Construction Contracts Docuements 06092008

48
CONSTRUCTION CONTRACTS CONSTRUCTION CONTRACTS DOCUEMENTS DOCUEMENTS APPLIED CIVIL ENGINEERING DEPT APPLIED CIVIL ENGINEERING DEPT BY LECTURER Maha Muhaisen

description

CPM

Transcript of Construction Contracts Docuements 06092008

Page 1: Construction Contracts Docuements 06092008

CONSTRUCTION CONTRACTS CONSTRUCTION CONTRACTS DOCUEMENTSDOCUEMENTS

APPLIED CIVIL ENGINEERING DEPTAPPLIED CIVIL ENGINEERING DEPT

BY

LECTURER

Maha Muhaisen

Page 2: Construction Contracts Docuements 06092008

ResourcesResources

p Construction Documents and Contracting, Joseph D. Coleman , 2004, Prentice Hall

p Construction Contracts, Keith Collier, 1987, Prentice Hall

p “Construction Management”, by Daniel W. Halpin and Ronald W. Woodhead, 2nd Edition , John Wiley & Sons

p Fidic Conditions of Contract for Construction, FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE EMPLOYER, 2005

p Fidic Tendering Procedures, prequalification, tendering and award the contract, 1994.

p Handouts and lecture notes

Page 3: Construction Contracts Docuements 06092008

Grades

Ø Research Projects & homework 30 %

Ø Midterm Exam. 30%

Ø Final Exam. 40%

Page 4: Construction Contracts Docuements 06092008

Course OutlineCourse Outline

1. Introduction to construction project stages, overview of the construction contracting methods, and contracts types.

2. Bidding document

n Invitation to bid

n Instruction to bidders

n Information to bidders & bid data

n Biding Forms

n General conditions of contract

n Specific condition of contract

n Specification

n BOQ

n Drawings

n Contract forms

3. Methods of Tendering, Bidding and Awarding

4. Contract Documents and Conditions

5. FIDIC Form of Contracts

Page 5: Construction Contracts Docuements 06092008

Introduction to Construction Project Stages

Lecture (1)

Page 6: Construction Contracts Docuements 06092008

Major Project PhasesMajor Project Phases

p The major phases in the project cycle that are common to most design and construction projects are :

Project Planning

Design

Schematic Design

Design Development

Contract Documents

Construction Procurement (Bidding Phase)

Construction

Post Construction

Page 7: Construction Contracts Docuements 06092008

Construction Project CharacteristicsConstruction Project Characteristics

Construction projects are different than other types of projects due to the following characteristics;

v Construction projects are complex undertaking.

v Every construction project is unique.

v Construction projects involve a lot of uncertainties, lack of information and variables.

Page 8: Construction Contracts Docuements 06092008

Project Life Cycle

Most of Construction projects life-cycle have common characteristics, Construction projects start with low cost and resources, high risk and uncertainty.

The life-cycle of a typical construction project could be summarized as following :

üStage I : represents the project formulation, feasibility studies, and the strategic decisions needed for project continue.

ü Stage II : represents planning, basic design, budgeting, tendering and placing the project major contracts.

üStage III : involves the construction phase of the project, equipment installation and testing.

üStage IV : represents the final phase in the project which includes the project turnover, final testing and start-up.

Page 9: Construction Contracts Docuements 06092008

Project Life Cycle

Page 10: Construction Contracts Docuements 06092008

Per

cent

Com

plet

e

Stage IStage II Stage III Stage IV

Project "GO"

Decision

Major Contracts

Let

Installation Substantially

Complete

Full

Operations

F easability

- Pro ject Formulation

- Feasabiltiy Studies

- Strategies Design &

Approval

P lanning & D esign

- Base Design

- Cost & Schedule

- Contract Terms &

Conditions.

- Detailed Planning

T urno ver

& Start Up

- Final Testing

- M aintenance

C o nstruct io n

- M anufacturing

- Delivery

- Civil Work

- Installation

- Testing

Figure 1.1 : Construction Projects Life-Cycle (Ref: PMBK, 2000)

Page 11: Construction Contracts Docuements 06092008

Construction Contracting Method Construction Contracting Method (delivery methods)(delivery methods)

Traditional Approach (D-B-B):

The most common delivery system is called “the traditional or standard approach” or “design-bid-build”, in which the employer assigns the design and construction phases to two different firms (consultant/designer and contractor).

ConstructingDesigning

Appointing Consultant

Appointing Main Contractor

Page 12: Construction Contracts Docuements 06092008

Traditional Approach (D-B-B):

v For many years, DBB has been the most common method of project delivery for public projects, and for many private projects as well.

v Design Bid-Build is effective on projects

n where the owner needs both professional design services and construction services

n where the designer does not require detailed knowledge of the means and methods of construction.

v DBB provides the owner with a high degree of control. That’s why it is the preferred project delivery system for owners who:

Page 13: Construction Contracts Docuements 06092008

B):B):--BB--Traditional Approach (DTraditional Approach (D

Ø The owner defines project goals and objectives, secures the financing, and specifies the standards and contract terms.

Ø The owner may perform planning, conceptual design and full design, or may engage an outside design professional (designer) for some or all of these tasks.

Ø During this planning and preliminary stage, owner and designer work as a team to obtain required permits and conduct necessary site investigations.

Ø The designer prepares the construction bid documents to reflect the owner’s project goals and objectives, the project’s site conditions, and sound engineering practices.

Ø Prospective contractors prepare their bids from these complete and specific bid documents.

Ø The bidders submit their proposals to the owner, who determines the most responsive (typically the lowest) bid meeting project requirements.

Ø In certain circumstances, owner may be justified in selecting a contractor outright and negotiating contract terms directly.

Page 14: Construction Contracts Docuements 06092008

Advantages of DAdvantages of D--BB--B ApproachB Approach

x Applicable to a wide range of projects.

x Well established and easily understood.

x Clearly defined roles for all parties.

x Provides the lowest initial price that competitive bidders can offer.

x Extensive litigation has resulted in well established legal precedents.

x Insurance and bonding are well defined.

Page 15: Construction Contracts Docuements 06092008

B ApproachB Approach--BB--Disadvantages of DDisadvantages of D

ü Least-cost approach requires higher level of inspection.

ü Initial low bid might not result in ultimate lowest cost or final best value.

ü Designers may have limited knowledge of the true cost and scheduling implication of design decisions.

Page 16: Construction Contracts Docuements 06092008

Build ApproachBuild Approach--DesignDesign

Design-build approach is a project delivery system involving a single contract between the project employer and a design-build contractor covering both the design and construction of a project.

The design-builder performs design, construction engineering, and construction according to design parameters, performance criteria and other requirements

established by the employer or his representative.

ConstructingDesigning

Appointing design & construction contractor

Tendering

Page 17: Construction Contracts Docuements 06092008

DesignDesign--Build ApproachBuild Approach

§ The owner contracts with a single entity to provide the design and to construct the project according to that design.

§ The contract might be negotiated with a single design-builder or result from competitive proposals.

§ The selection can be based on low price or on a set of value criteria (experience, staff, bonding capacity, etc.).

§ Design-build provides the owner with a single point of contact for project responsibilities, eliminating the need to assist in resolving designer-contractor disputes.

§ With the contractor playing a major role in design, costs are typically defined and maintained to a greater degree, and the coordination of fast-track management to achieve early completion is greatly simplified.

§ The design-builder makes many decisions that owner would make under DBB, due to delegation of greatly increased authority.

Page 18: Construction Contracts Docuements 06092008

DesignDesign--Build ApproachBuild Approach

p For many owners, delegation of responsibilities leads to satisfactory projects. However, if the parties are inexperienced and do not cooperate, the transfer of control and risk can be disappointing.

p The owner may need to restructure his/her internal procedures to accommodate design-build approach.

p Compared to DBB, this involves a significantly different set of requirements and expectations for process, timelines and communications.

p A clear understanding and documentation of design-build processes enhances the quality of design-build projects

Page 19: Construction Contracts Docuements 06092008

Advantage of DesignAdvantage of Design--Build ApproachBuild Approach

pInnovation and quality improvements through:

- Alternative designs and construction methods

suited to the contractor’s capabilities

- Flexibility in the selection of design, materials, and

construction methods.

• Earlier schedule and cost certainty

Page 20: Construction Contracts Docuements 06092008

Disadvantage of DesignDisadvantage of Design--Build ApproachBuild Approach

G Reduced opportunities for smaller, local construction firms.G Fewer competitors and increased risk may result in higher

initial costs.G Elimination of traditional checks and balances. Quality may

be subordinated by cost or schedule considerations. G Less Engineer control over final design.G Higher procurement costs.G Traditional funding may not support fast-tracking

construction or may require accelerated cash flow. G Accelerated construction can potentially overextend the

workforce.

Page 21: Construction Contracts Docuements 06092008

Others

pp TurnkeyTurnkey

pp Turnkey VariationsTurnkey Variations

pp Direct Labor Approach.Direct Labor Approach.

pp Construction managementConstruction management

Page 22: Construction Contracts Docuements 06092008

Turnkey

p Turnkey adds to the design-builder’s responsibilities the operation and/or maintenance of the completed project.

p Turnkey delivery has the potential for bringing a new project on line more quickly.

p Three forms of turnkey project delivery:n Design-build-operate-transfer

n Design-build-operate-maintain

n Design-build-own-operate-transfer

Page 23: Construction Contracts Docuements 06092008

Turnkey Variation

p Variations on turnkey add financing as a key component. While financing arrangements are unique for each project, developer financed projects generally resemble one of the turnkey delivery methods:n FDBT (Finance, design, build, transfer)

n FDBOT (Finance, design, build, operate, transfer)

n FDBOOT (Finance, design, build ,own, operate, transfer)

p In each case, the transfer of the project occurs only after the developer’s interests and financial obligations have been satisfied.

Page 24: Construction Contracts Docuements 06092008

Assignment (Assignment (11))

p Describe the turnkey methods, turnkey variation methods, direct labor approach, and construction management method, highlighting on advantage and disadvantage of each one.

Page 25: Construction Contracts Docuements 06092008

2nd lecture

p The contract, and contract types, overview of the construction documents.

Page 26: Construction Contracts Docuements 06092008

Contract DefinitionContract Definition

p Agreement of at least two parties with purpose of creating legal obligation between the parties and capable of being enforced by the court of law.

p Contract = offer + acceptance + consideration

Page 27: Construction Contracts Docuements 06092008

Introduction to contractsIntroduction to contracts

Why Use contract in construction:

v Describe scope of work

v Establish time frame

v Establish cost and payment provision

v Set fourth obligations and relationship

v Minimize disputes

v Improve economic return of investment

Page 28: Construction Contracts Docuements 06092008

Content of the contractContent of the contract

o Identify the parties

o Promises and responsibilities

o Scope of work

o Price and payment terms

o Commercial terms and conditions

o Project execution plan.

Page 29: Construction Contracts Docuements 06092008

Major Contract Types (traditional)

Page 30: Construction Contracts Docuements 06092008

Lump Sum Contract

p One price for the whole contract

p Lump sum includes costs plus overheads and profits

p Higher risk to contractor

p Price quoted is a guaranteed price as per contract documents.

p Payment based on a scheduled percentage scheme (monthly progress claims)

p The contractor is free to use means and methods to complete the work and responsible for proper performance

p Work must be well defined at bid time.

p Fully developed plans and specifications

Page 31: Construction Contracts Docuements 06092008

Lump Sum Contract/ advantage

p Low risk on the owner, Higher risk to the contractor

p Cost known at outset

p Contractor will assign best personnel

p Contractor selection is easy.

Page 32: Construction Contracts Docuements 06092008

Lump Sum Contract/disadvantage

p Changes is difficult and costly.

p Contractor is free to use the lowest cost of material equipment, methods.

Page 33: Construction Contracts Docuements 06092008

Unit Price

v Quote Rates / Prices by units

v No total final price

v Re-negotiate for rates if the quantity or work considerably exceeds the initial target

v Payment to contractor is based on the measure.

v Unbalanced bids

v Higher risk to owner

v Ideal for work where quantities can not be accurately established before construction starts.

Page 34: Construction Contracts Docuements 06092008

Unit Price contract

v Require sufficient design definition to estimate quantities of units

v Contractors bid based on units of works

v Time & cost risk (shared)ü Owner : at risk for total quantities

ü Contractor : at risk for fixed unit price.

v Large quantities changes (>15-25%) can lead to increase or decrease of unit price.

Page 35: Construction Contracts Docuements 06092008

Unit Price / Requirement

p Adequate breakdown and definition of work units

p Good quantity surveying and reporting system.

p Adequate drawings.

p Experience in developing BOQ

p Payment based on the measurement of the finished works.

p Quantity sensitive analysis of unit prices to evaluate total bid price for potential quantity variation.

Page 36: Construction Contracts Docuements 06092008

Unit Price / advantagesUnit Price / advantages

p Suitable for competitive bid

p Easy for contract selection

p Early start is possible

p Flexibility : quantities and scope can be easily adjusted

Page 37: Construction Contracts Docuements 06092008

Unit Price / disadvantagesUnit Price / disadvantages

vFinal cost not known from the beginning (BOQ only is estimated)

vStaff needed to measure the finished quantities and report on the units not completed.

vUnit price sometime tend to draw unbalanced bid. (For Unit-Price Contracts, a balanced bid is one in which each bid

is priced to carry its share of the cost of the work and also its share of the contractor’s profit.

Contractors raise prices on certain items and make corresponding reductions of the prices on other items ,without changing the total

amount of the bid)

Page 38: Construction Contracts Docuements 06092008

Cost Plus1. Actual cost plus a negotiated reimbursement to

cover overheads and profit.

2. different methods of reimbursement :§Cost + percentage

§Cost + fixed fee

§Cost + fixed fee + profit-sharing clause.

3. Higher risk to owner

4. Compromise : guaranteed maximum price (GMP) reduces risk to owner while maintain advantage of cost plus contract.

5. By using this type of contract the contractor can start work without a clearly defined project scope, since all costs will be reimbursed and a profit guaranteed.

Page 39: Construction Contracts Docuements 06092008

Cost + Percent of CostnFee = percentage of the total project cost

p(Cost = $500.000,Fee = 2%)

AdvantagesAdvantages DisadvantagesDisadvantages

profitable for profitable for the contractorthe contractor

No incentive No incentive to finish jobto finish job

quicklyquickly

Owner does Owner does not know totalnot know total

priceprice

Larger the Larger the cost of the cost of the job, thejob, the

higher the fee higher the fee the owner the owner payspays

Page 40: Construction Contracts Docuements 06092008

Cost + Fixed Fee

p Fee = percentage of the original estimated total figure

n Utilized on large multi-year jobs

n Ex: WW treatment plant Facility (Cost = $20 million, Fee = 1%)

n $20 Million 1% fee = $200,000 Million

AdvantagesAdvantages DisadvantagesDisadvantages

Fee amount is Fee amount is fixed fixed regardlessregardless

of price of price fluctuationfluctuation

Expensive Expensive materials andmaterials and

construction construction techniques maytechniques may

be used to be used to expediteexpedite

constructionconstruction

Provides Provides incentive to incentive to completecomplete

the project the project quicklyquickly

Page 41: Construction Contracts Docuements 06092008

Cost Plus Fixed Fee

n Most common form of negotiated contracts

n COST = expenses incurred by the contractor for the construction of the facility

p Includes: Labor, equipment, materials, and administrative costs

n FEE = compensation for expertisep Includes: profit

Page 42: Construction Contracts Docuements 06092008

Cost + Fixed Fee +Profit-Sharing Clause

n Rewards contractors who minimize cost

n Percentage of cost under GMP is considered profit

and shared with the contractor

p Guaranteed Maximum Price (GMP)

p % of profit sharing is specified in contract

AdvantagAdvantageses

DisadvantagesDisadvantages

Provides Provides incentive incentive to theto the

contractocontractor to save r to save moneymoney

Contractor Contractor must absorb must absorb anyany

amount over amount over the GMPthe GMP

Plans & specs. Plans & specs. need to need to detaileddetailed

Page 43: Construction Contracts Docuements 06092008

Cost + Fixed Fee +Profit-Sharing Clause

variation of this type of contract is called variation of this type of contract is called a guaranteed a guaranteed maximum price (GMP).maximum price (GMP).

pp In this type of contract the contractor is reimbursed at cost In this type of contract the contractor is reimbursed at cost with an agreedwith an agreed--upon fee up to the GMP, which is essentially upon fee up to the GMP, which is essentially a cap; beyond this point the contractor is responsible for a cap; beyond this point the contractor is responsible for covering any additional costs within the original project covering any additional costs within the original project scopescope

pp An An incentive clause, incentive clause, which specifies that the contractor which specifies that the contractor will receive additional profit for bringing the project in will receive additional profit for bringing the project in under the GMP. under the GMP.

Page 44: Construction Contracts Docuements 06092008

Construction Documentsu Bidding requirements

u Notice to Bidders

u Instruction to Bidders

u Proposal Form

u Contract Documents

u Contract Forms

u Conditions of the Contract

u Specifications

u Drawings

u Addenda

u Change Orders

u Agreement.

Page 45: Construction Contracts Docuements 06092008

Construction Documentsp Construction Documents are defined as the written and graphic documents

prepared or assembled by the A/E for communicating the design of the project and administering the contract for its construction.

p 2 major groups

1.Bidding Requirements

Used to attract bidders & explains bidding process

2.Contract Documents

Legally enforceable requirements that become part of the contract

Include all construction documents except bidding forms

Page 46: Construction Contracts Docuements 06092008

CONSTRUCTION DOCUMENTS

Page 47: Construction Contracts Docuements 06092008

CONSTRUCTION DOCUMENTSBIDDING REQUIREMENTS

BIDDING REQUIREMENTS

Bidding Requirements are used to attract bidders and explain the procedures to be followed

in preparing and submitting bids .

Bidding requirements help bidders follow established procedures and submit bids that will

not be disqualified because of technicalities. They do not become part of the contract

documents

Bidding documents

All of the construction documents issued to bidders before the signing of an owner-

contractor agreement.

Page 48: Construction Contracts Docuements 06092008

Bid PackageDocuments available to the contractor and on which he must make a decision to bid

or not

A set of plans and technical specifications, Proposal form, general conditions,

special conditions,

Description of the project to be constructed

Bid Package is prepared by: