Contract, Construction Sequence 01 rev 00, 13,05,11 start date 23,05,11.PDF
1
St Andrews House 1 Dreadnought Street Greenwich London SE10 0PU 020 8858 9124 www.okeefe.co.uk title: drawing: date: scale: checked by: drawn by: J.B. A.S. O'KEEFE CONSTRUCTION (Greenwich) LTD 115 Ridgeway, Wimbledon INFORMATION TOWER CRANE SPAN = 43m 1 2 3 4 5 6 7 8 9 10 EXISTING GROUND LEVEL APPROX 54.300 PILING MATT 600mm APPROX 54.000 PILING MATT 600mm APPROX 53.000 EXISTING GROUND LEVEL APPROX 54.300 (VARIES) HOUSES 1-5 HOUSES 6-10 TREE PROTECTION ZONE TREE PROTECTION ZONE INDICATIVE CRANE POSITION 1 3 5 2 4 6 7 KEY DATES TYPICAL WORK SEQUENCE HOUSE No.10 TYPICAL WORK SEQUENCE OK-RW-TWS-01 NTS(A1) 13/05/2011
-
Upload
lucian-gerea -
Category
Documents
-
view
17 -
download
0
Transcript of Contract, Construction Sequence 01 rev 00, 13,05,11 start date 23,05,11.PDF
St Andrews House1 Dreadnought Street
GreenwichLondon
SE10 0PU020 8858 9124
www.okeefe.co.uktitle:
drawing:
date: scale:
checked by:drawn by:J.B.A.S.
O'KEEFECONSTRUCTION (Greenwich) LTD
115 Ridgeway, Wimbledon
INFORMATION
TOWER CRANESPAN = 43m
1 2 3 4
5
6
7
8
9
10
EXISTINGGROUND LEVELAPPROX 54.300 PILING MATT 600mm
APPROX 54.000 PILING MATT 600mmAPPROX 53.000
EXISTINGGROUND LEVELAPPROX 54.300
(VARIES)
HOUSES 1-5 HOUSES 6-10
TREE PROTECTIONZONE
TREE PROTECTIONZONE
INDICATIVECRANE POSITION
1 3 5
2 4 6
7
KEY DATES
TYPICAL WORK SEQUENCEHOUSE No.10
TYPICAL WORKSEQUENCE
OK-RW-TWS-01
NTS(A1)13/05/2011