CONSTRUCTION UPDATE · Flooring will be start to be installed. Ceiling tile will be dropped and...
Transcript of CONSTRUCTION UPDATE · Flooring will be start to be installed. Ceiling tile will be dropped and...
CONSTRUCTION UPDATE Hales Corners Elementary
SAFETY:
SINCE LAST UPDATE:
New Addition The interior courtyard playground has the rubber
poured and is completed!!
The exterior playground equipment has been set in place and is only waiting for wood chips in order to be completed.
Ceiling grid is finished and MEP trades are dropping in their finishes to the ceiling grid before the above ceiling inspection when the ceiling tile will then be installed.
Case is being installed. The classroom cabinets are installed, just working on the cubby spaces.
Courtyard poured rubber surface Starting—June 3rd - Goal Achieved!!
Flooring Starting—June 24th
Please be mindful of the construction area as activi-ties continue. No students, parents, or school staff should pass the fence line without a CG Schmidt escort.
May 27th—June 14th 2019
MILESTONE DATES:
GOAL FOR NEXT UPDATE:
New Addition Casework cubbies will be fully installed and complet-
ed.
Flooring will be start to be installed.
Ceiling tile will be dropped and ceilings closed up.
We will be installing marker boards/tack boards, doors/hardware, and bathroom accessories
Interior Courtyard Playground Rubber Poured
Exterior Playground Equipment Installed
Classroom Casework Installed
Ceramic Tile Installed