Smart questions Smart answers Smart people Join Directory Search Tell A Friend Whitepapers Jobs Home > Forums > Engineering Computer Programs > General Engineering Programs > Computers and Structures: ETABS Forum Colums release and columns to beam joint in etabs thread802-244785 seny (Structural) 10 May 09 8:12 Hi everybody, I'm modeling 30 storey concrete building w/ shear walls lateral system and columns responsible only for gravity. As per ACI 318 section 8.8 we top of columns to be modeled as fixed and release can be assigned to bottom of the column. Is it appropriate way to model column in Etabs for service and ultimate stage – hinge at the bottom & fixed at the far end? So all the columns will have no release below the floor and hinge right above at all the point of column & slab intersection. One more question, I need to transfer at the second floor elevation on of column to two adjacent columns over the bridge (transfer) beam. What is the best way (technique) to model transfer beam to two columns below connections in Etabs? In case two columns below, three columns above and beam have no releases – all the columns (below and above) fail b/c of transferred moment from the beam and required enormous sections, what is not the case in real life. Assign releases at the beam ends? In this case haw Etabs takes in consideration that in real life there are no released beam & column joints in monolithically poured structures? I am sorry for long post. Any input on these matters are highly appreciated. Best regards. Skicat (Structural) 12 May 09 10:02 Seny, ACI 318 8.8 states that it is permitted to assume both ends of a column are fixed when computing gravity load moments, assuming the column is built integrally with the structure. I'm not sure why you would fix the top and (3) Share This Computers and Structures: ETABS - Colums release and columns to bea... http://www.eng-tips.com/viewthread.cfm?qid=244785 1 of 4 7/29/2013 8:35 AM

Transcript of Computers and Structures_ ETABS - Colums Release and Columns to Beam Joint in Etabs

Page 1: Computers and Structures_ ETABS - Colums Release and Columns to Beam Joint in Etabs

Smart questionsSmart answersSmart people

JoinDirectorySearchTell A FriendWhitepapersJobs

Home > Forums > Engineering Computer Programs > General Engineering Programs > Computers and Structures:ETABS Forum

Colums release and columns to beam joint in etabs thread802-244785

seny (Structural) 10May

098:12

Hi everybody,I'm modeling 30 storey concrete building w/ shear walls lateral system and columns responsible only for gravity.

As per ACI 318 section 8.8 we top of columns to be modeled as fixed and release can be assigned to bottom of thecolumn.Is it appropriate way to model column in Etabs for service and ultimate stage – hinge at the bottom & fixed at thefar end? So all the columns will have no release below the floor and hinge right above at all the point of column &slab intersection.

One more question, I need to transfer at the second floor elevation on of column to two adjacent columns over thebridge (transfer) beam. What is the best way (technique) to model transfer beam to two columns belowconnections in Etabs? In case two columns below, three columns above and beam have no releases – all thecolumns (below and above) fail b/c of transferred moment from the beam and required enormous sections, what isnot the case in real life. Assign releases at the beam ends? In this case haw Etabs takes in consideration that inreal life there are no released beam & column joints in monolithically poured structures?I am sorry for long post.Any input on these matters are highly appreciated. Best regards.

Skicat (Structural) 12May

0910:02

Seny,ACI 318 8.8 states that it is permitted to assume both ends of a column are fixed when computing gravity loadmoments, assuming the column is built integrally with the structure. I'm not sure why you would fix the top and

(3)

Share This

Computers and Structures: ETABS - Colums release and columns to bea... http://www.eng-tips.com/viewthread.cfm?qid=244785

1 of 4 7/29/2013 8:35 AM

Page 2: Computers and Structures_ ETABS - Colums Release and Columns to Beam Joint in Etabs

release the bottom as you stated above.

If you are going to transfer out one column at the second floor into two columns below at the first floor, I wouldexpect that the transfer beam would be enormous. If I understand what you are saying, the column you aretransferring is carrying 28 floors of load. I would not release the ends of the beam because you need to transferout the moment as well as the shear. Are you using post tensioned concrete floors? If so, the transfer beam couldalso be post tensioned, which would help. What program are you using to analyze and design your floors andbeams? If it were me, I would take the forces generated from the etabs model and model a transfer beam in aconcrete beam program and not rely on etabs to analyze / design my transfer beam. I hope this helps and I woulddefinately consult other sources given the magnitude of the task you are undertaking.

seny (Structural) 12May

0911:43

Skicat,Thanks for respond.I agree that bridge beam has to be fixed to the columns to guaranty condition of real moment connectionreinforcement and that is what I have in my model.Building is RC no PT.I am using Etabs and there is no problem w/ transfer beam.I have room for say 5'Wx6'H beam even more if req'd.Technique w/ bottom hinge was advised by Etabs support and this way commonly in use when you do not wantcolumn participation in lateral stability of the building.I have previously constructed buildings w/ the same transferring conditions.The question w/ modeling in Etabs – all three columns above the transfer beam (middle "B" point transferred andtwo ends continues"A"&"C") modeled w/ fixed bottom point fail b/c of bending moment transferred to columns frombeam (deflection & rotation).A B C|__|__|| |

Murali27 (Structural) 13May

096:33

Hi Seny

It may help by idealizing partial fixity to column B base (full moment capacity may not be achieved). I used to pinthe base of floating column and design the beam to absorb all the moment/shear. Nominal moments will betransferred to columns above or below. (may not be ideal if this is in seismic region).

Please also consider the construction sequence analysis (realistic way) for this transfer. It would help.

Hope the response is useful

seny (Structural) 13May

099:44

Computers and Structures: ETABS - Colums release and columns to bea... http://www.eng-tips.com/viewthread.cfm?qid=244785

2 of 4 7/29/2013 8:35 AM

Page 3: Computers and Structures_ ETABS - Colums Release and Columns to Beam Joint in Etabs

Hi Murali27,

As per real life i do not have concern about all three columns above since i can consider this situation as columnabove elastic footing and bottom end can b pinned.But as per Etabs modeling w/ all three columns above without release - all of them are failing and requiring bigreinforcement to govern bending from column & beam joint rotation.

ishvaaag (Structural) 14May

095:29

I have used may pinned assumptions in many buildings as murali over a transfer beam, and also at end of transferbeams, with entire success, and also seen amazing vierendeel behaviours (inversion of moments when a columnwas lacking in a tall building) and well, that's the nice property of continuity delivered by RC buildings, one can seeeven bombed buildings partially standing through continuities.

Then the question brought by Murali about construction sequence is also entirely meaningful; where I live (Spain)except some intelligent assumption sometimes standing in some programs, and except the only recentlymandatory checks to have proper formwork resistance, this is an issue that almost never appears. Given this, itseems that the current method used, classical one, seems enough to bring the buildings to proper safety IF you getto have them built. That is, a proper analysis of the sequence of loading may show things many would love not tosee, but that to some extent are (and for some kinds of buildings and kinds of sequences of construction anddetailings or are contemplated or will bring ruin).

Other than that, some programs seem to be quite esoteric in what they take care of or not (and the same happenswith some codes, that seem to be partisan for example to a slab with included beams respect those that passpunching without such: a flat plate unacceptable on punching without beams becomes magically acceptable onincluding them).

Vierendeel action over transfer beams uses to be detected by whole 3D models having the continuity embedded,and you can even play with the size of the transfer beam to get different proportions of members in elevation. Yetone must NEVER forget that these things, useful as they are are just MODELS of the structure, and the models onlyhave the intelligence we put within.

So, yes, I have also had cases of columns and beams failing in entire continuity and where the sometimes onlyamenable solution to the intent has been pinning something. It has proven to be a satisfactory solution as long therequirements of equilibrium and ways of passing the loads are met and any code issues of relevance have beencontemplated.

seny (Structural) 14May

098:57

thanks fro respond, ishvaaag.Building is flat slab, gravity column and shear walls taking lateral responsibility entirely - no beams, so there is noVierendeel trusses condition. In addition, slab is modeled w/ no out of plane stiff. What i topically do in this situation - ignore in model transferring of column and after based on forces obtainedfrom say Etabs calculate simple one bay beam to get bottom reinforcement and based on result provide inpercentage top reinforcement above the supporting ends columns and column calculation accordingly. It is enoughconservative way and i have already built structure w/ 25 storey transferred column.Beam is always overlapping supporting columns, so all the three columns above really can be pinned at the bottomand can be considered as above footing and do not require special reinforcement detailing efforts. I never usedpinned transfer beam since i am not comfortable w/ condition when beam is not overlaps in model the columns.

Computers and Structures: ETABS - Colums release and columns to bea... http://www.eng-tips.com/viewthread.cfm?qid=244785

3 of 4 7/29/2013 8:35 AM

Page 4: Computers and Structures_ ETABS - Colums Release and Columns to Beam Joint in Etabs

For me the main question was and is - in what way I can create in model the most "real" transferring conditions.In addition i will really appreciate if you can input a couple more words about your detailing in conditions when youhad pinned bottom of transferred (and ends?) columns or (and) pinned transfer beam.One more time thanks for respond.

Join | Jobs | Advertise | About Us | Contact Us | Site Policies

Copyright © 1998-2013 Tecumseh Group, Inc. All rights reserved.Unauthorized reproduction or linking forbidden without express written permission.

Engineering Degrees UKThe Foundation Courses At Bellerbys Prepare You To Achieve a Top Degree

isc.studygroup.com/bellerbys

Computers and Structures: ETABS - Colums release and columns to bea... http://www.eng-tips.com/viewthread.cfm?qid=244785

4 of 4 7/29/2013 8:35 AM