Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest...

18
SHRI ARJABHAI KHIMABHAI RATHOD EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE, TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR OVERSEAS MIN TECH CONSULTANTS | October2018 6 1.1 ToR Compliance Compliance to ToR S. No . TOR Conditions Compliance Status 1 Year-wise production details since 1994 should be given, clearly stating the highest production achieved in any one year prior to 1994. It may also be categorically informed whether there had been any increase in production after the EIA Notification 1994 came into force, w.r.t. the highest production achieved prior to 1994. Year wise production detail since Inception of the mines has been incorporated in Chapter 1, Page no. 41, and Table 1.2 of Draft EIA/EMP Report. Certified report has been enclosed as Annexure-2. 2 A copy of the document in support of the fact that the Proponent is the rightful Lessee of the mine should be given. The lease was granted to Shri Arjabhai Khimabhai Rathod vide order no. MCR-1578-(R-4)-3/427-CHH issued on dated 24.04.1979 by Government of Gujarat for a period of 20 year. Lease deed was signed on 08.10.1979. Lease deed has been enclosed as Annexure-1, Page no. 242-259 of Draft EIA/EMP Report. Lease applied for renewal on 28.09.1998 and the renewal is under-process. The first renewal shall be from 08.10.1999 to 07.10.2019. The mining operations were commenced from 05.12.1979. Renewal letter has been enclosed as Annexure-2 Page no. 260-266 of Draft EIA/EMP Report. As per section 8(A) of new MMDR Amendment Act -2015 the lease is liable for lease period extension up to Dated 7/10/2029. Letter for the same has been enclosed as Annexure-3 Page no. 267 of Draft EIA/EMP Report. 3 All documents including approved mine plan, EIA and Public Hearing should be compatible with one another in terms of the mine lease area, production levels, waste generation and its management, mining technology etc. and should be in the name of the lessee. All documents including approved mine plan, EIA has been compatible with one another in terms of the mine lease area, production levels, waste generation and its management, mining technology etc. and has been All documents are in the name of Arjabhai Khimabhai Rathod. Public Hearing will be done after submission of Draft EIA/EMP report with consolation of SPCB, Gujarat. Mining Lease Area- 2.0 ha Production18,000 TPA Waste generation- There is no overburden or mineral rejects. Small amount of domestic waste will be generated for which dustbin will be kept at proper place and it will be disposed properly and regularly. The dump will be protected by retaining wall with garland drain, compacted and temporarily rehabilitated by sowing fast growing grass seeds.

Transcript of Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest...

Page 1: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 6

1.1 ToR Compliance

Compliance to ToR

S.

No

.

TOR Conditions Compliance Status

1

Year-wise production details since

1994 should be given, clearly

stating the highest production

achieved in any one year prior to

1994. It may also be categorically

informed whether there had been

any increase in production after the

EIA Notification 1994 came into

force, w.r.t. the highest production

achieved prior to 1994.

Year wise production detail since Inception of the mines has

been incorporated in Chapter 1, Page no. 41, and Table 1.2

of Draft EIA/EMP Report.

Certified report has been enclosed as Annexure-2.

2

A copy of the document in support

of the fact that the Proponent is the

rightful Lessee of the mine should

be given.

The lease was granted to Shri Arjabhai Khimabhai Rathod

vide order no. MCR-1578-(R-4)-3/427-CHH issued on dated

24.04.1979 by Government of Gujarat for a period of 20 year.

Lease deed was signed on 08.10.1979. Lease deed has been

enclosed as Annexure-1, Page no. 242-259 of Draft

EIA/EMP Report. Lease applied for renewal on 28.09.1998 and the renewal is

under-process. The first renewal shall be from 08.10.1999 to

07.10.2019. The mining operations were commenced from

05.12.1979. Renewal letter has been enclosed as Annexure-2

Page no. 260-266 of Draft EIA/EMP Report. As per section 8(A) of new MMDR Amendment Act -2015

the lease is liable for lease period extension up to Dated

7/10/2029. Letter for the same has been enclosed as

Annexure-3 Page no. 267 of Draft EIA/EMP Report.

3

All documents including approved

mine plan, EIA and Public Hearing

should be compatible with one

another in terms of the mine lease

area, production levels, waste

generation and its management,

mining technology etc. and should

be in the name of the lessee.

All documents including approved mine plan, EIA has been

compatible with one another in terms of the mine lease area,

production levels, waste generation and its management,

mining technology etc. and has been All documents are in the

name of Arjabhai Khimabhai Rathod.

Public Hearing will be done after submission of Draft

EIA/EMP report with consolation of SPCB, Gujarat.

Mining Lease Area- 2.0 ha

Production–18,000 TPA

Waste generation-

There is no overburden or mineral rejects.

Small amount of domestic waste will be generated for which

dustbin will be kept at proper place and it will be disposed

properly and regularly.

The dump will be protected by retaining wall with garland

drain, compacted and temporarily rehabilitated by sowing fast

growing grass seeds.

Page 2: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 7

S.

No

.

TOR Conditions Compliance Status

Mining Technology –Opencast Semi-Mechanized Method

Name of the Lessee – Shri Arjabhai Khimabhai Rathod

4

All corner coordinates of the mine

lease area, superimposed on a High

Resolution Imagery/toposheet,

topographic sheet geomorphology

and geology of the area should be

provided. Such an Imagery of the

proposed area should clearly show

the land use and other ecological

features of the study area (core and

buffer zone).

All corner coordinates of the lease area has been

superimposed in Topographical map. Refer Figure 2-1 of

Chapter-2.

Image of the proposed area for show the land use and other

ecological features of the study area (core and buffer zone)

has been referred in Figure 3-1 in Chapter-3 of Draft

EIA/EMP report.

5

Information should be provided in

Survey of India Toposheet in

1:50,000 scale indicating

geological map of the area,

geomorphology of land forms of

the area, existing minerals and

mining history of the area,

important water bodies, streams

and rivers and soil characteristics.

A map of Survey of India Toposheet in 1:50,000 scale

indicating geology & geomorphology of the area, has been

given in Figure 2.1 for existing minerals and mining history,

important water bodies, streams & rivers & soil characteristics

has been given in has been shown in Figure 3.1, Page no. 83

of Draft EIA/EMP Report.

6

Details about the land proposed for

mining activities should be given

with information as to whether

mining conforms to the land use

policy of the State; land diversion

for mining should have approval

from State land use board or the

concerned authority.

The total mining lease area (2.0 ha) is Non-forest Government

waste land. Mining lease was granted by Industry, Mines and

Power department of Government of Gujarat in favor of Shri

Arjabhai Khimabhai Rathod vide order no. MCR-1578-(R-4)-

3/427-CHH issued on 24.04.1979 for a period of 20 years.

7

It should be clearly stated whether

the proponent Company has a well

laid down Environment Policy

approved by its Board of

Directors? If so, it may be spelt out

in the EIA Report with description

of the prescribed operating

process/procedures to bring into

focus any

infringement/deviation/violation of

the environmental or forest norms/

conditions? The hierarchical

system or administrative order of

the Company to deal with the

environmental issues and for

ensuring compliance with the EC

conditions may also be given. The

The company is having well laid down Environmental Policy

duly approved by its Board of Directors & the same is

enclosed as Annexure 6, Page no. 348-350.

Standard Operating Procedures (SoPs) have been incorporated

in the Corporate Environmental Policy of the company.

The hierarchical system or administrative order of the

company to deal with the environmental issues and for

ensuring compliance with the EC conditions etc. has been

given in Chapter- 10, Page no. 220 of Draft EIA/EMP Report.

Page 3: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 8

S.

No

.

TOR Conditions Compliance Status

system of reporting of non-

compliances / violations of

environmental norms to the Board

of Directors of the Company

and/or shareholders or

stakeholders at large, may also be

detailed in the EIA Report.

8.

Issue relating to Mine safety

including subsidence study in case

of underground mining and slope

study in case of open cast mining

blasting study study etc. should be

detailed. The proposed safeguard

measures in each case should also

be provided.

The proposed method of Mining will be Open-cast Manual

mining method by forming benches of 3.0 m height and width

more than height comprising Jack Hammer drilling, manual

breaking & loading of limestone with Tractor trolley.

Mines relating to mine safety has been adopted and same has

been incorporated in Chapter 4, Page no. 179-180 of Draft

EIA/EMP Report.

Mild Drilling & Blasting is proposed.

The proposed safeguard measures in each case has been

given in Chapter 4, page no 159 of Draft EIA/EMP Report.

9

The study area will comprise of 10

km zone around the mine lease

from lease periphery and the data

contained in the EIA such as waste

generation etc. should be for the

life of the mine / lease period.

The Study area of the proposed mining project comprises of

10 km zone around the mining Lease boundary. Map showing

core zone (ML area) and buffer zone (10 km radius from the

lease boundary) has been prepared and given in Figure-2.1,

Page no 56.

There will be no Top soil or waste will be generated due to

Mining.

Data like reserves, waste generation up to life of mine is given

in Chapter 2, page no. 61-63 of Draft EIA/EMP Report.

10

Land use of the study area

delineating forest area, agricultural

land, grazing land, wildlife

sanctuary, national park, migratory

routes of fauna, water bodies,

human settlements and other

ecological features should be

indicated. Land use plan of the

mine lease area should be prepared

to encompass preoperational,

operational and post operational

phases and submitted. Impact, if

any, of change of land use should

be given.

Land use / land cover map of the study area showing present

land use pattern & also, delineating agricultural land, water

bodies, forest land, human settlements and other ecological

features etc. is given in Figure-3.1, Page no. 83 of Chapter 3

of Draft EIA/EMP Report.

Land use plan of the mine lease area in pre-operational,

operational and post operational phases has been prepared and

given in Table 3.1 of Draft EIA/EMP report.

No, mineral reject & top soil will be generated during this

scheme period (five years). Whole area of 1.6842(excavated

area in plan period) will be converted into water reservoir.

11 Details of the land for any Over

Burden Dumps outside the mine

No land for any Over Burden Dumps outside the mine lease is

proposed hence no R & R issue.

Page 4: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 9

S.

No

.

TOR Conditions Compliance Status

lease, such as extent of land area,

distance from mine lease, its land

use, R&R issues, if any, should be

given.

12

A Certificate from the Competent

Authority in the State Forest

Department should be provided,

confirming the involvement of

forest land, if any, in the project

area. In the event of any contrary

claim by the Project Proponent

regarding the status of forests, the

site may be inspected by the State

Forest Department along with the

Regional Office of the Ministry to

ascertain the status of forests,

based on which, the Certificate in

this regard as mentioned above be

issued. In all such cases, it would

be desirable for representative of

the State Forest Department to

assist the Expert Appraisal

Committees.

The total mining lease area (2.00 ha) is a Govt. Waste land.

Deputy Conservator of Forest, Forest Department, Junagad

has been certified on dated 22.11.2017 that there is a Forest

extension present at a distance of 6.7 KM and Gir Century at a

distance of 21.9 km from the lease area. Forest letter has been

enclosed as Annexure-7, page no 351 of Draft EIA/EMP

Report

13

Status of forestry clearance for the

broken up area and virgin

forestland involved in the Project

including deposition of net present

value (NPV) and compensatory

afforestation (CA) should be

indicated. A copy of the forestry

clearance should also be furnished.

No forest clearance is required as the proposed mining lease

area is Government Waste Land (Non Forest Land).

NOC from forest department has been has been enclosed as

Annexure-7, Page no 351of Draft EIA/EMP Report

14

Implementation status of

recognition of forest rights under

the Scheduled Tribes and other

Traditional Forest Dwellers

(Recognition of Forest Rights)

Act, 2006 should be indicated.

Not Applicable

15

The vegetation in the RF / PF areas

in the study area, with necessary

details, should be given.

Reserved / Protected Forest falling within 10 Km radius of the

mining lease area.

1. Reserved forest ~ 8..20Km in South direction form mine

site

2. Reserved forest ~ 7.0 North-East direction form mine site

3. Reserved forest ~ 6.74, North direction form mine site

Same has been marked on Environment Sensitive map of

Figure 1.3 Page no 43 of Draft EIA/EMP report.

Details of Flora and fauna found in the study area are given

Page 5: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 10

S.

No

.

TOR Conditions Compliance Status

in Chapter 3 Page no 126 &131 of Draft EIA/EMP Report.

16

A study shall be got done to

ascertain the impact of the Mining

Project on wildlife of the study

area and details furnished. Impact

of the project on the wildlife in the

surrounding and any other

protected area and accordingly,

detailed mitigative measures

required, should be worked out

with cost implications and

submitted.

Biological study has been done for the project and it has been

assessed that there will no adverse effect will be on wildlife

because there is no wild life activity found.

Same has been details the impact on surrounding wildlife and

mitigation measures are given in Chapter 4, page no. 171

Draft EIA/EMP Report.

17

Location of National Parks,

Sanctuaries, Biosphere Reserves,

Wildlife Corridors, Ramsar site

Tiger/Elephant Reserves (existing

as well as proposed), if any, within

10 km of the mine lease should be

clearly indicated, supported by a

location map duly authenticated by

Chief Wildlife Warden. Necessary

clearance, as may be applicable to

such projects due to proximity of

the ecologically sensitive areas as

mentioned above, should be

obtained from the Standing

Committee of National Board of

Wildlife and copy furnished.

No National Parks, Wildlife Sanctuaries, Biosphere Reserves,

wildlife corridors, Tiger/Elephant Reserves (existing as well

as proposed) etc. falls within the study area (10 km radius of

the mine boundary).

18

A detailed biological study of the

study area [core zone and buffer

zone (10 km radius of the

periphery of the mine lease)] shall

be carried out. Details of flora and

fauna, endangered, endemic and

RET Species duly authenticated,

separately for core and buffer zone

should be furnished based on such

primary field survey, clearly

indicating the Schedule of the

fauna present. In case of any

scheduled-I fauna found in the

study area, the necessary plan

along with budgetary provisions

for their conservation should be

prepared in consultation with State

Forest and Wildlife Department

Detailed Biological study for the study area (core zone &

buffer zone) has been conducted.

List of Flora & Fauna for core & buffer zone has been

submitted to DFO for approval & the same is under process

with the Forest Department.

There is no Schedule I species found within the proposed

area.

Page 6: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 11

S.

No

.

TOR Conditions Compliance Status

and details furnished. Necessary

allocation of funds for

implementing the same should be

made as part of the project cost.

19

Proximity to Areas declared as

„Critically Polluted‟ or the Project

areas likely to come under the

„Aravali Range‟, (attracting court

restrictions for mining Operations)

should also be indicated and where

so required, clearance

certifications from the prescribed

Authorities, such as the SPCB or

State Mining Dept. Should be

secured and furnished to the effect

that the proposed mining activities

could be considered.

The Mine site does not fall under the Critically Polluted Area

and „Aravali Range‟ and it does not attract any court

restriction for mining operation.

20

Similarly, for coastal Projects, A

CRZ map duly authenticated by

one of the authorized agencies

demarcating LTL. HTL, CRZ area,

location of the mine lease w.r.t

CRZ, coastal features such as

mangroves, if any, should be

furnished. (Note: The Mining

Projects falling under CRZ would

also need to obtain approval of the

concerned Coastal Zone

Management Authority).

Not Applicable, as the project does not falls in Coastal area.

21

R&R Plan/compensation details

for the Project Affected People

(PAP) should be furnished. While

preparing the R&R Plan, the

relevant State/National

Rehabilitation & Resettlement

Policy should be kept in view. In

respect of SCs/STs and other

weaker sections of the society in

the study area, a need based

sample survey, family-wise,

should be undertaken to assess

their requirements, and action

programmes prepared and

submitted accordingly, integrating

the sectoral programmes of line

departments of the State

The total mining lease area (2.0 ha) is a Govt. Waste land. No

houses, villages connecting road and infrastructure existing in

the area will be disturbed.

Therefore no Rehabilitation and resettlement action plan is

required.

Page 7: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 12

S.

No

.

TOR Conditions Compliance Status

Government. It may be clearly

brought out whether the village(s)

located in the mine lease area will

be shifted or not. The issues

relating to shifting of village(s)

including their R&R and socio-

economic aspects should be

discussed in the Report.

22

One season (non-monsoon) [i.e.

March - May (Summer Season);

October - December (post

monsoon season) ; December -

February (winter season)] primary

baseline data on ambient air

quality as per CPCB Notification

of 2009, water quality, noise level,

soil and flora and fauna shall be

collected and the AAQ and other

data so compiled presented date-

wise in the EIA and EMP Report.

Site specific Meteorological data

should also be collected. The

location of the monitoring stations

should be such as to represent

whole of the study area and

justified keeping in view the pre-

dominant downwind direction and

location of sensitive receptors.

There should be at least one

monitoring station within 500 m of

the mine lease in the pre-dominant

downwind direction. The

mineralogical composition of

PM10, particularly for free silica,

should be given.

Primary baseline data on ambient air quality, water quality,

noise level, soil and flora and fauna are collected in Post

Monsoon Season (October, November, December) 2018.

Ambient Air quality has been determined by measuring the

concentration of parameters like P.M.2.5, P.M.10, SO2, NOx

according to the latest standards prescribed by CPCB. Site-

specific meteorological data has also been collected. The

location of the monitoring stations (minimum 7) has been

justified.

The selections criteria for monitoring locations have been

given in Chapter-3, page no. 98. Date wise collected baseline

AAQ data have formed part of EIA and EMP report. The

details of the same are given in Chapter 3, page no. 98..

The monitoring has been carried out by NABL approved

laboratory and copy of the certificate 8 & lab analyses report

has been enclose as Annexure-8, page no 352-405 of Draft

EIA/EMP Report.

23

Air quality modeling should be

carried out for prediction of impact

of the project on the air quality of

the area. It should also take into

account the impact of movement

of vehicles for transportation of

mineral. The details of the model

used and input parameters used for

modeling should be provided. The

air quality contours may be shown

on a location map clearly

indicating the location of the site,

Air quality modeling has been carried out for prediction of

impact of the project on the air quality of the area. The impact

of movement of vehicles for transportation of mineral has

been taken into account. The details of the model used and

input parameters used for modeling are given in Chapter 4,

page no 153 of the draft EIA report.

The Isopleths have been drawn on the topographical map. The

wind rose diagram has been prepared which is showing NE

pre-dominant wind direction and shown in Chapter-3, Page

no. 96-97.

Page 8: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 13

S.

No

.

TOR Conditions Compliance Status

location of sensitive receptors, if

any, and the habitation. The wind

roses showing pre-dominant wind

direction may also be indicated on

the map.

24

The water requirement for the

Project, its availability and source

should be furnished. A detailed

water balance should also be

provided. Fresh water requirement

for the Project should be indicated.

The total water requirement for the Ajodha Limestone Mine

is 3.83 KLD. Propose Quantity

(KLD)

Remarks

Domestic 1.44 0.320 KLD fresh water will used for

drinking purpose Dust

Suppression

0.39

Greenbelt

Development

2.0

Total 3.83

Detailed discussion has been done in Chapter-2, Point No.

2.15, page no.69 of Draft EIA/EMP Report.

25

Necessary clearance from the

Competent Authority for drawl of

requisite quantity of water for the

Project should be provided.

No groundwater will be abstracted for use at mine site.

26

Description of water conservation

measures proposed to be adopted

in the Project should be given.

Details of rainwater harvesting

proposed in the Project, if any,

should be provided.

In the proposed mining, the water will be required during

water sprinkling.

The rain water collected in the mine pit will be pumped out

and fed to the nearby pond by flexible pipes.

27

Impact of the Project on the water

quality, both surface and

groundwater, should be assessed

and necessary safeguard measures,

if any required, should be

provided.

Surface water: Surface water will not likely to be affected.

All water drains from the pits will be constructed in such a

way that the water will be drained to nallas

Ground Water: The ultimate depth of the pit would be done

at 16 mRL and the ground water table in area is beyond 10-15

m bgl hence the mining will be maintain up to 5-10 m above

the ground water table. So mining activity will not intersect

the ground water table at any point.

28

Based on actual monitored data, it

may clearly be shown whether

working will intersect

groundwater. Necessary data and

documentation in this regard may

be provided. In case the working

will intersect groundwater table, a

detailed Hydro Geological Study

should be undertaken and Report

Based on actual monitored data it has been found that:

Elevation range (Buffer

Zone)

21.43 m RL – 18.52

Depth of workings

(from natural

surface level starting

the pit excavation)

19.0 m RL- 16.0 m RL

Ultimate Working Depth 16.0 mRL

Page 9: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 14

S.

No

.

TOR Conditions Compliance Status

furnished. The Report inter-alia,

shall include details of the aquifers

present and impact of mining

activities on these aquifers.

Necessary permission from Central

Ground Water Authority for

working below ground water and

for pumping of ground water

should also be obtained and copy

furnished.

Difference from surface

level to ultimate working

pit

3.0 m

Ground Water Table Pre Monsoon –15-20 m BGL

Post Monsoon- 10-12 m BGL

Area 2.0 hect.

So mining activity will not intersect the ground water table at

any point.

29

Details of any stream, seasonal or

otherwise, passing through the

lease area and modification /

diversion proposed, if any, and the

impact of the same on the

hydrology should be.

There is a Sarswati River which is 1.40 km flows in South

west direction from the mining lease area. Rain water falling

around the lease area will be diverted to the low lying area.

There is no stream or seasonal water bodies passing through

the lease area.

So there will be no change in water bodies or the land surface

affecting drainage or run‐off.

30

Information on site elevation,

working depth, groundwater table

etc. Should be provided both in

AMSL and BGL. A schematic

diagram may also be provided for

the same.

Elevation range (Buffer

Zone)

21.43 m RL – 18.52

Depth of workings

(from natural

surface level starting

the pit excavation)

19.0 m RL- 16.0 m RL

Ultimate Working Depth 16.0 mRL

Difference from surface

level to ultimate working

pit

3.0 m

Ground Water Table Pre Monsoon –15-20 m BGL

Post Monsoon- 10-12 m BGL

Area 2.0 hect.

31

A time bound Progressive

Greenbelt Development Plan shall

be prepared in a tabular form

(indicating the linear and

quantitative coverage, plant

species and time frame) and

submitted, keeping in mind, the

same will have to be executed up

front on commencement of the

Project. Phase-wise plan of

plantation and compensatory

afforestation should be charted

clearly indicating the area to be

covered under plantation and the

species to be planted. The details

of plantation already done should

A time bound progressive greenbelt development plan is

given in Table 10.2 Page no 224 of Chapter-10. Greenbelt developments Programme within M.L. area

Year of

Plantation. Proposed

Plantation

Area

cover

in ha.

Species Place of

Plantation

1st Year 40 0.0631 Beal,

Amla,

Mango,

On the

statuary

barrier

and along

the haul

road

2nd

Year 40 0.0631

3rd

Year 40 0.0631

4th

Year 40 0.0631

5th

Year 40 0.0631

Total 200 0.315

Greenbelt developments Programme outside the M.L area

Year of

Plantation. Proposed

Plantation

Area

cover

in ha.

Species Place of

Plantation

Page 10: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 15

S.

No

.

TOR Conditions Compliance Status

be given. The plant species

selected for green belt should have

greater ecological value and should

be of good utility value to the local

population with emphasis on local

and native species and the species

which are tolerant to pollution.

1st Year 43 0.0688

Jamun,

Arjun,

Sissoo

Along the

road-

sides,

Gram

Sabha,

nearest

village,

nearby

schools &

hospitals

2nd

Year 43 0.0688

3rd

Year 43 0.0688

4th

Year 43 0.0688

5th

Year 43 0.0688

Total 215 0.344

32

Impact on local transport

infrastructure due to the Project

should be indicated. Projected

increase in truck traffic as a result

of the Project in the present road

network (including those outside

the Project area) should be worked

out, indicating whether it is

capable of handling the

incremental load. Arrangement for

improving the infrastructure, if

contemplated (including action to

be taken by other agencies such as

State Government) should be

covered. Project Proponent shall

conduct Impact of Transportation

study as per Indian Road Congress

Guidelines.

The Impact on local transport and infrastructure due to the

project will be on positive side as Post project PCU will be

1184 PCUs (1161.5 PCUs Existing + 22.5 PCUs Post) on SH-

6 (Somnath-una highway).

Project site to

NH

Vol. of

vehicle in

PCU/day

Capacity of

Roads in

PCU/day

LOS

SH-6 (Somnath-

una highway), 1184 2000

0.59 (Good/

Average/ Fair)

Not much impact will be there on the local transport. The

LOS value from the proposed mine may be “Good/ Average/

Fair” for State highway-6 (Somnath to Una Highway). So, the

additional load on the carrying capacity of the concern roads

is not likely to have any significant adverse effect.

Traffic Density is carried out at one locations on (Mine site to

SH-6) and the same is given in Chapter 2, Page no. 73

33

Details of the onsite shelter and

facilities to be provided to the

mine workers should be included

in the EIA Report.

Mine office & First Aid Station ,Store Room,Rest Shelter,

Drinking water facility, Domestic Water & Dust Suppression,

Adequate lighting arrangements: Storage of machinery, tools,

oil and grease, Toilets will be provides for workers.

Details of the infrastructure facilities to be provided for the

mine workers is given in Chapter-2 Page no. 71.

34

Conceptual post mining land use

and Reclamation and Restoration

of mined out areas (with plans and

with adequate number of sections)

should be given in the EIA report.

Post-Mining (Conceptual) Land Use of Core Zone with

Reclamation and Restoration of mined out areas has been

shown below:

S.

No. Head

Present

Land Use

At the end of

Fifth Year

At the end of

mine

1 Area under

mining

0.4270 1.1455 1.5725

2 Storage for top

soil

Nil Nil Nil

3 Waste dump site Nil Nil Nil

4 Mineral storage Nil Nil Nil

Page 11: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 16

S.

No

.

TOR Conditions Compliance Status

5 Infrastructure

workshop,

administrative

building etc.

0.0355 Nil 0.0355

6 Roads 0. 0762 Nil 0. 0762

7 Railways Nil Nil Nil

8 Tailing Road Nil Nil Nil

9 Effluent

treatment plant

Nil Nil Nil

10 Mineral

separation Plant

Nil Nil Nil

11 Township area Nil Nil Nil

12 Other

(green belt)

0.200 0.1158 0.3158

13 Virgin Area 1.2613 Nil Nil

Grand Total 2.000 2.000 2.000

& Conceptual Plan has been enclosed as Plate-7.

35

Occupational Health impacts of the

Project should be anticipated and

the proposed preventive measures

spelt out in detail. Details of pre-

placement medical examination

and periodical medical

examination schedules should be

incorporated in the EMP. The

project specific occupational

health mitigation measures with

required facilities proposed in the

mining area may be detailed.

The Mines Act and the Mines Rules, 1955 will be followed

for Occupational health and safety.

Impact & preventive measures on Occupational Health :

Near miss incident or injury which may require self-

administered first aid.

Injury requiring onsite treatment by medical

practitioner.

Serious injury requiring offsite treatment by medical

practitioner.

Regular Medical checkup of workers will be done to

check occupational disease, if any, and respective

records will be maintained at the mine.

Project specific occupational health mitigation measures with

required facilities proposed in the mining & Details of pre-

placement medical examination and periodical medical

examination schedules has been detailed in Table 4.6 of

Chapter-4, page no.177 of Draft EIA/EMP report.

36

Public health implications of the

Project and related activities for

the population in the impact zone

should be systematically evaluated

and the proposed remedial

measures should be detailed along

with budgetary allocations.

Limestone mining can cause such as Skin Diseases, Lung

diseases, Stomach diseases and Eye/Skin.

Impact of Limestone mining on Public health implication &

remedial measures has been detailed in Table 4.7 & Table 4.8

Page no. 177 of Chapter-4.

Budgetary amount:

About Rs. 0.50 Lakh/annum will be proposed for

Health check - up camps for villagers (the camp will

be conducted twice during the year for general health

check-up). About Rs. 0.80 Lakh/annum will be proposed for

health facility & insurance cover for mine workers.

37

Measures of socio economic

significance and influence to the

local community proposed to be

A field based socio economic survey has been conducted and

detailed in Para 3.16 of Chapter-3 Page no. 135.

The people around the mine area will get direct or

Page 12: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 17

S.

No

.

TOR Conditions Compliance Status

provided by the Project Proponent

should be indicated. As far as

possible, quantitative dimensions

may be given with time frames for

implementation.

indirect employment opportunities on mine and at

getting associated with ancillaries.

The villagers employed get the benefit of health

surveillance done statutorily for all workers under

Mines Rules.

Impact of proposed Limestone mining on Socio economic

conditions has been discussed in Para 4.10, page no. 172 of

Chater-4.

38

Detailed environmental

management plan (EMP) to

mitigate the environmental impacts

which, should inter-alia include the

impacts of change of land use, loss

of agricultural and grazing land, if

any, occupational health impacts

besides other impacts specific to

the proposed Project.

Detailed Environmental Monitoring Programme and

Environment Management Plan have been incorporated as a

Chapter-6, Page no. 185 & Chpater-10, page no. 204 of Draft

EIA/EMP report.

Occupational health impacts besides other impacts specific to

the proposed Project s has been detailed in Para 4.12, page no

177 of Chapter-4 of Draft EIA/EMP report.

39

Public Hearing points raised and

commitment of the Project

Proponent on the same along with

time bound Action Plan with

budgetary provisions to implement

the same should be provided and

also incorporated in the final

EIA/EMP Report of the Project.

Public Hearing points raised and commitment of the Project

Proponent on the same along with time bound Action Plan

with budgetary provisions to implement the same will be

provided after submission of Draft EIA/EMP report & public

hearing and same will be incorporated in the final EIA/EMP

Report of the Project.

40

Details of litigation pending

against the project, if any, with

direction /order passed by any

Court of Law against the Project

should be given.

There is no litigation or directions by any court.

41

The cost of the Project (capital cost

and recurring cost) as well as the

cost towards implementation of

EMP should be clearly spelt out.

Total Project cost is Rs. 30 Lacs.

Cost towards implementation of EMP:

S.No. Description

of Item

Budgetary

Calculation

Recurring

Cost

(Rs/Lakhs)

Per Annum

1 Air Pollution

Control

Water Sprinkling 1.20

2 Environmental

Monitoring

and

Management

Air quality Monitoring

Ground Water

sampling analysis

Surface Water

sampling analysis

Soil Sampling

Analysis

Noise Sampling

0.90

3 Green Belt Green Belt 0.61

Page 13: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 18

S.

No

.

TOR Conditions Compliance Status

Development Development

Total Rs. 2.72

Lakh/annum

42

A Disaster management Plan shall

be prepared and included in the

EIA/EMP Report.

Disaster Management Plan has been assessed and detailed in

Para 7.5, page no 191of Chapter-7.

Privation measures for Disaster has been detailed in Para 7.5.2

Page no 192 of Chapter-7.

43

Benefits of the Project if the

Project is implemented should be

spelt out. The benefits of the

Project shall clearly indicate

environmental, social, economic,

employment potential, etc.

Environmental Benefits: About Rs. 2.72 lakhs/- Will be

spent by project proponent to environment management plan.

Green belt development along the roads and villages will

improve the environment condition of surrounding area.

Social Benefits: The project will contribute additional

revenue to the State and Central Govt. in the form of royalty

and other taxes etc. The people in area will be able to utilize

improved facilities with regard to education, health care,

hygiene, recreational opportunities, small business

opportunities etc.

Economic Benefits: Limestone Mining from Ajodha supply

to the various consumers in the state and outside the state that

will encourage the industries to enhance or improve their

capacity for the end users which will support the economic

growth and industrial improvement.

Employment potential: Direct or indirect employment job

opportunities to the local people will improve the earning and

spending capacity of the people.

Besides the above, the below mentioned general points are also to be followed:-

1. Executive Summary of the

EIA/EMP Report Complied

2.

All documents to be properly

referenced with index and

continuous page numbering.

Complied

3.

Where data are presented in the

Report especially in Tables, the

period in which the data were

collected and the sources should be

indicated.

Complied

4.

Project Proponent shall enclose all

the analysis/testing reports of

water, air, soil, noise etc. using the

MoEF&CC/NABL accredited

laboratories. All the original

analysis/testing reports should be

available during appraisal of the

Project.

All the analysis/testing reports of water, air, soil; noise etc.

using the NABL accredited laboratories named OTH& RC

has been enclosed as Annexure-8, page no. 352.

All the original analysis/testing reports will be available

during appraisal of the Project.

5. Where the documents provided are The documents provided are in a English language.

Page 14: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 19

S.

No

.

TOR Conditions Compliance Status

in a language other than English,

an English translation should be

provided.

6.

The Questionnaire for

environmental appraisal of mining

projects as devised earlier by the

Ministry shall also be filled and

submitted.

Not Applicable

7.

While preparing the EIA report,

the instructions for the Proponents

and instructions for the

Consultants issued by MoEF vide

O.M. No. J-11013/41/2006-IA.II

(I) dated 4th August, 2009, which

are available on the website of this

Ministry, should be followed.

MoEF vide O.M. No. J- 11013/41/2006-IA. II (I) dated 4th

August, 2009 has been followed during preparing the EIA

report, the instructions for the Proponents and instructions for

the Consultants.

8.

Changes, if any made in the basic

scope and project parameters (as

submitted in Form-I and the PFR

for securing the TOR) should be

brought to the attention of

MoEF&CC with reasons for such

changes and permission should be

sought, as the TOR may also have

to be altered. Post Public Hearing

changes in structure and content of

the draft EIA/EMP (other than

modifications arising out of the

P.H. process) will entail

conducting the PH again with the

revised documentation.

There are no changes made in the basic scope and project

parameters

9.

As per the circular no. J-

11011/618/2010-IA.II (I) dated

30.5.2012, certified report of the

status of compliance of the

conditions stipulated in the

environment clearance for the

existing operations of the project,

should be obtained from the

Regional Office of Ministry of

Environment, Forest and Climate

Change, as may be applicable.

As per the circular no. J-11011/618/2010-IA. II (I) dated

30.5.2012, EC compliance will be submitted after grant of

EC.

10.

The EIA report should also include

(i) surface plan of the area

indicating contours of main

topographic features, drainage and

The EIA report has been include

(i) Surface plan of the area indicating contours of main

topographic features, drainage and mining area, (ii) geological

maps and sections and (iii) Sections of the mine pit and

Page 15: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 20

S.

No

.

TOR Conditions Compliance Status

mining area, (ii) geological maps

and sections and (iii) sections of

the mine pit and external dumps, if

any, clearly showing the land

features of the adjoining area.

external dumps, if any, clearly showing the land features of

the adjoining area.

Additional ToR

1.

Project site specific details such as

distance of the project site from

nearest (1) Village (Habitation)

(2) Water Body:

River/Creek/Nallah/Lake/Pond/Ch

eck dam/ reservoir/Canal/French

well/Percolation well (3) National

Highway/Bridge Pier (4) State

Highway/ Bridge Pier (5) Railway

line/Bridge (6) Heritage site (7)

National Park/Wild life

Sanctuary/Reserved

Forest/Protected Forest shall be

included in the rapid EIA report to

be prepared covering one season

(Other than monsoon) data. A map

indicating the aerial distance of the

lease area from these entities.

Project Site specific details have been incorporated in

Chapter-1, Table 1.2 of Draft EIA/EMP report.

A topographical map has been prepared with all details and

incorporated in Draft EIA/EMP Report as Figure 2.1, page no

57.

2.

Distance of nearby mining lease

area from the periphery of the

proposed project including a map

covering distance of 1.0 km from

the periphery of the proposed

project. In case of no mining lease

area are existing within 500 m

periphery of the proposed project,

certificate of the concerned

geologist in this

regards)Commissioner of geology

& mining, Indian Bureau of mines,

GPCB, current lease renewed

status from Industries and Mine

department. Government of

Gujarat with opinion of the district

geologist regarding compliance of

all the conditions in lease deed and

copy of renewed lease etc. to be

incorporated.

There is no other mining lease present within the proposed

lease area.

3. Approved mining plan including

progressive mine closure plan shall

Approved Mining plan including mine closure plan has been

attached as Annexure-5, page no 269.

Page 16: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 21

S.

No

.

TOR Conditions Compliance Status

be provided with EIA report.

Letter of approval of IBM shall

also be incorporated with

compliance of all the

recommendations mentioned in

approved mining plan.

4.

Specific Terms of Reference for the project on assessment of ecological damage, remediation

plan and natural and community resources augmentation plan for the proposals under

violation of EIA Notification 2006.

1.

Ecological damage shall be

assessed with respect to air, water,

land and other project & location

specific environment attributes.

The collection and analysis of data

shall be done by an environment

laboratory duly notified under

Environment (Protection) Act,

1986 or an environment laboratory

accredited by NABL, or a

laboratory of a council of

Scientific and Industrial Research

(CSIR) institution working in the

field of environment.

Ecological damage assessment report with respect to air,

water, land and other environmental attributes has been

enclosed as Annexure-9, Page no 406.

2.

The Environment Management

Plan shall be prepared which shall

comprise of the remediation plan

and community & natural resource

augmentation plan corresponding

to the ecological damage assessed

and economic benefits derived due

to violation. The remediation plan

and the natural & community

resource augmentation plan

prepared shall be included as

independent chapter in the EIA

report.

Environment Management Plan has been detailed in Chapter-

10, page no 204 of Draft EIA/EMP report.

3.

The project proponent shall submit

bank guarantee to Gujarat

Pollution Control Board prior to

grant of environmental clearance

equivalent to the amount of

remediation plan and natural &

community augmentation plans as

per the amount assessed in below

mentioned table as per the

indicative guideline. Po equivalent

The project proponent is in process for submit bank guarantee

to Gujarat Pollution Control Board prior to grant of

environmental clearance equivalent to the amount of

remediation plan and natural & community augmentation

plans as per the amount assessed in below mentioned table as

per the indicative guideline. equivalent to the CER amount as

per the MoEF&CC‟s office Memorandum No. F No 22-

65/2017-IA-III dated 01/05/2018 and will be comply during

final appraisal of EC.

Page 17: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 22

S.

No

.

TOR Conditions Compliance Status

to the CER amount as per the

MoEF&CC‟s office Memorandum

No. F No 22-65/2017-IA-III dated

01/05/2018, whichever is higher.

The amount shall be recommended

by the SEAC and finalized by the

regulatory authority. The bank

guarantee shall be released after

successful implementation of the

remediation plan and Naturals and

Community Resource

Augmentation Plan, and after

recommendation by regional office

of the Ministry followed by

recommendation of the SEAC and

approval of the regulatory

authority.

4.

Gujarat Pollution Control Board

shall initiate credible legal action

against the project proponent under

the provisions of Environment

(Protection) Act, 1986 and further

no consent to operate to be issued

till the project is granted

Environment Clearance.

Will be followed

5.

A notarized undertaking stating

that (1). Any such violation shall

not be repeated in future. (2) All

the statutory requirement shall be

fully compiled with and (3). A

status quo shall be maintained at

the projects site and remaining

activity shall be carried out only

after obtaining Environmental

Clearance from SEIAA.

A notarized undertaking stating that (1). Any such violation

shall not be repeated in future. (2) All the statutory

requirement shall be fully compiled with and (3). A status quo

shall be maintained at the projects site and remaining activity

will be carried out only after obtaining Environmental

Clearance from SEIAA has been enclosed as Annexure-10

Page no 436.

6.

Applicable of CRZ Notification,

2011 shall be verified for the

project and if found applicable,

due procedure shall be followed as

per the CRZ Notification 2011.

Not applicable

5. Project Specific Conditions

1.

The project proponent shall give

an undertaking by way of affidavit

to comply with all the statutory

requirement and judgment of

Hon‟ble Supreme Court dated 2nd

Project Proponent will complies all the statutory requirement

and judgment of Hon'ble Supreme Court dated the 2nd

August 2017 in Writ Petition (Civil) No. 114 of 2014 in the

matter of Common Cause versus Union of India. Same has

been enclosed as Annexure-10, Page no 436.

Page 18: Compliance to ToR - Gujarat Pollution Control Board · Deputy Conservator of Forest, Forest Department, Junagad has been certified on dated 22.11.2017 that there is a Forest extension

SHRI ARJABHAI KHIMABHAI RATHOD

EIA/EMP REPORT FOR LIMESTONE MINE AT AJOTHA VILLAGE,

TALUKA: VERAVAL, GIR SOMNATH DISTRICT OF GUJARAT COMPLIANCE OF ToR

OVERSEAS MIN TECH CONSULTANTS | October2018 23

S.

No

.

TOR Conditions Compliance Status

August 2017 in Writ Petition

(Civil) No. 114 of 2014 in the

matter of common cause versus

Union of India and others before

grant of TOR/EC . The

undertaking inter alia include

commitment of PP not repeat any

violation in future.

2.

In case of violation of above

undertaking, the TOR/EC shall be

liable to be terminated forthwith.

Will be followed.

3.

The Environmental Clearance will

not be operational till such time the

project proponent complies with

all the statutory requirement and

judgment of Hon‟ble Supreme

Court dated 2nd

August 2017 in

Wrt Petition (Civil) No. 114 of

2014 in the matter of Common

Causes versus Union of India and

others.

Will be followed.

4.

State government concerned shall

ensure that mining operation shall

not commence till entire

compensation levies, if any, for

illegal mining paid by the Project

proponent through their respective

department of mining and Geology

in strict compliance of judgment of

Hon‟ble Supreme Court dated 2nd

August 2017 in Wrt Petition (Civil

No. 114 of 2014 in the matter of

Common Cause versus Union of

India and others.)

Will be followed.