Construction & Demolition Recycling Seminar
Illinois Recycling Association
April 13, 2011 Champaign Illinois
Illinois Environmental Protection Agency
• PAUL PURSEGLOVE – Manager• Field Operation Section – Bureau of Land• 217/524-5597• [email protected]
The Mission of the Bureau of Land
• Ensure that hazardous and non-hazardous
wastes are managed in an environmentally sound manner;
• Encourage the recycling and recovery of waste materials through suitable incentive/disincentive efforts;
• Provide remedial responses and/or provide oversight to the uncontrolled releases of hazardous and petroleum substances into the environment.
SAFE
WASTE
MANAGEMENT
Illinois EPA’s Objective
COMPLIANCE
Waste … discarded materialSec 3.53 (1986)
Municipal Waste …. “means garbage, general household and commercial waste, landscape waste….and CONSTRUCTION OR DEMOLITION DEBRIS
Section 3.290 (1986)
MANAGEMENT OF GENERAL C&D DEBRIS
ILLINOIS ENVIRONMENTAL PROTECTION ACT
• Prohibitions of the “Act”
–NO open dumping of C&D waste
–NO open burning of C&D waste
MANAGEMENT OF GENERAL C&D DEBRIS
• Landfill• Transfer Station• C&D Transfer, Storage or Treatment Facility
(operated pursuant to 22.38 of the Act)• Recycling Center (not regulated by IEPA)
C&D Recycling
415 ILCS 5/22.38
Facilities accepting exclusively C&D for Transportation, Storage or Treatment
22.38 sites must comply with local Zoning
In the absence of zoning – 1300 ft. from a residence
Operating Requirements
• Within 48 hours sort/separate material that can be recycled from the waste that must be disposed
• Within 72 hours transport off site all non-recyclable wastes
• Limit non-recyclables to 25% -- wood recovered for the secondary fuel market counts toward the 75%
Operating Requirements
• Non-putrescibles can accumulate for 6 months• Putrescibles items must move off site in 45
days• Keep Records to demonstrate compliance and
identify the generator and transporter• CONTROL – odors, noise, vectors, dust, litter,
access • Take precautions against fire
Operating Requirements
• Storm water runoff must be controlled• Leachate properly managed• ASBESTOS – comply with all applicable laws• NOTIFY – the Illinois EPA• If operations commence after 8-24-2009 you
must obtain and Illinois EPA issued permit prior to commencing operations [ILCS 5/21(d)]
Local Siting Requirements
• ILCS 5/3.330 Pollution Control FacilityDefinition -- Any waste storage site, waste transfer
station, waste treatment facility
• ILCS 5/39.2 The county Board or governing body shall approve
or disapprove requests for local siting for each pollution control facility
ILCS 5/22.15 Solid Waste Management Fund
• $2.00/ton collected at the landfill• A unit of local government can collect
$1.27/ton• However ILCS 5/22.15(k) exempts the SWMF
fees from recyclers (22.38 sites) provided 50% of the waste received is reusable
• Processors must have written approval from the Illinois EPA
ILCS 5/22.44 Subtitle D Management Fund
• $0.22/ton collected at the landfill• However ILCS 5/22.44(c) exempts the SDMF
fees from recyclers (22.38 sites) provided 50% of the waste received is reusable
• Processors must have written approval from the Illinois EPA
Management of CCDD
• Section 3.160 of the Act(2005 & 2007 amendments)
• Uncontaminated concrete with protruding rebar and reclaimed asphalt pavement is NOT “waste” if separated or processed and returned to the economic mainstream within 4 years
• 25% removed each year
QUESTIONS