CONSTANCIA VIRTUAL SITE VISIT PRESENTATION
Transcript of CONSTANCIA VIRTUAL SITE VISIT PRESENTATION
March 2021
CONSTANCIA
VIRTUAL SITE VISIT
PRESENTATION
CAUTIONARY INFORMATIONThis presentation contains forward-looking information within the meaning of applicable Canadian and United States securities legislation. All information contained in this
presentation, other than statements of current and historical fact, is forward-looking information. Often, but not always, forward-looking information can be identified by the use
of words such as “plans”, “expects”, “budget”, “guidance”, “scheduled”, “estimates”, “forecasts”, “strategy”, “target”, “intends”, “objective”, “goal”, “understands”, “anticipates” and
“believes” (and variations of these or similar words) and statements that certain actions, events or results “may”, “could”, “would”, “should”, “might” “occur” or “be achieved” or
“will be taken” (and variations of these or similar expressions). All of the forward-looking information in this presentation is qualified by this cautionary note.
Forward-looking information includes, but is not limited to, production, cost and capital and exploration expenditure guidance and potential revisions to such guidance,
anticipated production at Hudbay Minerals Inc.’s (“Hudbay”) mines and processing facilities, expectations regarding the impact of the COVID-19 pandemic on the company’s
operations, financial condition and prospects and Hudbay’s ability to effectively engage with local communities in Peru and other stakeholders, expectations regarding the future
potential of the Constancia mining operations and the timing of mining activities at the Pampacancha deposit, the potential and Hudbay’s anticipated plans for advancing the
company’s mining properties surrounding Constancia and elsewhere in Peru, expectations regarding Hudbay’s community and social investments in Peru, expectations
regarding the social and political environment in Peru, the anticipated timing, cost and benefits of developing the Rosemont project and the outcome of litigation challenging
Rosemont's permits, expectations regarding the Helvetia exploration program, expectations regarding the Lalor gold strategy, including the refurbishment, commissioning and
ramp-up of the New Britannia mill and expectations regarding the mine plan for the 1901 deposit, increasing the mining rate at Lalor and optimizing the Stall and New Britannia
mills, the possibility of converting inferred mineral resource estimates to higher confidence categories, anticipated mine plans, anticipated metals prices and the anticipated
sensitivity of the company’s financial performance to metals prices, events that may affect its operations and development projects, anticipated cash flows from operations and
related liquidity requirements, the anticipated effect of external factors on revenue, such as commodity prices, estimation of mineral reserves and resources, mine life
projections, reclamation costs, economic outlook, government regulation of mining operations, and business and acquisition strategies. Forward-looking information is not, and
cannot be, a guarantee of future results or events. Forward-looking information is based on, among other things, opinions, assumptions, estimates and analyses that, while
considered reasonable by Hudbay at the date the forward-looking information is provided, inherently are subject to significant risks, uncertainties, contingencies and other
factors that may cause actual results and events to be materially different from those expressed or implied by the forward-looking information.
Factors that could cause or contribute to such differences include, but are not limited to, those discussed under the heading “Risk Factors” in Hudbay’s Annual Information Form
for the year ended December 31, 2019 and its Management’s Discussion and Analysis for the year ended December 31, 2020. Should one or more risk, uncertainty,
contingency or other factor materialize or should any factor or assumption prove incorrect, actual results could vary materially from those expressed or implied in the forward-
looking information. Accordingly, you should not place undue reliance on forward-looking information. Hudbay does not assume any obligation to update or revise any forward-
looking information after the date of this presentation or to explain any material difference between subsequent actual events and any forward-looking information, except as
required by applicable law.
This presentation contains certain financial measures which are not recognized under IFRS, such as Adjusted net earnings (loss), adjusted net earnings (loss) per share,
Adjusted EBITDA, net debt, cash cost, sustaining and all-in sustaining cash cost per pound of copper produced, cash cost and sustaining cash cost per pound of zinc produced
and combined unit cost and zinc plant unit cost. For a detailed description of each of the non-IFRS financial performance measures used in this presentation, please refer to
page 53 of Hudbay’s management’s discussion and analysis for the year ended December 31, 2020 available on SEDAR at www.sedar.com and EDGAR at www.sec.gov.
2
CONSTANCIA VIRTUAL SITE VISIT AGENDA
Introduction to Hudbay
Overview of Constancia Operations
Optimization Opportunities
Regional Exploration
Hudbay’s ESG Principles in Peru
Appendix
3
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
1
2
3
4
5
6
Introduction to Hudbay
4
1
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG PrinciplesPETER KUKIELSKI
PRESIDENT & CEO
HUDBAY SENIOR MANAGEMENT TEAM MEMBERS
5
PETER KUKIELSKIPRESIDENT & CEO• More than 30 years of sector
experience in base metals, precious metals and bulk materials across the globe
CASHEL MEAGHERSVP & COO• Extensive background in
exploration, resource and reserve estimation, engineering studies and operations
STEVE DOUGLASSVP & CFO• Over 25 years of financial
experience, key role in financial reporting, capital markets, treasury and taxation.
EUGENE LEISVP CORP. DEV. & STRATEGY• Over 18 years of global
mining investment banking and corporate development experience
OLIVIER TAVCHANDJIANVP EXPL. & GEOLOGY• Over 25 years of experience
in reserve and resource estimation and reporting, exploration and mine planning
PETER AMELUNXENVP TECHNICAL SERVICES• Responsible for managing
internal and external project review, due diligence processes, project & operational governance
JAVIER DEL RIOVP SOUTH AMERICA B.U.• Responsible for strategic and
operational performance in Peru and ensure corporate standards are met in Peru
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
PRESENTERS:
AVAILABLE FOR Q&A:
TSX, NYSE, BVL Symbol HBM
Market Capitalization1 C$2.7 billion
Shares Outstanding2 261 million
Available Liquidity3 $724 million
Debt Outstanding4 $1.2 billion
DIVERSIFIED MID-TIER COPPER PRODUCER
• Vision is to become a top-tier operator of long-life, low cost
mines in the Americas
• Mission is to create sustainable value through the acquisition,
development and operation of high-quality assets in
jurisdictions that support responsible mining
• Primary producer of copper, gold, silver, and zinc
• Operations located in Peru and Manitoba, Canada
• Built a leading portfolio of growth assets in Canada, United
States, Peru and Chile
Mason
Exploration
Constancia
Pampacancha
Exploration
Exploration
777
Lalor
WIM, 3 Zone & 1901
Exploration
Rosemont
Exploration
1. Based on Hudbay’s TSX closing share price on February 19, 2021.
2. Basic shares outstanding as at December 31, 2020.
3. Liquidity includes cash and cash equivalents of $439M as at December 31, 2020, availability under the $400M credit facilities less $115M in committed LCs.
4. Face value of long-term debt outstanding as at December 31, 2020.
5. Revenue for the full year ended December 31, 2020. Gold and silver revenues include deferred revenue and cash payments applicable to precious metals stream sales.
6. Revenue calculated from median of Hudbay production guidance and select commodity pricing ($3.50 / lb Cu, $1,800 / oz Au, $25.00 / oz Ag, $1.00 / lb Zn, and $10.00 / lb Mo).6
NEVADA
PERU
CHILE
MANITOBA
ARIZONA
Operations
Development
Exploration
RE
VE
NU
E B
Y
ME
TA
L
$1.1B
20205 20216
53%
24%
6%
15%2%
Cu Au Ag Zn Mo
$1.5B50%
19%
6%
23%
2%
Cu Au Ag Zn Mo
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
STRONG ENVIRONMENTAL, SOCIAL & GOVERNANCE (“ESG”) PERFORMANCE
7
INDUSTRY LEADER IN RESPONSIBLE MINING
ENVIRONMENT
GHG emissions declined
further in 2019 (1.8%)
In 2019, overall water
consumption declined by 9%
Manitoba received 2019
Toward Sustainable Mining
Leadership Award
Tailings facilities rated “AA”
in Manitoba and “A” in Peru
according to TSM’s tailings
management protocol
SOCIAL IMPACT
Manitoba COVID-19 relief
donations: together with our
partners, donated funds to
various charities supporting local
families
Peru COVID-19 relief donations:
biomedical equipment and
supplies to regional hospitals,
and >59 tonnes of basic
necessities to seven rural
communities in Chumbivilcas
Positive impact on surrounding
communities in Manitoba
through successfully
discovering, operating and
reclaiming over 25 mines in the
last 90 years
Government of Canada’s
Employment Equity
Achievement Award in Manitoba
Initiated “Hudbay Reduce”
campaign in Peru, resulting in a
68% reduction in plastic
generation
HEALTH & SAFETY
Constancia has the best
safety track record out of the
Peruvian copper mining
companies
Improved our current 3-year
average lost time accident
severity to 7.0
3-year total recordable injury
frequency average relatively
flat at 3.8
GOVERNANCE
Board refreshed in 2019 with
5 out of 10 new directors
3 female Board Directors
Moody’s governance rating
of GA1 2020, the highest in
the 4-tier structure
Ranked 7th among mining
companies in the Board
Games; ranked 1st among
base metal companies and
the only base metal company
in top 100
Source: Bloomberg, February 2021 Source: Ministry of Energy and Mines; LTA=Lost time accident
8178
7271
5952
#1(HBM)
#2 #3 #4 #5 #6
Base Metal Mining Company Rankings in Globe & Mail 2020
Board Games
12 13
5843 37
259242
#1(HBM)
#2 #3 #4 #5 #6 #7
2015-2019 Safety Record of Peruvian Copper Mining
Companies
Million hours worked w/out LTA # of LTAs
0
500
1000Peer GHG Emissions (2019)
GHG/Revenue Peer Average
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
5
8
17
17
18
19
1.5
5
11
2
9
1
Constancia
Snow Lake
Rosemont
777
Past Production Reserve Life M&I Resource Life Inferred Resource Life
LONG LIFE ASSETS LOCATED IN MINING FRIENDLY REGIONS
8
1 2
4
5
LOCATED IN TOP MINING FRIENDLY JURISDICTIONS IN THE AMERICAS6
Ne
vad
a
We
st A
ustr
alia
Saskatc
hew
an
Qu
eb
ec
Ala
ska
Ch
ile
Uta
h
Arizo
na
Yukon
NW
T
NF
& L
abra
dor
Man
itob
a
Qu
ee
nsla
nd
Peru
Nu
na
vut
Idah
o
Fin
lan
d
British C
olu
mbia
On
tario
Irela
nd
Sw
eden
Fiji
No
rth
ern
Terr
ito
ry
Sou
th A
ustr
alia
No
rth
ern
Ire
land
*
Wyo
min
g
Ru
ssia
*
Ne
w M
exic
o
Mexic
o
Ne
w B
runsw
ick
Mon
tan
a
Bots
wan
a*
Mic
hig
an
Min
ne
so
ta*
Co
lora
do
Suri
na
me
Ca
tam
arc
a*
Pola
nd
*
Gu
yan
a*
Ne
w Z
eala
nd
PN
G
Ne
w S
ou
th W
ale
s
Sou
th A
fric
a
Spa
in*
Zam
bia
*
Port
ug
al*
Indo
ne
sia
Co
lom
bia
San
ta C
ruz
Mali
Alb
ert
a
Fre
nch
Gu
ian
a*
No
rwa
y
Vic
toria
Tasm
an
ia*
Ecu
ado
r
No
va S
cotia
Bra
zil
Turk
ey
Na
mib
ia
Ca
liforn
ia
Zim
bab
we*
Gre
enla
nd
San
Ju
an
Phili
ppin
es*
Tan
zan
ia
(DR
C)*
Gh
an
a*
Ch
ub
ut*
Salta*
Wa
shin
gto
n
Ju
juy*
Men
doza*
Boliv
ia
La
Rio
ja*
Do
min
ican
Rep
ub
lic*
Eth
iopia
*
Ch
ina*
Pan
am
a
Gu
ate
mala
*
Nic
ara
gu
a
Ne
uq
uen
*
Ven
ezu
ela
Investment Attractiveness Index
3
1. Reserve and resource life as of January 1, 2020. 777 mine reserves are expected to be depleted in 2022 and have been adjusted here to show mine life as of January 1, 2021. Reserve and resource life is updated annually with reserves and resources reporting.
2. Contained M&I CuEq metal (exclusive of reserves) divided by 2019 CuEq production rate. Mineral resources that are not mineral reserves do not have demonstrated economic viability.
3. Contained Inferred CuEq metal (exclusive of reserves and M&I) divided by 2019 CuEq production rate. Mineral resources that are not mineral reserves do not have demonstrated economic viability.
4. Lalor mineral resources include indicated and inferred resources identified at Snow Lake, New Britannia, Wim, Pen II and 1901 Deposit.
5. Rosemont contained CuEq metal reserves and resources divided by annual LOM CuEq production rate as disclosed in NI 43-101 Technical Report on the Rosemont Project dated March 30, 2017.
6. Sourced from Fraser Institute 2018 Mining Survey’s Investment Attractiveness Index. *Denotes a surveyed region with <10 responses.
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
PROVEN TRACK RECORD OF OPERATIONAL EXCELLENCE &
LOW COST MINES
• Proven track record of achieving or exceeding copper production guidance over the last five years
• Hudbay is well-positioned on the cash cost curve
• Focus on cost control and continuous improvement initiatives maintains low cost profile
9
C1 CASH COSTS1(US$/lb Cu)
1. Source: Wood Mackenzie’s 2020 by-product C1 cash cost curve (Q3 2020 dataset dated November 2020). Wood Mackenzie’s costing methodology may be different than the methodology reported by Hudbay or its peers in their public disclosure. For details regarding Hudbay’s actual cash costs, refer to Hudbay’s management’s discussion and analysis for the three months and full year ended December 31, 2020.
CONSOLIDATED COPPER PRODUCTION AND GUIDANCE
First Quantum
Turquoise HillLundin
Oz Minerals
Capstone
Imperial
AntofagastaHudbay
($2.00)
($1.00)
$0.00
$1.00
$2.00
$3.00
0% 25% 50% 75% 100%(20) (15) (10) (5) 0 5 10 15 20
2016
2017
2018
2019
2020
+/- kt from Midpoint of Guidance
Guidance Outperform
Actual Production
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
FOCUSED ON FREE CASH FLOW GENERATION & PRUDENT BALANCE SHEET MANAGEMENT
• Generated ~$2.2B of EBITDA and ~$650M of free cash flow over the last five years and during
the volatile copper price environment due to un-hedged production and stable low-cost profile
• Prudent balance sheet management; next phase of growth focused on low capital, high return
brownfield projects with short paybacks on our invested capital
10
1. Adjusted EBITDA is profit or loss before net finance expense/income, tax expense/recoveries, depreciation and amortization of property, plant and equipment and deferred revenue, as well as certain other adjustments. We calculate Adjusted EBITDA by removing the impact of non-cash items and financing costs that are not associated with measuring the underlying performance of our operations. Free cash flow is calculated as operating cash flow before non-cash working capital less sustaining capital expenditures and less interest paid. Adjusted EBITDA and free cash flow are non-IFRS performance measures with no standardized definition under IFRS.
2. Consensus EBITDA and copper prices sourced from Bloomberg as of February 17, 2021.
ADJUSTED EBITDA, CAPEX, FREE CASH FLOW1
($M)Consensus Estimates 2
$423
$575 $555
$359
$307
$555
$664
$83
$295 $274
$22
($26)
$2.21
$2.82 $2.93 $2.73 $2.86 $3.40 $3.30
2016 2017 2018 2019 2020 2021E 2022E
Adj EBITDA Free Cash Flow Realized Copper Price
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
PRUDENT CAPITAL ALLOCATION
11
PAMPACANCHA
~160% CuEq GRADE INCREASE ¹
NEW BRITANNIA
GOLD RECOVERY AT 93% FROM 53%
• Engineering 99% complete, project procurement
99% complete, construction 73% complete2
• Low-risk mill refurbishment
• Increases Lalor’s annual gold production to over
150,000 ounces
FU
TU
RE
• Additional drilling at Lalor, 1901 Deposit and
other known deposits for further growth
potential
1. Copper equivalent grade calculated based on January 1, 2020. Constancia Mineral Reserves statement and using the following lo ng-term metal prices: $3.00 per pound of copper; $11.00 per pound of molybdenum; $18.00 per ounce of silver;
and $1,260 per ounce of gold.
2. As of February 2021.
LEVERAGING EXPERTISE THAT WAS DEMONSTRATED THROUGH BEST IN CLASS
DELIVERY OF CONSTANCIA
• Successfully constructed Constancia (Peru), Lalor (Canada) and Reed (Canada) mines
simultaneously during 2012-2014
• Satellite deposit located ~7 km by road from
processing facilities
• High-grade copper and gold mineralization
• Completed Consulta Previa in December 2020
• Production expected to commence in Q2 2021
• Prospective ~22,500 hectare regional land package
within trucking distance of Constancia processing
facility
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
12
118
107
90
2020 2021 2022
125
215
249
2020 2021 2022
95
112
140
2020 2021 2022
Source: 2020 actual production and 2021 guidance ranges. Shaded area represents the guidance range.
1. Achieved 2,751 koz of silver in 2020; 2021 guidance for silver expected to be between 3,000 and 3,570 koz.
2. 2022 copper and zinc production are from Hudbay’s previously issued 2022 guidance as of February 20, 2020.
3. 2022 gold production sourced from Snow Lake mine plan dated March 30, 2020 and Constancia NI 43-101 Technical report dated March 29, 2018. This excludes any gold production from 777.
Zn(kt)
Au1
(koz)
Cu(kt)
CONSTANCIA PRODUCTION PROFILE
HIGH-GRADE PAMPACANCHA TO GROW COPPER AND GOLD PRODUCTION
• Revised Constancia mine plan is expected at the end of March 2021, incorporating the commencement of
mining at Pampacancha in 2021 and reserves at Constancia North
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
2 23
RAMP-UP FROM FIRST PRODUCTION TO COMMERCIAL
PRODUCTION WAS 3X FASTER THAN THE PEER AVERAGE
5 Months
17 Months
57 Months
Constancia PeerAverage
PeerMax
PROVEN MINING INDUSTRY EXPERIENCE
131. 1st production commenced December 23, 2014, commercial production achieved April 30, 2015.
2. Wood Mackenzie Q3 2020 dataset; primary copper, open pit sulphide mines in South America. Operating costs include mining, pro cessing and general and administrative expenditures on a per tonne basis. Wood Mackenzie’s costing methodology may be different than the methodology reported by Hudbay or its peers in their public disclosure. For details regarding Hudbay’s costs, refer to Hudbay’s management discussion and analysis for the three months ended September 30, 2020.
1
LEADING MINE DEVELOPMENT & OPERATING COST PERFORMANCE
• Constancia’s project development and
mine ramp-up was best in class
• Continuous operational improvements at
Constancia have driven costs down, while
increasing efficiencies and productivity
LOWEST COST OPEN PIT COPPER MINES IN SOUTH AMERICA (2020)2
$6.33$8.88 $9.01
$10.80 $11.07 $11.12 $11.68 $12.70 $12.72 $13.54 $14.46 $14.58 $14.97 $15.68 $15.79 $16.81 $17.31
$21.53$23.79
$0
$10
$20
$30
Ch
ap
ad
a
To
rom
oc
ho
Co
ns
tan
cia
Co
bre
Pan
am
a
Sie
rra
Go
rda
Mir
ad
or
Cu
ajo
ne
Lo
s P
ela
mb
res
An
tap
ac
cay
Rad
om
iro
To
mic
Cen
tin
ela
So
sse
go
An
tam
ina
Sa
lob
o
La
s B
am
ba
s
Min
a M
inis
tro
Hale
s
Co
llah
ua
si
Ce
rro
Co
ron
a
El
So
lda
do
To
tal O
pen
Pit
Min
esit
e C
osts
(U
S$/t
mille
d)
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
PROVEN MINING INDUSTRY EXPERIENCE
14
1. Production calculated as tonnes mined multiplied by grades mined (i.e. assumes 100% recovery). The following metals price assumptions were applied to reserves for purposes of calculating copper equivalent: $3.00/lb Cu, $1.00/lb Zn, $1,260/oz Au and $18.00/oz Ag. Does not include impact of precious metal streams, as applicable.
2. Constancia reserve at bid date from NI 43-101 Definitive Feasibility Study Technical Report on the Constancia mine filed by Norsemont Mining, dated September 28, 2009.
ADDING VALUE THROUGH EXPLORATION
• Hudbay has been successful in significantly increasing the known reserves at both of its flagship
operations
• Constancia mine reserves have more than doubled since the acquisition in 2011, from 277Mt to 670Mt
• Lalor in Snow Lake was an in-house geophysical discovery on Hudbay's wholly-owned land and reserves
have grown by 138% through successful conversion and extension
CONSTANCIA (2009-2020)1
0.0
1.0
2.0
3.0
4.0
Reserve at Bid Date Production to Date +Current Reserve
Co
pp
er
Eq
uiv
ale
nt
(Mt)
Production Reserves
Constancia North,
Caballito,
Kusiorcco
& Maria Reyna
2
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
Initial Reserve Production to Date +Current Reserve
Go
ld E
qu
ivale
nt
(Mo
z)
Production Reserves
1901, Pen II,
New Britannia,
Birch & Watts
v
SNOW LAKE (2010-2020)1
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
LEADING ORGANIC GROWTH PIPELINEHUDBAY HAS BUILT A DIVERSIFIED PORTFOLIO FOCUSED ON COPPER & GOLD GROWTH
15
Constancia North
resource modelling expected Q1 2021
PRODUCTIONFEASIBILITY STUDY
COMPLETE
RESOURCE
DEFINITIONEXPLORATION
Quehuincha North
drilling initiated in Feb 2021
South America
Llaguen
drilling expected in 2021
Manitoba United States
Maria Reyna, Caballito & Kusiorcco
Leviatan & Paquitas
Chile Exploration Land Package
Pampacancha Deposit
mining start expected in 2021
Constancia Mine
Cu-Mo-Au-Ag
777 Mine
Zn-Cu-Au-Ag
Lalor Mine
Au-Zn-Cu-Ag
New Britannia Gold Mill Refurbishment
completion expected mid-2021
Rosemont Project
permitting appeals decision expected in 2021Helvetia Historic Copper District
drilling underway
Mason Project
PEA expected in 2021
1901 Deposit
prefeasibility study expected H1 2021
Manitoba Exploration Land Package
Lalor open at depth, regional properties
Mason Regional Exploration
WIM & 3 Zone Deposits
New Britannia, Watts, Pen II & Talbot
Deposits
Lalor In-mine Exploration
gold inferred conversion
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
2021 KEY OBJECTIVES
16
• FOCUS on operational efficiencies, maintain low-costs of production to continue to generate positive cash flow and strong returns on invested capital
• EXECUTE development and commence mining activities at the high-grade Pampacanchasatellite deposit
• DELIVER the refurbishment of the New Britannia gold mill to significantly increase gold production from Lalor
• PROGRESS the third phase of our Snow Lake gold strategy
• ADVANCE the appeals process and alternative options to unlock value at Rosemont
• MAINTAIN Constancia's industry-leading efficiency metrics
• DRILL regional copper exploration targets near Constancia, in northern Peru, and at Rosemont while continuing to advance exploration programs in the Snow Lake region, Peru and Nevada
• SUPPORT Hudbay’s workforce, their families and the communities in which the company operates through continuing to make health and safety a priority and providing ongoing COVID-19 support consistent with our ESG principles
• EVALUATE exploration, organic growth and acquisition opportunities that meet our stringent strategic criteria; allocate capital to pursue those opportunities that create sustainable value
Appendix
Strong ESG Performance
About Hudbay
Long Life & Mining Friendly Jurisdictions
Free Cash Flow & Prudent Capital Allocation
Experienced Management Team
Copper Focus & Organic Growth Pipeline
Low Cost & Operational Excellence
Overview of Constancia Operations
17
2
CASHEL MEAGHER
SVP & COO
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
CONSTANCIA LOCATION
18
MINE
TOWN
RAILROAD
ROAD
Lima
PERU
CONSTANCIA
AREQUIPA
Cusco
CUSCO
Matarani
Imata
Arequipa
Cerro Verde
MOQUEGUA
TACNA 100km0
Las Bambas
Yauri
Tintaya
Antapaccay
CONSTANCIA
&
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
CONSTANCIA HISTORY TIMELINE
19
COMMERCIAL PRODUCTION ACHIEVED ONLY 4 YEARS AFTER GREENFIELD ACQUISITION
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
2010 2011 2012 2013 2014 2015
Nov 2010
ESIA permit
received
Mar 2011
Hudbay acquires
Constancia through
Norsemont acquisition
Apr 2012
Initial resource
announced at
higher grade
Pampacancha
deposit
Aug 2012 updated
technical report
Hudbay’s board
approves
construction of
Constancia
Aug 2013
Updated capital
cost estimate
indicates
increase of
~10%Apr 2014
All critical
path families
resettled
Aug 2014
Powerline
energized
Q2 2015
Commercial
production
Q4 2014
First
concentrate
production
Mar 2014
Pre-stripping
commences
Sep 2013
ESIA modification
1 approved
Jun 2012
Beneficiation
concession
permit received
Mar 2011
US$116M
Constancia
pre-construction
program beginsH1 2012
Neighbouring
community
agreements
reached
80.1%
80.6%
81.2%
82.1%
80.7%
79.7%
85.0%
84.8%
86.2%
84.7%
86.0%
85.6%
84.3%
76.6%
83.3%
85.3%
Q1'17 Q2'17 Q3'17 Q4'17 Q1'18 Q2'18 Q3'18 Q4'18 Q1'19 Q2'19 Q3'19 Q4'19 Q1'20 Q2'20 Q3'20 Q4'20
Technical Report Average
79
86 86 86
60
80
100
2017A 2018A 2019A 2020A
Co
nsta
ncia
Mill
Th
rou
gh
pu
t R
ate
(ktp
d)
LOW-COST, LONG-LIFE COPPER MINE IN PERU
• 100%-owned, production commenced in 2014
• On-site processing plant producing copper and molybdenum
concentrate end products
• Developed and maintaining meaningful partnerships with local
communities
• Potential to add value through nearby satellite deposits such as
Pampacancha, which is expected to start production in 2021
CONSTANCIA MINE OVERVIEW
COPPER RECOVERIES
PLANT THROUGHPUT
CONTINUOUS OPTIMIZATION INITIATIVES
• Increasing throughput and quarterly trend in copper recoveries
• Continued integration of an automated, advanced process control system
• Flotation improvements – optimizing water recovery in the tailings thickener and the installation of enhanced equipment in the rougher circuit
72-88 KT2021E CU PRODUCTION
17 YEARSMINE LIFE
40-50 KOZ2021E AU PRODUCTION
$9.90/T2021E UNIT COSTS 1
86KTPDMILL CAPACITY
CU-MOPORPHYRY DEPOSIT
201. Midpoint of 2021E Peru unit cost guidance.
2. Excludes period during temporary mine suspension from March 20 to May 17, 2020.
Tuning of advance
process control system
Processing of stockpile
ore after temporary
government mandated
mine suspension
2
76ktpd
(original
design
capacity)
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
21
12
50
91
2020 2021 2022
73
88
125
2020 2021 2022
Source: 2020 actual production and 2021 guidance ranges. Shaded area represents the guidance range.
1. 2022 copper production is from Hudbay’s previously issued 2022 guidance as of February 20, 2020. 2022 gold production sourced from Constancia NI 43-101 Technical report dated March 29, 2018.
Au(koz)
Cu(kt)
CONSTANCIA PRODUCTION PROFILE
HIGH-GRADE PAMPACANCHA TO GROW COPPER AND GOLD PRODUCTION
• Revised Constancia mine plan is expected at the end of March 2021, incorporating the commencement of
mining at Pampacancha in 2021 and reserves at Constancia North
71% 658%
1 1
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
100
22
GLOBAL COPPER LANDSCAPE
Notes
1. Constancia is based on the 2022 copper production from Hudbay’s previously issued 2022 guidance as of February 20, 2020.
2. Majors include Anglo American, Antofagasta, Barrick, BHP, First Quantum, Freeport, Glencore, Ivanhoe Mines, KAZ Minerals, Lundin Mining, Pan Pacific, Rio Tinto, Southern Copper, Teck, Vale and Zijin
Source: Wood Mackenzie 2020 copper production (Q3 2020 dataset); Ivanhoe Mines Kamoa-Kakula is based on the average first 10 years of production as outlined in the September 8, 2020 IDP/PFS/PEA (PEA shown as it incorporates the Kamoa and Kakula
deposits); and Teck’s QB2 is based on the average first 10 years of production as outlined in the reserve case (Dec 4, 2018 press release)
• There are few assets in the global copper landscape where investors can get significant exposure
to a top-tier copper mine
50 LARGEST GLOBAL COPPER MINES BASED ON 2020 COPPER PRODUCTION (kt)
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
1.2Mt
125
0
200
400
600
800
1,000E
sco
nd
ida
(B
HP
)
Co
llahu
asi (G
len
co
re)
Ka
mo
a-K
aku
la (
Iva
nho
e/Z
ijin
)
Mo
renci (F
CX
)
Po
lish
Co
ppe
r (K
GH
M)
Ca
nan
ea (
SC
C)
El T
en
ien
te (
Co
de
lco
)
Ce
rro
Ve
rde
(F
CX
)
Ch
uqu
ica
ma
ta (
Co
delc
o)
An
tam
ina
(G
len
co
re +
Oth
ers
)
Lo
s P
ela
mb
res (
An
tofa
gasta
)
Gra
sb
erg
(F
CX
)
No
rils
k
Lo
s B
ron
ce
s (
An
glo
Am
erica
n)
La
s B
am
ba
s (
MM
G)
Qu
ella
ve
co
(A
ng
lo A
meri
ca
n)
QB
2 (
Te
ck)
Ka
mo
to (
Gle
nco
re)
To
qu
ep
ala
(S
CC
)
Se
ntin
el (F
Q)
Ka
nsa
nsh
i (F
Q)
Co
bre
Pa
na
ma (
FQ
)
Ra
dom
iro
To
mic
(C
od
elc
o)
An
tap
acca
y (
Gle
nco
re)
Sa
lob
o (
Va
le)
Oly
mp
ic D
am
(B
HP
)
To
rom
och
o (
Ch
ina
lco
)
Te
nke
Fu
ng
uru
me
(C
MO
C)
Sa
rch
esh
me
h (
Ira
n G
ov)
An
din
a (
Co
de
lco
)
Sp
en
ce
(B
HP
)
Cu
ajo
ne (
SS
C)
Ce
ntin
ela
(A
nto
faga
sta
)
Ca
se
ron
es (
Pa
n P
acific
)
De
xin
g (
Jia
ngxi)
Min
a M
inis
tro
Ha
les (
Co
de
lco
)
Oyu
To
lgoi (R
io T
into
)
Sie
rra
Go
rda
(K
GH
M)
Akto
gay (
KA
Z)
Erd
ene
t (G
ove
rnm
en
t)
Zh
ezka
zg
an
(K
AZ
)
La
Ca
rid
ad
(S
SC
)
Ga
brie
la M
istr
al (C
ode
lco
)
Co
nsta
ncia
(H
ud
bay)
Hig
hla
nd
Va
lley (
Te
ck)
Ca
nde
lari
a (
Lu
ndin
)
Lu
mw
an
a (
Ba
rric
k)
Za
ldiv
ar
(Ba
rric
k/A
nto
)
Bin
gh
am
Ca
nyo
n (
Rio
Tin
to)
Bo
zsh
ako
l (K
AZ
)
Mo
unt
Isa
(G
len
co
re)
Hudbay Government Ownership Majors
1
2
GENERAL SITE OVERVIEW
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
23
Constancia
Pit
Pampacancha
Deposit
Waste Rock
Facility
Tailings
Management
Facility
Mill Location
MILL FLOWSHEET
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
24
HEALTH & SAFETY STATISTICS
25
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
6.91 6.80 6.82 6.96
6.30
5.54
4.58
3.60
2.65
1.67
0.65
0.00
0.03 0.03 0.03
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00
0.02
0.04
0.06
0.08
0.10
0.12
0.14
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
Jan-20 Feb-20
Mar-20
Apr-20 May-20
Jun-20 Jul-20 Aug-20
Sep-20
Oct-20 Nov-20
Dec-20
Severity
Index (
SI)
SI 2020 FI 2020
Target SI: 7.7
Target FI: 0.11
Fre
quency
Index
(FI)
Hudbay Peru 2020 Severity and Frequency Index
(based on 200,00 hours worked)
SAFETY INDICATORS
• Focused on reducing frequency and severity since production start
• Below both 2020 Severity Index (SI) and Frequency Index (FI) targets
-
0.02
0.04
0.06
0.08
0.10
0.12
0.14
0.16
-
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
2015 2016 2017 2018 2019 2020
Hudbay Peru LTI Frequency and Severity(employee + contractor per 200,000 hrs worked)
Days Lost Severity Lost time injury Frequency
Severity
Fre
quency
• Current data shows the pit walls are in stable condition
• Zones considered as a geotechnical yellow alert are individually monitored and
inspected on field
• Daily inspections together with Operations Supervisors (OM, PM, Topography, etc.)
• Prism monitoring is executed 24/7 every hour using a robotic station
• A new monitoring base and prisms were installed in Phase II as the pit gets deeper
• The radar is located on Phase VII facing the north and east walls of Constancia´s pit;
from that location part of the west and south walls also are being monitoredPrism Monitoring Base
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
26
64Prisms
1Radar
3Monitoring
base
Instrumentation
Summary
RADAR
LOCATION
Radar is monitoring close to 70% of the
total pit area.
PHASE IV
PHASE II
ZCG19
-04
ZCG19
-02PHASE
VII
ZCG
07
ZCG
14
PHASE
III
ZCG20
-01
ZCG19
-03
RADAR
1Extensometer
FASE
V
ZCG21
-01
ZCG20
-04
Installed prismsZCG (Geotechnical criticality zone)
IBIS Radar
Monitoring Base
INSTRUMENTATION AND MONITORING - PIT
INSTRUMENTATION AND MONITORING - WRF
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
27
1Open Stand Pipe
Piezometer (OSP)
25Prisms
1Settlement Cell
3Inclinometers
1Pressure Cell
19Vibrating Wire
Piezometer
(VWP)
2Monitoring Base
Instr
um
en
tation
Sum
mary
1BM
416
0
418
0
42
20
41
40
41
2041
00
Controls for Giant Fleet discharge
42
35
Open Stand Pipe
Piezometer (OSP)
Prisms
Vibrating Wire Piezometer
(VWP)
Inclinometers
Existing Instrumentation
Settlement and Pressure
Cells (4100 level)
Monitoring Base
BM
• There are no significant movements at the WRF (stable condition)
• According to the monitoring of piezometers there is no significant variation of the piezometric level in the WRF
• Daily inspections are carried out to coordinate waste dump activities
INSTRUMENTATION AND MONITORING - TMF
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
28
178Vibrating Wire
Piezometers (VWP)
2Parshall
Flumes
4(*)Inclinometers
1(**)Acelerograph
38Oxygen/ 27 moisture
Sensors
26Prisms
6Settlement plates
12(***)OSP
Instr
um
en
tation S
um
mary
BH-KHP17-
03A
BH-
KHP17-
01
EAST
TMF
WEST
TMF
TMF
CG-
20-16
CG-
20-15
Piezometers
Inclinometers
Existing Instrumentation
Oxygen Sensors
Parshall Flume
Prism
Monitoring Base
Accelerograph
Settlement plates
• Instrument monitoring indicates there are no significant movements and the structure presents a stable condition• 26 prisms were relocated to the crest after the 2020 construction ended• Vibrating wire piezometers, inclinometer pipes and oxygen sensors were carefully raised as the new layers of
material are conformed• According to the monitoring of piezometers there is no significant variation of the piezometric level at the TMF
TAILINGS DAM RAISE
• Construction of the dike to reach elevation 4120 in 2021 from the elevation 4110.2 in 2020 and
downstream valley raise to elevation 4107 from 4077 (average of 4068.75W and 4084.5E) in 2020
• Construction in 2022 moved ahead in the downstream embankment (5.6 Mt in Stage 4) with mining
fleet to prepare for 2023 center line construction. This is to ensure we have a tailings beach against
the embankment and 2 metres of minimum free board
29
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
COPPER CONCENTRATE TRANSPORT TO PORT
30
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
Constancia
Espinar
Antapaccay
Condoroma
Imata
Patahuasi
Yura
ArequipaLa Joya
Matarani
Cusco
Negromayo
San Genaro
18-04(10 hours)
NightTraffic
Traffic Windows
Velille
Constancia
Maraniyoc (Desv. Livitaca)
Conn HHR LB
Coporaque
Chilloroya
Pinaya
Puente Queru
Espinar
Fortunia
HH LB
Las Bambas Puente Bailey
10.83 Km.
48.70 Km.
4.97 Km
Huayllapacheta
Puente Coporaque
MOST OF THE ROUTE SHARED WITH OTHER LARGE COPPER MINES IN THE REGION
• We believe we have one of the best logistics team in Peru; proactively manages through social
challenges along the transportation route to minimize impact to Constancia
Optimization Opportunities
31
3
PETER AMELUNXEN
VP TECHNICAL SERVICES
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
32
OPTIMIZATION AND CONTINUOUS IMPROVEMENT
• Bulk Ore Sorting
• 2020-2021 Geometallurgy program
• Advanced process control integration
• New data historian (OSISOFT™ Pi)
• Pebble Crushing
• Recovery increase project
• Moly plant upgrades
• Concentrate quality program
• DEM modeling & grate/lifter/liner
configuration
Enterprise
Geometallurgy, ore sorting
Advanced Process Control &
Automation
Bottleneck mapping, Constraint managers, Expert
Systems, AI/digital twins
Circuit Level
Grind Size, Rougher Mass Recovery, Regrind Size, Circulating Load Management
Unit Operations
Mill Power, Flotation Chemistry, Flotation Agitators, Cyclones, Instrumentation
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
33
GEOMETALLURGY
PRODUCTION FORECASTING AND OPTIMIZATION
• Geometallurgical studies allow us to
• Improve the confidence of our production forecasts
• Make informed decisions about plant configuration
• Ongoing metallurgical characterization of
future ores
• Both Constancia and Pampacancha
• Hardness (Grinding)
• Flotation Kinetics
• The ore is getting harder
• Pebble crushing originally planned for year 6
• Pampacancha is softer, allowing us to delay the
pebble crusher to 2024
0
10
20
30
40
50
60
70
80
90
100
0 50 100 150 200 250 300
Frecuencia Ac.
SGI,(min)
SAG Grindability Index
All
2019-2020
2021
2022
2023-2030
0
10
20
30
40
50
60
70
80
90
100
6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0
Frecuencia Ac.
SGI,(min)
Bond Work Index
All
2019-2020
2021
2022
2023-2030
Bond Work Index (kWh/t)
Constancia Ore Hardness
60
65
70
75
80
85
90
95
100
100 120 140 160 180 200 220 240
Recovery [%]
Grind Size [P80, um]
Pampacancha Copper Recovery [Std Reagents, Roughing]
Skarn/Supergene
Skarn/Mixed
Skarn/Hypogene
Skarn/Hi Zinc
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
34
SENSOR-BASED ORE SORTINGSUCCESSFUL TRIAL OF CAVEX CYCLONES
• Sensor-based ore sorting (XRF, XRT,
PGNAA, etc.) can be done at two
scales:
• Bulk –sorting ore at the shovel or loader post-
blast
• Particle – refers to sorting crushed material
on a conveyor
• Phase 1 - Bulk sorting amenability study
was positive
• Phase 2 – Laboratory sensor study
indicated positive results
• Economic impact calculated based
on truck-scale sorting
• Evaluating Phase 3
• Field demonstration with onsite loader
• Currently evaluating technical and
commercial proposals
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
35
RECOVERY UPLIFT PROJECT
PROJECT RECOVERY INCREASE
• 85% to 90% of metal losses occur in rougher tails
• Test work at 106 microns averaged 20% mass recovery (18% for Pampacancha)
• At 150 microns, mass recovery should be ~12%
• Percent mass recovery to rougher concentrate is the key performance indicator.
Controlled by:
• Frother, air rate and pulp level
• Rougher concentrate flow rate is constrained by downstream process
• Pump capacity to 800 m2/h, regrind cyclones, 1st cleaner / cleaner-scavenger dart valves
82.08
83.44
84.46
86.19
87.25
87.9088.27 88.45 88.53 88.49
0
200
400
600
800
1,000
1,200
1,400
1,600
78
80
82
84
86
88
90
6 7 8 9 10 11 12 13 14 15 16
Rougher Concentrate flow [m3/h]
Recovery [%]
Mass Recovered [%]
Mill Pump Upgrades
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
36
RECOVERY OPTIMIZATION PROJECTREGRIND AND CLEANER CIRCUIT DEBOTTLENECKING
• Rougher concentrate flow
needs to be increased
from 800 m3/h to ~1,200
m3/h
• Froth Crowders in
Roughers
• Increase concentrate
pumping
• Increase regrind cyclone
capacity
• Increase regrind circuit
power
• Add water lines to
cleaning circuit
• Froth crowding in cleaner-
scavengers
• Increased dart valves in
cleaners
• Possible circuit
configuration changes
• Integration of expert
control to regrind circuit
and cleaning
Regional Exploration
37
4
OLIVIER TAVCHANDJIAN
VP EXPL. & GEOLOGY
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
CONSTANCIA NORTH
38
Reserve pit
porphyryskarn
326320321
316
325
324
314
319
306
315323
317
307
308
109
313
310
318
312
309
311
215
2019-2020 CONSTANCIA NORTH DRILLING INTERSECTED CU PORPHYRY & SKARN
• Test a possible extension of Cu porphyry and
high-grade skarn mineralization within 300m of
current northern edge of Constancia pit
• Hole 316 intersected 78.6m @ 1.39% Cu, 305 g/t
Mo, 0.43 g/t Au, 16.0 g/t Ag
3D view of drill hole locations north of the existing Constancia reserve pit. Several of the drill holes intersected porphyry or skarn
mineralization along a SE-NW trend.
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
CONSTANCIA NORTH
39
CONSTANCIA NORTH DRILLING HAS EXTENDED THE RESERVE PIT TO THE NORTH
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
• Shallow porphyry and skarn mineralization intersected in the 2019-2020 drilling at Constancia
North has contributed to an extension of the Constancia reserve pit by approximately 300m
where there are no encumbrances as this area is part of the current permit of operation
• Revised Constancia mineral reserve estimates will be released at the end of March 2021 with
Hudbay’s annual mineral reserves and resources update
+300m
2020 reserve pit
2021 reserve pit
2019-2020 drilling
CONSTANCIA NORTH
40
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
• In addition to the extension of the reserve pit, high grade mineralization with economic potential
has also been extended to the north, which will contribute to an improvement of the head grade,
which will be incorporated into an updated mineral resource estimate to be published at the
March 2021 update
• A significant portion of this resource is expected to be classified as inferred due to wide drill
spacing and offers an opportunity to further increase the open pit reserve estimates in the near
future
CONSTANCIA NORTH DRILLING HAS ALSO EXTENDED THE RESOURCE PIT SHELL
2020 resource pit shell
2021 resource pit shell
2019-2020 drilling
CONSTANCIA NORTH
41
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
• There is an additional opportunity to include more resources and/or improve the life of mine plan
by mining some of the steeply dipping/narrower high-grade skarn mineralization as a satellite
underground operation to the main Constancia pit
• A scoping trade-off study will be conducted in 2021
UNDERGROUND POTENTIAL TO BE FURTHER INVESTIGATED
Block model filtered on Cu>0.5%
2019-2020 drilling
Constancia NorteSkarn bodies
CONSTANCIA REGIONAL POTENTIAL
42
K/Th radiometric data indicative of potassic alteration
associated with a mineralizing porphyry system
0 5,000 10,000
Meters
Kusiorcco Target
Acquired 2018
Acquired 2018
Acquired 2011
LEGEND
Process
Plant
Constancia Pit
Pampacancha Pit
Caballito
Target
Maria Reyna
Target
Pampacancha
Constancia
Caballito
Maria Reyna &
Kusiorcco
2.5km
Quehuincha North Target
Acquired 2020
Leviatan
Target
Paquitas Target
Property
Distance to
Process
Plant
Description
Pampacancha 5 km
• Community surface rights
agreement completed
• Consulta Previa process
completed
• Mining expected to start in 2021
Quehuincha
North11 km
• Community exploration
agreement completed
• Consulta Previa process
completed & drill permits
received
• Drilling initiated in Feb 2021
Paquitas &
Leviatan~10 km
• Community exploration
agreement completed
• Consulta Previa and drill permit
application processes underway
Maria Reyna &
Caballito5-10 km
• Negotiating community
agreement
• Caballito is a former copper
oxide mine (>5%)
• Maria Reyna is a prospective
copper skarn-porphyry
(historical drilling includes 160m
@ 1.0% CuEq from surface)
Kusiorcco 7 km
• Exploration agreement
discussions with communities
are pending
MINERAL PROPERTIES WITHIN TRUCKING DISTANCE OF CONSTANCIA INFRASTRUCTURE
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
MARIA REYNA HISTORICAL DRILL RESULTS
A summary of the historical drill results from Maria Reyna is contained in the table below, however a qualified person has not independently verified this historical data or the quality assurance and quality control program that was applied during the execution of this drill program for Hudbay and, as such, Hudbay cautions that this information should not be relied upon by investors.
43
Note: The intersections represent core length and are not representative of the width of the possible mineralised zone. Note: For additional information, including drill hole locations and the data verification and quality assurance / quality control carried out by the prior owner, please refer to Management’s Discussion and Analysis for IndicoResources Ltd. (“Indico”) for the year ended May 31, 2014, as filed by Indico on SEDAR on September 29, 2014.1. Intervals were calculated with maximum of 10m of 0.1% CuEq internal dilution, 0.2% CuEq edge grade, minimum length of 15m. For CuEq calculations the following variables were used: $3.00/lb Cu, $15.00/lb Mo, $21.00/oz Ag; no allowances for metallurgical recoveries were made.
VALE DRILL RESULTS
VALE DRILL INTERSECTIONS AT 0.2% CUEQ1 CUT-OFF
Hole ID From (m) To (m) Ag (ppm) Cu (%) Mo (ppm) CuEq % Interval (m)
DH-001 206 256 1.5 0.20 113 0.27 50
DH-002 0 136 4.1 0.52 78 0.61 136
DH-003226 256 1.7 0.24 122 0.31 30
460 480 0.3 0.19 62 0.22 20
DH-004
10 240 3.0 0.26 124 0.35 230
336 486 1.5 0.18 147 0.27 150
502 522 0.8 0.19 87 0.24 20
DH-005 10 76 4.8 0.63 122 0.74 66
DH-006 0 114 4.0 0.32 112 0.41 114
DH-007
0 106 2.5 0.39 267 0.55 106
176 216 1.7 0.25 280 0.41 40
232 310 1.0 0.17 272 0.31 78
DH-008256 394 1.4 0.28 130 0.36 138
432 520 1.7 0.23 209 0.36 88
DH-009
18 90 1.7 0.28 335 0.47 72
110 172 0.7 0.14 184 0.24 62
196 256 0.9 0.18 106 0.24 60
DH-010262 314 1.7 0.30 204 0.42 52
344 406 2.1 0.34 641 0.68 62
DH-01118 178 2.9 0.50 998 1.03 160
374 406 1.1 0.14 175 0.24 32
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
44
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
EXPLORATION PERMITTING TIMELINEDRIVEN BY COMMUNITY RELATIONS AND PERMITTING
• It can take up to 18 months to obtain drill permits
QUEHUINCHA NORTH: SKARN TARGET
45
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
• Quehuincha North target is located 3km north of the
Kusiorcco area
• Field work was conducted to follow up on coincidence of
aeromagnetic and radiometric anomalies
• Mapping shows copper mineralization in skarn extending
for almost 2 km
• Geophysics: ground magnetic and IP survey evidenced
chargeability and resistivity anomalies associated with the
lenses mapped on surface
• A 6-hole initial test drill program started in February 2021
46
• Hudbay’s field work has confirmed continuity of the mineralized
system southeast of the drilled area, coincident with
geochemistry and chargeability anomalies
• Community agreement signed in December 2019; all required
drill permits received in 2020 and drilling expected to commence
in Q2 of 2021
• No Consulta Previa required
Chargeability 300 m
LLAGUEN PROJECTGREENFIELD EXPLORATION
• Located near existing
infrastructure
• Located near available
workforce; 56km northeast
of Trujillo, the third largest
city in Peru
• Mineralization drilled by
Vale in 2006-2008 and is
open to the north and
northwest
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
Hole ID From (m) To (m) Intercept (m)Estimated true width
(m) 1 Cu (%) 2,3 Mo (g/t) 2,3 Au (g/t) 2,3 Ag (g/t) 2,3
LL-06-001 6 72 66 57.2 0.26 204.6 0.04 1.6
LL-06-002 6 284 278 240.8 0.37 296.1 0.04 2.3
LL-06-003 236.0 453.7 217.7 186.6 0.43 224.9 0.04 2.3
LL-06-004 4 172 168 139.3 0.28 156.5 0.03 1.8
LL-06-004 222 250 28 23.2 0.23 136.4 0.02 1.9
LL-06-005 14 434 420 363.7 0.33 306.6 0.03 2.1
LL-06-006 160 310 150 129.9 0.29 214.2 0.04 1.7
LL-06-007 196.0 567.6 371.6 317.5 0.29 194.5 0.03 1.8
LL-07-009 192 323 131 116.0 0.28 43.1 0.03 2.1
LL-07-009 368.5 430.0 61.5 54.3 0.32 137.7 0.05 2.1
LL-07-009 522 576 54 47.2 0.15 35.9 0.01 2.4
LL-07-010 252 438 186 158.5 0.26 60.0 0.02 1.8
LL-07-011 83 135 52 44.7 0.20 172.4 0.02 0.9
LL-07-012 374 402 28 24.5 0.19 43.6 0.02 1.5
LL-07-014 0 124 124 112.0 0.21 48.8 0.02 2.1
LL-07-015 18 60 42 36.2 0.17 77.0 0.02 0.7
LL-07-015 108 468 360 298.9 0.20 107.9 0.02 1.1
LL-07-016 8 212 204 182.9 0.36 265.2 0.03 2.3
LL-07-018 318 472 154 131.1 0.18 70.4 0.02 1.2
LL-08-022 372 436 64 52.5 0.22 129.3 0.02 1.2
LL-08-023 497.3 576.57 79.3 70.1 0.16 148.6 0.01 1.3
47
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
LLAGUEN PROJECTHISTORICAL VALE DRILL RESULTS INTERSECTED MINERALIZATION
• Vale drilled 23 holes totaling 10,834 metres
• Results include 186.6 metres at 0.43% Cu
1. True widths are estimated based on drill angle and intercept geometry of mineralization2. All copper, molybdenum, gold and silver values are uncut3. No SG data so assay results are length weighted
A summary of the historical drill results from Llguen is contained in the table below, however a qualified person has not independently verified this historical data or the quality assurance and quality control program that was applied during the execution of this drill program for Hudbay and, as such, Hudbay cautions that this information should not be relied upon by investors.
Hudbay’s ESG Principles in Peru
48
5
JAVIER DEL RIO
VP SOUTH AMERICA B.U.
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
GOVERNMENT AND COMMUNITY INSTITUTIONS
• We work with all levels of Government and Communities to develop stable operations and
to maximize the impact of our social investment in our area of influence and beyond
Level Applicable Area Election
Frequency
Next Election Candidates - political position - last
poll results(1)
National-Presidential Peru
Every 5 years April 11, 2021
1. George Forsyth - Center - 8.9%2. Yonhy Lescano - Center Left - 8%3. Keiko Fujimori - Right - 6.4%4. Veronika Mendoza - Left - 4.7%
National-Congress PeruEvery 5 years April 11, 2021
Strong regional promotion for congress by
different political parties.
Regional Cusco
Every 4 years 2022Provincial Chumbivilcas
District Chamaca, Livitaca &
Velille,
Local Community Chilloroya,
UchucarccoEvery 2 years 2022
•Ministry of Energy & Mines
•Ministry of Labor
• Mult-level coordination:Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
49
•Ministry of Health: partner in health social
projects and mitigation of COVID-19
•Ministry of Interior: security issues and
coordination with the National Police
•Ministry of Economy and Finance:
Investment promotion
LOCAL POLITICAL CONTEXT
50
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
RENEWED AGREEMENTS WITH DISTRICTS AND COMMUNITIES DURING THE COVID-19
PANDEMIC
PROVINCES
Chumbivilcas:
• Donations to mitigate COVID-
19 (partnership with other
organizations)
• Integral Health Networks
Project -Works for Taxes- for
PEN 5.4M under execution
• Consensus in the negotiation
for the signing of the
Framework Agreement with the
province of Chumbivilcas
Espinar: Negotiation to execute
social support of Works for Taxes
program
IAI - DISTRICTS
Chamaca: Specific Agreement for
PEN 7M (2 years) was executed
Livitaca: Specific Agreement for PEN
14M (4 years) was executed
Velille: Specific Agreement for PEN
3.5M (1 year) was executed
OTHER COMMUNITIES
Oquebamba: Specific Agreement
under execution for PEN 50K (1
year).
Pumahuasi: Specific Agreement
executed for PEN 50K (1 year).
Pausiri: Specific Agreement under
execution for PEN 50K (1 year).a
OTHER DISTRICTS
Coporaque: Specific Agreement for
PEN 600K under execution (1 year)
Condoroma: Specific Agreement for
PEN 500K under execution (1 year)
51
RECENT SOCIAL HIGHLIGHTS
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
● The "Tikary – Bordando el Futuro" Project, developed in the reactivationphase of the pandemic plan, was recognized in the “Proactivo Award”
● The Agrarian Development Program has been strengthened by joint support between Hudbay and strategic partners by providing increased technical and financial resources
• The Mining Cluster of Southern Peru initiative aimed at developing the south area of Peru through a technical cooperation agreement between the Inter-American Development Bank, Arequipa’s Chamber of Commerce and the mining industry
• Roundup negotiation table: reached an agreement with the province of Chumbivilcas, and on February 25th, signed an inter-institutional cooperation framework agreement
• Other projects in progress include:
• Work for Taxes: Integrated Health Network- Telemedicine (Ministry of Health)
• Two Health Centers in local communities (Regional Government)
• Two significant Irrigation Projects (Ministry of Agriculture)
• In the district of Velille we are constructing 9.7 km of road and 54,900 m2
of paved
sidewalks to furthur urban development
IN 2020 & 2021, HUDBAY HAS ADAPTED TO PROVIDE SUPPORT FOR THESE
UNPRECEDENTED TIMES
52
RECENT ENVIRONMENTAL HIGHLIGHTS
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
● The ISO 14001:2015 recertification and migration to ISO 45001:2018
was awarded based on the successful audit of our environmental,
health and safety management system
● The Ministry of the Environment of Peru recognized Constancia for its
efficiency in managing greenhouse emissions
• Significant native flora program is being implemented: seed germination
tests of native tree species are being carried out to be used in
restoration and biodiversity improvement works
• We are transforming organic waste into compost and reusing Waste
Water Treatment Plant sludge to enrich topsoil and use as added
fertilizer
• 54% of all solid waste was recycled in 2020, a 7% improvement over
2019
WE ALWAYS STRIVE TO ACHIEVE ENVIRONMENTAL BEST PRACTICES
53
SOCIAL INVESTMENT BREAKDOWNHUDBAY PERU HAS FIVE SOCIAL DEVELOPMENT AREAS
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
54
RECENT SOCIAL INVESTMENTCOVID-19 AND COMMUNITY RELIEF
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
55
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
RECENT SOCIAL INVESTMENTCOVID-19 AND COMMUNITY RELIEF (CONTINUED)
* Estimated investment pending approval of the Work For Taxes program by the regional and health authorities
Q&A SESSION
APPENDIX
PERU MINERAL RESERVES
CATEGORY TONNES Cu (%) Mo (g/t) Au (g/t) Ag (g/t)
CONSTANCIA1
Proven 408,800,000 0.28 85 0.035 2.76
Probable 77,500,000 0.27 70 0.044 3.58
Total Proven and Probable 486,300,000 0.28 83 0.036 2.89
PAMPACANCHA1
Proven 32,400,000 0.59 178 0.368 4.48
Probable 7,500,000 0.62 173 0.325 5.75
Total Proven and Probable 39,900,000 0.60 177 0.360 4.72
Total Mineral Reserves 526,600,000 0.30 90 0.061 3.03
AS AT JANUARY 1, 20201
Note: Totals may not add up correctly due to rounding.
1. Mineral reserves and resources calculated using metal prices of $3.10 per pound copper, $11.00 per pound molybdenum, $17.0 0 per ounce silver and $1,375 per ounce gold. The Constancia and Pampacancha reserve pits consist of operational
pits of proven and probable reserves and are based on metal prices noted, metallurgical recoveries applied by ore type (betwe en 84.4% to 90.5%), and processing costs of $4.54 per tonne milled, general and administrative costs of $1.60 per
tonne milled and mining costs of $1.30 and $1.35 per tonne moved (waste and ore, respectively).58
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
PERU MINERAL RESOURCES
AS AT JANUARY 1, 20201
CATEGORY TONNES Cu (%) Mo (g/t) Au (g/t) Ag (g/t)
CONSTANCIA
Measured 122,700,000 0.18 55 0.028 1.77
Indicated 154,300,000 0.20 65 0.033 1,87
Inferred 83,100,000 0.18 43 0.036 3.45
PAMPACANCHA
Measured 11,400,000 0.41 101 0.245 4.95
Indicated 6,000,000 0.35 84 0.285 5.16
Inferred 10,100,000 0.14 143 0.233 3.86
Total Measured and Indicated 294,400,000 0.20 63 0.045 2.01
Total Inferred 93,200,000 0.18 54 0.057 3.44
59
Note: Totals may not add up correctly due to rounding.
1. Mineral reserves and resources calculated using metal prices of $3.10 per pound copper, $11.00 per pound molybdenum, $17.0 0 per ounce silver and $1,375 per ounce gold. The Constancia and Pampacancha reserve pits consist of operational
pits of proven and probable reserves and are based on metal prices noted, metallurgical recoveries applied by ore type (betwe en 84.4% to 90.5%), and processing costs of $4.54 per tonne milled, general and administrative costs of $1.60 per
tonne milled and mining costs of $1.30 and $1.35 per tonne moved (waste and ore, respectively).
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
ADDITIONAL INFORMATION – RESERVES & RESOURCES
The reserve and resource estimates included in this presentation were prepared in accordance with National Instrument 43-101 –
Standards of Disclosure for Mineral Projects (“NI 43-101”) and the Canadian Institute of Mining, Metallurgy and Petroleum Standards
on Mineral Resources and Reserves: Definitions and Guidelines.
The mineral resource estimates in this presentation are exclusive of mineral reserves. Mineral resources that are not mineral reserves
do not have demonstrated economic viability.
The technical and scientific information in this presentation has been approved by Cashel Meagher, P. Geo, Hudbay’s Senior Vice
President and Chief Operating Officer. Mr. Meagher is a qualified person pursuant to NI 43-101. For a description of the key
assumptions, parameters and methods used to estimate mineral reserves and resources at Constancia and Pampacancha, as well as
data verification procedures and a general discussion of the extent to which the estimates of scientific and technical information may
be affected by any known environmental, permitting, legal title, taxation, sociopolitical, marketing or other relevant factors, please see
the technical report for Constancia as filed by Hudbay on SEDAR at www.sedar.com.
This presentation has been prepared in accordance with the requirements of the securities laws in effect in Canada, which may differ
materially from the requirements of United States securities laws applicable to U.S. issuers.
60
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
ADDITIONAL INFORMATION – LLAGUEN
61
Appendix
Introduction
Constancia Overview
Optimization Opportunities
Regional Exploration
ESG Principles
From To Azimuth at
intercept
Dip at
intercept
Core
SizeHole ID Easting Northing Elevation Easting Northing Elevation
LL-06-001 748,956.8 9,146,263.8 2,184.8 748,956.8 9,146,296.8 2,127.6 0 -60 HQ
LL-06-002 748,705.8 9,145,948.8 2,134.8 748,705.8 9,146,087.8 1,894.0 0 -60 HQ
LL-06-003 748,733.8 9,145,771.3 2,022.7 748,733.8 9,145,883.4 1,836.1 0 -59 HQ
LL-06-004 748,954.8 9,146,258.5 2,186.7 748,954.8 9,146,164.6 2,047.4 180 -56 HQ
LL-06-004 748,954.8 9,146,136.6 2,006.0 748,954.8 9,146,121.0 1,982.7 180 -56 HQ
LL-06-005 749,207.8 9,145,916.8 2,209.9 749,207.8 9,146,126.8 1,846.1 0 -60 HQ
LL-06-006 748,350.8 9,146,080.8 1,941.4 748,350.8 9,146,155.8 1,811.5 0 -60 HQ
LL-06-007 748,954.4 9,145,794.2 2,125.1 748,991.2 9,145,983.7 1,807.8 11 -59 HQ
LL-07-009 749,223.3 9,145,774.4 2,151.2 749,230.1 9,145,834.9 2,035.2 6 -62 HQ
LL-07-009 749,233.7 9,145,855.7 1,995.0 749,239.3 9,145,884.2 1,940.7 11 -62 HQ
LL-07-009 749,250.5 9,145,926.7 1,859.9 749,257.5 9,145,952.0 1,812.7 15 -61 HQ
LL-07-010 748,343.0 9,146,316.6 1,893.6 748,356.0 9,146,413.1 1,735.2 8 -58 HQ
LL-07-011 749,543.4 9,145,792.3 2,316.2 749,544.0 9,145,818.9 2,271.5 1 -59 HQ
LL-07-012 748,344.2 9,146,573.2 1,821.5 748,345.4 9,146,586.7 1,797.0 5 -61 HQ
LL-07-014 748,737.8 9,146,189.7 2,162.0 748,742.6 9,146,242.8 2,050.0 5 -65 HQ
LL-07-015 749,195.5 9,146,137.9 2,255.5 749,195.1 9,146,159.2 2,219.3 359 -59 HQ
LL-07-015 749,194.8 9,146,183.6 2,178.0 749,211.6 9,146,383.3 1,879.4 5 -56 HQ
LL-07-016 748,970.8 9,145,974.4 2,152.9 748,969.2 9,146,064.7 1,970.0 359 -64 HQ
LL-07-018 748,348.0 9,145,935.7 1,837.7 748,361.0 9,146,015.3 1,706.6 9 -58 HQ
LL-08-022 748,560.0 9,145,776.2 1,789.8 748,566.1 9,145,812.3 1,737.4 10 -55 HQ
LL-08-023 748,933.2 9,145,719.5 1,800.0 748,938.4 9,145,756.3 1,729.9 8 -62 HQ
VALE HISTORICAL DRILL HOLE INFORMATION
For More Informat ion Contact :
Candace Brûlé
Director, Investor Relations
416.814.4387 | [email protected]