Contents Page Number - Raja Ramanna Centre for … Supply of one number of vacuum cleaner of EUREKA...
Transcript of Contents Page Number - Raja Ramanna Centre for … Supply of one number of vacuum cleaner of EUREKA...
RRCAT/IMA/RKS/SD_HPIA/SPECS Date: 26-Sep-2013
1 of 11
Technical Specification for fabrication, supply and installation of
Carbon Steel Partition with Sliding Door (CSP)
# Contents Page Number
1. Introduction 2
2. Scope of Work 2
3. Pre-Qualification Criteria for Bidders 3
4. Mandatory Information / Instructions 3
5. Pre-Bid Meeting 5
6. Applicable Drawings 5
7. Applicable Standards 5
8. Lay Out of CSP 5
9. Material Requirements 5
10. Testing 5
11. Fabrication, Assembly & Installation Requirements 6
12. Electrically Operated Sliding Door 6
13. Demountable Plate 7
14. Warranty 8
15. Pre-Installation Requirements 8
16. Delivery Schedule 8
17. Acceptance 8
18. Quality Assurance Plan (QAP) 9
19. Check List 11
RRCAT/IMA/RKS/SD_HPIA/SPECS Date: 26-Sep-2013
2 of 11
1. INTRODUCTION
This specification lists the requirements for fabrication, supply and
installation of a Carbon Steel Partition with Sliding Door (CSP) at
IMA Building of RRCAT Indore (web site www.rrcat.gov.in).
2. SCOPE OF WORK
Following is the scope of work:
2.1 Preparation of manufacturing drawing,
2.2 Procurement & testing of materials, standard parts/components,
fasteners and other requisite components as per drawing and
specification,
2.3 Fabrication, machining, trial assembly and inspection of the
components at supplier’s works,
2.4 Safe delivery and installation at purchaser’s site (IMA Building,
RRCAT Indore) including sliding door and its integration with
electrical controller unit, fasteners, anchors, clamping devices and
handling at site.
2.5 Demonstration of sliding door functionality.
2.6 Repairing of CSP, if any pitfall is observed after installation and
demonstration of functionality.
2.7 Installation of CSP shall be done with proper precautions to prevent
spread of dust,
2.8 Supply and placement of two nos. “clean-air” Polypropylene dust
curtain/barrier at adjacent locations having approximate opening
size of 4.0 m height and 5.0 m width duly sealed by wide duct tape
on walls,
2.9 All civil works at site shall be done with proper tooling, precaution
and arrangement of all transports, tools & equipment, material
handling systems and man-power at the purchaser’s site,
2.10 Supply of one number of vacuum cleaner of EUREKA FORBES Model
No. ZW 100 SS or equivalent. The typical technical parameters are:
(1) Required power supply to operate the vacuum cleaner –
230V/50Hz (2) Air flow (min.) – 110 ltr/sec, (3) Suction power (min.) –
25 kPa, (4) Tank volume (min.) – 100 ltrs.,
2.11 Cleaning of complete area by vacuum cleaner (procured and supplied
RRCAT/IMA/RKS/SD_HPIA/SPECS Date: 26-Sep-2013
3 of 11
by Vendor as mentioned in point 2.10) after final installation (total
area about 200 square meters to be cleaned including adjoining
walls). Wet mopping shall be done every day during on-going site
work and twice after the work is finished,
2.12 All arrangements for completing the work with proper provisions of
safety for the equipment and personnel, including arrangements of
“personnel protective equipment- PPE” are in the scope of the
supplier.
3. PRE-QUALIFICATION CRITERIA FOR BIDDERS
3.1 Bidder shall have at least 3 years’ experience of fabrication jobs
involving similar material and sizes.
3.2 Bidder shall have in house infrastructure/facilities for handling and
machining of the components/parts mentioned in the “APPLICABLE
DRAWINGS”,
3.3 Bidder shall have management system to be considered for
prequalification. Management systems supported by Third Party
Accreditation Certificates, including the scope of the certification like
ISO 9001 or equivalent. If the Bidder’s management system is not
Third Party Certified, then its internal quality control procedure
should have at least following features:
(a) Information regarding resources (manpower, infrastructure and
equipments),
(b) Quality control procedure for procurement of materials and
components, manufacturing process and acceptance tests,
(c) Procedure for control of conforming and non-conforming
products,
(d) In-house provision for ensuring the quality control procedures.
3.4 Bidder shall have completed at least one job of value not less than
70% of the quoted price or at least two jobs of value not less than
50% of the quoted price in last three years (furnish details in
concurrence with point no. 4.3 in your bid)
4. MANDATORY INFORMATION / INSTRUCTIONS
Bidder shall submit the following information along with the
bid:
4.1 A copy of quality management certificate as mentioned in “PRE-
RRCAT/IMA/RKS/SD_HPIA/SPECS Date: 26-Sep-2013
4 of 11
QUALIFICATION CRITERIA”,
4.2 Organizational Chart
4.3 Past 3 years’ experience for the development of similar kind of jobs
with the following details:
(a) Project name, location and description,
(b) Contract value,
(c) Start date and date for practical completion.
(d) Photos/Drawings of work done.
4.4 Complete contact details (name, phone, email, web address, fax,
postal address etc.),
4.5 Make of steel plate to be used for construction of components,
4.6 What is the make and model of vacuum cleaner to be supplied,
4.7 List of in-house infrastructure/facilities pertaining to job like size of
workshop, overhead crane capacity, forklift capacity, welding
facilities, drafting/detailing and modeling computer softwares,
4.8 Name and accreditation of agency which will be employed for
mechanical, chemical and ultrasonic testing of plates,
4.9 Installation procedure for anchor fasteners and name of agency to be
employed for this purpose,
4.10 Assembly procedure (well defined procedure for assembly and fixture
development is required),
4.11 Name of manufacturer of the sliding door along with its technical
data sheet and catalogue for the offered product. Also enclose the list
of supply made by this company for similar type of door (door weight
more about a ton). Provide the photographs of installed doors,
4.12 Properly filled “CHECK LIST” duly stamped and signed by authorized
signatory,
4.13 Delivery period and installation schedule,
Bidder should note the following instructions before filling bid:
4.14 Bid may be rejected in the event of:
(a) Not getting a timely response of Purchaser’s queries with
complete information
RRCAT/IMA/RKS/SD_HPIA/SPECS Date: 26-Sep-2013
5 of 11
(b) An ambiguous response/information is produced for Purchaser’s
queries
4.15 Evaluation of the bid shall be done on the lowest total cost basis and
single purchase order will be placed to the lowest total and
technically suitable offer for maintaining compatibility of
components/sub-assemblies.
5. PRE-BID MEETING
Pre-bid meeting and site visit will be arranged for the interested
bidders for technical clarification regarding the scope of work.
6. APPLICABLE DRAWINGS
6.1. Drg. No.: (RRCAT/EAP/IMA/032/R0, Sheet 1 of 6 to 6 of 6).
6.2. Drg. No.: (RRCAT/EAP/IMA/033/R0, Sheet 1 of 1).
7. APPLICABLE STANDARDS
Following standards shall govern various aspects of the work:
7.1. IS: 2062 - Specification for weldable structural steel.
7.2. ASTM A435M, Standard Specification for Ultrasonic Straight-Beam
Examination of Steel Plates
7.3. ASTM E 1417M Standard Practice for Liquid Penetrant Testing
8. LAYOUT OF CSP
The assembled section of CSP has four sub-assemblies namely:
• Electrically operated sliding door,
• Demountable plate,
• Fixed plate,
• Ports for AHU duct connection.
9. MATERIAL REQUIREMENTS
The material shall be procured from a reputed manufacture like
SAIL/TATA or equivalent only. The entire material shall be free of
scales, blisters, laminations, cracked edges and defects of any sorts.
10. TESTING
10.1. Ultrasonic testing (UT) of the plates has to be performed as per the
requirements of ASTM A 435M before starting the fabrication. It has
to be carried out by certified personnel. Procedure of UT has to be
RRCAT/IMA/RKS/SD_HPIA/SPECS Date: 26-Sep-2013
6 of 11
submitted to RRCAT and got approved prior to the test.
10.2. Testing of mechanical and chemical properties according to IS 2062
or equivalent from National Accreditation Board for Testing and
Calibration Laboratories (NABL). These tests can be waived if mill test
certificate (MTC) is available with proper traceability.
10.3. Liquid Penetrant Examination shall be done by contractor after each
pass of welding.
11. FABRICATION, ASSEMBLY AND INSTALLATION REQUIREMENTS
11.1. Shielded Metal Arc Welding (SMAW) procedure with welding filler
E-6013 or equivalent shall be used for welding.
11.2. Anchor fastening to be done by using suitable steel HILTI anchor
fasteners (HDA-T-30 M16 x 190/60) and its recommended
procedures. Ferro scanning shall be done before anchoring to verify
location of steel reinforcement in concrete and avoiding rebar hits.
11.3. All steel structures shall be applied primer and suitable painting to
prevent corrosion (3 layers of each)
11.4. Any fixture or transport feature required for safe assembly and
installation has to be properly designed and fabricated by the
supplier.
12. ELECTRICALLY OPERATED SLIDING DOOR
12.1 Single steel plate without any joint has to be used for the door.
12.2 Sliding mechanism along with electrical motor shall be standard
product of reputed make.
12.3 The work of sliding door shall be done by an agency which has
constructed the door of similar kind in weight and dimension.
12.4 Design of sliding door including components, standard cataloged
design shall be vetted by RRCAT and Vendor shall incorporate the
changes suggested by RRCAT. Prior approval from RRCAT is required
before procurement of the components including sliding mechanism
along with motor.
12.5 The door movement (opening/closing) should be jerk free with end
stopper.
12.6 The sliding mechanism should be selected such that a single person
must be able to open or close the door manually in case of power
RRCAT/IMA/RKS/SD_HPIA/SPECS Date: 26-Sep-2013
7 of 11
failure.
12.7 Other details are as mentioned in following table:
# Item Value
12.7.1 Door Dimension Kindly refer the drawing mentioned in
“APPLICABLE DRAWINGS”
12.7.2 Door type Electrically operated sliding door
made of single steel plate with
provision of manual operation in case
of power failure
12.7.3 Door Material Weldable structural steel as per IS-
2062
12.7.4 Opening and
closing speed
0-30 mm/sec (settable)
12.7.5 Emergency
manual opening
There should be provision of manual
opening of the door in case of power
failure
12.7.6 Power supply 230V (±10%), 50 Hz
12.7.7 Door activation Large area push buttons with
lettering “OPEN/CLOSE” on the
button shall be used as activation
device for door on both sides
12.7.8 Safety system A reliable sensor like proximity
switches or light curtain or else shall
be fitted on the door to detect the
presence of personnel or material
movement and stop the door
operation.
13. DEMOUNTABLE PLATE
A rigid and stable framed structure, detachable type as shown in the
drawing, shall be fabricated and supplied for the portability of the
demountable plate. Nylon or PU wheels shall be properly selected to
bear the load of partition. Framed structure shall also be properly
RRCAT/IMA/RKS/SD_HPIA/SPECS Date: 26-Sep-2013
8 of 11
selected to bear all kind of loads and stresses.
14. WARRANTY
All offered (bought out items and customized) products shall carry
one year onsite warranty for repair, maintenance and replacement
against any manufacturing defect(s).
15. PRE-INSTALLATION REQUIREMENTS
15.1 All pre-requisites for installation shall be informed in writing to the
purchaser well in advance.
15.2 Type and number of power points required for the operation of door,
mechanism, etc. shall be discussed and finalized at least 2 months
before coming for installation.
15.3 Safety of all personnel & equipments is the sole responsibility of the
bidder. RRCAT and its staff member have no role to play in this
respect.
15.4 Supplier shall provide all the necessary PPEs (Personnel Protective
Equipments) and safe appliances to its working personnel.
15.5 Extension boards are to be used for using power at long distance
from power points. Two core double insulated cables in single length
and proper sockets are to be used for portable equipments.
16. DELIVERY SCHEDULE
The items shall be delivered and installed preferably within 4 months
after placement of purchase order and completion of commercial
formalities with the Purchaser. The supplier shall explicitly mention
this time in its offer.
17. ACCEPTANCE
The acceptance of CSP will be based on:
17.1. Compliance with all the points of this specification and applicable
drawings.
17.2. Compliance with Quality Assurance Plan (QAP).
17.3. Successful installation and commissioning of CSP at purchaser’s site.
RRCAT/IMA/RKS/SD_HPIA/SPECS Date: 26-Sep-2013
9 of 11
18. QUALITY ASSURANCE PLAN
LEGENDS
P : Performed by
W : Witnessed by
V : Verified by
1 : CUSTOMER
2 : VENDOR
3 : SUB-VENDOR
RAJA RAMANNE CENTRE FOR ADVANCED TECHNOLOGY (RRCAT), INDORE (M.P.)
QUALITY ASSURANCE PLAN (QAP)
# Items &
Characteristics
Type of Check Reference Document &
Acceptance Norm
Record of
Inspection
Agency Remarks
P W V
1. Manufacturing
Drawing
Dimension &
Tolerances
“APPLICABLE DRAWINGS” Approved
manufacturing
drawing
2 - 1
2. Vendor
establishment for
steel plate &
bought out items
Reputation &
prior experience
of supplier
Specification:
RRCAT/IMA/RKS/SD_HPIA/SPECS
Approval letter
for suppliers
2 - 1
3. Raw Material
3.1. Plates:
a) Chemical
Composition
b) Mechanical
a) Chemical Test
b) Mechanical
Test
For a) & b) – IS2062
for c) – ASTM A435M
a) Chemical
test report
b) M.T. report
The test
samples
has to be
cut in
presence
RRCAT/IMA/RKS/SD_HPIA/SPECS Date: 26-Sep-2013
10 of 11
Properties
c) Ultrasonic Test
c) UT c) UT
procedure &
report
of RRCAT
Engineer
4. Welds LPE of each pass ASTM E1417 LPE Report 2 1 1
5. Dimensions of
components
Dimensional
Inspection
Approved manufacturing drawing Dimensional
Inspection
report
2 1 1
6. Trial assembly at
vendor’s premises
Inspection for
assembly
“APPLICABLE DRAWINGS” Trial assembly
report
2 1 1
7. Painting Quality of paint Specification:
RRCAT/IMA/RKS/SD_HPIA
Painting
inspection
report
2 - 1
8. All the items after
delivery
Check for any
damage during
transport
Specification:
RRCAT/IMA/RKS/SD_HPIA/SPECS
& Manufacturing Drawing
-----
2 - 1
9. Sub-assemblies
during assembly
Correctness of
assembly
“APPLICABLE DRAWINGS” -----
2 1 1
10. Final assembly
after installation
Correctness of
assembly & door
movement
“APPLICABLE DRAWINGS” Installation
report
2 1 1
RRCAT/IMA/RKS/SD_HPIA/SPECS Date: 26-Sep-2013
11 of 11
19. CHECK LIST FOR BIDDERS
Bidder should furnish the check list given below duly signed and stamped by the bidder/authorized signatory.
Description Bidder’s response Remarks, if any
1. Do you agree to complete full scope of work as mentioned in Section-2? YES/NO
2. Have you attached all the documents mentioned in Section-4? YES/NO
3. Have you read and understood the “APPLICABLE DRAWINGS”? YES/NO
4. Will you comply with the “APPLICABLE STANDARDS”? YES/NO
5. Have you specified the make and model of vacuum cleaner? YES/NO
6. Have you mentioned the make of steel plates? YES/NO
7. Have you understood the testing requirements? YES/NO
8. Do you agree with “WARRANTY” clause? YES/NO
9. Have you written the name of agency to be involved for mechanical,
chemical and ultrasonic testing of plates?
YES/NO
10. Have you provided the information regarding the sliding door as asked in
Section-4.10?
YES/NO
11. Do you agree for Ferro-scanning before anchoring? YES/NO