CONSTRUCTION WASTE [1.5] Submittal Form

4
Contractor must recycle at least 80% of building related construction waste in weight and provide the University a waste report, including associated auditable chain of custody documentation upon request. Measure Project Name CONSTRUCTION WASTE [1.5] Submittal Form Page 1 of 4 Points Available 1 Points Claimed Date Name (print) Signature Project Team Representative Date Name (print) Signature Campus Infrastructure Services Sustainability Representative Signature Name (print) Date Project Team Representative As-Built Sign-off Date Name (print) Signature Campus Infrastructure Services Sustainability Representative 04/02/2015 Revision 1.0 CAMPUS INFRASTRUCTURE & SERVICES Mandatory Requirement By ticking this box the project team confirms the Pre-contract target meets the requirements of the measure and details are provided in this form. Sign-off: Pre-contract Design Stage By ticking this box the project team confirms the waste target meets the requirements of this measure Sign-off: As-built Stage - to be completed at Practical Completion of Project

Transcript of CONSTRUCTION WASTE [1.5] Submittal Form

Contractor must recycle at least 80% of building related construction waste in weight and provide the University a waste report, including associated auditable chain of custody documentation upon request.

Measure

Project Name

CONSTRUCTION WASTE [1.5] Submittal Form

Page 1 of 4

Points Available 1 Points Claimed

Date

Name (print)

Signature

Project Team Representative

Date

Name (print)

Signature

Campus Infrastructure Services Sustainability Representative

Signature

Name (print)

Date

Project Team Representative As-Built Sign-off

Date

Name (print)

Signature

Campus Infrastructure Services Sustainability Representative

04/02/2015 Revision 1.0 CAMPUS INFRASTRUCTURE & SERVICES

Mandatory Requirement

By ticking this box the project team confirms the Pre-contract target meets the requirements of the measure and details are provided in this form.

Sign-off: Pre-contract Design Stage

By ticking this box the project team confirms the waste target meets the requirements of this measure

Sign-off: As-built Stage - to be completed at Practical Completion of Project

04/02/2015 Revision 1.0 CAMPUS INFRASTRUCTURE & SERVICES

Page 2 of 4

Confirm the project construction waste recycling / reuse target (%):

1.1 Pre-Contract Commitment

1.2 Reference Documents

Project the following documents as part of the Pre-Contract sign-off:

Project specific Waste Management Plan which identifies all waste streams to be recycled and reused

Evidence of Waste Audit methdology used by Waste Recycler / Depot

2.0 As-built Stage - Construction Waste

Complete the following checklist:

Were all subcontractors inducted into the Waste Management Plan?

Were all wastes tracked throughout the project?

Was the required 80% recycling target met for non-hazardous wastes?

Were all subcontractors issued with the Waste Management Plan?

Have waste dockets and receipts been appended to this document?

2.1 Waste Recycling / Reuse Figures

Complete the following table for the project figures:

Materials / Waste Generated on Site Destination

Recycling & Reuse

Destination

Recycling & Reuse

Destination

Disposal

Recycling & Disposal Centre

Material Total Weight (Tonnes) On-site Off-site Landfill Site Comments

1.0 Pre-contract Design Stage - Construction Waste

Page 3 of 4

Materials / Waste Generated on Site Destination

Recycling & Reuse

Destination

Recycling & Reuse

Destination

Disposal

Recycling & Disposal Centre

Material Total Weight (Tonnes) On-site Off-site Landfill Site Comments

Totals

Totals (Excl Hazardous & Soil)Total Wastes Recycled (%)

04/02/2015 Revision 1.0 CAMPUS INFRASTRUCTURE & SERVICES

Confirm the project % Construction Wastes that were Recyced / Reused:

Page 4 of 4

2.2 Reference Documents

Final Project specific Waste Management Plan

Waste Disposal reports / statements from Contractors

Please list any other reference documents used in the above assessment (as required)

Provide the following documents as part of the As-built signoff:

04/02/2015 Revision 1.0 CAMPUS INFRASTRUCTURE & SERVICES