Contract Administration

21
Contract Administration Stacy Sassman Purchasing Agent Iowa State University Cory Harms Associate Director of Purchasing Iowa State University

description

Contract Administration. Stacy Sassman Purchasing Agent Iowa State University Cory Harms Associate Director of Purchasing Iowa State University. Contract Administration Session Outline. What is a Contract Administration Plan Why have a Contract Administration Plan - PowerPoint PPT Presentation

Transcript of Contract Administration

Page 1: Contract  Administration

Contract Administration

Stacy SassmanPurchasing AgentIowa State University

Cory HarmsAssociate Director of Purchasing Iowa State University

Page 2: Contract  Administration

Contract AdministrationSession Outline

• What is a Contract Administration Plan• Why have a Contract Administration Plan• Writing A Contract Administration Plan

– Purpose and Scope– Contacts and Responsibilities– Meetings– Vendor Requirements– Monitoring Performance– Dispute Resolution– Changes to the Contract– Closing the Contract

• Helpful Tips for a CAP• Common Issues• Questions

Page 3: Contract  Administration

Contract Administration• What is a Contract Administration Plan (CAP)– A loose set of guidelines– Flexible – allow the plan to fit the contract– Plan should be included in the contract– Plan should be agreed upon by Vendor– Plan should increase communication

• What is a Performance Assessment Plan (PAP)– Monitor the performance of the contract– Created to administer the CAP

Page 4: Contract  Administration

Contract Administration• When do you need a plan?– When the nature of the contract creates a need for

oversight• High Value Contracts• High Visibility Contracts• High Risk Potential in Contract• Customer Sensitive Contracts• Complex Contracts

– Term of the contract creates a need for review– Past experience creates need

Page 5: Contract  Administration

What is the Value of a Contract Administration Plan?

• Encourages open communication– Set a timeline for communication– Provide feedback – Maintain the relationship– Head off issues before they arise

• Provides a clear understanding of roles and responsibilities

• Identifies and minimizes the potential risks and problems

Page 6: Contract  Administration

Writing a CAPPurpose and Scope

• Describe the purpose of the contract administration plan and the contract (Requirements)

• State what you want from the contract:– Product/service delivered on-time– Quality product/service– Receive correct quantity– Accurate billing

Page 7: Contract  Administration

Writing a CAPContract Contacts and Responsibilities

• Describe the roles and the responsibilities of each person involved.– Purchasing Agent/contract manager– Department contact (for operational issues only)– Vendor contact

Page 8: Contract  Administration

Writing a CAPMeetings

• Kick-off meeting– Introduce contacts– Discuss scope of work in detail– Discuss contractual obligations of all parties

(Requirements)– Establish communication protocols (email, phone, etc)

• Additional meetings – quarterly, milestones, annually, etc.

Page 9: Contract  Administration

Writing a CAPVendor Requirements

• Requirements may be needed:– Before work can begin– After work has started/during the life of the contract– Upon Completion of the Contract– Months or years after the Work is completed

Page 10: Contract  Administration

Requirements• Before the work can begin– Certificates of insurance– Employee background checks– Surety/Payment bonds– Parking permits– Access cards or building keys– Equipment checks– Contractor registration number– Certifications/Licenses

Page 11: Contract  Administration

Requirements

• After the work has started– Milestone/progress meetings– Tests– Quarterly/Annual reports– Acceptance tests– Price audits– Payments – Surveys

Page 12: Contract  Administration

Requirements• Completion of the Work– Testing/Tests– Final reports– Payments – Completed work (design, drawings, equipment, rights)– University Data– Escrow Rights

Page 13: Contract  Administration

Requirements• Post Completion

–Completed Operations Endorsement–Protection of Records (University or Student)–Audit of Vendor Records

Page 14: Contract  Administration

Monitoring Performance • Period of performance/delivery dates• Inspection and acceptance• Milestones• Potential issues:– Wrong or unsatisfactory product delivered– Poor performance– Delays– Subcontractors– Property damage

Page 15: Contract  Administration

Writing a CAP Dispute Resolution

• Describe how disputes will be resolved• Who to contact• Actions to be taken if dispute is not resolved• Penalty clauses• Corrected work by another party

Page 16: Contract  Administration

Writing a CAPContract Changes

• Changes to:– Contract period of performance– Dollar amount of contract– Scope of work– Terms and conditions changes– Assignment

Page 17: Contract  Administration

Writing a CAPClosing the Contract

• Final deliverables• Property• Payments & invoices• Evaluation

Page 18: Contract  Administration

Helpful Tips

• Create a template for meeting notes• Track meetings and issues on a spreadsheet• Use the task function in Outlook• Documentation• Sample Plan

Page 19: Contract  Administration

Common Issues

• Poor communication• Level of involvement• Vendor not a good fit• Expectations of Dept. and Vendor not met

Page 20: Contract  Administration

Summary• What is a Contract Administration Plan?• Why have a Contract Administration Plan?• Writing A Contract Administration Plan

Purpose and Scope Contacts and Responsibilities Meetings Vendor Requirements Monitoring Performance Dispute Resolution Changes to the Contract Closing the Contract

• Helpful Tips for a CAP• Common Issues

Page 21: Contract  Administration

Questions