Congestion in Power Grid

download Congestion in Power Grid

of 24

Transcript of Congestion in Power Grid

  • 8/10/2019 Congestion in Power Grid

    1/24

    CONGESTION IN POWER

    NETWORK- M B SHARMA

  • 8/10/2019 Congestion in Power Grid

    2/24

    Congestion

    When transmission demand >capability When Voltage levels in a corridor beyond operable limits When Real time line flow exceeds the TTC Most fundamental transmission management problem A natural corollary of growth Occurs in deregulated markets Commercial signal to Tr. Requirement N-1 Planning System security at stake

  • 8/10/2019 Congestion in Power Grid

    3/24

    POWER SYSTEM DE-REGULATION(RESTRUCTING)

    GENCO

    TRANSCO

    DISCO

    Tie Lines

    GENCO

    TRANSCO

    DISCO

    GENCO

    DISCO

    GENCO

    DISCO

    GENCO

    TRANSCO

    DISCO

    Deregulation or Restructuring denotes breaking up of theVertically Integrated Utility(VIU) structure into CompetitiveMarket Entities.

  • 8/10/2019 Congestion in Power Grid

    4/24

    RESTRUCTURED ELECTRICAL

    INDUSTRY

    http://c/Documents%20and%20Settings/MANGZ%20SHARMA/My%20Documents/congestion/Presentation1.pptx
  • 8/10/2019 Congestion in Power Grid

    5/24

    ENTITIES RESULTING FROM DE-REGULATION

    SO

    GENCO TRANSCO DISCO

    SO is the Power System Operator and the Power MarketOperator, which may include other entities depending on themarket structure. SO, is independent of the other entities

  • 8/10/2019 Congestion in Power Grid

    6/24

  • 8/10/2019 Congestion in Power Grid

    7/24

  • 8/10/2019 Congestion in Power Grid

    8/24

    Congestion management methods

    Cost free methods (Physical) Generation/ Load Control Network Reconfiguration (Parallel Paths, Loops)

    FACTS/ FSC ETC Voltage improvement Non-cost free methods (Commercial )

    Rescheduling of transactions

    Curtailment Imposition of Congestions charge

  • 8/10/2019 Congestion in Power Grid

    9/24

    Congestion occurance

    Real Time : Inadequate system conditions Temporary outage of Tr. Line / Generator/

    Load

    Ex-ante (before fact): More transactions by a far end Consumer Seasonal skew in L-G balance More demand for transmission corridor

  • 8/10/2019 Congestion in Power Grid

    10/24

    Congestion mitigation

    Stage 1 : Ex-ante (before fact): Bidding for transmission corridor (for bilateral

    transactions) Market Split (for Collective transactions)

    Stage 2 : (Real time) Impose Congestion charges on UI

    Stage 3 : (Real time)Curtailment of S TOA/ Collective/ MTOA/ LTA

    http://c/Documents%20and%20Settings/MANGZ%20SHARMA/My%20Documents/congestion/Presentation1.pptxhttp://c/Documents%20and%20Settings/MANGZ%20SHARMA/My%20Documents/congestion/Presentation1.pptx
  • 8/10/2019 Congestion in Power Grid

    11/24

    Pre-requisites

    Observability of Grid (SCADA) Scheduling mechanism

    EMS tools (Contingency Analysis, SecurityConstrained Dispatch) Commercial Mechanism

  • 8/10/2019 Congestion in Power Grid

    12/24

    Congestion management in India

    Central Electricity Regulatory Commission (Measures torelieve congestion in real time operation) Regulations,2009

    congestion charge shall be applied as a commercialmeasure.

    The congestion charge will be payable by a Regionalentity or entities causing congestion in the inter-regionallink or intra-regional link

    and receivable by a Regional entity or entities relievingcongestion. In addition to the Unscheduled Interchange charges

  • 8/10/2019 Congestion in Power Grid

    13/24

    Measures to mitigate Congestion

    Transfer Capability Total Transfer Capability (TTC) means the amountof electric power that can be transferred reliably overthe inter-control area transmission system under agiven set of operating conditions considering theeffect of occurrence of the worst credible contingency .

    Transmission Reliability Margin (TRM) means theamount of margin kept in the total transfer capabilitynecessary to ensure that the interconnectedtransmission network is secure under a reasonablerange of uncertainties in system conditions.

  • 8/10/2019 Congestion in Power Grid

    14/24

    Measures to mitigate Congestion

    Transfer Capability Available Transfer Capability (ATC) means

    the transfer capability of the intercontrol areatransmission system available for schedulingcommercial transactions (through long termaccess, medium term open access and shortterm open access) in a specific direction,taking into account the network security.Mathematically ATC is the Total TransferCapability less Transmission ReliabilityMargin.

  • 8/10/2019 Congestion in Power Grid

    15/24

    Total Transfer Capability (TTC)

  • 8/10/2019 Congestion in Power Grid

    16/24

    Transmission Reliability Margin (TRM ) Computation of TRM for a region or

    control area or group of control areaswould be based on the consideration ofthe following: Two percent (2%) of the total anticipated peak

    demand met in MW of the control area/groupof control area/region ( to account forforecasting uncertainties)

    Size of largest generating unit in the controlarea/ group of control area/region

  • 8/10/2019 Congestion in Power Grid

    17/24

    Measures to mitigate Congestion

    Declare ATC by NLDC/ RLDCs / for InterRegional/ Intra regional and each control area

    Congestion charge imposed on only Deviationsfrom schedules

    Rate of congestion charge : Rs.5.45/u Notice of

    2 time blocks for imposing 1 time block for lifting congestion charge Congestion charge would be levied for

    over drawal or under-injection in the importing control area under drawal or over-injection in the exporting control area.

  • 8/10/2019 Congestion in Power Grid

    18/24

    NLDC/ RLDC display the TTC, ATC, Actual flow on the congested corridor oncommon SCADA display

    No congestion charges if congestion isdue to outage of a transmission line in thecorridor, but schedules are maintained

    In such case, curtailment of STOA/ MTOAand then LTA

  • 8/10/2019 Congestion in Power Grid

    19/24

    REAL TIME CONGESTION MANAGEMENT

    In case of transmission constraint or threat togrid security, the scheduled transactions may becurtailed in the manner as decided by the NLDC

    /RLDCs / SLDCs to relieve the transmissionconstraint/ to improve grid security. Collective Transaction through Power

    Exchange(s) would normally be curtailedsubsequent to the Short-Term BilateralTransaction(s).

  • 8/10/2019 Congestion in Power Grid

    20/24

    contd RLDCs would curtail a Transaction at the periphery of the Regional

    Entities. SLDC(s) shall further incorporate the inter-se curtailment ofintra-State Entities to implement the curtailment.

    In case of curtailment of a Transaction caused by transmissionconstraints

    / threat to grid security, the Transmission Charges in respect of suchtransaction shall be payable on pro-rata basis in accordance withthe finally Implemented Schedules. Operating Charges shall not berevised in case of curtailment.Power Exchange (s) shall be responsible for the settlement onaccount of curtailment, directly with its participants.

    NLDC/RLDCs/SLDCs shall interact only with the respective PowerExchange(s), for the same

  • 8/10/2019 Congestion in Power Grid

    21/24

    Payment /receipts though Congestioncharge a/c

    Utilization of fund for studies, SPS, Shuntcapacitrs

  • 8/10/2019 Congestion in Power Grid

    22/24

    Upstream

    O/D &U/G relieveU/D & O/G aggravateO/D &U/G receive chargesU/D & O/G pay charges

    DownstreamU/D & O/G relieve O/D &U/G aggravateU/D & O/G receive chargesO/D &U/G pay charges

    Congestion Charge Imposition

  • 8/10/2019 Congestion in Power Grid

    23/24

    Congestion accounting

    NLDC/ RLDC provide From/To time block corridor

    and Upstream /downstream entitiesdetails to RPCs on a weekly basis whencongestion charge is kicked along withreasons

    RPC to issue congestion account alongwith UI accounting

  • 8/10/2019 Congestion in Power Grid

    24/24