CBT architects
CANAL STREET HOTEL386 CANAL STREET NEW YORK, NY 10013
Cramer Brophy Tsinis Architects
The Bernard and Anne Spitzer School of Architecture
141 Convent Avenue New York, NY 10031
Design Critic: Martin Sitgsgaard
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
TITLE SHEET& GENERAL NOTES
A-001.00
SHEET LIST 1A-001
ADA REQUIREMENTS & LOCAL LAW DIAGRAMS 2A-001
SYMBOLS 3A-001
NOTES 4A-001
A-001.00 TITLE SHEET & GENERAL NOTES
A-002.00 ZONING ANALYSIS
D-101.00 DEMOLITION PLAN
A-101.00 SITE PLAN
A-102.00 CELLAR & GROUND FLOOR PLAN
A-103.00 2ND & 3RD FLOOR PLANS
A-104.00 4TH & 5TH FLOOR PLANS
A-105.00 6TH & 7TH FLOOR PLANS
A-106.00 8TH & ROOF FLOOR PLANS
A-107.00 GROUND FLOOR/TYPICAL ROOM FLOOR RCP
A-201.00 WEST BROADWAY ELEVATION
A-202.00 CANAL ST ELEVATION
A-203.00 CANAL ST CORNER ELEVATION
A-204.00 6TH AVE ELEVATION
A-205.00 SOUTH CORNER ELEVATION
A-30.00 6TH AVENUE SECTION
A-30.00 WEST BROADWAY SECTION
A-401.00 TYPICAL ROOM PART PLANS & ELEVATIONS
A-501.00 CORE STAIR DETAIL
A-50.00 RESTAURANT STAIR DETAIL
A-50.00 CURTAIN WALL SECTION A-50.00 CURTAIN WALL SECTION DETAIL6 6758&785$/',$*5$0)5$0,1*6 522)75866'(7$,/L-101.00 LANDSCAPE SITE PLAN
L-102.00 3RD FLOOR PLAZA LANDSCAPE PLAN
APDX 1 PROGRAM DIAGRAMS
APDX
APDX 3
SUSTAINABILITY DIAGRAMS
APDX 4
MEP DIAGRAM
APDX 5
MODEL PHOTOGRAPHS
APDX 6
RENDERINGS
APDX 7
STUDY MODELS
PDD & COST ESTIMATE
A
1A-401
3
4A-401
ELEVATION MARKER
SECTION CUT LINE
STRUCTURAL COLUMN GRID
ROOM LABEL & TAG
FINISHED FLOOR ELEVATION MARKER
EXTERIOR ELEVATION MARKER
DOOR TAG
DIMENSION LINE
DETAIL DRAWING CALL OUT
INTERIOR ELEVATION MARKER
NOTE: GC TO REFER TO INDIVIDUAL SHEETS FOR EXPANDED SYMBOL KEYS INDICATING FINISH MATERIALS, LIGHTING FIXTURES, ECT.
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
Patrick Brophy 12.12.14
1 : 1/16
DEMOLITIONPLAN
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
Patrick Brophy
1 : 1
D-101.00
6th
AV
EN
UE
CANAL STREET
WES
T BR
OAD
WAY
59'-0 516 "
1-' 617 16
"
65'-8
316
"
6'-7 116 "
109'
-91 8"
MTA Bus Shelterto be repositioned(Verify with MTA)
Remove andpreserve alltrees for reuse
Billboard mounted onbuilding to bedemolished with building
Remove allplanters andpaving
Remove andpreserve alltrees for reuse
PLP
L
24'-5
1 16"
24'-058"
24'-9 716 " Remove one story
masonry building
Property Line
Remove all of sidewalkto be replaced by pavers
Construction fence
YORK STREET
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
SCALE: 1 = 1/16
Patrick Brophy 12.12.14
1 : 1/16
SITE PLAN
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
SITE PLAN
SCALE: 1 = 1/
1A-101
Patrick Brophy
1 : 1
1A-10
A-101.00
6th
AV
EN
UE
CANAL STREET
WES
T BR
OAD
WAY
GC TO SEE SHEET L-101 FOR PAVER PATTERN
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
SCALE: 1 = 1/8
GROUND FLOOR PLAN
SCALE: 1 = 1/8
Patrick Brophy 12.12.14
1 : 1/8
CELLAR & GROUND FLOOR PLANS
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
CELLAR LEVEL PLAN
SCALE: 1 = 1/8
1A-102 SCALE: 1 = 1/8
Patrick Brophy
1 : 1/8
2A-102
1A-102
A-102.00
2A-503
1A-402
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
SECOND FLOOR PLAN
SCALE: 1 = 1/8
THIRD FLOOR PLAN
SCALE: 1 = 1/8
Patrick Brophy 12.12.14
1 : 1/8
SECOND & THIRDFLOOR PLANS
A-103.002
A-1032
A-103
2A-503
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
FOURTH FLOOR FINISH PLAN
SCALE: 1 = 1/8
FIFTH FLOOR PLAN WITH FURNITURE
SCALE: 1 = 1/8
Patrick Brophy 12.12.14
1 : 1/8
FOURTH & FIFTH FLOOR PLANS
A-104.001
A-1042
A-104
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
SIXTH FLOOR PLAN
SCALE: 1 = 1/8
SEVENTH FLOOR PLAN
SCALE: 1 = 1/8
11.6.14
Patrick Brophy 12.12.14
1 : 1/8
SIXTH & SEVENTHFLOOR PLANS
A-105.001
A-1052
A-105
1A-501
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
EIGTH FLOOR PLAN
SCALE: 1 = 1/8
ROOF FLOOR PLAN
SCALE: 1 = 1/8
11.6.14
Patrick Brophy 12.12.14
1 : 1/8
EIGTH & ROOF FLOOR PLANS
A-106.001
A-1062
A-106
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
GROUND FLOOR RCP
SCALE: 1 = 1/8
TYPICAL ROOM FLOOR RCP
SCALE: 1 = 1/8
Patrick Brophy 12.12.14
1 : 1/8
REFLECTED CEILING PLANS
A-107.001
A-1072
A-107
2A-401
8 5 AFF
7 5 AFF
8 5 AFF7 5 AFF
8 5
AFF
7 5
AFF
2A-402
5 0
-
CANAL STREET HOTEL386 Canal Street
New York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture
141 Convent Avenue
New York, NY 10031
Contact: Martin Stisgaard
Project Team
Architects
Ryan Cramer
Patrick Brophy
Lubov Tsinis
Structural Consultants
Ciro Cuono
Dominick Pilla
Sustainability Consultant
Ahu Aydogan
Zoning Consultant
Brian Gillen
MEP Consultant
Curt Rohner
Lighting Consultant
Peihing Tsai
Landscape Consultant
Taewook Cha
Spec Consultant
Jeff Feingold
Cost Estimating Consultant
Dave Miller
Design Consultant
Martin Stigsgaard
N o.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects
141 Convent Avenue, New York NY 10031
Drawn By Date
DateApproval By
Issued Date
Scale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
R. CRAMER 12/09/14
M. STIGSGAARD
08/28/14
1/8 = 1
WEST BROADWAY
ELEVATION
1WEST BROADWAY ELEVATION
1/8 = 1
120X12 GLAZED OPENING
12 REINFORCED CONCRETE WALL
WITH 4 PARAPET
Level 1
0' - 0"
Level 2
10' - 0"
Level 3
20' - 0"
Level 4
40' - 0"
Level 5
50' - 0"
Level 6
60' - 0"
Level 7
70' - 0"
Level 8
80' - 0"
Roof Level
90' - 0"
Mechanical Level
100' - 0"
Hat Truss
110' - 0"
I J K L 3
A-201.00
4X10 ALUMINUM AND GLASS PANEL CURTAIN WALL SYSTEM
CENTRAL CORE: 12 CONCRETE WITH EMBEDDED STEEL
COLUMNS CONNECTED TO HAT TRUSS
4X10 ALUMINUM AND GLASS PANEL CURTAIN WALL SYSTEM
42 ALUMINUM AND GLASS GUARDRAIL
POLYVINYL CHLORIDE ELECTRONICALLY OPERABLE
SOLAR LOUVER SYSTEM
STEEL W12X26 I BEAM HAT TRUSS STRUCTURAL
SYSTEM
-
CANAL STREET HOTEL386 Canal Street
New York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture
141 Convent Avenue
New York, NY 10031
Contact: Martin Stisgaard
Project Team
Architects
Ryan Cramer
Patrick Brophy
Lubov Tsinis
Structural Consultants
Ciro Cuono
Dominick Pilla
Sustainability Consultant
Ahu Aydogan
Zoning Consultant
Brian Gillen
MEP Consultant
Curt Rohner
Lighting Consultant
Peihing Tsai
Landscape Consultant
Taewook Cha
Spec Consultant
Jeff Feingold
Cost Estimating Consultant
Dave Miller
Design Consultant
Martin Stigsgaard
N o.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects
141 Convent Avenue, New York NY 10031
Drawn By Date
DateApproval By
Issued Date
Scale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
R. CRAMER 12/09/14
M. STIGSGAARD
08/28/14
1/8 = 1
CANAL STREET
ELEVATION1
CANAL STREET ELEVATION
1/8 = 1
Level 1
0' - 0"
Level 2
10' - 0"
Level 3
20' - 0"
Level 4
40' - 0"
Level 5
50' - 0"
Level 6
60' - 0"
Level 7
70' - 0"
Level 8
80' - 0"
Roof Level
90' - 0"
Mechanical Level
100' - 0"
Hat Truss
110' - 0"
3 M N O P Q
A-202.00
120X12 GLAZED OPENING
12 REINFORCED CONCRETE WALL
WITH 4 PARAPET
4X10 ALUMINUM AND GLASS PANEL CURTAIN WALL SYSTEM
CENTRAL CORE: 12 CONCRETE WITH EMBEDDED STEEL
COLUMNS CONNECTED TO HAT TRUSS
4X10 ALUMINUM AND GLASS PANEL CURTAIN WALL SYSTEM
42 ALUMINUM AND GLASS GUARDRAIL
POLYVINYL CHLORIDE ELECTRONICALLY OPERABLE
SOLAR LOUVER SYSTEM
STEEL W12X26 I BEAM HAT TRUSS STRUCTURAL
SYSTEM
-
CANAL STREET HOTEL386 Canal Street
New York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture
141 Convent Avenue
New York, NY 10031
Contact: Martin Stisgaard
Project Team
Architects
Ryan Cramer
Patrick Brophy
Lubov Tsinis
Structural Consultants
Ciro Cuono
Dominick Pilla
Sustainability Consultant
Ahu Aydogan
Zoning Consultant
Brian Gillen
MEP Consultant
Curt Rohner
Lighting Consultant
Peihing Tsai
Landscape Consultant
Taewook Cha
Spec Consultant
Jeff Feingold
Cost Estimating Consultant
Dave Miller
Design Consultant
Martin Stigsgaard
N o.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects
141 Convent Avenue, New York NY 10031
Drawn By Date
DateApproval By
Issued Date
Scale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
R. CRAMER 12/09/14
M. STIGSGAARD
08/28/14
1/8 = 1
NORTHWEST FACADE
ELEVATION
1NORTHWEST FACADE ELEVATION
1/8 = 1
Level 1
0' - 0"
Level 2
10' - 0"
Level 3
20' - 0"
Level 4
40' - 0"
Level 5
50' - 0"
Level 6
60' - 0"
Level 7
70' - 0"
Level 8
80' - 0"
Roof Level
90' - 0"
Mechanical Level
100' - 0"
Hat Truss
110' - 0"
4 1
A-203.00
12 REINFORCED CONCRETE WALL
WITH 4 PARAPET
4X10 ALUMINUM AND GLASS PANEL CURTAIN WALL SYSTEM
CENTRAL CORE: 12 CONCRETE WITH EMBEDDED STEEL
COLUMNS CONNECTED TO HAT TRUSS
4X10 ALUMINUM AND GLASS PANEL CURTAIN WALL SYSTEM
STEEL W12X26 I BEAM HAT TRUSS STRUCTURAL
SYSTEM
-
R. CRAMER 12/09/14
M. STIGSGAARD
08/28/14
1/8 = 1
6TH AVENUE
ELEVATION1
6TH AVENUE ELEVATION
1/8 = 1
CANAL STREET HOTEL386 Canal Street
New York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture
141 Convent Avenue
New York, NY 10031
Contact: Martin Stisgaard
Project Team
Architects
Ryan Cramer
Patrick Brophy
Lubov Tsinis
Structural Consultants
Ciro Cuono
Dominick Pilla
Sustainability Consultant
Ahu Aydogan
Zoning Consultant
Brian Gillen
MEP Consultant
Curt Rohner
Lighting Consultant
Peihing Tsai
Landscape Consultant
Taewook Cha
Spec Consultant
Jeff Feingold
Cost Estimating Consultant
Dave Miller
Design Consultant
Martin Stigsgaard
N o.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects
141 Convent Avenue, New York NY 10031
Drawn By Date
DateApproval By
Issued Date
Scale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
Level 1
0' - 0"
Level 2
10' - 0"
Level 3
20' - 0"
Level 4
40' - 0"
Level 5
50' - 0"
Level 6
60' - 0"
Level 7
70' - 0"
Level 8
80' - 0"
Roof Level
90' - 0"
Mechanical Level
100' - 0"
Hat Truss
110' - 0"
A B C D E F G H
A-204.00
120X12 GLAZED OPENING
12 REINFORCED CONCRETE WALL
WITH 4 PARAPET
4X10 ALUMINUM AND GLASS PANEL CURTAIN WALL SYSTEM
CENTRAL CORE: 12 CONCRETE WITH EMBEDDED STEEL
COLUMNS CONNECTED TO HAT TRUSS
4X10 ALUMINUM AND GLASS PANEL CURTAIN WALL SYSTEM
42 ALUMINUM AND GLASS GUARDRAIL
POLYVINYL CHLORIDE ELECTRONICALLY OPERABLE
SOLAR LOUVER SYSTEM
STEEL W12X26 I BEAM HAT TRUSS STRUCTURAL
SYSTEM
METAL LOUVERED VENTS 24X24
-
CANAL STREET HOTEL386 Canal Street
New York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture
141 Convent Avenue
New York, NY 10031
Contact: Martin Stisgaard
Project Team
Architects
Ryan Cramer
Patrick Brophy
Lubov Tsinis
Structural Consultants
Ciro Cuono
Dominick Pilla
Sustainability Consultant
Ahu Aydogan
Zoning Consultant
Brian Gillen
MEP Consultant
Curt Rohner
Lighting Consultant
Peihing Tsai
Landscape Consultant
Taewook Cha
Spec Consultant
Jeff Feingold
Cost Estimating Consultant
Dave Miller
Design Consultant
Martin Stigsgaard
N o.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects
141 Convent Avenue, New York NY 10031
Drawn By Date
DateApproval By
Issued Date
Scale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
R. CRAMER 12/09/14
M. STIGSGAARD
08/28/14
1/8 = 1
SOUTH FACADE
ELEVATION
A-205.00
1SOUTH FACADE ELEVATION
1/8 = 1
Level 1
0' - 0"
Level 2
10' - 0"
Level 3
20' - 0"
Level 4
40' - 0"
Level 5
50' - 0"
Level 6
60' - 0"
Level 7
70' - 0"
Level 8
80' - 0"
Roof Level
90' - 0"
Mechanical Level
100' - 0"
Hat Truss
110' - 0"
H I
STEEL W12X26 I BEAM HAT TRUSS STRUCTURAL
SYSTEM
4X10 ALUMINUM AND GLASS PANEL CURTAIN WALL SYSTEM
42 ALUMINUM AND GLASS GUARDRAIL
CENTRAL CORE: 12 CONCRETE WITH EMBEDDED STEEL
COLUMNS CONNECTED TO HAT TRUSS
CONCRETE STAIR: 7RISE, 11 TREAD
-
Level 1
0' - 0"
Level 2
10' - 0"
Cellar
-10' - 0"
Level 3
20' - 0"
Level 4
40' - 0"
Level 5
50' - 0"
Level 6
60' - 0"
Level 7
70' - 0"
Level 8
80' - 0"
Roof Level
90' - 0"
Mechanical Level
100' - 0"
Hat Truss
110' - 0"
Guestroom
405
Guestroom
505
Guestroom
604
Guestroom
705
Guestroom
805
Rooftop Bar
R-01
Guestroom
401
Guestroom
501
Guestroom
601
Outdoor Lounge
701
Guestroom
801
Balcony
604A
Balcony
705A
Balcony
805A
Balcony
405A
Balcony
505A
CANAL STREET HOTEL386 Canal Street
New York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture
141 Convent Avenue
New York, NY 10031
Contact: Martin Stisgaard
Project Team
Architects
Ryan Cramer
Patrick Brophy
Lubov Tsinis
Structural Consultants
Ciro Cuono
Dominick Pilla
Sustainability Consultant
Ahu Aydogan
Zoning Consultant
Brian Gillen
MEP Consultant
Curt Rohner
Lighting Consultant
Peihing Tsai
Landscape Consultant
Taewook Cha
Spec Consultant
Jeff Feingold
Cost Estimating Consultant
Dave Miller
Design Consultant
Martin Stigsgaard
N o.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects
141 Convent Avenue, New York NY 10031
Drawn By Date
DateApproval By
Issued Date
Scale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
R. CRAMER 12/09/14
M. STIGSGAARD
08/28/14
1/8 = 1
WEST BROADWAY
SECTION
A-301.00
1WEST BROADWAY SECTION
1/8 = 1
CENTRAL CORE: 12 CONCRETE WITH EMBEDDED STEEL
COLUMNS CONNECTED TO HAT TRUSS
12 CONCRETE SLAB
12X12 CONCRETE COLUMN
12 CONCRETE FOUNDATION WALL
24 CONCRETE SLAB ON GRADE FOUNDATION
STEEL W12X26 I BEAM HAT TRUSS STRUCTURAL
SYSTEM
W12X26 STEEL HANGERS
W12X26 STEEL FRAMING SYSTEM
-
CANAL STREET HOTEL386 Canal Street
New York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture
141 Convent Avenue
New York, NY 10031
Contact: Martin Stisgaard
Project Team
Architects
Ryan Cramer
Patrick Brophy
Lubov Tsinis
Structural Consultants
Ciro Cuono
Dominick Pilla
Sustainability Consultant
Ahu Aydogan
Zoning Consultant
Brian Gillen
MEP Consultant
Curt Rohner
Lighting Consultant
Peihing Tsai
Landscape Consultant
Taewook Cha
Spec Consultant
Jeff Feingold
Cost Estimating Consultant
Dave Miller
Design Consultant
Martin Stigsgaard
N o.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects
141 Convent Avenue, New York NY 10031
Drawn By Date
DateApproval By
Issued Date
Scale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
R. CRAMER 12/09/14
M. STIGSGAARD
08/28/14
1/8 = 1
6TH AVENUE SECTION
A-302.00
16TH AVENUE SECTION
1/8 = 1
CENTRAL CORE: 12 CONCRETE WITH EMBEDDED STEEL
COLUMNS CONNECTED TO HAT TRUSS
12 CONCRETE SLAB
12X12 CONCRETE COLUMN
12 CONCRETE FOUNDATION WALL
24 CONCRETE SLAB ON GRADE FOUNDATION
STEEL W12X26 I BEAM HAT TRUSS STRUCTURAL
SYSTEM
W12X26 STEEL HANGERS
W12X26 STEEL FRAMING SYSTEM
3 12 CONCRETE SLAB TERRACES
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
17 43 06 4
8 0
16 6
5 3 2 68 9
16 3
8 57 5
TYPICAL ROOM REFLECTED CEILING PLAN
SCALE: 1 = 1/2
TYPICAL ROOM WEST ELEVATION
SCALE: 1 = 1/2
TYPICAL ROOM EAST ELEVATION
SCALE: 1 = 1/2
TYPICAL ROOM NORTH ELEVATION
SCALE: 1 = 1/2
TYPICAL ROOM PLAN
SCALE: 1 = 1/2
12.12.14
Patrick Brophy 12.12.14
1 : 1/2
TYPICAL ROOM PLAN & ELEVATION
HEATPUMP
HEATPUMP
75 AFF85 AFF
TILE
CARPET
POINT LIGHT
VENTILATION
LED STRIP LIGHT
5 05 0
5 0
1A-401
2A-401
3A-401
4A-401
5A-401
8 5
A-401.00
3
4A-401
EXTERIOR LOUVER
GYPSUM ENCASED COLUMN
EXTERIOR GLAZING
WOOD FRAMING
LINE OF SOFFIT
WOOD DOOR
GYPSUM WALL
SLIDING WOOD DOOR CLOSET
LINE OF COLUMN BEYOND
RUBBER BASE
VANITY LIGHTING
EXTERIOR WINDOW BEYOND
MIRROR
MARBLE VANITYSTAINLESS STEEL SINK
GYPSUM
CARPETING
INTERIOR GYPSUM WALL
LED COVE LIGHTING
5A-401
-
5A-501
0'
- 11
3 /4"
3' - 2 3/32"
3'
-
0"
4'
- 3
7/32"
0
'
-
6
2
1
/
3
2
"
Level 10' - 0"
A-5013
7' - 3"
5
'
-
0
"
0
'
-
6
2
1
/
3
2
"
Level 10' - 0"
Level 210' - 0"
5A-501
0
'
-
6
2
1
/
3
2
"
3' - 0"
3
'
-
0
"
Level 10' - 0"
Level 210' - 0"
Cellar-10' - 0"
Level 320' - 0"
Level 440' - 0"
Level 550' - 0"
Level 660' - 0"
Level 770' - 0"
Level 880' - 0"
Roof90' - 0"
Core Top100' - 0"
Truss Top110' - 0"
1/4 = 11 CORE STAIRWELL PARTIAL PLAN
1 1/2" = 1'-0"3RAILING CONNECTION DETAIL
1/2" = 1'-0"2TYPICAL STAIR SECTION
1/2" = 1'-0"4TYPICAL STAIR ELEVATION
1/8" = 1'-0"5CORE STAIR SECTION THROUGH BUILDING
2
A-50
1
VERTICAL RAILING MEMBERS EMBEDDED
INTO PRECAST CONCRETE TREADS
12 CONCRETE SLAB LANDINGS
12 CONCRETE SHEAR WALL
CANAL STREET HOTEL386 Canal Street
New York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture
141 Convent Avenue
New York, NY 10031
Contact: Martin Stisgaard
Project Team
Architects
Ryan Cramer
Patrick Brophy
Lubov Tsinis
Structural Consultants
Ciro Cuono
Dominick Pilla
Sustainability Consultant
Ahu Aydogan
Zoning Consultant
Brian Gillen
MEP Consultant
Curt Rohner
Lighting Consultant
Peihing Tsai
Landscape Consultant
Taewook Cha
Spec Consultant
Jeff Feingold
Cost Estimating Consultant
Dave Miller
Design Consultant
Martin Stigsgaard
N o.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects
141 Convent Avenue, New York NY 10031
Drawn By Date
DateApproval By
Issued Date
Scale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
R. CRAMER 12/09/14
M. STIGSGAARD
08/28/14
AS NOTED
CORE STAIR DETAIL
A-501.00
8 RISERS @ 6 5/8 = 60
PRECAST CONCRETE STAIR
ALUMINUM PIPE HANDRAIL
OPEN TO
BELOW
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
Patrick Brophy
Various
12.12.14
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
RESTAURANT STAIR DETAIL
A-503.00
RESTAURANT SUSPENED CABLE STAIR ELEVATION
SCALE: 1 = 1/2
RESTAURANT SUSPENDED CABLE STAIR PARTIAL PLAN
SCALE: 1 = 1/2
1A-503
2A-503
SUSPENDED STAIR RISER DETAIL
SCALE: 1 = 1 1/2
3A-503
TREAD BOLT DETAIL
SCALE: 1 = 1
5A-503
SUSPENSION CABLE DETAIL
SCALE: 1 = 1
4A-503
STAINLESS STEELHAND RAIL
1/4 TENSION CABLE
OPEN RISE 3TIMBER TREADS
U PLATE BOLTED TO TIMBER TREAD
CONCRETE WALL
STEEL PIN BOLTED TO HEAD AND ADJACENT CONCRETE WALL
BOLT & WASHER SECURING U PLATE
OPEN RISE 3TIMBER TREAD
5A-503
TENSION CABLE
CABLE ATTACHMENT
SUSPENSION BOLT
CABLE HINGE
STEEL ANCHOR CONNECTION TO CONCRETE CEILING SLAB
4A-503
-
WALL SECTION
A-504
ECTIONWALL SE
A-504
EWALL SECTION
A-504
-
CURTAIN WALLSECTION DETAILS
A-505
-
ROOF TRUSS
S-102.00
LT
08/28/14
12/10/14
-
STRUCTURALFRAMING PLAN
S-101.00
FRAMING PLAN
S-101.00
STRUCTURAL
LT
08/28/14
11/19/14
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
SCALE: 1 = 1/16
Patrick Brophy 12.12.14
1 : 1/16
GROUND LEVELLANDSCAPE PLAN
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
GROUND LEVEL LANDSCAPE PLAN
SCALE: 1 = 1/
1L-101
Patrick Brophy
1 : 1
1 L-101.00
6th
AV
EN
UE
CANAL STREET
WES
T BR
OAD
WAYIMAGE GENERATED PAVER PATTERNGC TO SEE SHEET L-102
TYP. 5 PLANTERBOUNDARY DEFINEDBY IRREGULAR PAVERS
TYP. 4x8 UNIPAVERS
DENSE PATTERNINGAROUND ALL GUESTENTRANCES
THREE GRADATIONS IN TYP. UNIPAVER TO CREATEPIXELATED PATTERN
REPOSISTIONED MTA BUS SHELTER
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
SCALE: 1 = 1/8
Patrick Brophy 12.12.14
1 : 1/8
3RD FLOOR PLAZALANDSCAPE PLAN
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
3RD FLOOR PLAZA LANDSCAPE PLAN
SCALE: 1 = 1/
1L-102
Patrick Brophy
1 : 1
1
SCALE: N/A
UNIPAVER PATTERN DIAGRAM
SCALE:
2L-102 L-102.00
CONCRETE
4 X 8 UNIPAVER LIGHT TONE
4 X 8 UNIPAVER MEDIUM TONE
4 X 8 UNIPAVER DARK TONE
CONCRETE GRAND STAIR
40 CONCRETE PERIMETER WALL FORMEDBY EXTENSION GROUND FLOOR WALLS
PLANTER TOPOGRAPHY FORMED BY LIGHTWEIGHTSTACKED FOAM BELOW GROUND COVER
PLANTER BOUNDARY DEFINED BY IRREGULARPAVER PATTERN
TYPICAL 4X8 UNIPAVER, 3 GRADATIONSGC TO SEE DIAGRAM 2-L-102 FOR PAVER PATTERN
CONCRETE STADIUM SEATING AREA WITH 40 CONCRETE WALL PERIMETER AT EACH FFE
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
privateSTRUCTURE
PUBLIC
PRIVATE
cIRCULATION
PUBLIC
MECHANICAL/UTILITY
BACK OF HOUSE
STRUCTURE
BOH/mECHANICAL- 55 GUEST ROOMS- RESTAURANT & fULL KITCHEN- FITNESS CENTER- 3 SHARED LOUNGE SPACES- 5 PRIVATE BALCONIES- FULL FLOOR OUTDOOR LOUNGE- PRIVATE ROOFTOP BAR & lOUNGE
11.6.14
Patrick Brophy 11.6.14
AS NOTED
PROGRAMDIAGRAMS
APDX 1
-
ESTCODE
ESTCODE
ESTCODE
ESTCODE
ESTCODE
ESTCODE
ESTCODE
ESTCODE
ESTCODE
ESTCODE
ESTCODE
CANAL STREET HOTEL386 Canal Street
New York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture
141 Convent Avenue
New York, NY 10031
Contact: Martin Stisgaard
Project Team
Architects
Ryan Cramer
Patrick Brophy
Lubov Tsinis
Structural Consultants
Ciro Cuono
Dominick Pilla
Sustainability Consultant
Ahu Aydogan
Zoning Consultant
Brian Gillen
MEP Consultant
Curt Rohner
Lighting Consultant
Peihing Tsai
Landscape Consultant
Taewook Cha
Spec Consultant
Jeff Feingold
Cost Estimating Consultant
Dave Miller
Design Consultant
Martin Stigsgaard
N o.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects
141 Convent Avenue, New York NY 10031
Drawn By Date
DateApproval By
Issued Date
Scale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
R. CRAMER 12/09/14
M. STIGSGAARD
08/28/14
N.T.S.
M.E.P. SCHEMATIC
PLAN AND
AXONOMETRIC
APDX 4
1TYPICAL FLOOR M.E.P. LAYOUT
N.T.S.2
M.E.P. SCHEMATIC DIAGRAM
N.T.S.
EXHAUST AIR
SUPPLY AIR
M.E.P. VERTICAL SHAFT
HEAT PUMP
AIR HANDLING UNIT
COOLING TOWER
HEAT PUMP
BOILER
-
CANAL STREET HOTEL386 Canal Street
New York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture
141 Convent Avenue
New York, NY 10031
Contact: Martin Stisgaard
Project Team
Architects
Ryan Cramer
Patrick Brophy
Lubov Tsinis
Structural Consultants
Ciro Cuono
Dominick Pilla
Sustainability Consultant
Ahu Aydogan
Zoning Consultant
Brian Gillen
MEP Consultant
Curt Rohner
Lighting Consultant
Peihing Tsai
Landscape Consultant
Taewook Cha
Spec Consultant
Jeff Feingold
Cost Estimating Consultant
Dave Miller
Design Consultant
Martin Stigsgaard
N o.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects
141 Convent Avenue, New York NY 10031
Drawn By Date
DateApproval By
Issued Date
Scale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
R. CRAMER 12/09/14
M. STIGSGAARD
08/28/14
N.T.S.
FINAL MODEL
APDX 4
-
CANAL STREET HOTEL386 Canal Street
New York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture
141 Convent Avenue
New York, NY 10031
Contact: Martin Stisgaard
Project Team
Architects
Ryan Cramer
Patrick Brophy
Lubov Tsinis
Structural Consultants
Ciro Cuono
Dominick Pilla
Sustainability Consultant
Ahu Aydogan
Zoning Consultant
Brian Gillen
MEP Consultant
Curt Rohner
Lighting Consultant
Peihing Tsai
Landscape Consultant
Taewook Cha
Spec Consultant
Jeff Feingold
Cost Estimating Consultant
Dave Miller
Design Consultant
Martin Stigsgaard
N o.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects
141 Convent Avenue, New York NY 10031
Drawn By Date
DateApproval By
Issued Date
Scale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
R. CRAMER 12/09/14
M. STIGSGAARD
08/28/14
1/8 = 1
EXTERIOR AERIAL
RENDERING
APDX 5 - 01
EXTERIOR DAYTIME AERIAL RENDERING
N.T.S.1
-
CANAL STREET HOTEL386 Canal Street
New York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture
141 Convent Avenue
New York, NY 10031
Contact: Martin Stisgaard
Project Team
Architects
Ryan Cramer
Patrick Brophy
Lubov Tsinis
Structural Consultants
Ciro Cuono
Dominick Pilla
Sustainability Consultant
Ahu Aydogan
Zoning Consultant
Brian Gillen
MEP Consultant
Curt Rohner
Lighting Consultant
Peihing Tsai
Landscape Consultant
Taewook Cha
Spec Consultant
Jeff Feingold
Cost Estimating Consultant
Dave Miller
Design Consultant
Martin Stigsgaard
N o.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects
141 Convent Avenue, New York NY 10031
Drawn By Date
DateApproval By
Issued Date
Scale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
R. CRAMER 12/09/14
M. STIGSGAARD
08/28/14
1/8 = 1
ROOFTOP
BAR/LOUNGE
RENDERING
APDX 5 - 02
N.T.S.1ROOFTOP BAR/LOUNGE DAYTIME RENDERING
-
CANAL STREET HOTEL386 Canal Street
New York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture
141 Convent Avenue
New York, NY 10031
Contact: Martin Stisgaard
Project Team
Architects
Ryan Cramer
Patrick Brophy
Lubov Tsinis
Structural Consultants
Ciro Cuono
Dominick Pilla
Sustainability Consultant
Ahu Aydogan
Zoning Consultant
Brian Gillen
MEP Consultant
Curt Rohner
Lighting Consultant
Peihing Tsai
Landscape Consultant
Taewook Cha
Spec Consultant
Jeff Feingold
Cost Estimating Consultant
Dave Miller
Design Consultant
Martin Stigsgaard
N o.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects
141 Convent Avenue, New York NY 10031
Drawn By Date
DateApproval By
Issued Date
Scale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
R. CRAMER 12/09/14
M. STIGSGAARD
08/28/14
1/8 = 1
LOBBY RENDERING
APDX 5 - 03LOBBY NIGHT RENDERING
N.T.S.1
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
STUDY MODELS
APDX 6
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
PPD
APDX -001
A SUBSTRUCTURE
A10 FOUNDATIONS
A1020 Mat Foundations
A. A 2 foot thick mat foundation is being proposed to adequately support the structural load of the building. This foundation is subject to approval after consultation with the MTA.
A20 SUBGRADE ENCLOSURES
A2010 Walls for Subgrade Enclosures
A. Basement walls will house below grade cellar level. Walls will measure 12 inches thick Below grade.
10 PROJECT DESCRIPTION
1000 Project Introduction
A. The Project Design Description is intended to outline the general scope, building systems, project standards and reference applicable codes to be used as the basis for developing the schematic, design development and construction documents. It is also intended to compliment the various drawings issued by the design team.
1. This document shall serve the following additional purposes:
2. Document specific design direction that the design team has receivedfrom the Owner.
3. Document specific design assumptions or recommendations of thedesign team where the Owner has not given specific direction.
4. Identify and document other sources of design direction such as buildingcode authorities and zoning regulations.
5. This document is intended to furnish information to the Owner toestablish an estimated cost of construction for the project as it ispresently envisioned.
B. This PPD represents the scope of work by CBT Architects.
1010 Project Summary
A. The Project will provide a prominent address for the Spitzer School of Architecture. CBT Architects is responsible to enhance, articulate and deliver the vision established by the Spitzer School of Architecture.
B. The Project is located in New York City. The site is triangular and bordered by 6th Avenue on the West side, W Broadway on the East side, and Canal St on the North side.
C. The building will be 120 tall, with 8 floors above grade, an occupiable roof and 1 cellar floor.
1020 Project Program
A. Reception/Lobby 1. The hotel will have a ground floor lobby at the first floor with an entrance on W
Broadway. The main hotel lobby and reception will be located on the first floor on theeast side of the building. The ground floor and second floor will have a bar andrestaurant. Floors 5, 6, 7, and 8 will have additional lounge spaces.
B. Entertainment, Meeting and Events space 1. Level 3 will have a full floor outdoor space which will act as additional
lounge space to be landscaped accordingly
2. In addition to the restaurant located on the first and second floor, the roofwill feature an outdoor bar
B10 SUPERSTRUCTURE
B1010 Floor Construction
A. Gravity structural options studied: Engineer has studied several different optionsprior to the Schematic Design issue on date. Options studied include:
a. Concrete Slab Structure with typical column grid spaced an average of 24 ftapart
b. Outrigger System utilizing steel trusses.
c. Steel Hat Truss System utilizing hangers and steel framing on levels 4-8 andtwo way concrete slab with typical column grid on levels C-3
d. Suspended slab system using pretension concrete slabs tie into concreteshear walls of core.
B. Lateral structural options studied: Engineer has studied the following prior to theschematic design issue on date.
a. Concrete shear walls.
b. Cables bolted to foundation to brace lateral loading
C. Structural option chosen: After reviewing the above options with the architect andthe owner, the structural option chosen for the schematic design issue on 11.3.14was a steel Hat Truss System utilizing hangers and steel framing on levels 4-8 andtwo way concrete slab with typical column grid on levels C-3. The lateral structuralsystem is concrete shear walls at the core.
D. The structure was designed to conform per the following building codes:
a. The structure is designed per the 2008 Building Code of the City of New York,including latest amendments.
b. American Institute of Steel Construction Specification for Structural SteelBuildings.
c. American Concrete Institute Building Code Requirements for StructuralConcrete
E. Design criteria - The structural system shown was designed for the followingloading:
a. Dead Load = Self weight of the building
b. Superimposed Load = 30 pounds per square foot
c. Faade Load = 200 pounds per linear foot
Live Load = 50 pounds per square foot
B20 EXTERIOR VERTICAL ENCLOSURES
B2010 Exterior Walls
A. Description: The main residential core of the building (Levels 4-8) will feature a glass curtain wall withoperable photovoltaic louvers on the West, North East, and South East Faade.Unobstructed glass curtain walls with mullions will be on the North, South, and lower levelexterior walls. The exposed core on level 3 in the center of the building, will be comprisedof concete.
B. Functional Requirements: The Horizontal Photovoltaic louvers will be attached to the glass curtain wall and beoperable to maximize daylighting and solar gain within the building, as well as aid indirecting wind hitting the faade of the building. Each lover will be custom shaped creatingto create the appearance of an undulating surface along the faade of the building. Inaddition to varying the dimensions of the lovers, the frequency at which they occur will bedetermined by the intensity of sunlight on the given faade, ranging from a spacingbetween 2 and 4 feet. The opacity of the glass pane will fluctuate between lovers to createa more dynamic lighting effect across the faade.
C. Components: The Horizontal Photovoltaic louvers will be attached to the glass curtain wall systemcomprised of 4 x 10 double pane glass panels measuring approximately 1 inch thick. ThePhotovoltaic louvers measure approximately 10 by 8-18 with a thickness of 1. The depthof each louver will fluctuate between 8 and 18 to create an undulating surface. The louverswill be made of glass with photovoltaic panels on one side to maximize energy gain to thebuilding.
B2010.10 Curtain Wall Assemblies
B2050 Exterior Doors and Grilles
B2050.10 Exterior Doors
A. Description: Entry doors consist of 12 mm minimum thickness clear low-iron glass mounted into customprofile rails and ultra-narrow stiles of extruded aluminum clad with stainless steel sheet.Doors include center pivots and door closer, full-height stainless steel pulls, self-drainingstainless steel threshold, swing door operator with handicap actuator and all otherhardware required for a complete and serviceable assembly.
B2070 Exterior Louvers
A. Description: a. Combines the functions of solar shading with the generation of electrical power.b. From Colt Shadovoltaic Louver Product InfoShadovoltaic describes a fixed or controllable external solar shading system that
incorporates glass louvres with photovoltaic cells integrated into the glass so as to generateelectricity at the same time as providing shading. The louvres are available in various colours,surface finishes, patterns and coatings to meet specific design requirements. Both monocrystallineand polycrystalline cells may be used. The photovoltaic cells may be integrated into the glass,either by attaching them onto the reverse side of the glass panels or by laminating them betweentwo sheets of glass.
B30 EXTERIOR HORIZONTAL ENCLOSURES
B3010 Roofing
A. Roofing System 01 (RS01) - Membrane Roofing Assembly shall be constructed as an inverted roof membrane assembly (IRMA). The system will be comprised of the following:
1. Wearing Surface:
a. Precast pavers of thickness to resist insulation flotation and uplift due tonegative wind pressures. Pavers shall be high albedo type.
b. Roofing Aggregate (where applicable): ASTM D448, Size No. 57; clean,rounded water worn gravel or stone, white color, well graded with an averagesize of 1 in, with no more than 10% of fines or stones smaller than 3/4 in..
2. Water pervious filter fabric
3. Protection sheet
4. Reinforcing sheet
5. Insulation: Extruded polystyrene board with water drainage channels. Thicknessas required to achieve required U values
6. Roof Membrane System: Two-coat seamless reinforced hot rubberized asphalt(180 mil thick), Liquid Membrane 6125FR by American Hydrotech or equal
B. Prefabricated Metal Flashing System: 16 gauge stainless steel type 304 flashing with2B finish, in strict compliance with manufacturers fabrication requirements.
1. Pipe Penetration
a. Form a tubular flashing sleeve no less than 9 in. high and of proper diameterto provide minimum 1/8 in. and 1/4 in. maximum clearance from pipe orconduit.
b. Fabricate square flashing plate to a size 7 in. larger than protrusion. Punchhole out of appropriate size in center and extrude surrounding materialupward 1/4 in. providing a continuous vertical soldering flange and solder 9in. high tubular flashing sleeve. Cut 1 in. minimum radius on flashing platecorners.
c. Fabricate counter flashing 5 in. high with a diameter 1/2 in. to 2 inches larger.
d. Shop solder all seams water tight
2. Column and beam flashings
a. Form a 6 in. high 2 piece angular configuration similar to penetration butallowing 3/16 in. to 3/8 in. maximum clearance in any direction. Fabricate
C10 INTERIOR CONSTRUCTION
C1010 Interior Partitions
A. Applicable Standards Include
1. American Society for Testing and Materials (ASTM):
a. ASTM C645: Standard Specification for non structural steel framingmembers
b. ASTM C754: Standard Specification for Installation of Steel FramingMembers to Receive Screw-Attached Gypsum Panel Products
c. ASTM C840: Standard Specification for Application and Finishing ofGypsum Board
d. ASTM C919: Standard Practice for Use of Sealants in AcousticalApplications
e. ASTM C1396: Standard Specification for Gypsum Board
1. Gypsum Association (GA):
a. GA-214: Recommended Specification: Levels of Gypsum Board Finish
b. GA-216: Application and Finishing of Gypsum Panel Products
c. GA-600: Fire Resistance Design Manual
2. Provide fire-rated interior partition assemblies as required by code.
A. Performance Requirements
1. All interior partitions shall meet required STC rating.
2. All interior partitions must meet required fire ratings
B. Fixed Partitions
1. Gypsum Board Systems: Interior framed partitions, shaft enclosures, columnenclosures.
a. Framing Systems: Roll-formed galvanized steel, size, gauge and assemblyrequired to conform to all fire-rating and acoustical requirements.
1) Runners
2) Metal Studs
3) Furring (Hat) Channels
4) Furring Brackets
5) Resilient Channel
6) Metal Furring Strips
7) Sheet Metal Grounds
8) Corner Angles and Elevator Jamb Struts
9) Miscellaneous Framing Accessories
b. Gypsum Board Materials:
1) Gypsum Board
2) Gypsum Shaft Liner Board, Backing Board and Core board
c. All gypsum wallboard installed in toilet rooms and locker rooms shall be bothof water-resistant and mold resistant type.
C1040 Stair construction
A. Applicable Standards Include
1. ASTM E985 "Standard Specification for Permanent Metal Railing Systems andRails for Buildings".
2. American Welding Society (AWI)
a. AWS D1.1 "Structural Welding Code".
b. AWS D1.2 "Structural Welding Code -Sheet Steel"
3. National Association of Architectural Metal Manufacturers (NAAMM)
a. ANSI/NAAMM MBG 532 "Heavy Duty Metal Bar Grating Manual."
b. NAAMM "Pipe Railing Manual".
c. NAAMM "Metal Stairs Manual".
4. SSPC "Steel Structures Painting Manual, Volume 2, Systems andSpecifications".
5. Industrial Fasteners Institute "Fastener Standards Book".
6. Comply with requirements of ANSI A14, 13, A58.1
B. Performance Criteria
1. Treads and Platforms: Provide stairs and platforms to support a live load of notless than 100 lbs. psf and a concentrated load of 300 lbs. on an area of 4 sq. in.whichever produces the greater stress. Limit deflection of treads, platforms, andframing members to L/360 or 3/4 in. Stair framing shall be capable ofwithstanding stresses resulting from loads specified above in addition to stressesresulting from railing system loads.
2. Railings and Handrails: Installed handrails and supports shall withstand a 200 lb.load applied at any point, downward or horizontally or the simultaneousapplication of a lateral force of 40 plf and a vertical force of 50 plf, both applied atthe top of the railing; the more stringent requirement governing.
C. Stair Treads, Risers and Landings
1. FOH Feature Stair TBD
2. BOH Internal Communication Stairs:
a. Concrete Filled Steel Pan-Type Stairs: Provide metal stairs system designedwith steel channel stringers with open pans (treads and risers) fabricated toreceive concrete fill and concrete filled intermediate landings, and steel sheetrisers.
3. Miscellaneous stairs and ladders for BOH and MEP spaces:
C2010 WALL FINISHES:
C2010.001 CERAMIC TILE
A. Description: Ceramic tile wall finish including but not limited to:
1. Shower and Toilet areas
2. Food & beverage production areas: main kitchen, food preparation, specialtyrestaurant kitchen.
B. Functional requirements:
1. Comply with the Tile council of America (TCA) Handbook for ceramic tileinstallation, materials, workmanship and installation, tile and stone installation.
C. Components:
1. Ceramic Tile2. Waterproof membrane3. Crack isolation membrane4. Tile backing panels
C2010.002 EPOXY PAINT
A. Description: Epoxy Paint wall finish for:
1. Locker/Change Areas [Edition module 8B.6]
2. Soiled Linen Storage Sorting Room [module 11B.4]
3. Washing/ Clean Linen Storage/ Uniform Issue [modules 11B.5, 11B.10 &11B.12]
4. Food & Beverage Production- Dry Storage [module 10.14]
5. Banquet Pantries [module 10.22]B. Functional requirements:
C. Components:
C2010.003 VINYL WALL COVERING
A. Vinyl Wall covering for:
1. Administration Facilities [module 8A.1-8A.2]
2. General Offices [module 8A.4]
3. Accounting Offices [module 8A.6]
B. Functional Requirements:
C. Components:
C2010.004 PAINT
A. Paint for:
1. Engineering/ Maintenance Shops and Offices
2. MEP Spaces
B. Functional Requirements
C. Components:
C2010.005 FIRE RESITANT FIBERGLASS PANEL (FRFP)
A. Description: Glass Fiber Reinforced Plastic paneling for
1. Food & Beverage Production- Main Kitchen/ Preparation Area/ SpecialtyRestaurant Kitchen [module 10.14]
B. Functional Requirements:
C. Components:
C2050 Ceiling Finishes
C2050.001 GYPSUM BOARD - PAINTED (GWBXX)
A. Description: Ceiling Board: a 5/8 non-sag gypsum board product designed forceilings or alternatively, Sheetrock brand Ultra Light panels as manufactured byUSG or equivalent.
B. Functional Requirements: support at 2ft to avoid deflection.
C2050.002 ACCESSIBLE ACOUSTICAL TILE (CLGXX)
A. Description: Accessible acoustical tile will be installed in the following areas:
1. Locker/Change Areas
2. Administration Facilities
3. General Offices
4. Accounting Offices
5. Employee Dining
6. Purchasing and Receiving Offices
7. Soiled Linen Storage/ Sorting Room
8. Washing/ Clean Linen Storage/ Uniform Issue
9. Food & Beverage Production- Main Kitchen/ Preparation Area/ SpecialtyRestaurant Kitchen
10. Food & Beverage Production- Dry Storage
11. Food & Beverage Production- Non Food Storage
12. Banquet Pantries
B. Functional requirements:
C. Components:
1. Accessible acoustical tile2. Accesible Washable Tile3. Corrosion resistant grid4. Corrosion resistant support
C2050.003 EXPOSED (EXP)
A. Description: The following ceilings for Back of house areas as well as egress stairswill be left with an exposed structure and painted.
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
PPD
APDX -002
D20 PLUMBING
D2010 Domestic Water Distribution
A. Description:
1. Utility Services2. Domestic Cold Water System
3. Domestic Hot Water System
a.) Domestic hot water will be generated by gas fired storage type waterheaters as described below:
1.) 2 heaters at cellar level for floors C through 3 2.) 2 heaters at roof level for floors 4-8
D2020 Sanitary Drainage
D2025 Storm Drainage System
D2026 Gas System
A. Description:
1. Utility Service
D2030 Building Support Plumbing Systems
A. Description:
1. Complete cold and hot water distribution system serving all building fixtures andequipment requiring water.
B. Functional Requirements:
C. Components:
1. The components will consist of but not limited to piping, fittings, valves, gauges,hangers and supports, sleeves and escutcheons, insulation, etc.
D30 HEATING, VENTILATION AND AIR CONDITIONING (HVAC)
D3010 Facility Fuel Systems
D3020 Heating Systems
A. Description:
1. A central hot water will produce hot water for building space heating. The plantwill consist of high efficiency hot water boilers, hot water pumps and a hot waterpiping distribution system. The boiler plant will be located on the cellar level.
B. Functional Requirements: 1. A central hot water will produce hot water for building space heating. The plant
will consist of high efficiency hot water boilers, hot water pumps and a hot waterpiping distribution system. The boiler plant will be located on the cellar level.
B. Functional Requirements:
2. A central hot water boiler will produce hot water for building space heating.
D3030 Cooling Systems
A. Description:
1. Cooling for the building will be from a cooling tower placed on the roof levelmechanical space
B. Functional Requirements:
1. Cooling for the building will be from a central refrigeration plant that will generatechilled water for delivery to the hotel and support portions of the building.
C. Components:
1. Cooling Tower
D3050 Facility HVAC Distribution Systems
A. Description:
1. Air conditioning for the different areas will be provided by air conditioning units,fan coil units, etc.
B. Functional Requirements:
1. The air conditioning requirements will meet the Marriott Module 15 requirementsand ASHRAE Standard 90.1-2007.
C. Components:
1. Hotel Guest Room Air Conditioning System
2. Common Hotel Area Air Conditioning System
D3060 Ventilation
A. Description:
1. The ventilation for the different areas will be provided by dedicated outside airconditioning units, exhaust fans, etc.
B. Functional Requirements:
C. Components:
1. Hotel guest room air conditioning system
a.) Each hotel room will be supplied with tempered and dehumidifiedventilation air at 35 cfm from central ventilation air handling units with energy recovery.
b.) Corridors will be supplied with 100% outdoor air from central corridorventilation units with energy recovery at 2 air changes per hour.
2. Central Ventilation Air Handling Units with Energy Recovery (Hotel Corridors andHotel Guest Rooms)
a.) 100% outdoor air ventilation unit will be located on the roof.
b.) Units will provide ventilation air to hotel guest rooms and hotel corridors.
c.) Each central ventilation air unit will be an energy recovery units with supply fan, exhaust fan, enthalpy wheel for energy recovery, MERV 13 filter (with MERV 8 pre-filter), VFDs for supply and exhaust fans, cooling coil and heating coil with freeze protection circulation pump.
d.) Unit shall exchange sensible and latent heat between outside air and toilet exhaust.
3. Toilet Exhaust System (Public)
a.) Toilet exhaust systems shall be installed with exhaust fans, registers, dampers and ductwork. Air exhaust shall be a minimum of 50 cfm per water closet.
b.) A Locker Room exhaust system shall be provided for the fitness/spa locker room. Exhaust system shall be installed with exhaust fans, registers, dampers and ductwork. Air exhaust shall be a minimum of 2 cfm/sf.
4. Toilet Exhaust Systems (Hotel Guest Rooms)
a.) A toilet air riser for each toilet shall extend vertically through the floors and ventilate each toilet. Each toilet room will be provided with a two position constant airflow regulator (CAR) damper which will exhaust 50 cfm in the high flow mode and 25 cfm in the low flow mode. The high mode will be initiated when the bathroom lights are turned on.
b.) Toilet exhaust connection to riser will be accomplished utilizing a 22 sub duct for exhaust risers that exhaust upward and fire dampers where exhaust flow is downward.
c.) Each riser will bring the toilet exhaust to the exhaust side of a central energy recovery unit.
1. Commercial Kitchen Exhaust
a.) Kitchen exhaust and mechanical equipment will be located directly above kitchen on level 2 and comply with all standards for ventilation.
2. Miscellaneous
a.) Elevator machine rooms will be mechanically cooled and smoke venting will be provided with exhaust fan controlled by smoke detector.
b.) Ventilation for switchboard and transformer rooms, pump rooms, emergency generator and mechanical rooms shall be provided.
c.) Provide exhaust systems for locker rooms, electrical rooms, employee cafeteria, laundry chute room, housekeeping, vending rooms, etc.
d.) Provide heating for the entrance vestibule, loading dock, stairs, etc.
e.) Provide heat tracing system for all piping subject to freezing.
f.) Provide secondary drip pans with float switch for all horizontal fan-coil units.
D40 FIRE PROTECTION
D4010 Fire Protection
A. Description:
1. The Fire standpipes and combination standpipe/sprinkler systems are provided asper 2008 NYC Building code Chapter 9, Appendix Q, NFPA 13, 2002 edition andNFPA 14, 2003 edition. The facility consists of two zones: high-zone and low-zone. This building is R-1 occupancy. Marriot Design standards are to be providedin accordance with local codes. Fire pump to be connected to emergency powersystem.
A. Functional Requirements:
1. The source of supply for the low-zone standpipe system is via a 1000 GPMAutomatic Fire pump located in Cellar C-2. The automatic fire pump is supplied byone 6 fire service from 7th Avenue and one 6 fire service from 45th Street. Thehigh-zone and low-zone standpipe systems are interconnected in the Cellar C-2level. The high-zone is furnished with fire reserve tank capacity of 30,000 gallons,15,000 gallons in two tanks, and special service fire pump. Primary water supplyfor each tank is supplied by a dedicated tank fill line that feeds the buildingdomestic water system also. The special service fire pump for high-zone is locatedon Mech level 1 of the hotel. The pump is rated at 750 GPM and will pressureboost the upper portion of the combined fire standpipe/sprinkler system.
B. Components:
1. Fire Standpipes and Combination Fire/Sprinkler standpipe and sprinkler risers arelocated within fire rated stair enclosures. At each floor level at stair landing, thereis a fire hose valve, sprinkler connection with branch valve and tamper switch,water flow alarm indicator and inspectors test connection
D4030 Fire Protection Specialties
A. Description:
1. This building contains several occupancies that will be designed for eachseparately in each fire rated area.
B. Functional Requirements:
1. Sprinkler demand will be calculated based on occupancy and use classificationindicated in the New York City Building laws, as follows:
a.) Light Hazard - Hotel rooms, corridors, gymnasium, restaurant seatingarea, and lobbies, are designed for a density of 0.10 GPM/Sq. Ft. /minimum per apartment or in 1500 sq. ft. Quick response heads to beinstalled in light hazard areas.
b.) Ordinary Hazard (Group 1) - Storage, commercial kitchen, and mechanicalrooms are designed for a density of 0.15 GPM/Sq. Ft. / minimum in 1,500sq. ft.
C. Components:
1. Sprinklers specified for different hazard areas shall not be mixed in the same firearea.
2. Smoke Exhaust
a.) The smoke control systems comply with Marriott Design Standards Module 14, NFPA 92, and NYC Building Code 2008 Section 909 for life safety purposes.
b.) Mechanical smoke exhaust is required in all public areas, including the guestroom corridors, pre-function, meeting rooms, ballrooms, lobby, restaurant, nightclub, etc. to comply with Marriott Module 14 and NYC Building Code 2008 section 909 Smoke Control System in its entirety. A manual post fire smoke purge system is not acceptable.
b.) The smoke exhaust system must activate by both area smoke detectors and water flow alarms-independent from each other on guestroom floors. On non-guestroom floors, the smoke exhaust system must activate by area smoke detectors.
c.) The smoke exhaust system for the different spaces can be achieved by a series of exhaust fans located at the floor. The fans will connect to a plenum that will connect to a louver. The exhaust fans will be emergency power system.
d.) The air intake for the smoke exhaust system will be through either motor operated louvers located or make-up air fans and will be on emergency power system.
a.) Manual fire alarm pull stations must not activate the smoke exhaust system.
b.) A manual override is required.
3. Stair Pressurization
a.) The mechanical pressurize stairwells are in compliance with The Life Safety Code, NFPA 101. The stair pressurization system must have a pressure difference across the barrier of not less than .05 in. water column.
b.) The stairs will be provided with a stair pressurization system. Each stair will have two (2) fans located on the 10th floor mechanical room and the roof mechanical room.
D50 ELECTRICAL
D5020 Electrical Service and Distribution
A. Description:
1. The electric power distribution system shall include all the elements necessary toconduct electricity in an approved, safe manner to all lighting fixtures, airconditioning equipment, sanitary equipment, kitchen equipment, elevators,appliance outlets, and signal and communication equipment.
D5030 General Purpose Electrical Power
A. Description:
1. General convenience receptacles shall be provided as required based onarchitectural furniture plans.
C. Components:
1. General convenience receptacles on code prescribed spacing will be provided ineach hotel room including ground-fault interrupting protection on bathroomreceptacle(s).
2. Separate circuits will be provided for hotel room fan coil units.
3. Utility receptacle outlets for cleaning purposes and the like in public halls spacedno more than 50 feet apart.
4. Individual appliance outlet for each ice machine and vending machines in hotelfloor common spaces where required.
D5040 Lighting
A. Description:
1. Lighting fixtures shall be furnished and installed throughout the project. Alllighting fixtures and lighting control systems comply with the Energy Codeshaving jurisdiction.
D5030 General Purpose Electrical Power
A. Description:
1. General convenience receptacles shall be provided as required based onarchitectural furniture plans.
C. Components:
1. General convenience receptacles on code prescribed spacing will be provided ineach hotel room including ground-fault interrupting protection on bathroomreceptacle(s).
2. Separate circuits will be provided for hotel room fan coil units.
3. Utility receptacle outlets for cleaning purposes and the like in public halls spacedno more than 50 feet apart.
4. Individual appliance outlet for each ice machine and vending machines in hotelfloor common spaces where required.
D5040 Lighting
A. Description:
1. Lighting fixtures shall be furnished and installed throughout the project. Alllighting fixtures and lighting control systems comply with the Energy Codeshaving jurisdiction.
1. Lighting fixtures shall be furnished and installed throughout the project.
a.) Lighting consultant / others will specify all indoor and outdoor lighting for all areas other than back-of-house", for the project.
b.) Emergency lighting will be provided in stairs.
c.) All lighting fixtures shall be in compliance with New York State Energy Code.
D5080 Miscellaneous Electrical Systems
A. Description:
1. Fire Alarm
a.) An addressable manual and automatic Fire Alarm System will be providedfor the building as required by the New York City Building Code,
B. Components:
1. Fire Alarm
a.) All fire alarm system cabling will be installed in conduit, except wherepermitted by Code. Minimum conduit size shall be 3/4. Risers shall be
a.) The main fire alarm control panel (FACP) will be located at the mainentrance lobby the main fire alarm control panel is installed in an areamonitored by a hotel personnel at all times. In addition, the systems willconsist of a remote annunciators, Data Gathering Panels, manual pullstations, area and duct smoke detectors, heat detectors, audible(speakers) and visible (strobes) devices, two-way fire departmentcommunication devices, auxiliary devices and equipments and allinterconnected wiring.
b.) Area smoke detectors are required in all public common areas formechanical smoke exhaust activation such as lobbies, restaurant, meetingroom/ballroom, public corridors, etc.
c.) Area smoke detectors will be provided in top of elevator shafts, elevatormachine rooms, and all mechanical, electrical and telephone equipmentrooms. Weatherproof type fire alarm devices are required in allunconditioned areas.
d.) Ensure all guestroom smoke detectors are system photoelectric type withsounder bases. The smoke detectors must only sound a local alarm andreport back to the fire alarm panel with the exact location.
e.) Duct mounted smoke detectors will be provided for the air distributionsystem per NYC Mechanical Code.
a.) Manual pull stations will be provided not more than 5 feet from entranceto each exit.
b.) Sprinkler system water-flow switches and tamper switches will beconnected to the fire alarm system via addressable monitoring modulesfor alarm and trouble indication.
c.) ADA compliant strobes will be provided in common use and public areasand large mechanical and electrical rooms, and selected hotel guestrooms.
d.) Emergency voice/alarm communication devices will be provided atelevator lobbies, corridors, rooms and tenant spaces exceeding 1,000square feet, hotel guest rooms, areas of rescue assistance and stairwells.
e.) Generator, fire pumps and fire water storage tanks (if required for thisproject) will be monitored by the fire alarm system via addressablemodules.
f.) The Fire Alarm System will be connected to the Central Monitoring Station.
g.) Ensure a fire alarm speaker is installed in all guestroom sleeping areas forgeneral alarm notification purposes. Hearing-impaired guestrooms musthave a speaker/strobe in the sleeping area and a single strobe in thebathroom. The strobe must be programmed to activate upon local andgeneral alarm.
h.) Install magnetic door hold open devices for all meeting room/ballroomentry doors serving the public corridor. The magnetic door hold opendevices must be monitored by the fire alarm control panel and releaseupon general fire alarm with its associated zone.
i.) Provide signal circuit and auxiliary function disconnect capability byindividual disconnect/disabled buttons at the fire alarm control panel forthe following:
1.) Speaker/Strobe (Audible/Visual). 2.) Magnetic Door Hold Open Devices. 3.) Elevator Recall. 4.) Stair Pressurization/HVAC.
3. Ensure all fire alarm devices correspond with the permanent guestroom roomnumber signage and stair signage.
-
CANAL STREET HOTEL386 Canal StreetNew York, NY 10013
Client Representative:
Bernard & Anne Spitzer School of Architecture141 Convent AvenueNew York, NY 10031Contact: Martin Stisgaard
Project Team
ArchitectsRyan CramerPatrick BrophyLubov Tsinis
Structural ConsultantsCiro CuonoDominick Pilla
Sustainability ConsultantAhu Aydogan
Zoning ConsultantBrian Gillen
MEP ConsultantCurt Rohner
Lighting ConsultantPeihing Tsai
Landscape ConsultantTaewook Cha
Spec ConsultantJeff Feingold
Cost Estimating ConsultantDave Miller
Design ConsultantMartin Stigsgaard
No.: Date: Revision:
CBT architectsCramer Brophy Tsinis Architects141 Convent Avenue, New York NY 10031
Drawn By DateDateApproval By
Issued DateScale
Key Plan
Drawing Title
Drawing No.
Sheet No.
N
SITE
COST ESTIMATE
APDX -003
CANAL STREET HOTEL Date: 10-Dec-2014386 Canal Street, New York, NY 10013CBT Architects
GSF 40,917 ESTIMATE DETAIL SUMMARY
Description Quantity Unit $/Unit Total $ Subtotal Trades $/SF%
Trade Cost Notes
1 DEMOLITON 2 Demo of existing site contents 1 ls 100,000.00 100,000 3
4 End Trade5
6 DEMOLITON 100,000$ 7
8 SITE CONSTRUCTION9 Pavers @ Ground Floor 13,265 sf 20.00 265,300 10 Pavers @ 3rd Floor 3,866 sf 20.00 77,320 11
12 Landscaping 1 allowance 100,000.00 100,000 13 Trees included 14 Seating @ 3rd floor included 1215
16 End Trade17
18 SITE CONSTRUCTION 442,620$ 19
20 EXCAVATION AND FOUNDATION 21
22 Excavation and support of excavation 1,749 cy 250.00 437,130 23 Foundations -24 Strip Footing: 22 cy 500.00 11,144 25 Foundation Wall 111 cy 750.00 83,583 26 Slab on Grade 338.52 cy 500.00 169,259 27 Core28 Walls 9 cy 750.00 7,072 29 Footing @ Walls 47 cy 450.00 21,217 303132 Soil remediation excluded33
34 End Trade35
36 EXCAVATION AND FOUNDATION 729,406$ 37
38 STRUCTURAL FRAME 39
40 Concrete Frame 40,917 GSF 75.00 3,068,775 41 Poured in place concrete slabs included cy - 42 Concrete columns included cy - 43 Concrete beams included cy - 44 Cast in place stairs 40 flights 4,500.00 180,000 45 Misc concrete 46 Concrete pads for mech equipment 1 ls 5,000.00 5,000 47 Concrete curbs 1 ls 2,500.00 2,500 48
49 Steel Frame
Schematic estimate Page 1 of 4
CANAL STREET HOTEL Date: 10-Dec-2014386 Canal Street, New York, NY 10013CBT Architects
GSF 40,917 ESTIMATE DETAIL SUMMARY
Description Quantity Unit $/Unit Total $ Subtotal Trades $/SF%
Trade Cost Notes
50 Beams, Columns, bracing - including connections 409 tons 8,000.00 3,273,360 51 Hat Truss w/above tons - 52 Metal Deck included 53 Concrete on Metal Deck included 54
55 Spray Fireproofing 40,917 gsf 0.75 30,688 56 Intumescent Paint @ Hat Truss 1 allowence 300,000 57
58 1 40,917 gsf 2.50 102,293 59 Metal Pan Stairs 20 flights 5,000.00 100,000 60 Concrete fill at metal stairs included 61 OSHA Protection 40,917 gsf 1.25 51,146 6263 Decorative Interior Stair 1 each 50,000.00 50,000 64 Decorative Interior Stair 1 each 35,000.00 35,000 65
66 STRUCTURAL FRAME 7,198,762$ $175.94 39.46%67
68 EXTERIOR WALL 69
70 Exterior Wall 71 Concrete Exterior Wall 9 " 5,094 sf 125.00 636,750 72 Shear Core Wall - Concrete 12" 17,479 sf 125.00 2,184,875 73 Curtain Wall 1,153 sf 225.00 259,425 74 CurtainWall Clear Glass Store Front 1,511 sf 100.00 151,100 75 Exterior Glass Panel with Ralining- Roof Level 768 sf 125.00 96,000 76 Premium for Louvers @ Exterior 1 each 100,000.00 100,000 77
78 End Trade79
80 EXTERIOR WALL 3,428,150$ $83.78 18.79%81
82 ROOFING AND WATERPROOFING83
84 Roofing Membrane85 Roof Top 5,476 sf 35.00 191,660 86 Outdoor Lounge Open - Qty 1 547 sf 45.00 24,615 87 Outdoor Longes Covered - Qty 3 1,368 sf 45.00 61,560 88
89 End Trade90
91 ROOFING AND WATERPROOFING 277,835$ $6.79 1.52%92
93 INTERIOR PARTITIONS AND FINISHES94 Interior Partitions and finsihses 40,917 gsf 22.50 920,633 95 Interior Partitions- 4 7/8" Partition (1-hr) - Drywall w/ Metal Stud included sf - 96 Interior Partitions- 6 1/8" Partition (2-hr) - Drywall w/ Metal Stud included sf
Schematic estimate Page 2 of 4
CANAL STREET HOTEL Date: 10-Dec-2014386 Canal Street, New York, NY 10013CBT Architects
GSF 40,917 ESTIMATE DETAIL SUMMARY
Description Quantity Unit $/Unit Total $ Subtotal Trades $/SF%
Trade Cost Notes
9798 End Trade99 INTERIOR PARTITIONS AND FINISHES 920,633$ 100
101 SPECIALTIES102 Specialties 40,917 gsf 10.00 409,170 103
104105 End Trade10