355: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

11.1.First-StepProcedure:i.ThefirststepoftheevaluationshallinvolvethereviewofthepreliminaryconceptualdesignsandtrackrecordsubmittedbythecontractorasindicatedintheBiddingDocumentsusinganon-discretionarypass/failcriteriathatinvolvecompliancewiththefollowingrequirements:

a.Adherenceofpreliminarydesignplanstotherequiredperformancespecificationsandparametersanddegreeofdetails;b.Conceptofapproachandmethodologyfordetailedengineering,designandconstructionwithemphasisontheclarity,feasibility,innovativenessandcomprehensivenessoftheplanapproach,andthequalityofinterpretationofprojectproblems,risks,andsuggestedsolutions;c.Qualityofpersonneltobeassignedtotheprojectwhichcoverssuitabilityofkeystafftoperformthedutiesoftheparticularassignmentsandgeneralqualificationsandcompetenceincludingeducationandtrainingofthekeystaff;

ii.Forcomplexoruniqueundertakings,suchasthoseinvolvinghighlyspecializedoradvancedengineeringtechnology,eligiblebiddersmayberequired,attheoptionoftheagencyconcerned,tomakeanoralpresentationwithinfifteen(15)calendardaysafterthedeadlineforsubmissionoftechnicalproposals.

BACK

Page 356: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

11.2.Second-StepProcedure:Onlythosebidsthatpassedtheabovecriteriashallbesubjectedtothesecondstepofevaluation.TheBACshallopenthefinancialproposalofeachpassedbidderandshallevaluateitusingnon-discretionarycriteria-includingarithmeticalcorrectionsforcomputationalerrors-asstatedintheBiddingDocuments,andthusdeterminethecorrecttotalcalculatedbidprices.TheBACshallautomaticallydisqualifyanytotalcalculatedbidpricewhichexceedstheABC.Thetotalcalculatedbidprices(notexceedingtheABC)shallberanked,inascendingorder,fromlowesttohighest.ThebidwiththelowesttotalcalculatedbidpriceshallbeidentifiedastheLowestCalculatedBid(LCB).

BACK

Page 357: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

13.1.Noworksshallcommenceunlessthecontractorhassubmittedtherequireddocumentaryrequirementsandtheprocuringentityhasgivenwrittenapproval.Workexecutionshallbeinaccordancewithreviewedandapproveddocuments.

BACK

Page 358: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

13.2.Thecontractorshallberesponsibleforobtainingallnecessaryinformationastorisks,contingenciesandothercircumstanceswhichmayaffecttheworksandshallprepareandsubmitallnecessarydocumentsspecifiedbytheprocuringentitytomeetallregulatoryapprovalsasspecifiedinthecontractdocuments.

BACK

Page 359: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

13.3.TheContractorshallsubmitadetailedprogramofworkwithinfourteen(14)calendardaysaftertheissuanceoftheNoticetoProceedforapprovalbytheprocuringentitythatshallinclude,amongothers:i.Theorderinwhichitintendstocarryouttheworkincludinganticipatedtimingforeachstageofdesign/detailedengineeringandconstruction;ii.Periodsforreviewofspecificoutputsandanyothersubmissionsandapprovals;iii.Sequenceoftimingforinspectionsandtestsasspecifiedinthecontractdocuments;iv.Generaldescriptionofthedesignandconstructionmethodstobeadopted;v.Numberandnamesofpersonneltobeassignedforeachstageofthework;vi.Listofequipmentrequiredonsiteforeachmajorstageofthework;andvii.Descriptionofthequalitycontrolsystemtobeutilizedfortheproject.

BACK

Page 360: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

13.4.Anyerrors,omissions,inconsistencies,inadequaciesorfailuresubmittedbythecontractorthatdonotcomplywiththerequirementsshallberectified,resubmittedandreviewedatthecontractor scost.IftheContractorwishestomodifyanydesignordocumentwhichhasbeenpreviouslysubmitted,reviewedandapproved,thecontractorshallnotifytheprocuringentitywithinareasonableperiodoftimeandshallshoulderthecostofsuchchanges.

BACK

Page 361: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

13.5.Asarule,changesindesignandconstructionrequirementsshallbelimitedonlytothosethathavenotbeenanticipatedinthecontractdocumentspriortocontractsigningandapproval.Thefollowingguidelinesshallgovernapprovalforchangeorvariationorders:i.ChangeOrdersresultingfromdesignerrors,omissionsornonconformancewiththeperformancespecificationsandparametersandthecontractdocumentsbythecontractorshallbeimplementedbythecontractoratnoadditionalcosttotheprocuringentity.ii.Providedthatthecontractorsuffersdelayand/orincurscostsduetochangesorerrorsintheprocuringentitysperformancespecificationsandparameters,heshallbeentitledtoeitheroneofthefollowing:a.anextensionoftimeforanysuchdelaysunderSection10ofAnnexE;orb.paymentforsuchcostsasspecifiedinthecontractdocuments,provided,thatthecumulativeamountofthevariationorderdoesnotexceedtenpercent(10%)oftheoriginalcontractprice.

BACK

Page 362: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

13.6.Thecontractdocumentsshallincludethemannerandscheduleofpaymentspecifyingtheestimatedcontractamountandinstallmentsinwhichthecontractpricewillbepaid.

BACK

Page 363: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

13.7.ThecontractorshallbeentitledtoadvancepaymentsubjecttotheprovisionsofSection4ofAnnexE.

BACK

Page 364: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

13.8.Theprocuringentityshalldefinethequalitycontrolproceduresforthedesignandconstructioninaccordancewithagencyguidelinesandshallissuethepropercertificatesofacceptanceforsectionsoftheworksorthewholeoftheworksasprovidedforinthecontractdocuments.

BACK

Page 365: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

13.9.Thecontractorshallprovideallnecessaryequipment,personnel,instruments,documentsandotherstocarryoutspecifiedtests.

BACK

Page 366: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

13.10.AlldesignandbuildprojectsshallhaveaminimumDefectsLiabilityPeriodofone(1)yearaftercontractcompletionorasprovidedforinthecontractdocuments.Thisiswithoutprejudice,however,totheliabilitiesimposedupontheengineer/architectwhodrewuptheplansandspecificationforabuildingsanctionedunderSection1723oftheNewCivilCodeofthePhilippines.

BACK

Page 367: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

13.11.Thecontractorshallbeheldliablefordesignandstructuraldefectsand/orfailureofthecompletedprojectwithinthewarrantyperiodsspecifiedinSection62.2.2oftheIRR.

BACK

Page 368: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

a)Iftheprocuringentitysrepresentative/ProjectEngineerbelievesthataChangeOrderorExtraWorkOrdershouldbeissued,heshallpreparetheproposedOrderaccompaniedwiththenoticessubmittedbythecontractor,theplanstherefore,hiscomputationsastothequantitiesoftheadditionalworksinvolvedperitemindicatingthespecificstationswheresuchworksareneeded,thedateofhisinspectionsandinvestigationsthereon,andthelogbookthereof,andadetailedestimateoftheunitcostofsuchitemsofwork,togetherwithhisjustificationsfortheneedofsuchChangeOrderorExtraWorkOrder,andshallsubmitthesametotheHeadoftheProcuringEntityforapproval.

BACK

Page 369: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

b)TheHeadoftheProcuringEntityorhisdulyauthorizedrepresentative,uponreceiptoftheproposedChangeOrderorExtraWorkOrdershallimmediatelyinstructthetechnicalstafftoconductanon-the-spotinvestigationtoverifytheneedfortheworktobeprosecuted.AreportofsuchverificationshallbesubmitteddirectlytotheHeadoftheProcuringEntityorhisdulyauthorizedrepresentative.

BACK

Page 370: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

c)TheHeadoftheProcuringEntityorhisdulyauthorizedrepresentative,afterbeingsatisfiedthatsuchChangeOrderorExtraWorkOrderisjustifiedandnecessary,shallreviewtheestimatedquantitiesandpricesandforwardtheproposalwiththesupportingdocumentationtotheHeadofProcuringEntityforconsideration.

BACK

Page 371: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

d)If,afterreviewoftheplans,quantitiesandestimatedunitcostoftheitemsofworkinvolved,theproperofficeoftheprocuringentityempoweredtoreviewandevaluateChangeOrdersorExtraWorkOrdersrecommendsapprovalthereof,theHeadoftheProcuringEntityorhisdulyauthorizedrepresentative,believingtheChangeOrderorExtraWorkOrdertobeinorder,shallapprovethesame.

BACK

Page 372: CONTRACT IMPLEMENTATION GUIDELINES FOR THE … · contract implementation guidelines for the procurement of infrastructure projects 1. variation orders - change order/extra work order

e)ThetimeframefortheprocessingofVariationOrdersfromthepreparationuptotheapprovalbytheprocuringentityconcernedshallnotexceedthirty(30)calendardays.