Construction Plan vs Actuals After Stage 2
1
Construction Plan Phase Description Date Days % Duration Delays in Days Work % Roughly Construction Start 24-Mar-14 1 Plith Level 12-Apr-14 19 10% 2 10% 20 2 Ground floor Roof 30-May-14 48 24% 12 15% 30 3 First floor Roof 28-Jun-14 29 15% 4 15% 30 4 Electrician Work 5% 10 5 Plumbing Work 5% 10 6 External Plastering 8% 16 7 Internal Plastering 8% 16 8 Elevation Work 5% 10 9 Compound Walls 2% 4 10 Flooring (Internal + Parking) 8% 16 11 Fixtures - Wood 3% 6 12 Fixtures - Plumbing 3% 6 13 Fixtures - Electical 3% 6 14 Painting 8% 16 15 Final Finishing 2% 4 16 Key Handover 10-Oct-14 200 100% 18 100% 200 218 Days adding the delay
description
Construction Plan Actual Stages
Transcript of Construction Plan vs Actuals After Stage 2
Construction Plan
Phase Description Date Days % Duration Delays in Days Work % Roughly
Construction Start 24-Mar-14
1 Plith Level 12-Apr-14 19 10% 2 10% 20
2 Ground floor Roof 30-May-14 48 24% 12 15% 30
3 First floor Roof 28-Jun-14 29 15% 4 15% 30
4 Electrician Work 5% 10
5 Plumbing Work 5% 10
6 External Plastering 8% 16
7 Internal Plastering 8% 16
8 Elevation Work 5% 10
9 Compound Walls 2% 4
10 Flooring (Internal + Parking) 8% 16
11 Fixtures - Wood 3% 6
12 Fixtures - Plumbing 3% 6
13 Fixtures - Electical 3% 6
14 Painting 8% 16
15 Final Finishing 2% 4
16 Key Handover 10-Oct-14 200 100% 18 100% 200
218 Days adding the delay