Contract EW13/20 Alfred Cox Park/Awapuni School Cycle ......CONTRACT EW13/20 PAGE 3 3.1.27.1 Monthly...
Transcript of Contract EW13/20 Alfred Cox Park/Awapuni School Cycle ......CONTRACT EW13/20 PAGE 3 3.1.27.1 Monthly...
Contract EW13/20
Alfred Cox Park/Awapuni School Cycle and Walkway
Type of Contract: Physical Works
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR:
ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
C O N T E N T S ADVERTISEMENT(S) (1 pages)
TENDER DOCUMENTS (13 pages) FORM OF TENDER PREAMBLE TO SCHEDULE OF PRICES SCHEDULE OF PRICES PREAMBLE TO SCHEDULE OF DAYWORKS RATES SCHEDULE OF DAYWORKS RATES SCHEDULE OF PLANT AVAILABLE SCHEDULE OF MATERIALS SCHEDULE OF PROPOSED SUB-CONTRACTORS SCHEDULE OF TENDERER’S CURRENT COMMITMENTS SAFETY DECLARATION FOR CONTRACTORS
1.0 CONDITIONS OF TENDERING (4 pages)
2.0 CONDITIONS OF CONTRACT (24 pages) 2.1 GENERAL CONDITIONS OF CONTRACT 2.2 SCHEDULES FIRST : SPECIAL CONDITIONS OF CONTRACT PART A – SPECIFIC CONDITIONS OF CONTRACT
PART B – OTHER CONDITIONS OF CONTRACT
SECOND : FORM OF CONTRACT AGREEMENT THIRD : FORM OF CONTRACTOR’S PERFORMANCE BOND
FOURTH : FORM OF PRINCIPAL’S BOND
FIFTH : FORM OF CONTRACTOR’S BOND IN LEIU OF RETENTIONS
CONTRACT EW13/20 PAGE 2
SIXTH : FORM OF PRODUCER STATEMENT – CONSTRUCTION
SEVENTH : INFORMATION AS TO CONTRACT WORKS INSURANCE
EIGHTH : INFORMATION AS TO PUBLIC LIABILITY INSURANCE NINTH : INFORMATION AS TO CONTRACTOR’S CONSTRUCTION MACHINERY INSURANCE
TENTH : INFORMATION AS TO CONTRACTOR’S MOTOR VEHICLE INSURANCE ELEVENTH : INFORMATION AS TO CONTRACTOR’S PROFESSIONAL INDEMNITY INSURANCE
2.3 ANNEXURES A : COST FLUCTUATION ADJUSTMENT B : GENERAL CONDITIONS APPLYING TO PRINCIPAL’S BOND
C : SUPPORTING INFORMATION
D : TRAFFIC CONTROL
E : OCCUPATIONAL HEALTH AND SAFETY
F : CONSENTS AND LICENCES WHICH WILL BE OBTAINED BY PRINCIPAL G : GUARANTEES TO BE PROVIDED BY CONTRACTOR
H : PERFORMANCE REPORT
3.0 SPECIFICATIONS (23 pages) 3.1 General Specifications 3.1.1 Location of Contract 3.1.2 Scope of Work 3.1.3 Overview of Work 3.1.4 Standard Specifications and Publications 3.1.5 Hold Points 3.1.6 Drawings 3.1.7 Plans to be Kept on Job 3.1.8 Contractor to Inspect Site 3.1.9 Consents 3.1.10 Programme of Work 3.1.11 Weekly Reports 3.1.12 Site Establishment 3.1.13 Site Clearing and Tidying on Completion 3.1.14 Contract Quality Manager 3.1.15 Contractor’s Representative 3.1.16 Existing Services 3.1.17 Accessibility of Contractor 3.1.18 Access by Others 3.1.19 Health and Safety 3.1.19.1 Safety 3.1.19.2 Protective Clothing 3.1.19.3 Accident Reporting 3.1.19.4 Working Within a Hazardous Site 3.1.20 Protection of Public and Private Property and Services 3.1.21 Workmanship 3.1.22 Dust Control, Noise Control and Hours of Work 3.1.23 Traffic Management 3.1.24 Quality Management 3.1.24.1 General 3.1.24.2 Quality Plan 3.1.24.3 Quality Plan Requirements 3.1.25 Job Inspections 3.1.25.1 During Works 3.1.25.2 On Completion or During Period of Defects Liability 3.1.25.3 Reimbursements 3.1.26 Contract Meetings 3.1.27 Progress Payment and Final Claim
CONTRACT EW13/20 PAGE 3
3.1.27.1 Monthly Progress Claim 3.1.27.2 Final Claim 3.1.28 As-Built Information 3.1.29 Practical Completion/Defects Liability Certificate 3.1.29.1 Completion of the Contract Works 3.1.29.2 Period of Defects Liability 3.1.30 Statements to the Media 3.1.31 Archaeological Discoveries 3.1.32 Working Alongside Railway 3.1.33 Materials and Furniture 3.1.34 Public Notification 3.2 TECHNICAL SPECIFICATION 3.2.1 General Items 3.2.1.1 Establish, Disestablish and Clean Up on Completion 3.2.1.2 Survey and Setting Out 3.2.1.3 Prepare and Implement Temporary Traffic Management 3.2.1.4 Relocation of Services (Provisional Sum) 3.2.2 Quality Assurance Testing & Checking 3.2.2.1 Prepare and Implement Quality Plan 3.2.2.2 Provide Quality Assurance Testing 3.2.3 Site Clearance & Earthworks 3.2.3.1 Relocate Concrete Pavers, Bollards, Baskets, etc. 3.2.3.2 Remove from Site Surplus Materials 3.2.3.3 Excavate Existing concrete footpath at Stanley Road 3.2.3.4 Strip Topsoil to Stockpile 3.2.3.5 Excavate to Subgrade 3.2.3.6 Stockpile to Fill 3.2.3.7 Undercut Unsuitable and Replace 3.2.3.8 Prepare Subgrade 3.2.4 Path Construction 3.2.4.1 Supply and Place 100mm Compacted Subbase 3.2.4.2 temporary Edging 3.2.4.2.1 Timber Edging 3.2.4.2.2 Flexible Garden Edging 3.2.4.3 Construct Concrete Path (incl. Reinforcement) 3.2.4.3.1 Surface treatment – Type A (Main Pathway) 3.2.4.3.2 Surface Treatment – Type B (Gateways, Intersections and Lookouts) 3.2.4.3.3 Surface Treatment – Type C (Decorative Bands, Thresholds and Sculpture Areas) 3.2.4.3.4 Thickened Slab at Sculpture Features 3.2.4.3.5 Thickened Slab at Crossing Points 3.2.5 Drainage 3.2.5.1 Install culverts 3.2.5.2 Construct Timber Headwall 3.2.5.3 Install Subsoil Drain 3.2.6 Raised Platform at ‘Gateway’ Entrance 3.2.6.1 Reinforced Concrete Wall 3.2.7 Railway Crossing 3.2.7.1 Maze Fencing 3.2.7.2 Railway Crossing Sleepers 3.2.7.3 Railway Crossing Signs 3.2.7.4 Tactile Ground Surface Indicators 3.2.8 Grassing and Reinstatement 3.2.8.1 Respread Topsoil 3.2.8.1.1 Preparation 3.2.8.1.2 Timing 3.2.8.2 Sow Seed and Fertilise 3.2.8.2.1 Sow Seeds 3.2.8.2.2 Fertiliser 3.2.8.3 Maintain Grass 3.2.9 Miscellaneous Features
CONTRACT EW13/20 PAGE 4
3.2.9.1 Timber Blocks 3.2.9.2 Timber Posts with Resin Inlay
4.0 BASIS OF PAYMENT (5 pages)
4.1 General 4.1.1 Establishment, Dis-establishment and Clean-up on Completion 4.1.2 Survey and Setting Out 4.1.3 Prepare and Implement Traffic Management 4.1.4 Relocation of Service (Provisional Item) 4.2 Quality Assurance Testing and Checking 4.2.1 Prepare and Implement Quality Plan 4.2.2 Provide Quality Assurance Testing 4.3 Site Clearance and Earthworks 4.3.1 Relocate Concrete Pavers, Bollards, Baskets etc. 4.3.2 Remove from Site Surplus Materials 4.3.3 Excavate Existing Concrete Footpath at Stanley Road 4.3.4 Strip Topsoil to Stockpile 4.3.5 Excavate to Subgrade 4.3.6 Stockpile to Fill 4.3.7 Undercut Unsuitable and Replace 4.3.8 Prepare Subgrade 4.4 Path construction 4.4.1 Supply and Place 100mm Compacted Subbase 4.4.2 Temporary Edging 4.4.3 Construct Concrete Path (incl. Reinforcement) – Items 4.3.1/2/3 4.4.3.4 Extra-over for Thickened Slab at Crossing Points 4.4.3.5 Extra-over for Thickened Slab 4.5 Drainage 4.5.1 Install Culverts (900mm and 600mm diameter) 4.5.2 Construct Timber Headwall 4.5.3 Install Subsoil Drain 4.6 Raised Platform at ‘Gateway’ Entrance 4.6.1 Reinforced Concrete Wall 4.7 Railway Crossing 4.7.1 Maze Fencing 4.7.2 Railway Crossing Sleepers 4.7.3 Railway Crossing Signs 4.7.4 Tactile Ground Surface Indicators 4.8 Grassing and Reinstatement 4.8.1 Respread Topsoil 4.8.2 Sow Seed and fertilise (incl. Second Sowing) 4.8.3 Maintain Grass (incl. Watering and Mowing) 4.9 Miscellaneous Features 4.9.1 Timber Blocks 4.9.2 Timber Posts with Resin Inlay 4.10 Contingencies (Provisional Item)
5.0 APPENDICIES (29 pages)
5.1 Specification for Normal Concrete 5.2 Resource Consent 6.0 DRAWINGS (16 pages)
27 August 2013
Newspaper/s: Gisborne Herald Order No. W3726
Section: Tenders Insertion dates: Thursday, 29 August 2013
Saturday, 31 August 2013
ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
Contract Nº EW13/20
Tenders are invited for the construction of a cycle and walkway route situated at the rear of Awapuni School
and running along the length of Alfred Cox Park (Stanley Road to Grey Street). The work consists of minor
earthworks, drainage, reinforced concrete pathway (approximately 1.6km long, 3m wide) and reinstatement
work.
Tender documents are available from Customer Service at the address below. A document fee will not
apply.
Tenders close 1pm Wednesday 18 September 2013
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
TENDER DOCUMENTS
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
FORM OF TENDER I/We (the undersigned) hereby tender for CONTRACT Nº EW13/20 for ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
I/We confirm that we have inspected the site and examined the Tender Documents for the abovementioned works.
Our tender is for the sum of: ______________________________________________________ ($___________________)
(GST exclusive). Attached is a completed Schedule of Prices showing how we have calculated our tender sum.
The % for on site overheads is ____________________ % (Cl. 9.3.8 of the General Conditions)
The % for off site overheads and profit is ____________ % (Cl. 9.3.9 of the General Conditions)
The rate per working day is $______________________ /day (Cl. 9.3.10 of the General Conditions)
The variation processing fee is ____________________ % (Cl. 9.3.14 of the General Conditions)
(subject to a ceiling: see Special Conditions of Contract)
Except as otherwise specified, this tender includes the supply of all plant and labour, the purchase and procurement of all
materials and the performance of all services necessary to construct, complete and maintain the Contract Works described
in the Drawings and Specifications.
Unless and until a formal Agreement is prepared and executed, this Tender, together with written acceptance thereof, shall
constitute a binding agreement between me/us.
I/We further understand that no payment will be made until the Contract Agreement is signed by both Parties and, if
successful, we will sign without delay.
This tender is open for acceptance by the Principal for the period as stated in the Conditions of Tendering; otherwise for a
period of 30 days from the closing date for tenders.
I/We enclose herewith a cheque for the sum of $NIL being the required tender deposit.
I/We acknowledge the receipt of the following Notices to Tenderers: 1 2 3 4 5 6 (Circle all those received)
Dated this ___________________ day of __________________________________ 20__
2 ___________________________________ ___________________________________ Tenderer's Name Tenderer's Signature ___________________________________ Telephone: _________________________________ Tenderer's Designation Mobile: _________________________________ Fax: _________________________________ Email: _________________________________ For and on behalf of: ______________________________________________________________
(Name of Firm) ______________________________________________________________
(Address of Firm) ______________________________________________________________
(GST Registration No.)
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
PREAMBLE TO SCHEDULE OF PRICES 1. The Schedule of Prices forms part of this contract and shall be read in conjunction with the Tender, the
General and Special Conditions of Contract, the Specifications and the Drawings.
2. The unit rates are to be applied to the quantities cited to form the amount.
3. A price or rate shall be entered against each item in the Schedule, whether quantities are stated or not.
Items against which no price is entered shall be considered to be covered by the other rates and prices
in the Schedule.
4. Further to Conditions of tendering Clause 105.3 an electronic copy of the Schedule of Prices is now
available to tenderers.
This electronic copy of the Schedule of Prices will be provided on request to all who have uplifted tender
documents and can be obtained from the Consultant’s representative ([email protected]) via
email.
The Schedule of Prices is in Excel format and Tenderers will be able to enter their rates into relevant
unlocked cells.
Tenderers must use either the electronic Schedule or the appended copy of the Schedule contained in
the Tender Documents.
Page | 1
GISBORNE DISTRICT COUNCIL
CONTRACT No. EW13/20
CONTRACT FOR: Alfred cox Park/Awapuni School Cycle and Walkway
SCHEDULE OF PRICES
(GST Exclusive)
ItemItemItemItem DescriptionDescriptionDescriptionDescription QuantityQuantityQuantityQuantity UnitUnitUnitUnit RateRateRateRate Amount Amount Amount Amount
1111 General ItemsGeneral ItemsGeneral ItemsGeneral Items
1.1 Establish, disestablish and clean up on completion
100% LS
1.2 Survey and setting out 100% LS
1.3 Prepare and implement temporary traffic management
100% LS
1.4 Relocation of services 100% PS 2,000.00 2,000.00
2222 Quality Assurance Testing & CheckingQuality Assurance Testing & CheckingQuality Assurance Testing & CheckingQuality Assurance Testing & Checking
2.1 Prepare and implement quality plan 100% LS
2.2 Provide quality assurance testing 100% LS
3333 Site clearance & EarthworksSite clearance & EarthworksSite clearance & EarthworksSite clearance & Earthworks
3.1 Relocate concrete pavers, bollards, baskets etc
100% LS
3.2 Remove from site surplus materials 100% LS
3.3 Excavate existing concrete footpath at Stanley Road
100% LS
3.4 Strip topsoil to stockpile 460 m3
3.5 Excavate to subgrade 767 m3
3.6 Stockpile to fill 500 m3
Page | 2
Item Description Quantity Unit Rate Amount
3.7 Undercut material
3.7.1 Undercut unsuitable material from pathway 31 m3
3.7.2 Extra-over to remove hazardous material 20 m3
3.8 Prepare subgrade 4713 m2
4444 Path ConstPath ConstPath ConstPath Constrrrructionuctionuctionuction
4.1 Supply and place 100mm compacted subbase
475 m3
4.2 Temporary edging
4.2.1 Timber edging 2840 m
4.2.2 Flexible garden edging 250 m
4.3 Construct concrete path (incl. reinforcement and curing)
4.3.1 Surface treatment - Type A 4010 m2
4.3.2 Surface treatment - Type B 620 m2
4.3.3 Surface treatment - Type C 83 m2
4.3.4 Extra-over for thickened slab at sculptures 10 m2
4.3.5 Extra-over for thickened slab at crossing points
400 m2
5555 DrainageDrainageDrainageDrainage
5.1 Install culverts
5.1.1 Install 900mm dia RCRRJ culvert pipe (class 2)
9 m
5.1.2 Install 600mm dia RCRRJ culvert pipe (class
2)
8 m
Page | 3
Item Description Quantity Unit Rate Amount
5.2 Construct timber headwall 100% LS
5.3 Install subsoil drain (Provisional Item) 700 m
6666 Raised Platform at 'Gateway' EntranceRaised Platform at 'Gateway' EntranceRaised Platform at 'Gateway' EntranceRaised Platform at 'Gateway' Entrance
6.1 Reinforced concrete wall 19 m
7777 Railway CrossingRailway CrossingRailway CrossingRailway Crossing
7.1 Maze fencing 32 m
7.2 Railway crossing sleepers 15 m
7.3 Railway crossing signs 2 EA
7.4 Tactile ground surface indicators 2 m2
8888 Grassing and ReinstatementGrassing and ReinstatementGrassing and ReinstatementGrassing and Reinstatement
8.1 Respread topsoil 1379 m2
8.2 Sow seed and fertilise (incl. second sowing) 100% LS
8.3 Maintain grass (incl. watering) 100% LS
9999 Miscellaneous FeaturesMiscellaneous FeaturesMiscellaneous FeaturesMiscellaneous Features
9.1 Timber blocks 75 m
9.2 Timber posts with resin inlay 10 EA
10101010 Contingency Item PS 50,000.00 50,000.00
TOTAL (GST Exclusive)TOTAL (GST Exclusive)TOTAL (GST Exclusive)TOTAL (GST Exclusive) Carried to ForCarried to ForCarried to ForCarried to Form of Tenderm of Tenderm of Tenderm of Tender
$$$$
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
PREAMBLE TO SCHEDULE OF DAYWORKS RATES 1. This Schedule of Dayworks Rates forms part of this contract and shall be read in conjunction with the
Tender, the General and Special Conditions of Contract, the Specifications and the Drawings.
2. A rate shall be entered against each and every item in the Schedule, irrespective of whether the plant is
included in the “Schedule of Plant Available”.
3. Any item of plant included in the “Schedule of Plant Available”, which is not covered by one of the
categories given shall be specified under “Other miscellaneous plant” and a rate included.
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
SCHEDULE OF DAYWORKS RATES (GST Exclusive)
Plant Item Comment Year Make/ Model
Capacity/ Weight
Rate (Working)
1.
2.
3.
4. Labour (not associated
with operating plant)
(a) Foreman (b) Labourer
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
SCHEDULE OF PLANT AVAILABLE 1. The Tenderer shall insert on the form below all plant which will be available for exclusive use on this
contract should the company be awarded the contract.
2. The plant commitment made on this schedule may be taken into account when assessing attribute “4.
Appropriate Resources” on the Schedule of Supporting Information.
Plant Item
Comment
Year
Make/Model
Capacity/ Weight
9. Other Plant (state)
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
SCHEDULE OF MATERIALS The Tenderer shall insert on the form below the source and grading of materials on which the tender is based.
Item Description Unit Rate Source
Note: Above rates are GST exclusive
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
SCHEDULE OF PROPOSED SUB-CONTRACTORS It is proposed to employ the following sub-contractors on this contract:
Sub-Contractor’s Name Work to be Undertaken Value of Work
and these names are submitted for approval as required by Clause 4.1.2 of the Conditions of Contract.
With respect to Section 4 of the General Conditions of Contract, all material suppliers are deemed to be sub-
contractors.
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
SCHEDULE OF TENDERER’S CURRENT COMMITMENTS Tenderer's Current Work The Tenderer shall list current work being carried out by the Tenderer at the date of submitting the attached
tender:
Principal Project Name Contract Value Completion Date
Outstanding Tenders The Tenderer shall list outstanding tenders for which advice of acceptance is awaited at the time of submitting
the attached tender:
Principal
Project Name Approximate Contract Value
Completion Date
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: WASTEWATER PIPELINE - CCTV INSPECTION-2013/14
SAFETY DECLARATION FOR CONTRACTORS
1. I __________________________________________________ the undersigned as THE
CONTRACTOR will take all necessary precautions in connection with any work for Council in
order to ensure the safety, health and welfare of the personnel of THE CONTRACTOR and
third parties. I acknowledge Council has a strong commitment to safety and confirm I have
read, agree with, and support Council's safety requirements (appended).
2. Any failure by THE CONTRACTOR to comply with the safety requirements will be regarded
as a breach of contract. GISBORNE DISTRICT COUNCIL shall be entitled to immediately
suspend THE WORK at THE CONTRACTOR'S expense until any such failure has been
remedied.
3. GISBORNE DISTRICT COUNCIL have identified the following hazards :
• Vehicular traffic • Construction plant and machinery
• Underground and overhead services • Noise • Steep, slippery or uneven terrain • Stream or other waterways • Dust • Potential vandalism or break-ins
4. In addition to the above hazards identified by GISBORNE DISTRICT COUNCIL, I identify the
following hazards :
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
FULL NAME : _____________________________________________ SIGNED : _____________________________________________ DATE : _____________________________________________ TRADING NAME : _____________________________________________
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
1.0 CONDITIONS OF TENDERING
1.0 Conditions of Tendering Page 1
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
1.0 CONDITIONS OF TENDERING
The conditions of tendering shall be NZS3910:2003 : Conditions of Contract for Building and Civil
Engineering Construction : CONDITIONS OF TENDERING, except where modified below:
SCHEDULE TO CONDITIONS OF TENDERING
Contract for EW13/20: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
The conditions of tendering are those set out in NZS 3910:2003.
Clause numbers refer to conditions of tendering clauses.
102.2 Delete and replace with:
“A document fee is not required on uplifting tender documents.”
103.1
(a) An appointment to view the Site shall be made _________________________
(b) No appointment need be made to view the Site.
104.1 Add:
“Questions in relation to the tender documents shall be conveyed in writing to:
The Group Manager Engineering and Works
Gisborne District Council
Attention: Ms Kylie Cranston
By 1pm five days before tender closing date.”
104.3 Delete and replace with:
“Tenders shall be based on the Tender Documents and will be interpreted as relating to the Tender
Documents unless clearly endorsed otherwise. Tenders submitted subject to endorsement will be
considered accordingly.”
105.1 Delete and replace with:
“Tenders will close at the Gisborne District Council’s Administrative Office, Fitzherbert Street (PO Box 747),
Gisborne at 1pm on Wednesday 18 September 2013.
Tenders are to be enclosed in a sealed envelope addressed to:
The Tender Box
Gisborne District Council
PO Box 747
Gisborne
The envelope (and courier pack, if applicable) shall be marked in the top left hand corner:
“Tender for Contract EW13/20: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND
WALKWAY
The tender deposit is to be included in the tender envelope.”
105.2 Delete and replace with:
“However delivered the tender must be at the place for closing before the closing time. Late tenders, faxed
or emailed tenders will not be accepted.”
105.3 Delete and replace with:
1.0 Conditions of Tendering Page 2
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
“Tenders shall be fully completed on the Form of Tender and extra copy of the Tender Schedules provided and
shall include:
(a) Form(s) of Tender including GST registration number if applicable.
(b) Tender deposit
(c) Schedules of Prices (and summary where applicable)
(d) Schedule of Dayworks Rates
(e) Schedule of Plant Available
(f) Schedule of Materials
(g) Schedule of Proposed Sub-Contractors
(h) Schedule of Tenderers Current Commitments
(i) Safety Declaration for Contractors
(j) Information in accordance with the Schedule of Supporting Information
(k) Proposed Surety for Contract Bond (if applicable)
(l) The % for on site overheads
(m) The % for off site overheads and profit
(n) The rate per working day to be used where applicable
(o) Key information on the insurance cover which the Contractor proposes to provide
The tender deposit shall be $NIL lodged with the tender by crossed cheque made payable to the Gisborne
District Council. If a tenderer withdraws his tender at any time within the tender validity period and prior to
acceptance, the tender deposit shall be forfeited. The Contractor’s deposit shall be refunded with the first
progress payment. Other deposits will be returned within either ten days of acceptance, or within one month of
the closing date, whichever is earlier. The deposits will be held in trust by the Engineer, and no interest will be
payable.”
105.6 Delete and replace:
“If the tender contains any error in extension of unit rates or in summation of items such as to vary the
tendered sum, and the Principal or its agent becomes aware of the error prior to acceptance of any tender,
then the Principal or its agent shall draw the error to the attention of the tenderer whose tender contains the
error. The Principal or its agent shall adjust the unit rates after consultation with the tenderer to agree with
the tendered sum as shown on the Form of Tender. The adjusted rates shall become the contract rates for
payment. If agreement cannot be reached, then the tender may be rejected.”
105.7 Add new clause:
“Tenders will be opened in public at the Council’s Administrative Centre, Fitzherbert Street, Gisborne at 1pm
on the closing date.”
105.8 Add:
“If the tendered schedules contain any item where no rate or extension has been inserted by the tenderer, it
shall be assumed that the inserted rate is “nil” and that the tenderer has included the costs of undertaking
this item in the other inserted rates.”
106.4 Add:
“Where only one conforming tender is received, the tendering authority may negotiate with the tenderer but
shall not accept a negotiated price that exceeds the tendered price.”
107.1 Delete and replace with:
“The validity period of this tender is three months from date of opening. If no tender has been accepted
within the tender validity period the Principal will notify tenderers whether their tenders are still under
consideration, and if so will request tenderers to extend the validity period to suit.”
108 Add new
1.0 Conditions of Tendering Page 3
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
108.1 “Tagged Tenders
Tags that may be of long term benefit to the Principal are to be evaluated, solely at the discretion of the
Principal, as to their acceptability and cost implication. The tenderer will be requested to remove all
unacceptable tags and shall not be allowed to amend his tender price. Refusal to remove tags may result in the
tender being rejected. If a tenderer refuses to remove the tag and the tender is not rejected, it may be
evaluated and an alternative tender adjusted price determined by the Principal. If the consequence of the tag is
unacceptable to the Principal, the tender will be considered to be non-conforming and will be rejected.”
108.2 “Alternative Tenders - Either:
Alternative tenders will not be accepted;
OR:
Tenderers may submit alternative tenders which meet the same objectives as the tender specification, but which may allow the Contract
Works to be provided in a more economic, cost effective or efficient manner. Only alternative tenders which are within the scope of the
request for tenders, and which meet the requirements shall be considered. Tenders varying the duration of the contract shall only be
considered where the request for tenders specified that such variations were acceptable, and advised how they would be evaluated. The
duration of term maintenance contracts may not be varied (see Special Conditions of Contract 2.5).
The tender amount for the alternative tender is to be inserted on the appropriate form of tender provided. The Principal shall not be bound to
accept any alternative tender. The onus shall be on the tenderer to provide sufficient information with the tender to allow the tender to be
evaluated. Failure to provide sufficient information shall be grounds for rejecting the alternative tender. In addition to the items listed above,
alternative tenders shall include at least the following:
(a) A statement identifying the points of difference between the alternative and non-alternative tender.
(b) Materials or method specifications, in cases where it is intended to utilise materials or methods for which no specification has
been given in the tender document.
(c) A statement describing the design essentials, including preliminary drawings and the name and professional qualification of the
designer, in cases where the alternative tender involves an alternative design.
(d) A proposal for dealing with interim payments, in cases where the schedules of quantities given in the tender documents are not
applicable to the alternative tender.
(e) Name of client and location where the alternative has previously been used.”
109 Add new
“109 Tender Evaluation
109.1 Tenders shall conform to and be evaluated in accordance with the current issues of New Zealand
Transport Agency’s Contract Procedures Manual (SM012).
109.2 Tenders will be evaluated by the Lowest Price Conforming Tender method. This tender evaluation
process will be conducted in two stages as follows:
(a) The first stage shall consist of ranking tenders in ascending order based on prices.
(b) The second stage shall consist of determination of tender acceptability when assessed against
each of the non-price attributes defined in the Supporting Information contained within these
documents (Annexure C);
(c) The consultant’s completion report on past contracts.
Determination of acceptability shall commence with the lowest priced tender and shall cease when the
first acceptable tender is determined.
Each attribute shall be scored on a pass/fail basis. Any attribute which scores a fail may exclude that
tender from further consideration for NZ Transport Agency subsidised works. A fail may also exclude
that tenderer being considered further for work unsubsidised by NZ Transport Agency.
109.3 Evaluation of Alternative Tenders (Where Alternative Tenders are Allowed)
1.0 Conditions of Tendering Page 4
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
Alternative tenders shall be evaluated in two stages as follows, after the evaluation of non-alternative tenders has been
completed:
(a) The first stage shall consist of determining tender acceptability when judged on technical competence and
assessed against the non-price attributes. Each attribute shall be scored on a pass/fail basis. Any attribute which
scores a fail will exclude that tender from further consideration.
(b) The second stage shall consist of assessing the difference in the present value of the end result offered by the
preferred (lowest priced) non-alternative tender and each of the alternative tenders. The alternative tender price
shall then be adjusted by this amount.
(c) Each of the adjusted alternative tender prices shall then be compared with the preferred non-alternative tender
price to determine the best tender. If the preferred non-alternative tender remains the best tender following the
evaluation of alternative tenders then only this tender will be accepted. The Principal shall not be bound to accept
any alternative tender.
109.4 The Principal is not obliged to award a contract in response to this tender.”
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
2.0 CONDITIONS OF CONTRACT
2.0 Conditions of Contract Page 1
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
2.1 GENERAL CONDITIONS OF CONTRACT
The General Conditions of Contract shall be NZS3910:2003 : Conditions of Contract for Building and Civil
Engineering Construction, as modified by the First Schedule (the Special Conditions of Contract) as follows:
Part A : Specific Conditions of Contract
Part B : Other Conditions of Contract
These General Conditions may be inspected at the Gisborne District Council.
2.2 SCHEDULES TO GENERAL CONDITIONS OF CONTRACT
• FIRST SCHEDULE : SPECIAL CONDITIONS OF CONTRACT is included.
• SECOND SCHEDULE : CONTRACT AGREEMENT is included.
• THIRD SCHEDULE : FORM OF CONTRACTOR’S PERFORMANCE BOND is deleted.
• FOURTH SCHEDULE : FORM OF PRINCIPAL’S BOND is deleted.
• FIFTH SCHEDULE : FORM OF CONTRACTOR’S BOND IN LIEU OF RETENTIONS is deleted.
• SIXTH SCHEDULE : FORM OF PRODUCER STATEMENT is deleted.
• SEVENTH SCHEDULE : INFORMATION AS TO CONTRACT WORKS INSURANCE is deleted.
• EIGHTH SCHEDULE : INFORMATION AS TO PUBLIC LIABILITY INSURANCE is included.
• NINTH SCHEDULE : INFORMATION AS TO CONTRACTOR’S CONSTRUCTION MACHINERY
INSURANCE is deleted
• TENTH SCHEDULE : INFORMATION AS TO CONTRACTOR’S MOTOR VEHICLE INSURANCE is
included.
• ELEVENTH SCHEDULE : INFORMATION AS TO CONTRACTOR’S PROFESSIONAL INDEMNITY
INSURANCE is deleted.
2.0 Conditions of Contract Page 2
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
FIRST SCHEDULE
SPECIAL CONDITIONS OF CONTRACT
(Clause numbers refer to General Conditions)
PART A – SPECIFIC CONDITIONS OF CONTRACT
1.2
The Principal is the Gisborne District Council, Fitzherbert Street (PO Box 747), Gisborne, represented by the
Group Manager Engineering and Works.
(a) There are Separable Portions as set out in the following parts of the Contract Documents:
__________________________________________________________________
(b) There are no Separable Portions in this contract.
2.1.1
This contract is a: (a) Lump sum contract;
(b) Measure and value contract; (c) Cost reimbursement contract.
2.5
This contract is: (a) A construction contract in public roads;
(b) A term maintenance contract (including a road maintenance contract);
(c) Neither a construction contract in public roads nor a term maintenance contract.
2.6.1
This contract is:
(a) A local authority contract; (b) Not a local authority contract;
2.6.3
Clauses B1 and B2 of Appendix B:
(a) Shall apply to this contract; (b) Shall not apply to this contract.
2.6.4(a)
A safety plan for the Site:
(a) Is required, as set out in the following parts of the Contract Documents:
Clause 3.1.19 (b) Is not required.
2.6.4(b)
A traffic management plan:
(a) Is required, as set out in the following parts of the Contract Documents:
Clause 3.1.23 (b) Is not required.
2.7.1
Formation of this contract shall be by written acceptance by the Principal of the tender: (a) Without the execution of a formal Contract Agreement.
(b) Followed by the execution of a formal Contract Agreement as described in 2.7.2.
2.8.1
2.0 Conditions of Contract Page 3
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
(a) 2 sets of Contract Documents shall be supplied free of charge to the Contractor upon the acceptance of
tender in addition to tender, consent, and Contract Agreement sets. (b) No additional sets of Contract Documents will be supplied.
2.9
This clause does/does not apply.
2.9.22.9.22.9.22.9.2
......... sets of Contract Documents shall be supplied free of charge to the Engineer upon the acceptance of tender in addition to tender,
consent, and Contract Agreement sets.
3.1.1
A Contractor’s bond: (a) Is required;
(b) Is not required.
3.1.2
1.1 The Contractor’s bond shall be for the sum of $
A Contractor’s Bond is not required.
3.2.1
A Principal’s bond:
(a) Is not required; (b) Is required and the surety shall be
3.2.2
1.2 The Principal’s bond shall be for the sum of $
5.1.4
The Contractor is/is not responsible for design.
5.4.1
The Contractor shall be given possession of the Site on:
(a) The Date of Acceptance of Tender;
(b) Other date (specify)
5.4.3
The Principal will not arrange right of entry on adjoining properties.
5.5.1
Fulton Hogan Limited is the Roading Maintenance and Utilities Contractor for the City.
5.5.2
Separate Contractors will be carrying out routine park maintenance.
The Contractor shall allow unhindered access to others for routine maintenance.
5.6.6(g)
(a) Risks specifically excepted are (specify) _________________________________
(b) There are no excepted risks other than those in the General Conditions.
5.9.3
The Principal will not pay advances.
5.10.1
The Contractor shall provide the works programme within ten days from the date of acceptance....
5.11.1
(a) The Contractor is to be responsible, for and on behalf of the Principal, for obtaining project information memoranda, building
consents and code compliance certificates under the Building Act 2004 for the carrying out of the following parts of the Contract
Works to which Appendix D applies.
2.0 Conditions of Contract Page 4
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
(i) __________________________
(ii) ___________________________________________________________________
(b) There are no parts of the Contract Works to which Appendix D applies.
5.17.1
Quality management systems:
(a) Are required and details shall be submitted within ten days from the date of acceptance. (b) Are not required.
5.18.1(a)
(a) As-built drawings are required. (b) As-built drawings are not required.
5.18.1(b)
(a) Operation and maintenance manuals are required.
(b) Operation and maintenance manuals are not required.
6.1.2
The Engineer is the Group Manager Engineering and Works, Gisborne District Council, who for the time being is
Mr P D Higgs (PO Box 747, Gisborne).
8....1 and 8.6
(a) The Contractor shall insure as provided in 8.1; (b) The Principal shall insure as provided in 8.6.
8.1.2 or 8.6.1
The amount of the insurance to be effected in respect of the Contract Works and Materials shall be for not less
than the sum of the following:
(a) The Contract Price, after the acceptance of the tender or other offer, excluding any additions or
deductions which may be required to be made during the course of the contract;
(b) For the Cost of demolition, disposal and preparation for replacement work, the sum of:
(i) 5 % of the Contract Price as described in (a) above; or
(ii) ______% of the Contract Price as described in (a) above; or
(iii) $_________________________
(c) For professional fees including the Cost of clerks of works and inspectors, the sum of:
(i) 5 % of the Contract Price as described in (a) above; or
(ii) ______% of the Contract Price as described in (a) above; or
(iii) $_________________________
(d) The value of items incorporated, or to be incorporated, in the Contract Works, the Cost of which is not included in the Contract
Price, the sum of $
(e) For increased construction Costs not already provided for in the Contract Price during the period from the acceptance of the
tender or other offer until the issue of the Defects Liability Certificate for the Contract Works, the sum of:
(i) 5 % of the Contract Price as described in (a) above; or
(ii) ______% of the Contract Price as described in (a) above; or
(iii) $_________________________
The insurance shall make provision for automatic change of cover for items (a) and (e) above, to provide insurance
for any additions to or deductions from the Contract Price which occur after acceptance of the tender or other
offer.
8.2.1
Contractor’s Plant insurance is (a) required for each item of construction machinery on the Site owned by the Contractor that has a market value of more than:
$50,000; or
(b) not a contractual requirement. The Contractor is advised to obtain expert advice on the advisability of
insuring plant.
2.0 Conditions of Contract Page 5
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
8.3 and 8.7
(a) The Contractor shall insure as provided in 8.3; (b) The Principal shall insure as provided in 8.7.
8.3.1 or 8.7.1
Public liability insurance shall be effected for an amount not less than $2,000,000.
8.3.2
Motor Vehicle insurance is not required. Motor vehicle third party liability insurance shall be effected for an amount not less than $1,000,000. Evidence of this insurance is not
required by the Principal.
8.4.1 (a) Professional indemnity insurance for design by the Contractor shall be effected for an amount not less than $_______________
(b) Professional indemnity insurance for design by the Contractor is not required.
8.6.2
The existing structures are:
(i)
(ii)
(iii)
8.6
For the insurance policies required under the following clauses:
The insurers are:
8.6.2 (a) N/A
8.6.2 (b) N/A
The deductibles are:
8.6.2 (a) N/A
8.6.2 (b) N/A
The exclusions and other limitations, if any, are:
8.6.2 (a) N/A
8.6.2 (b) N/A
8.78.78.78.7
For the insurance policy required under clause 8.7:
The insurers are: _____________________________________________________
The deductibles are: _____________________________________________________
The exclusions and other limitations, if any, are: ______________________________
Amount of liability insurance cover under clause 8.7 for any one claim or series of claims arising out of the same occurrence:
$________________________
10.2.1
The periods to be used for calculating the Due Date for Completion are:
(a) In respect of the Contract Works 9 Weeks (including Anniversary Day and Waitangi Day); (b) In respect of Separable Portions
(i) _______________________________ : ________ Weeks
(ii) _______________________________ : ________ Weeks
(iii) _______________________________ : ________ Weeks
10.3.110.3.110.3.110.3.1(b)(b)(b)(b) (as amended by Appendix Appendix Appendix Appendix B3B3B3B3) (a) Allowance for inclement weather 10 Working Days.
(b) No allowance for inclement weather.
10.4.510.4.510.4.510.4.5 Prior to the issue of the certificate of Practical Completion:
(a) A producer statement in the form of the Sixth Schedule is required;
(b) Producer statements are required as set out in the following parts of the Contract Documents:
2.0 Conditions of Contract Page 6
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
(i) ____________________________________________________________
(ii) ____________________________________________________________
(iii) ____________________________________________________________
(c) A producer statement is not required.
10.5.110.5.110.5.110.5.1 (a) No liquidated damages provided, actual damages may be recovered from the Contractor.
(b) Liquidated damages shall be applied as follows:
(a) In respect of the Contract Works $$$$155155155155 per Week; (b) In respect of Separable Portions:
(i) ______________________________ : $____________ per Week
(ii) ______________________________ : $____________ per Week
(iii) ______________________________ : $____________ per Week
10.6.110.6.110.6.110.6.1
(a) A bonus shall not be payable. (b) A bonus shall be paid as follows:
(a) In respect of the Contract Works $_______________ per Week;
(b) In respect of Separable Portions:
(i) ______________________________ : $____________ per Week
(ii) ______________________________ : $____________ per Week
(iii) ______________________________ : $____________ per Week
11.1.111.1.111.1.111.1.1
The Period of Defects Liability shall be:
(a) In respect of the Contract Works 52 Weeks; (b) In respect of Separable Portions:
(i) ______________________________ : $____________ per Week
(ii) ______________________________ : $____________ per Week
(iii) ______________________________ : $____________ per Week
2.0 Conditions of Contract Page 7
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
11.3.211.3.211.3.211.3.2
Prior to the issue of the Defects Liability Certificate: (a) A producer statement in the form of the Sixth Schedule is required;
(b) Producer statements are required as set out in the following parts of the Contract Documents:
(i)
(ii)
(iii)
(c) A producer statement is not required.
11.5.111.5.111.5.111.5.1 (a) The Contractor shall provide guarantees as set out below:
________________________________________________________________
(b) No guarantees are required.
11.5.211.5.211.5.211.5.2
The form of guarantee shall be in the form annexed as the __________ Schedule.
12.1.212.1.212.1.212.1.2(b)(iv)(b)(iv)(b)(iv)(b)(iv) (a) Advances for Temporary Works, Plant, or Materials not yet on Site shall be made to the Contractor in accordance with:
(i) The following conditions:
___________________________________________________________
(ii) The conditions attached in ____________________________________
(b) Advances for Temporary Works, Plant or Materials not yet on Site shall not be made to the Contractor.
(c) No advances payable.
12.3.112.3.112.3.112.3.1
The percentage to be retained from each progress payment and the limit of the total sums retained shall be:
(a) 5% of the total work and this shall not be reduced on completion.
(b) The above retention is subject to a ceiling of $20,000 and (c) Where there are Separable Portions each will be accounted for separately insofar as retention is concerned.
(d) No retentions will be withheld.
12.3.112.3.112.3.112.3.1 No retentions will be withheld.
12.3.312.3.312.3.312.3.3
(a) Bonds will not be accepted in lieu of retentions. (b) Bonds will be accepted in lieu of retentions.
12.8.212.8.212.8.212.8.2
Cost fluctuation adjustments:
(a) Shall not be paid; (b) Shall be paid in accordance with Appendix A (which is part of NZS 3910. The indices shall be as follows:
- Labour Cost Index, use Series Ref. SG51E9 (Table 4.03) (Salary & Wages; Construction)
- Producers Price Index, use Series Ref. SNE (Table 6.08) (Inputs; Construction)
(c) Shall be paid as set out in the _____________ Schedule.
12.9.112.9.112.9.112.9.1
(a) Provisional Sums, if any, are included in the schedule of quantities; (b) There is no schedule of quantities and the Provisional Sums included in the contract are:
(i) ______________________________ : $_________________
(ii) ______________________________ : $_________________
(iii) ______________________________ : $_________________
(iv) ______________________________ : $_________________
(c) There are no Provisional Sums.
12.9.2(b)12.9.2(b)12.9.2(b)12.9.2(b)
Delete this clause.
12.10.112.10.112.10.112.10.1
2.0 Conditions of Contract Page 8
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
(a) Prime Cost Sums, if any, are included in the schedule of quantities;
(b) There is no schedule of quantities and the Prime Cost Sums included in the contract are:
(i) ______________________________ : $_________________
(ii) ______________________________ : $_________________
(iii) ______________________________ : $_________________
(iv) ______________________________ : $_________________
(c) There are no Prime Cost Sums.
12.11.112.11.112.11.112.11.1
The contingency sum (if any) included in the contract is shown in the schedule of prices.
12.12.212.12.212.12.212.12.2
This clause applies and the Principal shall issue the payment schedule in the form of a GST Invoice;
OR
Delete this clause, and the Contractor shall submit his claim in the form of a GST Invoice.
14.2.114.2.114.2.114.2.1
Add “(d) The Contractor failing to provide the level of insurance offered in their tender.”
15.1.215.1.215.1.215.1.2
For the purpose of service of payment claims or notices, the postal address of:
(a) The Principal is that given in clause 1.2
(b) The Engineer is that given in clause 6.1.2
(c) The Contractor is that given in the Form of Tender in the Tender Documents.
2.0 Conditions of Contract Page 9
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
FIRST SCHEDULE
SPECIAL CONDITIONS OF CONTRACT
(Clause numbers refer to General Conditions)
PART B – OTHER CONDITIONS OF CONTRACT
1.21.21.21.2 Definitions:
Variation. Add to end: “A variation is only a Variation if it is in writing, stated to be a Variation, and signed by the
Engineer.”
5.18.35.18.35.18.35.18.3 Delete (a) and replace with the following:
“(a) Prior to practical completion, the Contractor shall submit to the Engineer for approval the as-built drawings
and operation and maintenance manuals which the Contractor has been preparing and finalising
continuously during the course of the contract. The Contractor shall provide advice and assistance to the
Principal and engineer wherever shortcomings in the as-built drawings and manuals make this necessary.”
5.18.35.18.35.18.35.18.3 Delete (b) and replace with the following:
“(b) Prior to the end of the period of defects liability, the Contractor shall submit to the Engineer for his/her
approval, the updated as-built drawings and operational manuals taking into account any work carried out
after practical completion, and any comments, corrections or further information required by the Engineer
for his/her approval.”
6.1.26.1.26.1.26.1.2 Add to end of clause: “It shall be sufficient if the Engineer is named as being the holder for the time being
of a specific office.”
6.3.3(b)6.3.3(b)6.3.3(b)6.3.3(b) Add at the beginning: “The issuing and valuing of Variations, …”
9.2.19.2.19.2.19.2.1 Delete: “… an order in writing from …” and replace with “… a written Variation order signed by …”
9.2.29.2.29.2.29.2.2 Delete from 4th line of the clause: “… or as soon as practicable thereafter …” and replace with “… and in
any event, before commencing the work, …”
9.2.39.2.39.2.39.2.3 Delete from 3rd line of the clause: “… or as soon as practicable thereafter …” and replace with “… and in any
event, before commencing the work, …”
9.2.49.2.49.2.49.2.4 Add to end of clause: “…, provided that the written record specifically quotes the relevant clause by
number, e.g. “The Contractor gave a clause 9.2.2 Notice that ...”
9.3.19.3.19.3.19.3.1 Delete the whole clause and replace with: “The value, or method of valuing, each Variation shall be
determined by agreement between the Contractor and Engineer and recorded on the written Variation order before
work commences. This may be an agreed Lump Sum, or an agreed rate subject to a quantity to be confirmed by
measurement, a combination of these, or it may be an agreement that it be valued according to this clause 9.3. If
the Variation is based on an agreed lump sum or agreed rate or combination thereof, then it shall be deemed that
the lump sum and/or rate includes profit; and if the net effect of the Variation entitles the Contractor to an
Extension of Time, then it shall be deemed that the lump sum or rate also includes compensation for time based
cost. If a written Variation Order is issued without specifying a value, or method of valuing, then the value shall be
determined by the Engineer in accordance with this clause 9.3.”
9.3.29.3.29.3.29.3.2 Add to clause: “For removal of any doubt, nothing in this clause is to be interpreted as allowing the
Contractor to proceed with any variation before the written Variation order, signed by the Engineer, has been
issued.”
9.3.10(a)9.3.10(a)9.3.10(a)9.3.10(a) Insert into 4th line: “… allowance for profit. If the Variation order was valued by agreement between
the Contractor and Engineer, either by lump sum, or by rate, or both, then it shall be deemed that the agreed
2.0 Conditions of Contract Page 10
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
lump sum or rate includes profit and compensation for time based cost. In this case no further compensation
will be paid. To the extent that …”
9.3.149.3.149.3.149.3.14 Add at the beginning of the clause: “If the Variation order has been valued by agreement between
Contractor and Engineer, then it shall be deemed that the agreed value includes the cost of processing the
Variation. In this case no further compensation will be paid if the Variation proceeds. If the Variation does not
proceed, then the Contractor shall be entitled to the reasonable cost of processing the Variation. If this
reasonable cost has not already been agreed, then it shall be calculated as follows. If the conditions …”
9.3.149.3.149.3.149.3.14 Add after the first sentence of the clause “… subject to a $1,000 ceiling. If the Contractor expects that
the Variation processing fee as calculated will exceed this ceiling, he should notify the Engineer before
commencing with any processing and should only continue if the Engineer has specifically authorised the
increased amount.”
9.5.29.5.29.5.29.5.2 Add to clause: “… confirm such notification in writing, quoting this clause by number e.g. “This is a clause
9.5.2 Notice that ...”
9.5.39.5.39.5.39.5.3 Add to clause: “The Contractor shall not commence any work in respect of such conditions unless or until
the Engineer has issued a Variation order, or until the matter is otherwise resolved. If the Contractor commences
any work without a Variation order, then it shall be deemed that all the conditions encountered by the Contractor in
the course of such work as is completed in the absence of, or up to, the issue of a Variation order are not
Unforeseen Physical Conditions.”
10.3.1(b)10.3.1(b)10.3.1(b)10.3.1(b) Add “… with the progress of the works, occurring prior to the due date for completion, or”
10.3.2(a)10.3.2(a)10.3.2(a)10.3.2(a) Add to clause: “The Contractor notifies the Engineer in writing that it claims an extension …”
10.3.2(b)10.3.2(b)10.3.2(b)10.3.2(b) Delete: “..., or as soon as practicable thereafter;”
10.4.110.4.110.4.110.4.1 Delete opening paragraph and replace with the following: “Practical completion is that stage in the
execution of the work under the contract when the contract works or any separable portion, including as-built
drawings and/or manuals where required, are final and complete except for minor omissions and minor
defects.” (a), (b) & (c) remain unchanged.
12.9.2(b)12.9.2(b)12.9.2(b)12.9.2(b) Delete whole paragraph.
2.0 Conditions of Contract Page 11
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
SECOND SCHEDULE
FORM OF CONTRACT AGREEMENT
CONTRACT FOR: EW13/20 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
THIS AGREEMENT is made on __________________________________ 20
BETWEEN ___________________________________________________ (“the Contractor”)
and the GISBORNE DISTRICT COUNCIL, a Corporation constituted under the provisions of the Local Government
Act, of Gisborne (“the Principal”).
IT IS AGREED as follows:
1.1.1.1. THETHETHETHE Contractor shall carry out the obligations imposed on the Contractor by the Contract Documents.
2.2.2.2. THETHETHETHE Principal shall pay the Contractor the sum of $___________________________
or such greater or less sum as shall become payable under the Contract Documents together with
Goods and Services Tax at the times and in the manner provided in the Contract Documents.
3.3.3.3. EACHEACHEACHEACH party shall carry out and fulfil all other obligations imposed on that party by the Contract
Documents.
4.4.4.4. THETHETHETHE Contract Documents are this Contract Agreement and the following which form part of this
agreement:
(a) Notification of Acceptance of Tender
(b) Form of Tender
(c) Preamble to Schedule of Prices
(d) Schedule of Prices
(e) Preamble to Schedule of Dayworks Rates
(f) Schedule of Dayworks Rates
(g) Schedule of Plant Available
(h) Schedule of Materials
(i) Schedule of Proposed Sub-Contractors
(j) Schedule of Tenderer’s Current Commitments
(k) Safety Declaration for Contractors
(l) Notices to Tenderers
(m) Conditions of Tendering
(n) Conditions of Contract
(o) Specifications
(p) Appendices
(q) Drawings
(r) Additional Documents as follows:
(i) ____________________________________________________
2.0 Conditions of Contract Page 12
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
EXECUTED by ) in the presence of: ) _______________________________________ ) Authorised Signatory ) ) ) _______________________________________ ) Authorised Signatory in the presence of: Witness Signature _____________________________________ Witness Name _____________________________________ Witness Occupation _____________________________________ Witness Address _____________________________________
EXECUTED by GISBORNE DISTRICT COUNCIL )
by Judy Ellen Campbell )
) ________________________________________ Chief Executive in the presence of: Witness Signature _____________________________________ Witness Name _____________________________________ Witness Occupation _____________________________________ Witness Address _____________________________________
2.0 Conditions of Contract Page 13
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
Eighth schedule
INFORMATION AS TO PUBLIC LIABILITY INSURANCE
To Whom It May Concern: From: ___________________________________________________________________________________________
(Name of insurance company) ___________________________________________________________________________________________________
(Branch) ___________________________________________________________________________________________________
(Address) We confirm having effected public liability insurance for: ___________________________________________________________________________________________________
(The Contractor) ___________________________________________________________________________________________________
(The Principal) In respect of: EW13/20 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
(Project Title) Annual policy Yes / No
Policy expiry date:
8.3.1 The limit of indemnity $ (Plus GST)
Sub limit insured for vibration, removal or weakening of support $ (Plus GST)
Deductible is (GST inclusive) $
Deductible for vibration, removal or weakening of support (GST inclusive) $
We advise that “additional” terms, copy attached, have been specifically applied to this
project
Yes / No
The policy covers liability arising out of:
The ownership / use of construction machinery not required to be registered for road use Yes / No
The use of hired plant Yes / No
The ownership / use of watercraft up to 8 m Yes / No
The ownership / use of aircraft Yes / No
The use of explosives Yes / No
8.5.3, 8.8.4 Policy cover terms included are:
(a) Automatic reinstatement Yes / No
(b) No cancellation for non-payment without prior notification Yes / No
(c) Severally insured Yes / No
(d) No settlement delay due to exercise of subrogation Yes / No
2.0 Conditions of Contract Page 14
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
We undertake that this policy will not be cancelled or amended by us without written advice to the insured party which has
arranged the insurances.
The insurance issued is subject to the terms and conditions of the policy. We do not warrant that this policy complies with
the requirements of NZS 3910:2003.
Insurance Company Stamp ____________________________ Date _____________________ (Or name of insurance broking company confirming cover) SIGNED BY ________________________________ SIGNATORY TITLE ________________________________ (Clause numbers refer to NZS 3910:2003 and are for information only)
2.0 Conditions of Contract Page 15
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
TENTH SCHEDULE
INFORMATION AS TO CONTRACTOR’S MOTOR VEHICLE INSURANCE To Whom It May Concern: From: ___________________________________________________________________________________ (Name of insurance company) __________________________________________________________________________________________ (Branch) __________________________________________________________________________________________ (Address) We confirm having effected motor fleet insurance for: __________________________________________________________________________________________ (The Contractor) __________________________________________________________________________________________
(The Principal) In respect of: EW13/20: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY (Project Title) Annual policy Yes / No Policy expiry date: 8.3.1 The sums insured are: Section 2 - liability $ (Plus GST) The policy deductibles are: Section 2 (GST inclusive) $ We advise that “special” terms, copy attached, have been applied to this policy Yes / No 8.5.3 Policy cover terms included are: (a) Automatic reinstatement Yes / No (b) No cancellation for non-payment without prior notification Yes / No (c) No settlement delay due to exercise of subrogation Yes / No We undertake that this policy will not be cancelled or amended by us within the period of insurance without written advice to the insured party which has arranged the insurances. The insurance issued is subject to the terms and conditions of the policy. We do not warrant that this policy complies with the requirements of NZS 3910:2003. Insurance Company Stamp ____________________________ Date _____________________ (Or name of insurance broking company confirming cover) SIGNED BY ________________________________ SIGNATORY TITLE ________________________________ (Clause numbers refer to NZS 3910:2003 and are for information only)
2.0 Conditions of Contract Page 16
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
2.3 ANNEXURES
• ANNEXURE A (COST FLUCTUATION ADJUSTMENT) is deleted.
• ANNEXURE B (GENERAL CONDITIONS APPLYING TO PRINCIPAL’S BOND) is deleted.
• ANNEXURE C (SUPPORTING INFORMATION) is included.
• ANNEXURE D (TRAFFIC CONTROL) is included.
• ANNEXURE E (OCCUPATIONAL HEALTH AND SAFETY) is included.
• ANNEXURE F (CONSENTS AND LICENCES WHICH WILL BE OBTAINED BY THE PRINCIPAL) is included.
• ANNEXURE G (GUARANTEES TO BE PROVIDED) not applicable.
• ANNEXURE H (PERFORMANCE REPORT) is deleted.
2.0 Conditions of Contract Page 17
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
ANNEXURE C
SUPPORTING INFORMATION
In accordance with the Conditions of Tendering, Tenderers are required to provide information based on the six non-
price attributes defined below in the support of their Tender.
1. Relevant Experience:::: The Tenderer's previous experience, particularly in technical areas comparable to
this Contract. Tenderers shall include a statement of knowledge of local conditions and of appropriate
works. Where sub-contractors are proposed to be engaged, a statement of their relevant experience shall
also be supplied.
For newly formed firms, state the name of the company in which the experience is claimed, the person
concerned, and his/her responsibility in the project. Where staff named in this Tender were not involved in
projects detailed, comment on extent to which relevant experience will benefit this contract.
2. Technical Skills:::: The ability of the personnel the Tenderer proposes to employ, with particular regard to
their skills and experience, particularly in technical areas applicable to this Contract.
Tenderers shall nominate the following key personnel to be employed on the contract works. These details
shall include a brief resume of each person's experience and qualifications that clearly demonstrate that
their experience and skills are compatible with the project.
(i) Contractor's Representative: Refer Clause 5.2 of NZS3910:2003 General Conditions of
Contract.
(ii) Contract Manager: Responsible for the overall management of the contract works.
(ii) Site Manager: Responsible for the site works for the contract.
(iii) Safety Supervisor: Responsible for ensuring that the requirements of the Health
and Safety in Employment Act are complied with.
3. Methodology: The procedures and equipment the Tenderer proposes to use to achieve the specified end
result.
Tenderers are reminded that each attribute shall be scored on a pass/fail basis. Any attribute which scores a
fail will exclude that tender from further consideration.
2.0 Conditions of Contract Page 18
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
ANNEXURE D TRAFFIC CONTROL The Contractor shall be responsible for traffic control through the works at all times. Traffic control and signs layout shall comply specifically with “Temporary Traffic Management for Local Roads - Supplement to Transit New Zealand COPTTM: 1st Edition September 2005”, the relevant requirements of which shall be mandatory. Copies may be purchased from the Roading Engineer. The Contractor shall ensure that traffic signs, barricades and lighting are checked each morning and at the end of each working day, inclusive of weekends and public holidays, and any deficiencies found shall be made good immediately. Failure to provide adequate traffic control (inclusive of delineation cones, stop/go control and night lights), can result in suspension of the works and/or provision of the necessary control by Council at the Contractor's expense. The Contractor shall notify the Police, NZ Fire Service and St John Ambulance Association where the road will be blocked completely at any stage or where traffic flow will have restricted movement. During the working day, through traffic may be excluded only at the discretion of the Engineer. Reasonable access shall be afforded residents to their properties and to businesses in the street at all times. Vehicular access to properties shall be temporarily restored each night before the Contractor leaves the work site. When lime or cement is used “Lime (cement) Splashes : Wash Car Today” signs must be displayed in addition to above requirements. No traffic is to be delayed more than five minutes at any time.
2.0 Conditions of Contract Page 19
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
ANNEXURE E
OCCUPATIONAL HEALTH AND SAFETY
Care shall be taken to ensure that practices and procedures recognise and take full account of the need to
protect the health and safety of the public as well as the Contractor’s employees. Any practices or procedures
endangering public health or safety will be viewed seriously and may be grounds for terminating the contract.
Where excavation takes place, an effective barricade must be erected immediately work commences and
maintained until the surface is adequately restored.
The Contractor shall in execution of the work comply with:
(a) the Health & Safety in Employment Act 1992 and Amendments; and
(b) the Safety Requirements Applicable to Work for Gisborne District Council (attached).
The Contractor is assumed to be familiar with all the above requirements and the implications thereof for the
execution of the work. The Contractor shall complete and sign the Safety Declaration for Contractors included in
the tender documents.
Failure by the Contractor to comply with the requirements specified herein shall be regarded as a breach of this
contract. In the event of default, the Gisborne District Council shall be entitled to immediately suspend the work
at the Contractor's expense until any such failure has been remedied. This provision is in addition to the
remedies detailed in Section 13 of the General Conditions.
2.0 Conditions of Contract Page 20
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
SAFETY REQUIREMENTS APPLICABLE TO WORK FORSAFETY REQUIREMENTS APPLICABLE TO WORK FORSAFETY REQUIREMENTS APPLICABLE TO WORK FORSAFETY REQUIREMENTS APPLICABLE TO WORK FOR GISBORNE DISTRICT COUNCILGISBORNE DISTRICT COUNCILGISBORNE DISTRICT COUNCILGISBORNE DISTRICT COUNCIL
1. Responsibility
1.1 The Contractor shall in the execution of the work be fully responsible for compliance with:
(a) relevant local and national laws and regulations;
(b) local and national standards or codes of practice whichever are the more stringent unless
specified otherwise;
(c) the Council's regulations.
1.2 The Contractor shall be fully responsible for supervision of his/her personnel to ensure that they strictly
adhere to all applicable safety requirements.
1.3 The Contractor's representative shall be responsible for co-ordinating the Contractor's safety activities.
He/she and the Council's representative shall be the focal points for all safety matters.
2. Recruitment, Training and Key Personnel
2.1 The Council may, if it so wishes, monitor the Contractor's staff recruitment criteria. The Contractor shall
provide the relevant information for this.
2.2 When asked to do so by the Council, the Contractor's personnel shall demonstrate their ability and skills
relative to their qualifications.
2.3 The Contractor shall submit details of the safety qualifications and experience of his/her supervisors in
key positions and of other key personnel.
2.4 The Contractor shall at his/her own expense ensure that all his/her personnel and sub-contractor's
personnel have been given the necessary safety, survival and job-related training required by law, Council
regulations and good practice, prior to the start of the work, and will provide a certificate to that effect (if
so required).
2.5 The Contractor's personnel shall participate in any additional methods, materials and site-specific safety
training which may be provided by the Council.
2.6 The Engineer may refuse access to any work site when, in the Engineer's opinion, the Contractor does not
comply with Council standards for safe and good workmanship owing to attitude, lack of skill or
insufficient training or experience.
2.0 Conditions of Contract Page 21
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
3. Safety Meetings
3.1 The Contractor shall be responsible for maintaining and enhancing the safety awareness of his/her
personnel and sub-contractors personnel, including arranging his/her own safety meeting and
participating as appropriate in safety meetings held by the Council or its other Contractors.
3.2 The Contractor will inform the Council representative of the time and place of safety meetings arranged
by the Contractor.
3.3 Copies of minutes of the Contractor's safety meetings shall be sent to the Council. The Contractor's and
sub-contractor's personnel are to be encouraged to contribute actively to safety meetings and to identify
safety topics for inclusion in the agenda for each safety meeting.
4. Reporting of Accidents
4.1 The Contractor shall have an accident reporting system conforming to the Health & Safety in Employment
Act 1992 and Regulations 1995.
4.2 Without in any way diminishing his/her other reporting responsibilities, the Contractor shall immediately
notify the Council of all accidents resulting in:
• fatalities and other lost-time injuries to his/her personnel or sub-contractor’s personnel
• injury to third parties
• damage to any plant or equipment
• actual or potential damage to the environment (spillages, etc)
• outbreak of fire.
Immediate notification shall be followed by a full written report within 24 hours.
4.3 Both those accidents referred to in 4.2 and those resulting in less serious injuries shall be recorded and
the statistics reported to the Council.
4.4 Upon completion of the work under the contract and/or on an annual basis, whichever is more frequent,
the Contractor shall prepare a summary report of his/her safety performance including statistics.
5. Occupational Health and Hygiene
5.1 The Contractor shall be responsible for the medical welfare of his/her own and sub-contractor personnel
and shall provide for:
• facilities for administering first aid
• periodic medical examinations
• arrangements for professional medical treatment
• hospitalisation.
5.2 The Contractor shall ensure that all his/her personnel and sub-contractor's personnel are medically fit to
perform their work. If requested by the Council, the Contractor shall provide health certificates for
his/her own and sub-contractor personnel.
5.3 If applicable, the Contractor shall adhere to Government regulations or Council guidelines for medical
surveillance or industrial hygiene monitoring.
5.4 The Contractor shall ensure that his/her personnel and sub-contractor's personnel shall maintain the
highest standards of hygiene.
2.0 Conditions of Contract Page 22
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
5.5 If separate accommodation for Contractor personnel is provided (e.g. Contractor huts), the Contractor
shall comply with the Council’s standards for: hygiene, sanitation, sewage disposal, water supply,
sleeping quarters, food establishments, laundry and garbage disposal.
6. Environment
6.1 The Contractor shall pay due regard to the environment by preserving air, water, soil, animal and plant
life from adverse effects of the Contractor's activities, and minimising any nuisance which may arise from
such operations.
7. Alcohol and Drugs
7.1 The Contractor shall ensure that at any time during the performance of the work his/her personnel are
neither under the influence of nor partake of any alcoholic liquor, drug or intoxicating substance, other
than for bona fide medical reasons or other proper reasons which must first be approved by the Council.
8. Technical/Safety Audit by the Council
8.1 The Contractor shall allow the Council's representatives and nominees access at any time to plant,
equipment, personnel and records when requested, to enable the Council to inspect or audit any aspect
of the Contractor's operations relevant to safety and the work environment.
8.2 The Contractor shall establish and regularly update a written system of checks and audits to ensure that
the work is being performed in accordance with the safety requirements applicable to the work. A copy of
that system shall be supplied to the Council before work commences and each time the system is
updated.
9. Conduct of Contractor's Personnel
9.1 The Contractor shall instruct his/her personnel to comply with the following:
• No one shall enter any part of the Council's premises, including the work site, other than for the
purpose of carrying out the work. All Contractor personnel needing access will be required to
obtain a pass issued by the Council and to produce it if requested.
• Smoking on the Council's premises is strictly forbidden, except in the authorised smoking rooms or
other designated areas. Anybody found smoking outside the authorised smoking rooms or
designated areas will be immediately removed from the Council's premises.
• On sites requiring hot work permits, no fire or naked light, matches, cigarette lighters, or any
apparatus which can cause ignition, shall be taken onto the Council's premises or elsewhere in
relation to the Contract, as instructed by the Council, unless covered by a hot work permit (referred
to in 10 below).
• Personal protective equipment shall be used and worn in accordance with the safety regulations.
• It is essential that good housekeeping is maintained throughout the period of any work, both at the
work site and in and around any temporary buildings. The work site shall be kept tidy at all times,
escape and other access ways kept clear, safety equipment kept accessible, and surplus/scrap
material removed daily. Cleaning up only at the end of a job is not considered sufficient. Spillages
of oil or chemicals shall be cleared up immediately in view of the hazards from fire, slippery
surfaces, toxic substances, etc. Appropriate safety precautions shall be taken during the clearing
up.
10. Permits
2.0 Conditions of Contract Page 23
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
10.1 The Contractor shall be fully aware of the details of the work permit system as laid down in the Council's
regulations.
10.2 Unless the Council expressly states otherwise, the Contractor shall obtain a work permit signed by the
Council's authorised representative before any work is started. The work permit shall be accompanied by
associated permits, such as hot work permit or permits for specific work, and shall define the conditions
under which the work is to be carried out.
10.3 Where potential hazards exist from combustible gases or dusts, a hot work permit shall be obtained for
any work involving the use of fire, naked lights, spark-producing tools, and instruments or other potential
sources of ignition, e.g. welding arcs, combustion engines, torches, matches, lighters etc.
10.4 For specific work such as that on electrical equipment or with radioactive sources or for excavation work,
specific work permits are required.
10.5 It is essential that Contractor personnel read, understand, sign to that effect and carry out any conditions
or precautions laid down in work permits. If any doubts exist, guidance from the Council's representative
shall be obtained.
11. Sub-Contractors
11.1 The Contractor shall inform the Council of names of sub-contractors and obtain the Council's approval
prior to their engagement.
11.2 The Contractor shall ensure that sub-contractors be informed of, and have the opportunity to participate
in the safety activities required by the Council and which the Contractor is obliged to instigate pursuant to
the contract. The Contractor shall stipulate in any sub-contract that the sub-contractor shall take active
steps in the field of safety identical to those required of the Contractor. The Contractor shall regularly
check sub-contractors compliance with the safety requirements.
12. Emergencies
12.1 The Contractor shall establish with the Council, what the arrangements are in the event of an emergency.
12.2 In particular, the Contractor shall ensure that his/her staff are familiar with the essential emergency
equipment, such as breathing apparatus, life jackets and fire extinguishers, the use of which shall be
demonstrated and practised if so requested by the Engineer.
12.3 The Contractor shall check the emergency procedures and the location and condition of the emergency
equipment. If the Contractor considers these to be unsatisfactory or not fully appropriate for the work,
he/she shall take steps in consultation with the Council to improve them.
2.0 Conditions of Contract Page 24
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
ANNEXURE F
CONSENTS AND LICENCES WHICH WILL BE OBTAINED BY THE PRINCIPAL
The Principal has applied for and received a Resource Consent for the project, a copy of which is attached in the Appendices.
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
3.0 SPECIFICATIONS
3.0 Specifications Page 1
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
3.1 GENERAL SPECIFICATION 3.1.1 LOCATION OF CONTRACT
This Contract is to construct a cycle and walkway path from Stanley Road, through the back of Awapuni
School to Waikanae Creek, then across the Creek (bridge construction not in contract) with a link to
Anzac Street and the main route heading through Alfred Cox Park to Grey Street. Refer to the drawings
for a precise location of the works.
3.1.2 SCOPE OF WORK
The scope of Works is as follows. The path will consist of a nominal 3m wide, 100 mm thick reinforced concrete slab (150mm in places) on a bed of granular subbase. The route of the path will meander through the site making the best use of the existing flat terrain and minimising the amount of earthworks involved. The route also includes widened concrete entrances at Stanley Road and Grey Street and intermediate concrete node points. The Contractor shall note that the standard of the finished project is required to be very high and must be undertaken by qualified tradespeople. The path itself must flow smoothly through the site and have no sudden changes of line or level. A very good concrete finish is required, with no ponding of water on the surface or uncontrolled cracking. The adjacent ground cover must be reinstated to as good as original, and the levels/shape must be such that it does not retain water and is readily mowable, level with the edge of the slab. The Contract comprises the supply of plant, labour and materials for the completion of the Works, all necessary reinstatement and clearing of the site on completion to at least the equivalent standard that existed prior to commencing the work, and to the satisfaction of the Engineer. The works include but are not limited to the following: General
• Establish Contractor’s plant and labour on site. • Provide and maintain a construction programme. • Provide and implement a Quality Control Plan. • Provide and implement a Traffic Management Plan to manage traffic (if any) and pedestrian
movements in the vicinity of the worksite. • Site clearance and preparation, including any relocation work. • Setting out Earthworks
• Strip topsoil to stockpile • Excavation to required profile (cut-to-fill) including undercutting of soft areas and install
drainage to control surface water Footpath • Construct concrete cycleway and walkway track • Construct ancillary concrete paths and features Landscaping • Place topsoil • Sow grass areas and maintain Miscellaneous Works
3.0 Specifications Page 2
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
• Drainage
• Railway crossing including fencing and signage Not included in Contract: • Bridge construction • Furniture (seats, bins, lights, bollards) • Tree removal and planting
• Information signage.
3.1.3 OVERVIEW OF WORK
The following is a descriptive ‘walk-through’ of the Site starting at Stanley Road (NB the work is described in more detail in the Technical Specification): Stanley Road to Awapuni School Stanley Road to Awapuni School Stanley Road to Awapuni School Stanley Road to Awapuni School EntranceEntranceEntranceEntrance (refer drawing Sheet 02) There is an existing paving block and concrete slab walkway that currently leads school children from the school pick-up point on Stanley Road to the back entrance of Awapuni School. This path is to be uplifted, the blocks delivered to GDC’s yard at Makaraka and the waste concrete taken off site for recycling. The low level timber barrier is also to be removed to waste (leaving the chained-off access barrier). The new path is to veer away from the boundary fence and skirt around a tree before heading into the school grounds. The line of the original path will be topsoiled and re-grassed. There is a pronounced dip in the ground near the start of the path and this will need to be filled and evened out. There are indications in at least one area that the ground is soft and there may be a drainage problem. Undercutting of weak ground will be necessary, including stabilising and compaction of hardfill. The walkway entrance at Stanley Road is to be widened and will have a feature wall with a grassy bank (refer drawing Sheets 6 and 14). The concrete surface of the entrance area will contain a contrasting concrete pattern effect (decorative concrete band). Bollards will be installed (by others) to prevent vehicle access. The adjacent chained access for maintenance vehicles is to be retained. Awapuni School to New BridgeAwapuni School to New BridgeAwapuni School to New BridgeAwapuni School to New Bridge (refer drawing Sheet 03) As the walkway enters the school grounds it heads towards the main school buildings for a short distance before veering off towards the school carpark. The path then makes its way alongside existing palm trees until it merges with the edge of the carpark. There are a few bollards and a chain that are to be uplifted and relocated. Once past the carpark the path heads towards the creek crossing. The next section runs along the back of what was previously a timber treatment yard and the ground is likely to contain waste timber products and contaminated materials. The intention here is to disturb the ground as little as possible so as not to uncover buried waste. Surface material that is removed in order to found the path on firm ground must be taken to an approved site that will accept such material. Filling will be required to gradually raise the path up to the level of the railway track. An open drain running alongside the railway embankment will require culverting and fallen trees removed. The path narrows to 2m as it crosses the railway line and to match the bridge width. A formal ‘maze’ railway crossing is to be installed either side of the tracks as required by KiwiRail (refer drawing Sheet 07). Although this railway line is used infrequently, THE Contractor shall adhere to any reasonable conditions applicable to working on or alongside railway lines. It is expected that the bridge construction will be proceeding at the same time as the walkway and, due to the likely overlap between the bridge abutment and the far (river) ‘maze’, close cooperation and coordination will be required between contractors. The path in the vicinity of the bridge will contain a timber sleeper feature at both approaches. New New New New Bridge to Anzac StreetBridge to Anzac StreetBridge to Anzac StreetBridge to Anzac Street (refer drawing Sheet 03) The bridge contractor’s work will terminate at the back of the ‘Park’ abutment, and this is where the path will recommence. Once again it will gradually increase in width and will contain the ‘sleeper’ feature. The path will head directly towards an existing park entranceway located between houses on
3.0 Specifications Page 3
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
Anzac Street. Part way along there will be a 3-leg ‘node point’ where the path will also veer off along Alfred Cox Park. This node point will include a central area of strengthened concrete to accommodate an art feature, as well as contrasting concrete bands at each leg. Two legs of this section of the walkway will include a thickened (150mm) concrete path to allow access for maintenance vehicles. This area of the park contains a disused BMX Bike trackway, which is to be removed and the ground levelled. Suitable fill material is to be salvaged for reuse but all other material (tyres, concrete and timber) is to be taken off site, and the area contoured, topsoiled and regrassed. The path up to Anzac Street will be located between existing garden boundary fencing and will terminate at the street footpath. Bollards will be installed at a later date to restrict vehicle access. Note that Alfred Cox Park has been formed from a capped-off city waste disposal site. In order to avoid exposing waste material (which may require removal to an approved disposal facility) it is intended to restrict excavation work to the minimum required to construct the walkway. BMX Track to Grey StreetBMX Track to Grey StreetBMX Track to Grey StreetBMX Track to Grey Street (refer drawing Sheet 04) Much of the Park section of the walkway will meander between existing trees and will follow the contours of the park surface, with cuts and fills to form a smoothly undulating pathway. Care must be taken to ensure that the walkway does not form a dam and restrict the flow of surface water to the creek. One low section in particular will have a culvert installed to direct water under the path. Additional drainage may be necessary depending on the level of the new path and what re-contouring can achieve. The park contains baskets and posts for ‘Frisbee Golf’. Four posts are in the way of the new walkway and they are to be removed and relocated at the direction of GDC and staff working at the nearby Visitor’s Centre. Two ‘nodal points’ are introduced along the path to allow for rest and lookout areas (refer drawing Sheets 04, 09 and 10). The first makes use of a raised area near a sewer pipe that crosses the creek. A concrete platform is to be constructed and will contain seating and bins (by others). The concrete at these nodes will be in contrast to the path concrete, as will short lengths of path at either leg leading to the platform. The second ‘nodal point’ is similar, and both will contain provision for a statue to be installed in the future. Near the Grey Street entrance (refer drawing Sheets 05 and 11) the walkway will replace an existing paver block path (pavers to be transported to a site at Makaraka). It will once again meander between trees and terminate at a concrete platform similar to that at Stanley Road, with contrasting concrete finishes, bollards and seating (by others). There is a significant rise up to the tie-in at the existing footpath and filling will be required to reduce the slope of the path. This contract will be part of a city-wide cycle and walkway network as well as acting as a safe route for school children, and therefore good customer relations and a high standard of workmanship are paramount to the successful completion of the project. In particular the contractor will be expected to: • Adhere to the agreed programme and avoid any public perception that work has stalled for no
apparent reason.
• Keep affected parties informed as to the intended programme of the work and the impact that
the work will have on them, and update as necessary.
• Have in place and be able to demonstrate a system for dealing with public complaints.
• Ensure that the construction site is kept safe 24/7 from human interference and from
inclement conditions.
• Accommodate safe alternative routes for pedestrians (particularly school children) so that
normal access and usage can be maintained.
3.0 Specifications Page 4
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
The above factors will be taken into account when assessing whether or not the contractor has met expectations and the intent of the contract.
3.1.4 STANDARD SPECIFICATIONS AND PUBLICATIONS
This contract shall be carried out in accordance with this specification together with the NZTA, Opus and NZ Standards referred to in the Technical Specification. In addition, the following shall apply:
TNZ TQS2 Transit New Zealand Quality Standard TNZ Q/3 Normal QA Level Contracts TNZ Code of Practice for Temporary Traffic Management The Construction Act 1959 The Construction Regulations 1961 The Building Act 1991 The Health & Safety in Employment Act 1992 The Resource Management Act 1991 It is the Contractor’s responsibility to obtain access to a set of the publications referred to. The Contractor shall be deemed to be familiar with these Standard Specifications and shall be expected to have the specifications on site at all times whenever associated work is being carried out. Copies of TNZ Standard Specifications can be viewed on NZTA’s website: http://www.nzta.govt.nz or at Opus International Consultants Limited, Gisborne Office. NZ Standards are cited throughout the Specification, and they are available for purchase from the Standards Association of New Zealand (SANZ) or can be viewed at Opus International Consultants Limited, Gisborne Office. This Specification (including drawings and attachments) will take precedence over the standard specifications.
3.1.5 HOLD POINTS
Hold Points have been defined at various stages in the construction process to cover specific control points when submission of quality assurance documentation is required and/or the Engineer/Engineer’s Supervisor wishes to have the opportunity to inspect before work proceeds further. Further to Clause 6.4.4 of NZS 3910, the notification of readiness for inspection, recording, measuring and testing shall be a minimum of 24 hours prior to the availability of the work for the inspections etc. The “reasonable time” period shall not be less than 24 hours. Inspections at Hold Points will normally only be carried out between 8 am and 5 pm on Working Days as defined in NZS 3910. Arrangements for inspections outside those times will be entirely at the discretion of the Engineer/Engineer’s Supervisor. The following schedule defines ‘hold points’ when work covered by the specification shall not proceed further until the Engineer has been provided with specified information and/or been given the opportunity to inspect the work.
Hold Point (to be
completed)
(a) Quality Records Required
(b) Work for Inspection
(S) Supply Copy to Engineer
(R) Copy on Request
(A) Agree with Engineer
(I) Available for Inspection
3.0 Specifications Page 5
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
Hold Point (to be
completed)
(a) Quality Records Required
(b) Work for Inspection
(S) Supply Copy to Engineer
(R) Copy on Request
(A) Agree with Engineer
(I) Available for Inspection
Prior to any work
commencing on site
(a) Evidence of insurances,
Programme of Work, Contract
Quality Plan and Traffic
Management Plan for acceptance
by the Engineer.
(a) Evidence of Consents obtained
(S)
(S)
Survey (b) Provide opportunity to check
and adjust set-out pegs before
finalising the path alignment
(I)
Foundations (a) Provide records of Scala testing (S)
Excavation (b) Confirm suitability of excavated
founding level
(A)
Path foundation (a) Confirm depth and compaction
of subbase
(S), (I)
Timber Edging (a) Results confirming correct line
and depth achieved
(S), (A)
Concrete Pavement (a) Confirm source of concrete and
pouring plan
(I)
3.1.6 DRAWINGS
The drawings included as part of the Contract Documents are listed in Section 6.0 Drawings. Should ambiguities be apparent between the plans and the specifications the drawings shall take precedence.
3.1.7 PLANS TO BE KEPT ON JOB
At all times a complete set of plans and specifications is to be kept on the job by the Contractor. The Contractor shall ensure that, before any portion of the work commences, the foreman in charge of the works has studied the plans for that portion, and is familiar with the details of work required, the position of any services and the requirements of the specification relating to the work.
3.1.8 CONTRACTOR TO INSPECT SITE
The Contractor shall be deemed to have visited the site of works, and to have made himself familiar with all local conditions, the accuracy of the information provided, and any other matter that may in any way influence construction of the works.
3.1.9 CONSENTS
A Resource Consent has been obtained and is attached in the Appendices. The Contractor must obtain all other consents necessary to complete the works. The Contractor shall comply with the Conditions imposed on all consents obtained. With reference to the Resource Consent there are a number of Conditions associated with the need to work in the vicinity of the park area (previously a City waste disposal site) and at the rear of the ex-timber treatment yard (near the railway crossing). An assessment of both sites has been carried out which indicates the presence of buried hazardous substances, namely asbestos and arsenic. It is extremely unlikely that such substances will be encountered to any significant extent as in
3.0 Specifications Page 6
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
general the new path will be placed on or above the existing surface and therefore contaminants are unlikely to be disturbed. Where we are excavating below ground level (for reasons of substandard subgrade strength) then such material will need to be removed under controlled conditions (employing suitable safety equipment) and disposed of off-site to a waste disposal location that will accept and treat such waste.
3.1.10 PROGRAMME OF WORK
The Contractor shall submit a detailed programme of work (critical path diagram or dated bar chart that clearly identifies the critical path) within five days of the acceptance of tender or before commencing work on site, whichever is sooner. The submitted programme (the baseline programme) shall identify each operation and show how the work will be carried out within the contract period. The programme shall allow for all constraints to the works either detailed or implied in the documents. The programme shall be updated weekly and a copy submitted with the Contractor’s Weekly Report. The updated programme shall clearly show any variances in the baseline programme, and the Weekly Report must detail reasons for any delay to the programme. The Contractor shall programme the work so as to cause a minimum of inconvenience to affected parties. The programme shall be prepared and electronically stored using Microsoft Project so that it can be readily updated. The programme shall be presented to the Engineer as a clearly readable hard copy in format suited to sheets no larger than A3 size. Due to the restricted width available and the impact of school children using the existing path, the Contractor shall allow in his Programme to complete the section of walkway from Stanley Road to the school entrance during the school holiday period (30 September to 11 October), and this is likely to require that this section be the first to be constructed. The Contractor shall also note that the school property will be used for camping of visitors attending the Rhythm & Vines festival, which will commence on 27 December. The Contractor shall allow for the grounds to be used for this purpose on the lead up to the festival.
3.1.11 WEEKLY REPORTS
In order to provide a record of progress and to keep the Principal up to date it is a requirement of this Contract that the Contractor submit weekly emailed reports to the Engineer summarising progress on site. The reports are required to be submitted by 4:00pm each Friday. The reports shall contain comment on the following: • Comparison of actual progress with the current Programme of Work, including reasons for
delays
• Provide information where Variations or time extension claims are being considered,
• A summary of all works completed during the preceding week, giving the location, extent and
type of work.
• A summary of any quality control testing carried out during the preceding week.
Each weekly report shall be submitted regularly once work has commenced on site. The reports are to be submitted regardless of whether any work has been completed or not.
3.1.12 SITE ESTABLISHMENT AND ACCESS
Access to the southern portion of the Site (south of the Creek) will be via the path entrance at Stanley Road or from within the school grounds (by agreement with school authorities). The northern (Park) portion of the site will be accessed from the Grey Street entrance and from the chained entry points off Anzac Street (key available from GDC). In the case of both the public park and the school grounds the
3.0 Specifications Page 7
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
Contractor must restrict his working area to a minimum so as not to unduly interfere with the proper use of both sites. As stated previously, Alfred Cox Park has been formed on a Council refuse disposal site and the Contractor must take suitable precautions if waste material is exposed. Likewise the area between the railway and the nearby timber yard may contain timber preservative materials and disturbance shall be kept to a minimum.
The Contractor shall keep the Site safe and tidy at all times, and shall avoid the spread of waste material through the park, school and creek areas. Site establishment includes all work involved in the establishment of the Contractor on site, including the provision, maintenance and removal of all temporary works, tidying up on completion, traffic management, and services and general costs (including the provision of as-builts) which are not directly chargeable to other schedule items.
3.1.13 SITE CLEARING AND TIDYING ON COMPLETION
The Contractor shall be responsible for the removal from site of all extraneous materials. Should any accumulation of materials be considered a hazard to the public in general, the Engineer will direct the Contractor in writing to remove such surplus. Should the Contractor fail to comply with the Engineer’s order, the Engineer will arrange for the work to be done and the charges incurred will be deducted from the contract payments. Access to the site with plant will inevitably result in damage to the grassed surface. In order to minimise the need for unnecessary reinstatement at the end of the Contract, the contractor shall keep such access points and tracks to a minimum. At the conclusion of the works the Contractor must restore any damage caused and tidy up, leaving the site of the works in a condition no worse than that existing prior to construction.
3.1.14 CONTRACT QUALITY MANAGER
The Contractor shall nominate a Contracts Quality Manager, who is responsible for the day to day audit of the work and management of the Quality Plan. The Contracts Quality Manager shall carry out inspections of all the work, acknowledge all Hold Points and provide the Engineer with a copy of his inspection checklists with each Weekly Report. The inspection checklists should be sufficiently detailed to include the tolerances and the minimum quality standard required.
3.1.15 CONTRACTOR’S REPRESENTATIVE
Further to Clause 5.2 of NZS 3910, to be acceptable to the Engineer any representative shall have demonstrable experience and competence in the control and site management of the type and scale of works to be carried out under the Contract, including traffic management.
3.1.16 EXISTING SERVICES
A request has been made to service providers to identify existing services within the Site, and these have been annotated on the drawings. Before starting work on Site the Contractor shall liaise with all relevant service providers to update this information and to identify the presence of cables and the like within the Site. Thereafter the Contractor shall allow to work around these services. Should any such services require to be relocated then the Engineer must be advised.
3.1.17 ACCESSIBILITY OF CONTRACTOR
3.0 Specifications Page 8
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
The Contractor’s Representative shall be available on call 24 hours per day to the Engineer. In the event the Contractor’s Representative is unavailable then the Engineer shall be informed and given information to enable similar communication to be maintained with an alternative representative. The Contractor shall ensure that these lines of communication remain open at all times including after hours. The Contractor shall ensure at all times while any work is in progress that a site agent is nominated to be responsible for operations. This site agent shall make himself known to the Engineer in the event that it is necessary for the Engineer to direct operations in the field. The site agent shall ensure that all instructions given by the Engineer are actioned. Such site instruction will generally only be given in relation to matters affecting safety or the protection of assets. Instructions issued to site agents will always be confirmed to the Contractor’s Representative at the earliest convenient time.
3.1.18 ACCESS BY OTHERS
The Contractor shall provide access and reasonable facility to any other individual or organisation duly authorised by the Engineer to work in the general area to which this contract applies. It is anticipated that a parallel contract will be awarded for the construction of a pedestrian footbridge across Waikanae Creek and both contractors will be expected to cooperate fully in order that the project can be completed with the minimum of disruption and delay.
3.1.19 HEALTH AND SAFETY
3.1.19.1 Safety
All work undertaken by the Contractor or his agents under this contract must comply with the Health and Safety in Employment Act 1992. Before any work is commenced on the site and within two weeks of acceptance of tender, the Contractor shall advise the Engineer in writing of the name of ONE person appointed as Safety Supervisor for the work under the Health and Safety in Employment Act 1992. The person shall ensure that all legal requirements and measures for the safety of workers and the public are implemented. This person shall be able to stop or hold work from continuing on any part of the contract, including subcontractors, in the event of any hazards to safety. The Contractor must ensure the site of the works is left in a safe condition after each day’s work. A site-specific Health and Safety Plan shall be prepared for the Contract, the contents of which shall include, but not be limited to: • Contractor’s safety policy • Contractor’s safety training procedures • Site safety management organisation • Site safety personnel and Safety Supervisor • Access restrictions for and induction of visitors to the site • Safety helmet areas • Procedure for identifying and assessing hazards
• Procedure for recording of accidents • Procedure for dealing with emergencies that may arise • Procedure for monitoring health and safety performance • Procedure for monitoring the health of employees where they are exposed to hazards. The Health and Safety Management Plan shall list all known hazards (including those identified below and any others identified by the Contractor) and the measures taken or to be taken to eliminate or
3.0 Specifications Page 9
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
minimise them. It is also to provide for a procedure for identifying and reporting on new hazards by the Contractor’s staff to the Contractor and the Engineer. The known significant hazards on the site include, but are not limited to:
• Vehicular traffic • Construction plant and machinery • Underground and overhead services • Contaminated Land • Noise • Steep, slippery or uneven terrain • Stream or other waterways • Dust • Potential vandalism or break-ins
A copy of the Health and Safety Plan shall be maintained on site at all times, updated as necessary, and made available to the Engineer upon request.
3.1.19.2 Protective Clothing
The Contractor shall ensure that all persons working within the boundaries of the Construction Area,
including the personnel of subcontractors, wear high visibility clothing, safety footwear and any other protective clothing/equipment deemed necessary to carry out the works in a safe manner.
3.1.19.3 Accident Reporting
In the event that an accident occurs on an occupied site (i.e. the Contractor was on site at the time of accident), the Contractor shall provide the following: • Notification within 12 hours of the accident site
• Full details of the event
• A description of the traffic management operating (Stop/Go, 50 km/h, etc)
• Confirming that the site complied in all aspects with any TMP and Health and Safety Plan
• A Contractor assessment of whether there is a possibility that traffic control or worksite
conditions deficiencies may have contributed to the accident.
In the event that an accident occurs at an unoccupied site (i.e. traffic control in place but Contractor not present at the time of the accident), the Contractor shall provide the following: • Notification within five days for any accident that the Contractor becomes aware of
• Confirmation of the status of:
(a) Safety signage
(b) Site conditions at the time
(c) General details of the accident.
3.1.19.4 Working Within a Hazardous Site
The Contractor’s attention is directed to Clause 3.1.8 above which advises that there are potentially hazardous substances below surface level (left over from an old timber treatment site and a capped-off City waste disposal site) and that suitable precautions shall be taken when working in these areas. In particular:
• Wear suitable PPE when working with hazardous material
• Cordon off the site when such materials are exposed or being excavated
• Carte the materials off site using appropriate safety precautions and transport to a disposal site certified to take such material.
3.0 Specifications Page 10
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
3.1.20 PROTECTION OF PUBLIC AND PRIVATE PROPERTY AND SERVICES
The Contractor's attention is particularly drawn to the necessity of adopting measures to protect from damage, trees, fences, hedges, walls, paths, sealed surfaces, entrances, and other service installations, whether in reserves or on adjacent private property. Damage caused by the Contractor’s operations shall be remedied at the Contractor’s expense. The Contractor shall not operate plant with steel tracks on any sealed or concrete surface, except where tyres or planks are provided to protect the surface. The Contractor shall be responsible for the cost of making good any damage to existing services in the execution of the work.
3.1.21 WORKMANSHIP
This is a high-profile contract and therefore a first-class standard of finish is expected through each phase of the work. All construction and maintenance shall be carried out by workers experienced in such work and shall be completed in a workmanlike manner. Any work not specified in detail but necessary for the completion of the Contract in accordance with the letter and spirit of the Specification shall be carried out by the Contractor as if it had been so included.
3.1.22 DUST CONTROL, NOISE CONTROL AND HOURS OF WORK
The Site is within a park area and which has residential property nearby, and is also within school grounds. As such the Contractor shall minimise as much as possible the risk of nuisance being caused by his construction activities. In particular the Contractor shall ensure that dust generated through the construction area is controlled to an acceptable level so there is no dust nuisance that could cause harm to the general public or to workmen. The Contractor will be liable for any claims for compensation, damages or otherwise as a result of dust generated through negligence or ineffective control.
The Contractor shall ensure that all plant items have suitable noise suppressant devices fitted and working. Noise limits applying to the area in which the work is to be carried out are: Average maximum noise level (L10) – Mon-Sat (incl.) Sun & Public Holidays At all times 90 75 Where possible the Contractor shall programme and undertake the noisiest work during normal daylight hours when the ambient background noise is high. Noisy equipment shall not be operated between the hours of 7.00 p.m. to 8.00 a.m. except with the written approval of the Engineer. No work shall be permitted on Sundays except with the written approval of the Engineer.
3.1.23 TRAFFIC MANAGEMENT
The management of traffic shall include the safe control of pedestrians and cyclists through the Site and at the entry points at Grey Street, Stanley Road and Anzac Street. The Traffic management shall conform to the Transit New Zealand Code of Practice for Temporary Traffic Management. Access to the Site may be obtained from either of Grey Street, Anzac Street and Stanley Road. A Traffic Management Plan will be required to be produced to cover activities where frequent access to/from the site is expected at these particular locations.
3.0 Specifications Page 11
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
The Traffic Management Plan shall demonstrate that:
• Adequate procedures are in place to ensure that traffic control is pre-planned
• Specific procedures will be worked through when selecting a suitable speed restriction should a reduction be required.
• Traffic control will be continually monitored and amended where appropriate,
• Decisions are made by people capable of ensuring that all scenarios are considered and properly analysed
• Sufficient recording systems are in place to ensure there is a clear audit trail of what decisions were made for situations encountered.
The Traffic Management Plan shall detail the equipment to be used and include the names (including training) of the nominated Site Traffic Management Supervisor (STMS), Traffic Controller (TC) and Contract Supervisor. No existing permanent sign is to be covered without the prior approval of the Engineer. Restrictions on parking may be necessary in the existing street carparks. Any such restrictions shall only be imposed with the written approval of the Engineer. Entrance into adjacent businesses and residential properties shall not be hindered. The site has to be shared with pedestrians and cyclists, and reasonable measures must be put in place to allow safe passage past the works – your TMP shall demonstrate how you will manage this.
3.1.24 QUALITY MANAGEMENT
3.1.24.1 General
The Principal regards quality as an integral part of the contract works and has assessed the minimum quality requirements to be in accordance with TQS2 (1995). Any quality assurance system adopted by the Contractor shall be used only as an aid to achieving compliance with the Contract and to document such compliance. The Contractor’s quality assurance requirements shall not affect in any way the Contractor’s other obligations under the Contract. Knowledge of, or involvement in, the Contractor’s quality assurance system or the provision of any apparent approval resulting therefrom by the Engineer shall not in itself release the Contractor from any requirements of the Contract.
3.1.24.2 Quality Plan
The Contractor is required to prepare and operate a Quality Plan specific to this Contract. The plan as a minimum shall meet the requirements of TQS2. Throughout the Contract the Contractor shall: • review and where required amend the Quality Plan, • complete the Contract Works in accordance with the Quality Plan, • co-operate with the Engineer to audit the Contractor’s records. The Contractor shall submit his quality plan for acceptance by the Engineer within 5 days of acceptance of tender. On receipt of the Quality Plan, the Engineer shall make immediate and formal acknowledgement of its receipt to the Contractor, and in the next three working days the Engineer will advise acceptance of the
3.0 Specifications Page 12
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
Quality Plan or advise of indicative amendments that are required. The Quality Plan is to be revised and resubmitted for formal acceptance. Work shall not commence until this acceptance procedure is complete. In the period following receipt of the agreed Quality Plan, the Engineer and the Contractor will review that Plan and monitor that the contract requirements are continuing to be met. The Engineer will have the right to make comment or require amendments to the Quality Plan at any time.
3.1.24.3 Quality Plan Requirements
The Contractor shall produce a contract specific Quality Plan demonstrating how the Contractor will meet the requirements of this contract and the requirements of the Contractor’s own quality systems. The Quality Plan shall: • Define the test methods, standards and frequency of testing. • Define responsibilities and roles of the Contractor’s personnel. • Show procedures for reporting test results to the Engineer. • List the proposed Subcontractors and Suppliers. • Show how the works will be checked and how non-conformances will be dealt with. • Define the frequency of formal internal quality audits. • Include a H&S Management Plan.
3.1.25 JOB INSPECTIONS
3.1.25.1 During Works
The inspection of any work by the Engineer or the Engineer’s Representatives will be undertaken between 8.00 am and 5.00 pm on Working Days as defined in NZS 3910, unless otherwise agreed by the Engineer. The Contractor shall give the Engineer’s Representatives 24 hours advance written notice of work required to be inspected. The notice should outline the elements to be inspected and the date and time that the work will be available for inspection. Should any work not be ready to be inspected or supervised within one hour of the time nominated in the notice, or agreed by the Contractor and the Engineer, then a deduction shall be made by the Principal for costs and disbursements resulting from any delay beyond one hour, or for any revisits to the site as a consequence of the delay or rework. For the purposes of assessing costs, time will be measured to the nearest quarter hour.
3.1.25.2 On Completion or During Period of Defects Liability
After being advised by the Contractor that all items for attention under Clauses 10.4 and 11.2 of the General Conditions of Contract have been satisfactorily completed, the Engineer will carry out his inspection of the works. If, after the inspection, items are still not properly completed, the Engineer will so advise the Contractor and will later make further inspection(s) as required to accept all the work. A deduction shall be made by the Principal for costs and disbursements incurred by the Engineer in the second and subsequent inspections.
3.1.25.3 Reimbursements
Such reimbursements as outlined above may be deducted by the Engineer from any money that is due or becoming due to the Contractor. The costs of the Engineer, the Engineer’s Representative or any assistant shall be based on the following rates:
3.0 Specifications Page 13
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
• Engineer to Contract $150/hour • Other Professional personnel $110/hour • Vehicle running $0.80/km (All costs exclusive of GST)
3.1.26 CONTRACT MEETING
An initial contract meeting shall be held at least one week prior to the start of work on-site. The meeting is to be held at the office of Opus Consultants. At the meeting, the Contractor shall present for discussion and review, at least the following: • Confirmation of the Contractor’s key personnel, and their responsibilities • The Contractor’s after hours and normal working hours contact telephone and fax numbers. • The programme of work • The Quality Plan and H&S Plan • The Contractor’s Health and Safety policy in accordance with the Act • Evidence of Consents obtained • Any other topics the Contractor or Engineer may wish to discuss
3.1.27 PROGRESS PAYMENT AND FINAL CLAIM
3.1.27.1 Monthly Progress Claim
Further to Clause 12.1.2 of NZS 3910, the Contractor’s monthly progress claims shall be set out in the format of the Schedule of Prices. For each item in the schedule the item number, item description, tendered quantity, tendered rate, quantity claimed previously, quantity claimed for the month, amount claimed for the month and total amount claimed to date shall be set out across the page. The Contractor shall list separately all additions and amendments to the accepted tender schedule as Unscheduled Items (e.g. U1, U2 etc). The Contractor shall also provide an accurate Forecast of Expenditure to the end of the contract with each monthly claim.
3.1.27.2 Final Claim
The Contractor’s Final Claim shall be submitted in accordance with Clause 12.4.1 of NZS 3910 and shall be in the format of the Schedule of Prices listing all Variations (Unscheduled Items) to the Contract.
3.1.28 AS-BUILT INFORMATION
The Contractor shall provide as–built information on the construction drawings. The drawings shall be neatly marked-up in red-ink where actual construction is different from that shown on the drawings. An A3 size copy of the construction drawings will be provided for the purposes of recording as-built information. As-built information must be recorded by the Contractor as the work progresses and kept on site for inspection by the Engineer’s Representative at any time. The as-built information shall be provided before the issuing of the Certificate of Practical Completion.
3.1.29 PRACTICAL COMPLETION/DEFECTS LIABILITY CERTIFICATE
3.1.29.1 Completion of the Contract Works
3.0 Specifications Page 14
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
Further to Clause 10.4 of NZS 3910 the Contractor shall within 5 working days of the completion of the Contract Works: • Advise the Engineer in writing that the works associated with the Contract Works are complete
and comply in all respects with the requirements of the Contract Documents, and • Request the issue of the Certificate of Practical Completion for the Contract Works.
3.1.29.2 Period of Defects Liability
Further to Clause 11.3.1, the Contractor shall within five working days of completion of the Period of Defects Liability: • Advise the Engineer in writing that the period of defects liability has ended and the Contract
Works comply in all respects with the requirements of the Contract Documents, and • Request the issue of the Defects Liability Certificate.
3.1.30 STATEMENTS TO THE MEDIA
The Contractor shall not make statements to news media regarding policy, local conditions or contractual matters. All enquiries from the media are to be directed to the Engineer or to the Principal.
3.1.31 ARCHAEOLOGICAL DISCOVERIES
There is the potential for archaeological sites to be present in the area in which the works are being carried out. Work in certain areas may be subject to special observation by representatives of interested parties. The Contractor shall allow in his programme for delays of up to one week in the event of a halt to work while investigations are carried out should artefacts be uncovered.
3.1.32 WORKING ALONGSIDE RAILWAY
A portion of the site is adjacent to (and even over) the existing live railway tracks. The use of these tracks is extremely rare but requires that Contractors abide by the conditions applicable to working in the vicinity of railway property.
3.1.33 MATERIALS AND FURNITURE
All materials shall comply in full with the relevant New Zealand Standards (NZS) (or British Standards (BS) where appropriate NZS do not exist) or NZ Transport Agency’s Standards. Reference to any Standard shall include any amendments or substitutions. Where an item is mentioned by a trade name of other specific reference, it shall be deemed to mean the type of item so mentioned, or any other approved equivalent in quality, finish, durability and serviceability for the purpose intended. The quoting of a trade name shall not be construed as any desire to restrict the use of competitors’ materials, and the Contractor is at liberty of offer, for the Engineer’s approval, any materials he considers equivalent. No warranty is expressed or implied that materials specified are regularly stocked by merchants.
3.1.34 PUBLIC NOTIFICATION
The Contractor shall notify, in writing, at least two days prior to work commencing, all adjoining property owners of the following details:
• Contractor’s Company name
• Description of work
• Date of work commencement
• Duration of work
• Contractor’s contact person and phone number (including after-hours number).
3.0 Specifications Page 15
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
3.2 TECHNICAL SPECIFICATION
In general the following clause numbers match the item numbers in the Schedule of Prices.
3.2.1 GENERAL ITEMS 3.2.1.1 Establish, disestablish and clean up on completion
Refer Clause 3.1.12 & 13 of the Specification. 3.2.1.2 Survey and setting out
The Contractor shall set out the Works using the information (dimensions and co-ordinates) supplied on the drawings. A list of co-ordinates has been supplied for the setting out of the path. The Contractor shall peg out enough points to provide an indication of the path location and flow, and to allow the Engineer to confirm or make adjustments to the path alignment (this is a Hold Pointthis is a Hold Pointthis is a Hold Pointthis is a Hold Point). The Contractor shall programme reasonable time to have the proposed work inspected. At this time an initial assessment will be made of the cut/fill areas and the impact on surface drainage paths. The Contractor shall ensure that the track gradient and crossfall is as constant as possible. The new track shall not form a ‘stopbank’ preventing natural discharge of surface water – this is to be addressed by judicious filling and topsoiling.
3.2.1.3 Prepare and implement temporary traffic management
Refer Clause 3.1.23 of the Specification.
3.2.1.4 Relocation of services (Provisional Sum)
Refer Clause 3.1.16 of the Specification. Should any relocation of services be required then this will be treated as a Variation for which a Provisional Sum has been included in the Contract.
3.2.2 QUALITY ASSURANCE TESTING & CHECKING 3.2.2.1 Prepare and implement quality plan
Refer Clause 3.1.24 of the Specification.
3.2.2.2 Provide quality assurance testing Refer Clause 3.1.24 of the Specification.
3.2.3 SITE CLEARANCE & EARTHWORKS
This section covers site clearing and general earthworks including stripping of topsoil to stockpile, excavation to footpath depth, and preparation of the subgrade surface. All earthworks shall comply with TNZ F/1 unless stated otherwise. The control of surface drainage shall be undertaken early in the work so as to maintain the natural water drainage facilities and limit the introduction of water into the earthworks. Additional temporary surface drainage works shall be carried out during construction as required to safeguard the integrity of the works. The earthworks shall be carried out in such a manner that their surfaces have, at all times, a sufficient fall to shed water and prevent ponding. The Contractor shall maintain the fill area so that the time required between wet periods and the resumption of earthworks is kept to a minimum. Adequate provision shall also be made for the control of water borne soils.
3.2.3.1 Relocate concrete pavers, bollards, baskets, etc
3.0 Specifications Page 16
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
The Contractor shall uplift the existing concrete pavers located at the start of the path along from
Stanley Road and Grey Street. The pavers are to be neatly loaded on to pallets, wrapped and
transported to GDC’s storage yard at Makaraka.
The bollard/chain barrier adjacent to the Awapuni School carpark is in conflict with the proposed path
alignment. The barrier is to be relocated adjacent to the new walkway and at the direction of school
staff.
The picnic table at the Stanley Road entrance shall be delivered to the school – liaise with school staff
for delivery.
The Alfred Cox Park contains facilities for playing Frisbee Golf, including baskets, posts and marker
slabs. The Contractor shall relocate (to an agreed location nearby) any such features that conflict with
the new path. Allow to liaise with staff at the nearby Visitors Centre.
3.2.3.2 Remove from site surplus materials
The Contractor shall remove from site all surplus materials including:
- The concrete picnic table base at Stanley Road
- The portion of the timber barrier running adjacent to the footpaths on Stanley Road and Grey Street
that conflict with the new ‘Gateways’
- Tyres, concrete and timber materials found in the abandoned BMX practice track. Material suitable
for use as fill is to be stockpiled separately for use elsewhere and the site levelled. The site shall
be topsoiled/grassed in accordance with Cl 4.8 below.
3.2.3.3 Excavate existing concrete footpath at Stanley Road
The Contractor shall uplift and dispose off-site the existing concrete path that runs along the back of the
industrial property between Stanley Road and the school grounds. The waste concrete is to be
delivered to the Fulton Hogan quarry in Matokitoki Valley Road so that it can be crushed and recycled.
Much of the old path footprint will be reinstated with topsoil; allow to break up the subgrade to promote
drainage and the growth of grass cover.
3.2.3.4 Strip topsoil to stockpile
The areas to be cleared shall be stripped of all topsoil, roots, organic and other unsuitable matter.
Stripping techniques shall be such as to minimise excavation of the material underlying the topsoil
cover. The extent of stripping shall be 500mm outside the edge of the concrete slab. Volumes have
assumed a salvageable depth of 100mm.
All tree roots found above subgrade level during excavation will need to be removed. Where massed
roots, or roots over 30 mm in diameter, are encountered then these shall be brought to the attention of
the Engineer for a decision on removal. Where approved, roots shall be severed 200 mm outside of the
proposed alignment, removed from site and disposed of by the Contractor.
Topsoil shall be stockpiled in locations which facilitate later uplifting for respreading. Stockpile heights
shall not exceed 1m. Stockpiles shall not be placed in locations that may endanger the stability of the
stockpile or supporting ground and should not obstruct the public.
Usable topsoil must be kept separate from subgrade material in order to avoid contamination.
3.2.3.5 Excavate to subgrade
Once the available topsoil has been stripped from the site, excavation or filling will be required to
achieve the path subgrade level. Therefore, in order to form a reasonably level and smoothly graded
3.0 Specifications Page 17
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
pathway, judicious use of excavated material for fill will be required. Filling and contouring either side
of the path will also be required (which will involve salvaging and then replacing topsoil over the
raised/lowered area) in order to provide a walkway that melds into the Site.
Because a survey of the Site has not been undertaken it is difficult to provide precise quantities of cut-
to-fill, therefore the Contractor must make his own assessment of how much material requires to be
shifted. Excavation volumes assume an average depth of 100mm and a width of 200mm outside the
path edge. This item will include for either cut-to-fill or cut-to-stockpile of surplus material. Importation
of fill material is not expected to be necessary.
The Contractor shall limit excavation to that which will achieve the required profile and subsequent
footpath construction or other concrete works. 3.2.3.6 Stockpile to fill
Material cut and stockpiled from the pathway that is surplus to filling requirements, and material
salvaged from the BMX track, shall be spread on site as directed by the Engineer. The areas for
spreading of this material include low lying parts of the park that are likely to pond surface water.
Existing topsoil will need to be salvaged before filling (as per Cl. 3.2.3.4). 3.2.3.7 Undercut unsuitable and replace
Once the design/agreed profile has been achieved the Contractor shall test the subgrade to prove
suitability for footpath construction. Testing shall be by means of Scala Penetrometer or other
approved method to a depth of 0.5m. Frequency of testing shall be at 20 m intervals and results shall
be forwarded to the Engineer before proceeding further (this is a Hold Point).
Subgrade material not achieving a CBR of 2 or better shall be undercut and replaced with suitable fill
material to a depth of 300mm, compacted in 150mm lifts.
In areas where it is necessary to remove identified hazardous material then it shall be disposed of at a
landfill site authorised to take such materials. Appropriate precautions must be taken when excavating
and transporting the material, including suitable PPE. 3.2.3.8 Prepare subgrade
The entire surface of the completed subgrade shall be made smooth, firm and uniform by blading,
grading and rolling, approximating the crossfall required on the final surface.
The surface shall be finished so that all points are within 15 mm from a 3 m straight edge laid at any
point on the surface. 3.2.4 PATH CONSTRUCTION
The work in this section involves the construction of the footpath/cycle track and other concrete
surfaces, including the timber formwork, subbase metal and reinforced concrete path (refer Sheet 14
for details).
3.2.4.1 Supply and place 100mm compacted subbase
Following approval of the alignment and levels a 100 mm layer of subbase metal shall be placed in
preparation for laying the reinforced concrete path. The subbase layer shall extend 200mm outside the
edge of the concrete slab.
The subbase metal shall comply with the Local Subbase Specification (copy appended), and
compaction shall be to 95% of Heavy Compaction in accordance with NZS 4402 Part 4 Section 1.2.
3.0 Specifications Page 18
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
The surface of the subbase layer will need to be blinded off with a layer of sand to help produce an even
surface with minimum voids.
The tolerance on the subbase surface shall meet the requirements of TNZ B/2.
3.2.4.2 Temporary edging
Once the subbase surface has been prepared and compact, edging will be required to be installed to
act as concrete formwork. The edging shall be robust enough not to give when the concrete is poured,
but be sufficiently flexible to produce a smooth flowing line free from kinks or sharp changes in
direction.
The Contractor shall use the edging to check that the correct depths of concrete and the specified
crossfall will be achieved. Measurements are required to be recorded every 10m and results provided
to the Engineer before each concrete pour (this is a Hold Point). The Contractor shall allow for
adjustments of the edging to a satisfactory line and vertical profile.
Once approved, the edging must be protected to ensure that it is not knocked off line.
3.2.4.2.1 Timber edging
Timber for the edging formwork in contact with the poured concrete shall be dressed smooth on the
face and two edges and shall be free from knots, cracks and other deformities. Alternatives to timber
will be considered.
It is important that the edging be sufficiently flexible in order to produce a curved profile when required.
The edging can be formed from notched plywood or some other flexible but robust material.
3.2.4.2.2 Flexible garden edging
The ‘Decorative Concrete Bands’ (Type C) at the Gateway locations are to be formed and poured first
and then the main concrete (TYPE B) poured around it. The shape of the band has tight curves that
may best be formed using temporary flexible garden edging. Alternatives will be considered providing a
clearly defined shape is formed.
Note that the edging will have to accommodate the presence of the mesh steel (which will be
continuous through the entire slab). Ensure that the formwork is sufficiently tight to minimise loss of
concrete during the pour.
3.2.4.3 Construct concrete path (incl. reinforcement)
The Contractor shall construct the reinforced concrete slab for the walkway in accordance with the
details shown on the drawings and the following.
The Contractor shall note that a high standard of finish is required on the exposed surfaces of the slab,
and particular attention shall be given to forming the corners.
Concrete and reinforcing shall be in accordance with Opus Standard T-CES 101 (copy attached), the
relevant standard specifications and the following:
a Concrete shall be Normal grade, complying with NZS 3104:2003 with a minimum compressive
strength of 25 MPa at 28 days when tested in accordance with the various provisions of NZS
3112. Maximum slump shall be 120mm (+/- 40).
b Concrete construction shall comply with the requirements of NZS 3109:1997.
c No water is to be added to the concrete on site unless with the approval of the Engineer.
3.0 Specifications Page 19
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
d All reinforcement other than ties and stirrups shall be deformed unless otherwise detailed.
Reinforcement shall be Grade 300E and shall comply with NZS 3402 and placed in accordance
with CES 101.
e The length of lapped splices (without hooks) shall be 40 bar diameters in length.
f Steel reinforcement, at the time concrete is placed, shall be free from loose flaky rust, mud, oil or
other coatings that will destroy or reduce the bond.
g Reinforcement shall be accurately placed, adequately supported with chairs and secured against
displacement prior to placing the concrete.
h The minimum cover to all main reinforcing steel shall be 50 mm unless otherwise specified.
i Immediately prior to placing the concrete the subbase/sand layer shall be saturated with water.
j The path and slabs shall include transverse contraction joints at a maximum of 3m spacings.
The joints are indicated on the drawings but the Contractor shall choose locations to minimise
the risk of cracking. The joints shall be 55mm deep and must be cut as soon as possible after
the concrete has set and will not rip (no more than 18 hours). The preference is that the joints
be formed when the concrete is still plastic by means of inserting a steel strip (or T-section) and
snipping the reinforcement, then filling the gap with a joint fill to prevent ingress of water. The
methodology for joint forming shall be submitted and approved by the Engineer. Avoid placing
the joint where there is an overlap in the reinforcing layer. k In order to promote proper curing the concrete must have a curing compound applied after its
initial set (applied as per manufacturer’s instructions).. l Concrete treatments shall be as specified below. For each treatment a 1m2 sample of slab shall
be prepared in advance in order that they can be approved for use (this is a Hold Point). It is emphasised that surface cracking of the concrete slab will not be accepted. Should any cracks
appear then the entire slab (between expansion joints) shall be removed and replaced. In such cases
the mesh will have to be cut, compromising the continuity of the RC path. The Contractor shall ensure
that there is no differential settlement of the replaced slab (with the inclusion of dowels or similar
method of support) and that the surface level and the finished colour/texture are consistent. Any such
repairs shall be implemented soon after the defects become apparent and the method of repair shall
be submitted for approval by the Engineer.
3.2.4.3.1 Surface treatment - Type A (main pathway)
The main pathway shall be constructed as specified above. In general the concrete slab shall be
100mm thick, the exception being the sections identified in hatching on drawing Sheet 3 which are to
be thickened to 150mm to accommodate the weight of maintenance vehicles.
The concrete shall incorporate 2.5% black oxide and the surface shall have a ‘broom finish’. The path
shall be poured in sections of 25 lineal metres (max). In order to allow for longitudinal expansion a gap
of 15mm is to be left between sections, filled with polystyrene and 15mm depth of flexible filler (colour
gray) securely bonded to the concrete faces. The reinforcement is not to be continuous over the gap.
3.2.4.3.2 Surface treatment - Type B (Gateways, intersections and Lookouts)
The locations of the Type B treatment areas are as shown on the drawings. Concrete shall be plain with
an exposed aggregate finish and containing 2.5% black oxide.
3.2.4.3.3 Surface treatment - Type C (Decorative bands, Thresholds and Sculpture areas)
3.0 Specifications Page 20
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
Type C surfaces are to be plain concrete including 5% iron oxide with a sealed finish or acid wash finish.
The Decorative Bands are incorporated within the Type B slabs and are to be formed first using a
flexible former such as garden edging (refer Cl.3.2.4.2.2 above). A high standard of finish is required in
the formation of these features.
3.2.4.3.4 Thickened slab at sculpture features
The Sculpture areas are to be strengthened with a thickened slab of reinforced concrete – details are
as shown on the drawings. Locations are to be confirmed before laying out the slab. An expansion gap
is to be included to allow separation between the concrete slabs.
3.2.4.3.5 Thickened slab at crossing points
Sections of path near the BMX track are to be thickened up to 150mm to accommodate access by
maintenance vehicles (refer drawings Sheet 3).
3.2.5 DRAINAGE
This section covers the drainage requirements of the site, including culverts and subsoils.
3.2.5.1 Install culverts
A precast concrete culvert (900mm dia) is to be installed alongside the railway embankment and below
the southern approach to the railway crossing. Installation, bedding and backfill shall be in accordance
with TNZ F/3. The invert shall be consistent with the existing channel profile (line and level to be
confirmed on site before proceeding).
A 600mm diameter culvert is also required to drain a ditch located part-way along the park section.
Again, the line and level shall be confirmed before proceeding with the work. Allow to deepen the drain
upstream and downstream to encourage surrounding surface water to flow into the channel.
3.2.5.2 Construct timber headwall
A timber headwall is to be constructed at the entrance to the 600m diameter culvert in the park. The
headwall is to be made from 50mm x 150mm treated timber and shall be robustly constructed to retain
the backfill and blend in to the park surrounds.
3.2.5.3 Install subsoil drain
In an attempt to intercept water before it crosses the path a subsoil drain is to be installed on the
‘upstream’ side of the path and as shown on the drawings. The drain will only be required at locations
where there may be problems with surface/ground water (primarily along the park section) and
therefore the Contractor shall obtain approval to install before proceeding. The depth to invert will be
approximately 500mm but will vary in order to achieve a fall. The pipe shall discharge at suitable
locations under the path and out into the creek or into the new culvert.
Other areas of the park, for example the section from Stanley Road to the school, may also require the
installation of subsoils to encourage drainage – these will be installed as required.
3.2.6 RAISED PLATFORM AT ‘GATEWAY’ ENTRANCE
A raised sloping bank is to be constructed at the Stanley Street ‘Gateway’ as shown on the drawings
Sheets 6 and 15.
3.2.6.1 Reinforced concrete wall
3.0 Specifications Page 21
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
Construction of the reinforced concrete wall shall be in accordance with Opus Standard T-CES 101
(copy attached). Testing for the wall foundation shall involve Scalas at 5m centres, 500mm depth and
a target of 3 blows/100mm (copy results to Engineer). The wall shall be founded on a 100mm layer of
well-compacted subbase.
The exposed face, top and back surfaces of the wall shall be an F6 finish in accordance with NZS 3114
Specification for concrete surface finishes. A very high standard of finish is required, paying particular
attention to surface evenness and continuity of colour.
Backfilling of the wall shall be in accordance with Cl 3.2.3.5 above, and topsoil/grassing with Cl 3.2.8.
3.2.7 RAILWAY CROSSING
This section covers the ‘Maze’ railway crossing from the “maze’ entrance to the new bridge abutment.
The approach slab shall be a Type B in accordance with Cl 3.2.4.3.2 above.
3.2.7.1 Maze fencing
The fencing that forms a boundary for the Maze at the railway crossing shall be constructed from
proprietary aluminium pool fencing to the height and layout as shown on the drawings. The fencing
shall be robust and be suitable for use in a public place and shall comply with NZS 8500. The proposed
fencing shall be approved by the Engineer before ordering.
3.2.7.2 Railway crossing sleepers
In order to form a reasonably level surface at the crossing, railway sleepers are to be installed as shown on drawing Sheet 16. The Contractor shall confirm that the depth of the sleeper is consistent with the track depth so that the finished surface is level. The sleepers shall be securely fixed to the existing sleepers. The sleepers can be salvaged or new but they must be in good condition. The ends of the sleepers shall be liberally coated with bituminous paint.
3.2.7.3 Railway crossing signs
A WX8 ‘Look for Trains’ sign is to be installed at both approaches to the crossing. Post, signage and footings shall comply with the NZTA Signs and Markings Manual.
3.2.7.4 Tactile ground surface indicators The Contractor shall install proprietary ‘Tactile Ground Surface Indicators’ in the concrete slab at the entrances to the crossing.
3.2.8 GRASSING AND REINSTATEMENT
This section covers reinstatement of grass coverage to the Site.
Following completion of paving works all areas of exposed earth which have been disturbed by the Contractor’s operation shall be grassed.
The grassing of the Site shall be completed in accordance with accepted practices and the requirements below such that the areas grassed:
• achieve a 90% strike rate in any 1 m2. • bare areas do not exceed 80 mm in diameter in any 1 m2 area grassed.
3.0 Specifications Page 22
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
Note that any areas damaged by the Contractor’s operations (e.g. access tracks, storage etc) shall be reinstated to the same standard, with the cost of the work covered in the General item.
3.2.8.1 Respread topsoil
The Contractor shall spread the stockpiled topsoil within the limits and to the depth shown on the drawings (100 mm min. when lightly compacted). The topsoil shall be graded 25 mm above the top of the concrete edges. The finished surface shall not pond water.
3.2.8.1.1 Preparation
The seed bed shall be prepared by raking to form a consolidated granular seedbed. Final soil levels shall be smoothed free of depressions and shall present an even, tidy appearance. Gradients are to be no greater than 1 vertical to 5 horizontal, unless directed by the Engineer. Clods greater than 40 mm shall be removed.
3.2.8.1.2 Timing
Seed shall be sown on completion, with a second sowing undertaken during the Defects Liability Period.
3.2.8.2 Sow seed and fertilise 3.2.8.2.1 Sow seeds
All seed shall be thoroughly mixed and sown to ensure uniform seeding. The Contractor shall provide certificates proving the seed is certified, including a description of its age, % germination and purity. An acceptable grass seed is Perennial Rye-grass ‘Droughtmaster’, or as otherwise approved in writing by the Engineer, and shall be sown at a rate of 300 kg/ha. After seeding the surface shall be lightly raked and rolled with a light roller. The Engineer shall be advised, in writing, once this operation is completed.
3.2.8.2.2 Fertiliser
Not more than 72 hours prior to sowing, the Contractor shall broadcast a fertiliser such as Nitrophoska Blue or Ammophos at a rate of 250 kg/ha.
One month after sowing the Contractor shall fertilise the area sown with an application of sulphate of Ammonia at a rate of 200 kg/ha.
3.2.8.3 Maintain grass
The Contractor shall water and maintain the grassed areas from the date of sowing until an acceptable sward of grass has established or until the completion of the Defects Liability Period, whichever comes first. The Contractor shall re-grass any grassed area that is dead or dying due to lack of moisture, disease or general neglect. Any areas of water holding depressions shall be re-levelled with additional topsoil and re-grassed. As stated above, the minimum acceptable grass strike rate is 90% of specified seed on any one square metre, with any patches of uncovered topsoil being no greater than 80 mm in diameter. This will be assessed periodically during the contract period.
3.0 Specifications Page 23
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
Where weeds appear, the affected areas shall be treated with an approved selected weedkiller in accordance with the manufacturer’s specifications after the grass is three to four months old. At handover there shall be no more than 5% of broadleaf weeds within the sown areas.
3.2.9 MISCELLANEOUS FEATURES
3.2.9.1 Timber blocks
The Type C concrete Threshold slab is to be separated from the main path by a length of recycled
railway sleeper. The block shall be placed on well-compacted subbase and is to be securely fixed
between and the top surface level with the adjacent concrete slabs. The ends of the timber shall be
liberally coated with bitumen to help hinder rot.
Similar timber blocks are to be installed alongside the recycled railway tracks included in the
approaches to the bridge and railway crossing.
3.2.9.2 Timber posts with resin inlay
Totara posts are to be installed at the approach to the railway ‘Maze’ crossings. The posts are to be 250mm by 250mm, 2.2m long (1.2m above ground), placed along the edge of the concrete path at 800mm spacings (5 on the RH side of each approach). The posts are to have a 20mm by 20mm square check taken out of the face of the post for the exposed length, which is to be filled with 10mm of coloured resin of alternating green and red posts.
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
4.0 BASIS OF PAYMENT
4.0 Basis of Payment Page 1
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOL CYCLE AND WALKWAY
4.0 BASIS OF PAYMENT
4.1 GENERAL
The Schedule of Prices shall be read in conjunction with the contract documents and shall be paid at
the appropriate rates set out in the priced schedule for final quantities determined by the Engineer.
Attention is drawn to Clauses 2.3.2 and 5.1.1 of the General Conditions of Contract, which require the
Contractor to allow for all costs in carrying out the work as specified in the documents, unless expressly
excluded.
The Contractor shall not rely on the quantities given in the schedule for the purpose of ordering
materials.
The following abbreviations are used in the Schedule of Prices:
Lump Sum - LS
Lineal metre - m
Square metre - m2
Cubic metre - m3
Each - EA
Provisional Sum - PS
4.1.1 Establish, disestablish and clean-up on completion
Payment for establishment will be a lump sum. The payment will cover all direct and indirect costs, and
any other general costs which are not directly chargeable to any other scheduled items.
Payment not exceeding 60% of the lump sum will be made to the Contractor when the Contractor has
fully established and work is progressing to the satisfaction of the Engineer.
The remaining 40% will be paid after the site has been vacated and all clean-up and restoration work
completed to the satisfaction of the Engineer and any affected landowners.
This item shall also cover all costs associated with management of the following aspects of the contract
work:
• Attendance at contract meetings
• Liaison with land owners and service authorities (if required)
• Handling complaints
• Reporting
• Preparation and submission of Programme of Works
4.1.2 Survey and setting out
The Lump Sum tendered shall be in full compensation for all survey and setting out as specified.
4.1.3 Prepare and implement temporary traffic management
The Lump Sum tendered shall be in full compensation for the submission and regular review of the
Traffic Management Plan, and for the implementation of the Plan.
4.1.4 Relocation of services (Provisional Item)
A Provisional Sum has been included in the Pricing Schedule for work requiring relocation of conflicting
services. This item will only be utilised on the instruction of the Engineer. The cost of relocation will be
treated as a Variation.
4.0 Basis of Payment Page 2
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOOL CYCLE AND WALKWAY
4.2 QUALITY ASSURANCE TESTING AND CHECKING
4.2.1 Prepare and implement quality plan
The lump sum shall be in full compensation for the preparation, submission and implementation of the
Quality Plan. Half the tendered sum will be paid upon acceptance of the plans and the remaining 50%
paid progressively as an assessment by the Engineer of the work completed.
The sum shall include for all costs in the preparation, presentation of the plans, and for implementation
of the plan.
4.2.2 Provide quality assurance testing
The Lump Sum tendered shall be in full compensation for all testing and submission of results to show
evidence of compliance with the Contract Specification and the Contractor’s Quality Plan.
4.3 SITE CLEARANCE AND EARTHWORKS
4.3.1 Relocate concrete pavers, bollards, baskets etc
The Lump Sum tendered shall be in full compensation for the relocation of identified items and material
within and off site as specified. The Sum shall include for all necessary liaison and transportation.
4.3.2 Remove from site surplus materials
The Lump Sum tendered shall be in full compensation for the removal from Site of all surplus materials
not required for the Works. The sum shall include for transportation and disposal and for the
stockpiling of usable material for fill. Payment will be made on completion of all removal.
4.3.3 Excavate existing concrete footpath at Stanley Road
The Lump Sum tendered shall be in full compensation for the removal from Site of the concrete pavers
near Stanley Road and Grey Street. The sum shall include for preparing the compacted subgrade ready
to allow grass/plant growth.
4.3.4 Strip topsoil to stockpile
The tendered unit rate will be paid for each cubic metre of topsoil stripped from the Site and stockpiled
as specified. Measurement will be based on an existing (compacted) depth of 100mm over the area of
the Site that is to be stripped, including paths, lookouts and gateway entrances. Volumes will be
reassessed should the depth prove to be significantly different.
4.3.5 Excavate to subgrade
The tendered unit rate will be paid for each cubic metre of subgrade cut from the site and used as fill or
stockpiled for later use. Measurement will be based on an existing (compacted) depth of 100mm over
the area of the Site that is to be undercut, including paths, lookouts and gateway entrances.
4.3.6 Stockpile to Fill
The tendered unit rate will be paid for each cubic metre of suitable fill material taken from stockpile
and used as fill as agreed by the Engineer. Measurement will be based on an assessment of
compacted fill placed. Any removal and replacement of topsoil will be covered under Items 3.4 and 8.
4.3.7 Undercut unsuitable and replace
4.0 Basis of Payment Page 3
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOOL CYCLE AND WALKWAY
The tendered unit rate for Item 3.7.1 will be paid for each cubic metre of unsuitable subgrade material
excavated below the proposed subgrade level and either cut to stockpile (for later re-use) or disposed of
off-site, including the cost of backfilling with suitable material to subgrade level. If the cut material is
identified as being of a potentially hazardous nature then item 3.7.2 will apply.
Only areas that have been approved for additional undercutting by the Engineer will be paid.
4.3.8 Prepare subgrade
The tendered unit rate will be paid for each square metre of subgrade area prepared in accordance with
the Specification.
4.4 PATH CONSTRUCTION
4.4.1 Supply and place 100mm compacted subbase
The tendered unit rate will be paid for each cubic metre of subbase supplied, placed and compacted as
specified. Payment will be made on the calculated volume (from drawings) of material compacted solid
in place.
4.4.2 Temporary edging
The tendered unit rate will be paid for each linear metre of timber edging used to form the concrete
path in accordance with the Specification.
4.4.3 Construct concrete path (incl. reinforcement) – items 4.3.1/2/3
The tendered unit rate will paid for each square metre of reinforced concrete path constructed as
specified. The rate shall include for reinforcement and curing.
4.4.3.4 Extra-over for thickened slab at sculptures
The tendered unit rate will be paid for each square metre of thickened concrete pad above the standard
path depth at the proposed sculpture locations. The rate shall include for the additional reinforcement
as specified.
4.4.3.5 Extra-over for thickened slab at crossing points
The tendered unit rate will be paid for each square metre of thickened concrete pad (50mm) above the
standard path depth.
4.5 DRAINAGE
4.5.1 Install culverts (900mm and 600mm diameter)
The tendered unit rate will be paid for each lineal metre of RCRRJ pipe supplied and installed. The rate
shall include for any excavation, bedding, backfill and channel regrading required as specified.
4.5.2 Construct timber headwall
The tendered Lump Sum shall be in full compensation to cover the cost of constructing a timber
headwall as specified.
4.5.3 Install subsoil drain
The tendered unit rate will be paid for each lineal metre of subsoil installed along the edge or under the
new footpath. The rate shall include for all excavation, material and backfilling as specified.
4.0 Basis of Payment Page 4
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOOL CYCLE AND WALKWAY
4.6 RAISED PLATFORM AT ‘GATEWAY’ ENTRANCE
4.6.1 Reinforced concrete wall
The tendered unit rate will be paid for each lineal metre of reinforced concrete wall constructed
(including tapers). The rate shall include for all excavation, bedding, formwork, reinforcement and
concrete as specified.
4.7 RAILWAY CROSSING
4.7.1 Maze fencing
The tendered unit rate will be paid for each lineal metre of Maze fencing erected at the railway crossing
as specified. The rate shall include for the fencing, posts and post bases.
4.7.2 Railway crossing sleepers
The tendered unit rate shall be paid for each lineal metre of timber sleeper supplied and installed as
specified. The rate shall include for all fixings and preservatives.
4.7.3 Railway crossing signs
The tendered unit rate will be paid for each ‘Railway Crossing’ sign supplied and installed as specified.
The rate shall include for all posts and fixings.
4.7.4 Tactile ground surface indicators
The tendered unit rate will be paid for each square metre of proprietary ‘Tactile Ground Surface
Indicators’ supplied and installed on a concrete base as specified. The concrete slab will be paid under
item 4.3.
4.8 GRASSING AND REINSTATEMENT
4.8.1 Respread topsoil
The tendered unit rate will be paid for each square metre of topsoil uplifted from stockpile and spread
at the appropriate depth as specified.
4.8.2 Sow seed and fertilise (incl. second sowing)
The tendered Lump Sum shall be in full compensation for the supply and application of grass seed and
fertiliser as specified. The sum shall include for a second sowing in the Defects Liability Period. 50% of
the sum will be paid after initial application and the remainder when acceptable growth has been
achieved.
4.8.3 Maintain grass (incl. watering)
The tendered Lump Sum shall be in full compensation for maintaining and watering the grassed surface
until the end of the Defects Liability Period, as specified.
4.9 MISCELLANEOUS FEATURES
4.9.1 Timber blocks
The tendered unit rate will be paid for each lineal metre of timber block incorporated into the footpath
as specified. The rate shall include for preservative treatment.
4.9.2 Timber posts with resin inlay
4.0 Basis of Payment Page 5
PRJ-10-881 Contract EW13/20
August 2013 ALFRED COX PARK/AWAPUNI SCHOOOL CYCLE AND WALKWAY
The tendered unit rate will be paid for each totara post (including resin inlay) supplied and installed as
specified.
4.10 CONTINGENCIES (Provisional Item)
This is a Contingency Sum in terms of Clause 12.11 of the General Conditions of Contract.
All variations must be authorised in writing by the Engineer prior to commencing the work.
Payment will either be at approved Variation rates or at Scheduled Dayworks rates as appropriate.
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOOL CYCLE AND WALKWAY
5.0 APPENDICES
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOOL CYCLE AND
WALKWAY
5.1 T-CES 101 (NZ): Specification for Normal Concrete in General Civil
Engineering Works Materials, Plant, Mixing and Placing
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 1
T-CES 101 (NZ): SPECIFICATION FOR NORMAL CONCRETE IN
GENERAL
CIVIL ENGINEERING WORKS
MATERIALS, PLANT, MIXING AND PLACING
Contents
1 SCOPE
2 CONCRETE PLANT
3 MATERIALS
4 CONCRETE
5 REJECTION OF CONCRETE
6 FORMWORK
7 REINFORCEMENT
8 CONCRETING
9 SURFACE FINISHES
10 CURING
11 DEFECTS
12 REPAIR OF DEFECTS
13 TOLERANCES ON DIMENSIONS
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 2
Related Documents
Reference is made in this specification to the following…
T-CES 517 Specification for falsework in general civil engineering works
NZS 3101:2006 Concrete Structures Standard
NZS 3104:2003 Specification for concrete production
NZS 3109:1997 Specification for concrete construction
NZS 3111:1986 Methods of test for water and aggregate for concrete
NZS 3112:1986 Methods of test for concrete (Parts 1, 2 and 4)
NZS 3114:1987 Concrete surface finishes
NZS 3121:1986 Water and aggregate for concrete
AS/NZS 4671:2001 Steel reinforcing materials
Revision History
Revision 2/89: Altered to suit current New Zealand Standards. Plant Grading
requirements amended. Defects section added.
Revision 1990: Minor changes to plant grading clauses. Clause 5.1 amended to make
Contractor responsible for testing.
Revision 1992: Change of reference number from CD 101:1990 to CES 101:1992.
Document reformatted.
Revision 1995: Temperature matched curing added to 5.2. Other minor editorial changes.
Revision 4/97: Company name change.
Revision 12/04 CES 105 merged. Document updated for revisions to NZS 3104,
NZS 3109, and ASTM C1074. Requirements for reinforcement, reference
to AS/NZS 4671, and schedules for project specific requirements added.
Revision 11/05 Font change. Change of reference number from CES 101 to T-CES 101.
Revision 10/09 T-CES 101 divided into two documents; T-CES 101 (NZ) Normal (this
document) for Normal concrete and T-CES 102 (NZ) Special for Special
concrete. Appendix C updated in T-CES 102 (NZ) Special to include
specification options for marine concrete and wastewater concrete.
Addendum 1 to Notes incorporated into Notes.
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 3
1 SCOPE
1.1 Scope
This specification covers the materials, plant, mixing, placing and testing of Normal
concrete, as defined by NZS 3104; the materials, design, fabrication, erection and striking
of formwork for concrete; and the materials, handling fabrication placing and fixing of
reinforcement for civil engineering works. The basic requirements are set out in NZS
3109, Concrete Construction, and are modified by the requirements of this document.
The requirements for formwork are to be read in conjunction with the specification for
falsework, T-CES 517. Except as used for blinding concrete, Prescribed Mix concrete is
not covered by this specification. Special concrete is not covered by this specification.
1.2 General Requirements
1.2.1 The requirements of NZS 3109 Concrete Construction shall apply unless modified below
or elsewhere in the contract documents.
1.2.2 The Engineer will assume the role of Construction Reviewer defined by NZS 3109.
1.3 Production Standards
Concrete used in construction, whether made on the site or supplied ready mixed or
supplied in the form of precast units, shall comply with the requirements of NZS 3109, and
shall be manufactured in accordance with the requirements of NZS 3104 for the specified*
concrete class as defined by NZS 3109 and NZS 3104.
* Refer to the attached schedule.
2 CONCRETE PLANT
All plants supplying Normal concrete to the project shall hold and maintain a current
quality Certificate of Audit in accordance with NZS 3104 throughout the duration of their
supply of concrete for the contract. A copy of each plant’s current Certificate of Audit shall
be submitted to the Engineer prior to their initial supply of concrete. Should the Certificate
of Audit expire within the duration of supply of concrete for the contract, a copy of the
revalidated certificate shall be supplied to the Engineer prior to expiry of the initial
certificate. Supply of concrete from the plant shall otherwise cease until a revalidated
certificate has been supplied.
For a plant that does not already hold a quality Certificate of Audit, the Contractor shall
arrange for a First Audit, in accordance with the requirements of clause 2.16.3 of NZS
3104, which shall be completed and only after issue of a Certificate of Audit may concrete
from the plant be used for the contract.
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 4
3 MATERIALS
3.1 Cement
Consent shall be obtained from the Engineer for the particular brand and type of cement
to be used in each part of the work and no change shall then be made without the written
consent of the Engineer.
3.2 Aggregates
Consent shall be obtained for the aggregates proposed for use in each part of the work
and thereafter neither the quality nor the source shall be varied without the prior
agreement of the Engineer.
For most concrete work, the coarse aggregate shall contain particles of at least 19mm
nominal size. The use of pumps for concrete placement will not be accepted as
justification for a reduction in aggregate size.
3.3 Alkali-Silica Reaction (ASR)
If the aggregates used are potentially reactive with cement alkalis, the following
precautions shall be taken:
(a) The reactivity of the fine and coarse aggregates proposed for use in a particular concrete shall be determined by petrographic examination, accelerated laboratory
testing or field experience as described in section 6.1 of TR3 (2003)∗.
(b) If the aggregate supplier and/or concrete producer can confirm that the proposed aggregates are non-reactive as defined in clause 6.1 of TR3 (2003)* then no further precautions need be applied.
(c) If the aggregate supplier and/or concrete producer cannot confirm that the proposed aggregates are non-reactive as defined in clause 6.1 of TR3 (2003)* then the following precautions shall be taken:
(i) For Normal Concrete as defined by NZS 3104:2003 the concrete producer shall certify that the total alkali content in the concrete shall not exceed 2.5 kg/m
3
from all sources.
(ii) Where the concrete producer cannot certify that the total alkali content is less than 2.5 kg/m
3 then the concrete shall be designated as Special Concrete. The
Engineer shall be informed of the change in designation.
∗ CCANZ, (2003), “TR3 Alkali Silica Reaction”, Technical Report 3, Cement and Concrete Association of
New Zealand.
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 5
3.4 Reinforcement
Steel reinforcement bars and welded wire mesh shall conform to AS/NZS 4671 and shall
be of the grade or designation specified in the attached schedule of reinforcement
requirements.
4 CONCRETE
4.1 Concrete Grade
4.1.1 Concrete shall be Normal, as defined by NZS 3104, as specified in the attached Schedule
of Project Specific Concrete Requirements, and shall have a minimum 28 day
compression strength as also specified in the attached schedule.
4.1.1 Blinding concrete shall have a minimum 28 day compression strength of 10 MPa and
comply with the requirements for Prescribed Mix concrete specified by NZS 3104.
4.2 Concrete Production
4.2.1 Concrete shall be supplied from a plant satisfying the requirements of Section 2 above.
No concrete shall be manufactured for use in the contract until the consent of the
Engineer has been given. Final consent for concrete manufacture may be subject to a
site inspection of the plant in operation.
4.2.2 If at any time a plant supplying Normal concrete is unable to demonstrate to the Engineer
that it is maintaining the appropriate standard, then it shall cease supply of concrete to the
contract until test results show that corrective measures have proved adequate.
4.3 Concrete Mix Design for Normal Concrete
4.3.1 The concrete producer shall be entirely responsible for design of the concrete mix, within
the constraints given within this specification, to achieve the properties and durability
specified in the attached Schedule of Project Specific Concrete Requirements. Design of
the concrete mix for durability shall comply with the requirements of Appendix A and shall
be consistent with the concrete cover to the reinforcement adopted (refer to clause 7.2).
4.3.2 Prior to the commencement of concreting operations, the Contractor shall supply to the
Engineer the following details for each mix for acceptance.
(a) concrete grade;
(b) target mean strength;
(c) mix designation;
(d) batch weights of cementitious materials and aggregates (saturated and surface
dry);
(e) target slump;
(f) type and amount of admixture used including amount of air entrainment (if
applicable);
(g) yield;
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 6
(h) free water/cement ratio by weight; (i) free water content.
The Engineer, in addition, may require the provision of typical physical properties for each
separately batched component of aggregate and the batch weights of each in the mix for
the concrete being supplied.
During the course of concrete supply to the contract, any variation made to the mix design
shall be immediately notified to the Engineer.
Ready mixed concrete plants concerned to maintain the confidentiality of their mix designs
may supply the above information directly to the Engineer clearly marking their statement
"Confidential". This information will not be disclosed by the Engineer to other parties.
4.4 Surface Agents and Treatments
No surface agents shall be used on formwork or treatment applied to the surface of the
concrete without the prior written consent of the Engineer. Applications for such consent
shall give full details of the proposed compound including rate and method of application,
and the reason for its use.
4.5 Delivery Records for Ready Mixed Concrete
Delivery records shall be supplied to the Engineer’s site representative for all concrete
delivered for the contract, listing the following:
(a) mix designation or code (to enable the concrete to be identified with the mixing records)
(b) type of cementitious material (c) nominal maximum aggregate size (d) details of any admixtures (name and amount) (e) specified strength and delivery slump ordered (f) date and time of completion of mixing (g) quantity delivered (h) amount of any additional water added in transit from the batching plant or on site,
and the initial and re-measured slump values
4.6 Dry Pack Mortar
4.6.1 Dry pack mortar where specified on the drawings shall consist of a sand/cement mix in the
loose volume proportions of one part of cement to two parts of well drained Class A
(coarse) plastering sand or concrete sand complying with NZS 3103 and NZS 3121
respectively. The sand and cement shall be thoroughly dry mixed before the addition of
water. Sufficient water shall be added to produce a mortar which will retain its shape on
being moulded into a ball by slight pressure of the hands but will not exude free water.
4.6.2 The concrete against which the dry pack mortar is to be placed shall be saturated but
surface dry. The dry pack mortar shall be solidly compacted in layers by a hardwood
caulker and a hammer and shall be cured for seven days by moistening frequently or by
membrane curing (see clause 11.1), eg. plastic sheet secured in place.
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 7
4.6.3 Mortar for seating bearings shall have the same sand/cement proportions as above but
shall have sufficient water added to enable it to deform in a plastic manner under imposed
load.
5 REJECTION OF CONCRETE
If at any time the concrete does not satisfy the specification, delivery shall cease until
approved correction action has been taken. The cost of any mix alteration, including
increased cement content if required, necessary to make the concrete satisfactory, shall
be at the Contractor's expense.
5.1 Slump Tests
Concrete with a slump value immediately prior to placing that exceeds the tolerance limits
specified in NZS 3109 Clause 9.4.2 shall be liable to rejection at the discretion of the
Engineer.
5.2 Compression Tests
When concrete is liable to rejection based on the results of compression testing carried
out in accordance with NZS 3104, the Contractor may elect to take and test cores in
accordance with clause 9.5.3 of NZS 3109. Within one week of the rejection order and
before taking any action the Contractor shall notify the Engineer in writing of his intention
to cut cores. Cores shall be cut at the Contractor's expense, where agreed by the
Engineer, without damaging any reinforcement. Cores shall be as large as is practicable
up to a maximum of 100 mm diameter. The compression testing of cores shall be
undertaken by a testing authority acceptable to the Engineer.
In place of NZS 3109 Clause 9.5.3.1, the test results shall be evaluated as follows:
The test results shall be corrected for the shape of the specimen by multiplying the
compressive strength obtained by the appropriate factor from the following table:
Ratio of Length of Core
to Diameter (L/D)
Shape Correction
Factor
2.00
1.75
1.50
1.25
1.00
1.00
0.98
0.96
0.93
0.87
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 8
Cores tested shall be of dimensions providing L/D values within the range of the table.
Intermediate values shall be obtained by interpolation.
The test results shall also be corrected for the orientation of the core axis relative to the
direction of concrete placement by multiplying the compressive strength obtained by the
appropriate factor from the following table:
Orientation of Core Axis
Relative to the Direction
of Concrete Placement
Loading Direction
Correction Factor
Tested perpendicular to
the layers of concrete as
placed
Tested parallel to the
layers of concrete as
placed
1.0
1.08
Apart from the L/D correction factor and the loading direction correction factor, no other
correction factors shall be applied to the compression strength test results from cores.
The test report shall note whether or not the reported test results have been corrected.
If the corrected compressive strength is in compliance with the following criteria, the
concrete will be deemed to be satisfactory and the structure will be accepted after the core
holes have been repaired in accordance with this specification:
(a) The average strength resulting from the test of the cored specimens is not less than 0.85f’c or f’c - 3.5 MPa, whichever is greater, and
(b) No single specimen test result is less than 0.80f’c or f’c - 4.5 MPa, whichever is greater.
6 FORMWORK
6.1 Definitions
For the purposes of this specification, the following definitions apply:
Formwork:
The portion of the temporary work which gives the concrete structure its required shape,
and contains it until the concrete has hardened. It includes the sheathing and its
immediate supporting framework or stiffeners.
Permanent Formwork:
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 9
Formwork which remains in place and becomes part of the permanent structure. (Used
only where specified or consented to by the Engineer.)
Falsework:
The system of foundations, beams, struts, ties and bracing which supports the formwork,
associated accessways and the placed concrete, and any other part of the permanent
structure.
6.2 Design, Fabrication and Erection
6.2.1 Surface Quality Requirements
The joints between boards or panels shall form a regular pattern, consistent with the
general lines of the structure. The layout of form ties shall also be considered as part of
this pattern.
Provision shall be made for forms to be retightened against previously placed concrete
when concrete is placed in more than one lift or section.
6.2.2 Details of Formwork
Forms shall be filleted or chamfered at all sharp edges, unless detailed otherwise, and
shall be given a slight bevel at projections to ensure easy removal of the forms.
6.2.3 Permanent Formwork
All permanent formwork used in the construction shall comply with all relevant parts of this
specification. Its design shall ensure that it is permanently anchored to the concrete. The
surface where it is supported by the falsework shall be left undamaged after removal of
the falsework.
6.3 Dismantling of Formwork and Falsework
6.3.1 For prestressed concrete members, falsework and formwork shall not be removed from
the soffit until either the prestressing has been completed to a stage defined elsewhere in
the contract documents, or has been fully completed.
6.3.2 If the Contractor wishes to load any concrete member with plant or materials before the
concrete in that member, or in adjacent members continuous with it, has attained its
specified strength, prior consent shall be obtained from the Engineer. The request for
consent shall include calculations showing that no damage will be caused by the loading.
6.3.3 The sequence of dismantling shall be as shown on the drawings, or, if not shown, shall be
as consented to by the Engineer. For continuous slab, girder or arch spans, the falsework
shall not be removed until the required time has elapsed after the placing of the last
concrete in immediately adjacent spans.
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 10
7 REINFORCEMENT
7.1 Handling, Fabrication, Placing and Fixing
The handling, fabrication, placing and fixing of reinforcement shall comply with Section 3
of NZS 3109 except as modified below.
7.2 Concrete Cover to Reinforcement
The minimum concrete cover to the reinforcement shall comply with Appendix A for the
design life and exposure classification specified in the attached Schedule of Project
Specific Reinforcement Requirements and for the cement binder type adopted by the
concrete producer.
7.3 Reinforcement Lap Lengths
Where the lap lengths of splicing deformed reinforcement are not explicitly shown on the
drawings, the lap lengths shall comply with those given in the attached schedule
(Appendix A, clause A4).
7.4 Welding of Reinforcement
Steel reinforcement shall not be welded except where specified on the drawings or where
consented to by the Engineer.
8 CONCRETING
8.1 Handling and Placing
8.1.1 The contractor shall submit the proposed handling and placing methods, sequence and
timing of pours and location on construction joints for the Engineer's consent before
concrete placing commences. Where a placing diagram, construction joint location
diagram or equivalent is included in the drawings, the requirements thereof shall be
followed unless changes are specifically agreed by the Engineer in writing.
8.1.2 Unless otherwise agreed, the Engineer shall be advised at least eight working hours
before the proposed time for concreting, that foundation, falsework, reinforcing steel
construction joints are ready for inspection. Concrete shall not be placed until consent by
the Engineer is given.
8.1.3 Concrete shall not be dropped through a free fall greater than two metres unless
otherwise agreed.
8.1.4 Equipment for rain and frost protection shall be available immediately when required.
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 11
9 SURFACE FINISHES
9.1 Basic Finish
Except where a particular standard is shown on the drawings or specified in the attached
Schedule of Project Specific Concrete Requirements, the concrete surface finish on
general construction work shall comply with the requirements of NZS 3114, F3 finish for
formed surfaces and U1 finish for unformed surfaces.
9.2 Precast Concrete Units
9.2.1 For all precast concrete units all surfaces except those against which concrete will be
subsequently placed, shall have a concrete surface finish complying with the requirements
of NZS 3114, F4 finish for formed surfaces and U3 finish for unformed surfaces.
9.2.2 Surfaces of precast units against which concrete will be subsequently placed shall be
prepared as type B construction joints (refer NZS 3109, clause 5.6.3).
9.3 Special Finishes
9.3.1 Where special architecture formed finishes are shown on the drawings, these shall be
produced by casting the concrete against formwork complying with the consent procedure
specified in clause 9.3.3.
9.3.2 The colour and surface finish of the concrete for each type of special finish shall be
uniform throughout the whole job. Metal ties for formwork shall be placed in a regular
pattern as agreed with the Engineer.
9.3.3 Unless ordered otherwise by the Engineer, the Contractor shall construct sample panels of
each special finish shown on the drawings. The panels shall be cast using the
Contractor's proposed formwork, concrete mix and method of placing concrete. The
proposed time and method of stripping and method for any additional finishing shall also
be used. Additional sample panels may be required by the Engineer if the initial formwork
or methods do not produce the required standard of finish. When a finish has been
produced to the Engineer's satisfaction, that sample panel shall be the standard for the
whole of the work requiring that finish.
10 CURING
10.1 Membrane Curing
Only where the nature of the site or the shape of the concrete surface is such that water
curing will be difficult to effectively achieve, will consideration be given to the acceptance
of membrane curing compounds or the covering of the concrete with impermeable
sheeting. Where impermeable sheeting (eg, polythene sheet) is used, it must be
continuously secured in position at its edges.
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 12
The use of membrane curing shall be subject to the written consent of the Engineer,
following the submission of full details of the method proposed (including details of the
curing compound where applicable) and the area of proposed use.
Should a curing compound fail to weather and strip off concrete surfaces leaving an
acceptable uniform appearance, then any additional work (eg. removal by mechanical
means) required to achieve this will be at the Contractor's expense and will not constitute
any extra to the contract.
10.2 Accelerated Curing
Where an accelerated curing process is to be used, the Contractor shall supply evidence
to the Engineer, for his acceptance, that the plant and process is capable of producing the
desired results. The Engineer’s acceptance shall be obtained prior to the application of
accelerated curing to any concrete elements manufactured for the work.
10.3 Curing Time
For unformed surfaces, curing of the concrete shall commence on completion of finishing
operations as specified in NZS 3109: 1997 clause 7.8.2.
For formed concrete surfaces, curing shall commence immediately on loosening or
removal of forms as specified in NZS 3109: 1997 clause 7.8.3.
Curing shall be continued for the period specified in NZS 3101: 2006 Section 3.
Where an accelerated curing process is used, (clause 7.8.5 of NZS 3109 refers) as soon
as the temperature of the concrete unit has returned to ambient, water curing shall be
applied and maintained for a period of at least three days, unless at the termination of the
accelerated curing process the concrete has achieved the strengths given in the following
table as determined from a statistical analysis of compression tests of a minimum of 3 test
cylinders cured alongside and under the same conditions as the concrete unit.
Specified Minimum
Characteristic Strength
Minimum Strength at
Completion of Curing by
Accelerated Methods
25
32
40
50
15
20
25
32
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 13
11 DEFECTS
11.1 General
In the finished work concrete shall be sound dense and homogenous, free of any voids,
foreign matter or other defects except as permitted elsewhere in the contract documents.
11.2 Minor Surface Defects
Abrupt or gradual variations in surface evenness, blowholes, honeycombing and other
physical irregularities, which exceed the limits specified in NZS 3114 for the particular
class of surface finish required in section 10 of this specification, and plastic cracks up to
12mm depth shall not be permitted, unless agreed in writing by the Engineer and repaired
in accordance with clause 12.2.
11.3 Structural Defects
Structural defects as determined by the Engineer, including chipping, spalling,
honeycombing and cracking all deeper than 12mm, shall not be permitted unless agreed
in writing by the Engineer, and may constitute grounds for rejection of that component at
the discretion of the Engineer.
12 REPAIR OF DEFECTS
12.1 General
Where defective concrete is present the Contractor shall not undertake remedial
measures without the knowledge and consent of the Engineer.
All defective areas shall be thoroughly investigated to ascertain the extent to which the
defective work extends.
Surface plastering or cement washing to cover up poor workmanship is not permitted.
The colour and texture of repaired surfaces shall match that of the adjacent concrete.
12.2 Repair to Minor Surface Defects
Projecting defects shall be removed by grinding.
Dry pack mortar (Section 4.6) shall be packed into all formwork tie holes and holes of a
similar magnitude.
Other minor surface defects may be repaired by mortaring applied by ‘bagging in’ to a
method agreed with the Engineer.
Any excess mortar including that on adjacent surfaces shall be cleaned off immediately by
scraping with a steel float and/or by subsequent grinding.
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 14
12.3 Repair of Structural Defects
Structural defects may be repaired at the discretion of the Engineer, in accordance with a
method submitted by the Contractor that has received prior written acceptance from the
Engineer.
13 TOLERANCES ON DIMENSIONS
13.1 Accuracy of Dimensions
All shown dimensions of the concrete shall be established accurately within the tolerances
given in Table 5.1 of NZS 3109 for precast units, and given in Table 5.2 of NZS 3109 for
cast in situ concrete work, unless detailed otherwise on the drawings or as specified in the
following:
Departure from established alignment: 20mm
Variations from the level or from the grades indicated on the drawings:
(a) Overall 15 mm
(b) In beams, slabs, decks, floors, 10mm but not more than 5 mm variation
horizontal grooves, railings and from a 3 m template or straight edge.
similar:
Variations from the plumb or specified batter in the lines and surfaces of columns, piers,
walls and similar:
In dimensions up to
3 m 10 mm
in 6m 15 mm
in 12 m or more 25 mm
13.2 Standard of tolerance
In addition to the foregoing the standard of tolerance shall be such that attachments,
equipment etc, can be installed accurately in accordance with the drawings and
specifications. It is stressed that the acceptance of tolerances does not absolve the
Contractor from obligations to work within the boundaries of properties and to avoid
encroachment.
13.3 Reinforcing steel and concrete cover
For tolerances on reinforcing steel and concrete cover see Section 3.9 of NZS 3109.
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 15
APPENDIX A
CONCRETE DURABILITY REQUIREMENTS
A1. General
This Appendix refers to the following documents in addition to those listed on page 1:
AS 3582.1-1998 Supplementary cementitious materials for use with Portland and
blended cement – fly ash
AS 3582.2-2001 Supplementary cementitious materials for use with Portland and
blended cement – slag – ground granulated iron blast furnace
AS/NZS 3582.3-2002 Supplementary cementitious materials for use with Portland and
blended cement – amorphous silica
AS/NZS 1170.0-2002. Structural Design Actions. General Principles
The durability of concrete structures and elements shall satisfy the requirements of the New
Zealand Building Code Clause B2.
For designs based on the use of concrete made with GP, GB or HE cement complying with NZS
3122 with or without supplementary cementitious materials complying with AS 3582, durability of
the reinforced or prestressed concrete shall be designed in accordance with New Zealand
standard NZS3101:2006 Concrete Structures Standard, Chapter 3, modified as follows:
“Several durability enhancing measures other than those specified in NZS 3101:2006 can
be taken to extend the life of concrete structures and provide the required durability. These
include concrete coatings, corrosion inhibiting admixtures, galvanized or stainless steel
reinforcement, controlled permeability formwork, GRC permanent formwork, and cathodic
protection. Life prediction models offer an alternative approach to use of Tables 3.6 and 3.7
in NZS 3101 for determination of covers and mix designs for the C and B2 zones. Adoption
of any of these or other alternative measures shall be the subject of a Special Study as
described in AS/NZS 1170.0, and shall be fully documented and submitted to the Engineer
for acceptance.”
In the event that the Contractor cannot obtain a copy of NZS 3101:2006, a copy will be made
available on request for viewing at the local office of Opus International Consultants Limited.
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 16
A2 SCHEDULE OF PROJECT SPECIFIC REQUIREMENTS FOR NORMAL CONCRETE
PROJECT __________________________________________ Sheet _____ of _____
A2.1 Concrete Type and Properties (Clause 4.1.1 refers)
Location within the structure: _______________________________________________
Concrete class (as defined by NZS 3104 and NZS 3109): Normal / Special (delete one)
Concrete minimum 28 day compressive strength: __________ MPa
Nominal maximum coarse aggregate size: __________ mm
Slump: ________ mm
Method of Placement: _____________________________________________________
A2.2 Durability Requirements (Clause 4.3.1 refers)
Design Life: __________ years
Designed as the time to (complete):__________________________________________
Exposure classifications* for internal and external surfaces (delete the examples and add
rows to table as required):
Element Location Exposure classification*
e.g. prestressed beam type ### e.g. Span AB, outer beam e.g. B2
e.g. cast in situ concrete e.g. Soffit of ### e.g. U
* exposure classifications are in accordance with NZS 3101:2006.
A3 Concrete Surface Finishes (Clause 10.1 refers):
T-CES 101 (NZ): Specification for Normal Concrete in General Civil Engineering Works
T-CES 101 (NZ)
October 2009 17
A4 SCHEDULE OF PROJECT SPECIFIC REINFORCEMENT REQUIREMENTS
PROJECT __________________________________________ Sheet _____ of _____
A4.1 Reinforcement type
Steel reinforcement grade (Clause 3.4 refers): ___________
Welded mesh designation (Clause 3.4 refers): ___________
A4.2 Concrete cover to reinforcement (Clauses 8.2 and C2.2 refer)
A4.3 Reinforcement lap lengths (Clause 8.3 refers):
(Tabled values are for fy = 500 MPa, f’c = 30 MPa)
Bar Diameter (mm) A** B***
10 460 595
12 550 715
16 730 950
20 915 1190
25 1140 1485
32 1460 1900
** Lap lengths in column A apply to all reinforcement except those bars defined as
“top reinforcement”.
*** Lap lengths in column B apply to all reinforcement bars defined as “top
reinforcement”.
“Top reinforcement” are those bars where more than 300 mm of fresh concrete is cast in
the member below the bars.
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOOL CYCLE AND
WALKWAY
5.2 Resource Consent
GISBORNE DISTRICT COUNCIL
CONTRACT Nº EW13/20
CONTRACT FOR: ALFRED COX PARK/AWAPUNI SCHOOOL CYCLE AND
WALKWAY
6.0 DRAWINGS
LIST
Drawing No./Revision Description/Title Date
3/174/450/7314/01 R0 Alfred Cox/Awapuni School Walkway 22/08/2013
3/174/450/7314/02 R0 Site Plan – Stanley Road to Awapuni School
22/08/2013
3/174/450/7314/03 R0 Site Plan – Awapuni School to Railway Crossing/Pipe Bund
22/08/2013
3/174/450/7314/04 R0 Site Plan Rail Crossing to Carnarvon Street
22/08/2013
3/174/450/7314/05 R0 Site Plan – Carnarvon Street to Grey Street
22/08/2013
3/174/450/7314/06 R0 Enlarged Plan – Stanley Road Gateway Plan
22/08/2013
3/174/450/7314/07 R0 Enlarged Plan – Walkway to Railway Crossing
22/08/2013
3/174/450/7314/08 R0 Enlarged Plan – 3 Ways 22/08/2013
3/174/450/7314/09 R0 Enlarged Plan Node – Pipe and Bund 22/08/2013
3/174/450/7314/10 R0 Enlarged Plan Node – Carnarvon Street 22/08/2013 3/174/450/7314/11 R0 Enlarged Plan – Grey Street Gateway
Plan 22/08/2013
3/174/450/7314/12 R0 Setout Point Table – Walkway 22/08/2013
3/174/450/7314/13 R0 Setout Point Table – Enlarged Views 22/08/2013 3/174/450/7314/14 R0 Miscellaneous Details 22/08/2013
3/174/450/7314/15 R0 Wall and Raised Plinth Details 22/08/2013
3/174/450/7314/16 R0 Enlarged Plan – Railway Crossing and Walkway Path
22/08/2013
3 / 174 / 450 / 7314 SHEET 02
3 / 174 / 450 / 7314 SHEET 04
3 / 174 / 450 / 7314 SHEET 03
3 / 174 / 450 / 7314 SHEET 05
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:15 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX / AWAPUNI SCHOOL WALKWAYGISBORNE
LOCALITY PLAN
3 / 174 / 450 / 7314 01 R02S8600.08.061GG NTS
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
LOCALITY PLAN - STANLEY ROAD TO GREY STREET
SCHOOL OUT OF SCOPE
AREA OF SUBSIDENCE
REMOVE DRAINAGE FROM ADJOINING
PROPERTY
REMOVE SOFT SOILS
STABILISE AND COMPACT HARD FILL
NEW SPECIMEN TREES
NEW 3m WIDE CONCRETE FOOTPATH
S
T
A
N
L
E
Y
R
O
A
D
SS356 B9YU
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
SW
SW
S
W
W
W
W
W
W
W
W
W
W
W
W
W
W
S100
S101
S102
S103
S104
S105
S106
S107
S108
S109
S110
S111
S112
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:15 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX / AWAPUNI SCHOOL WALKWAYGISBORNE
SITE PLAN - STANLEY ROAD TO AWAPUNI SCHOOL
3 / 174 / 450 / 7314 02 R02S8600.08.061GG AS SHOWN
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Approved Revision DateRevision Amendment
Dimensions in metres unless otherwise stated
FOR GATEWAY ENLARGEMENT SEE SHEET 06
KEY:
NEW 3m WIDE CONCRETE FOOTPATH
NEW SPECIMEN TREES
NOTES:
NEW 3m WIDE CONCRETE FOOTPATH BRUSHED CONCRETE SURFACE SAW CUTS @ 3m CENTRES 100MM CONCRETE SLAB (150MM IN
DESIGNATED AREAS TO ALLOW FOR VEHICLE CROSSINGREFER TO SHEETS 3 AND 4)
100MM COMPACTED SUBBASE 665 MESH LATERAL FIELD DRAINS (NOVACOIL) COORDINATES ARE IN POVERTY BAY CIRCUIT 49 COORDINATE TABLE ON SHEET 12 AND INDICATE THE CENTRELINE OF WALKWAY
EXISTING FENCE
EXISTING TREES
SITE PLAN - STANLEY ROAD TO AWAPUNI SCHOOL
SCALE 1:500 (A1) ; 1:1000 (A3)
CONTINUES ON SHEET 3
NEW FENCE
NEW SHRUB PLANTING
SURVEY MARK
FOOTPATH - TYPE A
CONCRETE TYPES:
NODES - TYPE B
THRESHOLD PAVING/SCUPLTURE
AREA/DECORATIVE BANDS - TYPE C
ALL SERVICE LOCATIONS ARE INDICATIVE ONLY. CONTRACTOR SHALL LOCATE
ON SITE PRIOR TO COMMENCING ANY CONSTRUCTION WORK.
GAS
T T
W
S
GAS
TELECOM
WATER
WASTEWATER
LEGEND
SW
STORMWATER
P
POWER
SURVEY MARK
SS
NEW TIMBER FENCE WITH VISUAL
PERMEABLE RECESS PANELS -
(NOT IN THIS CONTRACT)
FUTURE ACCESS
NEW SHRUB PLANTING
(NOT IN THIS CONTRACT)
REMOVE EXISTING FENCE
(NOT IN THIS CONTRACT)
AMEND CONTOUR AND
REMOVE BMX MOUNDS
TO
A
NZ
AC
S
T
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
SS
SS
SS
SS
SS
S
SS
SS
SS
SS
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
SW
SW
SW
SW
SW
SW
SW
SW
REDISTRIBUTE ARISINGS
TO FILL HOLLOWS AND
CREATE EVEN LANDFORM
INSTALL 900mmØ RCRRJ CLASS 2 PIPE
LENGTH - 9.0M
MINIMUM COVER - 300mm
150mm CONCRETE - TYPE A
150mm CONCRETE - TYPE A
S113
S114
S115
S116
S117
S118
S119
S120
S121
S122
S123
S124
S125
S126
S127
S128
S129
S130
S131
S132
S134
S135
S136
S137
S138
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:15 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX / AWAPUNI SCHOOL WALKWAYGISBORNE
SITE PLANAWAPUNI SCHOOL TO RAILWAY CROSSING/PIPE BUND
3 / 174 / 450 / 7314 03 R02S8600.08.061GG 1:500 (A1) ; 1:1000 (A3)
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
FOR WALKWAY ENLARGEMENT AND RAILWAY CROSSING
DETAILS SEE SHEETS 07 AND 16
FROM SHEET 2CONTINUES ON SHEET 4
FOR '3 WAYS' ENLARGEMENT SEE SHEET 08
KEY:
NEW 3m WIDE CONCRETE FOOTPATH
NEW SPECIMEN TREES
EXISTING FENCE
EXISTING TREES
NEW FENCE
NEW SHRUB PLANTING
SITE PLAN - AWAPUNI SCHOOL TO RAILWAY CROSSING
FOOTPATH - TYPE A
CONCRETE TYPES:
NODES - TYPE B
GAS
T T
W
S
GAS
TELECOM
WATER
WASTEWATER
LEGEND
SW
STORMWATER
P
POWER
SURVEY MARK
SS
ALL SERVICE LOCATIONS ARE INDICATIVE ONLY. CONTRACTOR SHALL LOCATE
ON SITE PRIOR TO COMMENCING ANY CONSTRUCTION WORK.
FOOTPATH - TYPE A (150mm)
NOTES:
NEW 3m WIDE CONCRETE FOOTPATH BRUSHED CONCRETE SURFACE SAW CUTS @ 3m CENTRES 100MM CONCRETE SLAB (150MM IN
DESIGNATED AREAS TO ALLOW FOR VEHICLE CROSSING) 100MM COMPACTED SUBBASE 665 MESH LATERAL FIELD DRAINS (NOVACOIL) COORDINATES ARE IN POVERTY BAY CIRCUIT 49 COORDINATE TABLE ON SHEET 12 AND INDICATE THE CENTRELINE OF WALKWAY
THRESHOLD PAVING/SCUPLTURE
AREA/DECORATIVE BANDS - TYPE C
R
A
M
P
U
P
R
A
M
P
U
P
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
SS
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S SS
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
150mm CONCRETE - TYPE A
S138
S139
S140
S141
S142
S143
S144
S145
S146
S147
S148
S149
S150
S151
S152
S153
S154
S155
S156
S157
S158
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:15 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX / AWAPUNI SCHOOL WALKWAYGISBORNE
SITE PLANRAIL CROSSING TO CARNARVON STREET
3 / 174 / 450 / 7314 04 R02S8600.08.061GG 1:500 (A1) ; 1:1000 (A3)
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
FOR NODE ENLARGEMENT SEE SHEET 10
FOR NODE ENLARGEMENT SEE SHEET 09
FROM
SHEET 3
CONTINUES ON
SHEET 5
KEY:
NEW 3m WIDE CONCRETE FOOTPATH
NEW SPECIMEN TREES
EXISTING TREES
NEW SHRUB PLANTING
SITE PLAN - RAILWAY CROSSING TO CARNARVON STREET
FOOTPATH - TYPE A
CONCRETE TYPES:
NODES - TYPE B
GAS
T T
W
S
GAS
TELECOM
WATER
WASTEWATER
LEGEND
SW
STORMWATER
P
POWER
SURVEY MARK
SS
ALL SERVICE LOCATIONS ARE INDICATIVE ONLY. CONTRACTOR SHALL LOCATE
ON SITE PRIOR TO COMMENCING ANY CONSTRUCTION WORK.
FOOTPATH - TYPE A (150mm)
NOTES:
NEW 3m WIDE CONCRETE FOOTPATH BRUSHED CONCRETE SURFACE SAW CUTS @ 3m CENTRES 100MM CONCRETE SLAB (150MM IN
DESIGNATED AREAS TO ALLOW FOR VEHICLE CROSSING) 100MM COMPACTED SUBBASE 665 MESH LATERAL FIELD DRAINS (NOVACOIL) COORDINATES ARE IN POVERTY BAY CIRCUIT 49 COORDINATE TABLE ON SHEET 12 AND INDICATE THE CENTRELINE OF WALKWAY
THRESHOLD PAVING/SCUPLTURE
AREA/DECORATIVE BANDS - TYPE C
G
R
E
Y
S
T
R
E
E
T
SS131 B9QN
FORM/SHAPE SWALE DRAIN
T
O
A
N
Z
A
C
S
T
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
G
A
S
S
S
S
S
S
S
S
S
S
S
S
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
S
W
SW
SW
SW
SW
W
W
W
W
W
W
W
W
W
W
W
W
W
S158
S159
S160
S161
S162
S163
S164
S165
S166
S167
S168
S169
S170 S171
S172
S173
S174
S175
S176
S177
S178
S179
S180
S181
S182
S183
S184
S185
S186
S187
S188
S189
S190
S191
INSTALL 600mmØ RCRRJ CLASS 2 PIPE
LENGTH - 8.0M )
MINIMUM COVER - 300mm
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:15 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX / AWAPUNI SCHOOL WALKWAYGISBORNE
SITE PLANCARNARVON STREET TO GREY STREET
3 / 174 / 450 / 7314 05 R02S8600.08.061GG 1:500 (A1) ; 1:1000 (A3)
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
FOR GATEWAY ENLARGEMENT SEE SHEET 11
FROM SHEET 4
KEY:
NEW 3m WIDE CONCRETE FOOTPATH NEW SPECIMEN TREES
EXISTING TREES SURVEY MARK
SITE PLAN - CARNARVON STREET TO GREY STREET
FOOTPATH - TYPE A
CONCRETE TYPES:
NODES - TYPE B
GAS
T T
W
S
GAS
TELECOM
WATER
WASTEWATER
LEGEND
SW
STORMWATER
P
POWER
SURVEY MARK
SS
ALL SERVICE LOCATIONS ARE INDICATIVE ONLY. CONTRACTOR SHALL LOCATE
ON SITE PRIOR TO COMMENCING ANY CONSTRUCTION WORK.
NOTES:
NEW 3m WIDE CONCRETE FOOTPATH BRUSHED CONCRETE SURFACE SAW CUTS @ 3m CENTRES 100MM CONCRETE SLAB (150MM IN
DESIGNATED AREAS TO ALLOW FOR VEHICLE CROSSINGREFER TO SHEETS 3 AND 4)
100MM COMPACTED SUBBASE 665 MESH LATERAL FIELD DRAINS (NOVACOIL) COORDINATES ARE IN POVERTY BAY CIRCUIT 49 COORDINATE TABLE ON SHEET 12 AND INDICATE THE CENTRELINE OF WALKWAY
THRESHOLD PAVING/SCUPLTURE
AREA/DECORATIVE BANDS - TYPE C
R
3
.
5
0
EXISTING GRASS STRIP
E
X
IS
T
IN
G
F
E
N
C
E
L
IN
E
EXISTING SHELTER
1
.
9
0
PATH CONTINUES AT 3.00 WIDE
4
.5
0
S1
S2
S3
S4
S5
S6
S7
S8
S9
S10
S11
S12
S13
S14
S15
S16
S17
S18
S19
S20
S21
S22
S23
S24
1
2
.
5
0
R3.0
0
8
.
5
0
REMOVE PICNIC TABLE BASE
S25
S26
S27
S28
S29
S30
S31
S32
S33
S34
S35
S36
EXISTING FENCE
CONCRETE WALL (REFER TO SHEET 15 FOR DETAIL)
RAISED GRASS AREA
DECORATIVE CONCRETE BANDS (TYPE C)
(REFER TO SHEET 14 FOR DETAIL)
REMOVE EXISTING
TIMBER FENCE
SAW CUTS AT 3m CENTRES
5.1
0
3
0
.
6
0
1.0
0
1.4
0
1
5
.
5
0
CONCRETE - TYPE B
CONCRETE - TYPE A
5.00
4.50
4.00
3.75
3.25
3.00
6
.0
0
1
0
.
0
0
7
.
7
5
THRESHOLD PAVING (TYPE C)
(REFER TO SHEET 14 FOR DETAIL)
0.0
0.8
0.8
0.8
0.0
0.8
0.8
0.8
0.0
0.0
0.0
0.0
0.0
0.0
D
R
A
I
N
A
G
E
F
A
L
L
D
R
A
I
N
A
G
E
F
A
L
L
D
R
A
I
N
A
G
E
F
A
L
L
D
R
A
I
N
A
G
E
F
A
L
L
D
R
A
I
N
A
G
E
F
A
L
L
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:15 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX / AWAPUNI SCHOOL WALKWAYGISBORNE
ENLARGED PLANSTANLEY ROAD GATEWAY PLAN
3 / 174 / 450 / 7314 06 R02S8600.08.061GG 1:50 (A1) ; 1:100 (A3)
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
NOTES:
COORDINATES ARE IN POVERTY BAY CIRCUIT 49 COORDINATE TABLE ON SHEET 13 TREES REMOVED FOR CLARITY (REFER TO SHEETS 02 TO 05)
FOOTPATH - TYPE A
CONCRETE TYPES:
NODES - TYPE B
THRESHOLD PAVING/SCUPLTURE
AREA/DECORATIVE BANDS - TYPE C
A
15
A
15
CONCRETE - TYPE B
SAW CUTS
THRESHOLD PAVING (TYPE C)
(REFER TO SHEET 14 FOR DETAIL)
CONCRETE - TYPE A
RAILWAY CROSSING
(REFER TO SHEET 16 FOR DETAIL)
S130
S97
S97a
S98
S98a
3.25
3.0
0
2.75
1.7
5
R
3
.
0
0
4.50
4.0
0
2
.
5
0
R
3
.
0
0
2
0
0
m
m
200mm 200mm
RAILWAY SLEEPER
Railway sleeper
Concrete footpath
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:15 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX / AWAPUNI SCHOOL WALKWAYGISBORNE
ENLARGED PLAN - WALKWAY TO RAILWAY CROSSING
3 / 174 / 450 / 7314 07 R02S8600.08.061GG AS SHOWN
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
RAILWAY CROSSING TREATMENT - PLAN VIEW
SCALE 1:20 (A1); 1:40 (A3)
SLEEPER AND TRACK - TYPICAL CROSS SECTION
SCALE 1:10 (A1); 1:20 (A3)
NOTES:
COORDINATES ARE IN POVERTY BAY CIRCUIT 49 COORDINATE TABLE ON SHEET 13
FOOTPATH - TYPE A
CONCRETE TYPES:
NODES - TYPE B
THRESHOLD PAVING/SCUPLTURE
AREA/DECORATIVE BANDS - TYPE C
S37
S38
S39
S40
S41
S42
S43S44
S45
S46
S47
S48
R
2
2
.
2
5
R
1
3
.
7
5
R
2
0
.0
0
20
.2
5
17.25
5.5
0
4.50
13.25
13
.2
5
THRESHOLD PAVING (TYPE C)
(REFER TO SHEET 14 FOR DETAIL)
THRESHOLD PAVING (TYPE C)
(REFER TO SHEET 14 FOR DETAIL)
THRESHOLD PAVING (TYPE C)
(REFER TO SHEET 14 FOR DETAIL)
INTERPRETATION/SIGNAGE/SCULPTURE
(REFER TO SHEET 14 FOR DETAIL)
SURFACE TREATMENT (TYPE C)
(REFER TO SHEET 14 FOR DETAIL)
CONCRETE - TYPE B
150MM CONCRETE - TYPE A
150MM CONCRETE - TYPE A
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:15 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX / AWAPUNI SCHOOL WALKWAYGISBORNE
ENLARGED PLAN - 3 WAYS
3 / 174 / 450 / 7314 08 R02S8600.08.061GG 1:100 (A1) ; 1:200 (A3)
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
NOTES:
COORDINATES ARE IN POVERTY BAY CIRCUIT 49 COORDINATE TABLE ON SHEET 13
FOOTPATH - TYPE A
CONCRETE TYPES:
NODES - TYPE B
FOOTPATH - TYPE A (150mm)
THRESHOLD PAVING/SCUPLTURE
AREA/DECORATIVE BANDS - TYPE C
3
.
0
0
R
A
M
P
U
P
R
A
M
P
U
P
THRESHOLD PAVING (TYPE C)
(REFER TO SHEET 14 FOR DETAIL)
EXISTING PIPE AND BUND
SURFACE TREATMENT (TYPE C)
(REFER TO SHEET 14 FOR DETAIL)
INTERPRETATION/SIGNAGE/SCULPTURE
(REFER TO SHEET 14 FOR DETAIL)
THRESHOLD PAVING (TYPE C)
(REFER TO SHEET 14 FOR DETAIL)
8
.
0
0
3
.
0
0
R
3
1
.0
0
2
7
.
0
0
6
0
°
S49
S50
S51
S52
S54
S55
S56
S57
S58
S59
S60
SURFACE TREATMENT (TYPE B)
150MM CONCRETE - TYPE A
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:16 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX AWAPUNI SCHOOL WALKWAYGISBORNE
ENLARGED PLANNODE - PIPE AND BUND
3 / 174 / 450 / 7314 09 R02S8600.08.061GG 1:100 (A1) ; 1:200 (A3)
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
NOTES:
COORDINATES ARE IN POVERTY BAY CIRCUIT 49 COORDINATE TABLE ON SHEET 13 TREES REMOVED FOR CLARITY (REFER TO SHEETS 02 TO 05)
FOOTPATH - TYPE A
CONCRETE TYPES:
NODES - TYPE B
FOOTPATH - TYPE A (150mm)
THRESHOLD PAVING/SCUPLTURE
AREA/DECORATIVE BANDS - TYPE C
THRESHOLD PAVING (TYPE C)
(REFER TO SHEET 14 FOR DETAIL)
THRESHOLD PAVING (TYPE C)
(REFER TO SHEET 14 FOR DETAIL)
S61
S62
S63
S64
S65
S66
S67
S68
S69
3
.
0
0
R55.50
3
.
0
0
10.00
3
1
.
5
0
1
2
0
°
SURFACE TREATMENT (TYPE B)
INTERPRETATION/SIGNAGE/SCULPTURE
(REFER TO SHEET 14 FOR DETAIL)
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:16 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX AWAPUNI SCHOOL WALKWAYGISBORNE
ENLARGED PLANNODE - CARNARVON STREET
3 / 174 / 450 / 7314 10 R02S8600.08.061GG 1:100 (A1) ; 1:200 (A3)
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
NOTES:
COORDINATES ARE IN POVERTY BAY CIRCUIT 49 COORDINATE TABLE ON SHEET 13 TREES REMOVED FOR CLARITY (REFER TO SHEETS 02 TO 05)
NOTE : OVERHEAD POWERLINES AND POWERPOLE
WITHIN VICINITY OF WORKS
FOOTPATH - TYPE A
CONCRETE TYPES:
NODES - TYPE B
FOOTPATH - TYPE A (150mm)
THRESHOLD PAVING/SCUPLTURE
AREA/DECORATIVE BANDS - TYPE C
G
R
E
Y
S
T
R
E
E
T
THRESHOLD PAVING (TYPE C)
(REFER TO SHEET 14 FOR DETAIL)
DECORATIVE CONCRETE BANDS (TYPE D)
(REFER TO SHEET 14 FOR DETAIL)
EXISTING FOOTPATH
THRESHOLD PAVING (TYPE C)
(REFER TO SHEET 14 FOR DETAIL)
SURFACE TREATMENT (TYPE C)
INTERPRETATION/SIGNAGE/SCULPTURE
(REFER TO SHEET 14 FOR DETAIL)
S70
S71
S72
S73
S74
S75
S76
S77
S78
S79
S80
S81
S82
S83
S84
S85
S86
S87
S88
S89
S90
S91
S92
S93
S94
S95
S96
3
.
0
0
2
.
5
0
10.00
1
0
.
0
0
1
5
.0
0
R
1
2
.
0
0
R
2
2
.0
0
SURFACE TREATMENT (TYPE B)
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:16 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX AWAPUNI SCHOOL WALKWAYGISBORNE
ENLARGED PLANGREY STREET GATEWAY PLAN
3 / 174 / 450 / 7314 11 R02S8600.08.061GG 1:100 (A1) ; 1:200 (A3)
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
NOTES:
COORDINATES ARE IN POVERTY BAY CIRCUIT 49 COORDINATE TABLE ON SHEET 13 TREES REMOVED FOR CLARITY (REFER TO SHEETS 02 TO 05)
FOOTPATH - TYPE A
CONCRETE TYPES:
NODES - TYPE B
FOOTPATH - TYPE A (150mm)
THRESHOLD PAVING/SCUPLTURE
AREA/DECORATIVE BANDS - TYPE C
Coordinate Schedule
Northing
695281.35
695280.58
695278.93
695269.57
695260.27
695257.29
695255.32
695244.12
695234.23
695232.91
695231.42
695229.19
695226.41
695214.83
695212.86
695212.25
695211.41
695210.11
695206.56
695202.12
695201.23
695200.34
695198.65
695196.12
695192.51
695190.88
695189.21
695191.70
695202.47
695203.49
695204.04
Easting
310456.38
310462.13
310467.73
310489.74
310511.95
310523.80
310532.58
310582.34
310626.25
310632.11
310637.84
310643.79
310649.34
310670.40
310675.81
310681.91
310693.88
310708.86
310732.60
310762.27
310768.21
310774.14
310779.68
310785.30
310793.66
310802.73
310814.72
310826.27
310854.29
310859.88
310903.06
Description
S100
S101
S102
S103
S104
S105
S106
S107
S108
S109
S110
S111
S112
S113
S114
S115
S116
S117
S118
S119
S120
S121
S122
S123
S124
S125
S126
S127
S128
S129
S130
Coordinate Schedule
Northing
695236.48
695263.75
695331.46
695246.46
695245.84
695245.36
695244.39
695242.64
695238.71
695217.68
695214.37
695211.57
695209.15
695205.27
695204.43
695203.26
695200.62
695196.92
695193.05
695189.45
695181.50
695167.19
695161.90
695157.89
695152.37
695147.40
695145.19
695143.42
695141.59
695139.84
695135.32
Easting
310923.87
310930.37
310931.14
310947.56
310965.79
310971.77
310980.69
310992.50
311011.30
311067.54
311076.12
311084.61
311093.38
311113.89
311125.87
311137.76
311155.53
311173.13
311187.58
311198.95
311219.86
311253.37
311267.43
311278.91
311296.17
311313.61
311322.13
311333.91
311345.79
311354.39
311368.51
Description
S131
S132
S133
S134
S135
S136
S137
S138
S139
S140
S141
S142
S143
S144
S145
S146
S147
S148
S149
S150
S151
S152
S153
S154
S155
S156
S157
S158
S159
S160
S161
Coordinate Schedule
Northing
695129.97
695128.98
695128.61
695127.50
695124.05
695119.60
695114.12
695107.64
695106.13
695106.16
695105.42
695102.76
695096.12
695090.72
695087.27
695085.93
695085.26
695081.23
695072.95
695064.33
695059.00
695056.06
695048.63
695038.64
695026.61
695020.40
695014.49
695008.95
694999.97
694992.66
Easting
311382.39
311387.92
311399.75
311411.59
311429.09
311443.29
311453.96
311466.95
311475.20
311487.01
311492.84
311501.33
311510.33
311517.19
311524.78
311532.91
311538.74
311545.94
311558.30
311573.81
311584.57
311589.65
311599.08
311609.13
311617.84
311623.59
311630.12
311637.23
311644.38
311649.41
Description
S162
S163
S164
S165
S166
S167
S168
S169
S170
S171
S172
S173
S174
S175
S176
S177
S178
S179
S180
S181
S182
S183
S184
S185
S186
S187
S188
S189
S190
S191
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:16 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX AWAPUNI SCHOOL WALKWAYGISBORNE
SETOUT POINT TABLE - WALKWAY
3 / 174 / 450 / 7314 12 R02S8600.08.061GG NTS
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
NOTES:
SITE PLANS SHOWING WALKWAY ON SHEETS 02 - 05 COORDINATES ARE IN POVERTY BAY CIRCUIT 49 COORDINATES INDICATE THE CENTRELINE OF WALKWAY
Coordinate Schedule
Northing
695282.90
695285.10
695289.37
695295.58
695297.37
695293.22
695291.19
695286.93
695285.92
695284.53
695284.10
695283.85
695283.60
695283.34
695283.09
695279.75
695279.62
695279.49
695279.37
695279.28
695280.58
695282.69
695283.18
695282.43
695284.80
695286.50
695288.79
695290.64
695289.34
695288.35
695287.33
695286.94
695283.99
Easting
310425.14
310425.94
310427.50
310429.75
310430.41
310430.10
310431.33
310433.92
310434.49
310436.47
310441.56
310444.55
310447.54
310450.53
310453.52
310453.24
310450.21
310447.19
310444.17
310441.07
310435.66
310428.58
310426.96
310426.70
310427.46
310428.65
310427.85
310430.39
310429.83
310430.25
310431.58
310433.56
310429.39
Description
S1
S2
S3
S4
S5
S6
S7
S8
S9
S10
S11
S12
S13
S14
S15
S16
S17
S18
S19
S20
S21
S22
S23
S24
S25
S26
S27
S28
S29
S30
S31
S32
S33
Coordinate Schedule
Northing
695168.57
695165.82
694991.86
694993.45
694991.42
694989.83
694979.85
694976.72
694987.23
694986.17
694987.95
694989.10
694987.82
694986.70
694984.27
694983.39
694984.80
694987.76
694989.09
694985.07
694983.91
694982.45
694980.82
694978.01
694979.17
694980.68
694983.06
694983.92
694983.92
695205.58
695202.58
695207.41
695206.52
Easting
311253.92
311252.81
311648.13
311650.67
311652.02
311649.48
311650.18
311659.76
311667.32
311668.38
311670.06
311668.90
311666.73
311661.65
311659.68
311656.47
311654.11
311653.89
311654.42
311649.81
311652.08
311653.63
311654.25
311654.00
311660.86
311659.63
311660.44
311663.26
311664.14
310906.29
310906.33
310909.02
310910.81
Description
S68
S69
S70
S71
S72
S73
S74
S75
S76
S77
S78
S79
S80
S81
S82
S83
S84
S85
S86
S87
S88
S89
S90
S91
S92
S93
S94
S95
S96
S97
S97a
S98
S98a
Coordinate Schedule
Northing
695285.49
695284.35
695281.21
695236.80
695235.75
695240.97
695239.17
695261.33
695261.30
695263.74
695263.77
695248.11
695244.78
695248.11
695244.81
695237.27
695240.16
695239.56
695236.67
695232.06
695227.05
695221.86
695217.27
695220.00
695219.05
695216.32
695180.14
695182.86
695181.86
695179.17
695169.13
695166.68
695169.46
Easting
310431.95
310434.45
310435.55
310922.79
310924.73
310924.45
310927.81
310928.88
310931.88
310931.87
310928.88
310945.13
310945.11
310947.57
310947.55
311010.89
311011.70
311014.07
311013.26
311028.82
311022.82
311053.62
311064.67
311065.91
311068.16
311066.92
311219.23
311220.49
311222.72
311221.47
311222.57
311250.53
311251.65
Description
S34
S35
S36
S37
S38
S39
S40
S41
S42
S43
S44
S45
S46
S47
S48
S49
S50
S51
S52
S54
S55
S56
S57
S58
S59
S60
S61
S62
S63
S64
S65
S66
S67
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:16 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX AWAPUNI SCHOOL WALKWAYGISBORNE
SETOUT POINT TABLE - ENLARGED VIEWS
3 / 174 / 450 / 7314 13 R02S8600.08.061GG NTS
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
NOTES:
ENLARGED VIEWS ON SHEETS 06 - 11 COORDINATES ARE IN POVERTY BAY CIRCUIT 49
2.50
3.0
0
NEW CONCRETE FOOTPATH WITH MESH
(THRESHOLD - TYPE C)
NEW CONCRETE FOOTPATH (TYPE A) WITH MESH
(REFER TO NOTES ON SHEETS 02 TO 05)
200mm TIMBER BLOCK (E.G. TOTARA OR IRONBARK)
NEW CONCRETE FOOTPATH (TYPE A) WITH MESH
(REFER TO NOTES ON SHEETS 02 TO 05)
100mm SUBBASE
(REFER TO NOTES ON SHEETS 02 TO 05)
NEW CONCRETE FOOTPATH WITH MESH
(THRESHOLD - TYPE C)
TIMBER BLOCK
30
0m
m
TO
S
UIT
S
CU
LP
TU
RE
TO SUIT SCULPTURE
INTERPRETATION/SIGNAGE/
SCULPTURE (NOT IN CONTRACT)
SURFACE TREATMENT TO
MATCH THRESHOLD PAVING
(TYPE C)
D12 BARS
- 6 NO. EACH SIDE; 30MM COVER
D10 STIRRUPS AT 250mm CRS
- 3NO. PER SET
NEW CONCRETE FOOTPATH WITH MESH
(REFER TO NOTES ON SHEETS 02 TO 05)
100mm SUBBASE
(REFER TO NOTES ON SHEETS 02 TO 05)
TO SUIT SCULPTURE
DECORATIVE CONCRETE BAND (TYPE C)
(REFER TO SHEETS 06 AND 11 FOR SETOUT COODS)
NEW CONCRETE FOOTPATH (TYPE A)
(REFER TO NOTES ON SHEETS 02 TO 05)
NEW CONCRETE FOOTPATH (TYPE A) WITH MESH
(REFER TO NOTES ON SHEETS 02 TO 05)
100mm SUBBASE
(REFER TO NOTES ON SHEETS 02 TO 05)
NEW DECORATIVE CONCRETE BAND (TYPE C)
(REFER TO NOTES ON SHEETS 02 TO 05)
NEW CONCRETE FOOTPATH (TYPE A) WITH MESH
(REFER TO NOTES)
100mm SUBBASE
(REFER TO NOTES)
3.00 TYP
TOPSOIL AND SEED
2% CROSSFALL
300mm
Ø100mm PERFORATED SUBSOIL PIPE
(NOVAFLO OR SIMILAR)
PROVIDE A MINIMUM OF 150mm THICKNESS OF
FREE DRAINING MATERIAL (SCOFA OR SELECTED
CRUSHED ROCK BACKFILL) TO 300mm DEPTH
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:16 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX AWAPUNI SCHOOL WALKWAYGISBORNE
MISCELLANEOUS DETAILS
3 / 174 / 450 / 7314 14 R02S8600.08.061GG AS SHOWN
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
TYPICAL SECTION VIEW
SHOWING REINFORCING AT SCULPTURE AREA
SCALE 1:25 (A1) ; 1:50 (A3)
TYPICAL PLAN VIEW
SHOWING SCULPTURE AREA
SCALE 1:25 (A1) ; 1:50 (A3)
TYPICAL PLAN VIEW
SHOWING THRESHOLD PAVING DETAIL
SCALE 1:25 (A1) ; 1:50 (A3)
TYPICAL SECTION VIEW
SHOWING THRESHOLD PAVING DETAIL
SCALE 1:25 (A1) ; 1:50 (A3)
TYPICAL PLAN VIEW
SHOWING DECORATIVE BAND
SCALE 1:50 (A1) ; 1:100 (A3)
TYPICAL SECTION VIEW
SHOWING DECORATIVE BAND
SCALE 1:25 (A1) ; 1:50 (A3)
TYPICAL SECTION VIEW SHOWING FOOTPATH AND SUBSOIL
SCALE 1:10 (A1) ; 1:20 (A3)
800
mm
800
mm
19.0m (PROJECTION DISTANCE)
25
0m
m
25
0m
m
2.5m (CURVED FACE) 2.5m (CURVED FACE)
FFL
FFL
35
0m
m
300mm
NEW CONCRETE FOOTPATH WITH MESH
(REFER TO NOTES ON SHEETS 02 TO 05
100mm SUBBASE
(REFER TO NOTES ON
SHEETS 02 TO 05)
3
0
°
IN-SITU CAST CONCRETE RETAINING
WALL TO CLASS F6 FINISH
(STEEL TROWELED )
500mm
25
0m
m
1% FALL
200mm
LAWN
10
0m
m
STEEL TROWELED
FINISH TO 100mm
BELOW TOP OF WALL
100mm COMPACTED SUBBASE
(REFER TO NOTES ON
SHEETS 02 TO 05)
20Mpa PLAIN CONCRETE 2%
BLACK OXIDE WITH
D12-140 REINFORCING
RODS WITH R6-600 LINKS
80
0m
m
300mm
NEW CONCRETE FOOTPATH WITH MESH
(REFER TO NOTES ON SHEETS 02 TO 05
100mm COMPACTED SUBBASE
(REFER TO NOTES ON SHEETS 02 TO 05)
20Mpa PLAIN CONCRETE 2%
BLACK OXIDE WITH
D12-140 REINFORCING
RODS WITH R6-600 LINKS
IN-SITU CAST CONCRETE RETAINING
WALL TO CLASS F6 FINISH
(STEEL TROWELED)
768mm
1% FALL
3
0
°
468mm
25mm CHAMFER
LAWN
25
0m
m1
00
mm
STEEL TROWELED
FINISH TO 100mm
BELOW TOP OF WALL
100mm COMPACTED SUBBASE
(REFER TO NOTES ON
SHEETS 02 TO 05)
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:16 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX AWAPUNI SCHOOL WALKWAYGISBORNE
WALL AND RAISED PLINTH DETAILS
3 / 174 / 450 / 7314 15 R02S8600.08.061GG AS SHOWN
CONSTRUCTION
S STEYN A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
PROJECTED ELEVATION
SHOWING RAISED PLINTH
SCALE 1:25 (A1) ; 1:50 (A3)
SECTION A-A
SCALE 1:10 (A1) ; 1:20 (A3)
SECTION B-B
SCALE 1:10 (A1) ; 1:20 (A3)
A
15
B
15
Rail Crossing - Isometric
Scale 1:50 (A1); 1:100 (A3)
R
a
i
l
w
a
y
Alfred Cox Park
W
a
ik
a
n
a
e
S
tre
a
m
Existing Railway
Bridge
New Bridge
'WX8 Look for Trains sign
both sides of fence
Standard maze fencing
(Folded pool fence or similar)
Vertical bars at 75mm centres
(Some removed for clarity)
Continue fence up to existing fence
Surface Treatment
(Type B)
Surface Treatment
(Type B)
"Look for Trains" Signs
both sides of fence
No planting higher than 1m in
this area, and sufficient to
encourage pedestrians to use
the formed crossing
900mm Ø Culvert with
walkway over drain
Rail Crossing - Plan
Scale 1:100 (A1); 1:200 (A3)
A
w
a
p
u
n
i
S
c
h
o
o
l
Open drain
New Bridge
Gisborne R/W Station
Napier
Waikanae Stream
Alfred Cox
Park
Proposed walkway
Tactile ground surface indicator
Raised pavement markers
(Both sides)
1.9
0
2.00
1.9
0
2.30
Standard maze fencing
(Folded pool fence or similar)
Fence up to existing fence
Fence up to existing bridge
1.9
0
3.8
0
4.00
C of Railway
Basecourse
Tactile ground
surface indicator
Rail Crossing - Elevation
Scale 1:50 (A1); 1:100 (A3)
Abutment
Rock riprap
New bridge
L
400mm culvert
Proposed walkway
1.90 1.90
A modified platform to the new bridge
will be required to fit Pedestrian maze
Refer to plan for layout detail
Continue fence to existing fence
Fill
TIMBER BLOCKS 225mm X 150mm X 2200mm
LONG COACHSCREWED TO EXISTING
2.0
0
CONCRETE - TYPE B
TIMBER BLOCKS 225mm X 150mm X 2200mm
LONG COACHSCREWED TO EXISTING
EXISTING SLEEPERS
BASECOURSE
Approved Revision DateRevision Amendment
200
100
5010
0mm
300
mm
ScaleProject No. Drawing No. Sheet. No.
Project
Sheet
Revision
Original Sheet Size A1 [841x594] Plot Date 8/28/2013 2:16 p.m. Path G:\GDC EW08-25 PS\2S8600 Community Facilities\08 Alfred Cox Park Walkway\Drawings\3_174_450_7314_01-16R0.dwg
Drawn Approved Revision DateDesigned
Gisborne Office PO Box 49Gisborne 4040New Zealand+64 6 868 5199
GISBORNE DISTRICT COUNCILALFRED COX / AWAPUNI SCHOOL WALKWAYGISBORNE
ENLARGED PLAN - RAILWAY CROSSING AND WALKWAY PATH
3 / 174 / 450 / 7314 16 R02S8600.08.061GG AS SHOWN
CONSTRUCTION
PF/SS A WILLIAMSON 28/08/2013SS/CH
Dimensions in metres unless otherwise stated
TYPICAL PLAN VIEW
SHOWING RAILWAY CROSSING
SCALE 1:25 (A1) ; 1:50 (A3)
TYPICAL SECTION VIEW
SHOWING RAILWAY CROSSING
SCALE 1:25 (A1) ; 1:50 (A3)
Opus International Consultants Ltd F2, Wilson James Centre, 75 Peel St PO Box 49, Gisborne 4040 New Zealand t: +64 6 868 5199 f: +64 6 867 8075 w: www.opus.co.nz