OverviewPSA TemplateTimelineClosing Remarks
Execution of PSA between NPC and DUs
Relationship should be made legal and binding Enhance system reliability Firm up subsidy allocation for OPEX and CAPEX
DOE Remarks“professionalize” the electric industryOn-going PhP 0.30/kwh reduction and 3% prompt
payment discount should have a legal basisPSALM-NPC separation of books: must immediately
implement transfer of booksSPUG as residual of NPCSPUG is being subsidized by the mainland grid
revenues and UC-MECOA is already looking at SPUG operations
especially on the rate reduction and PPD since these are taxpayers money
SPUG Existing Areas
105 plants in 86 areas nationwide77 island grids and 9 isolated grids 44 DUs covered
23 in Luzon 10 in Visayas 11 in Mindanao
13 DUs with signed PSA with NPC that will expire 2012-2013
9 DUs with signed PSA with NPP
Status of PSA with DUs in Luzon
Areas - 41Number of DUs – 23 Areas per DU:DUs with PSA with NPC in # Areas– 9 in 11 areasDUs with PSA with NPPs in # Areas- 7 in 7 areas
Status of PSA with DUs in Visayas
Areas - 24Number of DUs – 10Areas per DU: DUs with PSA with NPC in # Areas– 1 in 1 areaDUs with PSA with NPPs in # Areas- 1 in 1 area
Status of PSA with DUs in Mindanao
Areas - 21Number of DUs – 11 Areas per DU: DUs with PSA with NPC in # Areas– 3 in 5 areasDUs with PSA with NPPs in # Areas- 1 in 1 area
Power Supply Agreement
The Parties to the PSA are NPC (NPC-SPUG) and DU The Parties to the PSA are NPC (NPC-SPUG) and DU (Off-taker)(Off-taker)
ScopeScope» Contract Demand and Energy Contract Demand and Energy » Full service (base load, peaking)Full service (base load, peaking)» TariffTariff» PenaltiesPenalties» AssignabilityAssignability
TIMELINEDistribution of Draft PSA to DUs 23 Jan 2009Consultation
Luzon 27 Jan 2009Visayas and Mindanao 29 Jan 2009
Presentation to DU’s Board of Directorsnlt 07 Feb 2009Submission of Revisions to NPC nlt 13 Feb 2009
SPUG Fax (02) 9213319 or 9213230 or em at [email protected] [email protected]
TIMELINENP Board Meeting week of 16 Feb 2009
PSA Template UC-ME application to ERC Prompt Payment Discount
Confirmation of the DUs Board of Directors nlt 28 Feb 2009
Submission of signed PSA of ECs to SPUG 28 Feb 2009
Signing of PSA by NPC and DUS week of 02 March 2009(venue – NPC Central Office)