Construction Update and Lessons Learned Stan Thomason Southern Nuclear Operating Company

Transcript of Construction Updated and Lessons Learned. · Construction Status •Forecast for operation for...

Page 1: Construction Updated and Lessons Learned. · Construction Status •Forecast for operation for Units 3 and 4 remains 4Q17 and 4Q18 respectively •Engineering, procurement and construction

Construction Update and

Lessons Learned Stan Thomason

Southern Nuclear Operating Company

Page 2: Construction Updated and Lessons Learned. · Construction Status •Forecast for operation for Units 3 and 4 remains 4Q17 and 4Q18 respectively •Engineering, procurement and construction

Safety

Safe, Quality, Compliant

Construction is our

priority.

Page 3: Construction Updated and Lessons Learned. · Construction Status •Forecast for operation for Units 3 and 4 remains 4Q17 and 4Q18 respectively •Engineering, procurement and construction

Construction Status

• Forecast for operation for Units 3 and 4 remains

4Q17 and 4Q18 respectively

• Engineering, procurement and construction of

the Facility is approximately 50% complete

• Major components are being delivered to site

• Construction is going vertical for Unit 3 NI

Page 4: Construction Updated and Lessons Learned. · Construction Status •Forecast for operation for Units 3 and 4 remains 4Q17 and 4Q18 respectively •Engineering, procurement and construction

Unit 4

Unit 3 Heavy Lift Derrick

Modular Assembly

Building

Nuclear Island

Turbine Island

Turbine Island

Nuclear Island

Containment Vessel

Unit 3

Condenser

Unit 3

Unit 4 Cooling Towers

Construction Site July 08, 2013

Page 5: Construction Updated and Lessons Learned. · Construction Status •Forecast for operation for Units 3 and 4 remains 4Q17 and 4Q18 respectively •Engineering, procurement and construction

U3 Liquid Processing Tanks

Page 6: Construction Updated and Lessons Learned. · Construction Status •Forecast for operation for Units 3 and 4 remains 4Q17 and 4Q18 respectively •Engineering, procurement and construction

U4 Nuclear Island Basemat

Page 7: Construction Updated and Lessons Learned. · Construction Status •Forecast for operation for Units 3 and 4 remains 4Q17 and 4Q18 respectively •Engineering, procurement and construction

U3 Turbine Island, Condenser A

Page 8: Construction Updated and Lessons Learned. · Construction Status •Forecast for operation for Units 3 and 4 remains 4Q17 and 4Q18 respectively •Engineering, procurement and construction

U3 Cooling Tower

Page 9: Construction Updated and Lessons Learned. · Construction Status •Forecast for operation for Units 3 and 4 remains 4Q17 and 4Q18 respectively •Engineering, procurement and construction

U3 Containment Vessel

Page 10: Construction Updated and Lessons Learned. · Construction Status •Forecast for operation for Units 3 and 4 remains 4Q17 and 4Q18 respectively •Engineering, procurement and construction

U4 Reactor Vessel

Page 11: Construction Updated and Lessons Learned. · Construction Status •Forecast for operation for Units 3 and 4 remains 4Q17 and 4Q18 respectively •Engineering, procurement and construction

U4 Deaerator

Page 12: Construction Updated and Lessons Learned. · Construction Status •Forecast for operation for Units 3 and 4 remains 4Q17 and 4Q18 respectively •Engineering, procurement and construction

Construction Inspection Lessons

• Communication with NRC

• IOC Process

• Document Sharing

• Schedule Detail & Activity tracking

Page 13: Construction Updated and Lessons Learned. · Construction Status •Forecast for operation for Units 3 and 4 remains 4Q17 and 4Q18 respectively •Engineering, procurement and construction

Questions?