Consultant Q & A

March 6, 2012Consultant Selection Process

ACEC/WisDOT Transportation Improvement Conference

Page 2: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

“If I can put everyone to sleep within the first five minutes, the rest of my presentation should go pretty well.”

Page 3: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

Wisconsin Department of Transportation’s Consultant Selection

ProcessNE Region SE Region SW Region NW Region NC Region

Solicitations Solicitations Solicitations Solicitations Solicitations

NOI’s NOI’s NOI’s NOI’s NOI’s

Region Review Region Review Region Review Region Review Region Review

Selection Selection Selection Selection Selection

Posting Posting Posting Posting Posting

ACEC/WisDOT Transportation Improvement Conference

Page 4: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

Inquiring Minds that Want to Know:

How WisDOT makes

Consultant Selections

Page 5: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

Blind-folded Dart Toss NOI Paper Toss

Page 6: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

The 1st Step to Selection is the NOI

NE Region SE Region SW Region NW Region NC Region

Solicitations Solicitations Solicitations Solicitations Solicitations

NOI’s NOI’s NOI’s NOI’s NOI’s

Region Review Region Review Region Review Region Review Region Review

Selection Selection Selection Selection Selection

Posting Posting Posting Posting Posting

Page 7: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

What does WisDOT want to see in a good NOI?

• Addresses all points in the Consultant Requirements Section

• Good brief descriptions of example projects

• Similar attributes to project being solicited

• Good availability for listed staff

• A clear explanation of the staff’s availability

Page 8: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

What does WisDOT want to see in a good NOI?

• Relevant comparable experience

• Verification that project narrative is understood

• Information needs to be accurate and representative

• Honest assessments of staff’s work quality

Page 9: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

The 2nd Step to Selection is the Region Review

NE Region SE Region SW Region NW Region NC Region

Solicitations Solicitations Solicitations Solicitations Solicitations

NOI’s NOI’s NOI’s NOI’s NOI’s

Region Review Region Review Region Review Region Review Region Review

Selection Selection Selection Selection Selection

Posting Posting Posting Posting Posting

Page 10: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

Areas for Improvement on NOI’s?

• Read the full project scope

• Insufficient information to determine qualifications

• Unrelated project experiences noted

• Poor grammar

Page 11: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

Areas for Improvement on NOI’s?

• Obvious errors resulting from cutting/pasting

• Evaluate past experience for listed staff

• Being accurate about availability of listed staff

• Focus on the key players’ qualifications

Page 12: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

Areas for Improvement on NOI’s?

• Address project specific skill or consultant requirements

• Identifying their specific roles on past projects

• Submissions sometimes need a fact checker

• Follow the furnished format

Page 13: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

How does WisDOT reduce your NOI’s down to the “short list”?

Page 14: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

You are on the shortlist. It’s between you and the firm that is getting the job.

Region Rating Team

Page 15: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

How does WisDOT reduce your NOI’s down to the “short list”?

• Good examples of similar project work for both staff experience and project examples

• Staff availability is reasonable especially for key staff

• Prior experience that the Region had with them

• Past performance of firms/listed staff based on evaluations

Page 16: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

How does WisDOT reduce your NOI’s down to the “short list”?

• Overall relevant experience/capabilities of listed staff

• Specific skill set demonstrated

• Work Type Ratings sheet/previous experience in Region

• Top two or three project specific skill requirements

Page 17: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

The 3rd Step to Selection is making the SELECTION

NE Region SE Region SW Region NW Region NC Region

Solicitations Solicitations Solicitations Solicitations Solicitations

NOI’s NOI’s NOI’s NOI’s NOI’s

Region Review Region Review Region Review Region Review Region Review

Selection Selection Selection Selection Selection

Posting Posting Posting Posting Posting

Page 18: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

What makes a winning selection?

• Project specific NOI

• Identifying project specific needs

• One that demonstrates that they have seen the project

Page 19: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

What makes a winning selection?

• Paints complete picture of your qualifications for the type of work in the solicitation

Page 20: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

What makes a winning selection?

What picture are youtrying to show us?

Page 21: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

What makes a winning selection?

• One that nails every aspect about the project

• Discussed potential issues with the local units of government

• Staffing at the appropriate level based on project complexity

• Good past performance on comparable projects

Page 22: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

What makes a winning selection?

• An accurate and complete NOI without obvious errors

• Demonstrate successful experience working together

• Be upfront & completely honest with any information in the NOI

Page 23: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

Page 24: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

What makes a winning selection?

• Not submitting the same NOI for 5 different projects

• Identifying project specific needs

• Communicating the ability to provide a successful project

Page 25: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

The Final Step is Posting the SELECTION

NE Region SE Region SW Region NW Region NC Region

Solicitations Solicitations Solicitations Solicitations Solicitations

NOI’s NOI’s NOI’s NOI’s NOI’s

Region Review Region Review Region Review Region Review Region Review

Selection Selection Selection Selection Selection

Posting Posting Posting Posting Posting

Page 26: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.

ACEC/WisDOT Transportation Improvement Conference

The Selection is Posted

• Firm chosen is happy

• Firms not shortlisted – look for ways to improve next time

• Feedback Sessions for Interview Projects

Page 27: Consultant Q & A March 6, 2012 Consultant Selection Process ACEC/WisDOT Transportation Improvement Conference.