Connect 2020 Update Rider Experience and Operations Committee January 16, 2020

Transcript of Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations...

Page 1: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

Connect 2020 UpdateRider Experience and Operations Committee

January 16, 2020

Page 2: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

2

Why we are here: Connect 2020

Information Only, no Board action needed

• Tying in East Link to the operating railroad.

• Service preservation vs. shut-down approach.

Page 3: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

3

Connect 2020 Schedule

Regular service resumes

Jan. 6 – Feb. 7PHASE1 Feb. 10 – Mar. 13PHASE

2

Single Tracking on SB – Working on NB

WEEKENDCLOSURE

Jan.4 - 6

WEEKENDCLOSURE

Feb.8 - 9

WEEKENDCLOSURE

Mar.14 - 15

March 16

Single Tracking on NB – Working on SB

Page 4: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

4

Connect 2020 SequencePreparing the work area

Single Tracking - SB

Platform Closed - NB

Stadium Station

Closed Abandoned New track Operating

PHASE

1 January - February

Page 5: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

5

Single Tracking - SB

Platform Closed - NB

Stadium island platform

Closed Abandoned New track Operating

Connect 2020 SequenceTrack and Systems installation

PHASE

1 January - February

from Angle Lake

Turnback track

Page 6: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

6

Platform closed - SB

Single Tracking - NB

Stadium island platform

Closed Abandoned New track Operating

Connect 2020 SequenceTrack and Systems installation

PHASE

2 February - March

Page 7: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

7

Connect 2020 Sequenceat Completion

IDS platform - SB

IDS platform - NB

Abandoned New trackOperating

Stadium Station

POSTCONSTRUCTION

Page 8: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

8

Adjacent Construction

Page 9: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

9

Track-bed Preparation

Page 10: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

10

Track Installation

Page 11: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

11

Systems Work

Page 12: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

12

Testing and Safety Certification

Page 13: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

13

Operations

Page 14: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

14

Operations

Page 15: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

15

Public Safety• Security operating 24/7, increased

staffing from 6am – 10pm.

• All station entrances remain open for emergency access.

• No fares during weekend closures to speed transfers between Link and bus shuttles.

• The overall passenger response has been supportive and positive.

Page 16: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

16

Temporary Signage:

Page 17: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

17

Ambassador Program• 705 staff have

participated.

• More than 6,000 staff hours of outreach.

• Ambassadors answering questions and receiving feedback.

Page 18: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

18

Feedback

Customer Service 81 total• Announcements (29)• Early/Late Operations

(29)

Social - Twitter183 total• Neutral or positive (133)• Negative (50)

Page 19: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

19

Partner Agencies

Page 20: Connect 2020 Update - Sound Transit · Connect 2020 Update. Rider Experience and Operations Committee. January 16, 2020

Thank you.