Construction Method (Roads)
Transcript of Construction Method (Roads)
-
8/11/2019 Construction Method (Roads)
1/1
Municipality of Polillo Contract Reference Number:_________Name of Contract: ________________Location of the Contract: ___________
Standard Form Number: SF-INFR-43Revised on: August 11, 2004
OUTLINE NARRATIVE DESCRIPTION OF CONSTRUCTION METHODS
1.0 INTRODUCTION
The Project name is Concreting of 20 Barangay Roadslocated at Polillo, Quezon.
2.0 BRIEF DESCRIPTION OF CONTRACT WORKS
Concreting of 20 Barangay Roads ( Length = 180 Linear Meter. Width = 4 meters.
Thickness = 0.15 meters. 9 Linear meters per Barangay).
3.0 CONSTRUCTION METHODS AND PROCEDURES
3.1 Methodology or General Approach
After the sub-grade has been placed and compacted to the required density,the areas which will support the paving machine and the grade on which the
pavement is to be constructed shall be trimmed to the proper elevation by means ofa proper designed machine extending the prepared work areas compacted at least
6cm beyond each edge of the proposed concrete pavement. If loss of density resultsfrom the trimming operations, it shall be restored by additional compaction before
concrete is placed. If any traffic is allowed to use the prepared sub-grade or base,
the surface shall be checked and corrected immediately ahead of the placingconcrete. The sub-grade or base shall be uniformly moist when the concrete is
placed.
The concrete shall be placed with an approved slip-form paver designed to
spread, consolidate, screed and float-finished and freshly placed concrete in onecomplete pass of the machine in such a manner that a minimum of hand finish will
be necessary to provide a dense and homogenous pavement in conformance with theplans and specifications. The machine shall vibrate the concrete for the full width
and depth of the strip of pavement being placed. The sliding forms shall be rigidly
held together laterally to prevent spreading of the forms. After the final finish, butbefore the concrete has taken its initial set, the edges of the pavement along eachside of each side of transverse expansion joints, formed joints, transverse expansion
joints and emergency construction joints, shall be worked with an approved tool and
rounded to the radius required by plans.
Immediately after the finishing operations have been completed and the
concrete has sufficiently set, the entire surface of the newly placed concrete hassufficiently set, the entire surface of the newly placed concrete shall be cured inaccordance with either one of the methods described herein. The concrete shall not
be left exposed for more than hour between stages of curing or during the curingperiod.
3.2 Program of Work
Please see attached Construction Schedule and S-Curve.
3.3 Financial Program
Please see attached Cash Flow by Quarter and Payment Schedule.
Submitted by:
LEO D. LLACUNAGeneral ManagerLD Llacuna Construction & Supply