Construction Engineering and Management Instructor: Dr. Ayham Jaaron.
-
Upload
cleopatra-freeman -
Category
Documents
-
view
229 -
download
5
Transcript of Construction Engineering and Management Instructor: Dr. Ayham Jaaron.
ENGINEERING MANAGEMENT
2
Class Rules and Instructor Expectations
•Turn off your cell phone before you get inside the class room.•Be on time and respect deadlines; late homework will not be accepted! •Participate and attend class: be ready and prepare well, that is the key to success! •Quizzes and exams will be closed-book. •Avoid Make-up/incomplete exams!
ENGINEERING MANAGEMENT
3
Topics1) Management Functions and introduction of construction project planning and scheduling2)Construction scheduling techniques3)Preparation and usage of bar charts4)Preparation and usage of the Critical Path Method (CPM)5)Preparation and usage of Precedence Diagramming Method (PDM)6)Issues relating to determination of activity duration7)Contractual provisions relating to project schedules8)Resource leveling and constraining9)Time cost tradeoff10)Schedule monitoring and updating.11)Communicating schedule12) Project control and earned value Control13) claims, Safety and Quality control
ENGINEERING MANAGEMENT
4
In order to understand project management, one must begin with the definition of a project. A project can be considered to be any series of activities and tasks that :.
● Have a specific objective to be completed within certain specifications
● Have defined start and end dates
● Have funding limits
● Consume human and nonhuman resources (i.e., money, people, equipment)
● Are multifunctional (i.e., cut across several functional lines)
What is the Project
ENGINEERING MANAGEMENT
5
OR
‘‘a temporary endeavor undertaken to create a unique product, service, or result’’
ENGINEERING MANAGEMENT
7
Five Process group
Project initiation ●Selection of the best project
given resource limits ●Recognizing the benefits of
the project ●Preparation of the documents
to sanction the project ●Assigning of the project
manager
Project planning ●Definition of the work
requirements ●Definition of the quality and
quantity of work ●Definition of the resources
needed ●Scheduling the activities
●Evaluation of the various risks
Project execution ●Negotiating for the
project team members ●Directing and managing
the work ●Working with the team
members to help them improve
Project monitoring and control
●Tracking progress ●Comparing actual outcome
to predicted outcome ●Analyzing variances and
impacts ●Making adjustments
Project closure ●Verifying that all of the work
has been accomplished ●Contractual closure of the
contract ●Financial closure of the charge
numbers ●Administrative closure of the
paper work
ENGINEERING MANAGEMENT
9
Successful project management can then be defined as having achieved the project objectives:
● Within Time
● Within Cost
● At the desired performance/Technology level
● While utilizing the assigned resources effectively and efficiently
● Accepted by the customer
ENGINEERING MANAGEMENT
10
What is Project Management Project management is the planning, organizing,
directing, and controlling of company resources for a relatively short-term objective that has been established to complete specific goals and objectives.
ENGINEERING MANAGEMENT
11
The potential benefits from project management are:
● Identification of functional responsibilities
● Minimizing the need for continuous reporting
● Identification of time limits for scheduling
● Identification of a methodology for trade-off analysis.
● Measurement of accomplishment against plans
ENGINEERING MANAGEMENT
12
The above definition requires further comment. Classical management is usually considered to have five functions or principles:
● Planning
● Organizing
● Staffing
● Controlling
● Directing
ENGINEERING MANAGEMENT
13
Planning
– Where the organization wants to be in the future and how to get there.
Organizing
– Follows planning and reflects how theorganization tries to accomplish the plan.
– Involves the assignment of tasks, grouping oftasks into departments, and allocation of resources.
ENGINEERING MANAGEMENT
14
Leading
– The use of influence to motivate employees toachieve the organization's goals.
– Creating a shared culture and values,communicating goals to employees throughoutthe organization, and infusing employees toperform at a high level.Controlling
– Monitoring employees' activities, determining if the organization is on target toward its goals, and making corrections as necessary
ENGINEERING MANAGEMENT
15
Conceptual Skill—the ability to see the organization as a whole and the relationship between its parts.
Human Skill—The ability to work with and through people.
Technical Skill—Mastery of specific functions and specialized knowledge
Management Skills
ENGINEERING MANAGEMENT
16
Project management is designed to manage or control company resources on a given activity, within time, within cost, and within performance. Time, cost, and performance are the constraints on the project.
Constraints of the project
ENGINEERING MANAGEMENT
17
Resources We have stated that the project manager must control company resources within time, cost, and performance. Most companies have six resources:
● Money
● Manpower
● Equipment
● Facilities
● Materials
● Information/technology
ENGINEERING MANAGEMENT
18
Actually, the project manager does not control any of these resources directly, except perhaps money (i.e., the project budget).
Resources are controlled by the line managers .
The project manager is responsible for coordinating and integrating activities across multiple, functional lines. The integration activities performed by the project manager include:
ENGINEERING MANAGEMENT
19
● Integrating the activities necessary to develop a project plan
● Integrating the activities necessary to execute the plan
● Integrating the activities necessary to make changes to the plan
ENGINEERING MANAGEMENT
21
Planning and Scheduling
Planning and scheduling are two terms that are often thought of as synonymous
They are not!
Scheduling is just one part of the planning effort.
ENGINEERING MANAGEMENT
22
Project planning serves as a foundation for several
related functions such as cost estimating, scheduling,and project control.
Project scheduling is the determination of the timing and sequence of operations in the project and their assembly to give the overall completion time
ENGINEERING MANAGEMENT
23
Planning is the process of determining how a project will be undertaken. It answers the questions:
1“ .What” is going to be done,2“ .how,”
3“ .where,”4 .By “whom”, and
5“ .when” (in general terms: start and finish).
Scheduling deals with “when” on a detailed level… See Figure 1 .
ENGINEERING MANAGEMENT
24
The Plan
WhatHow much
By whom
where
Why
How
when
Figure 1 . Planning and Scheduling
ENGINEERING MANAGEMENT
25
The PlanPMI defines project management plan as a ‘‘formal, approved document that defines how the project is executed, monitored and controlled”.
The plan can include elements that has to do with scope, design and alternate designs, cost, time, finance, land, procurement, operations, etc.
ENGINEERING MANAGEMENT
26
WHY SCHEDUALE PROJECTS ?
1 -To calculate the project completion.
2 -To calculate the start or end of a specific activity.
3-To expose and adjust conflict between trades
or subcontractor.
4 -To predict and calculate the cash flow.
5-To evaluate the effect of changing orders ‘CH . ’
ENGINEERING MANAGEMENT
27
6 -To improve work efficiency.
7 -To resolve delay claims , this is important in critical path method ‘CPM’ discussed later..
8 -To serve as an effective project control tool.
ENGINEERING MANAGEMENT
28
The Tripod of Good Scheduling System1.The Human Factor : A proficient scheduler
or scheduling team.
2. The Technology : A good scheduling computer system (software and hardware)
3. The Management : A dynamic, responsive, and supportive management.
If anyone of the above three ‘‘legs’’ is missing, the system will fail.
ENGINEERING MANAGEMENT
29
Scheduling and project management Planning, scheduling, and project control are extremely important components of project management.project management includes other components :• cost estimating and management,
• procurement,
• project/contract administration,
• quality management,
• and safety management.
These components are all interrelated in different ways.
ENGINEERING MANAGEMENT
31
DEFINITION AND INTRODUCTION• A bar chart is ‘‘a graphic representation of
project activities, shown in a time-scaled bar line with no links shown between activities’’
The bar may not indicate continuous work from the start of the activity until its end.
or
Non continuous (dashed) bars are sometimes used to distinguish between real work (solid line) and inactive periods (gaps between solid lines)
ENGINEERING MANAGEMENT
32
• Before a bar chart can be constructed for a project, the project must be broken into smaller, usually homogeneous components, each of which is called an activity, or a task.
Item ActivityM 10 Mobilization
Bars ( Month or Year )
ENGINEERING MANAGEMENT
33
ADVANTAGES OF BAR CHARTS
1- Time-scaled
2- Simple to prepare
3- Can be more effective and efficient if CPM based - Still the most popular method
4- Bars can be dashed to indicate work stoppage.
5- Can be loaded with other information (budget, man hours, resources, etc.)
ENGINEERING MANAGEMENT
34
Bar Charts Loaded with More Info.Such as : budget, man hours and resources .
10 12 7 11 10 9 15
500$
220$
400$
850$
140$ 500$
900$
ENGINEERING MANAGEMENT
35
DISADVANTAGES OF BAR CHARTS
1- Does not show logic
2- Not practical for projects with too many activities- As a remedy, we can use bar charts to show:
1. A small group of the activities (subset)
2. Summary schedules
ENGINEERING MANAGEMENT
37
DEFINITION AND INTRODUCTION
• A network is a logical and chronological graphic representation of the activities (and events) composing a project.
• Network diagrams are the preferred technique for showing activity sequencing.
• Two main formats are the arrow and precedence diagramming methods.
ENGINEERING MANAGEMENT
38
Two classic formatsAOA: Activity on ArrowAON: Activity on Node
Each task labeled withIdentifier (usually a letter/code)Duration (in std. unit like days)
There are other variations of labeling
There is 1 start & 1 end event
Time goes from left to right
ENGINEERING MANAGEMENT
39
Arrow Diagramming Method (ADM)
1 .Also called activity-on-arrow (AOA) network diagram or (I-J) method (because activities are defined by the form node, I, and the to node, J)
2 .Activities are represented by arrows.
3 .Nodes or circles are the starting and ending points of activities.
4 .Can only show finish-to-start dependencies.
ENGINEERING MANAGEMENT
40
i j
(a) Basic Activity
Activity Name
Node (Event) i
j > i
Each activity should have a unique i – j value
Node (Event) j
Basic Logic Patterns for Arrow Diagrams
ENGINEERING MANAGEMENT
41
2 A
(b) Independent Activities
4 10 B 12
3 A 6 B 9
(c) Dependent Activities
ENGINEERING MANAGEMENT
42
2
A
(d) A Merge
4
6B 8
(e) A Burst
C
Activity C depends upon the completion of both Activities A & B
8
A6
2B
4C
Activities B and C both depend upon the completion of Activity A
ENGINEERING MANAGEMENT
43
(f) A Cross
20
18C
16 D14
A12
B
Activities C and D both depend upon the completion of Activities A and B
ENGINEERING MANAGEMENT
44
ExampleDraw the arrow network for the project given next.
IPA Activity - A
A B
A C
B D
C,D E
ENGINEERING MANAGEMENT
46
Dummy activity (fictitious)
* Used to maintain unique numbering of activities.
* Used to complete logic, duration of “0” *The use of dummy to maintain unique
numbering of activities .
ENGINEERING MANAGEMENT
47
4 10
4 10
11
A
B
A
B
Divide node to correct
Dummy
(a) Incorrect Representation
(b) Correct Representation
ENGINEERING MANAGEMENT
48
ExampleDraw the arrow network for the project given next.
IPA Activity - A
A B
A C
B,C D
ENGINEERING MANAGEMENT
49
10 3020 40
C
DA
B
Solution :
10
30
4020 50
C
DA
BDummy
Improper solution
proper solution
ENGINEERING MANAGEMENT
505050
ExampleDraw the arrow network for the project given next.
IPA Activity - A
A B
A C
B D
B,C E
C F
ENGINEERING MANAGEMENT
52
Removal of Redundant Dummies
A
A
A
A
B
B
B
B
C C
Original Diagram Diagram after removal of redundant dummies
(a)
(b)
ENGINEERING MANAGEMENT
53
A
A
A
A
C
C
B
C
B B
Original Diagram Diagram after removal of redundant dummies(c)
(d)
B E
C
E
E E
ENGINEERING MANAGEMENT
54
Immediately Preceding Activity (IPA)
Depends Upon Activity
-----AB
-----A
A, B
ABC
B CA
Redundant
Relationship
ENGINEERING MANAGEMENT
55
Activity List with Dependencies:
Depends Upon Description Activity
----------A
A, B, CA, B, C
B, C, J, MB, C, D, E, KD, E, F, G, L
--------------------
Site ClearingRemoval of TreesExcavation for FoundationsSite GradingExcavation for Utility TrenchesPlacing formwork & ReinforcementInstalling sewer linesPouring concreteObtain formwork & reinforcing steelObtain sewer linesObtain concreteSteelworker availability
ABCDEFGHJKLM
ENGINEERING MANAGEMENT
56
Depends Upon Description Activity
----------A
A, B, CA, B, C
B, C, J, MB, C, D, E, KD, E, F, G, L
--------------------
Site ClearingRemoval of TreesExcavation for FoundationsSite GradingExcavation for Utility TrenchesPlacing formwork & ReinforcementInstalling sewer linesPouring concreteObtain formwork & reinforcing steelObtain sewer linesObtain concreteSteelworker availability
ABCDEFGHJKLM
Removing Redundant Relationships:
ENGINEERING MANAGEMENT
57
AOA Representation
H4040
G4545
C
F
D3535
1515
1010
55B
A
2020
M
2525J
3030
E
L
K
ENGINEERING MANAGEMENT
58
NODE NETWORKS MTHOD (AON)
a) Independent Activities
10A
10A
20B
20B
Activity number
Activity name
b) Dependent Activities
20B
20B
10A
10A
Link
LinkB depends on A
ENGINEERING MANAGEMENT
59
30C
30C
10A
10A
20B
20B
40 D40 D
c) A Merge Relationship
C depends on A & BD depends on C
d) A Burst Relationship
20B
20B
30C
30C
40D
40D
10 A10 A
B depends on AC depends on BD depends on B
ENGINEERING MANAGEMENT
60
e) Start & Finish Dummy Activities
AA
CC
BB
EE
DDAA
StartDummyStart
DummyFinish
DummyFinish
Dummy
CC
BB
EE
DD
6161
ExampleDraw the arrow network for the project given next.
IPA Activity - A
A B
A C
B D
C,D E
ENGINEERING MANAGEMENT
6363
ExampleDraw the arrow network for the project given next.
IPA Activity - A
A B
A C
B,C D
ENGINEERING MANAGEMENT
65656565
ExampleDraw the arrow network for the project given next.
IPA Activity - A
A B
A C
B D
B,C E
C F
ENGINEERING MANAGEMENT
67
ENGINEERING MANAGEMENT
Lags and Leads
In some situations, an activity cannot start until a certain time after the end of its Predecessor.Lag is defined as a minimum waiting period between the finish (or start) of an activity and the start (or finish) of its successor.
Arrow networks cannot accommodate lags. The only solution in such networks is to treat it as a real activity with a real duration, no resources, and a $0 budget.
68
ENGINEERING MANAGEMENT
Examples
Place Concrete
3
Strips Forms 2
3
A lag in a node network
Place Concrete Strips Forms Cure Concrete
A lag in an arrow network
69
ENGINEERING MANAGEMENT
The term lead simply means a negative lag. It is seldom used in construction. In simple language: A positive time gap (lag) means ‘‘after’’ and a negative time gap (lead) means ‘‘before.’’
74
ENGINEERING MANAGEMENT
A
B
C
Improper Proper
A
B
C
PS
(a) Do not start a network with more than one node
75
ENGINEERING MANAGEMENT
A
B
C
Improper Proper
A
B
C
PF
(a) Do not end a network with more than one node
77
ENGINEERING MANAGEMENT
Suppose you decide with your friend to go in hunting trip .
You must do specific activity such that the trip well be at the right way. The following activity must be done .
Introduction
78
ENGINEERING MANAGEMENT
From chart you can see that the 3rd activity (preparing the jeep) have the longest period of time any delay with this activity leads to delay in the trip this activity is a “critical activity”
Critical activity : An activity on the critical path any delay on the start or finish of a critical activity will result in a delay in the entire project Critical path : The longest path in a network from start to finish
79
ENGINEERING MANAGEMENT
Steps Required To Schedule a Project
The preparation of CPM includes the following four steps:
1 -Determine the work activities:The project must be divided into smaller activities or tasks.
The activity shouldn’t be more than 14-20 days (long durations should be avoided)
Use WBS in scheduling by using an order of letters and numbers
80
ENGINEERING MANAGEMENT
2 -Determine activity duration: Duration = Total Quantity / Crew Productivity The productivity has many sources:
1 .The company 2 .The market
3 .Special books
Note: The scheduler must be aware about the non-working days , such as holydays or rain days, etc……
81
ENGINEERING MANAGEMENT
3 -Determine the logical relationships:
This step is a technical matter and obtained from the project manager and technical team, and logical relationships shouldn’t confused with constraints
4- Draw the logic network and perform the CPM calculations
82
ENGINEERING MANAGEMENT
5-Reiew and analyze the schedule:
1 .review the logic
2 .Make sure the activity has the correct predecessor
3 .make sure there is no redundant activity
83
ENGINEERING MANAGEMENT
6- Implement the schedule: Definition: take the schedule from paper to the execution.
7-Monitor and control the schedule:
Definition: comparing what we planed with what actually done.
8-Revise the database and record feedback.
9-Resource allocation and leveling.(will discuss in chapter 6)
84
ENGINEERING MANAGEMENT
ExampleDraw the logic network and perform the CPM calculations for the schedule shown next.
Duration IPA Activity 5 - A
8 A B
6 A C
9 B D
6 B,C E
3 C F
1 D,E,F G
85
ENGINEERING MANAGEMENT
In mathematical terms, the ES for activity j is as follows : ESj =max( EFi )
where (EFi) represents the EF for all preceding activities.
Likewise, the EF time for activity j is as follows :
EF j= ESj + Dur j
where Dur j is the duration of activity j
Forward pass: The process of navigating through a network from start to end and calculating the completion date for the project and the early dates for each activity
Forward pass calculations
87
ENGINEERING MANAGEMENT
In mathematical terms, the late finish LF for activity j is as follows:
(LFj =min(LSk
where (LSk) represents the late start date for all succeeding activities.
Likewise, the LS time for activity j (LS j) is as follows:
LS j= LFj - Dur j
where Dur j is the duration of activity
Backward pass: The process of navigating through a network from end to start and calculating the late dates for each activity. The late dates (along with the early dates) determine the critical activities, the critical path, and the amount of float each activity has.
Backward pass calculations
88
ENGINEERING MANAGEMENT
Solution :
A5
G1
C6
D9
B8
E6
F3
22,23
5,11
5,13
13,22
13,19
11,14
0,5
22,23
13,22
19,22
16,22
5,13
10,16
0,5
CPM ( ES = LS , EF = LF , TF = FF = 0)
89
ENGINEERING MANAGEMENTFour Types Of Floats
There are several types of float. The simplest and most important type of float is Total Float (TF) Total float (TF): The maximum amount of
time an activity can be delayed from its early start without delaying the entire project.TF = LS – ES or TF = LF - EF orTF = LF - Dur - ES
90
ENGINEERING MANAGEMENT
Free Float: may be defined as the maximum amount of time an activity can be delayed without delaying the early start of the succeeding activities
FFi = min(ESi+1) - EFi
where min (ESi+1) means the least (i.e., earliest) of the early start dates of succeeding activities
91
ENGINEERING MANAGEMENT
In the previous example we can find the free float and total float for each activity as the following :
Activity C’s free float, FF = 11 - 11 = 0 daysAnd Activity C’s total float, TF =16 - 11= 5 days …… and so on.
FF TF LF LS EF ES Duration
Activity
0 0 5 0 5 0 5 A
0 0 13 5 13 5 8 B
0 5 16 10 11 5 6 C
0 0 22 13 22 13 9 D
3 3 22 16 19 13 6 E
8 8 22 19 14 11 3 F
0 0 23 22 23 22 1 G
Critical activity Note : We must always realize that FF ≤ TF
92
ENGINEERING MANAGEMENT
Interfering float: may be defined as the maximum amount of time an activity can be delayed without delaying the entire project but causing delay to the succeeding activities.
TF = FF - Int. or Int. F = TF - FF
Independent float (Ind. F): we may define it as the maximum amount of time an activity can be delayed without delaying the early start of the succeeding activities and without being affected by the allowable delay of the preceding activities.
Ind. Fi = min(ESi +1 ) – max(LFi-1) – Duri
Note: make sure that Ind. F ≤ FF
94
ENGINEERING MANAGEMENT
Event Times in Arrow Networks
The early event time, TE, is the largest (latest) date obtained to reach an event (going from start to finish).
The late event time, TL, is the smallest (earliest) date obtained to reach an event (going from finish to start).Examples
Perform the CPM calculations, including the event times, for the arrow network shown below.
95
ENGINEERING MANAGEMENT
10 30
40
20 60
C
EB 50
D
F
70
A
GH
10
5
7
8
9
4
5
8
d1d2
Arrow network for example
96
ENGINEERING MANAGEMENT
The preceding logic is similar to that of the forward and backward passes: When you are going forward, pick the largest number. When you are going backward, pick the smallest number.
i jAct. NameDur.
TEi
TLi
TEj
TLj
CPM
97
ENGINEERING MANAGEMENT
10 30
40
20 60
C
EB 50
D
F
70
A
GH
10
5
7
8
9
4
5
8
d1
d2
10
10
7
0
0
15
10
10
19
19
24
2727
27
(0,10)(0,10)
(5,10)(0,5)
(0,7)(8,15)
(10,18)(11,19)
(10,19)(10,19)
(7,11)(15,19)
(19,24)
(22,27)
(19,27)(19,27)
98
ENGINEERING MANAGEMENT
Float Calculations From Event Times
Total Float
TFij = TLj - TEi - Tij
Example ( In the previous network )
TF40-50 = TL50 – TE40 – T40-50
= 19 – 7 – 4 = 8
99
ENGINEERING MANAGEMENT
Free Float
FFij = TEj - TEi – Tij
ExampleFF40-50 = TE50 – TE40 – T40-50
= 19 – 7 – 4 = 8
100
ENGINEERING MANAGEMENTInterfering Float
INTFij = TLj – TEj
ExampleINTF40-50 = TL50 – TE50
= 19 – 19 = 0
Independent Float
INDFij= TEj – TLi - Tij
ExampleINDF40-50 = TE50 – TL40 – T40-50
= 19 – 15 – 4 = 0
102
ENGINEERING MANAGEMENT
Definitions Activity, or task: A basic unit of work as part of the total project that is easily measured and controlled. It is time- and resource consuming.
Backward pass: The process of navigating through a network from end to start and calculating the late dates for each activity. The late dates (along with the early dates) determine the critical activities, the critical path, and the amount of float each activity has.
Critical activity: An activity on the critical path. Any delay in the start or finish of a critical activity will result in a delay in the entire project.
Critical path: The longest path in a network, from start to finish, including lags and constraints.
.
103
ENGINEERING MANAGEMENT
Early dates: The early start date and early finish date of an activity.
Early finish (EF): The earliest date on which an activity can finish within project constraints.
Early start (ES): The earliest date on which an activity can start within project constraints.
Event: A point in time marking a start or an end of an activity. In contrast to an activity, an event does not consume time or resources.
Forward pass: The process of navigating through a network from start to end and calculating the completion date for the project and the early dates for each activity.
Late dates: The late start date and late finish date of an activity.
Late finish (LF): The latest date on which an activity can finish without extending the project duration.
Late start (LS): The latest date on which an activity can start without extending the project duration.
105
ENGINEERING MANAGEMENT
The Four Types Relationships
Activities represented by nodes and links that allow the use of four relationships:
1) Finish to Start – FS
2) Start to Finish – SF
3) Finish to Finish – FF
4) Start to Start – SS
106
ENGINEERING MANAGEMENT
Finish to Start (FS) Relationship. The traditional relationship between
activities .
.Implies that the preceding activity must finish before the succeeding activities can start.
.Example: the plaster must be finished before the tile can start .
Plaster Tile
107
ENGINEERING MANAGEMENT
Star to Finish (SF) Relationship
.Appear illogical or irrational.
.Typically used with delay time OR LAG.
.The following examples proofs that its logical .
steelreinforcement
Erect formwork
Order concrete
SF
Pour concrete
5
108
ENGINEERING MANAGEMENT
Finish to Finish (FF) Relationship
• Both activities must finish at the same time.
• Can be used where activities can overlap to a certain limit. Erect
scaffoldingRemove Old paint
sanding
painting inspectDismantle scaffolding
FF/1
FF/2
109
ENGINEERING MANAGEMENT
Start to Start (SS) Relationship
• This method is uncommon and non exists in project construction .
Spread groutClean surface
Set tile
SS
Clean floor area
110
ENGINEERING MANAGEMENT
Advantages of using Precedence Diagram
1. No dummy activities are required.
2. A single number can be assigned to identify each activity.
3. Analytical solution is simpler.
111
ENGINEERING MANAGEMENT
Calculation
1) forward calculations
EF = ES + D
Calculate the Lag LAGAB = ESB – EFA
Calculate the Free Float
FF = Min. (LAG)
112
ENGINEERING MANAGEMENT
2) Backward calculations
For the last task LF=EF , if no information deny that.
LS=LF-D
Calculate Total Float
TF = LS – ES OR LF – EF
TFi = Min (lag ij + TFj )
Determine the Critical Path
113
ENGINEERING MANAGEMENTExample
113Dur. E
S E
F FF TF LF
LS
A1 1
2002
1
B
9 2
110011
2
D
5 11
160016
11 4 16
200020
16 1 20
210021
20
F H
C
5 5
10307
2
E
4 10
143011
7 6 14
203317
11
G
54 3
1) Forward pass calculations 4) Backward pass calculations
2) Calculate the Lag ( LAGAB = ESB – EFA)
0
0 0 0 0
0 0
3) Calculate the Free Float (FF) FF = min.( LAG)
5) Calculate total Float (TF = LS – ES OR LF – EF)
114
ENGINEERING MANAGEMENT
114Dur. E
S E
F FF TF LF
LS
A
1 1
2002
1
B
9 2
110011
2
D
5 11
160016
11 4 16
200020
16 1 20
210021
20
F H
C
5 5
10307
2
E
4 10
143011
7 6 14
203317
11
G
54 3
6) Determine the Critical Path
0
0 0 0 0
0 0
The critical path passes through the critical activities where TF = 0
118
Schedule Updating and Project Control The most important use of schedules is project control : the scheduler compares actual performance with baseline performance.
What is Project Control Project control comprises the following continuous process
1. monitoring work progress .
2.comparing it with the baseline schedule and budget.
3.finding any deviations .
4.taking corrective actions.
ENGINEERING MANAGEMENT