Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

download Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

of 36

Transcript of Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    1/36

    Paper No.506

    CONSTRUCTION OF RAFT FOUNDATION IN DEEPSANDY BEDS FOR MAJOR BRIDGES ACROSS

    PERENNIAL RIVERS+

    By

    MS. ASHWINI UGALMUGLE* & DR. A.G. NAMJOSHI**

    CONTENTS

    Page

    1. Introduction ... ... 422

    2. Bridge Across River Bawanthadi ... ... 422

    3. Bridge Across River Kanhan ... ... 439

    SYNOPSIS

    The choice of shallow foundation is conventionally restricted to minor

    bridges (less than 60 m length) where the stream bed has non-erodable strata

    or where the design depth of scour in erodable strata is not much and there is no

    perennial flow/standing water in the river bed. In the present case, shallow

    foundations have been adopted for construction of bridges across major rivers viz.

    Bawanthadi & Kanhan having a linear waterway of 400 m & 180 m respectively.This paper describes in detail two different techniques adopted to tackle the

    construction of cut off walls for raft foundations where heavy dewatering was

    required.

    In the first case of submersible bridge across river Bawanthadi, the site is

    located very near to the confluence with river Wainganga and heavy dewatering was

    contemplated. In order to overcome the difficulty, the cut-off walls were cast above

    low water level and lowered down to the designed founding level below the bed.

    An innovative method of lowering down a unit of 22 m long pre-cast cut off wallsusing temporary fabricated steel frame stiffeners is described here.

    In the second case of high level bridge across river Kanhan, there was

    standing water of around 3.0 m depth in the river bed extending almost over 80

    per cent width of the river. Pre-Trenching method was adopted using Bentonite

    clay for construction of cast-in-situ cut off walls.

    + Written comments on this Paper are invited and will be received upto 31st

    December, 2004.

    * Senio r Desi gn Engi neer,

    ** Consu lt ing Engineer ,Dr. Namjoshi & Associates, Nagpur.}

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    2/36

    MS. UGALMUGLE & DR. NAMJOSHION422

    1. INTRODUCTION

    It is a conventional practice to rest the foundations of major

    bridges anchored firmly into sound rock. Streams where foundable strata

    is not available at a reasonable depth, always pose a problem to select

    appropriate type of foundations. The bridge engineers generally do not

    like to deviate from guide lines given in the IRC codes 1,2,3,4 which are

    general in nature covering various conditions all over the country. The

    bridge engineer, however, has to exercise his insight to adopt unique

    solution, to suit a particular site conditions. Such decisions a build upconfidence level, if they are supported by sound performance record of

    precedents.

    Over the years, Maharashtra state has developed raft foundations

    as available alternative for deep foundations such as wells and piles in

    locations where hard foundable strata are deep seated and dry weather

    flow is such that construction of cut off walls with manual open excavation

    is feasible. Recognizing the indisputable merits of raft foundation, designand construction, engineers of the department have been constantly

    innovating to achieve economy and furtherance of constructional ease.

    Construction of cut off walls upto desired depth is possible by

    excavating an open trench in case of cohesive soils which can be vertically

    cut. Dewatering is one of the major difficulties faced in the construction

    of raft foundations6

    specially in case of sandy soils and structures near

    irrigated areas because recharging of the ground makes dewatering difficult.

    Various innovative methods7 have been devised and put into practice in

    the field to overcome such difficulties. A number of major bridges have

    also been economically9 constructed successfully over raft foundations7

    in the past with a sound performance record.

    The Paper discusses construction of cut off walls for raft foundations

    for two major bridges viz. submersible bridge across river Bawanthadi andhigh level bridge across river Kanhan where innovative methods were

    developed during execution.

    2. BRIDGE ACROSS RIVER BAWANTHADI

    2.1. Brief History

    Tumsar Belaghat A State Highway (S.H. No.271) connects Tumsarin Maharashtra with Belaghat in Madhya Pradesh. It had an unbridged

    crossing across river Bawanthadi near Bapera. The State Highway at

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    3/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    423

    present is a fair weather road and prior to the construction the bridge

    temporary crossing was having constructed across this river during dryseason every year. The traffic, however, used to remain closed during

    monsoon period (June to October).

    Since heavy traffic is not likely to develop over this route in the

    near future, a submersible bridge with a single lane carriageway was

    constructed from economic considerations. The formation level of the

    bridge has been fixed at such a level, that the traffic may get interrupted

    only during high floods with a frequency and duration remaining withinthe permissible norms.

    Therefore, a continuous unit of multiple cell RCC box construction

    which satisfies all the requirements of a submersible bridge which causes

    minimum obstruction to flood waters was adopted.

    This single lane bridge being quite long (i.e. 381 m) cause

    considerable hindrance to two way traffic. Therefore waiting places of

    two lane capacity were provided at two locations (Plate 1).

    This bridge length is made up of 15 independent units of RCC Box

    Cells each having a length of 21.65 m. Each unit consists of 5 continuous

    box cells with opening 4.0 x 3.7 each (Plate 1). The gap between two

    independent (continuous) units is bridged by providing a simply supported

    solid slab having length of 4.0 m (Plate 2). The simply supported solidslab superstructures rest over the brackets projecting out from the vertical

    walls at ends of the box cell units. The foundation for each 5 cell unit

    is provided with reinforced cement concrete (RCC) continuous raft slab

    of length 22.55 m x 4.60 m (22.55 m x 7.80 m for 2 lane enlarged portion

    provided at two intermediate locations). The salient features of the bridge

    are given in Annexure-I.

    The raft slab is confined by detached plain cement concrete (PCC)cut off walls (300 mm x 2300 mm) on upstream (u/s) and downstream

    (d/s) sides extending for full length of the bridge from bank to bank.

    Cross cut-off walls of same size are provided at the beginning and end

    of each 5 cell continuous unit so as to confine the RCC raft slab foundation

    for each unit independently. The portion below the simply supported

    span between two cross cut-off walls is provided with 600 mm thick PCC

    flooring.

    The clear width of roadway is 4.25 m for 13 units whereas 7.50 m

    wide 2 units were provided at waiting places (Plate 3). 550 mm wide

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    4/36

    MS. UGALMUGLE & DR. NAMJOSHION424

    discontinuous road kerbs are provided on either side of the carriageway

    along full length of the bridge [Photo 1]. The width of kerb has beenkept as 550 mm with removable type post and pipe railing on either side

    for the safety of pedestrians. The riding spans on either side of the two

    lane units (provided as waiting/overtaking zones) are enlarged from

    4.2 m to 7.5 m wide carriageway to facilitate smooth transition. Thus the

    total length of the bridge is built as under :

    Photo 1. Two lane unit waiting place

    Unit A (Single Lane) : 13 x 21.65 = 281.45 m

    Unit B (Two Lane) : 2 x 21.65 = 43.30 m

    Riding spans (Single Lane) : 10 x 4.0 = 40.00 m

    Riding spans ( Flared ) : 4 x 4.0 = 16.00 m

    Total Length = 380.75 m

    2.2. Protection Works

    The raft foundation & cut off walls are further protected by providing

    1100 mm thick launching apron of rubbles. The velocity at bed level

    during peak floods does not exceed 2.50 m/sec, however, weight of each

    stone not less than 40 kg has been used for apron. The launching apronextends for a width of 6.75 m on u/s side and 9.0 m on d/s side. PCC toe

    walls are provided along full length of the apron on both sides.

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    5/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    425

    2.3. Problem Encountered

    The bed material predominantly consists of pure sand with almost

    no silt/clay content & could not stand a vertical cut necessary to allow

    excavation of an open trench. The work was, however, commenced with

    a conventional method of excavating a wide open trench. A block of

    28.0 m x 10.0 m was excavated in the sandy bed. The pit could hardly

    be excavated to a depth of 1.50 m below the bed level & it was observed

    that further digging is not possibly due to following impediments :

    (a) Collapse of sides due to heavy sand blows during excavation

    & dewatering, inspite of shoring & strutting.

    (b) The water level remained constant even after employing 200

    HP water pumps for dewatering.

    Further work was hampered due to occurrence of nonseasonal

    floods & the excavated pit got filled up to the original bed level. It was

    therefore considered necessary to explore the possibility of casting the

    cut off walls at bed level & thereafter lowering it down to the desired

    level below the bed, instead of conventional method of casting in situ in

    open trench.

    2.4. Construction Technique

    The above arrangement (Fig. 1) provided confinement to RCC raft

    foundation (for each unit of 5 celled box) at foundation level by an

    independent frame of cut off walls of 2.30 m depth (22.65 m length x

    4.60 m width) all along the periphery.

    It was, therefore, proposed to cast the PCC frame of cut off wall for

    each unit separately & lower it down to the desired position by scooping

    out the sand below the cut off & inside the frame simultaneously so

    that it could gradually sink uniformly by its own weight.

    2.5. General Features & Design Considerations for Raft Foundation

    The detached cut off walls are designed to perform the following

    main functions in service condition :

    (a) To confine the bed material below the raft foundation.

    (b) As a diaphragm that prevents the free flow of bed material/

    particles underneath raft foundation during floods.(c) To extend the path of exit gradient below the bridge

    foundation & its protection works.

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    6/36

    MS. UGALMUGLE & DR. NAMJOSHION426

    Fig.

    1.

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    7/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    427

    In short, under service condition of the bridge proper, the detached

    cut off walls are not designed to bear any stresses. It can therefore beconsidered as a non structural bridge component so far as transfer of

    forces to the foundation stratum under various critical combinations of

    loads are concerned . In the present case the cut-off walls are constructed

    in PCC M-15 grade. However as a conventional practice, skin reinforcement

    @ 5 kg/sqm is provided.

    The stability of the cut off wall frame was checked for the loading

    conditions, which it might have experiences during sinking process. Theinside dimensions of the rectangular frame under discussion was 22.55 x

    4.60 m with a height of 2.30 m and the thickness of wall was 300 mm.

    The frame of cut off wall was proposed to be lowered down to the desired

    position by removing the sand inside the box & below the cut off wall.

    The frame was designed to withsand following forces during sinking

    process :

    (a) The differential lateral pressure of saturated sand from outside

    for a height of 2.30 m inducing bending stresses in the horizontal

    plane.

    (b) Occurrence of non uniform settlement along the periphery of

    the frame resulting in bending stresses in the vertical plane

    due to self weight of the frame. The height of cut off wall is

    2.30 m and its thickness is 300 mm. The long walls are

    connected by cross cut-off walls at the ends only. It was,therefore, necessary to restrict the span length to maximum

    4.0 m, so as to safely bear the lateral thrust. The longitudinal

    walls, were, therefore stiffened from inside at five intermediate

    locations by providing removable vertical steel brackets thus

    dividing it into six short bays of length not exceeding 4.0 m

    each. The brackets on the opposite walls were braced by

    removable horizontal steel strut fixed at 0.75 m height from

    bottom.

    After carrying out detailed analysis of forces occurring during the

    lowering down operation, additional reinforcement wherever required was

    provided in the cut off wall frame at appropriate locations. The reinforcement

    for the cut off walls was designed for the stresses induced under critical

    conditions of the construction phase. The stress in concrete & steel has

    been allowed to exceed upto 33 per cent in the construction phase aspermissible.

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    8/36

    MS. UGALMUGLE & DR. NAMJOSHION428

    2.6. Construction Details

    2.6.1. Sinking of single lane main unit: The bed was prepared,

    levelled & timber logs were placed at one meter interval along the periphery

    of the unit. A 500 mm wide strip in brick on edge, was constructed all

    round the periphery so as to rest the base of 300 mm cut off wall. The

    shuttering was erected for a full height of 2.30 m & reinforcement cage

    was tied in position. The anchor bolts required for fixing the steel bracket

    were placed in a 20 mm dia & 300 mm long PVC pipe casings so as to

    facilitate easy removal. These bolts were placed in exact position &tightened with the centering plates.

    The concrete cut off wall was, thereafter cast in layers for full

    height of 2.30 m in one operation so as to ensure adequate self weight

    and to facilitate ease in sinking. [A top layer of 200 mm was left to be

    cast initially so as to leave scope for achieving a perfect level after final

    sinking] (Photo 2). The vertical shuttering plates were removed. Thereafter

    steel brackets were tightened to the concrete cut-off walls at predetermined

    locations. After that horizontal steel strut was braced at 0.75 m from

    bottom to the brackets on opposite walls (Fig. 1). It was ensured to place

    timber wedges at junction of bracket & steel strut on both sides so as

    to allow easy removal of brackets after final sinking (Photo 3). The

    sinking operation started after the concrete of cut off walls attained

    adequate strength. The following arrangement was made for sinking

    operation.

    Photo 2. Cut-off wall unit cast at bed level

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    9/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    429

    Photo 3. Stiffening arrangement of RCC cut-off walls

    Vertical steel bracket with horizontal strut

    In all 28 labourers, 4 in each intermediate bays and 6 in end bays

    were working inside the box. They first scooped out the sand beneath

    the cut off wall uniformly all along the periphery & removed the temporary

    timber supports placed beneath it simultaneously. The operation of removal

    of sand within the box & all along the periphery was carried out gradually

    & uniformly so as to avoid differential sinking. It was also observed that

    the sinking of cut-off wall continued to be uniform all along the periphery.

    When the whole unit of cut off wall was sunk upto the bottom level ofapron, the sand outside the cut off wall on u/s & d/s side was removed

    upto that level so as to reduce intensity of the differential lateral pressure.

    Thereafter, the sinking process was continued till the cut off wall reached

    the desired level.

    For removal of sand within the box, 3 nos. of Winch with Grab

    (Latur cranes) of 350 kg capacity (65 HP) were used. The removed sand

    was deposited at a distance of 10 m on d/s side i.e. beyond the toe ofapron on d/s side. In all 60 HP electrically operated water pumps were

    required to work continuously for the sinking operation.

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    10/36

    MS. UGALMUGLE & DR. NAMJOSHION430

    The cut-off wall unit was seated to the desired level. Sand was

    refilled in the box upto the top of horizontal steel strut (leaving theportion around the strut) so as to reduce the earth pressure on the cut-

    off wall from outside. Thereafter the wooden wedges were removed &

    the strut was relieved of axial thrust. The whole steel frame work i.e.

    horizontal struts & vertical brackets were removed one by one and side

    by side and sand filled in the box up to the bottom level of proposed raft

    (Photo 4).

    Photo 4. Cut-off wall unit sunk in final position

    The following material & labour were required for casting & sinking

    of one main unit (single lane) of cut off wall.

    Casting Operation

    PCC M15 - 39.50 cum

    Cement bags required - 240 nos

    Working hours required - 10

    Concrete mixer used - 1 no

    Labours (in 2 shifts) - 80 nos

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    11/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    431

    For removal of sand and sinking in all 60 HP water pumps were

    required to operate continuously.

    Period Required

    Preparation of base platform, erection - 5 days

    of centering, shuttering & tying of

    reinforcement cage etc.

    Casting & curing of cutoff wall - 7 daysSinking operation - 5 days

    2.6.2. Intermediate unit: The cut off walls required for bridging of

    the gap between the two adjacent main units (under simply supported

    span) overlapped both units by 300 mm from outside (Photo 5), (Fig. 2a).

    The cut-off walls were cast for the required length for full height on

    u/s & d/s side separately. These two cut off walls were braced with a

    single horizontal steel strut connected with a vertical steel bracket atboth ends for sinking purpose. The cut-off walls were cast leaving a gap

    of 50 mm on u/s and d/s side so as to avoid friction with the main unit

    Photo 5. Overlapping cut-off wall between two units

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    12/36

    MS. UGALMUGLE & DR. NAMJOSHION432

    while sinking. Both the cut-off walls were sunk to the desired level by

    adopting the same procedure as that followed for the main unit. It was,however, observed that the self weight of the intermediate unit (being

    small in length) was insufficient to overcome side friction & hence

    counterweight had to be provided during final sinking.

    The following labour & material were required for casting & sinking

    of the intermediate units of cut off walls.

    Casting Operation

    PCC M-15 - 6 cum

    No of bags required - 37 bags

    For removal of sand and sinking in all 40 HP water pumps were

    required to operate continuously.

    Period Required

    Preparation of base platform, erection - 2 days

    of centering, shuttering & tying of

    reinforcement cage etc.

    Casting & Curing of cut-off wall - 7 days

    Sinking operation - 3 days

    2.6.3. Method for ensuring continuity of cut-off walls: In order toensure an efficient functioning of the cut off wall to prevent free flow of

    bed material underneath the raft foundation, its functional continuity had

    to be maintained. If construction joints are inevitable it should be ensured

    that no gap is left in-between or is protected with additional lap joint

    so that sand should not flow through the gap from u/s to d/s during

    floods.

    The horizontal surface steel in the longitudinal walls of the mainunit was extended for one lap length beyond the outer face of cross cut

    off wall. After casting of concrete in cut off wall, the projecting

    reinforcement bars were bent upward & plastered with lean cement

    mortar flushed with the outer face of the cross cut off wall to ensure

    obstruction to free sinking. Similarly 8 mm dia bars in U shape were

    projected for a lap length in the transverse direction (Fig. 2b) in the cut

    off wall of intermediate unit. The longitudinal extended bars from main

    unit cut off were straightened (after scraping the lean plaster) and were

    tied with 8 mm for `U bar projecting from cut off of intermediate unit.

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    13/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    433

    Fig. 2b. Details showing continuity of cut off wall

    Fig. 2a.

    300

    f i ll e t 150 x 1 50

    up to 1 .3 m from

    bot tom

    M A I N U N I T M A I N U N I T

    I N T E R M E D I A T E U N I T

    A

    300300

    300

    2 5 0 0

    30 0

    Su r fa c e r e i n f

    ex tended f rom

    ma i n u n it i n te rmed ia te un i t

    Su r fa c e r e i n fex tended f rom

    M A I N U N I T

    I N T E R M E D I A T E U N I T

    cast in s i tu @ al l the four

    6 0 0 x 3 5 0 x 2 3 0 0 m m t o b eConc re te b lock o f s i ze

    corners o f i n te rmed ia te un i t

    after f ina l s inking

    DETAILS OF A

    37 5 45 0 75

    30 0

    35 0

    30 0 60 0

    90 0

    30 0

    Thereafter this overlapping piece of cut-off wall was cast in-situ making

    the lap joint fool-proof & thus maintaining a physical continuity throughoutthe length of the bridge foundation.

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    14/36

    MS. UGALMUGLE & DR. NAMJOSHION434

    2.7. Two Lane Unit

    The area covered by this unit is larger by about 70 per cent than

    the single lane unit. In order to limit the dewatering efforts, the two lane

    unit (Fig. 3a) of size (22.55 m x 7.90 m) was divided into two independent

    units of internal size 10.00 m x 7.90 m leaving a gap of 2.50 m (similar to

    that left between the single lane units). The intermediate cross cut off

    wall at the continuous end was cast 1.0 m below the raft top level so as

    to avoid propping action during service condition. The 1.0 m height was

    built up by constructing a temporary precast CC block masonry upto theraft top level in order to have uniform loading all along the periphery.

    The longitudinal walls were stiffened from inside at two intermediate

    locations by providing the removable vertical steel brackets thus dividing

    the same in three bays of length less than 4.0 m each. The brackets on

    the opposite walls were braced by removable horizontal steel strut fixed

    at 0.75 m height from bottom. The cross cut off walls were also stiffened

    from inside at center with a vertical steel bracket. The steel bracket on

    the opposite cross cut off walls were braced by longitudinal removablehorizontal steel strut which simultaneously stiffened the two struts provided

    in transverse direction also. The same procedure as adopted for other

    units for casting & sinking was adopted for these two units also. The

    intermediate unit was cast & sunk to desired level. The temporary walls

    of block masonary of 1.0 m height constructed over intermediate cross

    cut off wall was removed & sand was refilled upto the bottom level of

    proposed raft. These two parts of the units were finally joined to form

    a single unit for two lane flared portion (Fig. 3b).

    Fig. 3a.

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    15/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    435

    Fig. 3b. Arrangement of twin segements of cut

    off walls below two lane units

    After final

    sinking of

    o v e r l a p p i n g

    cut off the

    main cut off

    wall is cast

    insitu to main-tain continuity

    (All dimensions in mm unless otherwise specified)

    The following material & labour were required for casting & sinking

    of one part of Two lane unit of cut off wall.

    Casting Operation

    PCC M15 - 23.16 cum

    Cement bags required - 140 nos

    Working hours required - 8

    Concrete mixer used - 1 no

    Labours (in 2 shifts) - 80 nos

    For removal of sand and sinking in all 50 HP water pumps wererequired to operate continuously.

    Period Required

    Preparation of base platform, erection - 5 days

    of centering, shuttering & tying of

    reinforcement cage etc

    Casting & Curing of cut-off wall - 7 daysSinking operation - 5 days

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    16/36

    MS. UGALMUGLE & DR. NAMJOSHION436

    2.8. Difficulties Encountered

    2.8.1. The cut off units were sunk to an average depth of 3.50 m

    below the LWL and the inside dimension was increased by 150 mm

    (4600 mm to 4750 mm) so as to provide adequate margin for the likely

    shift, if any in the lateral direction during sinking. This was done so as

    to ensure uniform & symmetrical raft about the center line of the bridge

    of required minimum dimension. No change in dimension of the main

    units was warranted to accommodate shift in the longitudinal direction,

    as the same could be accommodated by varying the length of theintermediate unit which was cast after final sinking of main units on

    either side.

    2.8.2. The cut off wall has to satisfy the following main functional

    requirements

    (a) The minimum depth below the raft top RL should be 2.30 m

    (b) The cut off wall top should be in level with the raft top.

    The cut off wall was cast in upto 2.10 m height only in the initial

    stage before sinking. The surface reinforcement required, however, was

    tied for the full height of 2.30 m. There was no difficulty in sinking it

    to a little more depth so as to observe minimum depth of 2.30 m of cut

    off below raft top RL at all the corners & intermediate locations. After

    meeting with the requirement of minimum depth on final sinking, the

    remaining cut off height which was left to be cast initially (around 200

    mm), was concreted upto the desired level at top of the raft after making

    up the difference in height, if any, at all the corners. This ensured to

    achieve a perfect horizontal plane at the top of the raft level.

    2.8.3. It is already mentioned in the Brief History that a temporary

    crossing used to be constructed for restoring the traffic during the open

    season. This temporary crossing used to be constructed by drivingtimber piles/stamps in the river bed & laying branches of trees within, so

    that it could hold the filled up soil in flowing water for preparation of

    temporary service road. These timber stumps used to get plunged further

    into the sandy bed during monsoon. The alignment of the bridge overlapped

    a part of the service road. These timber logs stuck at some places while

    sinking the units. Such obstacles had to be removed after resorting to

    excavation from outside & pulling it out with a rope. The sinking operation

    all over the periphery was required to be slowed down or suspended tillsuch obstacles were removed so that uniform sinking could be possible.

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    17/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    437

    2.8.4. Initially the cut off wall frame required for two units of

    22.55 m each was cast & finally sunk in position one after the other. Agap of 4.0 m was left for simply supported span. Thereafter the intermediate

    cut off unit was cast. While removing the sand between the intermediate

    cut off wall for sinking purpose it was observed that the sand filled in

    the adjacent bays of units on either side also slipped in this unit through

    sand blows. Due to this phenomena the level of sand in the adjacent bays

    used to subside. It was therefore necessary to make up the level of sand

    filled in the adjacent bays also after filling sand in the intermediate unit.

    It is, therefore, advisable to lay the levelling coarse below RCC raft ofmain unit only after the sinking & sand refilling of adjacent intermediate

    units on either side of the main unit are completed.

    2.8.5. During construction of cut off walls near the banks it was

    observed that at some places, rock outcrops were struck under the units

    (Photo 6). It is a structural necessity that the cut of walls all along the

    Photo 6. Rock struck near banks

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    18/36

    MS. UGALMUGLE & DR. NAMJOSHION438

    periphery need to rest over a strata of uniform SBC in order to avoid

    differential settlement. This requirement was artificially generated byexcavating an open trench of dimension about 1 m. wide and half a meter

    deep below the desired seating level of the cut off walls in the rock

    outcrop (Fig. 4). The extra portion of the excavated trench (i.e. 0.50 m

    below the seating level of cut off) was refilled with sand cushion.

    Fig. 4. Sinking of cut off wall in rocky out crops

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    19/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    439

    If a continuous stretch of hard strata/rock is met with where the

    cut off wall is designed to rest it is desirable to provide a clear verticalseparation joint in the cut off wall at the junction of the two different

    strata. In order to protect this vertical joint an additional piece of cut off

    wall (covering cut off wall) with an overlap of 750 mm on either side of

    the vertical joint should be constructed from outside so as to arrest the

    free flow of sand through the construction joint.

    2.8.6. Similar rock outcrops were met with below the raft portion

    within the cut off walls, where the rock outcrops were cut to a depth suchthat a uniform sand cushion of minimum 900 mm could be laid below the

    proposed raft.

    2.8.7. Rock was continuously met with on both the banks. The cut

    off walls of the end units were therefore constructed by adopting

    conventional method of excavating an open trench and casting in situ of

    the PCC cut off walls.

    2.8.8. The rubble apron was deleted in the portions where rock was

    met with in the bed. However the apron and the toe wall was extended

    horizontally for 2 m length inside the rock so as to overlap the rocky bed

    and to ensure sufficient grip against local erosion (Fig. 5).

    2,8.9. PCC solid abutments supporting open foundation were end

    riding spans with constructed at both the ends where rock foundation

    was met. The end units of box cell superstructure were converted into

    intermediate units of box cell with simply supported riding spans at the

    ends.

    The actual construction of the bridge was commenced on 18 th Nov.

    2003. The most difficult task was to construct cut off walls. The construction

    of box cell superstructure units was, however, simultaneously completed

    leaving a margin of atleast one unit of cutoff frame sunk in positionahead, in the direction it progressed. The bridge work at a cost of Rs.190

    Lacs was completed on 15 th June 2003 @ Rs.50000 per m length

    (Photo 7).

    3. BRIDGE ACROSS RIVER KANHAN

    3.1. Brief History

    The bridge across river Kanhan is at 13 km on Parseoni -

    Khaperkheda road (MDR) in Nagpur District. River Kanhan is a perennial

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    20/36

    MS. UGALMUGLE & DR. NAMJOSHION440

    Fig. 5. Details of rubble apron anchoring in rocky banks

    Photo 7. Bapera Bawanthadi bridge work nearing completion

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    21/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    441

    river with catchment area of about 5221 sq km (2017 sq miles) upto the

    bridge site. There is a minor irrigation project constructed on u/s sidein Madhya Pradesh across this river . Therefore there is a perennial flow

    at the bridge site due to regeneration of the catchment. The low water

    spread extends for about 80 per cent of the bed width at bridge site

    having a maximum depth of about 3 m above the lowest bed level. Ferry

    crossing was the only available mode to cross at this site for the local

    population. The bridge provides an all weather connection from thermal

    power station at Khaparkheda to Nagpur Jabalpur N.H. 7 by a shorter

    route. Moreover the MSEB was also in a need of a high level crossingfor carrying the ash pipe line across river Kanhan. In order to serve both

    the purposes simultaneously, it was, therefore, decided to construct a

    high level bridge across this river.

    A linear water way of 180 m was required from hydraulic

    considerations. Foundable strata of sound rock was available at a depth

    of about 35 m below the L.W.L in the main gorge as revealed from the

    trial bores. The flood depth at HFL was around 11 m above the L.W.L.The total height of substructure including foundation worked out to 46

    m. The proposal was therefore framed as per conventional practice of the

    department. A proposal of 4 spans of 45 m each (Plate 4) with PSC box

    superstructure & hollow R.C.C. piers resting over well foundations was

    finalized and tenders were invited accordingly.

    The bids received were ranging between 5.0 to 6.5 crores with a

    similar arrangement as contemplated by the department. However one

    alternative proposal with R.C.C. raft foundation and elaborate protection

    work was offered at 4.27 crores. This alternative proposal being

    unconventional one (RCC raft foundation for a major bridge having

    perennial flow & standing water in the bed) took some time to arrive at

    a considered decision after carrying out a detailed technical scrutiny &

    examining construction viability. The contract was finally awarded in

    November 1997.

    3.2. Details of Bridge Proper

    This proposal contemplated a two lane bridge having 15 simply

    supported spans of 12 m center to center of solid slab construction

    (Plate 5). A separate trough slab superstructure adjacent to main

    carriageway was provided to carry MSEB ash pipe line. Both the

    superstructures rested over neoprene bearings placed over RCC pedestalon R.C.C. cantilever pier caps. R.C.C. wall type piers with semicircular cut

    and ease water were provided over R.C.C. raft foundations. The raft slab

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    22/36

    MS. UGALMUGLE & DR. NAMJOSHION442

    was provided with a haunched beam below each pier support. Abutment

    on left bank and Piers P-1 to P-11 had R.C.C. raft foundations whileremaining 3 piers and abutment on right bank rested over rock with open

    foundations. The foundable strata on right bank was available at a

    reasonable depth.

    3.3. Protection Work

    3.40 m deep and 0.35 m wide PCC detached cut off walls with

    nominal reinforcement were provided to confine the 900 mm thick sandfilling below the R.C.C. raft. The sand cushion was overtopped by 100 mm

    thick P.C.C. leveling coarse. 700 mm thick rubble apron overtopped by 300

    mm thick PCC paving cast in staggered bays of 2 m x 2 m were provided.

    This protection work extended for a length of 15.70 m on d/s side & 11.75

    m on u/s side beyond the cut off walls. The hydraulic features with

    calculation for protection work are given in Annexure-II.

    3.4. Design Features of Haunched Footing

    The RCC raft slab for foundation is designed as a wide beam on

    elastic foundation, on the same theory.

    The coefficient of subgrade reaction is assumed as under:

    (a) Sandy strata - 5600 T/m3

    (b) Sandy clay - 2800 T/m3

    The raft slab is provided with a haunched base below the RCC pier

    for even distribution of concentrated load over a span of 12.0 m

    (Photo 8).

    This part of the pier footing being a rigid one is not deformable.

    The load at bottom of pier is assumed to disperse uniformly through the

    deep concrete footing at 45 degrees to the base of raft.

    The value of the load transmitted at the end of haunches of the

    footing in the form of shear force on both sides has been considered

    for the design of raft slab of uniform thickness in between ends of two

    haunched footings.

    The sum of shear force at both ends of the haunches together isconsidered as a single concentrated load over the raft slab of uniform

    thickness.

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    23/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    443

    Photo 8. Reinf. details of haunched footing

    below pier

    The span between two such consecutive concentrated loads, over

    the raft slab (in the form of continuous beam of uniform thickness) is

    considered as distance between two consecutive ends of haunches ignoring

    the width of footing at the base of pier 5.

    3.5. Construction Technique for Casting of Cut off Wall

    Bentonite clay technique is commonly used for construction of

    diaphragm walls to enclose the area to be built up for building or some

    other structure. This is predominantly used in coastal areas/reclamation

    are as where heavy dewatering is involved and open excavation is not

    possible where or the soil cannot stand a vertical cut. This technique

    however is not adopted for the bridge works where there exists flowing

    water in the channel.

    As already explained, there was flowing/standing water in the river

    bed and the bottom level of the cut off wall was designed to rest at about

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    24/36

    MS. UGALMUGLE & DR. NAMJOSHION444

    6.0 m depth below the LWL. The water spread extended for almost about

    80 per cent width of the river. This situation naturally warranted heavy

    dewatering before laying raft foundation and the cut off walls. In order

    to reduce the dewatering efforts to the barest minimum, it was necessary

    to go in for such a technique which would allow the operation of open

    trenching as well as concreting of cut off wall under water. Hence the

    bentonite clay technique was employed here.

    The excavator was slightly modified to suit the specific purpose by

    extending the length of stick by 1.2 m and reducing the width of bucketto 490 mm from that of its standard size, was procured for construction

    of cut off walls. The width of cut off wall was increased to 500 mm to suit

    the operatable minimum size of bucket though 350 mm width of cut off

    wall was adequate from the design considerations.

    The cut off wall was to be constructed for a total length of 315 m

    i.e length on both sides and that required at ends. This operation was

    however tackled by taking a panel of about 30 m at a time. A workingearthen platform for a width of about 15 m was constructed in the river

    bed with its top at about 0.50 m above the low water level so as to cover

    the area required for construction of bridge foundation as well as the

    width of path required for operating the machinery and equipment.

    The following equipments were required for the above work.

    (i) Excavator (Photo 9)(ii) Crane RB 19 (For concreting & lifting of

    tremie set & compaction)

    (iii) Guide rail (To guide the bucket) (Photo 10)

    (iv) Miller mixing pump (To mix Bentonite slurry)

    (v) Two Bentonite slurry tanks each capacity (Photo 11)

    of 8000 litres (For recycling purpose)

    (vi) 2 sets of tremie pipe with hopper (For concreting) (Photo 12)

    (vii) Tremie spanner (For fixing of tremie pipe)

    (viii) Concrete mixer.

    (xi) Generator 45 HP (For lighting & welding purpose)

    (x) Chain (To measure depth/sounding)

    The alignment of the cut off wall and its width was precisely marked

    on the ground. The guide rails were embedded in the platform to form a

    defined width of the cut off wall trench (Photo 10). The trench wasexcavated to a depth of about 0.50 m and it was filled with bentonite

    slurry. The slurry was allowed to penetrate and saturate the adjacent soil

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    25/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    445

    Photo 9. Trench excavator

    Photo 10. The guide rails aligned

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    26/36

    MS. UGALMUGLE & DR. NAMJOSHION446

    Photo 11. Bentonite slurry tank

    Photo 12. Tremie pipe fitted with hopper

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    27/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    447

    for about 6 hours. This process stabilized the adjacent soil so as to

    facilitate further excavation. Thereafter excavation was resumed and the

    soil removed was simultaneously replaced by an equal amount of bentonite

    slurry. It is essential to maintain the level of bentonite slurry up to the

    level of guide rail and the rate of refilling should match with the rate of

    removal of soil. This process is continued till the trench was excavated

    upto RL at the bottom of cut off wall.

    A panel of length about 3-4 m was earmarked by placing two stop

    end pipes of diameter little less than that of the trench (Photo 13) forconvenience during concreting. Once the panel was ready a reinforcement

    cage was lowered into the panel (Photo 14) with the help of a crane.

    Thereafter the tremie pipes were lowered and a hopper was tightened in

    position at top (Photo 15). Generally one tremie pipe can conveniently

    feed a length of about 2 m. If the length of panel is larger, additional

    tremie pipe is to be lowered down.

    Photo 13. Stop end pipes placed to form a panel

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    28/36

    MS. UGALMUGLE & DR. NAMJOSHION448

    Photo 14. Lowering down of reinforced cage with crane

    Photo 15. Well point method with electrically operated pumps

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    29/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    449

    A tremie plug was provided at the base of hopper and concrete was

    filled up to the brim of the hopper. The plug was thereafter released with

    the help of a sling attached to the crane. The concrete just gushes down

    the tremie pipe as soon as the plug is removed and uniformly spreads

    over the bottom of the cut off wall. The concrete thus smoothly spreads

    over the panel bottom gradually replacing the bentonite slurry. A base

    layer of about 300 mm depth was thus carefully laid.

    The hopper was fitted with a hook attached to the sling of the

    crane. When the concrete passes through the tremie pipe it is raised andlowered so as to induce vibration and compaction of the concrete laid.

    In this process care is taken that the bottom of the tremie pipe always

    remains submerged in the concrete mass laid in the cut off wall so that

    there is no chance of bentonite slurry getting entrapped in the concrete

    mass. Concreting was thus continued till the panel was filled upto the

    desired height. The final level was checked by lowering a chain.

    The process of excavation and concreting of the cut off wall wascontinued in a phased manner till the full length of cut off wall was cast.

    3.6. Construction of Raft Slab and Substructure

    The construction of toe wall on u/s side together with the apron

    was tackled first. This reduced the dewatering effort required for the

    construction of the raft and the d/s apron. For construction of the above,

    the dewatering was done by adopting conventional method of wellpoint. A circular concrete caisson of 5.50 m internal diameter was sunk

    to a depth of about 5 m below the LWL and a number of electrically

    operated water pumps were used to keep the water level below the raft

    bottom till concrete was set (Photo 15). The RCC wall type piers

    together with cantilever caps were constructed thereafter.

    3.7. Construction of Counterfort Abutment

    Abutment on right bank was resting over open foundation and was

    designed and constructed as per usual practice. The left side abutment

    was located well inside the bank which was composed of sandy clay.

    The width of raft below piers was reduced to 8.5 m. The abutment,

    however, had to be provided for the full width i.e 11.25 m to retain the

    approach earth. The total length of raft provided below abutment was

    17.35 m in order to restrict the pressure within the safe being capacity(SBC) of the soil. This raft, stiffened by counterforts, was projected in

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    30/36

    MS. UGALMUGLE & DR. NAMJOSHION450

    the front by about 45 per cent of the total length so as to restrict the

    difference between maximum and minimum pressure over foundation by

    not more than 1t/sqm under all conditions. The raft below abutment was

    separated out from the main raft below piers by providing a cross cut

    off wall.

    3.8. Treatment Near Junction of Open & Raft Foundation

    The raft foundation below P1 to P11 was terminated at the end

    of haunch base below P11 by providing a cross cut off wall. ThoughP-12 was resting over open foundations in order to simulate smooth

    transition of the hydraulic conditions from raft foundation to open

    foundation the following measures were taken.

    (a) The cut off walls on u/s and d/s side were extended in the

    longitudinal direction further upto mid span between P-12 &

    P-13 though these were anchored in rock.

    (b) The vent portion around P-12 was provided with 300 mm thicknominally reinforced PCC M-20 grade paving resting over

    250 mm thick PCC M-10 base & 900 mm rubble filling.

    (c) This paved vent portion was confined by providing cut off

    walls all around which were anchored into rock.

    (d) The end piers (P-10 & P-11) over RCC raft foundation were

    provided with 1500 mm thick rubble filling below the 900 mm

    thick sand cushion as an additional precaution.(e) The rubble apron and the toe wall was extended horizontally

    for 2 m length inside the rock so as to overlap the rocky bed

    and to ensure sufficient grip against local erosion (Fig. 8).

    3.9. Construction of Solid Slab Superstructure

    The height of pier was about 13 m above the LWL and also due to

    standing water in the bed, suspended truss type centering was used for

    supporting the superstructure. The width of the pier cap was slightly

    increased so as to rest the ends of trusses. The superstructure was cast

    after placing the neoprene bearing pads over the RCC pedestals.

    ACKNOWLEDGEMENTS

    The Authors express their thanks to Shri D.G. Marathe, Chief Engineerand Shri S.K. Mukharjee, Superintending Engineer, Designs for their

    encouragement and able guidance during the construction of bridge

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    31/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    451

    across river Kanhan. A word of appreciation is also due to M/s. Khare

    & Tarkunde Infrastucture Pvt. Ltd., Nagpur for their relentless efforts in

    successful completion of the bridge.

    The Authors wish to thank Shri S.K. Veermani, Superintending

    Engineer, P.W. Circle, Nagpur for his valuable views and suggestions

    during execution of bridge across river Bawanthadi. Thanks are due to

    Shri D.H. Fulekar, Executive Engineer, PW Division, Bhandara and

    Shri B.K. Chilkalwar, Sub-divisional Engineer for their help in efficient

    execution of the above work. Similarly the authors express their gratitudeto M/s. Chaphekar & Co., Nagpur for their enterprising approach in

    adopting the technique and successfully executing this major bridge

    under difficult conditions.

    REFERENCES

    1 . I R C: 5 1 9 98 S t an d ar d s p ec i fi c at i on s a n d c o de of pr a ct i ce fo r r o ad

    bridges : Section I General features of design (Seventh Revision)

    2 . I R C: 6 2 0 00 S t an d ar d s p ec i fi c at i on s a n d c o de of pr a ct i ce fo r r o ad

    bridges : Section II Loads and stresses (Fourth Revision)

    3 . I R C: 7 8 20 0 0 S ta n da rd s pe c if i ca t io ns a nd c od e of p ra c ti c e f o r r o ad

    bridges : Section VII Foundation and substructure (Second Revision)

    4. IRC: 89 1997 Guidelines for design & construction of river training and

    control works for road bridges. (First Revision)

    5. Beams on elastic foundations Hetenyi (1946) ANN ARBOR. The University

    of Michigan Press.

    6 . Namjoshi , A.G. , Dewater ing Problem in construct ion of Raft Foundat ion

    bridge across Morna River on Borgaon Hatrum Road in Akola district,

    Journal of the Indian Roads Congress, Vol. 40, Part 3, 1979.

    7. Namjoshi, A.G. & Dr. Kulkarni, S.S., Shallow caissons design, construction

    and sinking technique and review of some field techniques adopted for construction

    of cut off walls, Journal of the Indian Roads Congress, Vol. 532, Sept.

    1992.

    8. Namjoshi , A.G. , Anticipated Scour depth in non al luvial /clayey beds

    International Seminar on Bridge Substructure and foundations, Delhi Conference

    Documentation, Vol. 2, Jan. 1992.

    9. Namjoshi, A.G. & Dr. Kulkarni S.S, Economic design of raft foundation

    bridges. Journal of International Seminar on Bridge Substructure and Foundations,

    Delhi Conference Documentation, Vol. 1, Jan. 1992.

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    32/36

    MS. UGALMUGLE & DR. NAMJOSHION452

    Annexure-I

    Bridge Across River Bawanthadi

    Salient Features

    1) Catchment Area - 2380 sq. km (920 sq. miles)

    2) Design Discharge - 5999 cumecs

    3) Maximum Mean Velocity - 2.77 m/sec

    4) Maximum Flood Level - 263.800 m5) E. O. H. F. L - 264.800 m

    6) Bridge Formation RL - 261.325 m

    7) Lowest Bed Level - 257.630 m

    8) Length of Bridge - 381 m

    9) Nature of Bed - Medium sand upto 6 m depth varying

    from 6 to 10 m depth below bed level

    in the main gorge. Silt Factor - 1.80

    10) Type of Bridge - Submersible11) Foundation - M25 RCC raft slab with detached

    cut off wall.

    12) Cut Off Wall - PCC cut off wall 2.30 m deep.

    13) Protection Work - 900 mm thick rubble apron over

    topped by 150 mm thick PCC paving

    6.75 m on u/s side & 9.0 m on d/s

    side.

    14) Substructure/Superstructure - RCC M25 Box Cell15) Kerbs & Railing - 550 mm wide discontinuous kerbs with

    GI Pipe & Post removable type railing.

    (i) Calculations for mean scour depth

    5999Unit Discharge q = = 17.885 Cumecs/m

    (380.75 45.32)

    Unit discharge to be increased by 22 per cent as per IRC:781983

    Cl.No. 703.1

    Hence designed unit discharge is 21.82 Cumecs/m

    Dsm = 1.34 x [21.822/1.80]1/3

    = 8.57 m

    C R F D S B M B

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    33/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    453

    (ii) Depth of cut off required

    L.B.L. = 257.630 m

    Mean Scour RL = 263.8008.57 = 255.230 m

    Cut off depth required = 257.330 255.230 = 2.10 m

    Provide minimum depth of cut off = 2.30 m

    (iii) Design of floor protection work to RCC raft foundation

    Max Scour Depth = 1.27 x 8.57 = 10.884 mMax Scour RL = 263.80 10.884 = 252.916 m

    Top RL of raft : 257.330 m

    Designed max. scour depth below the raft top

    (257.330 - 252.916) = 4.414 m

    U/S apron length = 1.5 x 4.414 = 6.621 m say 6.75 m

    D/S apron length = 2.0 x 4.414 = 8.828 m say 9.0 m

    (iv) Size of stone for apron

    (Designed velocity at HFL - 263.800 is 2.77 m/sec)

    Velocity at raft top

    = [(257.33 - .252.916)/(263.80 252.916] x 2 x 2.772

    = 2.49 m/sec

    Size of stone for apron

    d = (2.49/4.893)2

    = 0.259m

    w = 2650 x (4/3) x (22/7) x (0.1294)3

    = 24 kg

    Minimum weight of stone shall be 40 kg as per IRC:891997 cl.No. 5.3.7.2

    (v) Thickness of apron

    t = 0.06 x Q1/3

    = 0.06 x 5999 1/3

    = 1.09 m

    Provide 900 mm rubble apron overtopped by 150 mm PCC paving

    or 1100 mm rubble apron.

    M U & D N454

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    34/36

    MS. UGALMUGLE & DR. NAMJOSHION454

    Annexure-II

    Bridge Across River Kanhan

    1) Catchment Area - 5221 sq. km (2017 sq. miles)

    2) Design Discharge - 8872 cumecs

    3) High Flood Level - 102.500 m

    4) Maximum Mean Velocity - 4.95 m/sec

    5) E. O. H. F. L - 104.050 m6) Maximum Mean Velocity - 5.17 m/sec

    7) Bridge Formation RL - 105.325 m

    8) Low Water Level - 91.400 m

    9) Silt Factor - 1.70

    10) Length of Bridge - 180 m

    11) Nature of Bed - Coarse sand

    12) Type of Bridge - High Level

    13) Foundation - RCC raft slab M-25 with haunch below

    piers & with detached cut off wall.

    14) Cut Off Wall - PCC cut off wall 3.40 m deep.

    15) Protection Work - 700 mm thick rubble apron over topped

    by 300 mm thick PCC paving 11.75 m

    on u/s s ide & 15.70 m ond/s side.

    16) Substructure - RCC M-20 Wall Type Pier with cantilever

    Pier cap.

    17) Superstructure - RCC M-25 Solid Slab Superstructure

    over Neoprene bearing pads.

    18) Kerbs & Railing - 375 mm wide continuous kerbs with

    RCC Parapet

    (i) Calculations for mean scour depth

    8872

    Unit Discharge q = = 51.88 Cumecs/m

    (171)

    CONSTRUCTION OF RAFT FOUNDATION IN DEEP SANDY BEDS FOR MAJOR BRIDGES 455

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    35/36

    CONSTRUCTIONOF RAFT FOUNDATIONIN DEEP SANDY BEDSFOR MAJOR BRIDGESACROSS PERENNIAL RIVERS

    455

    Unit discharge to be increased by 19 per cent as per IRC:78-1983

    Cl.No. 703.1

    Hence designed unit discharge is 61.74 Cumecs/m

    Dsm = 1.34 x [61.742/1.70]1/3

    = 17.54 m

    (ii) Depth of cut off required

    Normal scour level - (102.5017.54) = 84.96 m

    Local scour level (1.27 Dsm)

    for Abutment foundation and

    design of floor protection works

    for raft foundation. (102.501.27 x 17.54) = 80.22 m

    Lowest bed level 88.35 m

    Top R.L. of raft to be kept 300 mm below lowest bed level.R.L. 88.35-0.30 = 88.05 m

    Cut off wall bottom to be kept 300 mm below normal scour level

    R.L.84.96-0.30 = 84.66 m proposed bottom R.L. = 84.65 m

    Max. depth of detached cut off wall

    88.05-84.65 = 3.40 m

    (iii) Design of floor protection work to RCC raft foundation

    Designed max. scour depth below the raft top

    88.05-80.22 = 7.83 m

    Length of floor protection from nose of pier on u/s side

    7.83 X 1.5 = 11.75 m

    Proposed length - 11.75 m

    Length of floor protection on d/s side from the nose of pier.

    7.83 X 2.00 = 15.66 m

    Proposed length - 15.70 m

    UGALMUGLE & DR NAMJOSHI ON CONSTRUCTION OF RAFT FOUNDATION IN DEEP456

  • 8/3/2019 Construction of Raft Foundation in Deep Sandy Beds for Major Bridges Across Perennial Rivers

    36/36

    (iv) Size of stone for apron

    (Designed velocity at EOHFL - 104.050 is 5.17 m/sec)Velocity at raft top

    = [(88.05 - 80.22)/(104.05 - 80.22)] x 2 x 5.172

    = 4.19 m/sec

    Size of stone for apron

    d = (4.19/4.893)2 = 0.7332 m

    w = 2650 x (4/3) x (22/7) x (0.3666)3

    = 547 kg Say 550 kg

    (v) Thickness of apron

    t = 0.06 x Q1/3 = 0.06 x 88721/3 = 1.240 m

    As Per IRC:89-19974 Cl. 5.3.5.2. The thickness computed from above

    formulae shall be subject to an upper limit of 1.0 m. Provide 700 mm rubble

    apron overtopped by 300 mm PCC paving in bays of 2 m x 2 m in

    staggered position.

    UGALMUGLE & DR. NAMJOSHION CONSTRUCTIONOF RAFT FOUNDATIONIN DEEPSANDY BEDSFOR MAJOR BRIDGES ACROSS PERENNIAL RIVERS

    456