Consensus Docs: Introduction to Integrated Project Delivery in Construction
description
Transcript of Consensus Docs: Introduction to Integrated Project Delivery in Construction
![Page 1: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/1.jpg)
Introduction To Integrated Project Delivery
Joe ClevesWill A. Lichtig
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 2: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/2.jpg)
DESIGN-BID-BUILD:A BROKEN SYSTEM
Productivity not improving
Selection criteria – lowest initial price
Fragmented process – flawed assumptions
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 3: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/3.jpg)
Requests for Information are wasteful
Bid margins contain past inefficiencies
Redesign is rampant and expensive
DESIGN-BID-BUILD:A BROKEN SYSTEM
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 4: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/4.jpg)
Traditional contracts – Rules of War
Risk flows down
Party’s incentive – own best interest
DESIGN-BID-BUILD:A BROKEN SYSTEM
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 5: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/5.jpg)
Spearin doctrine’s implied design warranty
Conflicting decisions mean unpredictable results
Results amplify adversarial relations
DESIGN-BID-BUILD:A BROKEN SYSTEM
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 6: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/6.jpg)
Economic loss decisions equally confusing
Complex doctrine with complex exceptions
Contract drafting becomes guesswork
DESIGN-BID-BUILD:A BROKEN SYSTEM
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 7: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/7.jpg)
Traditional Versus IPD
Owner
Planner A/E Builder
Other Partners
Traditional Model
• Hierarchical
• “Push processes”
• Risk avoidance© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 8: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/8.jpg)
TRADITIONAL PROJECT DELIVERYLEVEL OF COMMON UNDERSTANDING
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 9: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/9.jpg)
Traditional Project DeliveryRestricting communication
limits understanding
Limiting understanding undermines core assumption
Traditional approach conceals significant risk
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 10: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/10.jpg)
Seeing New Possibilities
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 11: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/11.jpg)
O A R
Change the observer
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 12: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/12.jpg)
Ohno’s World
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 13: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/13.jpg)
A Study in Production System Design
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 14: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/14.jpg)
Round 1 - Rules
Purpose: To enable each person to have everyone’s e-mail address on one card
Cards start at first positionWrite your e-mail address legibly on each cardWhen all are complete, pass stack to the next personWhen you are done, go to end to pick up your card
then sit downRepeat until group is finished
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 15: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/15.jpg)
Round 1 - MeasurementsTime to First Card Completed by GroupTime to Last Card Completed by Group
Also notice:Amount of time waiting to startAmount of time waiting for finished product
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 16: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/16.jpg)
Round 2 - Rules
Purpose: To enable each person to have everyone’s e-mail address on one card
Cards start at first positionWrite your e-mail address legibly on each cardAfter you complete each card, pass it to the next
personWhen you are done, go to end to pick up your card then
return to your seat and sit downRepeat until group is finished© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights
reserved
![Page 17: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/17.jpg)
Round 2 - Measurements
Time to First Card Completed by GroupTime to Last Card Completed by Group
Also notice:Amount of time waiting to startAmount of time waiting for finished product
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 18: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/18.jpg)
Production System Design
Reliable WorkflowSingle Piece Flow vs. Batch & Queue
What else might we do to improve performance of production system?
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 19: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/19.jpg)
O R
G A
N I
Z A
T I
O N O
P E
R A
T I N G
COMMERCIAL
ILPD as a Counter Measure
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 20: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/20.jpg)
Collaborate;Really Collaborate
Networks ofCommitment
Tightly CoupleLearning w/ Action
OptimizeThe Whole
IncreaseRelatedness
Courtesy LCI
Five Big Ideas
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 21: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/21.jpg)
OperatingSystemOrganization Commercial
Old
ILPD
Hierarchical
Siloed
Command & Control
CPM
Specialists
Parts
Lean
Sustainable
BIM
Collaborative
Flat
Consensus
Lump Sum
Low Price
Entrepreneurial
Collective
Best Value
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 22: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/22.jpg)
Organization
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 23: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/23.jpg)
Why? What? How?
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 24: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/24.jpg)
Why?
What?
How?
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 25: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/25.jpg)
Architect
Civil
StructuralMechanical
Electrical
Plumbing
LandscapeElevatorsInteriorParking
CM/GC
Site
SteelMechanical
Electrical
PlumbingLandscape
FramingFloor Cover
Painting
Owner
Geotech
MaterialsFood Service
Traffic
Medical Equip
PharmacyAdmin
OperationsDiagnostics
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 26: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/26.jpg)
OwnerStakeholder
CM/GC’s PMA/E’s PM
Owner Rep
Core Group
Civil
Structural
Mechanical
ElectricalPlumbing
Site
Steel
Mechanical
ElectricalPlumbing
Framing
Landscape
LandscapeOther
Other
Integrated Project Delivery Team
Diagnostics
Material Mgt
Plant Operations
Admin
Food Service
Imaging
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 27: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/27.jpg)
TVD Innovation TeamsM/E/P
Team Leaders
Structure
Landscape
Material Handling
Vertical Transp.
Site Improvements
Interior/ Finishes
Building Envelope
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 28: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/28.jpg)
Co
mm
on
Un
derstan
din
g CM/GC Hired
Major Trades Hired
Pre-Construction Services
Architect Hired
Engineers Hired
≤100%
SD DD CD
Construction
Time
Owner
Traditional Level of Common Understanding
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 29: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/29.jpg)
Time
Co
mm
on
Un
derstan
din
g
CM/GC Hired
Concept Design Implementation
Construction
Architect Hired
Engineers Hired
100%
Major Trades Hired
Pre-Construction Services
Valid.
Owner
ILPD Level of Common Understanding
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 30: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/30.jpg)
Tools and Techniques
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 31: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/31.jpg)
SETTING UP AN IPD SYSTEMCharacter
competency
Ability to collaborate
Begin team selection © 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights
reserved
![Page 32: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/32.jpg)
LEAN TOOLSOpen communication
Design in the Big Room – Project participants meet together for design.
Elimination of waste© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 33: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/33.jpg)
LEAN TOOLS –RELIABLE COMMITMENTS
Relational contracting
Binding contractual obligation
Improved workflow results© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 34: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/34.jpg)
LEAN TOOLS – PULL PLANNING
Reliable handoffs of work are critical
Pull planning removes waste
Last Planner System© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 35: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/35.jpg)
LEAN TOOLS – SCHEDULING
Master Phase scheduling pull planning
Look-ahead planning
Weekly work plans
Planned percentage complete© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 36: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/36.jpg)
A Study in Collaboration
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 37: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/37.jpg)
Commercial Terms
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 38: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/38.jpg)
Traditional Risk Management
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 39: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/39.jpg)
Open-Face Risk Management
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 40: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/40.jpg)
Fee
Salaried
Labor
General
Requirements
Co
st
of
Wo
rk
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 41: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/41.jpg)
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 42: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/42.jpg)
Fee
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 43: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/43.jpg)
Lean Operating System - Design
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 44: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/44.jpg)
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 45: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/45.jpg)
Target Cost
Actual Cost
Planning & Programming
System Design
Detailing
Production
Allowable Cost
Business Case
In-Service Date
Functional Program
Allowable Cost
Expected Cost
Production Innovation
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 46: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/46.jpg)
Concept Design ImplementationConstructionPre-Construction Services
Valid.
Planning & Programming
Design
Detailing
Production Plan
Levels of TVD
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 47: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/47.jpg)
Defining Value
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 48: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/48.jpg)
Desirability
Viability Feasibility
Change by Design
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 49: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/49.jpg)
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 50: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/50.jpg)
Expected Cost
Target Cost
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 51: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/51.jpg)
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 52: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/52.jpg)
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 53: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/53.jpg)
Full-scale mock-up of new ED
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 54: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/54.jpg)
Testing using case scenarios
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 55: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/55.jpg)
viscous wall damper• ultimate reduction
in damping budget of $9m
steel structure• validation ~ 22psf
• current design ~ 20psf
• industry standard ~ 30psf
Optimizing systems
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 56: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/56.jpg)
Optimized for construction• Attachment Bolts per VWD
• Previous 102 ~ 1-9/16 bolts• Current 36 ~ 1-9/16
66 ~ 1-3/16• Savings 2 man-day each
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 57: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/57.jpg)
PROTOTYPE COST SAVING IDEAS
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 58: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/58.jpg)
Lean Operating System - Production
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 59: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/59.jpg)
Lean ProductionPlanning &
Control
Built-in Quality
Constraint
Removal
ProblemSolving
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 60: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/60.jpg)
• Information• Access/
Space• Prior Work
(handoff)• External
Approvals
• Material• Equipment/Tools• Methods/Skills• Labor
Provide Worker Everything Needed to Succeed
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 61: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/61.jpg)
Expectations
DesignOperations
Results
Reject
Work Inspect
BiQ
QA/QC
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 62: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/62.jpg)
Produce Defect-Free Work
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 63: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/63.jpg)
First Run Study
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 64: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/64.jpg)
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 65: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/65.jpg)
Managing Takt Through Visual Control
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 66: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/66.jpg)
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 67: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/67.jpg)
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 68: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/68.jpg)
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved
![Page 69: Consensus Docs: Introduction to Integrated Project Delivery in Construction](https://reader035.fdocuments.us/reader035/viewer/2022070301/5452a19daf7959bb0c8b77f3/html5/thumbnails/69.jpg)
Daily Production Huddles
© 2013 Dressman Benzinger LaVelle psc and The Boldt Company. All rights reserved