Construction and Installation Readiness of TOTEM Roman Pots Detectors Federico Ravotti (PH/TOT)...
-
Upload
delilah-henderson -
Category
Documents
-
view
216 -
download
2
Transcript of Construction and Installation Readiness of TOTEM Roman Pots Detectors Federico Ravotti (PH/TOT)...
Construction and Installation Readiness of TOTEM Roman Pots
DetectorsFederico Ravotti (PH/TOT)
Gennaro Ruggiero (PH/TOT)LHCC minireview – 06 May 2009
• Layout of the Roman Pots (RPs) system;
• Construction steps of the Detector Package;
• Readiness of the RP services.
2
Summary
Experimental layout of the TOTEM Detectors
Services routing:From Castor to Racks
Patch Panels
T2
Services routing:From Castor to Racks
Patch Panels
T2
Roman Pots at147m, 220mfrom the IP
T1
T2
Services routing:From Castor to Racks
Patch Panels
T2
Services routing:From Castor to Racks
Patch Panels
T2
T2CMS
T1
Inelastics Telescopes
IP5
3
Roman Pots at147m, 220mfrom the IP
Horizontal Pot Vertical Pots BPM
Roman Pot (RP) Unit
10σ beam
Detectors overlap in the data taking
position
Special beam pipe insertion allowing to approach the detectors very close to the beam. Compensation system allows the movement from garage position to data taking position.
2221
150m thin window
5
All 8 RP Units installed in the LHC since autumn 2007
Station 220m
Station 147m
2 Mechanical units = 1 Station
6
The Detector Package (DP)
The Si microstrip edgeless detector
The “Champignon”VFAT chips
Si microstrip edgelessdetector
The Hybrid
5 u & 5 v oriented planes
Kapton pigtail
CE07support
plate
Connectors to detector hybrids
Roman Pot Motherboard
The RP Motherboard links the front-end to the counting
room. Preliminary tests in the TOTEM Lab. Bld. 555.
RP Motherboard and its mezzanines
7
DP production takes 30 days (3 DPs produced in parallel)
RP hybrid box with traveller
sheet
RP Production DB interface
The RP hybrid test and assembly data are kept on a Database and on the traveller
sheet.
8
PCB of the RP hybrid
Cards delivered by EN-ICE are inspected and then the VFATs
are mounted in the bonding lab.
9
RP hybrid test setupThe RP hybrids together with the VFATs are tested with the Totem Test Platform (TTP).
Totem Test Platform (TTP) 10
RP hybrid with VFATs and sensors all wire-
bonded
Pre-qualified Edgeless Silicon sensors are mounted and wire-
bonded in the bonding lab. Then the sensors are tested with the TTP.
11
Computer Measuring Machine (Bonding Lab)
The support bars are precisely mounted on the hybrid. The
hybrid is connected again to the TTP for a test of the VFAT +
Silicon sensor
RP hybrid fully mounted with support bars
12
The Detector Package is assembled. The DP is tested together with the Motherboard in the Lab. Bld. 555. DCS tests are also executed here.
RP Detector Package and its
Motherboard
13
RP DP checked in the Lab. Bld. 555
The DP and it’s Motherboard are assembled together with
the “Champignon”. A final check is then made.
RP Detector Package with the
Champignon
14
RP DP inserted in a prototype pot with thin window
The RP Detector Package is inserted in a prototype pot with thin window
and installed in a test setup in H8 for data taking. The H8 setup allow test with cosmic-rays or the SPS beam.
15
During summer 2008, the first 2 detector packages were installed
in the tunnel, in the horizontal Pots of the “far” units at 220m. on
both sides of IP5.
Open pot in the tunnel
16
Package ready for installation
Package installed(Sec. 5-6, station 220m., far unit, hor. pot)
17
POT 3 to POT 7 installed during 29-30 April 2009 in the RP Station 220m Sec. 5-6 as
planned!
Station 220m in Sec 5-6 is
now completed!
18
Roman Pots Services Layout
LV Power Supply Remote
Units
VacuumSystem220m
Cooling Plant
VacuumSystem147m
DCS: Motorization + High Volt. + Low Volt. Control Modules + Environmental Sensors Readout
XRP1(TOTEM)
19
Cabling / Installation of Power Supplies
Cabling
• Stations 220m. completed;
• Stations 147m. under completion.
Low Voltage Power Supplies
• Control Units in USC55 are installed;
• Remote Units in RRs are installed.
High Voltage Power Supply
• Crate installed in USC55;
• HV Patch Panel in assemblyHV (CAEN)
LV (Wiener)
Patch Panel in the tunnel
20
Cooling and Vacuum
Cooling System (EN-CV)
• Cooling Plant operational;
• Loops for 220m stations completed
and tested;
• Loops for 147m stations completed
and under test.
Vacuum System
• All installed RP detectors under
vacuum (~ 10mb). Vacuum needed
to avoid condensation and to reduce
stress at the window.
Cooling Plant(compressors)
Cooling Plant (tank)
RP Station Vacuum System
Environmental Sensors Readout
Vacuum & Temperature Box (RP) installed at IP5
RadMon Boxes (RP/T1+T2) under test in Lab. bld. 555
23
Thank you for your attention.
Many thanks to all TOTEM colleagues that supply the material for this presentation
Pinout tables: full connectivity chain from HW (HV/LV/Temp/RadMon/...) to DCS,Mapping single wires into control/monitoring functions
PBS of detector
Cabling
Counting Room PPs
DCS PVSS
datapoints
DATAPOINTS NAMES & PVSS IMPLEMENTATION
AUTOMATICALLY DONE
RP Panel for Motherboard + Detector Package tests in Lab. 555
HV
Monitoring
LV
Vacuum
HV Control
RadMonTemp.
Hybrids
Temp.
Cooling Lines