Construction Acc
Transcript of Construction Acc
-
8/8/2019 Construction Acc
1/85
WORKING AT DIFFERENTLEVELS
byS. A. Solanki
Deputy Director
Industrial Safety & Health (Retd.)
-
8/8/2019 Construction Acc
2/85
WORKING AT HEIGHT
Most of fall accidents happen while
working at height and most of them prove
fatal. Therefore seriousness of fall
accidents should be considered seriously.Fall accidents contribute at 10 to 20% total
fatal and 15 to 80% non-fatal accidents.
-
8/8/2019 Construction Acc
3/85
Types, Cases and Control of Fall Accidents
Falls and accidents due to falling objects can
be classified as under:
(A) Falls of Persons:
Falls from heights viz. structure, floor,
ladder, scaffold, platform.Falls into depth (negative height) viz.
wells, pit, sump, silos, ground, tank,
vessel, excavation, ditches.
Falls on the same level viz. falling or
slipping on the floor or flat at the standing
level.
-
8/8/2019 Construction Acc
4/85
(B) Falling Objects (bodies):
Falls of objects from height viz. tools,
machine part, equipment, material. Falls of objects from the hands of the
same person viz. tool, equipment,material being handled.
Structural collapse viz. wall, buildingceiling, pipe, ladder, scaffold, beam,truss.
Material collapse viz. falling of piles of
goods, layers of begs, cloth, paper rolls,carton boxes, grain, cement andfertilizer:
Slides and cave-ins viz. earth, rock, sand,stones, snow, ice.
-
8/8/2019 Construction Acc
5/85
Most serious accidents due to falls and
struck by falling bodies take place in miningand quarrying, building and construction,
structural repair, alteration, cleaning,
painting, demolition, maintenance and
unsafe use of lifting and other equipment. Major causes of such accidents are
makeshift arrangement, unsafe floor, unsafe
work practices, not using helmet, safety belt,
safety shoes, unsafe use of vehicles, poorsupervision, poor lighting etc.
-
8/8/2019 Construction Acc
6/85
Common Causes of Falls are:
Water, oil or grease not cleaned up.
Loose, defective broken floor or tow
board.
Scrap, chipping, swat and obstructions
lying on the way. Dusty, steamy or smoky atmosphere
restricting vision.
Carrying too much load making it difficult
to see over the load.
Warn out or unsuitable footwear.
Poor lighting, glare or shadows.
-
8/8/2019 Construction Acc
7/85
Rushing instead of walking.
Defective or weak scaffolds.
Ladders, ramps, planks and platformsnot rigid or safe for the job.
No or inadequate handrails.
Climbing oddly instead of using ladder.
Throwing instead of lowering tools ormaterials while working aloft.
Not using spectacles for clear vision.
Not using crawling board on fragile roof.
Not using a safety belt or using in awrong way, e.g. not tying its free-end ortying it with a weak support.
-
8/8/2019 Construction Acc
8/85
Not closing the manhole cover or floor-
opening etc.
Allowing roof work and floor work at a
time in the same vertical plane.
Touching of crane boom, hook etc. to
weak or unfastened structure. Non-compliance of statutory provisions.
Most of the falls from height prove fatal
or result in serious fracture. Therefore
their prevention or control is utmost
necessary.
-
8/8/2019 Construction Acc
9/85
Control Measures for Fall Accidents:
Safe, sound and dry (non-slippery)surfaces for walking and working.Fencing, guarding and tow boards.
Safe helmet, safety belt, foot-wear, etc.
Safe practice in walking and working. Noexcessive load lifting.
Safe means of access while working atheight or depth.
Use of crawling board, cat ladder, fallarrester net etc. while working on fragileroof.
-
8/8/2019 Construction Acc
10/85
Use of Safety work permit for working at
height or in depth. Safe and sound stairs, ladders, scaffold
etc. and safe use thereof.
Good lighting and supervision, cutting
off power supply in overhead electriclines.
Safety cordon to disallow persons in the
area where any object may fall from
height.
Removal of 20 causes mentioned above.
-
8/8/2019 Construction Acc
11/85
Statutory Provisions
Section 32 and 33 of the Factories Act, 1948
provide precautions regarding floors, stairs,means of access, pits, sumps, openings infloor etc. Accordingly all floors, steps, stairs,passages and gangways should be of soundconstruction, properly maintained and keptfree from obstructions and substances likelyto cause persons to slip. Steps, stairs,passages, gangways with substantialhandrails, fencing and safe means of access toevery work place, shall be provided to preventa fall and ensure safety.
Every fixed vessel, sump, tank, pit oropening in the ground or in the floor whosedepth, situation, construction or contents aredangerous should be securely covered orfenced.
-
8/8/2019 Construction Acc
12/85
Rule 68 describes the ladder quality that it
should have hooks or an effective non-skiddevice.
Rule 68E, GFR, provides for suitable andsufficient ladders, duck ladders or crawling
boards and a permit to work system whileworking on fragile roofs at a heightexceeding 3 mt.
Schedule 19 and other Schedules u/r 102 of
the Gujarat Factories Rules prescribe rules,for working at height and depth.
-
8/8/2019 Construction Acc
13/85
Section 36 prescribes details of entering any
confined space. Before such entry, the space
is to be made free of dangerous fume, gas,vapour or dust. Work permit system should
be followed and a suitable breathing
apparatus and safety belt to be used by the
person. Section 36 A require a portable electric light
up to 24 V and a flameproof lamp for
flammable atmosphere.
Dimension of manholes, under rule 64 of the
Gujarat Factories Rules are given as circular
41 cm diameter or rectangular 41 cm x 31 cm.
-
8/8/2019 Construction Acc
14/85
Safety requirement while working at Height
Falls happen due to falling from stairways,
runs, ramps, gangways, floors and ladders.
Therefore safety aspects of their design,construction and use are explained below:
-
8/8/2019 Construction Acc
15/85
Stairways:
The slope of a stairway should be 300 to 350
with the horizontal. The tread width shouldnot be less than 24 cm plus a non-slipnosing of 2.5 cm. the riser height shouldnot be more than 20 cm and not less than12.75 cm and should be constant for each
flight. All stairways should be fitted withrailings on the open sides and hand rails onsides which are otherwise enclosed. Theheight of the railings at the stairs should benot less than 75 cm or more than 90 cm
measured from the top surface of the stairtread. The stair landings should beprotected by railings and toe-boards. Non-skid strips on stair treads can preventslipping.
-
8/8/2019 Construction Acc
16/85
Adequate lighting on stairway should be provided to
avoid accidents. Two formulate are quoted in ILO
literature.
d + h = 46 cm nosel = d + n(d + 2h)
Where d is the depth of the step, h is the height of the riser,
n the number of steps and l the length of the landing.
l
l
d
h
d
n
-
8/8/2019 Construction Acc
17/85
Recommendation for h is 16 to 20 cm, then dshould be 30 to 26 cm.
The width of the staircase should be more than 75
cm. Instead of continuous steps, groups of 5 to 6steps should be preferred. Turning staircases shouldbe avoided. Steps is outdoor staircases should havea slight (1 to 2%) slope towards the nose to run awaythe water.
Stairways should be of fireproof material to givesupport for a longer time. Stairwell acts as achimney. Therefore if should be kept free fromsmoke and gases. This can be achieved by providingtop and bottom ventilation and self-closing firedoors on each landing. Double doors are provided to
form an air lock. In high rise building, positiveventilation pressure is applied in case of fire, to driveaway smokes.
Proper signs and symbols should be marked intraffic aisles. Arrows for escape routes arenecessary.
-
8/8/2019 Construction Acc
18/85
Ramps, Runways and Gangways:
The slope of ramps, runways, gangways
etc. should be as small as possible and the
recommended maximum is 150 to the
horizontal. Cleats not more than 40 cm
apart, should be provided on ramps with
steep slopes. Toe-boards should be
provided where a ramp extends over a work
place or a passage. Wire screens are
necessary on the sides, if there is a risk of
materials falling through the sides.
Runways are long with uniform slope as
they are at arodram.
-
8/8/2019 Construction Acc
19/85
Floors and Platforms:
The design should consider all types of loadin the form of materials, persons and otherforces acting on the floor. Acid proof brickslaid in acid resistant plaster should be thechoice of flooring for a workroom in whichacids are handled. Unprotected floor edges
situated at heights and openings, sumps,pits etc, in platforms or floors should beprotected by railings, toe-boards or guards.The height of the railing from the baseshould be not less than 90 cm or more than
120 cm. It should have intermediatemembers to shorten the gap less than 47cm. The toe-board should not be less than15 cm in height.
-
8/8/2019 Construction Acc
20/85
Floors should be of sufficient strength and
shall never be overload. They should be non-
slippery, free from holes, openings, pinch
points, uneven surfaces, irregularities,
accumulation of oil, water, waste, dust etc.
Near wet processes and water showers,proper drainage should be provided.
Open gutters and floor openings (holes,
chutes, inspection plates) must be fenced or
guarded to protect unwary persons orprevent material falling through it to the floor
below.
-
8/8/2019 Construction Acc
21/85
Non-conductive floor in explosiveatmosphere pose special hazard. Discharge
of static electricity generates spark whichcan ignite the explosive mixture near thefloor. Therefore steel tipped or nailed bootsor dropping of steel tools on such floor ishazardous. Such floors must be earthedproperly.
In industry, criteria for floor selection aremany. In addition to strength, comfort andcost, resistance to (a) wear and abrasion (b)chemicals (c) fire (d) environmental factorsand (e) material in process are also to beconsidered.
-
8/8/2019 Construction Acc
22/85
Floors are also of many types. Acids andalkali should be avoided on concrete,
granolithic, linoleum, magnestite, quarry tile,ceramic, wood and terrazzo type floor.Solvents and oils should be avoided onrubber, thermoplastic, vinyl and vinylasbestos floor. The cleaning process shouldnot damage the floor affecting its strength oranti-slip properties. Cleaners like soaps,natural detergents, alkaline solution,abrasive powder and damp floor cloths
should be used. Slope is an important factor in floor design. 1
to 2 % gradient towards drain helps ensureto flow away water and keep the surface dry.
-
8/8/2019 Construction Acc
23/85
Ladders:
Ladders may be classified under two broad
categories, the portable and the fixed.Since the portable ladder is a ratherhazardous piece of equipment, every effortshould be made, wherever possible, to
replace it by fixed stairs, fixed ladder,scaffolding, or any other suitablearrangement. Not using ladders whererequired is a common cause of seriousaccidents. Men climb on machines,
equipment, boxes, barrels, etc. to getaccess to places above the floor and thusget involved in accidents.
-
8/8/2019 Construction Acc
24/85
Ladders should rest on firm ground and its
top should extend at least 1 m above the
place of landing.
Step (Swing back) ladders and folding trestle
ladders: In situations where there is no
suitable facility to lean the ladders, suchladder should be the right choice. Step
(Swing back) ladders are generally provided
with a convenient platform and a hand rail at
the top.
-
8/8/2019 Construction Acc
25/85
Fixed ladders: Wherever the length of a fixed
ladder exceeds 9 m, it is necessary toprovide a crinoline for ensuring the safety of
the user. Alternatively, a suitable fall arrester
should be used. In the fall arrester a slide
runs smoothly up and down a steel cablefitted along with the centre of the ladder. The
slide is attached to the users belt by a chain.
The slide moves up and down the cable as
long as the user climbs or descends the slidecauses it to catch on the cable and thus the
fall is arrested (controlled).
-
8/8/2019 Construction Acc
26/85
Transport of ladders: Ladders should be
carried always with the leaning end at least 2m above the ground. Long and heavy ladders
should be carried by two or more persons.
The ladder is safest and easiest to climb
when it is at an angle of about 750 to thehorizontal, i.e. a slop of about four vertical to
one horizontal.
Portable ladder should not be more than
20 ft long.
-
8/8/2019 Construction Acc
27/85
Non-slip devices for ladder feet: Slipping ofthe feet of the ladder can be prevented by
fixing non-slip ladder shoes to the stiles.They are of fixed or pivoted type, and thesoles may be of rubber, cork, braided rope,leather, felt or lead. Steel spikes or pointed
ferrules fixed to the feet of the stiles, alsoserve as ladder shoes. Lashing the ladder byside guys should be resorted to where noanchorage is available near the top. A verylong ladder should also be tied by guy ropes.
-
8/8/2019 Construction Acc
28/85
Climbing ladders: A person ascending ordescending a ladder should always face theladder. Facing away from the ladder while
descending is a dangerous practice. Whenclimbing or descending a ladder, the rungsshould be held firmly hand over hand. It is easierand hence safer for a person to cling on to arung than to a stile, in case the foot slips.
However, in the case of fixed ladders with widesteps and narrow stiles, it is safer to hold thestiles. Tools should be carried in a holsterattached to a belt or in a tool bag or box slungfrom a strap over the shoulder. The safestprocedure is to hoist or lower the tools andmaterials by a rope. There is greater danger ofslipping when the footwear or rungs are wet,dirty or covered with paint, plaster, grease or oil.
Therefore they should be cleaned.
-
8/8/2019 Construction Acc
29/85
Work on ladders: Working from the top of asingle ladder can be particularly dangerouswhen the job requires the use of both hands.
The safer way is to stand on a rung about ameter below the top rung to which safety beltis attached. The equilibrium of ladder can beeasily upset if one leans sideways.
Misuse of ladder: Use of trestle ladders assingle ladders can easily lead to accidents.Crawling ladders used over roofs are notdesigned for use as ordinary single ladders.They should be supported throughout their
length. Likewise, single ladders are notdesigned to be used in a horizontal positionas bridges or platforms.
-
8/8/2019 Construction Acc
30/85
A door should be closed before
placing ladder over it. Do not use metal
ladder near live electric lines. Use the ladderby facing toward it and not otherwise.
Ladders should not be put on aisle. Do not
rest it on drums, machines, boxes etc. to
reach at height. Filling in cracks and faults orcovering up repaired portions with putty and
paint is a dangerous practice as the potential
weak points are then hidden and cannot be
detected during inspections. Ladders shouldnot be allowed to lie in the open exposed to
the sun and the weather.
-
8/8/2019 Construction Acc
31/85
Scaffolding:
General Requirements:
A scaffold is a temporary structure thatprovide support for workers, plant andmaterials used in building, construction,maintenance, repair and demolition work.
The scaffold serves two purposes. One isto provide a convenient platform forpersons to work at height and the other isto provide a safe means of access to allplaces where any person may be required
to work at any time. Accidents at scaffoldsare generally caused either due to directcollapse of the scaffold or as a result ofpersons or material falling off the scaffold.
-
8/8/2019 Construction Acc
32/85
The scaffolds should be of sound material,sufficient strength (4 times the expectedload) and properly designed. Their erection,
alteration and dismantling should be doneunder the supervision of a competentperson. They should be securely supportedor suspended and should be properly
strutted or braced to ensure stability. Normalsize is 4 cm thick x 23 cm wide x 3-4 m long.
Steel components of tubular (normally 5 cmdia) scaffolds should conform to IS:2750 and
4014 for Steel Scaffoldings. Wood andbamboo should meet the specifications laiddown by the Forest Research Institute andCollege, Dehra Dun.
-
8/8/2019 Construction Acc
33/85
Overhead protection, not more than 3 m
above the work platform of the scaffoldbecomes necessary if overhead work is
going on. Similarly for the persons working
or passing under a scaffold, at least 30 cm
projected canopy or screen should beprovided at the scaffold working level.
In high wind or storm work on scaffold
should the avoided. No hot work should be
carried out on wooden platform. Fire fighting
facility should be kept nearby.
-
8/8/2019 Construction Acc
34/85
Means of Access: Failure to provide such
access has caused serious accidents. The
safe means of access may be ladders,portable or fixed, ramps, runways, gangways
or stairways. It is recommended that portable
ladders should not be used as a means of
access where the height of the scaffoldplatforms exceeds 3.75 m. Slope of the
ladder should be 4 vertical to 1 horizontal. It
should rise 1 m above landing platform and
securely fixed at upper end. The use of crossbraces or framework of the scaffold as a
means of access should not be permitted.
-
8/8/2019 Construction Acc
35/85
1 If the platform is used as a footing only. 0.7 m
2 If the platform is used for the deposit of
material
0.9 m
3 If the platform is used for support of anyhigher platform
1.1 m
4 If the platform is one upon which stone
or bricks are dressed or roughly shaped
1.3 m
5 If the platform is used for support of any
higher platform and is one upon which
stone or bricks are dressed or roughly
shaped
1.5 m
Width of working platforms: The following minimum
widths are recommended as a general rule.
-
8/8/2019 Construction Acc
36/85
Railings and toe-boards: A common cause of
accidents at scaffold is the failure to provide
railings at the exposed sides of the scaffoldplatforms. Often, the failure is when the
scaffolding is erected for jobs of short
duration. Where materials are stacked on a
platform, the height of the toe-board mayhave to be raised; or it may even be
necessary to cover the entire space between
the top rail and the toe-board with wire
netting or planks. Normal height of railing is
1 m and toe board 15 cm.
-
8/8/2019 Construction Acc
37/85
Boards and planks in working platforms,gangways and ramps: For platforms of
wooden planks, in general, the spacingshould not exceed the following:
Planks 32 mm thick 1 m
Planks 38 mm thick 1.5 m
Planks 50 mm thick 2.6 m Boards or planks which form part of a
working platform, gangway or ramp shouldnot project beyond their end supports to a
distance exceeding four times the thicknessof the board or plank. 50 mm projection isdesirable. Overlapping of boards is unsafe.
-
8/8/2019 Construction Acc
38/85
Hazards and Safety measures: Scaffolds
should never be loaded in excess of the
working load for which they are designed.Wood scaffolds are not generally painted.
However, in case of ladders and certain
permanent types of scaffolds such as the
mobile scaffold, protection is generallyprovided by periodically treating them with a
coating of linseed oil.
-
8/8/2019 Construction Acc
39/85
-
8/8/2019 Construction Acc
40/85
Scaffold foundation should be verified before
erection. Loose or friable packing like bricks
should not be used as support. For heightmore than 15 mt, steel scaffold should be
preferred and not a wooden one.
Inspection after 7 days and after every
damage is necessary. Points to be checkedinclude: stability, ties and fixing, alignment
of members, bending, tightness of lashing or
couplers, planks, platforms, guard rails, toe
boards and condition of ladders.
Warning notice should be displayed near
incomplete or damaged scaffold.
-
8/8/2019 Construction Acc
41/85
Dismantling should be carried out in thereversed order to erection. Materials should
not be thrown from heights and should notbe left lying here and there. They should beproperly collected.
After completion of work, all scaffold
materials should be stored in a dry protectedplace using racks, boxes or trays. Thedamaged parts should be replaced orrepaired, cleaned, treated with preservative
or paint. Couplers and other fittings shouldbe lubricated.
-
8/8/2019 Construction Acc
42/85
Types of Scaffold:
Some common types of scaffold are as follows:
Pole type scaffolds: It may be an independent structure or the
putlog type erected and supported near wall
or another structure.
The uprights (vertical poles) should rest on
strong foundation to support load without
settlement. They should not be kept more
than 3 mt apart. Tubular uprights have steel
base plates places on wooden sole plates.
Soft ground should be well rammed and
leveled.
-
8/8/2019 Construction Acc
43/85
Fixings like steel bolts, nails or fibre rope of
approved size, joint pins and couplers
should be properly fitted. For load bearing
right-angled or swivel couplers should be
used. Putlog members (horizontal) should at
least 10 cm be inserted in wall. Bracing
(diagonal connection) should be tied to
ensure structural stability and prevent
buckling. To prevent overturning the scaffold
should be secured at intervals not greater
than 7.6 m vertically and horizontally.
-
8/8/2019 Construction Acc
44/85
Rolling Scaffolds or Mobile Towers:
Such scaffolds move on rollers (wheels) orcastors with wheel locking device. They are
portable and most useful for maintenancework.
To prevent overturning, height should not bemore than three times the minimum width ofthe base. Minimum base length should be 4 ft.
While pushing or pulling the tower, personsshould not ride on it. Tools and materialsshould be removed before moving.
The top working platform must have handrailsand toe boards. It should support 30 lb/ft2
distributed load. Rigidity of the tower issecured by diagonal bracing on all four sidesand on plan.
Moving the tower by pulling at the top orleaning sideways should be avoided.
-
8/8/2019 Construction Acc
45/85
Outrigger Scaffolds:
It is a balcony type cantilever scaffold
resting on wall. If other types of scaffoldare possible, this type should not be used.
The outriggers should be passed rightthrough the wall and be secured on the
inner side. Supporting hook between brickjoints is dangerous.
Platform should not project beyond 2 mtfrom the wall. Guard rail and toe board
should be provided.
-
8/8/2019 Construction Acc
46/85
Swinging (Hanging) Scaffolds:
Here the platform is hanging by two chain
pulley blokes, ropes and hooks onsupporting beam. Suspended platform can
be raised or lowered as per need.
Movement of both the ends should be
simultaneously. They anchorage and thesuspension gear should be strong enough
to withstand the load with good factor of
safety. Suspension ropes should withstand
6 times the intended load. Rope diametershall be more than 0.75 inch.
-
8/8/2019 Construction Acc
47/85
A safety rope shall be provided in addition tothe suspension ropes.
The width of the platform should be morethan 50 cm and less than 90 cm. Guard railsand toe boards necessary on all the threesides open. The platform should be lashed or
secured while in use, to prevent swaying. Each person working on swinging scaffold
should wear safety belt with lifeline attachedto an anchorage other than the scaffold
itself.
-
8/8/2019 Construction Acc
48/85
Suspended Scaffolds:
Two or more platform are suspended byropes from overhead outriggers anchoredto the building.
Such scaffolds are designed with a factorof safety 4 and shall never be overloaded.Anchor plates should be tied with U bolts.
Counter weights are used to preventoverturning. Wire ropes (FS 6) are used tosupport scaffold. Hoisting drum (like winch)is used with at least 2 dead turns. Gapbetween handrail and toe board should be
covered by a wire mesh of 38 mm and 16gauge wire. Overhead protection should beprovided if risk of falling objects ispossible.
-
8/8/2019 Construction Acc
49/85
Boatswains Chair:
Boatswains chair is used for supporting andhoisting single person in sitting position.
General chair (seat) size is 60 cm x 30 cm,with 25 mm thick timber. Cleats extending infront to at least 23 cm should be securelyfixed under the chair at both ends. The chair issupported by a suitable sling passing through
the four corner holes in the chair for properstability. The suspension rope is fixed to anoverhead support or passed through a pulleyblock fastened to such support. The free endis secured to a conveniently accessibleanchorage and the person in chair must weara safety belt, the life line of which is securedto the tackle supporting the chair. Fibre ropeslings should not be used if the person in thechair has to do welding or cutting work.
-
8/8/2019 Construction Acc
50/85
Safety Belts and Harness:
In addition to all engineering controls and
work permits, personal protectiveequipment should not be forgotten while
working at height or depth.
Safety belts of various types are available.
Pole safety belt, general purpose safetybelt with or without remote anchorage and
harness (man hoisting by another man)
type safety belt are in common use. They
should fulfil IS specifications. They are
available in leather and webbing of natural
and man made fibres, of which, webbing is
superior to leather.
-
8/8/2019 Construction Acc
51/85
Webbing can withstand loads 3 to 4 timesthat of leather of the same size. Web material
may be cotton, nylon or Dacron. Whileselecting a belt, its normal and emergencyuse should be considered. Life lines ofmanila rope of 19 mm diameter or nylon ropeof 13 mm diameter are suitable provided a
shock absorbing device is available. Care ofbelts is always necessary.
Respiratory equipment should be selecteddepending upon the working environment.
Harness consists of a safety belt and rope orlifeline. It can stop a person falling or he canbe pulled out if working below in a confinedspace.
-
8/8/2019 Construction Acc
52/85
General Requirements:
All workers working at height of more than 2
m (window cleaners, construction workersetc.) must wear safety harnesses i.e. safetybelts connected with ropes. The belt shouldbe tied with the body while the free end ofthe rope should be anchored with a fixedunbreakable sound structure or should beheld by another person standing outside aconfined space when the wearer is workinginside. The belt and rope should be of sound
material, examined by a competent personevery six month and maintained in very goodcondition.
-
8/8/2019 Construction Acc
53/85
Length of the rope is normally 2 m sincemore fall height and sudden arrest maycause internal injuries to the workers.
But in case of working in depth the ropelength should be more than 2 m andextending upto the bottom level of workingsince the worker is to be pulled out when hegives indication of any difficulty to him orwhen it is observed by the person holdingthe rope, standing outside and watching theperson working inside.
Workers should be trained, encouraged and
supervised to wear safety belt properlybecause it can save their precious lives.
All safety equipment are to be freely suppliedby the employer and it should be seen thatworkers use them. This is a statutory
requirement.
-
8/8/2019 Construction Acc
54/85
-
8/8/2019 Construction Acc
55/85
Safety block (like chain pulley block or hoistingdrum block) is used to connect the wire ropewith the safety belt to allow more freedom of
movement. A sudden pull operates lock or braketo stop the rope. Because of a friction brake onthe rope drum, jolt is avoided and the fallingperson is stopped smoothly. In anotherdesign, a
centrifugal brake is applied on the drum so thatthe person descends slowly to reach the ground.
Tensile tests and drop tests are carried out onsafety belts and apparatus used with them.
Safety belts should be kept in a cool, dry andwell ventilated place. Regular cleaning, visualinspection for defects and repair only b y acompetent person are necessary for goodmaintenance.
-
8/8/2019 Construction Acc
56/85
Types of Safety Belts:
Mainly four types of safety belts are in practice:
General purpose Safety Belt:
It consists of a waist belt, a restraining line(lifeline) and the metal components. Strapscovering shoulders, chest, waist and hips arepreferable as by wearing it the forces during
fall will be absorbed not only by the trunk butalso by the legs. Choice of model depends onworking method, time of work, environmentalfactors etc. Rope (normally 2 m) is attached toD ring secured to the waist belt.
For window cleaning, straps are long enoughto fit windows and terminate in snap hooks foranchor on each side of the window. Tworestraining lines are used for window cleaners
belt.
-
8/8/2019 Construction Acc
57/85
Linemans or Pole Safety Belt:
To climb on poles, towers, masts, trees etc.
these belts are used. They are used as
support while climbing and protection while
falling. Here waist belt is fitted with 2 D-
rings at different points. The length of therestraining line is adjustable by a buckle.
Generally fall is restricted to 60 cm.
-
8/8/2019 Construction Acc
58/85
Harness (Man hoisting) Safety Belt:
It is used for working in a confined space,
silo, tank, vessel etc. The life line is held bya person standing outside to rescue thewearer when he is unable to come out byhis own efforts. On the rescue line there isa wrist strap by which the wearer can behauled up through a manhole or otheropening.
Work permit should be followed and thework place should be made free from any
toxic/flammable vapour and oxygendeficiency.
-
8/8/2019 Construction Acc
59/85
Fall Arrester or Anti fall Device:
Here waist belt is connected to a sliding
anti fall device which automatically stopswhile moving in fall direction. Here fallarrest distance is small due to close (short)life line.
Anti fall systems are of two types (1) With asliding and blocking device on a verticalsafety support (pole, cable rail) (2) With anautomatic catching device for rolling,unrolling and blocking a tether (cable, rope,strap). Specific braking system includes anabsorber of kinetic energy used with atether.
-
8/8/2019 Construction Acc
60/85
A competent person should be consulted
for selection of appropriate device. A cross
belt is tied with the body and a sliding
mechanism moves with the body in upward
direction but it will be locked and stop the
fall at the descending movement. Other type
allows the horizontal (to and fro) movement
but will catch the falling body through rope
and a shock absorber.
-
8/8/2019 Construction Acc
61/85
Safety Nets:
Where safety belt is not possible or inaddition to safety belt for further safety of aperson, particularly when fall height is veryhigh or falling in sea or deep water ispossible, or work surface is fragile andsudden fall is possible, safety net is verymuch essential to catch a falling person.Net is useful to stop a fall of a person aswell as of falling objects. For stoppingfalling material, the mesh size should besmall.
The net and the structure to which it isattached should be capable of catching andsupporting at least two persons at a time.
-
8/8/2019 Construction Acc
62/85
The nets are made of synthetic fibres which
are strong, light weight and weatherproof.Diameter of the mesh cords and that of theborder cord should be at least 3 mm and 8mm respectively.
Standard net size is 6 x 4 m but it can bemanufactured of required sizes also. Themesh size of 5 x 5 cm is preferable. Forfalling objects that size should be 3 x 3 cm.
Four corners should have eyes to support.
Big net should have eyes every 2 m on theboarder cords. Two nets can be connectedwith each other to cover more surfaces.
-
8/8/2019 Construction Acc
63/85
While attaching net with the structure, somesafety distance should be maintained. It
should not be lower than 3.5 m below theworking level and less than 3.5 m above anyobject or structure below the net. The netmust project at least 2 mt. outside the falling
area. Nets should be cleaned regularly and
checked periodically for cuts and otherobjects. It should have serial number so asto keep record of maintenance.
Nets should be kept on pallets in a dry, cooland well ventilated place. It should be keptaway from chemicals and hot materials.
W ki R f
-
8/8/2019 Construction Acc
64/85
Working on Roofs:
Serious accidents happen due to fall ofpersons working on roofs. Fall through
fragile roof sheeting, loss of balance due tothe slope of the roof or effect of wind andinsufficient care while working at the edgeof the roof constitute the principal causesof such accidents which could be
prevented by appropriate safety measureslike crawling or walk-boards, railing, safetybelt and safety net.
Use of a safety belt alone while working ona fragile roof or at a height more than 6 ft(2m) is not permitted. It is dangerous andmany fatal accidents have happenedbecause of this condition. Sound platform,adequate support or safety net should alsobe provided.
-
8/8/2019 Construction Acc
65/85
Factors affecting fall of roofers are workingheight, nature, shape and slope of the roof,roof covering material, roof condition and the
weather. Low-strength roofing materials are
asbestosis, cement, glass, plastic, wood androofing tiles. Heat, rain, humidity, pollutionand corrosion spoil the roof condition.Hidden cracks in a roof increase the hazard.
The shape of the roof-flat or sloping with astraight, polygonal or curved profile affectsthe fall direction. Water, oil, snow, moisture,
chemical, dust and other deposits on roofsurface increase fall proneness. High windand bigger sized sheet in hands cause aroofer to lose his balance.
-
8/8/2019 Construction Acc
66/85
Whatever may be the reason, danger offalling toward the roof edge or fallingthrough the roof opening is always there.Smoke or gas coming on the roof oroverhead electric power lines alsocontributes hazards.
Roof work should be pre-planned and only fit
and skilled workers should be employed. Assessment of the nature of work and
possible hazards will help to draw safetywork permit. Fixed or mobile scaffold, flatladders (roofers ladder), sufficient cat
ladders or crawling boards side by side,safety belts and nets must be provided toeach roofer.
-
8/8/2019 Construction Acc
67/85
-
8/8/2019 Construction Acc
68/85
Falls through fragile roofing materials: Thecommon practice to walking along the
purling cannot be relied upon. The best wayto prevent falls through such fragilematerials is to use cat or roof ladders. Theyshould be at least 38 cm wide and shouldhave cross battens at least 3.2 cm thick,
fixed not more than 38 cm apart. Safety beltsand fall arrester net should also be used asan additional precaution. A permit-to-worksystem under the control of a responsible
person can help to ensure that the workersare not allowed to work on roofs withouttaking appropriate safety measures.
-
8/8/2019 Construction Acc
69/85
Reinforced AC sheets are now available inthe market. They are not a fragile as normal
AC sheets. The manufacturer Eternit EverstLtd., New Delhi, names their product asEverest Lifeguard and tells it a solution forSafety on Roof Tops. Their literature runsas under:
Everest Lifeguard a high strength fibrecement sheet, with Polypropylenereinforcement strips inserted along preciselyengineered locations which run the full
length of the sheet in each corrugation, thusproviding maximum reinforcement strengthwith no loss of durability in service.
-
8/8/2019 Construction Acc
70/85
This product has been developed in
conformance of the guidelines issued by
UKs Health & Safety Executive, with regardto Health & Safety on roof work (HSG33).
Falls from sides of roof: In case of flat roofs,
either the standard railings and toe-boards or
a complete barrier to a minimum height of 90cm should be provided. For sloping roofs,
the barrier may be in the form of scaffold
boards extending to a minimum height of 40
cm above the roof surface and a guard rail ata height more than 90 cm but not more than
120 cm.
-
8/8/2019 Construction Acc
71/85
Safety Work Permit:
A well designed Permit to Work System is
always useful to check safety points beforehand.
General Precautions while Working at Height:
They are as under_
Cut off power in nearby electric lines to avoid
shock and fall.
Do not lift or carry excessive load so as to
loose balance and fall. Tools should be attached by lanyard to the belt
orgarment to prevent their fall on others.
-
8/8/2019 Construction Acc
72/85
Safety helmet, shoes, safety belt, respirator
and other PPEs should be worn as per
need. Keep the work floor always dry, clean and
well protected. The floor should be checked
for fragility, crack and its soundness to
carry load. Non fragile metal sheets orreinforced AC sheets are preferable.
Know safe means of access, emergency
staircase, fire extinguisher, first aid box
and other device like aerial platform, ropeladder etc. before starting the work.
-
8/8/2019 Construction Acc
73/85
Pre-employment and periodic medical
examination of workers to check their
suitability for working at height. Workerssuffering from balance disorders, vertigo,
epilepsy, blackouts etc. should not be
employed or continued to work at height.
Trained Workers: Safety belts, harness andlanyards are to be used in conjunction with
permanent anchorage points. Workers
should be trained to know how to check,
wear and adjust before they start work andhow to connect themselves to the structure
or safety time.
-
8/8/2019 Construction Acc
74/85
Workers can also use mobile access
equipment i.e. mobile elevating work
platforms, cradles and mast platforms. Allusers of such equipment should be trained
and competent to operate it. They should
also be aware of emergency and evacuation
procedures so that if, for example, the powerto platform fails, they know what they should
do.
It is essential for employers to implementsafe working procedures for working at
heights.
-
8/8/2019 Construction Acc
75/85
C fi d S i l d ib d l
-
8/8/2019 Construction Acc
76/85
Confined Space is also described as a placewhich_
is mostly enclosed and partially open.
is at atmospheric pressure and temperature. has limited or restricted openings for entry and
exit.
is not designed orintended fornormal place of
work (i.e. not forlong time worker occupancy). has unfavourable natural ventilation due to
stagnant air, no free air movement, oxygendeficiency or enrichment or nitrogenatmosphere.
has contaminated air with toxic or/andflammable gas, dust etc and
may cause engulfment (swallowing) inunstable orloose material.
-
8/8/2019 Construction Acc
77/85
Examples (Types) of confined spaces are_
Storage tank
Process Vessels / Reaction vessel
Pressure Vessels
Boilers
Tank cars (trucks) Tank wagons
Digester
Wells/bores Under floor/ Floor opening
Sumps
Pits
Sil
-
8/8/2019 Construction Acc
78/85
Silos
Pipes
Ducts Gutters
Tunnels
Sewers
Vats
Bilges
Shafts
Go-down of grain, sulphur, cement, clayand similar loose material
Roof voids/ Gap between roof and falseceiling
Hazards of Confined Space can be classified as_
-
8/8/2019 Construction Acc
79/85
Poor lighting and ventilation.
Oxygen deficiency.
Contamination of toxic and / or flammablegases.
Unexpected activation of machinery orflow.
No way or no time available for exit. Engulfment (burying) in loose material.
Non specific work practices.
Other hazards are suffocation, burning,poisoning, explosion, drowning, freezing,crushing, entrapment, scalding, stroke, heatstress, radiation, physical trauma, in jury bymoving machinery, slipping or falling etc.
M f t l d i id t h d
-
8/8/2019 Construction Acc
80/85
Many fatal and serious accidents have occurredwhile working in a confined space. Threereasons_ flammable air mixture, toxic gases andoxygen deficiency are found responsible forsuch accidents. Tanks (vessels) with top coveropen but all other sides closed, should beconsidered as a confined space, because, in
such situation persons working inside have toface direct fire, explosion, or toxic exposure andhave no other way to run away except the onlyway of their entry. Therefore doubtlessly and as
per above statutory definition, such situation /condition is a confined space. One worker dieddue to solvent fire, one died due to chloroformvapour and two died due to nitrogen (oxygendeficiency) atmosphere in such confined spaces.
-
8/8/2019 Construction Acc
81/85
Safety equipment for working in a confined
space
Following equipment are useful for workingsafely in a confined space.
Vessel Entry Permit:
Tanks vats, pits, sumps, vessels, floor
opening etc. should be protected by guard
rails or cover. Fixed ladder with handrail if
possible, should be provided to step down
safely. Portable (rope) ladder may be usedwhile working inside a tank or vessel for
temporary work.
Other precautions are
-
8/8/2019 Construction Acc
82/85
Other precautions are_
Check the concentration of toxic or flammablegas, dust, vapour etc., by a gas detector.
Oxygen content should also be checked forsafe proportion. It should be > 18%.
Air line or self contained breathing apparatusand safety belt are essential.
Sump pumps with flameproof electric orpneumatic motors and air extraction fans(spark proof) and exhaust ducting to removeheavy vapours are necessary.
Complete isolation of the vessel, cleaning,
purging and ventilation of the vessel,inspection and testing, safety permit and allrescue arrangements must be done beforesuch work and only a trained worker will workunder constant help and supervision.
L t t f t d t h ld
-
8/8/2019 Construction Acc
83/85
Latest safety and rescue systems shouldbe used. Winch arrangement connectedwith the workers harness in useful to lower
and pull out quickly. Hand freecommunication system is available to keepthe worker in the tank in constant touchwith the supervisor outside. Hand operatedclutch, cord and chair assembly can be
used to lower the person while working atheight or depth.
Bottom drain valve and other nozzlesshould be kept open to allow goodventilation and fresh air in a vessel or tank.
Before allowing vessel (confined space)entry permit, it is necessary to carry outhazard assessment of the space.
WORKING UNDERGROUND
-
8/8/2019 Construction Acc
84/85
WORKING UNDERGROUND
Working underground has hazards similar to
working in a confined space. Therefore allprecautions including entry permitmentioned in part 2 above should befollowed.
Under ground work includes digging also.
Hazard assessment of undergroundatmosphere is most important. Oxygen level,measurement and removal of other gases(e.g. H2S, CO, methane etc) by exhaustventilation, artificial lighting (flameproof ifnecessary), necessary ladders, supports,water evacuation, safety harness, helmet,respirators, safety shoes etc. are necessaryas per hazard assessment report.
-
8/8/2019 Construction Acc
85/85