Contract Change Order No. 18 Redacted

download Contract Change Order No. 18 Redacted

of 8

Transcript of Contract Change Order No. 18 Redacted

  • 8/20/2019 Contract Change Order No. 18 Redacted

    1/17

    Citv of Carmel-bv-the-Sea

    PUBLIC WORKS DEPARTMENT

    POST OFFICE BOX CC, CARMEL-BY -THE-SEA, CA 93921

    (831) 620-2070

    CONTRACT CHANGE ORDER NO_ 18

    CONTRACT AWARDED BY: City Council DATE

    OF

    AWARD Apr 7, 2015

    ~   ~ O ~ J ~ ~ T ~ ~ ~ ~ s ~ t _ T~ ~ ~ ~ ~   ~ e ~ n _ o ~ v ~ ~ t i ~ o ~

    ________

    ____

    ____________________

    _________

    SHEET

    _____

    _

    o_f_

    ____

    PROJECT ID#: 13-70903 Purchase Order#: 76-004428

    TO: Otto

    Construction

    Company; 2150 Garden Road, Suite A-1, Monterey, CA 94940

    ,CONTRACTOR

    You are

    hereby requested

    to make the

    herein described

    changes

    from the

    plans and

    specifications

    or do

    the

    following

    described

    work not included in the plans and specifications

    on

    this

    contract

    .

    NOTE: THIS CHANGE IS NOT EFFECTIVE UNTIL FULLY EXECUTED.

    Chan

    Description:

    1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.

    Deletion: Credit labor and materials related

    to

    the following: Reference RFP #25, Bulletins #14

    &

    14.1, and PCO #42

    Rev1

    (Otto's tracking number). Summary of Work; multiple items related

    to Driveway Revisions and difficulty

    in

    drilling driveway piers.

    Agreed Lump Sum ... .. . .... ..

    ..............................................

    ....... ......... ........ .. .

    2 CONTRACT PRICE

    Total decrease in contract price

    3 CONTRACT TIME

    Twenty Five (25) additional working days

    $ (12,203.00)

    Decrease

    Original Contract Price

    Approved Cost Changes to Date

    Total

    of

    all Contract Changes

    includ this Order

    Sum net change in Contract Price

    is

    $ 1 462,236.00

    $ 97,524.00

    $

    321.00

    of the original Contract Price 5.8%

    We  the undersigned contracto

    r

    have given careful consideration to the change proposed

    and

    hereby agree  if his proposal is

    approved  that we will provide all equipment furnish all materials except as may otherwise be noted above and perform all services

    necessary for the work above specifi

    ed

     

    and

    will accept

    as

    full payment therefore the price shown above.

    Contractor:

    Otto Construction Company

    Signed

    :

    I

    f he contractor does not sign acceptance of this order his attention is dir

    ec

    ted to the requirements

    of

    the

    Submitted

    :

    ea

    $

    (12,203.00)

    $ (12,203.00)

    25

  • 8/20/2019 Contract Change Order No. 18 Redacted

    2/17

      TT

    Pr o

    je ct

    Forest

    Th

    eater Renovation

    Description

    of

    Change

    Below

    and t t c h ~ d _ p l

    mg is

    related to RFP 25 amendment No. 1,

    Bulletin

    14

    &

    14.1 and Pricing is related to

    the

    reduction

    of

    the quantity of

    driveway piers,

    wall

    height

    and

    stone veneer.

    The additional

    work

    is

    relate

    the raising of

    grade at

    the

    lower

    pathways and discovered stone per RFI 2

    Excludes

    change in footing design

    (Bulletin

    14

    &

    14.1) at

    section

    of

    already

    poured

    wall

    at

    the

    acceptable parking

    area.

    Will

    be

    addressed in

    separate

    change

    order

    .

    Excludes engineering

    ,

    permits, surveyor,

    detailing/shop

    drawings and

    undiscovered existing conditions.

    Excludes

    General Conditions costs,

    to be

    discussed at a

    later date

    .

    CHANGE ESTIMATE ITEM

    COST

    M/U %

    MIUTOTAL

    GC DIRECT COSTS

    GC

    DIRECT LABOR

    GC DIRECT MATERIALS

    GC

    DIRECT EQUIPMENT

    GC OTHERIINDIRECTS

    GC

    MARKUP

    ON DIRECT

    COST

    GC

    MARKUP ON DIRECT LABOR

    GC MARKUP ON DIRECT MATERIAL

    GC MARKUP ON DIRECT EQUIPMENT

    GC MARKUP ON DIRECT OTHERIINDIRECTS

    GC SUBCONTRACT(S) OR OTHERS'

    Patania Masonry

    GC

    FEE ON

    SUBCONTRACT(S)

    - 3,830

    -

     

    ,046

    7,

    419

    -$991

    ($3,830)

    ($6,046)

    $7,419

    ($991)

    ($8,755)

    - 8,755

    0.0%

    0.0%

    0.0%

    0.0%

    0.0%

    0

    0

    $0

    0

    0

    Related RFI

    42 Rev1

    25

    14.1

    25

    DATE: 12/03/15

    TOTAL L, M,

    &

    E DIRECT COST -$3,448

    TOTAL MARKUP ON DIRECT COST

    0

    TOTAL SUBCONTRACT

    COST

    - 8

    ,755

    TOTAL

    GC FEE

    ON SUBCONTRACT( )

    0

  • 8/20/2019 Contract Change Order No. 18 Redacted

    3/17

  • 8/20/2019 Contract Change Order No. 18 Redacted

    4/17

    OJ

    TO

    ' '

    D ~ 5 t r l , . :m

    RFP2

    5

    U220 &1.f 5

    ldt « d .

    a

    nd a( l.( lfl

    Dol

    .::" , I

    ti. Ec :- va o } r o:OT.(

    l l l Gr.t,. 1 C B.c:kh.•

    ;o tlo

    , ' '

    )IIF'A

    fC

    .

    '" 'l" '-1

    0 2 _ . lOO U . ~ n t

    sn.art

    01\••

    CI Ptt 1i

    ~ ~ ~ P• t uce

    } t -«.4-:J.'P-

    4f

    C.J •

    1\flf .n

    1'

    • l ' l . ' P ' . c

    "lO• j• P.a

    i') . , r • F . · ~ s N . . , : / 0

    ~ ~ . -

    R . . - . . . c r o ~ ·

    ..u.JP·1')\c;

    Stral,t.t 1 f t Ortha r ' l po FW

    t ~ t

    Lf.

    i:J. I )I

    l;,.

    "

    ) h •• 'l

    O·,,T ' f " " ' f l f \ I .

    ~ · Y I

    ' t ~ 20

    0 r;, : f f'Cetl

    rrg

    f l : o ~ F · ~ )

    • . , .•

    ·( .

    '< ol

    '

    ,,.,.t

    & G

    .do

    r' J.'

    . , . 'O(' IUtt f '

    II

    ~ : . . , ~ ~ · , . v ~ t ' f l t i . ' . I ' U L F

    '"- f

    -"11

    .....,...

    ' 1 -:\

    F

    -1

    P . .&;("'

    ..   l ln t

    i

    Of .

    L

    U n " . . , ' " ' " ./,;.

    1

    1l-   P t . r ~ 1 

    t i l : PS

    YJ.II ' f

    .o·

    Co nc'' ' ' wa

    J VI t .. u t\)•J&

    O l l i ~

    Con

    e . SC01n 0"10 .-eM

    214 F

    . C. C,,,•'t' ~ l

    .,

    "

    tr<

    tie.

    ,, ,.

    i ) "A l

    ~ " " 1 1 1 . F

    I

    :;:r

    _

    :;r-

    (. ••·

    •o

      ;

    ;o;c,

    (o t ',

    - · 'iio4lfCV . J . . _ _ L ~ 2

    Hr•j l ,

    ICY

    ~ . 0 4

    13"Jlo

    __

    ; ,1 )

    ~ \ 1 I f

    4 1 ~ · . .

    t:

    (

    l ?t

    • '.J

    .C"'

    r

    c -::r_ ·

    "

    H·;c.; r :":

    1'Ur't. U' \1 \ t • t t

    ) l . ~ (

    ...a,

    })

    :

    .;;

    . ~ '

    f1

    ,H..2)

    i ..

    "

    .,

    ; c ~ .

    tnt )

    i11

    1)

    t

    l C )

    j ( } . , ~ CY

    ~

    A m O .o"'f

    ""'

    I

    _ .J

    ( l

    urt

    thr:C\Hit

    A -,

    ,m

    U

    l l tHct l

    1

     1 U

    _o

    i T . •

    ""

    1411

    (41)

    t 1 ~ : )

    f

    4j,

    P?1)

    6 , 3 9 ~

    _'J(.t'

    ::'IC;'} .(;Y

    ~ r . l : J

    1 4

  • 8/20/2019 Contract Change Order No. 18 Redacted

    5/17

      DDITION L

    WORK

    UTHORIZ TION

    ATTENTION

    C('f.J I

    :> ll   ..t l

    r:ll'

    : I A I

     o   l . O G t

    I

    t

  • 8/20/2019 Contract Change Order No. 18 Redacted

    6/17

    P O

    42 Additional Time equest Summaries

    Driveway Revisions Discovered Bedrock 21 Days

    • Existing bedrock discovered Wednesday September 23, 2015. RFI 75 drafted and submitted

    same day (9/23/15). Received new potential footing design 10/12/15 Cost of labor, material

    and equipment was

    not

    beneficial to the project

    or

    the city. Bulletin 14.1 received 11/4/15

    o Thirty-seven (31 usiness days

    from

    discovery

    of

    bedrock

    o Requesting Twenty-one

    Drilling Piers 4 Days

    • Existing soil conditions

    would not

    allow required piers

    to

    install

    per

    plan

    s

    Section

    of

    piers was

    removed

    from lower

    retaining wall per Bulletin 14.1. Contrac

    tor

    drilled piers per Bulletin 14

    and original plans to best

    of

    ability. Not all piers could be drilled to required depth. Specialized

    equipment was brought in.

    o Four (4) days delay

  • 8/20/2019 Contract Change Order No. 18 Redacted

    7/17

    OTTO

    ONSTRU TION

    To: Andrew Vanderford

    CITY OF CARMEL BY THE SEA

    P.O. Box CC

    Carmel By the Sea, CA 93921

    Ph: 831-620-2078

    R I

    I

    RFI : 75

    Date: 9/23/2015

    2150 GARDEN ROAD, SUITE A-1

    MONTEREY, CA 93940

    Ph

    : 831 657-9805

    Job: 15-3141-00 FOREST THEATER RENOVATIONS

    Phone: 831 )620-2078

    CC: Monique Wood (Cody Anderson Wasney), Jilian Cadouri (Cody Anderson Wasney). Oscar Cisneros (Otto Construction), Matt

    Wetmore (Otto Construction)

    Subject:

    Exposed Bedrock at Driveway

    Drawing:

    A0.4

    Cost Impact: TBD

    Request:

    Spec Section: 310000

    Schedule Impact: TBD

    Date Required: 9/30/2015

    During excavation of the footings for the stone walls along the driveway, contractor exposed a large area of bedrock at the south

    most end of driveway. This bedrock intersects with our footing, piers and driveway. For the footings, Contractor is proposing to

    jackhammer down to elevation per plans until reaching bottom of footings. Then in lieu of the piers at these locations, Contractor

    proposes to dowel into the bedrock. Please verify with specialist and confirm acceptable.

    Due to the unknown size of this area of bedrock, there is a possibility of hitting bedrock again when excavating

    fo

    r piers further up

    the driveway. In this situation, Contractor is unsure of direction to take. It would be physically diffic

    ul

    t to dowel inside t

    he

    small, and

    possibly deep excavation required for the piers. See attached map. Please advise.

    Requested by: Scott Vander Heyden

    OTTO CONSTRUCTION

    Response:

    See Attached Detail for Revised Footing with key at driveway . There is one design for 3 retained

    soil and another with 1.5 retained soil.

    The detail shows concrete shel f to support stone

    veneer

    notify RPSE if contractor prefers

    to

    use bolted

    ledger angle to support stone on the driveway side.

  • 8/20/2019 Contract Change Order No. 18 Redacted

    8/17

  • 8/20/2019 Contract Change Order No. 18 Redacted

    9/17

    Rinne

    &

    Peterson

    ST R U

    CT UR

    AL E N G IN

    EE

    R S

    C RMEL FOREST THE TER

    Sheet No R I

    75 -  

    By MSB

    Dote 11/12/15

    Keyways not included

    in

    PCO

    ~ 2

    \6\1

    f l ~ C V K e . P t l . / > < ; \ L ; . : ;

    OC(.vRS ? . A ~ P t

    II

    II

    0 ~ \ \ l t : I N ~

    il

    - - - -

    f k \ 1 1 ~

    r

    ·-

     

    l'h"OX ~ ~ r

    -

    ,_

    I

    5@

    12"

    o.c.

    VERT

    EA FACE

    X

    ~

    2

    '

    I

    5

    @ 16" o.c.

    HORIZ EA FACE

    - 0

    I

    #5@

    12 O.C. EA WAY

    TOP & BOT

    STD HOOK AT

    TOP

    & BOT

    TRANSVERSE

    w

    w

    ) .

    F l t l . t . ~ .

    h

    0 ~ $

    1

    D.4.

    BARS

    -

     

    :=

    .

    - :

  • 8/20/2019 Contract Change Order No. 18 Redacted

    10/17

    BULLETIN

    NO.:

    PROJECT NAME:

    PROJECT

    No.:

    ISSUED

    TO

    ' CODY ANDERSON W SNEY

    14.1

    P

    er

    location

    cl

    a

    rificat

    i

    on

    Carmel Forest

    Theater

    14017

    Otto Construction

    2150 Garden

    Road,

    Su

    i

    te

    A 1

    Monterey,

    CA

    93940

    ARCHITE CTS

    ISSUE DATE:

    RFI No.:

    ISSUED BY·

    CC

    ULLETIN

    11

    /4/

    15

    Jilian

    Cadouri

    Andrew Vanderford

    All

    materials

    and work

    hereinafter

    shall

    conform to

    all the

    requiroments

    of he project

    Drawings and Specifications.

    except

    as otherwise

    described.

    Choose

    one

    of

    h

    e

    ollowing)

    D

    D

    DESCRIPTION 

    Item

    No. 01

    Exec ute promptly the nstr

    uct

    ions given herein, which in

    terpret

    the

    Contract

    Documents or order minor c

    hanges

    in t

    he

    Work without

    change

    in

    Contrac

    t Sum

    or

    Contract Time.

    If

    you

    cons

    ider that a change n Contract Su mor Contract

    Ti

    me

    is required, submit an itemized proposal to he Architec t immediately and before proceeding

    with

    this Work. If your

    proposal is found tobe sa

    tisfactory

    and in proper order.

    th

    is

    Bulletin

    will be

    superseded

    by aChange Order.

    II.

    Changes

    described

    horein are being

    considered

    for

    incorporation

    in

    to

    h

    eWork .

    Submit an

    it

    emized quotat

    i

    on, in

    format

    required by

    the Contra

    ct Documents.

    indicating

    your proposed

    changes

    to the Contract Sum or Contract Time.

    Do no

    t

    proceed wi

    th

    th

    echanges described herein

    unt

    i

    further

    written instruct ions are iss

    ue

    d

    by

    the Architect.

    Ill. In order

    to

    expedite

    the Work and avoidor minimize de

    lays

    in the Work wh ich may affect

    Cont

    ract Sum or Contract

    Time, t

    he

    Contract Documents

    are

    hereby

    amended

    as

    described below . Poceed with this

    work

    promptly and subm it

    final

    costs

    fo

    r

    Work

    involved and change in

    Contract Time

    (if

    any), for

    incl

    usion in

    asubsequent

    Change Order.

    See attached markup

    for

    approximate pier locations

    a

    lon

    g

    dr

    i

    veway. On

    east edge

    of

    driveway,

    first

    pier

    to

    occur where elevation

    of

    driveway

    surface

    is above surround

    i

    ng grade, as shown. Piers

    to

    continue

    at

    6'

    -0

     

    o.c.

    Where driveway

    elevation

    is lower than or equal to surrounding grade, provide 6 curb only a

    nd

    regrade

    away from

    driveway as

    necessary.

    Delete

    piers

    from scope as

    shown in

    red.

    On west

    e

    dge, piers

    to occur

    at 6'-0 o.c. starting

    at

    base of driveway

    ,

    including where sandstone occurs.

  • 8/20/2019 Contract Change Order No. 18 Redacted

    11/17

    * 1=5

    @

    12 O .C. H ORIZ.

    _

    OW LS

    W

    ~ O O K @ T O P I £

    3 '-6   LAP . . 0 PIER

    * 1:3 S PIRA-L AT

    3  

    PITCH

    '12 ..,..OP It

    BO

    T :0:---1

    S ~ E

    V ERT. BARS

    1 12 C L R

    S TA IRS / S .O.G .

    OR EX

     : .

    GRA-DE

    q .

    4

    · 4

    . 4

  • 8/20/2019 Contract Change Order No. 18 Redacted

    12/17

  • 8/20/2019 Contract Change Order No. 18 Redacted

    13/17

    CODY

    NDERSON W SNEY ARCHITE CTS

    U   ETIN

    BULLETIN

    NO.

     

    14Dr

    iveway Revisions

    PROJECT NAME: Carmel

    Forest

    Theater

    ISSUE DATE:

    9/16/

    15

    RFI

    No.:

    PROJECT No.:

    ISSUED

    TO

    14017

    Otto Construction

    2150 Garden Road, Suite

    A-1

    Monterey, CA

    93940

    ISSUED BY. Jilian

    Cadour

    i

    CC Andrew Vanderford

    All mate

    rials

    and

    work

    hereinafter shall

    conform

    t all the

    requirements

    of he project Drawings and Specifications, except

    as

    otherwise described.

    Choose

    one

    of he following}

    D

    DESCRIPTION

     

    Item No.

    01

    I

    Execute

    promptly t

    he

    instructions given

    he

    r

    ein,

    which

    in

    terpret the Contract

    Documents

    or order minor changes

    in

    the

    Work

    without change in Contract Sum or Contract Time . If you

    consider

    that a

    change

    in Contract

    Sum

    or ContractTime

    is required 

    submit

    an itemized proposal to the

    Architect

    immediately and before proceeding

    with

    this Wor

    k

    If your

    proposal is found to

    be

    sa t

    isfac

    tory and in

    pr

    oper order, this Bulletin will

    be superseded by

    aChange

    Order.

    II. Changes described

    herein

    are

    being considered for incorpor

    ation

    i

    nto

    the Work

    .

    Submit

    an

    i

    te

    mized

    qu

    otation, in

    format requir

    ed by

    the

    Contrac

    t Docum

    en

    ts, i

    nd

    icating your proposed

    changes to

    t

    he Contrac

    t

    Sum

    or Contract

    Time

    .

    Do not proceed

    wi

    th t

    he

    changes

    described

    here in

    un

    ti further writt

    en

    inst

    ru

    cti

    ons are

    issued by

    th

    e

    Archit

    ect.

    Ill.

    In

    order toexpedi

    te th

    eWork

    and

    avoid or min imize

    de

    l

    ays

    in

    th

    eWork which m

    ay

    affect Contract

    Sum

    or

    Contract

    Time,

    the

    Contract Documents are

    hereby

    amended

    as

    described below . Proceed with th is

    work

    promptly and submit

    final costs for Work involved and change in

    Contrac

    t Time

    (if

    any), for inclusion in a subsequent Change

    Ord

    e

    r

    Driveway

    and

    Stai

    r

    Layout

    See

    attached

    CA-30.1 for

    r

    evised driveway

    and

    stai

    r

    layout.

    S

    ee attached

    C1.1

    or

    r

    evised

    wall

    he

    ights

    and

    stair eleva

    t

    ions. Reduced wall heights allow

    a

    reduction

    in

    pier foot

    i

    ng

    d

    epth and rebar

    size. See

    attached

    CA-30

     2

    for

    revised detaii4/A6.7.

    Stone

    Wall

    Per

    attached

    CA-30, omit sec

    t

    ion

    of stone wall at top of

    dr

    iveway.

    Omi

    t

    ballar

    d light

    at this

    l

    ocation.

    Grad

    in

    g

    adjacen

    t

    to dr

    iveway

    See

    C1 1

    for

    revised

    grading adjacent

    to

    driveway

    to

    soften retaining wall

    .

    Omit

    plante r

    wall (delete detail

    4/A6.6)

    .

    REVIEWED

  • 8/20/2019 Contract Change Order No. 18 Redacted

    14/17

    I

    L o ~ . ~

    Cody nderson Wasney rch i tec

    t s,

    Inc

    455 L a m b e r t

    Ave

    n u e • P a I o A I t o, CA 94306

    6 5 o . 3 2 a . 1 a 1 a ·

    Fax

    3 2 a . 1 a a a

    C

    opy

    righ

    C

    2012 by CODY ANDERSON WASNEY ARCHI

    TECT

    S. INC.

    J

    FOREST

    THE TER

    Pr ojcici Naiiie · · · · ·

    14017

    PicitccfNu oo r

    0

    ~ i . f c r o n

    s

    nee

    £ : ~ r . - 1 1

    CA 30.0

    iiie · · ·

    . -·-·· •. ... - - - Shoct

    NUrrib r

  • 8/20/2019 Contract Change Order No. 18 Redacted

    15/17

    ·

    iJI•Y

    ·  ..

    l

    :

    o

    : > y \:_.

    ~

  • 8/20/2019 Contract Change Order No. 18 Redacted

    16/17

    STONE

    VE JEER,

    SEE

    3

    /

    DR

    IVEWAY/AC

    PA'v1 '

    l

    i:t5 12 

    O.C. HOR

    IZ .

    i:t3 SP.

    RAL

    A : 3   P IT

    CH

    W   1

    11

    2 TURNS

    TOP It

    1 11

    2

    CL R

    STA IRS / S.O.G.

    OR

    EXT

    .

    GRA?E

    q

  • 8/20/2019 Contract Change Order No. 18 Redacted

    17/17

     

     

    t

     

    1

     

    t

    t

    l

     

    ·

     

    .

    .

     

    I

    e

     

    I

    :

    :

    1

     

    ;