Construction of Two Story Csc La Union Field Office Building

9
CONSTRUCTION OF TWO-STOREY CSC LA UNION FIELD OFFICE BUILDING BILL OF MATERIALS, BY CONTRACT I. START UP PARTICULARS - QUANTITY - UNIT A-1 Mobilization/demobilization A-2 Temporary Facilities/Utilities Utilities ( Water, electricity) - 5.00 - month Temporary Wall Enclosure - 1.00 - lot Bunkhouse - 1.00 - lot Warehouse - 1.00 - lot A-3 Clean Up Disposal of Debris - 1.00 - lot Housekeeping - 1.00 - lot II STRUCTURAL A SUBSTRUCTURE A-1 Earth Works Excavation & disposal of waste materials - 41.49 - cu m Backfill - 53.94 - cu m A-2 Termite Control Works Soil Poisoning - 4.00 - liter A-3 Footing (2,500 psi) Cement - 67.00 - bag Sand - 3.49 - cu m 1

description

project

Transcript of Construction of Two Story Csc La Union Field Office Building

Page 1: Construction of Two Story Csc La Union Field Office Building

CONSTRUCTION OF TWO-STOREY CSC LA UNION FIELD OFFICE BUILDINGBILL OF MATERIALS, BY CONTRACT

I. START UP PARTICULARS - QUANTITY - UNITA-1 Mobilization/demobilization

A-2 Temporary Facilities/UtilitiesUtilities ( Water, electricity) - 5.00 - monthTemporary Wall Enclosure - 1.00 - lotBunkhouse - 1.00 - lotWarehouse - 1.00 - lot

A-3 Clean UpDisposal of Debris - 1.00 - lotHousekeeping - 1.00 - lot

II STRUCTURAL

A SUBSTRUCTURE

A-1 Earth WorksExcavation & disposal of waste materials - 41.49 - cu mBackfill - 53.94 - cu m

A-2 Termite Control WorksSoil Poisoning - 4.00 - liter

A-3 Footing (2,500 psi)Cement - 67.00 - bagSand - 3.49 - cu mGravel - 6.98 - cu m16mm def RSB (Grade 33) - 56.00 - pc# 16 GI Tiewire - 8.00 - kg

1

Page 2: Construction of Two Story Csc La Union Field Office Building

Ordinary Plywood 4' x 8' 1/2'' - 7.00 - sheetCoco Lumber - 140.00 - bd ftAssorted CWN - 8.00 - kgGravel Bedding - 3.78 - cu m

A-4 Wall Footing (2,500 psi)WF1Cement - 31.00 - bagSand - 1.79 - cu mGravel - 3.57 - cu m12mm def RSB (Grade 33) - 37.00 - pc# 16 GI Tiewire - 3.00 - kgOrdinary Plywood 4' x 8' 1/2'' - 15.00 - pcCoco Lumber - 714.00 - bd ftAssorted CWN - 3.00 - kg

WF2Cement - 17.00 - bagSand - 0.95 - cu mGravel - 1.90 - cu m10mm def RSB (Grade 33) - 21.00 - pc# 16 GI Tiewire - 2.00 - kgOrdinary Plywood 4' x 8' 1/2'' - 8.00 - pcCoco Lumber - 380.00 - bd ftAssorted CWN - 2.00 - kg

A-5 Slab on Grade (2,500 psi)Cement - 65.00 - bagSand - 3.78 - cu mGravel - 7.56 - cu m12mm def RSB (Grade 33) - 50.00 - pc#16 GI Tiewire - 4.00 - kg25mm Gravel Bedding, 50 mm thick - 3.78 - cu m

2

Page 3: Construction of Two Story Csc La Union Field Office Building

B SUPERSTRUCTURE -B-1 Column (3,000 PSI)

Cement - 79.00 - bagSand - 4.13 - cu mGravel - 8.26 - cu m20mm def RSB ( Grade 33) - 98.00 - pc10mm def RSB (Grade 33) - 112.00 - pc#16 GI Tiewire - 21.00 - kgOrdinary Plywood 4' x 8' 1/2'' - 34.00 - pcCoco Lumber - 1,652.00 - bd ftAssorted CWN - 21.00 - kg

B-2 Stair (3,000 psi) -Cement - 15.00 - bagSand - 0.74 - cu mGravel - 1.48 - cu m12mm def RSB (Grade 33) - 23.00 - pc10mm def RSB (Grade 33) - 18.00 - pc#16 GI Tiewire - 3.00 - kgOrdinary Plywood 4' x 8' 1/2'' - 6.00 - pcCoco Lumber - 297.00 - bd ftAssorted CWN - 3.00 - kg

B-3 2nd Floor Beam ( 3,000 psi)Cement - 64.00 - bagSand - 3.32 - cu mGravel - 6.65 - cu m20mm def RSB ( Grade 33) - 50.00 - pc16mm def RSB (Grade 33) - 12.00 - pc10mm def RSB (Grade 33) - 108.00 - pc#16 GI Tiewire - 19.00 - kgOrdinary Plywood 4' x 8' 1/2'' - 27.00 - pcCoco Lumber - 1,330.00 - bd ft

3

Page 4: Construction of Two Story Csc La Union Field Office Building

Assorted CWN - 19.00 - kg

B-4 2nd Floor Suspended Slab ( 3,000 psi)Cement - 89.00 - bagSand - 4.63 - cu mGravel - 9.27 - cu m12mm def RSB (Grade 33) - 101.00 - pc#16 GI Tiewire - 15.00 - kgOrdinary Plywood 4' x 8' 1/2'' - 38.00 - pcCoco Lumber - 1,854.00 - bd ftAssorted CWN - 15.00 - kg

B-5 Roof Beam (3,000 psi) Cement - 68.00 - bagSand - 3.53 - cu mGravel - 7.06 - cu m16mm def RSB (Grade 33) - 48.00 - pc10mm def RSB (Grade 33) - 115.00 - pc#16 GI Tiewire - 14.00 - kgOrdinary Plywood 4' x 8' 1/2'' - 29.00 - pcCoco Lumber - 1,412.00 - bd ftAssorted CWN - 14.00 - kg

B-6 CHB WALLSCHB 6'' - 2,975.00 - pcPortland Cement - 282.00 - bagSand - 22.97 - cum12mm def. RSB (Grade 33) - 194.00 - pc#16 GI Tiewire - 16.00 - kg

CHB 4" - 1,568.00 - pcPortland Cement - 96.00 - bagSand - 7.76 - cu m10mm def RSB (Grade 33) - 98.00 - pc

4

Page 5: Construction of Two Story Csc La Union Field Office Building

#16 GI Tiewire - 6.00 - kg-

C RoofingTruss System - 104.00 - area2x2x4.5mm Angle Bars - 47.00 - pc2x4x1.5mm C Purlins - 30.00 - pc16mm cross bracings - 5.00 - pc16mm turnbuckles - 5.00 - pc12mm sag rods - 5.00 - pcBase plate - 1.00 - sheetWelding rods - 11.00 - kgEpoxy Primer - 5.00 - gal

C-2 Roofing - 100.86 - sq mPanels & bended accessories- Prepainted long span roofing 0.60 mm x 1150mm - 106.00 - lmEnd wall capping 0.60mm x 915mm - 5.00 - lmEnd wall flashing 0.60mm x 610mm - 5.00 - lmRidge wall flashing 0.60 mm x 610 mm - 6.00 - lmRidge/end wall flashing 0.60mm x762mm - 9.00 - lm

Hardware accessoriesConcrete Nail 25mm - 21.00 - pcBlind rivets 5/32'' x 3/8'' - 27.00 - pcSilicon rubber sealant, clear - 5.00 - tubeTekscrew,12-24 x 75 mm HWF with neo washer - 505.00 - pcTekscrew, Type S,12-24 x 25mm - 26.00 - pcTouchup paint - 1.00 - liter

InsulationP.E. Foam insulation, 2 sided, aluminum 5mmx 1m x 50m - 3.00 - rollAluminum duct tape, 2''x 50 yards - 3.00 - rollBlind rivets 5-8 - 114.00 - pcStraps - 57.00 - pc

5

Page 6: Construction of Two Story Csc La Union Field Office Building

C-3 Equipment RentalBar Cutter - 21.00 - dayWelding Machine - 21.00 - day

III ARCHITECTURAL WORKS/FINISHES A Ceramic TilesA-1 Ground floor tiles - 54.18 - sq m

Vitrified ceramic non skid floor tiles 300 x 300 - 595.00 - pcABC Tile Grout - 22.00 - bagCement - 66.00 - bagSand - 5.94 - cu m- - - -

A-2 Rest room floor tiles - 7.92 - sq mVitrified ceramic non-skid floor tiles, 300 x 300 - 81.00 - pcABC Tile Grout - 4.00 - bagCement - 12.00 - bagSand - 1.08 - cu m- - - - -

A-3 Rest room wall tiles - 23.81 - sq mCeramic wall tiles,300x 300 - 258.00 - pcABC Tile Grout - 10.00 - bagCement - 30.00 - bagSand - 2.70 - cu m

A-4 Second floor tiles - 68.44 - sq mVitrified ceramic non-skid floor tiles, 300 x 300 - 754.00 - pcABC Tile Grout - 28.00 - bagCement - 84.00 - bagSand - 7.56 - cu m

B CEILING DESIGN FINISH ( 3.5 mm thick Hardilite Board on Metal Furring Frame, includes cornices - - Ground Floor - 72.00 - sq mSecond Floor - 72.00 - sq m

6

Page 7: Construction of Two Story Csc La Union Field Office Building

C PAINTING WORKSExterior Wall, plain liquid tile finish - 267.90 - sq mInterior Wall, plain latex finish - 290.70 - sq mCeiling , plain flat finish - 144.00 - sq m

D Doors and Jambs-Doors - 10.75 - sq mDoor Jambs - 7.00 - pc

E Windows Steel Casement Windows - 49.30 - sq m

IV PLUMBING/SANITARYPlumbing/sanitary, includes roughing-ins,fixtures & septic tanks - 1.00 - L.S.

-V ELECTRICAL WORKS - -

Electrical Panel board, Single Phase/2 pole, Bolt-on Type, 175-AmpereTrip/225 AF Main, Molded Case, with ten branches, Single phase/2-pole10 pcs 30 AT/50AF and 1 pc 60 AT/100AF, Bolt-on type, indoor type - 1.00 - unitElectrical Panel board, Single Phase/2 pole, Bolt-on Type, 60-AmpereTrip/100 AF Main, Molded Case, with ten branches, Single phase/2-pole10 pcs 30 AT/50AF a, Bolt-on type, indoor type - 1.00 - unitStranded Electrical Wire 60 mm2, Black Insulation - 30.00 - mStranded Electrical Wire 14 mm2, Black Insulation - 4.00 - mStranded Electrical Wire 14 mm2, Green Insulation - 15.00 - mStranded Electrical Wire 8 mm2, Green Insulation - 2.00 - mStranded Electrical Wire 5.5 mm2, Black Insulation, 150 m per roll - 4.00 - rollStranded Electrical Wire 3.5 mm2, Black Insulation, 150 m per roll - 4.00 - rollStranded Electrical Wire 3.5 mm2, Green Insulation, 150 m per roll - 2.00 - rollRSC Pipe 50mm - 1.00 - pcRSC Entrance Cap No. 50 mm - 1.00 - pcElectrical PVC Pipe No. 50mm - 3.00 - pcElectrical PVC Pipe No. 15mm - 102.00 - pcDuplex Lighting Luminaries with reflector and louver with 2 Preheat 36 watts at 230 volts - 25.00 - set Pin Light Housing 6 inches diameter with 20 Watts ESL - 6.00 - set

7

Page 8: Construction of Two Story Csc La Union Field Office Building

Aircon Outlet, 3 prong 20 Amperes - 9.00 - setDuplex Convenience Outlet, 3 Prong, Universal, 15 Amperes - 29.00 - setFlush single switch with cover plate - 4.00 - setFlush duplex switch with cover plate - 9.00 - setplate - 2.00 - setUtility Box, PVC, Orange, Heavy Duty - 53.00 - pcOctagonal Box, PVC, Orange, Heavy Duty - 50.00 - pcPVC Adapter for 50mm PVC with PVC Lock Nut - 2.00 - pcPVC Adapter for 25mm PVC with PVC Lock Nut - 2.00 - pcPVC Adapter for 15mm PVC with PVC Lock Nut - 120.00 - pcElectrical Tape - 10.00 - rollConcrete Post with Service Equipment - 1.00 - lsMiscellaneous items like screw, bolts, brackets, etc. - 1.00 - ls

8