Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program...
Transcript of Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program...
![Page 1: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/1.jpg)
Composite Program in Composite Program in Taiwan Aviation Taiwan Aviation
Industry and Areas of Industry and Areas of Interest(s)Interest(s)
Eric ChenInitial Airworthiness Section
CAA of TaiwanSingapore, September 3, 2015
![Page 2: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/2.jpg)
2
OutlineOutline
![Page 3: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/3.jpg)
3
CAAFlight Standards Division (FSD)
Introduction
![Page 4: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/4.jpg)
4
Trend of Global Flight Safety ManagementTrend of Global Flight Safety Management
Establishment and Implementation of State Safety Program (SSP)
Enhancement & Improvement of Regional Integration & Cooperation
![Page 5: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/5.jpg)
5
CAA OrganizationCAA Organization
![Page 6: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/6.jpg)
Division Director
Deputy Division Director
OperationsInspection Section
Senior TechnicalSpecialistSenior Specialist
Formal Sections
Command & Supervision Organization
Civil Aviation Medical Center
9
Taskforce Unit
Flight OpsInspection
Administration
CabinInspection
FlightInspection
Administration
AirworthinessInspection
AirworthinessInspection Flight Ops
Inspection
AirworthinessFlight Ops
Airmen Certification
Airworthiness Certification
Major Repair/
Alteration Approval
OnboardEngineers
Pilots
Flight Operators
AirworthinessInspection Section
Policy & ProcedureSection
Airmen Certification Section
Initial AirworthinessSection
Flight Check Group
FSD OrganizationFSD Organization
![Page 7: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/7.jpg)
7
Civil Aviation Act § 1:This Act is enacted to insure the aviation safety, a sound civil aviation system, compliance with international civil aviation standards, and promote the development of civil aviation.
§ 9 delegates MOTC the authority to prescribe 06-07A§ 23 adopts international airworthiness standards
FAR Part 23, 25, 27, 29, 31, 33, 34, 35, 36EASA CS 23, 25, 27, 29, 31, E, 34, P, 36
FAA Technical Standard OrdersEASA European Technical Standard Orders
Regulation StructureRegulation Structure
Civil
Aviatio
n Act
Advisory Circulars, Aviation Safety Bulletins
![Page 8: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/8.jpg)
8
254
Increasing Number of AircraftIncreasing Number of Aircraft
Aircraft (Total)GA-HelicopterTraining School
Air TransportGA-Balloon
GA-AircraftCAA
Num
ber of Aircraft
![Page 9: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/9.jpg)
9
Composite Activities in Taiwan Aviation Industry
Introduction
![Page 10: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/10.jpg)
10
Aerospace Industrial Development Corp. (AIDC)Taiwan Advanced Composite Center (TACC)
Composite Design, Development and Manufacturing
![Page 11: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/11.jpg)
11
Taipei
Kaohsiung
Taichung
Sha‐Lu (604,580 m2)
Aircraft Assy. & TestingAvionics & Flight Control EngineeringHarness Fabrication & InstallationFlight Test / Maintenance
TACC (42,000m2)
Composite Design & AnalysisComposite Process DevelopmentComposite ManufacturingComposite AssemblyComplex Area: 10.4 AcresInaugurate at Nov. 2010
Taichung (285,260m2)
AIDC HeadquartersEngineeringAircraft Parts FabricationAvionics Assembly & Testing
Gang‐Shan (191,580m2)
Engine Parts FabricationEngine Assembly & Testing
AIDC Profile
![Page 12: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/12.jpg)
12
NADCAP certified facility: 210 m long x 120 m wide.Total working area: 33,000 m2 (360,000 ft2)100,000 class clean room: 8,900 m2 (96,500 ft2)
1st Floor: Receiving & Parking Lot
2nd Floor: Freezer, Material Preparation3rd Floor: OOA Process Production
Production Floor: Lay‐up, Curing, Machining,Inspection, Painting and Assembly
TACC Facility Layout
![Page 13: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/13.jpg)
13
Design, Analysis, Test and Integration
Material & Process Engineering
NDI and NDT
Production Engineering
Tooling Design & Manufacturing
Composite Assembly
Composite Painting
Composite Repair
Composite Fabrication
TACC Composite Capability
![Page 14: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/14.jpg)
14
A320 A320
MRJMRJ C‐SeriesC‐Series
M429M429 S76S76 S92S92
TACC provides high quality and high production rate products to worldwide prime aircraft manufacturers including:
Airbus, Boeing, Alenia, MHI, KHI,Bombardier, Bell,Sikorsky, Eurocopter,Honeywell.
ERJ‐190ERJ‐190
B787B787B787B787
Worldwide Customers
![Page 15: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/15.jpg)
15
1997‐ Sikorsky S92
1997‐ Boeing B717 2000‐Bombardier CL300
1998‐ Alenia C27J2008‐Mitsubishi MRJ
Design and Production Composite Projects
![Page 16: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/16.jpg)
16
AIDC has 30 years experienceand knowledge in:Airframe DesignStress AnalysisStatic TestFatigue TestDynamic TestDamage ToleranceBird Strike TestSubsystem DesignElectrical DesignM&P EngineeringMeets FAA/EASA/JCABRequirements
Engineering Capability
![Page 17: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/17.jpg)
17
Test Lab (NADCAP Certified)Perform material receiving test, curing specimen test and part destructive test with:HPLC (High‐Performance Liquid Chromatography)
FTIR (Fourier Transform Mid‐Infrared Spectrometer)
DSC (Differential Scanning Calorimetry)
DMA (Dynamic Mechanical Analysis)
TMA (Thermal Mechanical Analysis)
Material & Process Engineering
![Page 18: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/18.jpg)
18
OOA ProcessOOA Process
Fully developed capability in RTM, RFI, VaRTM processesIn development of other out of autoclave process
Auto Lay‐upAuto Lay‐upThe future of manufacturing.Machine installed and start production at August 2012.
Hand Lay‐upHand Lay‐up Over 30 years experience.Expertise in severe contour parts.
Manufacturing‐ Technology
![Page 19: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/19.jpg)
21
TACC‐19 Facility Re‐Construction
![Page 20: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/20.jpg)
22
Expanding area for more autoclaves
Heating up system: Electrical type
Stable and reliability system
Scholz
Autoclaves:
TACC‐19 Equipments
![Page 21: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/21.jpg)
23
Dedicated For SA AFT BF Project :
TACC‐19 Facility
![Page 22: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/22.jpg)
24
Composite Applications in Appliance16g Seat - Composite Seat
Back Structure
![Page 23: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/23.jpg)
25
Cargo Container Composite Structural Panels
Taiwan Fylin Inc. (TFI)
Composite Applications in Appliance
![Page 24: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/24.jpg)
26
CAL sets up the ability to maintain A350
Composite over 53%
![Page 25: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/25.jpg)
27
EGAT sets up the ability to maintain B787
Composite over 50%
![Page 26: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/26.jpg)
28
Areas of Interests
A proposal of safety thinking
![Page 27: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/27.jpg)
29
Areas of Interests Damage tolerance capability for composite
material Inspection/Maintenance program for ensuring
continued safety of transport airplane composite structure
Accidental damage (HEWABI) Fuselage segment replacement Lightning strikes Supplier audit: NADCAP vs company audit Cooperation between authorities on supplier
surveillance
![Page 28: Composite Program in Taiwan Aviation Industry and Areas of … · 2015-09-30 · Composite Program in Taiwan Aviation Industry and Areas of Interest(s) Eric Chen Initial Airworthiness](https://reader034.fdocuments.us/reader034/viewer/2022042110/5e8b41b4f396e351493fff3d/html5/thumbnails/28.jpg)
30
Thank you!Thank you!