Connect Plus: Session Checklist © Cambridge Assessment 2012 1 Connect Plus Session Checklist It is the centre’s responsibility to complete the below checklist prior to each Connect Plus session. Task Description Reference Deadline Complete Computer Specification All TSA and candidate workstations must meet the minimum required technical specification. Technical Guide Monitor Resolution Screen Resolutions are set to 4:3 ratios (for example 1024x768 or 1280x1024). Widescreen resolutions will present test rendering issues. Technical Guide Soundcards Soundcards are functional, not muted. Create Test Sittings Create test sittings according to your test venue and test sessions Setup. Test Administration Guide 5 days prior to Test Day Set up Connect Plus Users Set up additional accounts in Connect Plus according to your centre’s venue/room requirements. Each account must use a valid email address. Test Administration Guide 5 days prior to Test Day Installation Install Connect Plus TSA and CW software on the required number of workstations adhering to the recommended TSA: CW ratio detailed below. Technical Guide 2 days prior to Test Date Number of TSAs Ratio of 1 TSA for every 100 candidate workstations. Maximum of 5 TSAs per Test Centre. Technical Guide 2 days prior to Test Date Spare workstations Setup 1 spare workstation for every 20 candidates taking the test. Spare computers must be ready to take the test if required. Technical Guide 2 days prior to Test Date Familiarisation Test Run a Familiarisation Test . Technical Guide 2 days prior to Test Date Test Content & Test Keys Check via the Test Centre website that All test content has been downloaded on to the candidate workstations and all Test Keys have been downloaded to the TSA machines. Technical Guide 16.00hrs the day prior to the Test Date TSA and CW health All candidate workstations (CWs) must be registered to TSAs. All TSAs & CWs must be in a ‘healthy’ state and show as Ready. Technical Guide 16.00hrs the day prior to the Test Date

description

Connect Plus Session Checklist

Transcript of Connect Plus Session Checklist

Page 1: Connect Plus Session Checklist

Connect Plus: Session Checklist © Cambridge Assessment 2012

1

Connect Plus Session Checklist It is the centre’s responsibility to complete the below checklist prior to each Connect Plus session. Task Description Reference Deadline Complete Computer Specification All TSA and candidate workstations must meet the minimum required technical

specification. Technical Guide

Monitor Resolution Screen Resolutions are set to 4:3 ratios (for example 1024x768 or 1280x1024).

Widescreen resolutions will present test rendering issues. Technical Guide

Soundcards Soundcards are functional, not muted. Create Test Sittings Create test sittings according to your test venue and test sessions Setup. Test Administration

Guide 5 days prior to Test Day

Set up Connect Plus Users

Set up additional accounts in Connect Plus according to your centre’s venue/room requirements. Each account must use a valid email address.

Test Administration Guide

5 days prior to Test Day

Installation Install Connect Plus TSA and CW software on the required number of workstations

adhering to the recommended TSA: CW ratio detailed below. Technical Guide 2 days prior to Test Date

Number of TSAs Ratio of 1 TSA for every 100 candidate workstations. Maximum of 5 TSAs per Test

Centre. Technical Guide

2 days prior to Test Date

Spare workstations Setup 1 spare workstation for every 20 candidates taking the test. Spare computers

must be ready to take the test if required. Technical Guide

2 days prior to Test Date

Familiarisation Test Run a Familiarisation Test . Technical Guide

2 days prior to Test Date

Test Content & Test Keys

Check via the Test Centre website that All test content has been downloaded on to the candidate workstations and all Test Keys have been downloaded to the TSA machines.

Technical Guide

16.00hrs the day prior to the Test Date

TSA and CW health All candidate workstations (CWs) must be registered to TSAs. All TSAs & CWs must be

in a ‘healthy’ state and show as Ready. Technical Guide

16.00hrs the day prior to the Test Date

Page 2: Connect Plus Session Checklist

Connect Plus: Session Checklist © Cambridge Assessment 2012

2

Task Description Reference Deadline Complete Passwords printed Candidate usernames and passwords have been printed out and are ready to be

handed to the candidates when they arrive. Test AdministrationGuide

Page 3: Connect Plus Session Checklist

Connect Plus: Session Checklist © Cambridge Assessment 2012

3

Managing and running tests at a permanent test venue The flowchart below illustrates the tasks that you need to carry out to manage and run tests, and a typical timeline. The steps shown in this flowchart are described in detail in the following chapters in this guide.

Page 4: Connect Plus Session Checklist

Connect Plus: Session Checklist © Cambridge Assessment 2012

4

Managing and running tests at a temporary venue (for example a rented computer lab) The flowchart below illustrates the tasks that you need to carry out to manage and run tests, and a typical timeline an external venue. The steps shown in this flowchart are described in detail in the following chapters in this guide.