CONSTRUCTION
OF
CONCRETE PAVEMENTS
PRIMARY STEPS
Surface preparation
Concrete mixing plant operations
Transport to paver
Preliminary steps prior to paving by machineries
Surface Preparation
Prepare subgrade for new pavement
Soil type
Moisture contentDensity
Preparing an existing pavement surfacefor overlay by removing top layer throughmilling, demolition
Remove pockets of unsuitable materials
Stabilize unsuitable soils
-
8/3/2019 Concrete Road Construction 1
2/16
Prepare granular subbase or basecourse
Similar to subgrade preparation
Usually higher density requirement
Cement-stabilized materials
Placed using slipform or asphalt equipment
Surface Preparation
Almost all PCC intended for pavementuse is ready mixed concrete
Mixing cement, aggregate, water andadmixtures
Plant Operations
Transport
Transportation to paving machinery from batchingfacility via truck mixer or non-agitating truck
Unload quickly upon arrival
Unload as close as possible to final placement
spot Quality control
Synchronisation rates of batching plant production,truck transport and paver
NEXT STEP PAVING
but reinforcement placement also common to both
-
8/3/2019 Concrete Road Construction 1
3/16
TWO KINDS OF PAVINGTECHNIQUES
FIXED FORM PAVING
SLIP FORM PAVING
manual
ALL functions to place reinforcement,strikeoff, spread, compact/consolidate,
finishing, texturing, cure
Fixed Form Paving
Different activitiesdone by separateindependentmachine traveling on
fixed forms (rails)
Slip Form Paving
Different activitiesdone by a single ornot more than 3machines travelingon crawlers
-
8/3/2019 Concrete Road Construction 1
4/16
Manual method - for small jobs
Fixed FormPaving Operations
Paving form is the mould Holds concrete in place
Establishes grade and alignment
Serves as tracks for paving equipment
Forms
Mould that determines
Pavement depth
Pavement width
Pavement smoothness
Made of steel (large job) or timber (small job with
less machineries) and has small side holes for
insertion of tie bars
-
8/3/2019 Concrete Road Construction 1
5/16
Typical SteelForm
Form Lock
Reinforcement
Dowel bars
-
-
-
-
-
Tie bars fixed by hand (FF) or t ie bar inserter(SP)
Mesh reinforcement, if required
Dowel BarsPlaced on a
Lean ConcreteBase in
Advance ofPCC Placement
-
8/3/2019 Concrete Road Construction 1
6/16
End Dump TruckDischarging PCC in Front
of a Paver
End Dump TruckDischarging PCC onto a
Spreader/Placer
InitialLeveling by
VibratingTruss Screed
Traveling CarriageScreed
Roller Screed
Roller screed consists of a steel tube that rotates up to250 rpm in the opposite direction of movement. Thetube strikes off PCC and pushes excess PCC forwardby the rolling action
-
8/3/2019 Concrete Road Construction 1
7/16
Small Hand-Operated Vibrator
Compaction1. Hand-operated vibrators.
2. Screed vibration.
Compacted Concrete in Steel Forms
Finishing and Texturing
Finishing using handfloats to eliminate
high/low spotsTexture types:
Longitudinal
Transverse
20 mm or less spacing
Random Spacing
-
8/3/2019 Concrete Road Construction 1
8/16
Mechaniseddragging artificial
turf
Manual draggingtexturing
Manual Texturing
-
8/3/2019 Concrete Road Construction 1
9/16
Curing
Curing carried out toprevent moistureloss. Ponding wateror cover slab withwater retainingmaterial.
Manually insert dowel bars into the constructionjoint at the end of the work day
Forms Removal Tie Bars Along a Longitudinal Joint
When one lane at a time is paved, tiebars are inserted at mid-slab depthand bent back until adjacent slab is
ready to be paved
-
8/3/2019 Concrete Road Construction 1
10/16
Critical Factors in FixedForm Paving - Ride Quality
Uniform grade - properly compacted Uniform subbase eliminate if subgrade CBR
above 15%
Forms meet specifications
Consistent mix, slump
Placement of reinforcing, dowel baskets
Timely delivery of concrete
Proper placement mix on grade
Critical Factors Fixed FormPaving - Ride Quality
Adequate vibration - compaction
Care in placement and vibration ofreinforcements, dowels
Proper machine adjustments
Steady machine progress
Avoid excessive finishing
Avoid excessive water on surface
Straightedge check of slab
Adequate cure
SLIPFORM
PAVING
-
8/3/2019 Concrete Road Construction 1
11/16
SLIPFORM PAVING
Uses low-slump PCC. Low-slump PCC is
necessary so that the fresh PCC is able to hold itsshape once the slipform paver has passed.
High productivity. Large jobs generally requirehigh production rates in order to be profitable.
Smooth riding surface. Automation and computercontrol allow slipform pavers to produce verysmooth riding surfaces
GENERAL SLIPFORM PAVINGPROCESS
EITHER a single
OR accomplished by 3 separate machineries:
spreader/placer; concrete paver; texturing and
curing machine
Slipform Paving Philosophy
To shape a material
byforcing it through a
mould.
-
8/3/2019 Concrete Road Construction 1
12/16
Extrusion Envelope
Profile Pan levels
concrete to right eleva
Tamper (150 strokes/min)pushes large aggregatebelow surfaceVibrator (group)
Strike Off remove excess
portion of auger-placed PCC
Concrete Head
Profile Pan Batter -Compression-Paver Uplift
FluidizedConcrete
Spread
by auger
Side Form Resistance Batter
Movement 1-2.5 m/min
Excess Concrete
Dowel bar inserter
Slipform
Compaction/consolidation Steel placement Form into a Shape Finish the Surface
SUBGRADE
Proper Compaction
Built to SpecifiedTolerances
Uniform Support
May be Stabilized
Place SUBBASE to Specified Tolerances
Enhance UNIFORMsupport for concrete layer
Working platform for concrete paving
Enhance smoothness
Reduce occurrence of mud pumping
-
8/3/2019 Concrete Road Construction 1
13/16
Track Line
Extend base onemeter beyondoutside edge ofpavement
Durable for pavingtrain
Keep it clean
Pavement Steel
Dowel bars
Tie bars
Reinforcing mesh
Continuous reinforcement
Placing Dowel Bars
Automatic
Manual
-
8/3/2019 Concrete Road Construction 1
14/16
Mechanical method
Hand placing ormanual method
Place PCC infront of paverusing a seriesof conveyorbelts, augersand strikeoff
devices
Discharging
Leveling and Vibration
Initial leveling by strike off screed
Compacting Concrete Mass
Series of vibrators at 7000-9000 VPM
-
8/3/2019 Concrete Road Construction 1
15/16
Vibration
Positioned so that their influence zone overlap by 50-75 mm
Finishing and Curing
As in fixed form paving
Dragging ArtificialTurf behind SP
Groove texture
-
8/3/2019 Concrete Road Construction 1
16/16
Spraying Curing Membrane
Curing
Uniform
Timely
THANK
YOU