CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan –...

33
Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page i January 2012 CONSTRUCTION and ENVIRONMENTAL MANAGEMENT PLAN RESIDENTIAL SUBDIVISION ALEXANDRA DRIVE BELLWOOD January 2012 de Groot & Benson Pty Ltd

Transcript of CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan –...

Page 1: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page iJanuary 2012

CONSTRUCTION and ENVIRONMENTAL MANAGEMENT

PLAN

RESIDENTIAL SUBDIVISION

ALEXANDRA DRIVE BELLWOOD

January 2012

de Groot & Benson Pty Ltd

Page 2: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page iiJanuary 2012

CONSTRUCTION and ENVIRONMENTAL MANAGEMENT

PLAN

RESIDENTIAL SUBDIVISION

ALEXANDRA DRIVE BELLWOOD

January 2012

de Groot & Benson Pty Ltd

ACN 052 300 571 Ph 02 6652 1700 Fax 02 6652 7418 Email: [email protected]

236 High StreetPO Box 1908

Coffs Harbour NSW 2450

Page 3: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page iiiJanuary 2012

TABLE OF CONTENTS

TABLE OF CONTENTS ................................................................................................................ iii 

DOCUMENT CONTROL STATUS .............................................................................................. iv 

1  INTRODUCTION .................................................................................................................. 5 

2  PROJECT DESCRIPTION ........................................................................................................ 6 

3  OBJECTIVES ........................................................................................................................... 7 

4  ENVIRONMENTAL MANAGEMENT PLAN ............................................................................ 8 

4.1  MONITORING AND MEASUREMENT ......................................................................................... 8 4.1.1 SITE INSPECTIONS AND RECORD KEEPING ................................................................................. 8 4.1.2 PUBLIC FEEDBACK ................................................................................................................. 8 4.1.3 SITE INDUCTION ................................................................................................................... 8 

5  IMPLEMENTATION OF MANAGEMENT PLAN ..................................................................... 9 

5.1  INTRODUCTION ............................................................................................................... 9 5.2  TRAFFIC MANAGEMENT .................................................................................................... 9 5.2.1 GENERAL ........................................................................................................................... 9 5.2.2 SITE ACCESS CONDITIONS ................................................................................................ 9 5.2.3 WORKING HOURS .......................................................................................................... 11 5.2.4 PEDESTRIANS .................................................................................................................. 11 5.2.5 EMERGENCY VEHICLE ACCESS ........................................................................................ 11 5.2.6 POTENTIAL IMPACT OF CONSTRUCTION TRAFFIC ....................................................... 11 5.2.7 EXISTING TRAFFIC FLOWS .............................................................................................. 11 5.2.8 CONSTRUCTION TRAFFIC IMPACT ................................................................................. 12 5.3  CONTRACTOR MANAGEMENT ....................................................................................... 13 5.4  CONSTRUCTION PHASE .................................................................................................. 14 5.4.1 GENERAL ......................................................................................................................... 14 5.4.2 DUST MANAGEMENT ..................................................................................................... 15 5.4.3 SEDIMENT AND EROSION CONTROL ............................................................................. 16 5.4.4 SURFACE WATER MONITORING .................................................................................... 17 5.5  MAINTENANCE PHASE .................................................................................................... 19 5.5.1 SEDIMENT AND EROSION CONTROL ............................................................................. 19 5.5.2 SURFACE WATER MONITORING .................................................................................... 20 5.5.3 MAINTENANCE ............................................................................................................... 21 5.6  OPERATIONAL PHASE ..................................................................................................... 22 5.6.1 SURFACE WATER MONITORING .................................................................................... 22 5.6.2 MAINTENANCE OF STRUCTURES ................................................................................... 23 

APPENDIX A ............................................................................................................................. 24 

APPENDIX B .............................................................................................................................. 25 

Page 4: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page ivJanuary 2012

DOCUMENT CONTROL STATUS

Issue Rev. Issued To Qty Date Reviewed Approved

draft Geoff Smyth January 2009 RDG RDG

final Geoff Smyth October 2010 RDG RDG

Final2 Geoff Smyth January 2012 RDG RDG

Printed: 24 January, 2012 4:23 PM Last Saved: 24 January 2012 4:21 PM File Name: S:\91\91111 Faringdon Way\WP\91111 Construction Management Plan Jan

2012.doc Project Manager: Rob de Groot Name of Organisation: Nambucca Gardens Estate Pty Ltd Name of Project: Construction Management plan Name of Document: Bellwood CMP Job Number: 91111

Page 5: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 5January 2012

1 INTRODUCTION

The site of the proposed Alexandra Drive development is located on 54.92ha of land approximately 1km west of the Nambucca, in the Nambucca Local Government area.

The land is situated on the northern corner of on either side of Alexandra drive and borders two creeks, Swampy creek and Bellwood creek.

Figure 1.1, area to be enclosed by the proposed development.

The land is to be sub divided for residential living with all the land being subdivided except for the various reserve areas proposed. The site is planned to be developed over several stages.

The following document outlines the construction, traffic and pedestrian management measures to be adopted by the Head Contractor for Stage 1. The actions recommended will provide for safe ingress and egress from the site whilst minimising and mitigating potential impacts drivers using Alexandra Drive. A particular focus is on traffic and pedestrian management for the construction of Stage 1 of the proposed development.

This document also identifies a range of sound construction practices to mitigate environmental risks during Stage 1 works. These will be addressed by the Stage 1 Construction Environmental Management Plan (CEMP) to be undertaken by the Head Contractor. The list of issues is based upon the NSW Department of Housing’s standard, which is a benchmark document for this type of construction in NSW.

The traffic, construction and environmental management issues identified and the recommended actions will be similar for ongoing stages of the works and the management process outlined in this section will be used as a template for future stages of work, to be implemented at the development progresses.

Page 6: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 6January 2012

2 PROJECT DESCRIPTION The following drawing shows the layout of the proposed development.

Figure 2.1, Lot Layout..

The main development is located west of the Pacific Highway occupies both sides of Alexandra Drive. Access during construction, to the site is proposed from one point:

Alexandra Drive –the eastern leg of the roundabout at the entrance to the undeveloped land.

The type of construction operations which will be undertaken onsite will include:

Bulk Earthworks

Road and drainage works

Service utility installation

Residential construction

Landscape works.

The type of vehicles which will be operating on the site and requiring access to the site include, tip trucks, excavators, backhoes, graders, water carts, concrete mixers and pumps, rollers etc.

Page 7: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 7January 2012

3 OBJECTIVES

The Environmental and Construction Management Plan will be used to define the traffic and environmental management measures to be adopted by the Head Contractor for the Stage 1 works on the site. These measures are to be implemented to:

provide a safe environment for all surrounding residents, road users and workers onsite

provide protection to workers, visitors and the general public from traffic and environmental hazards that may arise as a result of the construction activity

minimise the disruption, congestion and delays to all road users

Ensure network performance is maintained at an acceptable level throughout the term of the work.

eliminate or mitigate risks of damage or degradation to the environment through sound construction management practices

To achieve these objectives, the Construction Management Plan will:

ensure that the road capacity is sufficient to accommodate vehicle traffic volumes and disruptions are minimised

ensure that appropriate warning and information signs are installed

ensure that all needs of road users, motorists, pedestrians, cyclists, public transport passengers and people with disabilities are accommodated

provide for work activities to be undertaken sequentially to reduce the adverse impacts of the work

provide for safety procedures to enable work personnel to enter and leave the work area in a safe manner

Identify potential environmental risks from standard construction activities and define sound construction practices to be adopted by the Head Contractor to eliminate or mitigate these risks.

Page 8: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 8January 2012

4 ENVIRONMENTAL MANAGEMENT PLAN

4.1 Monitoring and Measurement

4.1.1 Site Inspections and Record Keeping The operation will monitored to ensure that it proceeds as explained in the Head Contractors CMP. Daily inspections before construction will ensure are concurrent with those specified in the plan and that there are no potential hazards. Any adverse impacts will be recorded and immediately dealt with if they arise.

4.1.2 Public Feedback The head contractor will be obligated to develop a constructive relationship with those in the immediate vicinity and community of the development.

A forum for consultation with the public will be set up where feedback will be encouraged and updates on the development will be posted to keep residents up to date with activities on site. A letter box drop to inform local residents of construction timing, work duration and what works are occurring at what times, changes to these times should also be notified to residents.

Any suggestions or complaints concerning the construction traffic will be processed, recorded and appropriate action taken where necessary. Public will be notified as to how the issue has been dealt with.

4.1.3 Site Induction Anyone entering the site will be required to undergo a site induction. The induction will include access routes, parking, deliveries, emergency procedures, OH & S and standard environmental requirements and regulations.

Page 9: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 9January 2012

5 IMPLEMENTATION OF MANAGEMENT PLAN

5.1 INTRODUCTION Projects of this size are typically required to prepare an Environmental Management plan prior to Construction.

The Environmental Management Plan construction site specific plan which is used to ensure that

best practice environmental management procedures are applied to the construction practices and the maintenance and environmental phases of each stage of development

The findings of the site’s environmental assessment are adhered to and the conditions of approval are followed to the letter

On site activities comply with all current environmental legislation

The environmental risks associated with the project are properly identified and managed.

An Environmental Management Plan will be prepared for the development prior to construction. This will be prepared with reference to the NSW Government’s “Guideline for Preparation of Environmental Management Plans” (DIPNR 2004). Many issues considered as part of the Environmental Management Plan are common on such developments. The NSW Department of Housing Guideline EMP Checklist (2000), can be used as a guide as many of these issues are identified. The checklist is summarised in Appendix B. The following sections outline the proposed control measures for a range of issues that may arise during construction, operation and maintenance stages of development; and proposes the implementation of these control measures to each stage of development. It should be noted that the application of these control measures at each stage of development will be assessed on a case-by-case basis as development progresses. The diagram shown below in [Section 5.2.2] (including vehicle access routes and control measures) will be used as a template for the layout of future stages of development.

5.2 TRAFFIC MANAGEMENT

5.2.1 GENERAL Traffic Management Plans will be required to be prepared by the Head Contractor at each stage of construction. The recommendations contained in this document will be adopted for the Stage A1 and A2 plan of construction.

Where traffic management measures are required on RTA controlled roads (such as Pacific Highway), the design is to be certified by an RTA accredited professional.

5.2.2 SITE ACCESS CONDITIONS Site access during the construction of Stage A1 and A2 is proposed from Alexandra Drive. Heavy vehicle and delivery movements via a main temporary access, will be only access point to site. Alexandra Drive is a local two lane rural road of variable width; it has a 50km/h speed; the grade leading up the intersection is gentle with the rest if the road traversing downhill towards the development. Stage access routes are shown below in Figure 5.1.

Page 10: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 10January 2012

Figure 5.1 - Site Access Routes for Stage A1 and A2

STAGE A1 and A2

STAGE 1 SITE ACCESS

Page 11: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 11January 2012

5.2.3 WORKING HOURS The environmental assessment states that all construction activities including materials delivery is restricted to the following hours:

7:00am – 6:00pm, Monday to Friday

8:00am – 1:00pm, Saturday

No work on Sunday or Public Holidays

Any construction work outside the above hours can only be approved by appropriate authorities prior to work commencing after appropriate consultation with affected residents.

5.2.4 PEDESTRIANS Pedestrian amenity within the vicinity of the site will be protected through signage, barricades and webbing. There will be no public pedestrian route through the construction site. Pedestrian routes in close proximity or within area of site works will be diverted to safely cater for the needs of pedestrians. Where construction works interrupt existing pedestrian routes, temporary pedestrian access in close proximity to the existing arrangements will be provided with suitable signage. Pedestrian movements will be subject to continuous review and will be adjusted when necessary. Pedestrian movements within the construction site will be subject to standard construction OH&S practices.

5.2.5 EMERGENCY VEHICLE ACCESS Emergency vehicle access will be available through the main access point. The access for police and emergency services will remain open during construction working hours to minimise response times. Liaison will be maintained with the police and emergency services agencies throughout the construction period and a 24 hour contact will be made available for out of hour’s emergencies and access.

5.2.6 POTENTIAL IMPACT OF CONSTRUCTION TRAFFIC The potential impact of vehicles associated with the construction has been investigated so as to enable the implementation of the appropriate traffic management measures.

5.2.7 EXISTING TRAFFIC FLOWS The existing peak hour traffic movements are taken from a Traffic Counting Study undertaken in February 2009. The full results of the traffic assessment are given in Annexure D.

Alexandra Drive North-South

Morning peak 61 vehicles/hour

Evening peak 56 vehicles/hour

Page 12: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 12January 2012

5.2.8 CONSTRUCTION TRAFFIC IMPACT

ALEXANDRA DRIVE The number of workers onsite at any one time is estimated at between 10-15 persons with the maximum no more than 15. Assuming that the workers arrive by private vehicles and each vehicle transports two persons it can be assumed that up to 8 vehicles per day will be present. A low flow of vehicles visiting and exiting the site will occur throughout the day. These extra vehicles will have limited impact on Alexandra Drive as these vehicles will only be using a very small section of the road (100m) and will not interfere with other resident’s properties or other traffic. This has been confirmed by the Traffic Assessment report given in Annexure D. Road safety and noise issues will need to be addressed to ensure minimal discomfort and delay is caused on residents. It is considered that this can be addresses through community consultation, education and sign postage.

The following measures will be adopted

Site induction will include procedures for accessing the site from Alexandra Drive

Ongoing staff meetings will reinforce the need for care when using Alexandra Drive.

Signage will be placed at the access and at Alexandra Drive warning site employees that they must observe speed limits and to reduce noise.

Car pooling will be encouraged to reduce vehicle numbers.

Opportunities to stagger arrival and departure times will be investigated to minimise effect on pedestrians and school children during Bus drop off times

Cars will access the site via a maintained gravel road. A wash down area will not be required however a cattle grid may be used to ensure no dirt exits the site.

Page 13: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 13January 2012

5.3 CONTRACTOR MANAGEMENT Person Responsible: Consulting Engineer Issue Contractor management

Operational policy To ensure the proponents Duty of Care is met by ensuring the Contractor is aware of his responsibilities under the terms of the SWMP and the EPA

Performance criteria Contractor is fully aware of his responsibilities under the terms of the SWMP.

Implementation strategy

• Review of the SWMP and the construction phase contracts by the proponent. • Periodic checks to be made by an independent Environmental Consultant; • Training for construction staff in implementation of SWMP provisions.

Monitoring Weekly site inspections to be carried out

Auditing Inspections will be carried out monthly during the construction phase by an Environmental Consultant for every stage of development.

Reporting Full details to be available to the contractor together with suggested corrective actions if required

Corrective action To be detailed at the time

Page 14: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 14January 2012

5.4 CONSTRUCTION PHASE

5.4.1 GENERAL Prior to construction in any stage, detailed Environmental Management Plans will be prepared, based on the requirements of DIPNR (2004) and submitted to council. The estate will developed in several stages to minimise the potential for soil erosion and water pollution and places less strain on the immediate ecosystem. This would also mean less impact on residents surrounding the development. By developing in stages it enables the environment to be progressively rehabilitated as the development proceeds. Wherever possible the site will remain undisturbed until construction of that area or stage is to take place. Prior to commencement of bulk earthworks, temporary sediment and erosion control measures should be installed in accordance with the management plan and the Institution of Engineers Soil Erosion and Sediment Control Guidelines. All the runoff from disturbed areas is to be managed by the installation of silt fences and contour drains. Runoff should be dispersed evenly and concentrated flows should be limited. Runoff from undisturbed area should be diverted around disturbed areas wherever practical to minimise erosion of construction site. Control measures such as sediment ponds, silt fences, contour drains should be installed and maintained in accordance with the recommendations contained in the “Soil Erosion and Sediment Control Engineering Guidelines for Queensland Construction Sites” June 1996, by the institution of engineers Australia (Queensland Division). Sediment and erosion control must remain in place throughout the entire construction process until final landscaping is finished and established. Additional sediment and erosion control plans are outlined in Appendix C The soil on site has been earmarked as being low fertility soil, however nutrient transport from site should be minimised with appropriate measures.

Page 15: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 15January 2012

5.4.2 DUST MANAGEMENT Person Responsible: Contractor’s Site Manager Issue Minimisation of movement of dust offsite

Operational policy To achieve acceptable air quality standards through the control of the movement of dust offsite from site works.

Performance The target level for complaints by nearby residents is no criteria more than one in any seven day period. Ambient air quality should not

deteriorate by more than 30% over a period of seven consecutive days. Dust deposition at any nearby residence should not exceed 100mg/m2/day.

Implementation The minimisation of the movement of dust offsite will be strategy achieved through the following onsite practices:

1. All permanent bunds and reshaped areas will be revegetated within 10 days after completion of earthworks (including excavation and backfilling of services trenches). 2. Stockpiling onsite will be minimised where possible. 3. An on-site water cart will be available at all times. The site will be watered daily and additional watering will be conducted during high-risk times such as high winds and low rainfall and after receipt of complaints. 4. All dust creating activities to cease if wind speed exceeds 10m/sec. 5. Contractors staff to be trained to implement dust minimisation measures.

Monitoring Daily inspections will be carried out to verify that dust mitigation measures are being implemented. Dust monitoring will be conducted upon receipt of complaints by residents. If dust monitoring is to take place, the following will occur: • Temporary dust deposition gauges will monitor the movement of dust offsite at the nearest residences adjacent to the proposed stages and within the predominant wind directions . • Monitoring will be undertaken in accordance with AS 3580.10.1 (1991).

Auditing Management to examine the complaints register weekly and review corrective action taken

Reporting The contractor to notify EPA of a possible environmental nuisance on receipt of 3 or more dust complaints in any 24 hour period. Reports will be provided to Nambucca Shire Council upon request. Complaints by residents are to be recorded in a Complaints Register and notified to Nambucca Shire Council.

Identification of incident or failure

Any dust-related complaints by residents will indicate a failure of the dust control measures.

Corrective Action Locate the source of the dust and implement the following measures: • apply water sprays to vegetation • cover or water exposed areas • if dust persists, cease the dust creating activities All dust complaints to be addressed in consultation with Council Officers.

Page 16: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 16January 2012

5.4.3 SEDIMENT AND EROSION CONTROL Person Responsible: Contractor’s Site Manager, Consulting Engineer Issue Sediment and Erosion Controls

Operational policy To prevent the displacement of sediment and soil across and offsite during storm events.

Performance criteria • Off-site discharges to comply with requirements for suspended sediments as detailed in Section 6.3 of the this report. • No visual indication of erosion on stages under construction, including evidence of rilling (an indicator of sheet erosion).

Implementation strategy

1. Erosion and sediment control devices shall be installed prior to commencement of work in each stage in accordance with the approved engineering plans and to the reasonable satisfaction of Nambucca Shire Council. 2. Temporary erosion measures (eg. silt fences) are to be employed onsite during construction where reasonably deemed necessary by CHCC from an assessment of slope and soil type. Such measures should be in accordance with the recommendations in the IE Aust. Qld. Soil Erosion and Sediment Control Guidelines. 3. Stockpiled soil should be stored/bunded in a manner to prevent soil being washed offsite (ie. bunding where necessary). 4. Outside the construction area of each stage existing surface water conditions shall be maintained.

Monitoring • Carry out visual inspections daily and after rainfall events (>25mm in 24hrs.) to ensure that erosion measures are in place and operational to suit the activities taking place at the time, . • Surface water quality to be monitored fortnightly (refer to the section titled ‘Surface Water Monitoring’ which details monitoring of surface water and stormwater quality including during storm events).

Auditing Visual inspections to be carried out monthly and after rainfall events to verify that control measures are in place and properly maintained.

Reporting of Monitoring Results

Reporting only required if insufficient sediment and erosion measures are identified.

Identification of incident or failure

1. Signs of erosion on site. 2. Damaged or failed erosion control devices. 3. Falling water quality as identified by Environmental Consultant. 4. Build-up of sediment.

Corrective action Apply remedial measures to Improve sediment and erosion measures, for example; silt fences, and shake down areas.

Page 17: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 17January 2012

5.4.4 SURFACE WATER MONITORING Person Responsible: Contractor’s Site Manager, Environmental Consultant Issue Surface water monitoring

Operational policy To maintain water quality conditions of receiving waters during the construction phase.

Performance criteria All water discharged from the site during the construction phase should comply with the following criteria: Water Quality Parameter Release

Water Quality Parameter

Release Criteria Criteria Type

pH 6.5 – 9.0 Range EC 1500µS/cm Maximum

Turbidity <60NTUI Maximum

Implementation strategy

• In-situ surface water samples to be conducted during rainfall events from established monitoring points at the site outlets. • Monitoring results should be reviewed after 6 months and sampling frequency revised in consultation with Council Officers. • Stormwater control should be achieved by directing as much runoff as practicable from disturbed areas to the temporary control measures. “Clean” runoff from undisturbed areas should be diverted around disturbed areas if possible.

Monitoring 1. Surface water monitoring during construction should be conducted at the monitoring points for the parameters shown above. Flow rates are to be estimated and recorded at the time of sampling. 2. Sampling frequency is to be during rainfall events (>25mm in any 24hr period).

Auditing The Consulting Engineer to audit water quality results to ensure all discharges comply with the performance criteria.

Reporting • Monthly reports to Nambucca Shire Council including raw data, a results summary and a discussion comparing results with baseline values and ANZECC guidelines. • Result sheets to be compiled for monitoring results. All results to be kept on site for inspection by local and state government officers at all times.

Identification of incident or failure

1. Degradation of surface water quality at the monitoring points to below the levels specified in “Performance Criteria” above prior to discharge. 2. Apparent visual changes in water body conditions.

Corrective action Locate the source of the contaminant Take all possible actions to contain and control the contaminant. Investigate the cause of the contamination and take action to prevent a recurrence. If the test result for any parameter fails to meet the performance criteria, then weekly monitoring shall commence and continue until the recorded value/s meets the performance criteria. For Example; If the turbidity exceeds the water quality criteria for this parameter, then water may need to be contained on site for a period sufficient to allow suspended solids to settle out prior to release, or settling shall be aided by dosing with flocculation agents at the

Page 18: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 18January 2012

Issue Surface water monitoring

rate recommended by the manufacturer. Erosion control devices should be immediately inspected and cleaned if necessary. Additional devices should be installed if a need is detected to prevent future breaches of the suspended solids criteria. The placement of stockpiles and management of disturbed areas should be reviewed with regard to sediment and silt control.

Page 19: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 19January 2012

5.5 MAINTENANCE PHASE

5.5.1 SEDIMENT AND EROSION CONTROL Person Responsible: Contractor’s Site Manager, Consulting Engineer Issue Sediment and Erosion Controls

Operational policy To prevent the displacement of sediment and soil across and offsite during storm events.

Performance criteria Off-site discharges to comply with requirements for suspended sediments as detailed in Section 7.3 of the this report..

Implementation strategy

Temporary erosion and sediment control devices shall be maintained in an operational state during the maintenance period.

Monitoring Temporary erosion control measures are to be inspected monthly and after storm events. Permanent control measures are to be inspected monthly and after storm events

Auditing Quarterly inspections to be carried out by an Independent Environmental Consultant

Reporting of Monitoring Results

Reporting only required in the event of failure of the sediment and erosion measures.

Identification of incident or failure

• Signs of erosion on site • Build up of sediment • Falling water quality

Corrective action Repair temporary sediment and erosion control measures. Check permanent measures for build up of sediment and clean out as necessary.

Page 20: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 20January 2012

5.5.2 SURFACE WATER MONITORING Person Responsible: Contractor’s Site Manager, Environmental Consultant Issue Surface Water Monitoring

Operational policy To -establish stable surface water conditions and verify that development management is appropriate.

Performance criteria All water discharged from the site will comply with the following criteria: Water Quality Parameter Release Criteria Criteria Type pH

Water Quality Parameter

Release Criteria Criteria Type

pH 6.5 – 9.0 Range EC 1500µS/cm Maximum

Turbidity <60NTUI Maximum

Implementation strategy

1. Surface water entering and exiting the development shall be monitored at the environmental monitoring points during the “On-Maintenance” period. 2. Surface water monitoring shall be undertaken at the discharge points from the development stages until stable water quality criteria have been established. 3. Monitoring will also be undertaken during flood events where practicable. This monitoring will allow water quality comparisons to be made.

Monitoring Surface water monitoring will be conducted during the first rainfall event in each month. • Rainfall events are defined as >25mm rainfall in 24 hours. • To revert to construction phase provisions if problems are identified. • If problems are identified, laboratory analysis at a NATA registered laboratory for the total suspended solids, total nitrogen and total phosphorus to be undertaken until such time as Nambucca Shire Council is satisfied that the Proponent’s duty of care under the EPA has been discharged. • These provisions will conclude at the end of the “On Maintenance” period.

Auditing • Management to audit water quality results quarterly to verify that discharges comply with the performance criteria.

Reporting of Monitoring Results

1. Monitoring test results are to be compiled on monthly result sheets. Monthly reports containing raw data and an interpretation to be sent to Nambucca Shire Council. 2. Results to be available at all times.

Identification of incident or failure

Fall in surface water quality at the environmental monitoring points.

Corrective action 1. Identify reason for deterioration in surface water quality to identify if it is linked to the development. 2. Take necessary steps to address the problem such as Improved temporary sediment and erosion controls.

Page 21: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 21January 2012

5.5.3 MAINTENANCE Person Responsible: Contractors site Manager, Consulting Engineer Issue Maintenance

Operational policy To maintain the water quality control structures to ensure adequate performance during the maintenance period.

Performance criteria The control measures are maintained and operational.

Implementation strategy

1. Ensure inlets and outlets are not blocked and are structurally stable. 2. All waste to be disposed of at Council approved waste facilities.

Monitoring • Monthly inspection of control structures during the maintenance period • Any recurring problems with the control structures to be rectified during the maintenance period • Structures also to be inspected following major rainfall events

Auditing • Management to carry out quarterly inspections to verify that the control measures are properly maintained.

Reporting of • Record inspection details. Monitoring Results • Record details of all maintenance activities including volume of material

removed from wetlands, etc. and include in monthly reports to Nambucca Shire Council • Results to be available to EPA at all times

Identification of 1. Blockage of stormwater system incident or failure 2. Re-entrainment of trapped sediments 3. Deterioration of water quality

within or downstream of control structure.

Corrective action 1. Clean or maintain stormwater control structures as appropriate. 2. Take necessary steps to address the problem to prevent a recurrence.

Page 22: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 22January 2012

5.6 OPERATIONAL PHASE

5.6.1 SURFACE WATER MONITORING Person Responsible: Nambucca Shire Council

Issue Surface Water Monitoring

Operational policy To verify that stable surface water conditions are maintained.

Performance All water discharged from the site will comply with the criteria following criteria: Water Quality Parameter Release Criteria Criteria

Water Quality Parameter

Release Criteria Criteria Type

pH 6.5 – 9.0 Range EC 1500µS/cm Maximum

Turbidity <60NTUI Maximum

Implementation strategy

Surface water entering and exiting the development shall be monitored at the environmental monitoring points during the operational phase of the development.

Monitoring Surface water monitoring will be conducted quarterly for 12 months then half yearly. • If problems are identified, monthly laboratory analysis at a NATA registered laboratory for Suspended Solids, Total N, & Total P until such time as Nambucca Shire Council determines the cause of the problem and rectifies it.

Auditing Council to audit water quality results annually to verify that discharges comply with the performance criteria.

Reporting of Monitoring Results

1. Monitoring test results are to be compiled annually Annual reports containing raw data and an interpretation to be made available to all persons on request. 2. Results to be available at all times

Identification of incident or failure

Fall in surface water quality at the environmental monitoring points.

Corrective action 1. Identify reason for deterioration in surface water quality to identify if it is linked to the development and/or the treatment structures. 2. Take necessary steps to address the problem such as public education program regarding fertilisers and other nutrients

Page 23: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 23January 2012

5.6.2 MAINTENANCE OF STRUCTURES Person Responsible: Nambucca Shire Council Issue Operation and maintenance of the water quality control structures.

Operational policy To maintain the water quality control structures to ensure adequate performance during the operational period.

Performance criteria The control measures are maintained and operational. Pollutant concentration of stormwater released from the treatment system satisfies the quality criteria set out in Section 8.3.

Implementation strategy

• Ensure inlets and outlets are not blocked. • Ensure that trash and/or sediment accumulation does not impair operation.

Monitoring • Water sampling to be carried out according to Section 6.3. • If elevated levels are found for any parameter commence weekly sampling and testing for the parameter concerned and if possible examine the composition/constituents of the pollutant. • Establish complaints register and record details of complaints. • Inspect control structures after rainfall events. These inspections are to be recorded.

Auditing Nambucca Shire Council to carry out quarterly inspections to verify that monitoring has been carried out and that action has been implemented if required to correct any shortcomings.

Reporting of monitoring results

• Annual reports to Nambucca Shire Council. • Record details of all maintenance activities. • Results to be available to EPA at all times

Identification of incident or failure

Water quality of outflow fails to meet the release criteria.

Corrective action Clean or maintain stormwater control structure as appropriate. Implement contingency measures.

Page 24: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 24January 2012

APPENDIX A

Construction ahead

Construction ahead

Page 25: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 25January 2012

APPENDIX B

EMP ACTION PLAN RESPONSIBILITIES Source Document: NSW Dept of Housing (Resitech) EMP Checklist 2000

1 GENERAL SITE MANAGEMENT

Actions If applicable Responsible Person

Implement the Soil and Water Management Plan for the site Sweep roads free of dirt each day Regularly check and clean silt from behind silt fences and barriers if required All vehicles to remain on clean all weather surface within the site Minimise water use for cleaning Install appropriate silt fences and other sediment control structures Ensure sediment control measures are in place before starting clearing and

excavation activities

Install a fence at the site boundary to limit site access from footpath Minimise clearing of vegetation Fence off no-go areas to minimise disturbance Stockpile materials only in designated areas behind sediment fences Limit vehicle entry points and lay geotextile and blue metal to stabilise

vehicle access ways

Do not disturb the nature strip between the site and the roadway Implement the site Construction Waste Management Plan (see attached) Order only required quantities of materials Separate recyclable from non-recyclable waste Other: Ensure the correct waste containers are used by all site personnel Minimise chemicals stored on site Make staff aware of emergency phone numbers (such as the Fire Brigade) to

use in case of a large spill

Keep Material Safety Data Sheets (MSDSs) on site at all times Keep clearly marked booms and/or absorbent material on site to contain

spills if they occur

If a spill occurs, stop the source, contain it, clean up in accordance with MSDSs and notify relevant authorities

Damp down dusty areas as required

Page 26: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 26January 2012

Do not burn off any waste products or off cuts Identify site access with minimal impacts on residents and instruct trucks to

use this access

Avoid parking site vehicles where they will unduly impact local use of the street

Do not place waste containers, skip bins or building materials on road or footpath – store all materials within the work site

Limit hours of operations to suit council requirements listed in consent conditions

Use noise suppressors on machinery Do not use loud radios where neighbours can be disturbed Take appropriate care when using construction equipment adjacent to

buildings

Advise the adjoining neighbours of the work at least one week prior to commencement, including hours of work

Protect trees during construction Do not stockpile soil or other materials under the canopy of a protected tree

as designated by Resitech or the local council

Ensure site amenities such as sheds and material storage areas are not sited underneath tree canopies or in a position to disturb neighbours

Identify and protect heritage items present on site.

Page 27: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 27January 2012

2 DEMOLITION

Actions If applicable Responsible Person

Stockpile materials only in designated areas behind sediment fences Cover stockpiled materials with plastic to prevent erosion by wind and rain Install a fence around the site with a cloth barrier to act as a wind break if

dust is a problem

Damp down surfaces such as stockpiles as required to reduce wind blown dust

Implement the site Demolition Waste Management Plan (attached) Do not bury or burn demolished materials on site Ensure hazardous materials such as asbestos are handled and disposed of

correctly by licensed contractors, following Environment Protection Authority requirements

Do not mix hazardous materials with other demolition materials Identify and protect heritage items present on site

3 CONCRETING

Actions If applicable Responsible Person

Wash out trucks at supplier’s depot Wash out in an area where water cannot enter waterways, stormwater

drains, footpath or roads up slope from a sediment control device

Collect wash water in plastic container carried by delivery truck and return with the truck to the supplier for recycling or proper disposal

Collect wash water in an on-site container to allow solids to settle Irrigate a flat grassy area with diluted wash out water, ensuring that it does

not enter waterways or stormwater

Other: Implement the site Construction Waste Management Plan (attached) Order and supply only sufficient quantities of concrete Return excess concrete with delivery truck to supplier for recycling or

proper disposal

Use excess concrete as fence post footings or place areas to be used for paths or driveways

Store excess concrete in a lined bin or pit for eventual recycling or disposal

4 BRICKLAYING

Actions If applicable Responsible Person

Wash out in an area where water cannot enter driveways, stormwater drains, footpaths or roads, preferable up slope from a sediment control device

Collect wash water in an on-site container to allow solids to settle Irrigate a flat grassy area with diluted wash out water, ensuring that it does

not enter waterways or stormwater

Ensure brick cutting is undertaken where waste will not run onto footpaths or roads

Implement the site Construction Waste Management Plan Store excess mortar with waste concrete in a lined bin or pit for eventual

recycling or disposal

Page 28: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 28January 2012

5 PAINTING

Actions If applicable Responsible Person

Wash out in an area where water cannot enter waterways, stormwater drains, footpaths or roads, preferably up slope from a sediment control device

Transfer as much paint as possible back to the tin Spin brushes and roller sleeves in a waste paint drum Irrigate a flat grassy area with diluted wash out water, ensuring that it does

not enter waterways or stormwater

For solvent based paints, return solvent to a solvent recycling depot Dispose of solid paint waste with other solid waste Determine if lead is present in surfaces to be painted Seal the area with plastic sheeting to prevent escape of dust To prevent lead fumes, do not use open flame torches on lead paint Use a high efficiency particulate air (HEPA) vacuum cleaner to clean up lead

dust

Wash surfaces with a small amount of high phosphate detergent Minimise paints and chemicals on site by ordering the minimum quantities Store paints and chemicals in a bunded area where they can be contained if

spills occur

Keep Material Safety Data Sheets (MSDSs) on site at all times Keep clearly marked booms and/or absorbent material on site to contain

spills if they occur

Page 29: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 29January 2012

Other: If a spill occurs, stop the source, contain it, clean up in accordance with the

MSDSs and notify relevant authorities

6 BUILDING SERVICES

Actions If applicable Responsible Person

Fill in service trenches as soon as work is completed to minimise erosion Cover service trenches with plastic sheeting or another suitable cover if

filling cannot be immediately completed

Connect guttering and downpipes to the stormwater system as soon as the roof is completed

Other: Ensure there are no cross connections made between the stormwater and public sewerage system

7 LANDSCAPING

Actions If applicable Responsible Person

Once no longer required, reinstate ground level around the works, fill spoon drains and sediment basins, level blanks and remove surplus soil

Complete landscaping and revegetation as soon as possible following building activities

Ensure sediment control measures are in place until all vegetation is established

Regularly check all sediment control structures to ensure they are working effectively

Ensure that no disturbance of the nature strip occurs between the site and the roadway

Do not locate stockpiles within 2 metres of hazard areas such as spoon drains or areas of high flow

Ensure stockpiles and open dusty areas are damped down as required Cover stockpiles as needed to minimise dust Ensure that soils and fill used in landscaping area are free from weeds and

weed seeds

Ensure appropriate trees are chosen for the site and location relative to building and services considering their eventual height and root system

Page 30: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 30January 2012

DEMOLITION WASTE MANAGEMENT

Waste Materials

Estimated quantity Planned Actions

(1)

Vol(m3) (2)

Mass (t) (3)

On site reuse (specify proposed reuse or recycling methods) (4)

Off site recycling/ reuse (specify recycler and recycling outlet) (5)

Disposal (specify contractor and landfill site) (6)

Cardboard packaging

Bricks

Timber

Tree waste

Tiles

Pavers

Concrete

Metal waste

Rubble

Mixed waste

Plastic

Asbestos

Synthetic fibre

Other (specify)

Page 31: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

de Groot & Benson Pty Ltd

Construction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc

Page 31January 2012

APPENDIX C – Sediment and Erosion Control Plans for Construction Phase development

Page 32: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

Drawing No.

Coffs Harbour NSW 2450

236 Harbour Drive

A.C.N. 052 300 571

Pty Ltd

de Groot &

Benson

Email [email protected]

Fax (02) 6652 7418

Phone (02) 6652 1700

Engineers &

Planners

Consulting

ApprovedDesign

NAMBUCCA SHIRE COUNCIL

APPROVED ON BEHALF OF

Drawn

Date

DATE

CITY ENGINEER

CheckedSheet No.

COPYRIGHT 2008

AP.BYDR.BYREVISIONDATERDG JAN 2012

RDGJAT

AS SHOWN

91111-170

RDG

REV

Amendment No.

Council No.

Scale

Surveyed

-

DVD No.

5

Datum

AHD

BELLWOOD, NAMBUCCA HEADS

PROPOSED SUBDIVISION OF LOT 2 DP1119830

STAGE A - SEDIMENT AND EROSION CONCEPT

Drawing No.

Coffs Harbour NSW 2450

236 Harbour Drive

A.C.N. 052 300 571

Pty Ltd

de Groot &

Benson

Email [email protected]

Fax (02) 6652 7418

Phone (02) 6652 1700

Engineers &

Planners

Consulting

ApprovedDesign

NAMBUCCA SHIRE COUNCIL

APPROVED ON BEHALF OF

Drawn

Date

DATE

CITY ENGINEER

CheckedSheet No.

COPYRIGHT 2008

AP.BYDR.BYREVISIONDATERDG JAN 2012

RDGJAT

AS SHOWN

RDG

REV

Amendment No.

Council No.

Scale

Surveyed

-

DVD No.

5

Datum

AHD

LEGEND

AREA NOT TO BE DISTURBED

AREA IN CUT

STAGE ACCESS POINTS

DIVERSION DRAINS

SEDIMENT FENCES

FINISHED CONTOUR

GEOFABRIC UNDER ROAD TO PREVENT SCOURING

STOCKPILE

TOPSOIL

WORKS SHOWN

OUTSIDE STAGE A WILL

BE CONSTRUCTED IN

THEIR RESPECTIVE

STAGES.

SEPARATE PLANS WILL

BE PREPARED FOR

THESE STAGES.

NOTE:

WORKS ARE SHOWN FOR INDICATIVE FOR STAGE A ONLY.

ADDITIONAL PLANS WOULD NEED TO BE PREPARED FOR

THE OTHER STAGES WHEN CONSTRUCTION FOR THESE

STAGES IS PROPOSED.

REFER SHEET 171 FOR NOTES AND DETAILS

Page 33: CONSTRUCTION and ENVIRONMENTAL MANAGEMENT · PDF fileConstruction Management Plan – Alexandra Drive Job No: 91111– File name : 91111 Construction Management Plan Jan 2012.doc Page

Drawing No.

Coffs Harbour NSW 2450

236 Harbour Drive

A.C.N. 052 300 571

Pty Ltd

de Groot &

Benson

Email [email protected]

Fax (02) 6652 7418

Phone (02) 6652 1700

Engineers &

Planners

Consulting

ApprovedDesign

NAMBUCCA SHIRE COUNCIL

APPROVED ON BEHALF OF

Drawn

Date

DATE

CITY ENGINEER

CheckedSheet No.

COPYRIGHT 2008

AP.BYDR.BYREVISIONDATERDG JAN 2012

RDGJAT

AS SHOWN

91111-171

RDG

REV

Amendment No.

Council No.

Scale

Surveyed

-

DVD No.

5

Datum

AHD

BELLWOOD, NAMBUCCA HEADS

PROPOSED SUBDIVISION OF LOT 2 DP1119830

STAGE 1 - SEDIMENT NOTES

Drawing No.

Coffs Harbour NSW 2450

236 Harbour Drive

A.C.N. 052 300 571

Pty Ltd

de Groot &

Benson

Email [email protected]

Fax (02) 6652 7418

Phone (02) 6652 1700

Engineers &

Planners

Consulting

ApprovedDesign

NAMBUCCA SHIRE COUNCIL

APPROVED ON BEHALF OF

Drawn

Date

DATE

CITY ENGINEER

CheckedSheet No.

COPYRIGHT 2008

AP.BYDR.BYREVISIONDATERDG JAN 2012

RDGJAT

AS SHOWN

RDG

REV

Amendment No.

Council No.

Scale

Surveyed

-

DVD No.

5

Datum

AHD

SEDIMENT AND EROSION CONTROL NOTES

GENERAL

SITE INFRASTRUCTURE

CLEARING

TOPSOIL STRIPPING

EROSION CONTROL

SEDIMENT CONTROL

SEDIMENT CONTROL (Cont)

DUST CONTROL

TOPSOIL REPLACEMENT

REVEGETATION

MONITORING

MAINTENANCE

AT COMPLETION

EVALUATION

Cross Section of Typical Sediment Basin.

Plan View of Typical Sediment Basin

Temporary Construction Exit

Straw Bale Drop Inlet Sediment Trap.

Straw Bale Check Dam

Rock Check Dam

Sediment Trap.

Geotextile Filter Fabric Drop Inlet

Portable Gravel Kerb Inlet

Sediment Trap

Level Spreader (or Sill)

Sediment Fence.

Sandbag Kerb Inlet Sediment Trap.

Culvert Entry Sediment Trap.

Perimeter Bank (without channel)

Perimeter Bank (with channel)

Hay Bail Sediment Fence.