    OUTLINE NARRATIVE DESCRIPTION OF CONSTRUCTION METHODS

    1.0 INTRODUCTION

    The Project name is Concreting of 20 Barangay Roadslocated at Polillo, Quezon.

    2.0 BRIEF DESCRIPTION OF CONTRACT WORKS

    Concreting of 20 Barangay Roads ( Length = 180 Linear Meter. Width = 4 meters.

    Thickness = 0.15 meters. 9 Linear meters per Barangay).

    3.0 CONSTRUCTION METHODS AND PROCEDURES

    3.1 Methodology or General Approach

    After the sub-grade has been placed and compacted to the required density,the areas which will support the paving machine and the grade on which the

    pavement is to be constructed shall be trimmed to the proper elevation by means ofa proper designed machine extending the prepared work areas compacted at least

    6cm beyond each edge of the proposed concrete pavement. If loss of density resultsfrom the trimming operations, it shall be restored by additional compaction before

    concrete is placed. If any traffic is allowed to use the prepared sub-grade or base,

    the surface shall be checked and corrected immediately ahead of the placingconcrete. The sub-grade or base shall be uniformly moist when the concrete is

    placed.

    The concrete shall be placed with an approved slip-form paver designed to

    spread, consolidate, screed and float-finished and freshly placed concrete in onecomplete pass of the machine in such a manner that a minimum of hand finish will

    be necessary to provide a dense and homogenous pavement in conformance with theplans and specifications. The machine shall vibrate the concrete for the full width

    and depth of the strip of pavement being placed. The sliding forms shall be rigidly

    held together laterally to prevent spreading of the forms. After the final finish, butbefore the concrete has taken its initial set, the edges of the pavement along eachside of each side of transverse expansion joints, formed joints, transverse expansion

    joints and emergency construction joints, shall be worked with an approved tool and

    rounded to the radius required by plans.

    Immediately after the finishing operations have been completed and the

    concrete has sufficiently set, the entire surface of the newly placed concrete hassufficiently set, the entire surface of the newly placed concrete shall be cured inaccordance with either one of the methods described herein. The concrete shall not

    be left exposed for more than hour between stages of curing or during the curingperiod.

    3.2 Program of Work

    Please see attached Construction Schedule and S-Curve.

    3.3 Financial Program

    Please see attached Cash Flow by Quarter and Payment Schedule.

    Submitted by:

    LEO D. LLACUNAGeneral ManagerLD Llacuna Construction & Supply