Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest...
Transcript of Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest...
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 6
1.1 ToR Compliance
Compliance to ToR
S.
No
.
TOR Conditions Compliance Status
1
Year-wise production details since
1994 should be given, clearly
stating the highest production
achieved in any one year prior to
1994. It may also be categorically
informed whether there had been
any increase in production after the
EIA Notification 1994 came into
force, w.r.t. the highest production
achieved prior to 1994.
Year wise production detail since Inception of the mines has
been incorporated in Chapter 1, Page no. 41, and Table 1.2
of Draft EIA/EMP Report.
Certified report has been enclosed as Annexure-2.
2
A copy of the document in support
of the fact that the Proponent is the
rightful Lessee of the mine should
be given.
The lease was granted to Shri Arjabhai Khimabhai Rathod
vide order no. MCR-1578-(R-4)-3/427-CHH issued on dated
24.04.1979 by Government of Gujarat for a period of 20 year.
Lease deed was signed on 08.10.1979. Lease deed has been
enclosed as Annexure-1, Page no. 242-259 of Draft
EIA/EMP Report. Lease applied for renewal on 28.09.1998 and the renewal is
under-process. The first renewal shall be from 08.10.1999 to
07.10.2019. The mining operations were commenced from
05.12.1979. Renewal letter has been enclosed as Annexure-2
Page no. 260-266 of Draft EIA/EMP Report. As per section 8(A) of new MMDR Amendment Act -2015
the lease is liable for lease period extension up to Dated
7/10/2029. Letter for the same has been enclosed as
Annexure-3 Page no. 267 of Draft EIA/EMP Report.
3
All documents including approved
mine plan, EIA and Public Hearing
should be compatible with one
another in terms of the mine lease
area, production levels, waste
generation and its management,
mining technology etc. and should
be in the name of the lessee.
All documents including approved mine plan, EIA has been
compatible with one another in terms of the mine lease area,
production levels, waste generation and its management,
mining technology etc. and has been All documents are in the
name of Arjabhai Khimabhai Rathod.
Public Hearing will be done after submission of Draft
EIA/EMP report with consolation of SPCB, Gujarat.
Mining Lease Area- 2.0 ha
Production–18,000 TPA
Waste generation-
There is no overburden or mineral rejects.
Small amount of domestic waste will be generated for which
dustbin will be kept at proper place and it will be disposed
properly and regularly.
The dump will be protected by retaining wall with garland
drain, compacted and temporarily rehabilitated by sowing fast
growing grass seeds.
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 7
S.
No
.
TOR Conditions Compliance Status
Mining Technology –Opencast Semi-Mechanized Method
Name of the Lessee – Shri Arjabhai Khimabhai Rathod
4
All corner coordinates of the mine
lease area, superimposed on a High
Resolution Imagery/toposheet,
topographic sheet geomorphology
and geology of the area should be
provided. Such an Imagery of the
proposed area should clearly show
the land use and other ecological
features of the study area (core and
buffer zone).
All corner coordinates of the lease area has been
superimposed in Topographical map. Refer Figure 2-1 of
Chapter-2.
Image of the proposed area for show the land use and other
ecological features of the study area (core and buffer zone)
has been referred in Figure 3-1 in Chapter-3 of Draft
EIA/EMP report.
5
Information should be provided in
Survey of India Toposheet in
1:50,000 scale indicating
geological map of the area,
geomorphology of land forms of
the area, existing minerals and
mining history of the area,
important water bodies, streams
and rivers and soil characteristics.
A map of Survey of India Toposheet in 1:50,000 scale
indicating geology & geomorphology of the area, has been
given in Figure 2.1 for existing minerals and mining history,
important water bodies, streams & rivers & soil characteristics
has been given in has been shown in Figure 3.1, Page no. 83
of Draft EIA/EMP Report.
6
Details about the land proposed for
mining activities should be given
with information as to whether
mining conforms to the land use
policy of the State; land diversion
for mining should have approval
from State land use board or the
concerned authority.
The total mining lease area (2.0 ha) is Non-forest Government
waste land. Mining lease was granted by Industry, Mines and
Power department of Government of Gujarat in favor of Shri
Arjabhai Khimabhai Rathod vide order no. MCR-1578-(R-4)-
3/427-CHH issued on 24.04.1979 for a period of 20 years.
7
It should be clearly stated whether
the proponent Company has a well
laid down Environment Policy
approved by its Board of
Directors? If so, it may be spelt out
in the EIA Report with description
of the prescribed operating
process/procedures to bring into
focus any
infringement/deviation/violation of
the environmental or forest norms/
conditions? The hierarchical
system or administrative order of
the Company to deal with the
environmental issues and for
ensuring compliance with the EC
conditions may also be given. The
The company is having well laid down Environmental Policy
duly approved by its Board of Directors & the same is
enclosed as Annexure 6, Page no. 348-350.
Standard Operating Procedures (SoPs) have been incorporated
in the Corporate Environmental Policy of the company.
The hierarchical system or administrative order of the
company to deal with the environmental issues and for
ensuring compliance with the EC conditions etc. has been
given in Chapter- 10, Page no. 220 of Draft EIA/EMP Report.
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 8
S.
No
.
TOR Conditions Compliance Status
system of reporting of non-
compliances / violations of
environmental norms to the Board
of Directors of the Company
and/or shareholders or
stakeholders at large, may also be
detailed in the EIA Report.
8.
Issue relating to Mine safety
including subsidence study in case
of underground mining and slope
study in case of open cast mining
blasting study study etc. should be
detailed. The proposed safeguard
measures in each case should also
be provided.
The proposed method of Mining will be Open-cast Manual
mining method by forming benches of 3.0 m height and width
more than height comprising Jack Hammer drilling, manual
breaking & loading of limestone with Tractor trolley.
Mines relating to mine safety has been adopted and same has
been incorporated in Chapter 4, Page no. 179-180 of Draft
EIA/EMP Report.
Mild Drilling & Blasting is proposed.
The proposed safeguard measures in each case has been
given in Chapter 4, page no 159 of Draft EIA/EMP Report.
9
The study area will comprise of 10
km zone around the mine lease
from lease periphery and the data
contained in the EIA such as waste
generation etc. should be for the
life of the mine / lease period.
The Study area of the proposed mining project comprises of
10 km zone around the mining Lease boundary. Map showing
core zone (ML area) and buffer zone (10 km radius from the
lease boundary) has been prepared and given in Figure-2.1,
Page no 56.
There will be no Top soil or waste will be generated due to
Mining.
Data like reserves, waste generation up to life of mine is given
in Chapter 2, page no. 61-63 of Draft EIA/EMP Report.
10
Land use of the study area
delineating forest area, agricultural
land, grazing land, wildlife
sanctuary, national park, migratory
routes of fauna, water bodies,
human settlements and other
ecological features should be
indicated. Land use plan of the
mine lease area should be prepared
to encompass preoperational,
operational and post operational
phases and submitted. Impact, if
any, of change of land use should
be given.
Land use / land cover map of the study area showing present
land use pattern & also, delineating agricultural land, water
bodies, forest land, human settlements and other ecological
features etc. is given in Figure-3.1, Page no. 83 of Chapter 3
of Draft EIA/EMP Report.
Land use plan of the mine lease area in pre-operational,
operational and post operational phases has been prepared and
given in Table 3.1 of Draft EIA/EMP report.
No, mineral reject & top soil will be generated during this
scheme period (five years). Whole area of 1.6842(excavated
area in plan period) will be converted into water reservoir.
11 Details of the land for any Over
Burden Dumps outside the mine
No land for any Over Burden Dumps outside the mine lease is
proposed hence no R & R issue.
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 9
S.
No
.
TOR Conditions Compliance Status
lease, such as extent of land area,
distance from mine lease, its land
use, R&R issues, if any, should be
given.
12
A Certificate from the Competent
Authority in the State Forest
Department should be provided,
confirming the involvement of
forest land, if any, in the project
area. In the event of any contrary
claim by the Project Proponent
regarding the status of forests, the
site may be inspected by the State
Forest Department along with the
Regional Office of the Ministry to
ascertain the status of forests,
based on which, the Certificate in
this regard as mentioned above be
issued. In all such cases, it would
be desirable for representative of
the State Forest Department to
assist the Expert Appraisal
Committees.
The total mining lease area (2.00 ha) is a Govt. Waste land.
Deputy Conservator of Forest, Forest Department, Junagad
has been certified on dated 22.11.2017 that there is a Forest
extension present at a distance of 6.7 KM and Gir Century at a
distance of 21.9 km from the lease area. Forest letter has been
enclosed as Annexure-7, page no 351 of Draft EIA/EMP
Report
13
Status of forestry clearance for the
broken up area and virgin
forestland involved in the Project
including deposition of net present
value (NPV) and compensatory
afforestation (CA) should be
indicated. A copy of the forestry
clearance should also be furnished.
No forest clearance is required as the proposed mining lease
area is Government Waste Land (Non Forest Land).
NOC from forest department has been has been enclosed as
Annexure-7, Page no 351of Draft EIA/EMP Report
14
Implementation status of
recognition of forest rights under
the Scheduled Tribes and other
Traditional Forest Dwellers
(Recognition of Forest Rights)
Act, 2006 should be indicated.
Not Applicable
15
The vegetation in the RF / PF areas
in the study area, with necessary
details, should be given.
Reserved / Protected Forest falling within 10 Km radius of the
mining lease area.
1. Reserved forest ~ 8..20Km in South direction form mine
site
2. Reserved forest ~ 7.0 North-East direction form mine site
3. Reserved forest ~ 6.74, North direction form mine site
Same has been marked on Environment Sensitive map of
Figure 1.3 Page no 43 of Draft EIA/EMP report.
Details of Flora and fauna found in the study area are given
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 10
S.
No
.
TOR Conditions Compliance Status
in Chapter 3 Page no 126 &131 of Draft EIA/EMP Report.
16
A study shall be got done to
ascertain the impact of the Mining
Project on wildlife of the study
area and details furnished. Impact
of the project on the wildlife in the
surrounding and any other
protected area and accordingly,
detailed mitigative measures
required, should be worked out
with cost implications and
submitted.
Biological study has been done for the project and it has been
assessed that there will no adverse effect will be on wildlife
because there is no wild life activity found.
Same has been details the impact on surrounding wildlife and
mitigation measures are given in Chapter 4, page no. 171
Draft EIA/EMP Report.
17
Location of National Parks,
Sanctuaries, Biosphere Reserves,
Wildlife Corridors, Ramsar site
Tiger/Elephant Reserves (existing
as well as proposed), if any, within
10 km of the mine lease should be
clearly indicated, supported by a
location map duly authenticated by
Chief Wildlife Warden. Necessary
clearance, as may be applicable to
such projects due to proximity of
the ecologically sensitive areas as
mentioned above, should be
obtained from the Standing
Committee of National Board of
Wildlife and copy furnished.
No National Parks, Wildlife Sanctuaries, Biosphere Reserves,
wildlife corridors, Tiger/Elephant Reserves (existing as well
as proposed) etc. falls within the study area (10 km radius of
the mine boundary).
18
A detailed biological study of the
study area [core zone and buffer
zone (10 km radius of the
periphery of the mine lease)] shall
be carried out. Details of flora and
fauna, endangered, endemic and
RET Species duly authenticated,
separately for core and buffer zone
should be furnished based on such
primary field survey, clearly
indicating the Schedule of the
fauna present. In case of any
scheduled-I fauna found in the
study area, the necessary plan
along with budgetary provisions
for their conservation should be
prepared in consultation with State
Forest and Wildlife Department
Detailed Biological study for the study area (core zone &
buffer zone) has been conducted.
List of Flora & Fauna for core & buffer zone has been
submitted to DFO for approval & the same is under process
with the Forest Department.
There is no Schedule I species found within the proposed
area.
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 11
S.
No
.
TOR Conditions Compliance Status
and details furnished. Necessary
allocation of funds for
implementing the same should be
made as part of the project cost.
19
Proximity to Areas declared as
„Critically Polluted‟ or the Project
areas likely to come under the
„Aravali Range‟, (attracting court
restrictions for mining Operations)
should also be indicated and where
so required, clearance
certifications from the prescribed
Authorities, such as the SPCB or
State Mining Dept. Should be
secured and furnished to the effect
that the proposed mining activities
could be considered.
The Mine site does not fall under the Critically Polluted Area
and „Aravali Range‟ and it does not attract any court
restriction for mining operation.
20
Similarly, for coastal Projects, A
CRZ map duly authenticated by
one of the authorized agencies
demarcating LTL. HTL, CRZ area,
location of the mine lease w.r.t
CRZ, coastal features such as
mangroves, if any, should be
furnished. (Note: The Mining
Projects falling under CRZ would
also need to obtain approval of the
concerned Coastal Zone
Management Authority).
Not Applicable, as the project does not falls in Coastal area.
21
R&R Plan/compensation details
for the Project Affected People
(PAP) should be furnished. While
preparing the R&R Plan, the
relevant State/National
Rehabilitation & Resettlement
Policy should be kept in view. In
respect of SCs/STs and other
weaker sections of the society in
the study area, a need based
sample survey, family-wise,
should be undertaken to assess
their requirements, and action
programmes prepared and
submitted accordingly, integrating
the sectoral programmes of line
departments of the State
The total mining lease area (2.0 ha) is a Govt. Waste land. No
houses, villages connecting road and infrastructure existing in
the area will be disturbed.
Therefore no Rehabilitation and resettlement action plan is
required.
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 12
S.
No
.
TOR Conditions Compliance Status
Government. It may be clearly
brought out whether the village(s)
located in the mine lease area will
be shifted or not. The issues
relating to shifting of village(s)
including their R&R and socio-
economic aspects should be
discussed in the Report.
22
One season (non-monsoon) [i.e.
March - May (Summer Season);
October - December (post
monsoon season) ; December -
February (winter season)] primary
baseline data on ambient air
quality as per CPCB Notification
of 2009, water quality, noise level,
soil and flora and fauna shall be
collected and the AAQ and other
data so compiled presented date-
wise in the EIA and EMP Report.
Site specific Meteorological data
should also be collected. The
location of the monitoring stations
should be such as to represent
whole of the study area and
justified keeping in view the pre-
dominant downwind direction and
location of sensitive receptors.
There should be at least one
monitoring station within 500 m of
the mine lease in the pre-dominant
downwind direction. The
mineralogical composition of
PM10, particularly for free silica,
should be given.
Primary baseline data on ambient air quality, water quality,
noise level, soil and flora and fauna are collected in Post
Monsoon Season (October, November, December) 2018.
Ambient Air quality has been determined by measuring the
concentration of parameters like P.M.2.5, P.M.10, SO2, NOx
according to the latest standards prescribed by CPCB. Site-
specific meteorological data has also been collected. The
location of the monitoring stations (minimum 7) has been
justified.
The selections criteria for monitoring locations have been
given in Chapter-3, page no. 98. Date wise collected baseline
AAQ data have formed part of EIA and EMP report. The
details of the same are given in Chapter 3, page no. 98..
The monitoring has been carried out by NABL approved
laboratory and copy of the certificate 8 & lab analyses report
has been enclose as Annexure-8, page no 352-405 of Draft
EIA/EMP Report.
23
Air quality modeling should be
carried out for prediction of impact
of the project on the air quality of
the area. It should also take into
account the impact of movement
of vehicles for transportation of
mineral. The details of the model
used and input parameters used for
modeling should be provided. The
air quality contours may be shown
on a location map clearly
indicating the location of the site,
Air quality modeling has been carried out for prediction of
impact of the project on the air quality of the area. The impact
of movement of vehicles for transportation of mineral has
been taken into account. The details of the model used and
input parameters used for modeling are given in Chapter 4,
page no 153 of the draft EIA report.
The Isopleths have been drawn on the topographical map. The
wind rose diagram has been prepared which is showing NE
pre-dominant wind direction and shown in Chapter-3, Page
no. 96-97.
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 13
S.
No
.
TOR Conditions Compliance Status
location of sensitive receptors, if
any, and the habitation. The wind
roses showing pre-dominant wind
direction may also be indicated on
the map.
24
The water requirement for the
Project, its availability and source
should be furnished. A detailed
water balance should also be
provided. Fresh water requirement
for the Project should be indicated.
The total water requirement for the Ajodha Limestone Mine
is 3.83 KLD. Propose Quantity
(KLD)
Remarks
Domestic 1.44 0.320 KLD fresh water will used for
drinking purpose Dust
Suppression
0.39
Greenbelt
Development
2.0
Total 3.83
Detailed discussion has been done in Chapter-2, Point No.
2.15, page no.69 of Draft EIA/EMP Report.
25
Necessary clearance from the
Competent Authority for drawl of
requisite quantity of water for the
Project should be provided.
No groundwater will be abstracted for use at mine site.
26
Description of water conservation
measures proposed to be adopted
in the Project should be given.
Details of rainwater harvesting
proposed in the Project, if any,
should be provided.
In the proposed mining, the water will be required during
water sprinkling.
The rain water collected in the mine pit will be pumped out
and fed to the nearby pond by flexible pipes.
27
Impact of the Project on the water
quality, both surface and
groundwater, should be assessed
and necessary safeguard measures,
if any required, should be
provided.
Surface water: Surface water will not likely to be affected.
All water drains from the pits will be constructed in such a
way that the water will be drained to nallas
Ground Water: The ultimate depth of the pit would be done
at 16 mRL and the ground water table in area is beyond 10-15
m bgl hence the mining will be maintain up to 5-10 m above
the ground water table. So mining activity will not intersect
the ground water table at any point.
28
Based on actual monitored data, it
may clearly be shown whether
working will intersect
groundwater. Necessary data and
documentation in this regard may
be provided. In case the working
will intersect groundwater table, a
detailed Hydro Geological Study
should be undertaken and Report
Based on actual monitored data it has been found that:
Elevation range (Buffer
Zone)
21.43 m RL – 18.52
Depth of workings
(from natural
surface level starting
the pit excavation)
19.0 m RL- 16.0 m RL
Ultimate Working Depth 16.0 mRL
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 14
S.
No
.
TOR Conditions Compliance Status
furnished. The Report inter-alia,
shall include details of the aquifers
present and impact of mining
activities on these aquifers.
Necessary permission from Central
Ground Water Authority for
working below ground water and
for pumping of ground water
should also be obtained and copy
furnished.
Difference from surface
level to ultimate working
pit
3.0 m
Ground Water Table Pre Monsoon –15-20 m BGL
Post Monsoon- 10-12 m BGL
Area 2.0 hect.
So mining activity will not intersect the ground water table at
any point.
29
Details of any stream, seasonal or
otherwise, passing through the
lease area and modification /
diversion proposed, if any, and the
impact of the same on the
hydrology should be.
There is a Sarswati River which is 1.40 km flows in South
west direction from the mining lease area. Rain water falling
around the lease area will be diverted to the low lying area.
There is no stream or seasonal water bodies passing through
the lease area.
So there will be no change in water bodies or the land surface
affecting drainage or run‐off.
30
Information on site elevation,
working depth, groundwater table
etc. Should be provided both in
AMSL and BGL. A schematic
diagram may also be provided for
the same.
Elevation range (Buffer
Zone)
21.43 m RL – 18.52
Depth of workings
(from natural
surface level starting
the pit excavation)
19.0 m RL- 16.0 m RL
Ultimate Working Depth 16.0 mRL
Difference from surface
level to ultimate working
pit
3.0 m
Ground Water Table Pre Monsoon –15-20 m BGL
Post Monsoon- 10-12 m BGL
Area 2.0 hect.
31
A time bound Progressive
Greenbelt Development Plan shall
be prepared in a tabular form
(indicating the linear and
quantitative coverage, plant
species and time frame) and
submitted, keeping in mind, the
same will have to be executed up
front on commencement of the
Project. Phase-wise plan of
plantation and compensatory
afforestation should be charted
clearly indicating the area to be
covered under plantation and the
species to be planted. The details
of plantation already done should
A time bound progressive greenbelt development plan is
given in Table 10.2 Page no 224 of Chapter-10. Greenbelt developments Programme within M.L. area
Year of
Plantation. Proposed
Plantation
Area
cover
in ha.
Species Place of
Plantation
1st Year 40 0.0631 Beal,
Amla,
Mango,
On the
statuary
barrier
and along
the haul
road
2nd
Year 40 0.0631
3rd
Year 40 0.0631
4th
Year 40 0.0631
5th
Year 40 0.0631
Total 200 0.315
Greenbelt developments Programme outside the M.L area
Year of
Plantation. Proposed
Plantation
Area
cover
in ha.
Species Place of
Plantation
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 15
S.
No
.
TOR Conditions Compliance Status
be given. The plant species
selected for green belt should have
greater ecological value and should
be of good utility value to the local
population with emphasis on local
and native species and the species
which are tolerant to pollution.
1st Year 43 0.0688
Jamun,
Arjun,
Sissoo
Along the
road-
sides,
Gram
Sabha,
nearest
village,
nearby
schools &
hospitals
2nd
Year 43 0.0688
3rd
Year 43 0.0688
4th
Year 43 0.0688
5th
Year 43 0.0688
Total 215 0.344
32
Impact on local transport
infrastructure due to the Project
should be indicated. Projected
increase in truck traffic as a result
of the Project in the present road
network (including those outside
the Project area) should be worked
out, indicating whether it is
capable of handling the
incremental load. Arrangement for
improving the infrastructure, if
contemplated (including action to
be taken by other agencies such as
State Government) should be
covered. Project Proponent shall
conduct Impact of Transportation
study as per Indian Road Congress
Guidelines.
The Impact on local transport and infrastructure due to the
project will be on positive side as Post project PCU will be
1184 PCUs (1161.5 PCUs Existing + 22.5 PCUs Post) on SH-
6 (Somnath-una highway).
Project site to
NH
Vol. of
vehicle in
PCU/day
Capacity of
Roads in
PCU/day
LOS
SH-6 (Somnath-
una highway), 1184 2000
0.59 (Good/
Average/ Fair)
Not much impact will be there on the local transport. The
LOS value from the proposed mine may be “Good/ Average/
Fair” for State highway-6 (Somnath to Una Highway). So, the
additional load on the carrying capacity of the concern roads
is not likely to have any significant adverse effect.
Traffic Density is carried out at one locations on (Mine site to
SH-6) and the same is given in Chapter 2, Page no. 73
33
Details of the onsite shelter and
facilities to be provided to the
mine workers should be included
in the EIA Report.
Mine office & First Aid Station ,Store Room,Rest Shelter,
Drinking water facility, Domestic Water & Dust Suppression,
Adequate lighting arrangements: Storage of machinery, tools,
oil and grease, Toilets will be provides for workers.
Details of the infrastructure facilities to be provided for the
mine workers is given in Chapter-2 Page no. 71.
34
Conceptual post mining land use
and Reclamation and Restoration
of mined out areas (with plans and
with adequate number of sections)
should be given in the EIA report.
Post-Mining (Conceptual) Land Use of Core Zone with
Reclamation and Restoration of mined out areas has been
shown below:
S.
No. Head
Present
Land Use
At the end of
Fifth Year
At the end of
mine
1 Area under
mining
0.4270 1.1455 1.5725
2 Storage for top
soil
Nil Nil Nil
3 Waste dump site Nil Nil Nil
4 Mineral storage Nil Nil Nil
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 16
S.
No
.
TOR Conditions Compliance Status
5 Infrastructure
workshop,
administrative
building etc.
0.0355 Nil 0.0355
6 Roads 0. 0762 Nil 0. 0762
7 Railways Nil Nil Nil
8 Tailing Road Nil Nil Nil
9 Effluent
treatment plant
Nil Nil Nil
10 Mineral
separation Plant
Nil Nil Nil
11 Township area Nil Nil Nil
12 Other
(green belt)
0.200 0.1158 0.3158
13 Virgin Area 1.2613 Nil Nil
Grand Total 2.000 2.000 2.000
& Conceptual Plan has been enclosed as Plate-7.
35
Occupational Health impacts of the
Project should be anticipated and
the proposed preventive measures
spelt out in detail. Details of pre-
placement medical examination
and periodical medical
examination schedules should be
incorporated in the EMP. The
project specific occupational
health mitigation measures with
required facilities proposed in the
mining area may be detailed.
The Mines Act and the Mines Rules, 1955 will be followed
for Occupational health and safety.
Impact & preventive measures on Occupational Health :
Near miss incident or injury which may require self-
administered first aid.
Injury requiring onsite treatment by medical
practitioner.
Serious injury requiring offsite treatment by medical
practitioner.
Regular Medical checkup of workers will be done to
check occupational disease, if any, and respective
records will be maintained at the mine.
Project specific occupational health mitigation measures with
required facilities proposed in the mining & Details of pre-
placement medical examination and periodical medical
examination schedules has been detailed in Table 4.6 of
Chapter-4, page no.177 of Draft EIA/EMP report.
36
Public health implications of the
Project and related activities for
the population in the impact zone
should be systematically evaluated
and the proposed remedial
measures should be detailed along
with budgetary allocations.
Limestone mining can cause such as Skin Diseases, Lung
diseases, Stomach diseases and Eye/Skin.
Impact of Limestone mining on Public health implication &
remedial measures has been detailed in Table 4.7 & Table 4.8
Page no. 177 of Chapter-4.
Budgetary amount:
About Rs. 0.50 Lakh/annum will be proposed for
Health check - up camps for villagers (the camp will
be conducted twice during the year for general health
check-up). About Rs. 0.80 Lakh/annum will be proposed for
health facility & insurance cover for mine workers.
37
Measures of socio economic
significance and influence to the
local community proposed to be
A field based socio economic survey has been conducted and
detailed in Para 3.16 of Chapter-3 Page no. 135.
The people around the mine area will get direct or
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 17
S.
No
.
TOR Conditions Compliance Status
provided by the Project Proponent
should be indicated. As far as
possible, quantitative dimensions
may be given with time frames for
implementation.
indirect employment opportunities on mine and at
getting associated with ancillaries.
The villagers employed get the benefit of health
surveillance done statutorily for all workers under
Mines Rules.
Impact of proposed Limestone mining on Socio economic
conditions has been discussed in Para 4.10, page no. 172 of
Chater-4.
38
Detailed environmental
management plan (EMP) to
mitigate the environmental impacts
which, should inter-alia include the
impacts of change of land use, loss
of agricultural and grazing land, if
any, occupational health impacts
besides other impacts specific to
the proposed Project.
Detailed Environmental Monitoring Programme and
Environment Management Plan have been incorporated as a
Chapter-6, Page no. 185 & Chpater-10, page no. 204 of Draft
EIA/EMP report.
Occupational health impacts besides other impacts specific to
the proposed Project s has been detailed in Para 4.12, page no
177 of Chapter-4 of Draft EIA/EMP report.
39
Public Hearing points raised and
commitment of the Project
Proponent on the same along with
time bound Action Plan with
budgetary provisions to implement
the same should be provided and
also incorporated in the final
EIA/EMP Report of the Project.
Public Hearing points raised and commitment of the Project
Proponent on the same along with time bound Action Plan
with budgetary provisions to implement the same will be
provided after submission of Draft EIA/EMP report & public
hearing and same will be incorporated in the final EIA/EMP
Report of the Project.
40
Details of litigation pending
against the project, if any, with
direction /order passed by any
Court of Law against the Project
should be given.
There is no litigation or directions by any court.
41
The cost of the Project (capital cost
and recurring cost) as well as the
cost towards implementation of
EMP should be clearly spelt out.
Total Project cost is Rs. 30 Lacs.
Cost towards implementation of EMP:
S.No. Description
of Item
Budgetary
Calculation
Recurring
Cost
(Rs/Lakhs)
Per Annum
1 Air Pollution
Control
Water Sprinkling 1.20
2 Environmental
Monitoring
and
Management
Air quality Monitoring
Ground Water
sampling analysis
Surface Water
sampling analysis
Soil Sampling
Analysis
Noise Sampling
0.90
3 Green Belt Green Belt 0.61
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 18
S.
No
.
TOR Conditions Compliance Status
Development Development
Total Rs. 2.72
Lakh/annum
42
A Disaster management Plan shall
be prepared and included in the
EIA/EMP Report.
Disaster Management Plan has been assessed and detailed in
Para 7.5, page no 191of Chapter-7.
Privation measures for Disaster has been detailed in Para 7.5.2
Page no 192 of Chapter-7.
43
Benefits of the Project if the
Project is implemented should be
spelt out. The benefits of the
Project shall clearly indicate
environmental, social, economic,
employment potential, etc.
Environmental Benefits: About Rs. 2.72 lakhs/- Will be
spent by project proponent to environment management plan.
Green belt development along the roads and villages will
improve the environment condition of surrounding area.
Social Benefits: The project will contribute additional
revenue to the State and Central Govt. in the form of royalty
and other taxes etc. The people in area will be able to utilize
improved facilities with regard to education, health care,
hygiene, recreational opportunities, small business
opportunities etc.
Economic Benefits: Limestone Mining from Ajodha supply
to the various consumers in the state and outside the state that
will encourage the industries to enhance or improve their
capacity for the end users which will support the economic
growth and industrial improvement.
Employment potential: Direct or indirect employment job
opportunities to the local people will improve the earning and
spending capacity of the people.
Besides the above, the below mentioned general points are also to be followed:-
1. Executive Summary of the
EIA/EMP Report Complied
2.
All documents to be properly
referenced with index and
continuous page numbering.
Complied
3.
Where data are presented in the
Report especially in Tables, the
period in which the data were
collected and the sources should be
indicated.
Complied
4.
Project Proponent shall enclose all
the analysis/testing reports of
water, air, soil, noise etc. using the
MoEF&CC/NABL accredited
laboratories. All the original
analysis/testing reports should be
available during appraisal of the
Project.
All the analysis/testing reports of water, air, soil; noise etc.
using the NABL accredited laboratories named OTH& RC
has been enclosed as Annexure-8, page no. 352.
All the original analysis/testing reports will be available
during appraisal of the Project.
5. Where the documents provided are The documents provided are in a English language.
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 19
S.
No
.
TOR Conditions Compliance Status
in a language other than English,
an English translation should be
provided.
6.
The Questionnaire for
environmental appraisal of mining
projects as devised earlier by the
Ministry shall also be filled and
submitted.
Not Applicable
7.
While preparing the EIA report,
the instructions for the Proponents
and instructions for the
Consultants issued by MoEF vide
O.M. No. J-11013/41/2006-IA.II
(I) dated 4th August, 2009, which
are available on the website of this
Ministry, should be followed.
MoEF vide O.M. No. J- 11013/41/2006-IA. II (I) dated 4th
August, 2009 has been followed during preparing the EIA
report, the instructions for the Proponents and instructions for
the Consultants.
8.
Changes, if any made in the basic
scope and project parameters (as
submitted in Form-I and the PFR
for securing the TOR) should be
brought to the attention of
MoEF&CC with reasons for such
changes and permission should be
sought, as the TOR may also have
to be altered. Post Public Hearing
changes in structure and content of
the draft EIA/EMP (other than
modifications arising out of the
P.H. process) will entail
conducting the PH again with the
revised documentation.
There are no changes made in the basic scope and project
parameters
9.
As per the circular no. J-
11011/618/2010-IA.II (I) dated
30.5.2012, certified report of the
status of compliance of the
conditions stipulated in the
environment clearance for the
existing operations of the project,
should be obtained from the
Regional Office of Ministry of
Environment, Forest and Climate
Change, as may be applicable.
As per the circular no. J-11011/618/2010-IA. II (I) dated
30.5.2012, EC compliance will be submitted after grant of
EC.
10.
The EIA report should also include
(i) surface plan of the area
indicating contours of main
topographic features, drainage and
The EIA report has been include
(i) Surface plan of the area indicating contours of main
topographic features, drainage and mining area, (ii) geological
maps and sections and (iii) Sections of the mine pit and
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 20
S.
No
.
TOR Conditions Compliance Status
mining area, (ii) geological maps
and sections and (iii) sections of
the mine pit and external dumps, if
any, clearly showing the land
features of the adjoining area.
external dumps, if any, clearly showing the land features of
the adjoining area.
Additional ToR
1.
Project site specific details such as
distance of the project site from
nearest (1) Village (Habitation)
(2) Water Body:
River/Creek/Nallah/Lake/Pond/Ch
eck dam/ reservoir/Canal/French
well/Percolation well (3) National
Highway/Bridge Pier (4) State
Highway/ Bridge Pier (5) Railway
line/Bridge (6) Heritage site (7)
National Park/Wild life
Sanctuary/Reserved
Forest/Protected Forest shall be
included in the rapid EIA report to
be prepared covering one season
(Other than monsoon) data. A map
indicating the aerial distance of the
lease area from these entities.
Project Site specific details have been incorporated in
Chapter-1, Table 1.2 of Draft EIA/EMP report.
A topographical map has been prepared with all details and
incorporated in Draft EIA/EMP Report as Figure 2.1, page no
57.
2.
Distance of nearby mining lease
area from the periphery of the
proposed project including a map
covering distance of 1.0 km from
the periphery of the proposed
project. In case of no mining lease
area are existing within 500 m
periphery of the proposed project,
certificate of the concerned
geologist in this
regards)Commissioner of geology
& mining, Indian Bureau of mines,
GPCB, current lease renewed
status from Industries and Mine
department. Government of
Gujarat with opinion of the district
geologist regarding compliance of
all the conditions in lease deed and
copy of renewed lease etc. to be
incorporated.
There is no other mining lease present within the proposed
lease area.
3. Approved mining plan including
progressive mine closure plan shall
Approved Mining plan including mine closure plan has been
attached as Annexure-5, page no 269.
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 21
S.
No
.
TOR Conditions Compliance Status
be provided with EIA report.
Letter of approval of IBM shall
also be incorporated with
compliance of all the
recommendations mentioned in
approved mining plan.
4.
Specific Terms of Reference for the project on assessment of ecological damage, remediation
plan and natural and community resources augmentation plan for the proposals under
violation of EIA Notification 2006.
1.
Ecological damage shall be
assessed with respect to air, water,
land and other project & location
specific environment attributes.
The collection and analysis of data
shall be done by an environment
laboratory duly notified under
Environment (Protection) Act,
1986 or an environment laboratory
accredited by NABL, or a
laboratory of a council of
Scientific and Industrial Research
(CSIR) institution working in the
field of environment.
Ecological damage assessment report with respect to air,
water, land and other environmental attributes has been
enclosed as Annexure-9, Page no 406.
2.
The Environment Management
Plan shall be prepared which shall
comprise of the remediation plan
and community & natural resource
augmentation plan corresponding
to the ecological damage assessed
and economic benefits derived due
to violation. The remediation plan
and the natural & community
resource augmentation plan
prepared shall be included as
independent chapter in the EIA
report.
Environment Management Plan has been detailed in Chapter-
10, page no 204 of Draft EIA/EMP report.
3.
The project proponent shall submit
bank guarantee to Gujarat
Pollution Control Board prior to
grant of environmental clearance
equivalent to the amount of
remediation plan and natural &
community augmentation plans as
per the amount assessed in below
mentioned table as per the
indicative guideline. Po equivalent
The project proponent is in process for submit bank guarantee
to Gujarat Pollution Control Board prior to grant of
environmental clearance equivalent to the amount of
remediation plan and natural & community augmentation
plans as per the amount assessed in below mentioned table as
per the indicative guideline. equivalent to the CER amount as
per the MoEF&CC‟s office Memorandum No. F No 22-
65/2017-IA-III dated 01/05/2018 and will be comply during
final appraisal of EC.
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 22
S.
No
.
TOR Conditions Compliance Status
to the CER amount as per the
MoEF&CC‟s office Memorandum
No. F No 22-65/2017-IA-III dated
01/05/2018, whichever is higher.
The amount shall be recommended
by the SEAC and finalized by the
regulatory authority. The bank
guarantee shall be released after
successful implementation of the
remediation plan and Naturals and
Community Resource
Augmentation Plan, and after
recommendation by regional office
of the Ministry followed by
recommendation of the SEAC and
approval of the regulatory
authority.
4.
Gujarat Pollution Control Board
shall initiate credible legal action
against the project proponent under
the provisions of Environment
(Protection) Act, 1986 and further
no consent to operate to be issued
till the project is granted
Environment Clearance.
Will be followed
5.
A notarized undertaking stating
that (1). Any such violation shall
not be repeated in future. (2) All
the statutory requirement shall be
fully compiled with and (3). A
status quo shall be maintained at
the projects site and remaining
activity shall be carried out only
after obtaining Environmental
Clearance from SEIAA.
A notarized undertaking stating that (1). Any such violation
shall not be repeated in future. (2) All the statutory
requirement shall be fully compiled with and (3). A status quo
shall be maintained at the projects site and remaining activity
will be carried out only after obtaining Environmental
Clearance from SEIAA has been enclosed as Annexure-10
Page no 436.
6.
Applicable of CRZ Notification,
2011 shall be verified for the
project and if found applicable,
due procedure shall be followed as
per the CRZ Notification 2011.
Not applicable
5. Project Specific Conditions
1.
The project proponent shall give
an undertaking by way of affidavit
to comply with all the statutory
requirement and judgment of
Hon‟ble Supreme Court dated 2nd
Project Proponent will complies all the statutory requirement
and judgment of Hon'ble Supreme Court dated the 2nd
August 2017 in Writ Petition (Civil) No. 114 of 2014 in the
matter of Common Cause versus Union of India. Same has
been enclosed as Annexure-10, Page no 436.
SHRI ARJABHAI KHIMABHAI RATHOD
EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,
TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR
OVERSEAS MIN TECH CONSULTANTS | October2018 23
S.
No
.
TOR Conditions Compliance Status
August 2017 in Writ Petition
(Civil) No. 114 of 2014 in the
matter of common cause versus
Union of India and others before
grant of TOR/EC . The
undertaking inter alia include
commitment of PP not repeat any
violation in future.
2.
In case of violation of above
undertaking, the TOR/EC shall be
liable to be terminated forthwith.
Will be followed.
3.
The Environmental Clearance will
not be operational till such time the
project proponent complies with
all the statutory requirement and
judgment of Hon‟ble Supreme
Court dated 2nd
August 2017 in
Wrt Petition (Civil) No. 114 of
2014 in the matter of Common
Causes versus Union of India and
others.
Will be followed.
4.
State government concerned shall
ensure that mining operation shall
not commence till entire
compensation levies, if any, for
illegal mining paid by the Project
proponent through their respective
department of mining and Geology
in strict compliance of judgment of
Hon‟ble Supreme Court dated 2nd
August 2017 in Wrt Petition (Civil
No. 114 of 2014 in the matter of
Common Cause versus Union of
India and others.)
Will be followed.