Connection and Transmission Use of System Charge...
Transcript of Connection and Transmission Use of System Charge...
Connection and Transmission Use of System Charge Methodology:
Initial Proposals Paper
Attachment to the Authority’s letter dated 31 May 2018
i
Table of Contents
1. Introduction 1
Scope and structure of this Initial Proposals document 2
2. The assessment of the existing CUSC methodology 3
The Connection and Use of System Charge Methodology 3
The objectives and principles of transmission charging 6
3. Potential reforms to the connection charge methodology 8
Assessment of connection charge methodology 8
Possible reforms to the connection charge methodology 10
4. Potential reforms to the transmission use of system charging methodology 26
Assessment of transmission and use of system charging methodology 26
Possible reforms to the transmission use of system charge methodology28
Conclusion 59
5. Interactions between the CUSC and the price control review 62
Conclusion 65
6. Timetable for review of the CUSC methodology 66
Appendix A: list organizations that responded to the CUSC Consultation Paper 67
ii
Glossary
CUSC Connection and Use of System Charges
DSSS Distribution Security of Supply Standard
ENTSO-E European Network of Transmission System Operators (electricity)
GAV Gross Asset Value
kW Kilowatt
kWh Kilowatt hour
LDC Load Dispatch Centre
MAR Maximum Allowable Revenue
MEDC Muscat Electricity Distribution Company
MIS Main Interconnected System
MJEC Majan Electricity Company
MTSD Maximum Transmission System Demand
MW Megawatt
MWh Megawatt hour
MZEC Mazoon Electricity Company
O&M Operation and Maintenance
OETC Oman Electricity Transmission Company
OPWP Oman Power and Water Procurement Company
OR Omani Rial
PPA Power Purchase Agreement
RAEC Rural Areas Electricity Company
TRC Transmission Running Charge
TSS Transmission Security Standard
TUoS Transmission Use of System
WACC Weighted Average Cost of Capital
Page 1 of 67
1. Introduction
1.1 This document sets out the Authority’s Initial Proposals with respect to the possible
modification of the Transmission Connection and Use of System Charge (CUSC)
methodology.
1.2 The CUSC methodology sets the rules through which the Oman Electricity Transmission
Company (OETC) recoups the costs of financing, building and operating the electricity
transmission system for the Main Interconnected System (MIS) and the Dhofar Power
System.1 These costs are comprised of connection charges (i.e., the capital and
operating costs of a connection to the transmission network) that are paid by
generators and transmission-connected customers and Use of System charges (i.e., the
capital and operating costs of the transmission system) that are paid by licensed
suppliers.
1.3 Based on the CUSC methodology, OETC publishes annually a Statement of
Transmission System Charges that sets out the Transmission Use of System (TUoS) and
connection application fees that will apply for the following year.2 The same charges
apply to both the MIS and the Dhofar systems.
1.4 Transmission charging plays an important role in the efficient operation of the
electricity system and therefore in the overall development of the Omani economy. In
addition to facilitating the recovery of the costs of investment and operation of
transmission infrastructure, charges can also provide signals for investment
requirements in generation and transmission and, to the extent that the charges are
reflected in end-user tariffs, can also encourage more efficient electricity consumption
behaviour.
1.5 In January 2018, the Authority published a Consultation Paper that discussed the
strengths and weaknesses of the existing CUSC methodology based on an assessment
against a set of principles and objectives that electricity transmission charging should
deliver. The Consultation Paper also discussed the interactions between the CUSC
methodology and OETC’s price control review (i.e., whether the CUSC methodology
creates incentives for OETC, generators and/or transmission-connected customers that
improves or reduces the overall efficiency of transmission costs). Finally, the
Consultation Paper proposed a range of areas in which the CUSC methodology could
potentially be reformed in order to better deliver those objectives.
1 In other areas, transmission services are provided by the vertically integrated Rural Areas Electricity
Company (RAEC).
2 The Statement of Transmission System Charges for 2018 can be found at: http://www.aer-
oman.org/aer/NetworkCharges.jsp?heading=2
Page 2 of 67
1.6 The Consultation Paper was sent to a range of stakeholders in the electricity sector,
including OETC, Oman Power and Water Procurement Company (OPWP), the Discos and
to generators. These stakeholders were invited to submit their views on both the
Authority’s assessment of the existing methodology and the proposed reforms.
1.7 The Authority has scrutinized and analysed the responses received in order to develop
this Initial Proposals document, which considers a number of possible changes to the
CUSC methodology.
Scope and structure of this Initial Proposals document
1.8 The remainder of this Initial Proposals paper is structured as follows:
Section 2 provides an overview of the responses related to the criteria that the
Authority used to assess the existing CUSC methodology;
Section 3 provides an overview of responses from stakeholders to proposals related
to connection charging and the Authority’s Initial Proposals;
Section 4 provides an overview of responses from stakeholders to proposals related
to TUoS charges and the Authority’s Initial Proposals;
Section 5 provides an overview of the questions related to the interactions between
the CUSC methodology and OETC’s ongoing price control review; and
Section 6 sets out the timetable for responding to these Initial Proposals and the
Authority’s timetable for making any changes to the CUSC methodology.
Page 3 of 67
2. The assessment of the existing CUSC methodology
2.1 In this section, we provide a brief overview of the CUSC methodology and the objectives
and principles that were developed in the Consultation Paper in order to assess that
methodology. The full methodology is set out in the Connection and Use of System
Charge Methodology Statement (also known as the “Condition 25 Statement”), which is
developed by OETC.3
The Connection and Use of System Charge Methodology
2.2 The Transmission and Dispatch Licence places obligations on OETC with respect to
connection and use of the transmission system. With respect to connection, OETC has
an obligation pursuant to a condition of its licence to offer terms for connection to any
person who applies, where the capital and operating costs of the connection are
recouped from the connecting entity. In terms of use of the transmission system, in
accordance with its licence, OETC is required to accept electricity into the transmission
system from OPWP or a licensed supplier and to deliver such quantities of electricity to
exit points on the transmission system as required by OPWP, or a licensed supplier. The
costs of the transmission system are recouped from licensed suppliers through TUoS
charges.
Connection charge methodology
2.3 Connection charges cover the costs of ‘Connection Assets’ (which are defined as the
assets solely required to connect an individual user to the transmission system and
would not normally be used by another party), any ancillary items (e.g., common
buildings that house the connection assets and other assets) as well as covering the
on-going costs of maintaining the connection.4 The connection charges apply to all
parties connected to the transmission system, which includes electricity generators,
suppliers and transmission-connected customers.
3 See:
www.omangrid.com%2Fen%2FReport%2FConnection%2520and%2520Use%2520of%2520System%2520C
harge%2520Methodology.PDF&usg=AOvVaw1ZPMDMXcw9qnIgZkOz4OMw
4 Connection and Use of System Charge Methodology Statement, Section 2 (Charging Principles).
Page 4 of 67
2.4 The annual connection charge is composed of two elements: (a) capital charge; and (b)
transmission running charge (TRC). The capital charge component recovers the capital
cost of providing the connection assets. The capital charge is based on the Gross Asset
Value (GAV) of the connection assets (which represents the capital element of the
actual costs of providing the asset, including the costs of purchase, transport,
installation, financing, design and consents) annuitized over the weighted average
asset lifetime. The annuitized value includes a rate of return based on the weighted
average cost of capital (WACC), set through OETC’s price control process. The WACC
that is used in the charge calculation remains unchanged across the lifetime of the
asset The capital charge is based on the following formula (reproduced from the
CUSC5):
Capital charge = (GAV x WACC) / 1 – (1 + WACC)-N
Where:
GAV = gross asset value
WACC = weighted average cost of capital
N = weighted average asset lifetime
2.5 Connecting entities have some flexibility in deciding on the period over which they will
repay the capital costs of their connection. Parties choosing to pay back the costs over
time (rather than up front) can choose to annuitize the capital costs over a period of 5,
10, 15 or 20 years.
2.6 In addition, connecting entities have the opportunity to make an up-front capital
contribution through the Capital Charge Payment Option. Any up-front capital
contribution is deducted from the GAV in the calculation of the annual capital charge.
In the situation where the connecting entity pays the capital costs up-front in full, the
annual capital charge will be zero.
2.7 The TRC component of the annual connection charge recovers the costs of operation
and maintenance of the connection assets. Some entities are responsible for the
operation and maintenance (O&M) of their connection asset (so-called ‘user
maintained assets’). As such, no TRC is charged to these entities.
2.8 For all other entities, the TRC is calculated through an annual ‘TRC factor’, which is
based on the inflation-adjusted connection asset operating expenditure allowance
(which is set in OETC’s price control review) as a proportion of the total connection
asset GAV (excluding user maintained connection assets). The TRC factor is calculated
through the following formula:
5 Connection and Use of System Charge Methodology (p.19)
Page 5 of 67
TRC Factor = Connection Asset Operating Expenditure Allowance (inflation
adjusted) / (Connection Asset GAV – User Maintained Connection Asset GAV)
2.9 The TRC factor will therefore vary from year-to-year depending on the evolution of
operating costs and connection capex. The TRC for a particular entity is then calculated
by multiplying the TRC factor by that entity’s GAV. The TRC is calculated through the
following formula:
TRC for customer A = TRC factor x (customer A’s Connection Asset GAV –
customer A’s user maintained Connection Asset GAV)
Transmission use of system charge methodology
2.10 Transmission Use of System Charges are designed to recover OETC’s Maximum
Allowed Revenue (“MAR”). This is set by the Authority at periodic price control reviews
and covers the investment, operation and maintenance costs of the transmission
network and those costs associated with balancing and dispatch. The same charges
apply in both MIS and Dhofar.
2.11 The MAR is recovered from licensed suppliers (and transmission-connected customers,
who are required to have a supply agreement with the appropriate licensed supplier)
through TUoS charges that reflect their share of Maximum Transmission System
Demand (MTSD). That is, “the maximum average electricity demand in an hour as
metered or otherwise measured at exit points on the Transmission System in relevant
year t”6 meaning that the transmission charge for each supplier is determined entirely
by the consumption of that supplier’s customers during the peak hour of the year.
2.12 For each year, OETC estimate the MAR for the coming year (based on forecasts of
MTSD and total units transmitted). OETC then deducts from MAR any other regulated
income earned in order to reach the residual amount to be recovered through TUoS
charges. The residual amount is then divided by forecast MTSD to derive a TUoS charge
expressed in Omani Rials (OR) per MW. This TUoS tariff is published by OETC in
December of each year, for the following calendar year, as part of the Transmission Use
of System and Connection Charging Statement.
2.13 As MTSD cannot be known in advance OETC invoices licensed suppliers based on an
expectation of their contribution to maximum transmission system demand. That is, if it
is expected that a licensed supplier will account for 20% of maximum transmission
system demand, it will be required to pay 20% of the MAR (minus other regulated
income).
6 Connection and Use of System Charge Methodology Statement, Section 3.
Page 6 of 67
2.14 OETC revisits these calculations at the end of the year (once maximum system demand
is known) to reflect each supplier’s actual/outturn contribution to the system and will
make any required adjustments to the amounts paid by suppliers.
The objectives and principles of transmission charging
2.15 The Consultation Paper set out a number of objectives that are potentially impacted by
the approach to connection and use of system charges. These included, objectives
related to energy (e.g., security of supply, sustainability and affordability) and the
economy (e.g., through the impact on the perception of Oman as a place to do
business).
2.16 Based on these objectives, the Authority identified a number of key principles that were
used to assess the existing CUSC methodology and guide potential reforms. These
were:
Efficiency: does the CUSC methodology encourage efficient behaviours in terms of
investment and operation of the transmission network and in terms of the type and
location of generation and demand that is connected to the network?
Non-discrimination: does the CUSC methodology avoid undue discrimination (i.e.,
differences in the costs charged to different customers that cannot be objectively
justified)?
Cost reflectivity: does the CUSC methodology target the costs of investment and
operating the transmission network at the entities responsible for those costs?
Fairness: are the costs to current and future customers of using and connecting to
the transmission network reasonable?
Simplicity: is the CUSC methodology simple to administer and understand?
Transparency: are market participants able to predict future changes in connection
and transmission charges? Is it clear to participants how they can reduce their
costs?
Future-proofed: is the CUSC methodology appropriate given the changes that are
expected within the electricity sector over the short to medium-term (i.e., creation of
a spot market for electricity and greater penetration of renewable energy)?
2.17 In the Consultation Paper, the Authority asked stakeholders if they agreed with the
principles which the Authority had mentioned in the Consultation Paper.
Page 7 of 67
Stakeholder views
2.18 In total, there were 15 responses to the Consultation Paper, from a variety of
stakeholders. This included OETC, OPWP, distribution companies and a number of
electricity generators. A list of all of the entities that responded to the consultation can
be found at Appendix A.
2.19 All of the responses indicated support for the principles set out in the Consultation
Paper. While it considered the principles a good basis for assessing the CUSC
methodology, OPWP felt that more emphasis could be put on ensuring that the
methodology provides incentives for OETC to undertake its activities in an efficient
manner (although OPWP did acknowledge that this issue was addressed in the
Consultation Paper in the section related to the interactions between the CUSC
methodology and the price control review).
2.20 Noting the responses to the Consultation Paper, the Authority continues to regard the
principles and objectives described above as appropriate for evaluating the CUSC
methodology. The Authority uses these principles and objectives in its evaluation of the
methodology throughout the rest of this Initial Proposals document.
Page 8 of 67
3. Potential reforms to the connection charge methodology
3.1 In this section, we provide an overview of the assessment of the transmission
connection charging methodology presented in the Consultation paper and consider
whether any reforms would be appropriate.
Assessment of connection charge methodology
3.2 The Consultation Paper discussed the features of the existing transmission connection
charging methodology against the assessment criteria summarized in the previous
section. A summary of that discussion is presented in Table 1. A more comprehensive
discussion can be found in the Consultation Paper.
Table 1: summary of the assessment of the existing transmission connection charge
methodology presented in the Authority’s Consultation Paper
Criteria Assessment
Cost-reflectivity
/ Efficiency
Shallow charging methodology (i.e., connecting entities pay
the cost of their connection but not the costs of any network
reinforcement that is required) means that, in the presence
of network constraints, connectors do not face the full cost
of their decision to connect.
This issue could be compounded in future given the
expected increase in renewable generation, especially if
renewable generation capacity is located far from centres of
demand.
The cost of the connection assets are passed through to the
connecting entity in full (i.e., irrespective of the costs of the
connection). It could be argued that this does not place a
strong incentive on OETC to deliver the connection at least
cost).
Non-
discrimination
The CUSC methodology offers generators and transmission-
connected customers non-discriminatory terms for
connection to the network in that they are charged directly
for the cost of their connection asset.
However, the methodology for allocating connection
operating costs (based on the value of a customer’s own
connection assets) could potentially discriminate between
customers if actual connection O&M is not proportional to
the value of the asset.
Page 9 of 67
Criteria Assessment
Fairness
Annuitizing the capital costs of connections across the
lifetime of the asset can help to achieve a fair
intergenerational distribution of costs (i.e., both current and
future customers that benefit from the connection asset are
required to pay a share of the costs).
On the other hand, though more an efficiency rather than a
fairness issue, the requirement for OETC to meet connection
costs up-front, whilst recovering such costs over the lifetime
of the asset, could potentially impact on OETC’s cash-flows
and financeability.
Simplicity
The use of shallow connection charges that just recover the
cost of the connection (but not the wider costs associated
with any system expansion or reinforcement) from the
connecting entity is relatively straightforward, which means
that it is simple to administer and understandable by
market participants.
Transparency
Both the connection charging methodology and the annual
statement of transmission system charges (which sets out
the application fees for connections) are published by OETC.
During their application, connecting entities are provided by
OETC with an indicative estimate of the capital costs of
connection. However, since the connecting entity does not
know the cost of connecting before it agrees the connection
offer the arrangement is not perfectly transparent.
Future proofed
Under the current shallow connection charging regime a
future increase in the volume of remotely located grid-
connected capacity (for example some renewables or even
conventional thermal capacity in new demand centres)
could significantly increase the costs of grid reinforcements.
These would need to be recovered through transmission
charges and would not be attributed to the party causing
such costs. Potentially this could lead to a less cost efficient
system.
Source: Connection and Use of System Charge Methodology: Consultation Paper
3.3 In the Consultation Paper, the Authority asked stakeholders whether they agreed with
the Authority’s assessment of the existing connection charging methodology.
Page 10 of 67
Stakeholder views
3.4 In general, there was a high level of support for the Authority’s assessment of the
transmission charging methodology. For example, Muscat Electricity Distribution
Company (MEDC) felt that while the current methodology is fit for purpose, it was
prudent to consider whether amendments are required given the anticipated changes
in renewable penetration (e.g. to move towards greater cost-reflectivity in connection
charging).
3.5 OPWP highlighted that, while the assessment presented in the Consultation Paper was
a good conceptual consideration of the current methodology, it would be important to
understand the materiality of the issues presented in order to properly judge the case
for reform.
Possible reforms to the connection charge methodology
3.6 The following sections discuss the range of potential reforms to the transmission
connection charging methodology that were proposed in the Consultation Paper. These
are:
Deep connection charges: this entails charging connecting entities for the costs
of any reinforcement to the transmission network that are required as a result of
the decision to connect (in addition to the costs of the connection itself). In
principle, deep connection charges should help to ensure that connecting
entities take account of the broader costs associated with their decision to
connect and, specifically, should provide an incentive to entities to avoid
connecting at more constrained parts of the network.
Reforming the methodology for charging for connection operating and
maintenance: as discussed in Table 1, the current method of charging
connection operating costs may discriminate between connections if the actual
connection O&M costs are not proportional to the value of the asset. As such,
the Authority indicated it would explore whether an alternative charging
methodology could result in a more equitable distribution of operating costs
across connections.
Up-front charging of connection capex: connecting entities are currently
permitted to repay connection capex over time (up to 20 years). Requiring that
these costs are paid up-front has a positive impact on OETC’s cash flows and
financeability, though it would have the opposite effect on parties connecting to
the network.
Page 11 of 67
3.7 For each reform, we present the range of views presented by stakeholders as well as
the Authority’s assessment and Initial Proposals. Reform options are assessed against
the set of criteria set out above. Where appropriate, the Authority has also considered a
broader set of criteria such as the impact of options on the competitiveness of the
Omani economy and public finances.
3.8 In assessing these reform options, the Authority is mindful of the fact that the Omani
market is a dynamic one, characterised by rapid, and to some extent, geographically
concentrated economic growth. This creates a potential for there to be a significant
change in the pattern of generation and demand over the next few years.
3.9 Furthermore, the Authority notes that the Omani electricity sector operates within an
economic environment characterized by a mixed economy, with private sector
investment increasing, but with significant restraints, (e.g., in relation to the availability
of land and the freedom to carry out generation or demand related activities in
different geographical locations). The Authority notes that this can limit the ability of
customers and investors to respond to price signals provided by transmission
connection and use of system charges.
Deep connection charges
3.10 As was discussed above, the current approach of shallow connection charges means
that, in the presence of network constraints, connecting entities do not necessarily face
the full cost of connecting to the transmission network. In a situation where a new
connection results in the requirement for wider network reinforcement, this cost will be
recovered from suppliers through the Transmission Use of System (TUoS) charges
rather than from the connecting entity.
3.11 This means that, in the presence of material system constraints, entities are not facing
efficient economic incentives to guide their location decisions (and may, therefore,
locate in an area that is sub-optimal from the perspective of transmission costs). A
system of deep connection charges would ensure that connecting entities face a
charge that equals the cost that they are imposing on the transmission network (i.e.
connection costs plus any required network reinforcement). This should, therefore,
provide the signals for entities to connect to the less congested parts of the
transmission network.
Stakeholder views
3.12 In the Consultation Paper, the Authority asked stakeholders whether the current
shallow connection charging methodology had resulted in sub-optimal location
decisions by generators and transmission-connected customers.
Page 12 of 67
3.13 In its response, OETC described two instances where the location of generation
capacity (i.e. Sur and Ibri power plants) was sub-optimal from the perspective of
minimizing transmission costs. In these cases, OETC noted that the power from both of
these plants needed to be transported to the Muscat area, which required substantial
investment in transmission capacity (in excess of RO 150 million). However, OETC also
pointed to a number of factors that suggest that the incentive provided by deep
connection charges would have limited impact on the market outcome. These were:
Lack of material network constraints: OETC are required to maintain and invest
in the network in order to adhere to the Transmission Security Standard (TSS),
which they argue means that there are no sustained and material transmission
constraints.7 This being the case, there would be no benefit to introducing deep
connection charges (i.e., the lack of transmission constraints means that OETC
should, in most cases, be indifferent to the location of new connections from the
perspective of required network reinforcement).
Availability of land: OETC argued that there is a very limited number of sites
available for new generation plant and that, in general, transmission connected
customers locate in ‘free zones’ or ‘special economic zones’ (which confer
benefits in terms of tax and ‘lighter touch’ regulation). That being the case, OETC
argue that it is unlikely that connecting entities would respond to the signal
provided by deep connection charges;
The importance of other factors: OETC described that there were a range of
other factors that were important in determining the location of generation plant.
For example, easy access to fuel is one of the most critical factors for fossil-
burning generation while being located in an area with the right climatic
conditions is important for renewable generation. This means that the decision
on location needs to balance a broad range of considerations (and not simply
the costs of transmission); and
Transmission costs already considered in site location: OETC noted that
transmission costs are already a factor that is considered by OPWP when
deciding on the location for new capacity. OETC describe how they provide OPWP
with analysis of the transmission costs associated with different proposed sites,
and that this is one of the factors that OPWP considers in making its decision.
7 The Transmission Security Standard is designed to ensure that transmission investment is done
in a way that will deliver the power that is required in Oman. OETC’s primary objective – which is
given effect through the TSS – is to ensure that the demand for power can be met.
Page 13 of 67
3.14 While some respondents saw some in-principle advantages of a system of deep
connection charges (e.g., MEDC felt that generators should be encouraged to locate
closer to centres of load), there was a high level of consensus around the points raised
by OETC about the lack of choice for generators in relation to locational flexibility.
3.15 OPWP pointed to the new generation procurement process that has been developed for
‘Power 2022’, which will in principle allow generators to choose between different
locations. However, OPWP felt that, in practice, the lack of available sites for new
generation would continue to be a real constraint on this choice.
Assessment
3.16 The Authority notes that moving to a deep charging methodology would potentially
result in greater cost-reflectivity in connection charges. This could result in more
efficient locational decisions by generators and transmission-connected customers,
which could help to reduce the costs of the transmission system.
3.17 Moving to a system of deep connection charges could result in larger variations
between the connection charges that are faced by different entities. For example, an
entity that connected in a constrained part of the transmission network would face a
substantially higher connection charge than an entity that connected at an
unconstrained part of the network. The Authority considers that such differences would
reflect costs placed on the system and would not therefore be discriminatory.
3.18 However, a system of deep connection charges would require OETC to make an
assessment of the impact of a connection on the requirement for system
reinforcement in order to make the connection offer. The Authority considers that this
would increase the administrative burden on OETC and would reduce the transparency
of the system of connection charges. This could make it more challenging for
connecting parties to predict and understand the costs of connection to the
transmission network. The Authority notes that the uncertainty of connection costs
under a deep system of charges could be exacerbated by planning issues, which can
on occasions result in relatively last-minute changes in substation and route locations.
The Authority considers that this could cause substantial additional costs and
complexity for connecting entities under a deep connection charging regime.
Page 14 of 67
3.19 The Authority notes that, in some circumstances, a system of deep connection charges
could be said to be a fairer system, because costs are recovered from those entities
responsible for causing costs, rather than from all customers. However, deep charges
could result in substantially higher charges on certain entities and may be less
appropriate in an environment where the pattern of supply and demand reflects other
economic drivers and limitations, such as land availability and planning constraints.
Indeed, the Authority also notes that, to the extent that deep connection charges
increase the costs of connecting to the transmission network (which would be expected
to be the case in the presence of material system constraints), this could reduce the
attractiveness of Oman as a place to do business. That is, internationally mobile
electricity-intensive businesses may choose to locate in another country in which the
connection costs are not so high. As such, deep connection charges could have a
negative impact on economic growth.
3.20 Moving to deep connection charges may also have an impact on the timescale over
which costs are recovered by OETC (and potentially therefore the requirement for
Government subsidy). Currently, the costs of network reinforcement are added to
OETC’s Regulated Asset Base (RAB) and these costs are recouped through TUoS
charges over the lifetime of the network asset (35 years). Under a system of deep
charges, these reinforcement costs are charged to the connecting entity, which can pay
the costs back either up-front or annuitized over 5, 10, 15 or 20-years. As such, deep
charges will mean that OETC will recoup these reinforcement costs over a faster
timescale, which could have a positive impact on OETC’s cash flows and financeability.
3.21 In the Authority’s view, there are some clear pros and cons associated with deep
connection charges. The key advantage of a system of deep charges relates to the
efficiencies that could be achieved through encouraging entities to connect to less
constrained parts of the network. However, realizing these benefits requires a number
of conditions to hold. These are:
Material constraints on the transmission system: in the absence of material
transmission constraints there would be no network expansion or reinforcement
required as a result of the connection, which means that the connecting entity
would simply face the cost of the connection. In this case there would be no
benefit to the introduction of deep connection charges;
Entities have a choice about where to connect: realizing the benefits of deep
charging also relies on entities being able to respond to the price signal. That is,
an entity needs to have the flexibility to be able to choose a location in a less
congested part of the network in order to effectively manage its connection
costs; and
That the current process for selecting sites for generation does not consider
transmission costs: if the transmission system costs associated with different
Page 15 of 67
potential sites are already factored into the process through which OPWP
determine the sites for new generation it is unlikely that the application of deep
charges will, in practice, impact on site selection.
3.22 As discussed in the Consultation Paper, OETC’s annual Capability Statement sets out
its assessment of system performance, which details the parts of the network that are
under stress.8 The Capability Statement suggests that there is a lack of capacity at
certain points on the transmission system to accommodate demand at summer peak.
This will limit the ability to make new transmission connections in these areas unless
action is taken to reinforce the transmission network (and/or transfer demand from
heavily loaded to more lightly loaded grid stations). However, the Capability Statement
also sets out the actions that OETC is planning in order to bring the network in
compliance with the TSS.
3.23 The Authority notes that the effectiveness of deep connection charges to influence the
behaviour of generators will also depend on how those generators are remunerated for
the power they produce. Generators currently recover their connection costs through
Power Purchase Agreements (PPAs) with OPWP. Under this set-up a generator would be
able to pass-through the full cost of a deep connection charge within the PPA price.
What this means is that generators would not suffer any financial penalty from facing a
substantial connection charge. However, the Authority notes that this could change
with the inception of the spot market. Under the new market arrangements, a
generator that faced a substantial connection charge may be less likely to be within the
merit order in the spot market (all else equal). Under these circumstances, deep
connection charges could provide a financial incentive for generators to choose a lower
cost location. We will return to the issue of the spot market in Section 4.
3.24 The Authority notes that deep connection charges are used in some other jurisdictions.
The approach to connection charging in a range of European counties is shown in Table
2 (which also shows whether the approach to TUoS charging includes a locational
element).
Table 2: approach to connections and TUoS charging in European countries
Country
Do TUoS
charges
vary by
location?
Shallow or
deep
charges?
Notes
Austria No Shallow -
Belgium No Shallow -
Bosnia & Herzegovina No Shallow -
8 OETC (2017), Five Year Annual Transmission Capability Statement (2017-21)
Page 16 of 67
Country
Do TUoS
charges
vary by
location?
Shallow or
deep
charges?
Notes
Bulgaria No Shallow -
Croatia No Deep
Generation pays
reinforcement costs. Load
pays a reduced rate.
Cyprus No Shallow -
Czech Republic No Shallow -
Denmark No Shallow -
Estonia No Deep -
Finland No Shallow -
France No Shallow -
Germany No Shallow -
Great Britain Yes Shallow -
Greece No Shallow -
Hungary No Deep Discounts for renewable
generators
Iceland No Shallow/
deep -
Ireland Yes Shallow -
Italy No Shallow -
Latvia No Deep -
Lithuania No Deep Discounts for renewable
generators
Luxembourg No Shallow -
Macedonia No Shallow -
Montenegro No Shallow -
Netherlands No Shallow -
Northern Ireland Yes Shallow -
Norway Yes Shallow -
Poland No Shallow -
Portugal No Shallow -
Romania Yes Shallow/
deep
Generation pays
reinforcement costs. Load
pays shallow charges
Serbia No Deep -
Slovakia No Shallow -
Slovenia No Shallow -
Spain No Shallow -
Sweden Yes Deep -
Switzerland No Shallow -
Source: ENTSO-E9
9 ENTSO-E (2017), Overview of Transmission Tariffs in Europe: Synthesis 2017
Page 17 of 67
3.25 The data in Table 2 shows that while deep charges are used by some countries (only
nine of the 35 countries listed, two of which use a combination of shallow and deep),
most use shallow charges. Of the countries with deep charges, only two (Romania and
Sweden) also use a locational element in their TUoS charges. As such, it appears that
countries tend to use either deep charges or locationally-varying TUoS charges to
provide signals to connectors, but typically not both.
3.26 The Authority also notes that in some cases discounts are provided on deep charges
for particular types of connectors. For example, Romania and Croatia both offer
discounts to transmission-connected customers (which should help to prevent the
impact of deep charges on economic competitiveness) while Lithuania and Hungary
provide discounts for connecting renewable generation.
Initial Proposal
3.27 The Authority has carefully considered the responses from stakeholders on this issue. A
summary of the Authority’s assessment of this reform against the assessment criteria
is shown in Table 3.
Table 3: Authority’s assessment of deep connection charges against assessment
criteria
Criteria Deep connection charges
Cost-reflectivity / Efficiency √
Non-discrimination -
Fairness √
Simplicity X
Transparency X
Future proofed √
Notes: √ positive assessment against criteria; X negative assessment against criteria; -
no substantive impact
3.28 The Authority notes that there are some clear in-principle benefits of a system of deep
connection charges. However, the apparent lack of material transmission constraints
suggests that creating a system of charges aimed at encouraging entities to locate on
less-congested parts of the network is not required. In addition, the lack of choice
around the location for new generation suggests that entities would be unable to
respond to such an incentive. Furthermore, we also note that the impact on
transmission costs is something that is already considered when OPWP proposes the
location of new generation. This suggests that even if a deep connection charges
methodology was adopted, it would be unlikely to change the outcome in terms of
where new generators are located. As such, the Authority is not minded to consider this
option further at this time.
Page 18 of 67
3.29 However, the Authority intends to keep under review whether it may be appropriate to
adopt a deep connection charging regime at some point in the future. As a contribution
to further thinking in this area, the Authority would encourage OPWP to monitor the
costs of transmission system constraints based on an analysis of daily constrained and
unconstrained schedules that they receive from OETC. This analysis will make an
important contribution to understanding the nature and cost associated with
transmission network constraints.
Connection Operating Costs
3.30 The previous section described how connection operating and maintenance costs are
charged on the basis of the GAV of a customer’s connection asset. That is, a customer
with a GAV that represents 1% of total connection GAV would face a charge equal to 1%
of aggregate connection charge opex.
3.31 Aggregate connection charge opex is calculated in OETC’s price control by allocating
total controllable opex to transmission system assets (for recovery through TUoS
charges) and connection assets (for recovery through connection assets). This
allocation is done on the basis of the relative value of network and connection assets,
which for T&D-PCR4 resulted in a split of 80% of opex recovered through TUoS and
20% through connection charges.
3.32 As discussed in Table 1, this methodology for allocating connection operating costs
potentially discriminates between customers where connection O&M is not proportional
to the GAV of a customer’s asset.
3.33 This was an issue that the Authority was keen to seek views on and, as such, asked
stakeholders in the Consultation Paper whether the current methodology for calculating
the TRC resulted in an unfair allocation of costs across connections.
Stakeholder views
3.34 Both MEDC and Majan Electricity Company (“MJEC”) felt that the existing methodology
had the potential to create an unfair distribution of costs across entities. MJEC cited
the illustrative example of a high-usage industrial customer with connection assets of a
132kV breaker and underground cable. The GAV of this connection would be high but
MJEC argue that this would require little O&M costs. As such, this type of an entity
would bear a disproportionate share of connection O&M costs.
3.35 MEDC also noted that the age of connection assets could also impact on the
requirement for connection O&M. That is, a newer connection asset may be less costly
to maintain compared to an older asset. However, the current charging methodology
does not distinguish between assets based on age.
3.36 However, neither MEDC nor MJEC offered any evidence on the extent of this problem.
None of the other respondents felt that this was a substantive issue.
Page 19 of 67
3.37 OETC did argue, however, that the existing methodology is complex, which creates a
substantial administrative burden on them as well as uncertainty for connecting
entities. OETC noted that any change in connection assets (e.g., a new entity connects
to the transmission network, which increases aggregate connection GAV) will require
the recalculation of the TRC and a reapportioning of the connection O&M costs
between customers. OETC point out that this means that they have to await year-end
finalization before invoicing customers.
3.38 As such, OETC proposed that charges for connection O&M should be based on a fixed
2% of GAV (which would be a reversion to the previous methodology for charging for
connection O&M). OETC argued that this would represent a more straightforward
approach for them to administer and would ensure that charges were more transparent
and predictable for connecting entities.
Assessment
3.39 The Authority notes that the current methodology of charging for connection O&M may
in certain cases result in a less than optimal distribution of costs (e.g., where O&M is
not proportional, due to differences in the age or size of the assets, to a customer’s
actual connection asset’s GAV). Reforming the methodology so that connection O&M
costs more closely reflects the actual O&M costs of each connection could therefore
result in a more equitable distribution of costs.
3.40 Moving to a system where O&M charges more accurately reflect the costs of
maintaining each connection would result in an improvement in terms of cost
reflectivity. However, the Authority notes that a system of charging O&M on a more
cost-reflective basis would necessarily result in a greater administrative burden on
OETC and the Authority. In addition, this would increase the complexity of the system,
which would potentially make it more difficult for connecting entities to understand and
predict their connection O&M charges.
3.41 The Authority does not believe that this reform would have an impact (positively or
negatively) on the robustness of the transmission system to future changes in the
electricity sector.
3.42 The rationale for making this reform rests on the presumption that, in many cases,
connection O&M is not proportional to connection GAV. If this is not the case, the
argument for making this case on the grounds of distributional equity falls away.
Furthermore, the Authority notes that, based on the responses received from
stakeholders, the fairness of connection opex charges does not appear to be a
substantive issue.
Page 20 of 67
3.43 Indeed, the Authority notes that similar methodologies (i.e., where connection opex set
in a price control review is recovered based on a calculated TRC factor and individual
connection GAVs) is in use in other jurisdictions (e.g., Great Britain).10
3.44 The Authority understands that the existing methodology for calculating connection
O&M is more complex (and therefore entails an additional administrative burden) than
OETC’s proposed approach of charging based on a fixed 2% of GAV. However, the
Authority notes that the existing methodology is designed to ensure that OETC can
recoup the permitted level of connection O&M that is set in the price control review.
Furthermore, the Authority is concerned that charging for connection O&M based on a
fixed 2% of GAV could result in OETC under or over-recovering connection operating
costs.
3.45 This point is illustrated in Table 4, which shows the, permitted connection opex set in
OETC’s price control, TRC factor,11 the level of connection opex that would have been
recouped by OETC based on its proposed fixed 2% factor and the level of under or over-
recovery that would result if connection opex was charged on the basis of 2% of GAV.
3.46 As an example, in 2013, OETC were permitted to collect RO 2.6 million (2017 prices) in
connection charges based on a TRC factor of 3.13%. Had connection charges been
based on a fixed 2% of GAV, then OETC would have recovered only RO 1.6 million. This
would result in a substantial deficit against permitted connection O&M costs of RO 0.9
million.
Table 4: impact of fixed 2% on cost recovery (2017 prices)
Year
Connection
opex
(RO mn)
TRC factor (%) GAV x 2%
(RO mn)
Under/over
collection
(RO mn)
2013 2.6 3.13% 1.6 -0.9
2014 3.2 2.83% 2.3 -0.9
2015 3.5 2.19% 3.2 -0.3
2016 3.7 2.11% 3.5 -0.2
2017 3.8 1.83% 4.2 +0.4
Source: OETC
3.47 The figures presented in Table 4 show that the TRC factor has been falling over time
(which implies that aggregate connection GAV is increasing at a faster rate than
aggregate connection O&M), Indeed, this shows that, by 2017, charging based on 2%
10 See: https://www.nationalgrid.com/sites/default/files/documents/13630-
Guide%20to%20Connection%20Charging.pdf
11 As discussed in the previous section, the TRC factor is calculated based on OETC’s aggregate connection
opex (determined in the most recent price control review) and the aggregate connection GAV. The TRC factor
is then used to calculate the charge for each connection (based on each individual GAV) and, in doing so,
allows OETC to recoup exactly the amount of connection opex that is determined by the price control review.
Page 21 of 67
of GAV would result in a RO 0.4 million over-recovery of costs by OETC. The extent of
over or under-recovery in future would depend on the evolution of aggregate GAV and
aggregate connection O&M costs. The Authority notes that increasing numbers of
customers wishing to move from distribution to transmission-connected in response to
the CRT may result in some upward pressure on connection GAV in the coming years.
Initial proposal
3.48 As discussed above, the Authority has carefully considered the responses from
stakeholders on this issue. Combining the points above, a summary of the Authority’s
assessment of this reform against the assessment criteria is shown in Table 5.
Table 5: Authority’s assessment of changing the basis for charging connection
operating costs against assessment criteria
Criteria
Changing the basis for charging connection
operating costs
Cost-reflectivity / Efficiency √
Non-discrimination -
Fairness √
Simplicity X
Transparency X
Future proofed -
Notes: √ positive assessment against criteria; X negative assessment against criteria; -
no substantive impact
3.49 In principle, it appears that the existing methodology for calculating connection O&M
charges could result in some connections bearing disproportionately high costs (e.g.,
when GAV is high relative to actual operating costs). In principle, therefore, a change to
the methodology so that connection O&M charges more closely reflected the actual
O&M costs of each connection could result in a more cost-reflective and equitable
approach. However, it is not clear from the responses received that this is, in practice,
a substantive issue, which in the Authority’s view weakens the case for making this
reform.
3.50 Furthermore, the existing methodology is designed so that it ensures that OETC can
recoup exactly the level of connection O&M allowance set in its price control review.
Page 22 of 67
3.51 The Authority acknowledges that OETC’s proposal to move to charging customers
based on a fixed 2% would offer a simpler solution that would be easier to understand
and administer for OETC. However, the Authority believes that this will create additional
complexities that will need to be managed. For example, it appears that charging based
on a fixed 2% would inevitably result in some under or over-recovery of opex by OETC.
This disparity would then need to be accounted for through some adjustment to the
TUoS charges, which (depending on the time lag between the under/over-recovery and
the correction through TUoS) may require further adjustment to account for the time
value of money. In the Authority’s view this would create an additional layer of
complexity and unpredictability within the methodology.
3.52 Based on this assessment, the Authority does not consider the benefits that could be
realised to be commensurate with the costs that would be created through this reform.
As such, the Authority is not minded to consider this option further at this time.
Up-front charging of connection capex
3.53 As set out in the previous section, connection charges are made up of a capital charge
(which allows OETC to recoup the capital cost of the connection asset) and a
transmission running charge (which allows OETC to recoup the connection operation
and maintenance costs). Under the existing CUSC methodology, connecting entities are
permitted to decide on whether they will pay for the capital costs of their connection
up-front (through a lump sum payment) or over time (through an annuitized charge).
3.54 In a situation where an entity decides to pay their connection capital costs over time,
OETC is required to fund the up-front costs of the connection. OETC will then recover
these costs over the annuity period chosen by the connecting party. The Consultation
Paper raised the issue of whether annuitizing connection costs could create cash flow
and financeability issues for OETC and, as such, sought stakeholder views on this
issue.
Stakeholder views
3.55 The majority of respondents felt that they did not have sufficient understanding of the
financing arrangements for new connections to offer a view to this question. However,
both MJEC and the Mazoon Electricity Company (“MZEC”) pointed out that while
shifting to up-front payment of connection capital costs would improve the cash flows
of OETC, it may create cash flow challenges for generators and transmission-connected
customers.
3.56 OETC reported that, under the current arrangements, entities have the choice to pay
their connection costs up-front or to annuitize them over a period of 5, 10, 15 or 20
years (with relatively few choosing to pay the costs up-front and the majority choosing
to repay the costs over a 20 year period). The split between up-front and annuitized
connection costs are shown in Table 6. This shows that 92% of all connections by
number (and 98% by value) chose to annuitize their connection capital costs rather
Page 23 of 67
than pay up-front.
Table 6: up-front and annuitized connection asset values (2017 prices)
Payment method Number of connections Total value of connection
assets (RO mn)
Up-front 10 4.8
Annuitized 112 221.8
Source: OETC
3.57 In spite of this, OETC noted that they do not have major concerns with the current
approach to annuitizing connection capex costs. OETC felt that this had not caused
them any financeability issues to date (not least because it is permitted to collect a
WACC element in the annuitized payment which adjusts for the time value of money).
However, OETC did feel that this could become an issue in future, particularly if there
was an increase in the number of transmission-connected customers.
3.58 Specifically, OETC stated that its own funding plan is typically based on a 10—year
repayment period and argued that there would be a benefit in capping the annuity
period to the same timescale, in order to more closely match connection capex
payments with OETC’s repayment schedule.
Assessment
3.59 The Authority notes that, in principle, allowing connecting entities to pay their
connection costs over time (rather than up-front) could create financeability challenges
for OETC, although this had not been shown to create any problems to date. There is
also the potential that it could discourage entities from wanting to connect. The
Authority notes that the decision about whether to charge connection costs up-front or
over time does not alter the present value of the costs that a connecting entity is
required to pay. As such, the Authority does not believe that this reform will impact
(positively or negatively) in terms of the cost-reflectively of the charges, or the efficiency
of the transmission system. Similarly, the Authority does not believe that this reform
would have a substantive impact on the transparency or simplicity of the system of
charges. Nor would it impact on the robustness of the transmission system to future
changes in the electricity sector.
3.60 As was noted in the Consultation Paper, changing to up-front charging would impact on
the profile of connection cost for distribution companies. Connection charges are a
pass-through for the distribution companies, which means that a shift towards paying
for the cost of connections up-front would result in a large increase in pass-through in
certain years (and, therefore, in the subsidy requirements for that year). The Authority
notes that this is contrary to the typical treatment of asset purchases, for which the
costs tend to be recovered over time.
Page 24 of 67
3.61 This is illustrated by Figure 1, which shows the ‘lumpy’ distribution of connection capex
over time for MEDC, MJEC and MZEC.
Figure 1: profile of connection capex for Muscat, Majan and Mazoon distribution
companies (values based on nominal value of asset at the time of installation)
Source: OETC
3.62 The Authority also notes that (in common with a system of deep connection charges), a
move towards requiring greater up-front payment of connection capex could reduce the
attractiveness of Oman as a place to do business.
3.63 The Authority has also considered the potential incentives that could be created by
changing the approach to recouping connection capital costs. For example, a longer
annuity period potentially creates a greater risk of a company defaulting on their
connection payments (although OETC report that this is a relatively rare occurrence),
while a shorter period potentially undermines the incentive for OETC to maintain the
connection asset once the capital costs have been fully repaid.
3.64 Finally, the Authority notes that similar methodologies for charging the capital costs of
connections are used in other jurisdictions. For example, in Great Britain, connecting
entities have the flexibility to repay the capital cost of connection up-front or over the
lifetime of the asset (which is based on a 40 year useful lifetime).
Initial proposal
3.65 The Authority has carefully considered the responses from stakeholders on this issue. A
summary of the Authority’s assessment of this reform against the assessment criteria
is shown in Table 7.
0
2
4
6
8
10
12
14
OM
R M
illio
ns
Muscat Majan Mazoon
Page 25 of 67
Table 7: Authority’s assessment of up-front charging of connection opex against
assessment criteria
Criteria Up-front charging of connection opex
Cost-reflectivity / Efficiency -
Non-discrimination -
Fairness X
Simplicity -
Transparency -
Future proofed -
Notes: √ positive assessment against criteria; X negative assessment against criteria; -
no substantive impact
3.66 The Authority understands OETC’s perspective on the potential financeability issues
that could result from longer annuity periods. However, given OETC has indicated that
the current arrangements have not, to date, caused it any financial issues, the
Authority considers that there is insufficient rationale for this reform.
3.67 Taking all of the above into account, on balance, the Authority is not minded to
consider this reform further at this stage.
3.68 The Authority proposes to retain the current arrangements for capital charging as set
out in the CUSC Statement.
Conclusion
3.69 In this section we have reviewed the potential reforms to the connection charging
methodology in light of the responses received to the Consultation Paper, as well as
our own analysis of available data, review of economic theory and regulatory
precedent. As discussed above, the Authority is not minded to make any of the reforms
that were raised in the Consultation Paper.
3.70 However, the Authority invites stakeholders to comment on these initial proposals and
on any aspect of the Authority’s assessment of the reform options.
Page 26 of 67
4. Potential reforms to the transmission use of system charging
methodology
4.1 In this section, we provide an overview of the assessment of the TUoS charging
methodology presented in the Consultation Paper and consider whether any
modifications to the TUoS charging methodology may be appropriate.
Assessment of transmission and use of system charging methodology
4.2 The Consultation Paper discussed the features of the existing TUoS charging
methodology against a set of objectives which transmission charging should deliver. A
summary of that discussion is presented in Table 8. A more comprehensive discussion
can be found in the Consultation Paper.
Table 8: summary of the assessment of the existing TUoS charging methodology
presented in the Authority’s Consultation Paper
Criteria Assessment
Cost
reflectivity/
Efficiency
While the CUSC methodology allows OETC to recover its full
economic costs through its MAR, there are several aspects
of the charging methodology that may not be fully cost-
reflective and may be reducing the efficiency of investment
and operating decisions. These are: (1) charges are levied
on demand only; (2) TUoS charges do not vary by location;
(3) TUoS charges do not vary by generation technology; and
(4) the treatment of costs associated with balancing and
dispatch are recouped through the TUoS charges (but might
more appropriately be distributed across network users in a
different fashion).
It is also important to note that charging on the basis of
MTSD provides a strong signal for customers to contribute
to overall system efficiency by reducing demand at system
peak times, though it is worth considering whether a more
powerful incentive to reduce peak demand could be created
through moving from a charge based on a single snapshot
of peak demand to one based on multiple snapshots. The
allocation of TUoS charges entirely on the basis of peak
transmission system demand also means that large
customers do not face a strong incentive to reduce their
overall demand (i.e., Regulated Units Transmitted (RUT)).
Page 27 of 67
Criteria Assessment
Fairness
It could be argued that the way in which costs are allocated
across users (i.e., generators versus suppliers) and network
locations (i.e., congested versus unconstrained parts of the
network) does not fairly and accurately represent the costs
of providing transmission services to those users.
However, the allocation of costs does appear to be relatively
fair from an inter-generational perspective (i.e. in broad
terms, all customers who benefit from the assets, current
and future, are required to contribute).
Transparency
The Consultation Paper discussed whether market
participants were able to predict future changes in
connection and transmission charges and whether it is clear
to participants how they can reduce their costs.
The way in which TUoS charges are allocated to suppliers
based on their demand at system peak is transparent and
helps to create a clear incentive for reducing consumption
at peak periods for certain customers and enables them to
take actions to reduce their costs.
Future proofed
A substantial increase in the penetration of renewables may
require changes to the way in which the costs of the
transmission system are allocated (in a scenario where part
of the TUoS charges are levied on generation). Intermittent
renewables tend to have lower capacity factors than
conventional generation sources. Allocating the costs of
transmission based on the share of peak system usage may
not be representative of the costs that renewable
generation places on the transmission system throughout
the year.
Source: Connection and Use of System Charge Methodology: Consultation Paper
4.3 In the Consultation Paper, the Authority asked stakeholders whether they agreed with
the Authority’s assessment of the TUoS charging methodology.
Stakeholder views
4.4 There was a high level of support for the Authority’s assessment of the TUoS charging
methodology among respondents to the Consultation Paper. OETC, suppliers and
generators all, in general, agreed with the Authority’s assessment of the existing TUoS
charging methodology. As was the case with the assessment of the connection
charging methodology, OPWP noted that the Authority had made a reasonable
qualitative assessment but that it would be beneficial to supplement this where
possible with quantitative analysis.
Page 28 of 67
Possible reforms to the transmission use of system charge methodology
4.5 The following sections discuss the range of potential reforms to the TUoS charging
methodology that were proposed in the Consultation Paper. These are:
Charging a share of TUoS to generators: currently, TUoS charges are paid
entirely by suppliers. Given that generators also impose costs on the
transmission system, charging them a share of TUoS would in principle be cost
reflective;
Charge a share of TUoS to generators based on location: should a share of TUoS
charges be levied on generators, then some consideration would need to be
given as to whether charges should vary by location. For example, charging a
higher rate for use of the transmission network in constrained zones or nodes
could help to encourage generators to locate in less congested parts of the
network (and, therefore, reduce the costs of the transmission system);
Accommodating an increase in renewable generation: should a share of TUoS
charges be levied on generators, then some consideration would need to be
given to how the methodology may need to evolve in order to accommodate the
anticipated increase in renewable generation in Oman. TUoS is currently
charged on the basis of contribution to MTSD. However, this may not be
appropriate for some types of renewables. For example, intermittent renewable
generation tends to have a lower capacity factor than conventional generation,
which means that allocating the costs of the transmission network based on the
share of peak system usage may not be representative of the costs that
renewable generation places on the transmission system throughout the year;
Reforming the methodology for levying TUoS on suppliers: TUoS charges are
currently levied on suppliers based on contributions to MTSD (i.e., the one hour
of maximum transmission system demand in a year), on the basis that peak
demand is the key drivers of the requirement for new transmission
infrastructure. In principle, alternative allocation methodologies could create a
more sustained incentive for customers to manage their peak demand and
overall demand; and
Creating a separate charge for balancing and dispatch costs: costs associated
with system balancing and dispatch are currently recouped through TUoS
charges. In principle, a more cost-reflective approach could be to separately
identify the costs associated with transmission from those associated with
balancing and dispatch and have separate charges for each.
4.6 For each possible reform, we present the range of views presented by stakeholders as
well as the Authority’s assessment and Initial Proposals.
Page 29 of 67
Charging a share of TUoS to generators
4.7 The existing methodology does not require generators to contribute to the costs of the
system. In principle this means that they will not take system costs into account when
taking decisions about when and how to operate and could make sub-optimal
decisions, from an overall system perspective. On the other hand, generators in Oman
are subject to a centralised dispatch system operated by the OETC Load Dispatch
Centre (“LDC”) through which planned plant outages are scheduled and agreed as part
of an overall co-ordinated generation and transmission outage programme.
4.8 Against this background the Consultation Paper sought views on whether generators
should pay a share of TUoS charges.
Stakeholder views
4.9 Responses to this question tended to consider together whether to charge TUoS to
generators and whether those charges should vary according to location (i.e., should
TUoS charges be higher in parts of the network that are subject to material
constraints). The responses showed a variety of views. All of the generators who
responded were of the view that they should not have to pay TUoS charges. Many
noted that, in the case of locational charges, there was little or no flexibility about
location, meaning that they are effectively unable to respond to such signals.
4.10 OPWP concurred with this view. They argued that there are a range of binding
constraints (e.g., availability of land, access to fuel) that were of greater importance
than transmission costs in determining the location of new generation. As such, OPWP
felt that there would be limited value in charging TUoS to generators at this time, but
that this decision should be kept under review.
4.11 While they were typically silent on the issue of locational prices, some of the
distribution companies were in favour of charging TUoS to generators. They argued that
the activities of generators are imposing costs on the transmission network and, as
such, they should be required to bear a proportion of the cost.
4.12 OETC noted that locational transmission charges were frequently used in other
jurisdictions and that applying TUoS charges to generators was worthy of further
consideration. They argued that under the current market structure, where all power is
being procured through power purchase agreements (PPAs), any charge on generators
would simply be passed on through to the distribution companies (which would likely
not result in any benefit to customers in terms of lowering system costs). However,
once substantial volumes of power are being procured through the spot market, the
application of TUoS to generators could help to drive more efficient dispatch outcomes.
Assessment
4.13 As discussed above, TUoS charges are currently paid by licensed suppliers and
generators do not face any economic signals with respect to their use of the system. In
Page 30 of 67
theory levying TUoS charges on generators could result in more cost-reflective
transmission charging and costs savings in the energy system. However, the realization
of these benefits relies on: (1) transmission costs varying across generators; and (2)
power procurement arrangements that are sufficiently flexible to respond to such cost
variations.
4.14 The Authority notes, however, that under the current market structure, generators are
required to operate as per the terms of their PPA and that planned plant outages are
scheduled and agreed with the OETC Load Dispatch Centre. As a result, generators are
effectively unable to respond to economic signals related to their use of the system.
4.15 In its response to the Consultation Paper, OETC set out how the inception of the spot
market will impact on the way in which power is contracted and dispatched. A summary
of considerations under the current and future (i.e., once substantial quantities of
energy are being procured through the spot market) market structures for power
procurement is shown in Table 9.
Table 9: current and future market structures for power procurement
Scenario How is power procured? Impact of levying TUoS on generators
Current
state
All power is procured
by PWP through Power
Purchase Agreements
Levying TUoS on generators would
qualify as a change of law under
existing PPAs. New and existing
PPAs would be permitted to pass-
through the TUoS charges into the
price charged to OPWP for power
generated.
Page 31 of 67
Future state
(i.e., post
start of spot
market)
OPWP will continue to
procure some
generation capacity
through PPAs (in order
to ensure security of
supply)
All generators will be
required to submit an
offer to the spot
market, which will
establish the merit
order
Dispatched generation
that has a PPA will
receive a price for its
power based on that
PPA
Dispatched generation
that does not have a
PPA will receive a price
determined by the
spot market
Generators’ offers into the spot
market should incorporate the
costs of transmission (that they will
have to pay) based on TUoS
charges.
In principle, the levying of TUoS
charges could change the merit
order (i.e., generators that impose
lower costs on the transmission
system would be more likely to be
dispatched) and result in lower
overall power production costs.
In the short to medium term the
savings would be limited if most
generators continue to receive a
price for power based on PPA, but
the savings may increase over time
as increasing volumes of power are
procured on the spot market.
Source: Authority analysis of OPWP information
4.16 As discussed in the Consultation Paper, the present arrangements for transmission
charging arguably reduce the fairness of charges to different users of the transmission
system. That is, the way that costs are currently allocated across generation and
demand may not fully reflect the costs of transmission.
4.17 The Authority notes that the current methodology spreads costs over time consistent
with achieving inter-generational equity. The Authority would not expect that this would
be affected by a move to charge generators a share of TUoS costs.
4.18 The Authority notes that, if TUoS were to be levied on generators, then decisions would
need to be taken on the proportion of TUoS costs to be charged to generation as well
as the appropriate way of levying TUoS charges (i.e. based on contribution to peak or
annual energy production). For example, as discussed in Section 3, the anticipated
increase in the volume of grid-connected intermittent renewable electricity in Oman
could impact on the required transmission network capacity. Should the decision be
taken to allocate a share of TUoS charges to generators the Authority notes that
consideration should be given to how costs are allocated to different generation
technologies, given that intermittent renewables tend to have lower capacity factors
than conventional generation sources.
Page 32 of 67
4.19 However, although the levying of TUoS charges on generation could have an impact on
the order of dispatch under certain circumstances, given that all power is currently
procured through PPAs and generators would be able to pass through the full TUoS
cost in the price they charge to OPWP, the savings associated with this reform could be
limited in the short term. Indeed, the impact would likely continue to be muted even
after the spot market commences operation in 2020, given that the volumes of power
procured based on the spot market price are, at least in the initial years, likely to be
relatively low.
4.20 Furthermore, the Authority does not believe that a move to charging generators a share
of TUoS charges will substantively impact (positively or negatively) on the simplicity or
transparency of the system. There would, however, be some administrative burden
associated with implementing these changes (e.g., overseeing the necessary changes
to the PPAs).
4.21 In considering the case for reform of the CUSC methodology, the Authority has also
examined precedent from other markets. The approach to transmission charging in
Europe provides an interesting case study. The share of TUoS that was charged to
generators in European countries in 2017 is shown in Table 10.
4.22 For the purpose of this analysis, the sample is split into two: jurisdictions where TUoS
charges do not vary by location; and jurisdictions where TUoS charges vary by location.
The data shows that in the majority of counties that do not vary TUoS charges by
location (i.e., where TUoS charges are uniform across geographies) also do not levy any
TUoS charges on generators (i.e., all of TUoS costs are recouped from demand).
Indeed, Table 10 shows that 19 of 28 do not levy any TUoS charges on generation and
do not apply any TUoS charges on generation while the average share of TUoS charges
on generation was just 4% for these countries. This is in stark contrast to the countries
where TUoS charges vary according to location. For these countries, the average share
of TUoS on generation was 24% in 2017.
4.23 Based on the range of countries surveyed, this suggests that regulators tend to levy a
relatively small share of TUoS charges on generators and that the extent of these
charges tends to be larger in jurisdictions where TUoS charges are intended to give
generators a price signal that varies by location.
Page 33 of 67
Table 10: share of TUoS charges to generators in European countries (2017)
Country
Proportion of TUoS
charged to generators
(%)
Jurisdictions where TuoS charges do not vary by location
Austria 35%
Belgium 7%
Bosnia & Herzegovina 0%
Bulgaria 0%
Cyprus 0%
Czech Republic 0%
Denmark 3%
Estonia 0%
Finland 19%
France 3%
Germany 0%
Greece 0%
Hungary 0%
Iceland 0%
Italy 0%
Latvia 0%
Lithuania 0%
Luxembourg 0%
Macedonia 0%
Montenegro 36%
Netherlands 0%
Poland 0%
Portugal 7%
Serbia 0%
Slovakia 3%
Slovenia 0%
Spain 10%
Switzerland 0%
Average (arithmetic mean across all countries in sample) 4%
Jurisdictions where TUoS charges vary by location
Great Britain 17%
Ireland 25%
Northern Ireland 25%
Norway 38%
Romania 3%
Sweden 36%
Average (arithmetic mean across all countries in sample) 24%
Source: ENTSO-E12
12 ENTSO-E (2017), Overview of Transmission Tariffs in Europe: Synthesis 2017
Page 34 of 67
4.24 In terms of the way in which TUoS is levied on generators, the Authority notes that a
range of approaches can be observed across international jurisdictions (although the
majority of countries surveyed opted for an approach based on MTSD). For example,
Great Britain, Ireland, Northern Ireland and Sweden all levy TUoS on generators based
on generation at system peak, whereas Australia levies TUoS based on a combination
of peak and annual demand.
4.25 Beyond the considerations of how generation TUoS charges could impact dispatch and
generation costs, it is also important to understand the potential distributional impact
across customers and Government. Under the current system, all TUoS costs are levied
on the suppliers, with the level of the charge based on contribution to MTSD. Suppose
instead that a share of TUoS is levied on generators. Generators would pass these
costs through in the price charged to OPWP and, in turn, OPWP would reflect this cost
in the BST. Ultimately, all of the TUoS costs are passed through to the suppliers (who in
the case of their CRT customers pass them directly on in customer bills).
4.26 While the total value of TUoS charges is unchanged, shifting some of the TUoS cost to
generators means that these costs are being recouped on a per MWh basis (rather
than a MW basis as under the existing methodology), which could impact on the
distribution of TUoS costs across customer types.
4.27 This is illustrated in Table 11, which uses 2017 RUT and MTSD data for MZEC to show
how the burden of TUoS costs would fall across large customers who are facing the
cost reflective tariff (CRT) and other customers who are not currently facing a CRT. This
is significant as it has implications for the amount of cost that paid by customers
(through tariffs) versus the Government (through subsidy). That is, Government subsidy
decreases as a greater share of TUoS costs is levied on CRT customers.
4.28 The MZEC RUT and MTSD data in Table 11 show that, while CRT customers accounted
for 19% of total MZEC supply (MWh) in 2017, they only accounted for 9% of peak
demand (MW). This is to be expected, as CRT customers include many electricity-
intensive users who will be consuming significant amounts of electricity throughout the
year (and not just at summer peak). Based on the current TUoS charging methodology,
MZEC CRT customers will pay for 9% of TUoS costs that are levied on MZEC.
4.29 If, on the other hand, a share of the TUoS charges are levied on generators (and
therefore recouped on a MWh-basis through the BST), then CRT customers will pay a
larger share of the costs. For example, if 20% of TUoS costs are levied on generators,
then the share of MZEC’s TUoS costs paid by CRT customers increases from 9% to
11%. The fact that a greater share of costs is now being paid by customers that are
paying a cost-reflective price will in turn reduce the requirement for Government
subsidy.
Page 35 of 67
Table 11: illustration of the distribution of TUoS costs across customer types (based
on MZEC data)
2017 Large (CRT) customers Other (non-CRT) customers
RUT (MWh) 1,651,428 6,873,599
RUT (%) 19% 81%
MTSD (KW) 194,497 1,926,303
Share of TUoS costs based
on existing methodology
(%)
9% 91%
Share of TUoS costs based
on charging a share of
costs to generators:
20%13 11% 89%
50% 14% 86%
100% 19% 81%
Source: OETC, MZEC, Authority calculations
4.30 The Authority notes this would increase electricity costs faced by CRT customers. Based
on outturn electricity consumption and CRT rates in 2017, a 20% share of TUoS levied
on generators would increase the energy costs of transmission-connected customers
by around 2.2%. This could negatively impact on the attractiveness of Oman as a
destination for internationally mobile capital.
Initial proposal
4.31 The Authority has carefully considered the responses from stakeholders. A summary of
the Authority’s assessment against the assessment criteria is shown in Table 12.
13 For clarity, the share of TUoS costs faced by CRT customers in the 20% scenario is calculated by:
20% x {MWh (CRT customers) / MWh (non-CRT customers)] +
80% x {MW (CRT customers) / MW (non-CRT customers)]
Page 36 of 67
Table 12: Authority’s assessment of charging TUoS to generators against
assessment criteria
Criteria Charging TUoS to generators
Cost-reflectivity / Efficiency √
Non-discrimination -
Fairness -
Simplicity X
Transparency X
Future proofed √
Notes: √ positive assessment against criteria; X negative assessment against criteria; -
no substantive impact
4.32 The Authority notes that there are theoretical benefits associated with levying TUoS
charges on generators. Generators impose costs on the transmission system through
their actions. To the extent that those costs vary across generators it is possible that
levying TUoS charges on generators could help to ensure more efficient use of
available generation resources.
4.33 Charging a share of TUoS to generators could also reduce the requirement for public
subsidy, though this would create an additional cost burden on CRT customers.
4.34 However, the Authority notes that the current set-up of the generation market in Oman,
where power is procured through PPAs and dispatch is governed through the terms of
those agreements and instructions from the OETC LDC. Thus, while the beginning of
the spot market will begin to alter the way in which power is procured and dispatched,
this will be a gradual process. The Authority is therefore unconvinced that levying TUoS
on generators will yield material efficiency benefits at this time and is not minded to
levy a share of TUoS on generators at this time.
Charge TUoS to generators based on location
4.35 Given the decision not to charge generators a share of TUoS costs, the question of
whether those costs should vary by location is less significant. However, were a share
of TUoS costs levied on generators at some future point, consideration would also need
to be given as to whether such charges should vary by location. Where TUoS charges
are uniform geographically they would not provide signals to users about where on the
system to connect. Under certain conditions, this could increase system costs.
Stakeholder views
4.36 As discussed in the previous section, OETC felt that locational transmission charges
were worthy of further consideration (though benefits would be limited until substantial
amounts of power were being procured through the spot market). OPWP and the
generators all noted that there is a lack of flexibility for generators to respond to
locational signals, which would limit the potential benefits of the reform.
Page 37 of 67
Assessment
4.37 Many of the same considerations that apply to the assessment of applying TUoS
charges to generators are also relevant here. That is, whether this reform would yield a
benefit (in terms of lowering the costs of the transmission system) would depend on:
(1) transmission costs varying across locations; (2) the method of procuring power
being sufficiently flexible to respond to these variations in cost; and (3) generators
being able to responds to transmission signals in terms of where they locate.
4.38 As discussed under the previous option, levying a share of TUoS costs on generators
could ensure that the market reaches the most efficient outcome by ensuring the
lowest-cost generation (inclusive of transmission costs) is dispatched to meet demand.
4.39 In a system with material transmission system constraints, cost-reflective TUoS charges
would be expected to vary across regions (i.e. charges should be higher in parts of the
system with greater network constraints). Where this is the case, it is possible that the
application of location TUoS charges could change the order of generation dispatch
(i.e., capacity in highly constrained parts of the network are less likely to be
dispatched).
4.40 Conversely, in a system without material system constraints, we would expect TUoS
charges to be uniform across regions. Where this is the case, the application of TUoS
charges will not alter the order of dispatch.
4.41 As discussed in the Section 3, OETC’s response to the Consultation Paper indicated
there are currently no material constraints in the transmission system. This being the
case, we would not expect that levying TUoS charges on generators would have an
impact on dispatch.
4.42 As discussed in Section 3 (in the discussion of deep connection charges), generators
do not appear to be able to exercise much choice in terms of where they locate (either
due to a lack of available sites or because of the importance of other factors, such as
the proximity to fuel). What this means is that a locational TUoS charge is unlikely to
impact on site selection because generators are unable to respond to the incentive.
Furthermore, responses to the Consultation Paper suggested that transmission system
costs associated with different potential sites are already factored into the process
through which OPWP determine the sites for new generation. As such, it is unlikely that
the application of locational TUoS charges will have an impact on site selection.
4.43 The move towards greater cost-reflectivity under this reform arguably results in a fairer
distribution of costs across users of the transmission system. Indeed, this reform could
result in substantial variation in TUoS charges across generators. As was discussed
under the previous section, the Authority does not consider that this would create an
issue with respect to non-discrimination as the charges reflect the burdens that
different users are placing on the system. The Authority also considers that charging
Page 38 of 67
generators TUoS based on their locations would not have any impact on
inter-generational equity.
4.44 The Authority notes, however, that a system of locational charges could substantially
increase the complexity of the TUoS methodology given that different charges would
apply across geographies depending on the extent of system constraints. The Authority
believes that this will make the system of charging less transparent and the charges
less predictable for users.
Initial proposal
4.45 As noted above, the decision of the Authority not to charge a share of TUoS to
generators means that this reform is not necessary. However, the Authority considers it
is worthwhile to summarise the merits and drawbacks of locational charges in case it is
decided at some point in the future to levy TUoS charges on generators.
4.46 The Authority has carefully considered the responses from stakeholders on this issue. A
summary of the Authority’s assessment of this reform against the assessment criteria
is shown in Table 13.
Table 13: Authority’s assessment of charging TUoS to generators based on location
against assessment criteria
Criteria Charging TUoS to generators based on location
Cost-reflectivity / Efficiency √
Non-discrimination -
Fairness √
Simplicity X
Transparency X
Future proofed √
Notes: √ positive assessment against criteria; X negative assessment against criteria; -
no substantive impact
4.47 Although there are arguments both in favour of and against locational charging we
reiterate that the Authority is not at present minded to levy TUoS charges on
generators.
Accommodating an increase in renewable generation
4.48 Similar to the case of varying TUoS charges by location, the question of whether to vary
charges by generation technology is contingent on firstly charging a share of TUoS to
generators. Given the decision not to charge generators, the issue of whether the
charges need to reform in order to accommodate renewables is a moot point. However,
should the decision ever be taken to levy a share of TUoS on generators, some
consideration should be given as to whether to vary such charges by technology.
4.49 Accordingly, the Consultation Paper discussed how the TUoS charging methodology
Page 39 of 67
may have to evolve in light of the anticipated increase in the level of renewable
electricity in Oman. The paper noted that intermittent renewables tend to have lower
capacity factors than conventional generation. Allocating the costs of transmission
based on the share of peak system usage may not be representative of the costs that
renewable generation places on the transmission system throughout the year. As such,
the Authority considered whether the method of allocating TUoS charges should be
amended to reflect the characteristics of different generation technologies (and,
specifically, the demand that different technologies place on the transmission system)
and the Consultation Paper sought the views of stakeholders on whether the existing
system of TUoS charges should be reformed.
Stakeholder views
4.50 There was general consensus across responses that (were TUoS to be charged to
generators) the existing methodology of charging based on a share of MTSD would not
be suitable for intermittent renewable generation.
4.51 Both OETC and DPC felt that the method for allocating TUoS to generators should
reflect the lower average load factors of renewables. OPWP, on the other hand, favored
an approach based on capacity use during system peak (measured using a larger
number of system snapshots rather than a single point in time) rather than an
adjustment based on average load factors.
4.52 Both OPWP and MEDC noted that a substantial increase in renewable generation was
still a number of years away. However, OPWP felt that it remained prudent to consider
these issues at this stage in anticipation of the increased penetration.
Assessment
4.53 As discussed above, the proposal to vary the way that TUoS is allocated based on
technology is grounded in the assumption that charging all technologies based on
contribution to MTSD may result in an unfair distribution of costs across technologies.
4.54 The Authority notes that the allocation of TUoS costs would be likely to differ between
renewable technologies. For example, solar generation is likely to be generating power
during system peak (i.e., maximum system demand in 2017 occurred on the 31st May
at 15:00), wind will only be generating to the extent that the wind is blowing at this
point of time. As such, solar and wind technologies would potentially need to be treated
differently under a system that charged TUoS based on contribution to MTSD.
Page 40 of 67
4.55 Judging the case for reform therefore requires that we are satisfied that the current
charging methodology is not appropriate for all technologies. The Authority notes that
the approach of varying TUoS charges by technology is adopted in some other
jurisdictions. For example, in Great Britain, TUoS charges are levied on generators in a
way that distinguishes between the burdens that intermittent renewable generation
and conventional generation place on the transmission system (see Box 1 below for a
more detailed discussion of the GB charging methodology). The TUoS charges act to
reduce the charges that are paid by renewable generators (and facilitate the meeting of
an ambitious renewable energy target).
Page 41 of 67
Box 1: TUoS charges in Great Britain
Following a process of consultation and review, the electricity regulator (Ofgem) decided to
reform the TUoS charging methodology in Great Britain (GB) in 2016 in order to better reflect
the burden that different users were placing on the transmission system. In particular, Ofgem
felt that intermittent renewable generation tended to result in lower requirements for
transmission investment than conventional generation and that this should be reflected in the
TUoS charges that different generation technologies were required to pay.
Transmission requirements in GB are driven by the Security and Quality of Supply Standards
(SQSS), which includes two components: (1) Demand security criterion: which describes the
minimum transmission capacity required to ensure that conventional generators can meet
demand at times when intermittent generators cannot run (i.e., when there is no wind); and (2)
Economy criterion: which describes the additional capacity needed above that to meet peak
demand to efficiently manage the system taking into account the need to manage constraint
costs in an effective and economic manner.14
The TUoS tariff for generators was therefore split into two parts: (1) a ‘peak security’ tariff; and
(2) a ‘year-round’ tariff. All generators pay the year-round tariff but only conventional
generators pay the peak security tariff.
The peak security tariff is only paid by conventional generators. This is because, under the
SQSS, intermittent renewable generators are assumed not to contribute to peak security and
therefore do not drive investment on the transmission network.
All generators are required to pay the year-round tariff. However, this tariff is split into two
parts: a ‘shared’ and ‘non-shared’ element. This refers to a generators ability to ‘share’
transmission capacity, which depends on the concentration of types of generators in a
particular area. This recognizes that it is efficient to build more transmission capacity for areas
with high-concentrations of renewable generation because this plant is likely to be generating
at the same time (i.e., when the wind blows) and is expensive to constrain off. Once the
proportion of low-carbon generation in an area exceeds 50%, then a part of the year-round
tariff will be classified as non-shared.
A final adjustment is made to the shared element of the year-round tariff to reflect the
generator’s average annual load factor for the past five years. This recognizes that there is a
link between the level of constraint costs and the level of transmission investment.
Source: Ofgem (2014) ‘Project TransmiT: Decisions on proposals to change the electricity
transmission charging methodology’
14 Constraint costs are the payments made to a generator by the system operator to manage constraints on
the system where there is insufficient network capacity.
Page 42 of 67
4.56 The TUoS charging methodology that is in place in Great Britain provides an example of
how charges can be set in a way that more closely reflects the burden that different
generation technologies are placing on the transmission system and this could bring
efficiency improvements in relation to plant dispatch. However, the Authority notes that
this is part of a more comprehensive transmission planning and operation philosophy
for large capacities of renewable generation that has not yet been needed in Oman.
The approach also adds significant complexity into the calculation of transmission
charges and, potentially, makes the costs less transparent and predictable for market
participants.
4.57 The Authority also notes that the issue of the fairness of TUoS charges across
generation technologies only becomes relevant once a share of TUoS charges is levied
on generators. If, as under the current methodology, all TUoS costs are levied on load,
no generators can be disadvantaged.
4.58 As discussed under the previous two options, this reform could result in large variations
in the transmission costs that are paid by different generators. However, this would not
create an issue with respect to non-discrimination (and arguably results in a fairer
distribution of costs) as the charges would more accurately reflect the costs that
different generators are imposing on the transmission system.
4.59 Finally, the Authority notes that renewable generation is currently at an embryonic
stage in Oman. In its most recent 7-year statement, OPWP set its plans to procure new
renewable generation capacity (see Figure 2). This shows that renewable capacity is
expected to grow from less than 1% of total generation capacity in 2021 to over 7% in
2025. The 7-year statement also suggests that the majority (75%) of the new capacity
in 2025 will be solar generation.15
15 PWP 7-Year Statement (2018-2024)
Page 43 of 67
Figure 2: expected renewable generation as a share of all capacity (MIS & Dhofar)
Source: OPWP (2018), OPWP 7-Year Statement 2018-2024
Initial Proposals
4.60 As noted above, the decision of the Authority not to charge a share of TUoS to
generators means that the Authority does not intend to charge different TUoS to
different types of generating plant.
4.61 The summary in Table 14 below reflects the Authority’s summary assessment of the
merits and drawbacks of differential charging for generation technologies should it be
decided in the future to levy TUoS charges on generators.
Table 14: Authority’s assessment of reforming TUoS to accommodate an increase in
renewable generation against assessment criteria
Criteria Accommodating an increase in renewables
Cost-reflectivity / Efficiency √
Non-discrimination -
Fairness √
Simplicity X
Transparency X
Future proofed √
Notes: √ positive assessment against criteria; X negative assessment against criteria; -
no substantive impact
Page 44 of 67
4.62 In principle, the Authority understands that the characteristics of renewables may
require these types of generators to be treated differently (than conventional
generation) under a TUoS charging regime. The Authority notes that this practice can
be observed in some other jurisdictions (e.g., Great Britain)
4.63 However, given that the penetration of renewables within the sector over the short to
medium term remains relatively low, the Authority believes that it would be premature
to consider this reform at this point in time.
Reforming the methodology for levying TUoS charges on suppliers
4.64 In the Consultation Paper, the Authority discussed whether the way in which TUoS
charges are levied on suppliers (i.e. based on shares of MTSD) gives appropriate
signals to customers to manage their peak and overall demand.
4.65 As discussed above, TUoS charges are currently levied on load (suppliers and large CRT
customers) based on shares of MTSD (i.e., the one hour of highest transmission system
demand in a given year). That is, a transmission-connected customer that is
responsible for 5% of maximum system demand will face 5% of the total TUoS costs. It
is possible that a more powerful incentive could be created through moving from a
charge based on a single snapshot of peak demand to one based on multiple
snapshots. Moving to a system of charges based on multiple snapshots of system
demand (e.g., transmission costs based on the average share of the two hours of
highest transmission system demand in a year) can help to intensify the incentive on
customers to manage their demand. That is, customers will need to manage their peak
demand over a longer period to increase their chance of minimising their consumption
during both hours.
4.66 The Consultation Paper also raised the issue that allocating TUoS charges entirely on
the basis of peak transmission system demand means that large customers may not
face a strong incentive to reduce their overall demand (i.e., MWh).
4.67 Noting these issues, in the Consultation Paper the Authority sought views of
stakeholders on whether TUoS charges should be calculated based on multiple
snapshots of MTSD or whether TUoS charges should reflect the RUT for each supplier.
Stakeholder views
4.68 Reponses indicated a high level of support for changing the basis for TUoS charging
from a single to multiple snapshots. Many respondents noted that this could result in a
more sustained incentive for customers to manage peak demand but pointed out that
the multiple snapshots would need to be separated by a substantial period of time
(OPWP proposed that periods were at least one week apart) to ensure that the multiple
peaks are not concurrent.
Page 45 of 67
4.69 OETC noted that, prior to the implementation of the CRT for large customers, the TUoS
charges on peak demand had no discernable impact on reducing peak load and that
since the introduction of the CRT, only a small number of customers (i.e., steel mills at
Shadeed, Sohar, Muscat and Modern Steel) had taken measures to manage their peak
demand. OETC argued therefore that a move to allocating TUoS based on multiple
snapshots would not necessarily have a dramatic impact on peak demand. However,
OETC remained in favor of the reform as they argued that it was potentially a fairer way
of allocating costs, as it could reduce the chance of anomalies (e.g., when a customer’s
demand is, by chance, abnormally low during system peak, resulting in that customer
facing a low share of TUoS costs).
4.70 There was substantially less support amongst stakeholders for allocating a share of
TUoS costs based on overall demand or energy (i.e., MWh). Many stakeholders noted
that the incentive to manage their total consumption is already present in the energy
component of tariffs (bz/MWh) charged to both CRT and non-CRT customers. They
argued that allocating a share of the TUoS costs based on energy (MWh) could
potentially undermine the incentive on customers to manage peak demand, which is
the key driver of transmission system costs.
Assessment
4.71 The Authority can see that there is an in-principle case for reforming the methodology
for charging TUoS to one based on multiple snapshots. While it is arguable that a move
away from charging solely on the basis of MTSD (i.e. the one hour of maximum system
demand, which is the key driver of transmission capacity demand) represents a
departure from cost-reflectivity, the Authority considers that it is plausible that the use
of multiple snapshots could create a more sustained incentive to manage peak
demand. To the extent that this is the case, this reform could drive efficiencies and
cost reductions in terms of network infrastructure.
4.72 The Authority notes that a move to allocating TUoS based on multiple snapshots will
marginally increase the complexity and administrative burden associated with
calculating charges, which could make it more difficult for customers to understand
and anticipate the level of their TUoS charges.
4.73 The Authority does not consider that this reform will have any substantive impact
(positive or negative) in terms the extent of non-discrimination or fairness of the
charges.
4.74 The Authority notes that this reform could potentially help to make the transmission
system more robust to future changes in the electricity sector. For example, should
there be an increase in the amount of distributed generation using renewables, a
system of multiple snapshots could help to reduce the chance of anomalies in the
allocation of charges. For example, under a system with a single snapshot, the TUoS
Page 46 of 67
charge for a customer that is generating its power using renewables would be highly
dependent on whether the sun was shining or the wind was blowing during the hour of
maximum system demand. This risk is mitigated somewhat by using multiple
snapshots.
4.75 However, the case for making this reform rests on the presumption that customers will
be more responsive to a system of multiple snapshots in terms of the way that they
manage their demand during peak periods.
4.76 The Authority notes that, given the way in which customers are charged for their
electricity, most will not see a difference in their charges following this reform. This
means that, only customers facing the CRT will have an incentive to respond to this
price signal. It is particularly relevant, therefore, to consider how this reform would
impact upon this group of customers.
4.77 The reform also rests on there being multiple system peaks throughout the summer
season. That is, if the profile of demand over the year was, in fact, relatively flat with a
single well-defined peak, then there would be limited benefit of making this reform.
4.78 Figure 3 shows the pattern of hourly peak demand in Oman during 2017, which shows
that there is a sustained period of higher demand during the summer months. Figure 4
shows the pattern of hourly peak demand in 2017 just for the months of May, June and
July. The data shows that maximum system demand in late May (specifically the hour
of highest peak demand occurred on the 31st May). While the data shows that there is
a clear system peak, it also shows that there is a period throughout May, June and July
that is characterized by multiple peaks in system demand (albeit somewhat lower than
maximum system peak). That being the case, there appears to be some merit in
considering the case for switching to allocating TUoS based on multiple system
snapshots, in order create a more sustained incentive on customers to manage their
peak demand.
Page 47 of 67
Figure 3: hourly peak demand in 2017 (MW)
Source: OETC
Figure 4: peak demand in 2017 (May-July) (MW)
Source: OETC
Page 48 of 67
4.79 Figure 5 shows the same hourly demand data (as Figure 3) but for 2016. This shows a
very similar pattern of demand as the 2017 data – i.e., a period of peak demand
throughout the summer months, punctuated by multiple system peaks. However, the
data shows that the hour of maximum system demand occurred slightly later in the
year, on the 12th June.
Figure 5: hourly peak demand in 2016 (MW)
Source: OETC
4.80
4.81 Figure 6 shows the pattern of demand for transmission-connected customers in 2017.
This data shows that these customers are consuming larger amounts of electricity in
the off-peak months and dramatically reduce their consumption in the summer
months. Indeed, some transmission-connected customers are exporting power during
peak periods and have some flexibility in managing their load.
Page 49 of 67
Figure 6: hourly peak demand for transmission-connected customers in 2017 (MW)
Source: OETC
4.82 Allocating TUoS based on multiple snapshots of system demand requires decisions on
both the number of snapshots and the duration between snapshots. Snapshots that
are too close together could undermine the objective to create a more sustained
incentive to manage peak demand. Conversely, snapshots that are too far apart will be
of less relevance to the management of system peak demand (as they will capture
‘peaks’ that are substantially lower than the maximum peak).
4.83 Some analysis of the alternative options is presented in Box 2. This suggests that a
system based on either: (a) two snapshots separated by a six-week period; (b) or three
snapshots that are separated by a three-week period will cover the May to July peak
period. The latter option would potentially create a marginally higher administrative
burden (given the higher number of snapshots) but the smaller duration between
snapshots helps to mitigate the risk of snapshots falling outside of the May to July peak
period.
Box 2: allocating TUoS based on multiple snapshots
The figure below shows the period captured by a system based on 2 snapshots with either: (1)
1 week between snapshots; (2) 3 weeks between snapshots; and (3) 6 weeks between
snapshots. This shows that, based on the 2017 demand data, 2 snapshots separated by a 6-
week gap would have covered the May, June and July peak period.
Page 50 of 67
The figure below shows the period captured (i.e., the period between the first and last
snapshot) by a system based on 3 snapshots with either: 1 week between snapshots; (2) 3
weeks between snapshots; and (3) 4 weeks between snapshots. Under this approach, a
system based on 3 snapshots separated by a 3-week gap would have covered the May, June
and July peak period.
4.84 Turning to the case for allocating a share of TUoS charges based on MWh. The case for
making this reform rests on the assumption that this will create a more powerful
incentive for customers to manage their energy demand and that it does not
undermine the incentive for customers to manage their peak demand.
4.85 Understanding the incentives that this reform would create for customers requires an
assessment of the extent to which TUoS charges are passed through to end users and
the balance between capacity (MW) and energy (MWh) charges in current tariffs.
Page 51 of 67
4.86 The balance between energy and capacity in existing tariffs varies across CRT and non-
CRT customers. The cost reflective tariff includes elements reflecting: (1) the cost of
energy (charged on a per KWh basis); (2) transmission costs (charged on the basis of
contribution to peak demand); (3) distribution costs (charged on a per KWh basis); and
(4) supply costs (charged on a per customer basis). The permitted tariff (charged to
non-CRT customers) charges customers solely on a per KWh basis.
4.87 Figure 7 shows how 2017 energy costs for transmission-connected CRT customers and
non-CRT customers break down by fixed (per customer charges), capacity and energy
charges.
4.88 This shows that the majority of cost for CRT customers and all costs for non-CRT
customers are charged on the basis of energy consumed and that the share of demand
charges in the overall tariffs are less than 5% for CRT customers and 0% for non-CRT
customers. This suggests that customers are already mainly paying on the basis of the
amount of energy that they use and, as such, these customers already have an
incentive to try to reduce energy consumption. That being the case, allocating a share
of the TUoS charge on a MWh basis would have only a marginal impact on the incentive
for customers to change their consumption behaviours.
Figure 7: capacity and energy charges across CRT and non-CRT customers
Note: fixed costs for CRT customers are only RO 50 per account, so are not visible on
the above chart
Source: OETC
Page 52 of 67
4.89 The Authority notes, however, that allocating a share of TUoS charges to energy is a
common practice in many jurisdictions. The share of TUoS levied on the basis of
capacity and energy in European countries that levy all of TUoS charges on demand in
2017 is shown in Figure 8. This shows that most countries charge a share of TUoS on
the basis of MWh, in order to provide an incentive for customers to manage their
energy demand throughout the year.
Figure 8: share of TUoS charges to energy and capacity in European countries
(2017) (only countries which levy all TUoS charges on demand)
Source: ENTSO-E16
Initial proposals
4.90 The Authority has carefully considered the responses from stakeholders on this issue. A
summary of the Authority’s assessment of this reform against the assessment criteria
is shown in Table 15.
16 ENTSO-E (2017), Overview of Transmission Tariffs in Europe: Synthesis 2017
Page 53 of 67
Table 15: Authority’s assessment of changing the basis on which TUoS is allocated
against assessment criteria
Criteria Multiple snapshots Allocating based on
RUT
Cost-reflectivity / Efficiency √ -
Non-discrimination - -
Fairness - -
Simplicity X X
Transparency X X
Future proofed √ -
Notes: √ positive assessment against criteria; X negative assessment against criteria; -
no substantive impact
4.91 Responses to the Consultation Paper suggest that there has not been a substantial
change in behaviour from most customers with respect to their energy use. As such, it
is not clear that changing the approach to allocating TUoS will result in a step change in
the way in which customers manage their peak demand. However, the load data for
large energy users suggests that these customers are able to exercise some flexibility
in managing their load and the Authority considers that it is plausible that a system of
multiple snapshots could create a more sustained incentive to manage peak demand.
As such, the Authority believes that this reform could help to reduce peak demand and
lower the costs of the transmission system.
4.92 The Authority notes that this reform increases the complexity and administrative
burden of the system of allocating TUoS charges. However, the Authority considered
that this impact will be modest and, therefore, commensurate with the potential
benefits of the reform.
4.93 As such, the Authority is minded to change the basis of charging from a single snapshot
to multiple snapshots in order to create a more sustained incentive to manage
demand.
Page 54 of 67
4.94 As discussed earlier, the snapshots cannot be too close together as it is possible (as in
2017) that peaks could fall on consecutive days, which would undermine the objective
to create a more sustained incentive. Nor should the snapshots be too far apart, as this
may mean that snapshots fall far from the system peak, and undermine the incentive
to manage peak demand. The choice of the number of system snapshots and the
length of time between snapshots needs to take into account these considerations.
Based on the analysis of the yearly demand data presented earlier, the Authority
proposes to change the method for allocating TUoS to one based on the share of total
transmission system demand averaged across the three hour one-hour periods in
which total system demand is at its highest. The three snapshots of highest
transmission system demand should be at least three-weeks apart. The Authority
believes that this will create an incentive for customers to continue to manage their
peak demand throughout the summer peak season.
4.95 With respect to the question of whether to allocate a share of TUoS based on RUTs,
(rather than MTSD), while the Authority notes that charging a share of TUoS based on
MWh is common practice in many jurisdictions, it is clear energy charges already make
up a sizeable proportion of the overall electricity tariffs and that customers already face
an incentive to manage their energy demand through the existing CRT and Permitted
tariffs. It is not clear therefore that allocating some of TUoS to RUT will have a
significant impact on the pattern of demand. As such, the Authority is not minded to
allocate a share of TUoS costs on the basis of RUT.
Creating a separate charge for balancing and dispatch costs
4.96 As discussed in Table 8, another potential issue related to cost-reflectivity of the
current transmission charging methodology relates to the fact that the costs of system
balancing and dispatch (i.e., the costs incurred by OETC for undertaking the functions
related to system balancing and dispatch of electricity17) are currently recouped from
suppliers through the TUoS charges.
4.97 In principle, a more cost-reflective approach could be to separately identify the costs
associated with transmission network activities from the costs associated with
balancing and dispatch and have separate charges for each that reflect the full cost of
providing these distinct services. Accordingly, in the Consultation Paper the Authority
sought views from stakeholders on whether there could be a benefit to introducing a
separate charge for dispatch and balancing.
17 These costs represent the operating costs of running OETC’s Load Dispatch Centre.
Page 55 of 67
Stakeholder views
4.98 Responses indicated a high level of support for introducing a separate charge for
balancing and dispatch. Many respondents felt that this would give supplier and
generators the correct signals for efficient dispatch and load balancing.
4.99 OETC noted that the costs that they incur for undertaking balancing and dispatch
activities are driven by aggregate demand as well as individual customer demands.
Specifically, they argued that the resources required for balancing varies across power
stations, with a fixed component across each power station and a variable component
that varies based on the number of plant units (rather than the output of the plant).
4.100 OETC proposed that separate charges should be levied on: (a) generators: where the
charge includes fixed and variable components based on the number of plant units; (b)
suppliers: where the charge is based on demand; and (c) transmission connected
customers above a certain capacity threshold. OETC noted that they did not as yet have
a methodology for calculating the precise charges that should be levied on different
market participants but they offered to work with the Authority to develop the approach
to charging if required.
4.101 OPWP felt that there would be advantages in separating the balancing and dispatch
costs from TUoS charges as it would allow for charges to be levied on the entities that
are responsible for generating the costs. Specifically, they felt that the costs of certain
ancillary services could be charged to a generator, when the generator is the driver of
the requirement for ancillary services (e.g., by generating less power than is
requested/anticipated by the market operator).18 However, given that the market for
ancillary services is likely to develop alongside the spot market and given that the costs
of ancillary services are at present included in power purchasing rather than
transmission system costs, OPWP felt that further development of balancing and
dispatch charges should be done alongside the spot market to ensure consistency.
18 Ancillary services refer to the range of services that transmission system operators can procure from
generators or other third parties in order to maintain system security (e.g., black start capability; frequency
response and fast reserve).
Page 56 of 67
Assessment
4.102 The Authority notes that there are some potential benefits from creating a separate
charge covering balancing and dispatch activities performed by OETC. These costs are
currently recouped through the TUoS charges levied on and paid by suppliers and CRT
customers based on shares of MTSD. Based on the responses to the consultation, the
Authority notes that this approach of recouping these balancing and dispatch costs
does not appear to be cost-reflective. That being the case, a separate charge for
balancing and dispatch that charges users based on the extent to which they are
responsible for generating these costs, would in future be more cost-reflective
(allocatively efficient) and help to encourage more efficient behaviours from generators
and customers.
4.103 As is the case for many of the charges discussed in this section, the creation of a
separate balance and dispatch charge could result in different charges for different
users of the transmission system. However, this could be considered to result in a
fairer allocation of costs as the level of charges would better reflect burdens that
entities are placing on the system.
4.104 However, the Authority notes that the creation of a separate charge for balancing and
dispatch would increase the complexity and administrative burden compared to the
current system of TUoS charges for OETC activities and would need to be consistent
with spot market developments and modifications to OPWPs power procurement costs,
This could result in charges being more difficult to understand and predict for users of
the transmission system and needs considerable more thought.
4.105 One of the considerations for whether to create a separate charge for dispatch and
system balancing relates to the materiality of the cost of these services. The split of
OETC’s costs across business functions in 2017 is shown in Figure 9. This shows that
dispatch and system balancing accounted for around 10% of OETC operating costs in
2017. These activities therefore represent a small, but not insignificant, share of total
TUoS costs.
Page 57 of 67
Figure 9: OETC opex split by function (2017)
Source: OETC
4.106 OETC have indicated to the Authority that they expect these costs to become more
material over time. OETC also contend that the introduction of CRTs and the
anticipated increase in renewable generation will increase uncertainty on both the
demand and supply side and will, therefore, increase balancing costs over time.
4.107 The Authority also notes that balancing and dispatch are separately charged for in a
number of international jurisdictions. As discussed in the Consultation Paper, Great
Britain, Germany and the Netherlands all have separate balancing and dispatch
charges that charge generators and suppliers based on the extent to which these users
are responsible for creating the system imbalance (e.g., a supplier demands more
energy than anticipated, which requires additional generation to be dispatched at short
notice).
4.108 The Authority notes that (based on the international examples surveyed) balancing and
dispatch charges are typically levied on both generators and suppliers, as both types of
entities are responsible for generating balancing and dispatch costs. As was discussed
in 4.15, we might expect that the levying of a charge for balancing and dispatch to
have an impact on the way in which generators are dispatched where those charges
vary across generators (which we would expect them to as costs will be levied on
generators who cause those costs). However, the potential cost savings of levying an
additional charge on generators is unlikely to impact behaviours whilst the majority of
Page 58 of 67
power continues to be procured through PPAs.
4.109 Finally, the Authority notes that a separate charge for dispatch and balancing would
have an impact on the shares of costs paid by different types of customers (specifically
between CRT and non-CRT customers). The costs of balancing and dispatch are
currently recouped through suppliers and CRT customers through the TUoS charges. As
discussed in 4.25 to4.30, levying some of this cost on generators could change the
balance of costs across CRT and non-CRT customers (and potentially on the
requirement for subsidy). As was shown in Table 11, levying a share of costs on
generators would increase the proportion of costs faced by CRT customers (and also
the amount of subsidy required).
Initial proposals
4.110 The Authority has carefully considered the responses from stakeholders on this issue. A
summary of the Authority’s assessment of this reform against the assessment criteria
is shown in Table 16.
Table 16: Authority’s assessment of creating a separate charge for balancing and
dispatch against assessment criteria
Criteria
Creating a separate charge for balancing and
dispatch
Cost-reflectivity / Efficiency √
Non-discrimination -
Fairness √
Simplicity X
Transparency X
Future proofed -
Notes: √ positive assessment against criteria; X negative assessment against criteria; -
no substantive impact
4.111 The responses from stakeholders suggest that balancing and dispatch costs vary
across market participants and that the way in which these costs are recouped is not
cost-reflective. Given the materiality of these costs and the expectation that they will
grow over time, the Authority believes that a separate charge for balancing and
dispatch could help to encourage more efficient behaviour from generators and
suppliers. The Authority is therefore minded to create a separate charge for system
balancing and dispatch at an appropriate point in time.
Page 59 of 67
4.112 However, it is clear that the full benefit of the reform will be realized only when the spot
market has been implemented (and when substantial volumes of power are being
procured on that market). As such, the Authority believes that the rationale for
implementing this reform at this point of time is weak. Instead, the Authority proposes
to maintain a watching brief on this reform to monitor the evolution of the spot market,
the market for ancillary services and the costs of balancing and dispatch. The Authority
will then consider making a change to the CUSC methodology at a later date.
4.113 As a first step in this direction and recognizing that robust separate identification of the
costs of undertaking balancing and dispatching activities the Authority is, as separately
discussed in OETC’s T&D-PCR5 Initial Proposals, intending to create a separate term in
OETC’s Maximum Allowable Revenue to separately capture and account for the
economic costs for these balancing and dispatch costs.
Conclusion
4.114 In this section we have reviewed the potential reforms to the TUoS charging
methodology in light of the responses received to the Consultation Paper as well as our
own analysis of available data, economic theory and regulatory precedent. A summary
of our Initial Proposals for the various reform options is as follows:
Charging a share of TUoS to generators: the Authority is not minded to charge a
share of TUoS to generators but intends to keep the issue of network system
constraints under review;
Charge TUoS to generators based on location: the Authority is not minded to
make this reform;
Accommodating an increase in renewable generation: the Authority is not
minded to vary TUoS charges by technology at this time, but intends to keep this
issue under review should it decide in the future to charge a share of TUoS to
generators;
Reforming the methodology for levying TUoS on suppliers: the Authority is
minded to alter the methodology for levying TUoS to one based on three
snapshots of peak demand separated by a three-week gap. The Authority is not
minded to levy a share of TUoS based on energy/MWh; and
Creating a separate charge for balancing and dispatch costs: the Authority is
minded to create a separate charge for balancing and dispatch but intends to
pause until the spot market is more established before deciding on the
appropriate course of action. As a first step, the Authority intends to separately
identify these costs within OETC’s MAR formula in the T&D-PCR5 price control.
Page 60 of 67
4.115 These reforms will impact on both the way in which TUoS charges are levied and on
who pays those charges. The key characteristics of the current system and the
proposed system (including reforms to accommodate renewables and to create a
separate charge for balancing and dispatch) is set out in Figure 10 and Figure 11.
4.116 The Authority invites stakeholder to comment on these initial proposals and on any
aspect of the Authority’s assessment of the reform options.
Figure 10: schematic of the current system of TUoS charges
Page 62 of 67
5. Interactions between the CUSC and the price control review
5.1 In this section, we summarise the issues that were raised in the Consultation Paper in
relation to the interactions between the CUSC methodology and OETC’s price control
and consider if any changes may be required either to the CUSC methodology or to
OETC’s price control.
Interactions between CUSC methodology and OETC’s price control review
5.2 It is important to ensure that the transmission charging methodology is not creating
incentives for OETC, generators and/or transmission-connected customers that leads
to inefficiencies in the overall transmission costs and in turn, OETC’s MAR. As such, the
Consultation Paper considered the interdependencies between the CUSC and the
current price control review.
5.3 A number of areas of interaction were discussed:
Speculative requests: that is, entities requesting a connection but, for whatever
reason, deciding not to connect (or connecting later than expected) and/or
inappropriately sized connection (e.g., an entity requests a connection based on
an expectation of generation capacity or load which turns out to be too high). In
this case, the entity will pay the cost of the connection but the cost of any
required network reinforcement will be recovered from suppliers through the
TUoS charges. This means that OETC need to undertake effective due diligence
on all connection applications in order to make sure that it is only responding to
necessary and appropriately sized connection requests.
Default: that is, the extent to which connecting entity defaults on its connection
agreement. For example, when a transmission-connected customer goes out of
business and cannot pay any of the remaining capital costs for their connection
(assuming it was paying over-time rather than up-front). In this case, OETC will
need to recover the residual capital costs through another route.
Efficiency of procuring and delivering connections: in developing, procuring and
delivering connections based on Minimum Scheme, OETC is bound by its license
conditions, which obligate OETC to ‘develop, operate and maintain an efficient
and economic transmission system in accordance with the Transmission
Security Standard and the Grid Code’.19 There is, however, no economic
incentive to encourage OETC to deliver connections as efficiently and quickly as
19 The technical specification of the connection is based on the Minimum Scheme. The Minimum
Scheme is defined in the CUSC as the design with the lowest cost to provide the requested connection
capacity.
Page 63 of 67
possible (as the full cost and risk is borne by the connecting entity), which could
result in inefficiently incurred capex.
5.4 In the Consultation Paper the Authority sought the views of stakeholders on whether
any of the issues above were actually present in practice and, if so, whether any
changes to the CUSC methodology or OETC’s price control should be considered in
order to address these issues.
Stakeholder views
5.5 A small number of responses highlighted cases where they felt that there had been
speculative and/or inappropriately sized connections. For example, MEDC cited two
cases: the Almouge project (which they felt had an inappropriately sized connection);
and the Al Salm Yity Project (which they considered speculative and, ultimately, was
cancelled). OPWP referred to the case of the Saitic petrochemical company in Dhofar,
which OPWP felt was a speculative request (and was eventually cancelled following
substantial delays).
5.6 OETC commented that connection applications are usually based on justified project
needs rather than being speculative in nature. They noted that, in some cases, the
take-up of load at a given installation is slower than originally planned, but they argue
that this was likely due to inefficiencies (of the connector) rather than a speculative
application. They also argue that, over the medium term, the installed capacity will be
appropriately utilized. Furthermore, OETC felt that their own improvements in demand
forecasting and the established connection management processes are such that
speculative and inappropriately-sized connections is not seen as a concern for the
present or the future.
5.7 On the issue of the efficiency of the connection process, each of OPWP, MEDC and
MJEC felt that there was a case for incentivizing OETC to deliver connections in a more
efficient manner. For example, MEDC referred to instances of delays in connections in
previous years that had led to them having to incur additional costs in order to meet
customer demands and the Distribution Security of Supply Standard (DSSS) – i.e.,
delays in the completion of new grid stations resulted in additional costs associated
with balancing the load across existing infrastructure.
5.8 The Authority notes that OETC’s work to connect new entities is guided by the
requirements of the Grid Code. OETC have provided evidence of well-defined Standard
Operating Procedures (SOP) that describe how they respond to connection requests
and select the most appropriate connection option. Specifically, OETC described the
following SOPs:
SOP-M-003 (modifying and applying for a connection): this outlines the
timescale for a connection application processing and the associated
connection fees. It also sets out the data that needs to be submitted along with
Page 64 of 67
the application.
SOP-M-002 (handling connection application and releasing connection offer):
this outlines the process through which OETC responds to the applicant in a
timely manner and without discrimination or bias.
SOP-M-007 (preparing the pre-investment appraisal document) describes the
process of selecting the most cost-effective connection option considering
factors such as Transmission Security Standard (TSS) compliance, deliverability,
cost, risk analysis, losses and environment impact.
5.9 OETC argued that, through their adherence to these SOPs, they have performed well in
terms of the cost and timeliness of new connections. The Authority recognises the
processes that OETC has in place in order to ensure that connections take place in a
prompt and efficient manner. Furthermore, the Authority notes the evidence submitted
by OETC setting out the details of the new connections that they have made over the
past three years, which shows that, in many cases, the connections were completed
and energized ahead of the connection date agreed with the customer. The data also
showed that in the majority of cases, the costs of the connection was less than the
amount in the indicative connection offer. A summary of this evidence is presented in
Table 17.
Table 17: OETC recent transmission connections (2015-17)
Connection Date
energized
Date of
connection
Actual cost
less than
offered cost
Madinat Nizwa Grid Station 31-Mar-15 2016 Yes
Amerat Grid Station 04-May-15 2016 No
Ghala Grid Station 01-Jul-15 2016 Yes
A’salam Grid Station 15-Jul-15 2016 Yes
Al Ayjah Grid Station 30-Jul-15 2016 Yes
Ibra Grid Station 30-Apr-16 2016 Yes
Izki Grid Station 04-Jul-16 2017 Yes
Dhofar Generating
Company Connection 08-Mar-17 2017 No
Salalah Free Zone Grid
Station 28-Mar-17 2017 Yes
Khadhra Grid Station 03-Jul-17 2017 Yes
Hay Asim Grid Station 22-Jul-17 2017 No
Upgrading Mawalleh North 25-Jul-17 2017 Yes
Madinat Bakra Grid Station 18-sep-17 2017 Yes
Suwaiq Grid Station 16-Oct-17 2017 No
Source: OETC Narrative Business Plan Questionnaire responses
Page 65 of 67
5.10 OETC noted that, once the connection is agreed, the connecting party does carry the
pricing risk. However, OETC argued that it has no ability to influence the prices for the
agreed and defined once the works are underway and therefore should not carry this
risk. On the basis of this, OETC argued that there would be no benefit to be gained from
introducing such an incentive into its price control.
Initial Proposal
5.11 The Authority has carefully considered the responses received from stakeholders. The
Authority is satisfied that OETC has a robust process in place to verify, assess and
deliver new connections, which has in general resulted in connections that are
efficiently delivered. As such the Authority is not minded to make changes to the CUSC
methodology, Grid Code or to introduce a new incentive into OETC’s price control in
these areas at this time. If any issues are identified with the connections process in
future, the Authority may re-consider this issue.
Conclusion
5.12 In this Section, we have reviewed evidence related to the interactions between the
CUSC methodology and OETC’s price control. As discussed above, the Authority is not
minded to create an incentive in OETC’s price control to incentivise efficient and timely
connection.
5.13 The Authority invites stakeholders to comment on these initial proposals and on any
aspect of the Authority’s assessment of the reform options.
Page 66 of 67
6. Timetable for review of the CUSC methodology
6.1 The preceding sections set out a summary of the issues raised in the Consultation
Paper, the responses received from stakeholders on that paper and the Authority’s
initial proposals for reforming the CUSC methodology. The Authority now invites
stakeholders to comment on any aspect of its Initial Proposals.
6.2 OETC and other stakeholders are invited to respond to this these Initial Proposals by 30
June 2018.
6.3 The Authority will consider any responses received and issue its Final Proposals by xx
2018.
6.4 Once the final proposals are agreed, OETC shall commence the modification procedure
as set out in the CUSC methodology.
6.5 These stages will be conducted according to the timetable illustrated in Table 18
below.
Table 18: Timetable for the review of transmission and use of system charges
Initial Proposals
Authority issues initial proposals 31 May 2018
Response to initial proposals 30 June 2018
Final proposals
Authority issues final proposals 25 October 2018
OETC to respond to final proposals
OETC to undertake modification process (as required)
Page 67 of 67
Appendix A: list organizations that responded to the CUSC Consultation Paper
Oman Electricity Transmission Company
Oman Power and Water Procurement Company
Dhofar Power Company
Muscat Electricity Distribution Company
Majan Electricity Distribution Company
Mazoon Electricity Distribution Company
Rural Areas Electricity Company
Al Kamil Power Company
Al Rusail Power Company
Al Suwadi Power
Barka Power Company
Al Batinah Power
Phoenix Power Company
Sohar Power
United Power Company