Construction Engineering and Management Instructor: Dr. Ayham Jaaron.

119
Construction Engineering and Management Instructor : Dr. Ayham Jaaron

Transcript of Construction Engineering and Management Instructor: Dr. Ayham Jaaron.

Construction Engineering and Management

Instructor:

Dr. Ayham Jaaron

ENGINEERING MANAGEMENT

2

Class Rules and Instructor Expectations

•Turn off your cell phone before you get inside the class room.•Be on time and respect deadlines; late homework will not be accepted! •Participate and attend class: be ready and prepare well, that is the key to success! •Quizzes and exams will be closed-book. •Avoid Make-up/incomplete exams!

ENGINEERING MANAGEMENT

3

Topics1) Management Functions and introduction of construction project planning and scheduling2)Construction scheduling techniques3)Preparation and usage of bar charts4)Preparation and usage of the Critical Path Method (CPM)5)Preparation and usage of Precedence Diagramming Method (PDM)6)Issues relating to determination of activity duration7)Contractual provisions relating to project schedules8)Resource leveling and constraining9)Time cost tradeoff10)Schedule monitoring and updating.11)Communicating schedule12) Project control and earned value Control13) claims, Safety and Quality control

ENGINEERING MANAGEMENT

4

In order to understand project management, one must begin with the definition of a project. A project can be considered to be any series of activities and tasks that :.

● Have a specific objective to be completed within certain specifications

● Have defined start and end dates

● Have funding limits

● Consume human and nonhuman resources (i.e., money, people, equipment)

● Are multifunctional (i.e., cut across several functional lines)

What is the Project

ENGINEERING MANAGEMENT

5

OR

‘‘a temporary endeavor undertaken to create a unique product, service, or result’’

ENGINEERING MANAGEMENT

6

Project Life Cycle

ENGINEERING MANAGEMENT

7

Five Process group

Project initiation ●Selection of the best project

given resource limits ●Recognizing the benefits of

the project ●Preparation of the documents

to sanction the project ●Assigning of the project

manager

Project planning ●Definition of the work

requirements ●Definition of the quality and

quantity of work ●Definition of the resources

needed ●Scheduling the activities

●Evaluation of the various risks

Project execution ●Negotiating for the

project team members ●Directing and managing

the work ●Working with the team

members to help them improve

Project monitoring and control

●Tracking progress ●Comparing actual outcome

to predicted outcome ●Analyzing variances and

impacts ●Making adjustments

Project closure ●Verifying that all of the work

has been accomplished ●Contractual closure of the

contract ●Financial closure of the charge

numbers ●Administrative closure of the

paper work

ENGINEERING MANAGEMENT

8

ENGINEERING MANAGEMENT

9

Successful project management can then be defined as having achieved the project objectives:

● Within Time

● Within Cost

● At the desired performance/Technology level

● While utilizing the assigned resources effectively and efficiently

● Accepted by the customer

ENGINEERING MANAGEMENT

10

What is Project Management Project management is the planning, organizing,

directing, and controlling of company resources for a relatively short-term objective that has been established to complete specific goals and objectives.

ENGINEERING MANAGEMENT

11

The potential benefits from project management are:

● Identification of functional responsibilities

● Minimizing the need for continuous reporting

● Identification of time limits for scheduling

● Identification of a methodology for trade-off analysis.

● Measurement of accomplishment against plans

ENGINEERING MANAGEMENT

12

The above definition requires further comment. Classical management is usually considered to have five functions or principles:

● Planning

● Organizing

● Staffing

● Controlling

● Directing

ENGINEERING MANAGEMENT

13

Planning

– Where the organization wants to be in the future and how to get there.

Organizing

– Follows planning and reflects how theorganization tries to accomplish the plan.

– Involves the assignment of tasks, grouping oftasks into departments, and allocation of resources.

ENGINEERING MANAGEMENT

14

Leading

– The use of influence to motivate employees toachieve the organization's goals.

– Creating a shared culture and values,communicating goals to employees throughoutthe organization, and infusing employees toperform at a high level.Controlling

– Monitoring employees' activities, determining if the organization is on target toward its goals, and making corrections as necessary

ENGINEERING MANAGEMENT

15

Conceptual Skill—the ability to see the organization as a whole and the relationship between its parts.

Human Skill—The ability to work with and through people.

Technical Skill—Mastery of specific functions and specialized knowledge

Management Skills

ENGINEERING MANAGEMENT

16

Project management is designed to manage or control company resources on a given activity, within time, within cost, and within performance. Time, cost, and performance are the constraints on the project.

Constraints of the project

ENGINEERING MANAGEMENT

17

Resources We have stated that the project manager must control company resources within time, cost, and performance. Most companies have six resources:

● Money

● Manpower

● Equipment

● Facilities

● Materials

● Information/technology

ENGINEERING MANAGEMENT

18

Actually, the project manager does not control any of these resources directly, except perhaps money (i.e., the project budget).

Resources are controlled by the line managers .

The project manager is responsible for coordinating and integrating activities across multiple, functional lines. The integration activities performed by the project manager include:

ENGINEERING MANAGEMENT

19

● Integrating the activities necessary to develop a project plan

● Integrating the activities necessary to execute the plan

● Integrating the activities necessary to make changes to the plan

ENGINEERING MANAGEMENT

20

Project Scheduling Planning, Scheduling,

and Control

1

ENGINEERING MANAGEMENT

21

Planning and Scheduling

Planning and scheduling are two terms that are often thought of as synonymous

They are not!

Scheduling is just one part of the planning effort.

ENGINEERING MANAGEMENT

22

Project planning serves as a foundation for several

related functions such as cost estimating, scheduling,and project control.

Project scheduling is the determination of the timing and sequence of operations in the project and their assembly to give the overall completion time

ENGINEERING MANAGEMENT

23

Planning is the process of determining how a project will be undertaken. It answers the questions:

1“ .What” is going to be done,2“ .how,”

3“ .where,”4 .By “whom”, and

5“ .when” (in general terms: start and finish).

Scheduling deals with “when” on a detailed level… See Figure 1 .

ENGINEERING MANAGEMENT

24

The Plan

WhatHow much

By whom

where

Why

How

when

Figure 1 . Planning and Scheduling

ENGINEERING MANAGEMENT

25

The PlanPMI defines project management plan as a ‘‘formal, approved document that defines how the project is executed, monitored and controlled”.

The plan can include elements that has to do with scope, design and alternate designs, cost, time, finance, land, procurement, operations, etc.

ENGINEERING MANAGEMENT

26

WHY SCHEDUALE PROJECTS ?

1 -To calculate the project completion.

2 -To calculate the start or end of a specific activity.

3-To expose and adjust conflict between trades

or subcontractor.

4 -To predict and calculate the cash flow.

5-To evaluate the effect of changing orders ‘CH . ’

ENGINEERING MANAGEMENT

27

6 -To improve work efficiency.

7 -To resolve delay claims , this is important in critical path method ‘CPM’ discussed later..

8 -To serve as an effective project control tool.

ENGINEERING MANAGEMENT

28

The Tripod of Good Scheduling System1.The Human Factor : A proficient scheduler

or scheduling team.

2. The Technology : A good scheduling computer system (software and hardware)

3. The Management : A dynamic, responsive, and supportive management.

If anyone of the above three ‘‘legs’’ is missing, the system will fail.

ENGINEERING MANAGEMENT

29

Scheduling and project management Planning, scheduling, and project control are extremely important components of project management.project management includes other components :• cost estimating and management,

• procurement,

• project/contract administration,

• quality management,

• and safety management.

These components are all interrelated in different ways.

ENGINEERING MANAGEMENT

30

Bar (Gantt) Charts

2

ENGINEERING MANAGEMENT

31

DEFINITION AND INTRODUCTION• A bar chart is ‘‘a graphic representation of

project activities, shown in a time-scaled bar line with no links shown between activities’’

The bar may not indicate continuous work from the start of the activity until its end.

or

Non continuous (dashed) bars are sometimes used to distinguish between real work (solid line) and inactive periods (gaps between solid lines)

ENGINEERING MANAGEMENT

32

• Before a bar chart can be constructed for a project, the project must be broken into smaller, usually homogeneous components, each of which is called an activity, or a task.

Item ActivityM 10 Mobilization

Bars ( Month or Year )

ENGINEERING MANAGEMENT

33

ADVANTAGES OF BAR CHARTS

1- Time-scaled

2- Simple to prepare

3- Can be more effective and efficient if CPM based - Still the most popular method

4- Bars can be dashed to indicate work stoppage.

5- Can be loaded with other information (budget, man hours, resources, etc.)

ENGINEERING MANAGEMENT

34

Bar Charts Loaded with More Info.Such as : budget, man hours and resources .

10 12 7 11 10 9 15

500$

220$

400$

850$

140$ 500$

900$

ENGINEERING MANAGEMENT

35

DISADVANTAGES OF BAR CHARTS

1- Does not show logic

2- Not practical for projects with too many activities- As a remedy, we can use bar charts to show:

1. A small group of the activities (subset)

2. Summary schedules

ENGINEERING MANAGEMENT

36

Basic Networks

3

ENGINEERING MANAGEMENT

37

DEFINITION AND INTRODUCTION

• A network is a logical and chronological graphic representation of the activities (and events) composing a project.

• Network diagrams are the preferred technique for showing activity sequencing.

• Two main formats are the arrow and precedence diagramming methods.

ENGINEERING MANAGEMENT

38

Two classic formatsAOA: Activity on ArrowAON: Activity on Node

Each task labeled withIdentifier (usually a letter/code)Duration (in std. unit like days)

There are other variations of labeling

There is 1 start & 1 end event

Time goes from left to right

ENGINEERING MANAGEMENT

39

Arrow Diagramming Method (ADM)

1 .Also called activity-on-arrow (AOA) network diagram or (I-J) method (because activities are defined by the form node, I, and the to node, J)

2 .Activities are represented by arrows.

3 .Nodes or circles are the starting and ending points of activities.

4 .Can only show finish-to-start dependencies.

ENGINEERING MANAGEMENT

40

i j

(a) Basic Activity

Activity Name

Node (Event) i

j > i

Each activity should have a unique i – j value

Node (Event) j

Basic Logic Patterns for Arrow Diagrams

ENGINEERING MANAGEMENT

41

2 A

(b) Independent Activities

4 10 B 12

3 A 6 B 9

(c) Dependent Activities

ENGINEERING MANAGEMENT

42

2

A

(d) A Merge

4

6B 8

(e) A Burst

C

Activity C depends upon the completion of both Activities A & B

8

A6

2B

4C

Activities B and C both depend upon the completion of Activity A

ENGINEERING MANAGEMENT

43

(f) A Cross

20

18C

16 D14

A12

B

Activities C and D both depend upon the completion of Activities A and B

ENGINEERING MANAGEMENT

44

ExampleDraw the arrow network for the project given next.

IPA Activity - A

A B

A C

B D

C,D E

ENGINEERING MANAGEMENT

45

Solution :

10

30

4020 50

C

D

A

B

E

ENGINEERING MANAGEMENT

46

Dummy activity (fictitious)

* Used to maintain unique numbering of activities.

* Used to complete logic, duration of “0” *The use of dummy to maintain unique

numbering of activities .

ENGINEERING MANAGEMENT

47

4 10

4 10

11

A

B

A

B

Divide node to correct

Dummy

(a) Incorrect Representation

(b) Correct Representation

ENGINEERING MANAGEMENT

48

ExampleDraw the arrow network for the project given next.

IPA Activity - A

A B

A C

B,C D

ENGINEERING MANAGEMENT

49

10 3020 40

C

DA

B

Solution :

10

30

4020 50

C

DA

BDummy

Improper solution

proper solution

ENGINEERING MANAGEMENT

505050

ExampleDraw the arrow network for the project given next.

IPA Activity - A

A B

A C

B D

B,C E

C F

ENGINEERING MANAGEMENT

51

Solution :

10

30

40

20 60

C

EA

B

Dummy 1

50Dummy 2

D

F

ENGINEERING MANAGEMENT

52

Removal of Redundant Dummies

A

A

A

A

B

B

B

B

C C

Original Diagram Diagram after removal of redundant dummies

(a)

(b)

ENGINEERING MANAGEMENT

53

A

A

A

A

C

C

B

C

B B

Original Diagram Diagram after removal of redundant dummies(c)

(d)

B E

C

E

E E

ENGINEERING MANAGEMENT

54

Immediately Preceding Activity (IPA)

Depends Upon Activity

-----AB

-----A

A, B

ABC

B CA

Redundant

Relationship

ENGINEERING MANAGEMENT

55

Activity List with Dependencies:

Depends Upon Description Activity

----------A

A, B, CA, B, C

B, C, J, MB, C, D, E, KD, E, F, G, L

--------------------

Site ClearingRemoval of TreesExcavation for FoundationsSite GradingExcavation for Utility TrenchesPlacing formwork & ReinforcementInstalling sewer linesPouring concreteObtain formwork & reinforcing steelObtain sewer linesObtain concreteSteelworker availability

ABCDEFGHJKLM

ENGINEERING MANAGEMENT

56

Depends Upon Description Activity

----------A

A, B, CA, B, C

B, C, J, MB, C, D, E, KD, E, F, G, L

--------------------

Site ClearingRemoval of TreesExcavation for FoundationsSite GradingExcavation for Utility TrenchesPlacing formwork & ReinforcementInstalling sewer linesPouring concreteObtain formwork & reinforcing steelObtain sewer linesObtain concreteSteelworker availability

ABCDEFGHJKLM

Removing Redundant Relationships:

ENGINEERING MANAGEMENT

57

AOA Representation

H4040

G4545

C

F

D3535

1515

1010

55B

A

2020

M

2525J

3030

E

L

K

ENGINEERING MANAGEMENT

58

NODE NETWORKS MTHOD (AON)

a) Independent Activities

10A

10A

20B

20B

Activity number

Activity name

b) Dependent Activities

20B

20B

10A

10A

Link

LinkB depends on A

ENGINEERING MANAGEMENT

59

30C

30C

10A

10A

20B

20B

40 D40 D

c) A Merge Relationship

C depends on A & BD depends on C

d) A Burst Relationship

20B

20B

30C

30C

40D

40D

10 A10 A

B depends on AC depends on BD depends on B

ENGINEERING MANAGEMENT

60

e) Start & Finish Dummy Activities

AA

CC

BB

EE

DDAA

StartDummyStart

DummyFinish

DummyFinish

Dummy

CC

BB

EE

DD

6161

ExampleDraw the arrow network for the project given next.

IPA Activity - A

A B

A C

B D

C,D E

ENGINEERING MANAGEMENT

62

Solution :

A E

C

DB

ENGINEERING MANAGEMENT

6363

ExampleDraw the arrow network for the project given next.

IPA Activity - A

A B

A C

B,C D

ENGINEERING MANAGEMENT

64

A

C

D

B

Solution : ENGINEERING MANAGEMENT

65656565

ExampleDraw the arrow network for the project given next.

IPA Activity - A

A B

A C

B D

B,C E

C F

ENGINEERING MANAGEMENT

66

Solution :

A PF

C

DB

E

F

ENGINEERING MANAGEMENT

67

ENGINEERING MANAGEMENT

Lags and Leads

In some situations, an activity cannot start until a certain time after the end of its Predecessor.Lag is defined as a minimum waiting period between the finish (or start) of an activity and the start (or finish) of its successor.

Arrow networks cannot accommodate lags. The only solution in such networks is to treat it as a real activity with a real duration, no resources, and a $0 budget.

68

ENGINEERING MANAGEMENT

Examples

Place Concrete

3

Strips Forms 2

3

A lag in a node network

Place Concrete Strips Forms Cure Concrete

A lag in an arrow network

69

ENGINEERING MANAGEMENT

The term lead simply means a negative lag. It is seldom used in construction. In simple language: A positive time gap (lag) means ‘‘after’’ and a negative time gap (lead) means ‘‘before.’’

70

ENGINEERING MANAGEMENTRecommendations for Proper Node Diagram

Drawing

Incorrect Correct

71

ENGINEERING MANAGEMENT

A

B A B

A

B

A

BImproper proper

72

ENGINEERING MANAGEMENT

Improper Proper

73

ENGINEERING MANAGEMENT

Improper Proper

74

ENGINEERING MANAGEMENT

A

B

C

Improper Proper

A

B

C

PS

(a) Do not start a network with more than one node

75

ENGINEERING MANAGEMENT

A

B

C

Improper Proper

A

B

C

PF

(a) Do not end a network with more than one node

76

The Critical Path Method (CPM)

4

77

ENGINEERING MANAGEMENT

Suppose you decide with your friend to go in hunting trip .

You must do specific activity such that the trip well be at the right way. The following activity must be done .

Introduction

78

ENGINEERING MANAGEMENT

From chart you can see that the 3rd activity (preparing the jeep) have the longest period of time any delay with this activity leads to delay in the trip this activity is a “critical activity”

Critical activity : An activity on the critical path any delay on the start or finish of a critical activity will result in a delay in the entire project Critical path : The longest path in a network from start to finish

79

ENGINEERING MANAGEMENT

Steps Required To Schedule a Project

The preparation of CPM includes the following four steps:

1 -Determine the work activities:The project must be divided into smaller activities or tasks.

The activity shouldn’t be more than 14-20 days (long durations should be avoided)

Use WBS in scheduling by using an order of letters and numbers

80

ENGINEERING MANAGEMENT

2 -Determine activity duration: Duration = Total Quantity / Crew Productivity The productivity has many sources:

1 .The company 2 .The market

3 .Special books

Note: The scheduler must be aware about the non-working days , such as holydays or rain days, etc……

81

ENGINEERING MANAGEMENT

3 -Determine the logical relationships:

This step is a technical matter and obtained from the project manager and technical team, and logical relationships shouldn’t confused with constraints

4- Draw the logic network and perform the CPM calculations

82

ENGINEERING MANAGEMENT

5-Reiew and analyze the schedule:

1 .review the logic

2 .Make sure the activity has the correct predecessor

3 .make sure there is no redundant activity

83

ENGINEERING MANAGEMENT

6- Implement the schedule: Definition: take the schedule from paper to the execution.

7-Monitor and control the schedule:

Definition: comparing what we planed with what actually done.

8-Revise the database and record feedback.

9-Resource allocation and leveling.(will discuss in chapter 6)

84

ENGINEERING MANAGEMENT

ExampleDraw the logic network and perform the CPM calculations for the schedule shown next.

Duration IPA Activity 5 - A

8 A B

6 A C

9 B D

6 B,C E

3 C F

1 D,E,F G

85

ENGINEERING MANAGEMENT

In mathematical terms, the ES for activity j is as follows : ESj =max( EFi )

where (EFi) represents the EF for all preceding activities.

Likewise, the EF time for activity j is as follows :

EF j= ESj + Dur j

where Dur j is the duration of activity j

Forward pass: The process of navigating through a network from start to end and calculating the completion date for the project and the early dates for each activity

Forward pass calculations

86

ENGINEERING MANAGEMENT

A5

G1

C6

D9

B8

E6

F3

22,23

5,11

5,13

13,22

13,19

11,14

0,5

Solution :

87

ENGINEERING MANAGEMENT

In mathematical terms, the late finish LF for activity j is as follows:

(LFj =min(LSk

where (LSk) represents the late start date for all succeeding activities.

Likewise, the LS time for activity j (LS j) is as follows:

LS j= LFj - Dur j

where Dur j is the duration of activity

Backward pass: The process of navigating through a network from end to start and calculating the late dates for each activity. The late dates (along with the early dates) determine the critical activities, the critical path, and the amount of float each activity has.

Backward pass calculations

88

ENGINEERING MANAGEMENT

Solution :

A5

G1

C6

D9

B8

E6

F3

22,23

5,11

5,13

13,22

13,19

11,14

0,5

22,23

13,22

19,22

16,22

5,13

10,16

0,5

CPM ( ES = LS , EF = LF , TF = FF = 0)

89

ENGINEERING MANAGEMENTFour Types Of Floats

There are several types of float. The simplest and most important type of float is Total Float (TF) Total float (TF): The maximum amount of

time an activity can be delayed from its early start without delaying the entire project.TF = LS – ES or TF = LF - EF orTF = LF - Dur - ES

90

ENGINEERING MANAGEMENT

Free Float: may be defined as the maximum amount of time an activity can be delayed without delaying the early start of the succeeding activities

FFi = min(ESi+1) - EFi

where min (ESi+1) means the least (i.e., earliest) of the early start dates of succeeding activities

91

ENGINEERING MANAGEMENT

In the previous example we can find the free float and total float for each activity as the following :

Activity C’s free float, FF = 11 - 11 = 0 daysAnd Activity C’s total float, TF =16 - 11= 5 days …… and so on.

FF TF LF LS EF ES Duration

Activity

0 0 5 0 5 0 5 A

0 0 13 5 13 5 8 B

0 5 16 10 11 5 6 C

0 0 22 13 22 13 9 D

3 3 22 16 19 13 6 E

8 8 22 19 14 11 3 F

0 0 23 22 23 22 1 G

Critical activity Note : We must always realize that FF ≤ TF

92

ENGINEERING MANAGEMENT

Interfering float: may be defined as the maximum amount of time an activity can be delayed without delaying the entire project but causing delay to the succeeding activities.

TF = FF - Int. or Int. F = TF - FF

Independent float (Ind. F): we may define it as the maximum amount of time an activity can be delayed without delaying the early start of the succeeding activities and without being affected by the allowable delay of the preceding activities.

Ind. Fi = min(ESi +1 ) – max(LFi-1) – Duri

Note: make sure that Ind. F ≤ FF

93

ENGINEERING MANAGEMENT

Node Format

Activity Name

Activity ID

Duration

ES EF

LS LF

TF FF

94

ENGINEERING MANAGEMENT

Event Times in Arrow Networks

The early event time, TE, is the largest (latest) date obtained to reach an event (going from start to finish).

The late event time, TL, is the smallest (earliest) date obtained to reach an event (going from finish to start).Examples

Perform the CPM calculations, including the event times, for the arrow network shown below.

95

ENGINEERING MANAGEMENT

10 30

40

20 60

C

EB 50

D

F

70

A

GH

10

5

7

8

9

4

5

8

d1d2

Arrow network for example

96

ENGINEERING MANAGEMENT

The preceding logic is similar to that of the forward and backward passes: When you are going forward, pick the largest number. When you are going backward, pick the smallest number.

i jAct. NameDur.

TEi

TLi

TEj

TLj

CPM

97

ENGINEERING MANAGEMENT

10 30

40

20 60

C

EB 50

D

F

70

A

GH

10

5

7

8

9

4

5

8

d1

d2

10

10

7

0

0

15

10

10

19

19

24

2727

27

(0,10)(0,10)

(5,10)(0,5)

(0,7)(8,15)

(10,18)(11,19)

(10,19)(10,19)

(7,11)(15,19)

(19,24)

(22,27)

(19,27)(19,27)

98

ENGINEERING MANAGEMENT

Float Calculations From Event Times

Total Float

TFij = TLj - TEi - Tij

Example ( In the previous network )

TF40-50 = TL50 – TE40 – T40-50

= 19 – 7 – 4 = 8

99

ENGINEERING MANAGEMENT

Free Float

FFij = TEj - TEi – Tij

ExampleFF40-50 = TE50 – TE40 – T40-50

= 19 – 7 – 4 = 8

100

ENGINEERING MANAGEMENTInterfering Float

INTFij = TLj – TEj

ExampleINTF40-50 = TL50 – TE50

= 19 – 19 = 0

Independent Float

INDFij= TEj – TLi - Tij

ExampleINDF40-50 = TE50 – TL40 – T40-50

= 19 – 15 – 4 = 0

101

ENGINEERING MANAGEMENT

Summary

i jTTEi

TLi

TEj

TLj

Float Direction TF

FF

Int. F

Ind. F

102

ENGINEERING MANAGEMENT

Definitions Activity, or task: A basic unit of work as part of the total project that is easily measured and controlled. It is time- and resource consuming.

Backward pass: The process of navigating through a network from end to start and calculating the late dates for each activity. The late dates (along with the early dates) determine the critical activities, the critical path, and the amount of float each activity has.

Critical activity: An activity on the critical path. Any delay in the start or finish of a critical activity will result in a delay in the entire project.

Critical path: The longest path in a network, from start to finish, including lags and constraints.

.

103

ENGINEERING MANAGEMENT

Early dates: The early start date and early finish date of an activity.

Early finish (EF): The earliest date on which an activity can finish within project constraints.

Early start (ES): The earliest date on which an activity can start within project constraints.

Event: A point in time marking a start or an end of an activity. In contrast to an activity, an event does not consume time or resources.

Forward pass: The process of navigating through a network from start to end and calculating the completion date for the project and the early dates for each activity.

Late dates: The late start date and late finish date of an activity.

Late finish (LF): The latest date on which an activity can finish without extending the project duration.

Late start (LS): The latest date on which an activity can start without extending the project duration.

104

Precedence Diagram

5

105

ENGINEERING MANAGEMENT

The Four Types Relationships

Activities represented by nodes and links that allow the use of four relationships:

1) Finish to Start – FS

2) Start to Finish – SF

3) Finish to Finish – FF

4) Start to Start – SS

106

ENGINEERING MANAGEMENT

Finish to Start (FS) Relationship. The traditional relationship between

activities .

.Implies that the preceding activity must finish before the succeeding activities can start.

.Example: the plaster must be finished before the tile can start .

Plaster Tile

107

ENGINEERING MANAGEMENT

Star to Finish (SF) Relationship

.Appear illogical or irrational.

.Typically used with delay time OR LAG.

.The following examples proofs that its logical .

steelreinforcement

Erect formwork

Order concrete

SF

Pour concrete

5

108

ENGINEERING MANAGEMENT

Finish to Finish (FF) Relationship

• Both activities must finish at the same time.

• Can be used where activities can overlap to a certain limit. Erect

scaffoldingRemove Old paint

sanding

painting inspectDismantle scaffolding

FF/1

FF/2

109

ENGINEERING MANAGEMENT

Start to Start (SS) Relationship

• This method is uncommon and non exists in project construction .

Spread groutClean surface

Set tile

SS

Clean floor area

110

ENGINEERING MANAGEMENT

Advantages of using Precedence Diagram

1. No dummy activities are required.

2. A single number can be assigned to identify each activity.

3. Analytical solution is simpler.

111

ENGINEERING MANAGEMENT

Calculation

1) forward calculations

EF = ES + D

Calculate the Lag LAGAB = ESB – EFA

Calculate the Free Float

FF = Min. (LAG)

112

ENGINEERING MANAGEMENT

2) Backward calculations

For the last task LF=EF , if no information deny that.

LS=LF-D

Calculate Total Float

TF = LS – ES OR LF – EF

TFi = Min (lag ij + TFj )

Determine the Critical Path

113

ENGINEERING MANAGEMENTExample

113Dur. E

S E

F FF TF LF

LS

A1 1

2002

1

B

9 2

110011

2

D

5 11

160016

11 4 16

200020

16 1 20

210021

20

F H

C

5 5

10307

2

E

4 10

143011

7 6 14

203317

11

G

54 3

1) Forward pass calculations 4) Backward pass calculations

2) Calculate the Lag ( LAGAB = ESB – EFA)

0

0 0 0 0

0 0

3) Calculate the Free Float (FF) FF = min.( LAG)

5) Calculate total Float (TF = LS – ES OR LF – EF)

114

ENGINEERING MANAGEMENT

114Dur. E

S E

F FF TF LF

LS

A

1 1

2002

1

B

9 2

110011

2

D

5 11

160016

11 4 16

200020

16 1 20

210021

20

F H

C

5 5

10307

2

E

4 10

143011

7 6 14

203317

11

G

54 3

6) Determine the Critical Path

0

0 0 0 0

0 0

The critical path passes through the critical activities where TF = 0

115

Resource Allocation and Resource Leveling

6

116

ENGINEERING MANAGEMENT

CATEGORIES OF RESOURCES

Labor

Materials

Equipment's.

117

Schedule Updating and Project Control

7

118

Schedule Updating and Project Control The most important use of schedules is project control : the scheduler compares actual performance with baseline performance.

What is Project Control Project control comprises the following continuous process

1. monitoring work progress .

2.comparing it with the baseline schedule and budget.

3.finding any deviations .

4.taking corrective actions.

ENGINEERING MANAGEMENT

119

Schedule updating

Schedule updating is just one part of the project control process.

Schedule updating must reflect

Actual work , and involves change orders (CO) .

ENGINEERING MANAGEMENT