Construction Phase
-
Upload
rainnie-casandra -
Category
Documents
-
view
12 -
download
1
description
Transcript of Construction Phase
Construction Phase
Important because:
(i) The quality of the completed project is highly dependent on the workmanship and management of construction
(ii) Majority of the total project budget and schedule is expanded during construction phase
(iii) More time and cost in construction imply that any delay or cost variance will have greater effect on the project
Construction Phase
Quality of construction depends on: (i) Completeness and quality of contract
documents (ii) Skilled labourers who have the skills
necessary to produce the work (iii) Field supervisors who have the ability to
coordinate the numerous activities (iv) Quality of material and appropriate tools
and equipment that are used for construction (v) Effective management of the skilled
workers and schedule and cost
Construction Phase
Objective of construction: To build the project in accordance with
the plans and specifications and within budget and on schedule and to the satisfaction of the owner
To achieve the objective, there are three assumptions:
Assumptions for construction phase
(1) Scope: The design plans and specifications contain no errors and meet the owner’s requirements and appropriate codes and standards.
(2) Budget: The budget is acceptable: i.e. it is what the owner can afford to pay and what the contractor can build it with a reasonable profit.
(3) Schedule: The schedule is reasonable. i.e. short enough to finish when the owner needs it, but long enough for the contractor to do the work
The above assumptions are reasonable but in practice they are often variances due to the nature of construction work.
Bidding or Tendering
Prequalification of prospective contractors or bidders
Evaluation criteria: Records of experience Financial capability Safety records General character and reputation in the
industry
Tendering Open tender or closed tender Advertisement for invitation to tender Bid bond or tender deposit to be provided during
submission of tender. Bid bond is refundable to the unsuccessful contractors. For competitive bidding, obtain 3 to 5 bids Generally, the more the bids the more competitive the
bidding i.e. lower bid price. However quality of bidders is more important the quantity.
Bid period must be reasonable to ensure adequate time for the contractors to prepare proposals ( bids)
Too short – some may decline Too long – unnecessary delay in construction
Methods of Tendering
Open Tendering An open invitation to contractors
through newspaper or journal Advantage is competitive price Disadvantage is indiscriminate request
for open tender may lead to poor quality work
Contractors are sometimes ill-equipped, financially unstable or lack the experience to take up the job
Methods of Tendering
Selective Tendering Contractors are short listed and invited to
submit quotations Lists of contractors are either recommended by
the consultants or invited to submit prequalification to tender
Contractor chosen is usually the lowest bid Proper control of tenders to ensure that they
are qualified in terms of experience, financially sound and have technical experience to undertake the job
Methods of Tendering
Negotiated or closed tendering Under the contract, time factor is
important Technical drawings and bill of quantity
(BQ) are not prepared and the extent of the contract is not yet defined
Continuation of the project of repetition of existing contract may be desirable
Tendering
Addendum ( or addenda) Changes in bid package during the tender period to
correct errors, clarify requirement or make changes Too many addenda --- frighten the bidders, create
doubt, create risk in the mind of bidders thus increase bid price
Pre-bid conference Clarify any unique aspect of work Explain special working conditions Answer questions of contractors All clarification at the meeting, not in the bid
documents should be confirmed in writing to all bidders (use addenda)
Bid opening
Closed or open Must have proper procedure to
record Normally attended by the owner
Award of contract
Letter of intend or letter of award Signing of contract Engineer’s Instruction to start work Performance Bond, CAR, Contractor
all risk insurance and third party liability
Performance Bond
Usually 10 % of contract amount Performance bond is a three-party instrument in
which a bonding company ( termed surety) guarantees ( or bonds) to the owner that the project will be build by the contractor in accordance with the contract. If for any reason, the contractor becomes unable or unwilling to complete the contract, the surety will take steps to engage another contractor to complete contract or other steps specified in the instrument. The cost of performance bond depends on the size and risk of the contract and the reputation and expertise of the contractor.
Engineering Instruction (EI) The Engineering may from time to time issue further
drawings, details or written instructions related to: The variation works (VO) Discrepancy between the contract documents Removal from site of any materials brought in by the
contractor Removal of any person employed by the contractor who
has misconducted himself Removal or re-execution of any works executed by the
contractor Opening up for inspection of work covered up Making good of any defect during the defect liability
period Any matter which the Engineer is empowered by the
contract to issue instruction for the good of the works
Variation Order (VO)
Any changes during construction may be instituted through variation order in writing
The changes may be for the following: Increase or decrease the quantity of any work
included in the contract Omit any such work Change the character or quality of any such work Change the level, line position and dimensions of
any part of the works Execute addition work of any kind necessary for the
completion of the works Clarify discrepancy between contract documents
Dispute Resolutions
Due to nature of construction projects it is almost certain that contractor, owner and designer will be involved in disputes
There are four(4) methods of resolution of disputes: Direct negotiations Mediation Arbitration Litigation
Direct Negotiations
Direct negotiation between parties in dispute Quickest and most economical Factual matters are discussed without the
formality of legal formats Negotiator for each party must have authority to
act for his company Success of the negotiation depends on the
willingness of both parties to negotiate in good faith
Can enhance good business relationships between the parties
Mediation Used when direct negotiation failed Use an independent, objective person to assist in
resolving the dispute Mediator has no authority to issue a final decision Mediation is voluntary Mutual agreement to have the mediator to serve
as a catalyst to explore alternative solutions To gather facts, clarify discrepancies and to
persuade the parties to adopt flexibility in their stance
Arbitration It is similar to mediation except the arbitrator has the
authority to issue a final binding decision that cannot be appealed by the disputing parties
Submission of a dispute to a mutually agreed impartial third party whose decision is legally binding and enforceable
Arbitration clause is provided in the Conditions of Contract 5 steps procedure
Agreement to arbitrate Selection of arbitrator Preparation of hearing Hearing of disputes The award
Decision by the arbitrator is made within 30 days from the close of the hearing
Litigation
Resolution of disputes by lawsuits Adopt the legal formality of the court
system Most costly, time consuming and complex
method for resolution of dispute Legal counsels who follow the formality of
the legal judicial system are used to represent the interest of the parties
Fianl resolution of dispute is determined by a court of law
Extension of time Contractor must apply through written notice of the
causes of delay when work is going to be delayed Engineer will have to consider granting extension of
time Engineer shall estimate the length of the delay beyond
the completion date and approve in writing a fair and reasonable extesion of time
Extension of time can be granted based on the following reasons
Force majeure – this means any event which happens beyond the control of man
Exceptional inclement weather – this refers to the weather condition which deviates from the normal annual weather trend.
Loss or damage occasioned by fire, lightning, explosion, storm, flood, ground subsidence etc.
Extension of time Any instruction given by the engineer provided such
instructions are not issued due to any default of the contractor or his subcontractors.
Contractor not having received in due time from the engineer necessary instructions, drawings, levels etc
Delay in giving possession of site Action due to strike, affecting any trades employed
by the works Delay on the part of the artisans, trademen or other
engaged by the employer Contractor’s inability to procure any material for
reason beyond his control which he could not reasonably have foreseen at the closing of tender
Delay on the part of the nominated supplier
Quality Control
Quality control is part of a quality assurance program that has for many years been recognized as the inspection and testing of materials and workmanship to see that the work meets the requirements of the drawings and specifications
Quality is the responsibility of all parties, though principal responsibility is placed on the contractor
Quality Control
What can we do to pass quality control? What can we do to get pass inspection? What can we do to finish the project that
we can be proud of that meets the specifications and satisfies the owner?
Without right attitude, even the best planned quality-control program cannot be successful
Major objectives of Quality Control
To ensure the completed work meets the specifications
To reduce customers’ or clients’ complaints
To improve the reliability of products or work produced
To increase customers’ or clients’ confidence
To reduce production costs
Evolution of quality control
Inspection A process of checking what is produced is what is
required Two forms --- quantifiable e.g. level, dimensions, or
open to interpretation e.g. cleaniness, safety
Quality control by sampling Involve inspection to stages in the development of
goods and services to ensure that they are carried out to satisfy requirements
Done on sampling basis dictated by statistical methods e.g. taking cube tests
Evolution of quality control
Quality assurance Emphasize “defect prevention” To ensure that specifications are consistently
met. “Fit for Purpose” and “Right first time” are the
principles of quality assurance ISO 9000 (BS 5750) certification Document of quality control process and
always follow the process to ensure consistency of product i.e ensure that quality is built into the production sustem
Evolution of quality control
Total quality management Based on the philosophy of continuously improving of
quality of goods or services and customer satisfaction Everyone in the company should be involved and
committed TQM ensures that its goods and services meet the
following criteria: Be fit for purpose on a consistently reliable basis Delight the customer with the service Quality of product is so much better than the competitors that
customers want it regardless of prices There is a mechanism for continuous improvement on the
quality of goods
Job site safety Safety is an important part of project management just
as are planning, scheduling, estimating, cost control and other project work
Concern of safety must be shown at all levels and each phase of the project
Accidents not only affect workers but also their families The economic costs, liability consequences, regulatory
requirements and the image of a company all show the importance of safety related to a project
Construction, by the nature of the work, involves manay potential hazards to workers and equipment, such as heat, noise, wind, dust, vibrations and toxic chemicals
Job site safety The Occupational Safety and Health Administration
(OSHA) was enacted by the Federal Government as a regulatory agency to ensure safety of workers
It applies to all parties involved in the project Project manager must work closely with his team
members to include safety in every aspect of the project
Safety should start at the top level of an organisation and by words and actions, be infused in each level of management through to the workers at the job site
Accident costs include medical costs premiums for compensation benefits, liability and property loss and delay, (cost of loss time)
Safety and productivity are two related parts for higher job performance. The safer the workers, the quicker they work, the higher the productivity
Common causes of accident
Negligence of workers Unsafe working conditions Improper erection of scaffolding Inadequate safety precautionary measures such
as warning sign, barricades, safety belt etc. Insufficient lighting Indifference to safety rules and regulations Failure to check the safety of handing equipment Inexperience workers Inadequate design
Steps to prevent accidents Institute job site safety by management and monitoring
safety as part of the requirement of the project management Form safety committee to monitor the safety requirements at
site Install adequate warning signs and lightings Use of safety gears at the site Briefing / training of safety requirement to all workers at site Regularly check and maintain the handling equipment in safe
working order Maintain order and cleanliness at site Follow proper design and erection procedure for scaffolding Adopt good / standard engineering codes of practices in
construction