CONSTRUCTION WASTE [1.5] Submittal Form
Transcript of CONSTRUCTION WASTE [1.5] Submittal Form
Contractor must recycle at least 80% of building related construction waste in weight and provide the University a waste report, including associated auditable chain of custody documentation upon request.
Measure
Project Name
CONSTRUCTION WASTE [1.5] Submittal Form
Page 1 of 4
Points Available 1 Points Claimed
Date
Name (print)
Signature
Project Team Representative
Date
Name (print)
Signature
Campus Infrastructure Services Sustainability Representative
Signature
Name (print)
Date
Project Team Representative As-Built Sign-off
Date
Name (print)
Signature
Campus Infrastructure Services Sustainability Representative
04/02/2015 Revision 1.0 CAMPUS INFRASTRUCTURE & SERVICES
Mandatory Requirement
By ticking this box the project team confirms the Pre-contract target meets the requirements of the measure and details are provided in this form.
Sign-off: Pre-contract Design Stage
By ticking this box the project team confirms the waste target meets the requirements of this measure
Sign-off: As-built Stage - to be completed at Practical Completion of Project
04/02/2015 Revision 1.0 CAMPUS INFRASTRUCTURE & SERVICES
Page 2 of 4
Confirm the project construction waste recycling / reuse target (%):
1.1 Pre-Contract Commitment
1.2 Reference Documents
Project the following documents as part of the Pre-Contract sign-off:
Project specific Waste Management Plan which identifies all waste streams to be recycled and reused
Evidence of Waste Audit methdology used by Waste Recycler / Depot
2.0 As-built Stage - Construction Waste
Complete the following checklist:
Were all subcontractors inducted into the Waste Management Plan?
Were all wastes tracked throughout the project?
Was the required 80% recycling target met for non-hazardous wastes?
Were all subcontractors issued with the Waste Management Plan?
Have waste dockets and receipts been appended to this document?
2.1 Waste Recycling / Reuse Figures
Complete the following table for the project figures:
Materials / Waste Generated on Site Destination
Recycling & Reuse
Destination
Recycling & Reuse
Destination
Disposal
Recycling & Disposal Centre
Material Total Weight (Tonnes) On-site Off-site Landfill Site Comments
1.0 Pre-contract Design Stage - Construction Waste
Page 3 of 4
Materials / Waste Generated on Site Destination
Recycling & Reuse
Destination
Recycling & Reuse
Destination
Disposal
Recycling & Disposal Centre
Material Total Weight (Tonnes) On-site Off-site Landfill Site Comments
Totals
Totals (Excl Hazardous & Soil)Total Wastes Recycled (%)
04/02/2015 Revision 1.0 CAMPUS INFRASTRUCTURE & SERVICES
Confirm the project % Construction Wastes that were Recyced / Reused:
Page 4 of 4
2.2 Reference Documents
Final Project specific Waste Management Plan
Waste Disposal reports / statements from Contractors
Please list any other reference documents used in the above assessment (as required)
Provide the following documents as part of the As-built signoff:
04/02/2015 Revision 1.0 CAMPUS INFRASTRUCTURE & SERVICES