Transcript of Consortium Meeting La Palma October 1-2 2008 ICC Status Tanya Lim 1 SPIRE Consortium Meeting La...
ICC Status Tanya Lim 1
Consortium Meeting La Palma October 1-2 2008
SPIRE Consortium MeetingLa Palma, Oct. 1 – 2 2008
ICC Status
Tanya Lim
RAL
ICC Status Tanya Lim 2
Consortium Meeting La Palma October 1-2 2008
ICC Operations Manager
Tanya Lim
DAPSAS UK Manager
Dave Clements
DAPSAS Fr ManagerMarc Sauvage
DAPSAS Can Manager
Peter Davis-Imhof
Cal ScientistSarah Leeks
Software Manager
Steve Guest
OBST Team Leader
Dave Clements
OPS ScientistSunil Sidher
System EngineerSunil Sidher
Support Group
Jane PorterBrian Coan
User GroupMattia Vaccari
Operations TeamCalibration Team ICC Software Development Team Observations and Data Reduction Team
ICC Institute Managers
Software Engineers Science Developers
Instrument Scientist
Bruce Swinyard
PIMatt Griffin
Calibration Scientists Instrument Engineers
ICC ScientistSeb Oliver
ICC Management Team
Consortium
PA/QAManager
Eric Clark
ICC Organisation
ICC Status Tanya Lim 3
Consortium Meeting La Palma October 1-2 2008
SPIRE ICC Systems Overview• Several machines based at RAL but with access from all ICC sites…
• Propagated Database(s)• Remote access e.g. via QLA, ObsExporter
• Product Pools• Data Processing and Calibration Products
• Operational Software and Results (Health Monitoring, Operational Day logging, Trend Analysis etc)
• Common Uplink System
• Helpdesk system (RAL)
• Websites• TWiki based at Leuven (main site for information sharing)• Wiki based at NHSC (NHSC analysis and results)• Test Team Website based at RAL (Test Data)• HSC/ESTEC Sites hosting SxR system, NCR system and
documentation
ICC Status Tanya Lim 4
Consortium Meeting La Palma October 1-2 2008
ICC Status Tanya Lim 5
Consortium Meeting La Palma October 1-2 2008
Operations Team Status• Operational Procedures and Interactions• Instrument Users Manual• Helpdesk• SPIRE mailbox is operational• AOT Maintenance and Testing• CUS Scripts and Procedures• Operational Day Logging• Instrument Health Monitoring• Trend Analysis
ICC Status Tanya Lim 6
Consortium Meeting La Palma October 1-2 2008
Calibration Team Status• PV Phase Planning• Observation Definition• Testing PV Phase• Uplink Calibration File Design and Population• DP Calibration File Design and Population• DP Calibration File Testing
ICC Status Tanya Lim 7
Consortium Meeting La Palma October 1-2 2008
Observations Group Status• DP Requirements• Acceptance Testing• Scientific Validation
ICC Status Tanya Lim 8
Consortium Meeting La Palma October 1-2 2008
Software Team StatusSPIRE Data Processing Development• So far mostly pipeline oriented although some display tool
development has also taken place• Full integration into HIPE in progress• Interactive Analysis
• By design pipeline modules can be used for interactive analysis and all tasks can be run interactively,
• Effort will move to interactive analysis development between now and launch
• Integration with HIPE is a major step in this process• Extended Work Packages• Contribution to HCSS/DP
ICC Status Tanya Lim 9
Consortium Meeting La Palma October 1-2 2008
Summary
• The ICC is moving forward with a good working structure• This will be maintained going into operations
• The work division between the teams is generally well understood
• The work is generally on track to be ready for operations,• However, staffing (and expertise of staff) is a perennial issue
which remain
• Many thanks to Ken!